Loading...
Agenda 01/27/2026 Item #16A 2 (Final acceptance of the potable water and sewer utility facilities for St. Katherine’s Greek Orthodox Church)1/27/2026 Item # 16.A.2 ID# 2025-5057 Executive Summary Recommendation to approve final acceptance of the potable water and sewer utility facilities for St. Katherine’s Greek Orthodox Church. [PL20250008634] OBJECTIVE: To have the Board of County Commissioners, as Ex Officio Governing Board of the Collier County Water Sewer District, approve final acceptance of the potable water and sewer facilities, in accordance with the Collier County Utility Standards and Procedures, Ordinance No. 2004-31. CONSIDERATIONS: 1) The Developer of St. Katherine’s Greek Orthodox Church constructed the potable water and sewer facilities within dedicated easements to serve this private development (see attached location map). 2) A final inspection to discover defects in materials and workmanship was conducted by staff on October 27, 2025, in coordination with Public Utilities, and these facilities have been found to be satisfactory and acceptable. 3) Staff recommends final acceptance of the subject potable water and sewer utility facilities. The subject potable water and sewer facilities are owned and maintained by the developer. 4) This final acceptance is in accordance with Collier County, Ordinance No. 2004-31, as amended. 5) Staff are unaware of any issues that would serve to negate the recommendation to release the project. This item is consistent with the Collier County strategic plan objective to operate an efficient and customer-focused permitting process. FISCAL IMPACT: Review and inspection fees in the amount of $1,396.63 were paid under the original application, SDPA PL20230015432, and deposited in Planning Fund (1014). GROWTH MANAGEMENT IMPACT: There is no growth management impact associated with this action. LEGAL CONSIDERATIONS: This item has been approved as to form and legality, and requires a majority vote for Board approval. – SAA RECOMMENDATION(S): To approve final acceptance of the potable water and sewer utility facilities for St. Katherin’s Greek Orthodox Church. [PL20250008634] PREPARED BY: Lucia S. Martin, Project Manager I, Development Review Division ATTACHMENTS: 1. Location Map 2. Verification of Final Cost Page 742 of 5261 ST. KATHERINE’S GREEK ORTHODOX CHURCH LOCATION MAP Page 743 of 5261 Page 744 of 5261 Page 745 of 5261