Agenda 01/27/2026 Item #16A 6 (Final acceptance of the potable water and sewer utility facilities for Valencia Sky – Phase 5)1/27/2026
Item # 16.A.6
ID# 2025-5109
Executive Summary
Recommendation to approve final acceptance of the potable water and sewer utility facilities and accept the conveyance
of the potable water and sewer utility facilities for Valencia Sky – Phase 5. [PL20250008673]
OBJECTIVE: To have the Board of County Commissioners, as Ex Officio Governing Board of the Collier County
Water Sewer District, approve final acceptance of the potable water and sewer utility facilities, accept the conveyance of
the potable water and sewer utility facilities, in accordance with the Collier County Utility Standards and Procedures,
Ordinance No. 2004-31, as amended.
CONSIDERATIONS: 1) The Developer has constructed the potable water and sewer utility facilities for Valencia Sky
– Phase 5 within dedicated easements to serve this development (see attached location map). The potable water and
sewer utility facilities were offered for conveyance to the County, as described in Official Records (O.R.) Book 6529,
Page (PG) 1666, and are located within County utility easements dedicated by the plat of Valencia Sky, recorded in Plat
Book 75, Pages 72-90, of the Public Records of Collier County, Florida. The value of these potable water and sewer
utility facilities (assets) was $177,390.42 and $130,275.76, respectively.
2) Staff recorded all final acceptance documents associated with the potable water and sewer utility facilities conveyed
to the County in the public records of Collier County, which were reviewed and approved by the County Attorney’s
office as to form and legality. The County acquired its interest in the potable water and sewer utility facilities by
Warranty Deed and Bill of Sale recorded in O.R. Book 6529, PG 1666 (“the Utilities Facilities Deed”).
3) A final inspection to discover defects in materials and workmanship was conducted by staff on September 5, 2025, in
coordination with Public Utilities, and these facilities are satisfactory and acceptable.
4) Staff recommends final acceptance of the subject potable water and sewer utility facilities in the total amount of
$307,666.18. Staff also recommends acceptance of the Utilities Facilities Deed and the facilities described therein.
5) This final acceptance is in accordance with Collier County, Ordinance No. 2004-31, as amended.
6) Staff are unaware of any issues that would serve to negate the recommendation to approve this final acceptance.
This item is consistent with the Collier County strategic plan objective to operate an efficient and customer-focused
permitting process.
FISCAL IMPACT: Approval of this Executive Summary will have no specific financial impact. However, approval of
this Executive Summary will result in the Collier County Water-Sewer District receiving title to the potable water and
sewer utility facilities, which has a total gross value of $307,666.18 (no depreciation applied).
GROWTH MANAGEMENT IMPACT: There is no growth management impact associated with this action.
LEGAL CONSIDERATIONS: This item has been approved as to form and legality, and requires a majority vote for
Board approval. – SAA
RECOMMENDATION(S): To approve final acceptance of the potable water and sewer utility facilities and accept the
conveyance of the potable water and sewer utility facilities, for Valencia Sky – Phase 5. [PL20250008673]
PREPARED BY: Lucia S. Martin, Project Manager I, Development Review Division
ATTACHMENTS:
1. Location Map
2. Assets Sheet
Page 827 of 5261
1/27/2026
Item # 16.A.6
ID# 2025-5109
3. Verification of Final Cost
4. Warranty Deed and Bill of Sale
5. Plat Map
Page 828 of 5261
VALENCIA SKY – PHASE 5
LOCATION MAP
Page 829 of 5261
CERTIFICATION OF CONTRIBUTORY ASSETS - COUNTY
PROJECT NAME:Valencia Sky - Phase 5
LOCATION: Valencia Sky - Phase 5
NAME & ADDRESS OF OWNER: Naples Associates VI, LLLP
1600 Sawgrass Corporate Pkwy, Suite 400
Sunrise FL, 33323
TYPE OF UTILITY SYSTEM: POTABLE WATER (MATERIAL)
ITEM SIZE QUAN.UNIT COST TOTAL
2" PVC DR-18 WM w/Fittings 2 84 LF $3.83 $321.72
8" PVC DR-14 w/Fittings 8 98 LF $36.27 $3,554.46
8" PVC DR-18 WM w/Fittings 8 964 LF $30.62 $29,517.68
10" PVC DR-18 WM w/Fittings 10 1247 LF $35.13 $43,807.11
8" Gate Valve w/ Box 8 5 EA $1,899.25 $9,496.25
10" Gate Valve w/ Box 10 6 EA $2,926.45 $17,558.70
Fire Hydrant w/ 6" Gate Valve 6 6 EA $5,564.00 $33,384.00
Single Water Service 17 EA $722.25 $12,278.25
Double Water Service 15 EA $936.25 $14,043.75
Automatic Flushing Device 2 EA $5,885.00 $11,770.00
Permanent Bact Sample Point 1 EA $1,658.50 $1,658.50
TOTAL COST $177,390.42
Page 830 of 5261
Page 831 of 5261
CERTIFICATION OF CONTRIBUTORY ASSESTS - COUNTY
PROJECT NAME:Valencia Sky - Phase 5
LOCATION: Valencia Sky - Phase 5
NAME & ADDRESS OF OWNER:
1600 Sawgrass Corporate Pkwy, Suite 400
Sunrise FL, 33323
TYPE OF UTILITY SYSTEM: SANITARY SEWER (MATERIAL)
ITEM SIZE QUAN.UNIT COST TOTAL
8" PVC (0'-6' Cut)8 676 LF $14.45 $9,768.20
8" PVC (6'-8' Cut)8 890 LF $14.45 $12,860.50
8" PVC (8'-10' Cut)8 526 LF $14.45 $7,600.70
8" PVC (10'-12' Cut)8 67 LF $14.45 $968.15
Manhole (0'-6' Deep)6 EA $4,681.25 $28,087.50
Manhole (6'-8' Deep)5 EA $5,751.25 $28,756.25
Manhole (8'-10' Deep)1 EA $6,928.25 $6,928.25
Drop Manhole (10'-12' Deep)1 EA $8,827.50 $8,827.50
6" Single Sewer Service Lateral 6 6 EA $695.50 $4,173.00
6" Double Sewer Service Lateral 6 21 EA $802.50 $16,852.50
6" PVC DR-18 Force Main w/Fittings 6 58 LF $41.72 $2,419.76
6" Pug Valve (Force Main)6 1 EA $3,033.45 $3,033.45
TOTAL COST $130,275.76
Naples Associates VI, LLLP
Page 832 of 5261
Page 833 of 5261
VERIFICATION OF FINAL COST
PROJECT NAME:Valencia Sky - Phase 5
LOCATION: Valencia Sky - Phase 5
NAME & ADDRESS OF OWNER: Naples Associates VI, LLLP
1600 Sawgrass Corporate Pkwy, Suite 400
Sunrise FL, 33323
TYPE OF UTILITY SYSTEM: POTABLE WATER (MATERIAL AND SERVICES)
ITEM SIZE QUAN.UNIT COST TOTAL
2" PVC DR-18 WMw/Fittings 2 84 LF 12.16$ $1,021.44
8" PVC DR-14 w/Fittings 8 98 LF 54.15$ $5,306.70
8" PVC DR-18 WM w/Fittings 8 964 LF 48.22$ $46,484.08
10" PVC DR-18 WM w/Fittings 10 1247 LF 74.16$ $92,477.52
8" Gate Valve w/ Box 8 5 EA 2,729.21$ $13,646.05
10" Gate Valve w/ Box 10 6 EA 3,912.77$ $23,476.62
Fire Hydrant w/ 6" Gate Valve 6 6 EA 7,994.70$ $47,968.20
Single Water Service 17 EA 1,493.36$ $25,387.12
Double Water Service 15 EA 1,823.06$ $27,345.90
Automatic Flushing Device 2 EA 7,544.25$ $15,088.50
Permanent Bact Sample Point 1 EA 2,948.93$ $2,948.93
TOTAL COST $301,151.06
Page 834 of 5261
Page 835 of 5261
VERIFICATION OF FINAL COST
PROJECT NAME:Valencia Sky - Phase 5
LOCATION: Valencia Sky - Phase 5
NAME & ADDRESS OF OWNER:
1600 Sawgrass Corporate Pkwy, Suite 400
Sunrise FL, 33323
TYPE OF UTILITY SYSTEM: SANITARY SEWER (MATERIAL AND SERVICES)
ITEM SIZE QUAN.UNIT COST TOTAL
8" PVC (0'-6' Cut)8 676 LF 51.50$ 34,814.00$
8" PVC (6'-8' Cut)8 890 LF 66.20$ 58,918.00$
8" PVC (8'-10' Cut)8 526 LF 80.90$ 42,553.40$
8" PVC (10'-12' Cut)8 67 LF 95.60$ 6,405.20$
Manhole (0'-6' Deep)6 EA 7,598.06$ 45,588.36$
Manhole (6'-8' Deep)5 EA 9,404.06$ 47,020.30$
Manhole (8'-10' Deep)1 EA 10,954.91$ 10,954.91$
Drop Manhole (10'-12' Deep)1 EA 12,905.03$ 12,905.03$
6" Single Sewer Service Lateral 6 6 EA 1,412.78$ 8,476.68$
6" Double Sewer Service Lateral 6 21 EA 1,525.13$ 32,027.73$
6" PVC DR-18 Force Main w/Fittings 6 58 LF 58.85$ 3,413.30$
6" Plug Valve (Force Main)6 1 EA $ 4,077.62 4,077.62$
TOTAL COST $307,154.53
Naples Associates VI, LLLP
Page 836 of 5261
Page 837 of 5261
Page 838 of 5261
Page 839 of 5261
Page 840 of 5261
Page 841 of 5261
Page 842 of 5261
Page 843 of 5261
Page 844 of 5261
Page 845 of 5261
Page 846 of 5261
Page 847 of 5261
Page 848 of 5261
Page 849 of 5261
Page 850 of 5261
Page 851 of 5261
Page 852 of 5261
Page 853 of 5261
Page 854 of 5261
Page 855 of 5261
Page 856 of 5261
Page 857 of 5261
Page 858 of 5261
Page 859 of 5261
Page 860 of 5261
Page 861 of 5261
Page 862 of 5261
Page 863 of 5261
Page 864 of 5261
Page 865 of 5261
Page 866 of 5261
Page 867 of 5261