Loading...
Agenda 09/10/2019 Item #16B1 (Interlocal Agreement w/City of Naples & CRA)09/10/2019 EXECUTIVE SUMMARY Recommendation to approve an Interlocal Agreement between the City of Naples and the Board of County Commissioners, acting as the Community Redevelopment Agency, to upgrade water lines and install / upgrade of fire hydrants on Coco Avenue, Areca Avenue, Basin Street, Canal Street and Captains Cove in the Bayshore Gateway Triangle Community Redevelopment Area. OBJECTIVE: To approve an Interlocal Agreement between the City of Naples and the Board of County Commissioners, acting as the Community Redevelopment Agency (the “County”), to improve the water lines and fire hydrants along Coco Avenue, Areca Avenue, Basin Street, Canal Street and Captains Cove in the Bayshore Gateway Triangle Community Redevelopment Area (the “Project”). CONSIDERATIONS: The Collier County Community Redevelopment Agency/Bayshore Gateway Triangle Community Redevelopment Area (“BGTCRA”) applied for and was awarded $300,000 from the FY2019-2020 U.S. Housing and Urban Development (“HUD”) Community Development Block Grant (“CDBG”) program. The County approved the Subrecipient Agreement at its June 25, 2019 meeting (Agenda Item # 16B1). The purpose of the Project is to upgrade existing water lines and install new and/or upgrade fire hydrants along five streets in the BGTCRA. The improvements will be along Coco Avenue, Areca Avenue, Basin Street, Canal Street and Captains Cove. The BGTCRA is located on the periphery of the City of Naples water service area and has historically experienced low water flow and pressure conditio ns. The Greater Naples Fire Control and Rescue District confirms those conditions. The City of Naples Utilities Department will provide design services and construction documents for the water line improvements along the streets identified above as well as construction management. A study prepared in 2016 reviewed the existing water system in the CRA and identified potential improvements to increase levels of fire protection. That study provided a multi -phase approach to complete an estimated total of $5.3 million in necessary improvements. The County and the City cooperated in FY2018 and FY2019 to complete the phase one and two portions of the Project. The Interlocal Agreement outlines the County’s and City’s responsibilities for the Project. The BGTCRA will utilize the HUD CDBG funds awarded identified above and the City will remit payment for the balance of the construction cost in excess of the CDBG funds. In addition, the City agrees to provide design services to upgrade the water utility services, t hus allowing the HUD CDBG funds to be applied to construction. The City of Naples Staff and the City’s Attorney have reviewed the Interlocal Agreement and are prepared to recommend approval to the City of Naples Council on September 18, 2019. This project is Phase 3 of the construction upgrades, Phase 1 was successfully completed in April of 2018 and phase 2 is underway with a completion date of October 2019. LEGAL CONSIDERATIONS: This item is approved for form and legality and requires a majority vote for Board action.-SRT FISCAL IMPACT: There is no fiscal impact to approving the Interlocal Agreement other than recording fees. The water line and hydrant upgrade phase 3 project budget of $650,000 is included in Bayshore CRA Grant Funds 717/718, Project 33639. Project funding is provided by a CDBG grant of $300,000 and reimbursement from the City of Naples for the balance of construction costs estimated to be $350,000. 16.B.1 Packet Pg. 1056 09/10/2019 GROWTH MANAGEMENT IMPACT: The authorization of the Interlocal Agreement to upgrade City water lines in the BGTCRA and install additional fire hydrants is in accordance with the intent of the Growth Management Plan Intergovernmental Coordination Element. RECOMMENDATION: Recommendation to approve an Interlocal Agreement between the City of Naples and the Board of County Commissioners, acting as the Community Redevelopment Agency, to upgrade water lines and install fire hydrants on Coco Avenue, Areca Avenue, Basin Street, Canal Street and Captains Cove in the Bayshore Gateway Triangle Community Redevelopment Area and authorize the Chairman to sign the attached agreement. Prepared by: Tami Scott, Project Manager ATTACHMENT(S) 1. Interlocal Agreement Coco Ave srt 082319 (PDF) 2. Technical Memo and Construction Estimates Fire Suppression (PDF) 16.B.1 Packet Pg. 1057 09/10/2019 COLLIER COUNTY Board of County Commissioners Item Number: 16.B.1 Doc ID: 9625 Item Summary: Recommendation to approve an Interlocal Agreement between the City of Naples and the Board of County Commissioners, acting as the Community Redevelopment Agency, to upgrade water lines and install / upgrade of fire hydrants on Coco Avenue, Areca Avenue, Basin Street, Canal Street and Captains Cove in the Bayshore Gateway Triangle Community Redevelopment Area. Meeting Date: 09/10/2019 Prepared by: Title: – Bayshore CRA Name: Tami Scott 07/23/2019 2:10 PM Submitted by: Title: – County Manager's Office Name: Debrah Forester 07/23/2019 2:10 PM Approved By: Review: County Manager's Office Debrah Forester Director - CRAs Completed 08/06/2019 11:35 AM Procurement Services Opal Vann Level 1 Purchasing Gatekeeper Completed 08/22/2019 8:13 AM County Manager's Office Sean Callahan Executive Director- Corp Business Ops Completed 08/26/2019 7:42 AM Procurement Services Ted Coyman Additional Reviewer Completed 08/26/2019 2:29 PM County Attorney's Office Scott Teach Level 2 Attorney Review Completed 08/26/2019 2:35 PM Grants Erica Robinson Level 2 Grants Review Completed 08/27/2019 10:56 AM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 08/27/2019 3:56 PM Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 08/28/2019 8:05 AM Budget and Management Office Ed Finn Additional Reviewer Completed 08/28/2019 5:03 PM Grants Therese Stanley Additional Reviewer Completed 08/29/2019 4:14 PM County Manager's Office Leo E. Ochs Level 4 County Manager Review Completed 08/30/2019 9:45 AM Board of County Commissioners MaryJo Brock Meeting Pending 09/10/2019 9:00 AM 16.B.1 Packet Pg. 1058 16.B.1.a Packet Pg. 1059 Attachment: Interlocal Agreement Coco Ave srt 082319 (9625 : Fire Suppression Phase 3-Interlocal Agreement) 16.B.1.a Packet Pg. 1060 Attachment: Interlocal Agreement Coco Ave srt 082319 (9625 : Fire Suppression Phase 3-Interlocal Agreement) 16.B.1.a Packet Pg. 1061 Attachment: Interlocal Agreement Coco Ave srt 082319 (9625 : Fire Suppression Phase 3-Interlocal Agreement) 16.B.1.a Packet Pg. 1062 Attachment: Interlocal Agreement Coco Ave srt 082319 (9625 : Fire Suppression Phase 3-Interlocal Agreement) 16.B.1.a Packet Pg. 1063 Attachment: Interlocal Agreement Coco Ave srt 082319 (9625 : Fire Suppression Phase 3-Interlocal Agreement) 16.B.1.a Packet Pg. 1064 Attachment: Interlocal Agreement Coco Ave srt 082319 (9625 : Fire Suppression Phase 3-Interlocal Agreement) 16.B.1.a Packet Pg. 1065 Attachment: Interlocal Agreement Coco Ave srt 082319 (9625 : Fire Suppression Phase 3-Interlocal Agreement) Q. Grady Minor & Associates, P.A. Civil Engineers  Surveyors  Land Planners  Landscape Architects 3800 Via Del Rey  Bonita Springs, Florida 34134  (239) 947-1144  Fax (239) 947-0375 MEMORANDUM TO: Elly McKuen; Bayshore Gateway Triangle CRA FROM: Michael J. Delate, P.E. Justin A. Frederiksen, P.E. SUBJECT: Water System Improvements for Fire Protection DATE: August 16, 2016 1. INTRODUCTION As authorized by the Bayshore Gateway Triangle CRA, Q. Grady Minor & Associates, P.A. has prepared this Technical Memorandum, (Work Order 4500126920 under Contract FT-09-5262-CI-GEN). The purpose of this study is to review the existing water system in the CRA in regards to the current status of fire protection and identify potential improvements to the system to increase levels of fire protection. 2. STUDY AREA The proposed study area consists of the Bayshore Gateway Triangle CRA with exception of the Collier County Government Complex and that portion within the Windstar Development. These areas generally have adequate fire protection in place. Figure No. 1 provides a general location map of the study area. 3. EXISTING CONDITIONS The Bayshore Gateway Triangle CRA is located in Collier County and through an interlocal agreement receives water service from the City of Naples. The East Naples Fire Control and Rescue District provides fire protection for the CRA. The CRA is a mix of commercial and residential properties. The CRA is at the periphery of the City of Naples water system. The existing system has mains varying in size from 2 to 16 inch diameter. (Larger mains have been identified as cast iron and ductile iron and smaller diameter mains as asbestos cement, AC.) The age of the water system varies with some portions being in excess of 40 yeas of age. There are also a limited number of fire hydrants present for fire protection. Those hydrants located in public rights of way are generally owned and maintained by the City of Naples and those within private developments are either owned and maintained by the fire district or the development. 16.B.1.b Packet Pg. 1066 Attachment: Technical Memo and Construction Estimates Fire Suppression (9625 : Fire Suppression Phase 3-Interlocal Agreement) Q. Grady Minor & Associates, P.A. Civil Engineers  Surveyors  Land Planners  Landscape Architects 3800 Via Del Rey  Bonita Springs, Florida 34134  (239) 947-1144  Fax (239) 947-0375 Because of the CRA location on the periphery of the City’s water service area, the area has historically experienced low water flow and pressure conditions. The East Naples Fire Control and Rescue District has confirmed these conditions. Some system improvements and additions have been made to the system over the years. The City of Naples is also in the process of completing pumping system improvements at Lois and Pineland storage and repump facility which should assist in reducing some of the flow and pressure deficiencies. However it is anticipated that some deficiencies will still exist. The northern portion of the CRA area is served from the primary City of Naples water system. This is generally the area referred to as the Gateway Triangle. The southern portion of the CRA area is served from the City’s water storage/re-pump facilities located at Lois Street and Pineland within the Gateway Triangle area. Current water system deficiencies include undersized water mains not capable of supporting fire flows, lack of fire hydrants at adequate spacing and dead end pipe segments with no looping. (Many streets are finger streets ending at canals.) In discussion with the fire district and in accordance with generally accepted standards, fire hydrants in single family residential should be spaced approximately at 500 feet, hydrants in multifamily residential at 250 feet and those in commercial areas at 250 feet. Fire hydrants should be installed on mains with a minimum diameter of 6”. Where multiple hydrants exist (or within multi- family and commercial areas), the main size should be 8” or larger. Based upon review of the existing system, the study area can be divided into four (4) areas requiring differing levels of water system improvements for fire protection. See Figure No. 2 for the location of these areas. Area No. 1 is south of US 41 and north of Haldeman Creek. It consists of both commercial and residential properties. The commercial areas are generally along US 41 and Bayshore Drive. Included in these commercial properties are Gulf Gate Plaza and the Courthouse Shadows Plaza. Both of these areas are served by mains at their perimeter. Also in the area is the Harmony Shores Mobile Home Community. Harmony Shores has a private water distribution system with no fire protection. Area No. 1 is generally served by small diameter main (6” or less) with a few interconnections to the 12” and 16” water main on Bayshore Drive and mains on US 41. Area No. 2 is south of Haldeman Creek and north of Thomasson Drive and is on the east and west sides of Bayshore Drive. This area is a mix of commercial and residential properties. The commercial properties are generally on Bayshore Drive. The residential properties are primarily single family units; however there are multi-family units in the following areas; Plantation Way (East of Bayshore), Bayshore Landings Apartments (West of Bayshore), Botanical Place (East of 16.B.1.b Packet Pg. 1067 Attachment: Technical Memo and Construction Estimates Fire Suppression (9625 : Fire Suppression Phase 3-Interlocal Agreement) Q. Grady Minor & Associates, P.A. Civil Engineers  Surveyors  Land Planners  Landscape Architects 3800 Via Del Rey  Bonita Springs, Florida 34134  (239) 947-1144  Fax (239) 947-0375 Bayshore) and Abaco Bay (East of Bayshore). These multi family units do have fire protection (fire hydrants) within them. These multi-family areas are served from the 16” water main on the east side of Bayshore. (Parts of this main are located under the existing northbound pavement). Also within this area is the Moorhead Manor Mobile Home Community. This community has a private water distribution system with no fire protection. The commercial and remaining residential properties are generally served from the 6” water main on the west side of Bayshore. There are minimal interconnects between the 6” and 16” mains. This area generally has undersized mains and limited fire hydrants. Area No. 3 is south of Thomasson Drive and includes that area adjacent to Bayshore Drive and that area north and south of Thomasson Drive west of Bayshore. It is primarily single family residential with exception of the commercial properties at the Thomasson Drive and Bayshore intersection. This area is served by a 12 inch main on Bayshore, Thomasson and Hamilton Avenue. This area has adequate sized mains and fire hydrant spacing. Area No. 4 is the Gateway Triangle area and is generally bound by US 41, Airport Pulling Road and Davis Boulevard. This area also includes an area just north of Davis Boulevard and an area east of Airport Pulling Road including the County Government Complex. The Eastern portion of this area is generally residential and the western portion is commercial. Areas along the major roads at the perimeter are also commercial. The area is generally served by small diameter main (6” and less) and has limited hydrant coverage. There are City water storage and re-pump facilities within the area; however, these facilities do not serve this area. These facilities generally serve the areas south of US 41 (Areas 1, 2 and 3). There are also limited connections to the existing 16” water main that feeds the City water storage/re-pump facilities. The area east of Airport Pulling Road generally has adequate facilities. The remaining area has undersized mains and limited fire hydrant coverage. 4. PROPOSED IMPROVEMENTS 4.1 IMMEDIATE IMPROVEMENTS It is proposed that an initial phase be completed to improve fire protection by the addition of fire hydrants to existing mains and making interconnects between smaller and larger diameter mains. The fire hydrant additions would be made to mains with a minimum size of 6 inches. The addition of fire hydrants and main interconnects on this initial phase is shown on Figure No. 3. A total of 25 fire hydrant additions and 7 water main interconnects have been identified. The probable project cost is estimated at $426,000. 16.B.1.b Packet Pg. 1068 Attachment: Technical Memo and Construction Estimates Fire Suppression (9625 : Fire Suppression Phase 3-Interlocal Agreement) Q. Grady Minor & Associates, P.A. Civil Engineers  Surveyors  Land Planners  Landscape Architects 3800 Via Del Rey  Bonita Springs, Florida 34134  (239) 947-1144  Fax (239) 947-0375 4.2 AREA No. 1 Recommended improvements to this area consist of the following items: See Figure No. 4 for additional information.  Upgrade mains and add fire hydrants in Sub-area 1A consisting of Peters and Gordon Avenue and Collee Court. Also included is a water main extension to connect to the 12 inch water along the south side of US 41, east of Bayshore. The probable project cost is estimated at $422,970.  Upgrade mains and add fire hydrants in Sub-area 1B consisting of the Weeks, Becca, Pine, Arbutus and Mangrove areas. The probable project cost is estimated at $447,879. The total project cost for these two areas is estimated at $870,849. Fire protection improvements are also needed in the Harmony Shores Mobile Home Park. However this is a private development with private streets and a private water distribution system. It is served by a master water meter. If a fire main was extended in this area it’s estimated project cost is $293,802. While the Gulf Gate Shopping Plaza has basic fire protection consisting of a 6” main and fire hydrants, it is typical that a commercial development would be serviced by 8 or 10” mains. To upgrade this system to a 10” main with new hydrants is estimated to cost $222,318. The total project cost for all these areas in AREA No. 1 is estimated at $1,386,969. 4.3 AREA No. 2 Recommended improvements to this area consist of the following items: See Figure No. 5 for additional information.  Upgrade mains and add fire hydrants in Sub-area 2A consisting of Bayview, Shoreview, Gulfview, Riverview and Lakeview. The probable project cost is estimated at $416,898.  Upgrade mains and add fire hydrants in Sub-area 2B consisting of Coco, Areca, Canal and Basin. The probable project cost is estimated at $156,216.  Upgrade mains and add fire hydrants in Sub-area 2C consisting of Barrett, Storter, VanBuren, Linda, Lunar, Full Moon, New Moon, Harvest and Jeepers. The probable project cost is estimated at $774,801. The total project cost for these areas is estimated at $1,347,915. 16.B.1.b Packet Pg. 1069 Attachment: Technical Memo and Construction Estimates Fire Suppression (9625 : Fire Suppression Phase 3-Interlocal Agreement) Q. Grady Minor & Associates, P.A. Civil Engineers  Surveyors  Land Planners  Landscape Architects 3800 Via Del Rey  Bonita Springs, Florida 34134  (239) 947-1144  Fax (239) 947-0375 Fire protection improvements are also needed in the Moorhead Manor Mobile Home Park. This is a private development with private streets and a private water distribution system. It is served by a master water meter. If a fire main was constructed in this development, its estimated project cost is $259,302. The total project cost for all these areas in AREA No. 2 is estimated at $1,607,217. 4.4 Area No. 3 No improvements are recommended for Area No. 3. See Figure No. 6. 4.5 Area No. 4 Recommended improvements to this area consist of the following items: See Figure No. 7.  Upgrade mains and add fire hydrants in Sub-area 4A. This is the residential area of the Gateway Triangle. The probable project cost is estimated at $1,522,416.  Upgrade mains and add fire hydrants in Sub-area 4B. This is the commercial area of the Gateway Triangle. The probable project cost is estimated at $536,613.  Add fire hydrants on the north side Davis Boulevard in the commercial area. (Sub-area 4C) The probable project cost is estimated at $41,400. The total project costs for these areas are estimated at $2,100,429. 4.6 Summary of Costs Below is an estimate of project costs. Attached Table 1 includes a breakdown of Project costs. The Project costs include: budget estimates of construction costs; surveying; engineering and permitting; construction engineering and inspection services and; a 15% contingency for a total of $5,520,615. SUMMARY OF COSTS AREA COSTS Immediate $ 426,000 No. 1 $1,386,969 No. 2 $1,607,217 No. 3 N/A No. 4 $2,100,429 TOTAL $5,520,615 16.B.1.b Packet Pg. 1070 Attachment: Technical Memo and Construction Estimates Fire Suppression (9625 : Fire Suppression Phase 3-Interlocal Agreement) Q. Grady Minor & Associates, P.A. Civil Engineers  Surveyors  Land Planners  Landscape Architects 3800 Via Del Rey  Bonita Springs, Florida 34134  (239) 947-1144  Fax (239) 947-0375 No costs have been included for removal and disposal of asbestos cement (AC) pipe beyond that incidental needed. It is anticipated that AC pipe will be abandoned in place and mains 4” or greater grouted in place. 5. OTHER CONSIDERATIONS It is critical that the proposed water system improvements be coordinated with the City of Naples. The City of Naples owns, operates and maintains the water system with the CRA. It is also important that coordination also be completed with Collier County, the East Naples Fire Control and Rescue District and private utilities in the area. Those activities immediately adjacent or within the US 41 right-of-way will need to be coordinated and permitted with the Florida Department of Transportation. Ideally planning for individual projects should begin one (1) year prior to planned construction to allow proper coordination to occur, engineering surveys to be complete, plans and specification developed and permitting to be completed prior to bidding and construction. 16.B.1.b Packet Pg. 1071 Attachment: Technical Memo and Construction Estimates Fire Suppression (9625 : Fire Suppression Phase 3-Interlocal Agreement) GradyMinor Civil Engineers Ɣ Land Surveyors Ɣ Planners Ɣ Landscape Architects CERT. OF AUTH. EB 0005151 CERT. OF AUTH. LB 0005151 BUSINESS LC 26000266 Bonita Springs 239.947.1144 Fort Myers 239.690.4380 North Port 941.426.5858 Naples 239.444.2397 www.GradyMinor.com Q. Grady Minor and Associates, P.A. PARK %+6;1( 0#2.'5 /114+0)5 -''9#;&+0 +5.#0& 64#+. #%4'5 0#2.'5 /#014 .'.; 4'5146 0#2.'5 #+42146 ).#&'5 -+0)5 .#-' %4190 21+06' (#..+0) 9#6'45 21+0%+#0# 8+..#)' )4'; 1#-5 9;0&'/'4' )1.&'0 )#6'%+6; $4+#4911& $'4-5*+4' .#-'5 %17064;5+&'(1:(+4'2.#06#6+10 %'&#4 *#//1%-(14'56 ).'0 0#2.'5 *'4+6#)' 6*'%.7$ '56#6'5 0#2.'5 .#-'55*#&19911&41;#. 911&5 4+8+'4#)1.( '56#6'5 .'.; 567&; #4'# 16.B.1.b Packet Pg. 1072 Attachment: Technical Memo and Construction Estimates Fire Suppression (9625 : Fire Suppression Phase 3-Interlocal Agreement) &GradyMinorCivil EngineersƔLand SurveyorsƔPlannersƔLandscape ArchitectsCERT. OF AUTH. EB 0005151CERT. OF AUTH. LB 0005151BUSINESS LC 26000266Bonita Springs239.947.1144Fort Myers239.690.4380North Port941.426.5858Naples239.444.2397www.GradyMinor.com Q. Grady Minor and Associates, P.A.&&%%$''%'&#'$#$#'%'&'16.B.1.bPacket Pg. 1073Attachment: Technical Memo and Construction Estimates Fire Suppression (9625 : Fire Suppression Phase 3-Interlocal Agreement) GradyMinorCivil EngineersƔLand SurveyorsƔPlannersƔLandscape ArchitectsCERT. OF AUTH. EB 0005151CERT. OF AUTH. LB 0005151BUSINESS LC 26000266Bonita Springs239.947.1144Fort Myers239.690.4380North Port941.426.5858Naples239.444.2397www.GradyMinor.com Q. Grady Minor and Associates, P.A.&&&%%$''%'&#'$#$#'%'&'+%+%+%+%+%+%+%+%16.B.1.bPacket Pg. 1074Attachment: Technical Memo and Construction Estimates Fire Suppression (9625 : Fire Suppression Phase 3-Interlocal Agreement) GradyMinorCivil EngineersƔLand SurveyorsƔPlannersƔLandscape ArchitectsCERT. OF AUTH. EB 0005151CERT. OF AUTH. LB 0005151BUSINESS LC 26000266Bonita Springs239.947.1144Fort Myers239.690.4380North Port941.426.5858Naples239.444.2397www.GradyMinor.com Q. Grady Minor and Associates, P.A.%$%#&'#&'#$*#4/10;5*14'5#16.B.1.bPacket Pg. 1075Attachment: Technical Memo and Construction Estimates Fire Suppression (9625 : Fire Suppression Phase 3-Interlocal Agreement) GradyMinorCivil EngineersƔLand SurveyorsƔPlannersƔLandscape ArchitectsCERT. OF AUTH. EB 0005151CERT. OF AUTH. LB 0005151BUSINESS LC 26000266Bonita Springs239.947.1144Fort Myers239.690.4380North Port941.426.5858Naples239.444.2397www.GradyMinor.com Q. Grady Minor and Associates, P.A.$'#&#$16#0+%#.2.#%'#'$'%''%#$#%1$#;&*#4/10;5*14'5/114*'#&/#01416.B.1.bPacket Pg. 1076Attachment: Technical Memo and Construction Estimates Fire Suppression (9625 : Fire Suppression Phase 3-Interlocal Agreement) GradyMinorCivil EngineersƔLand SurveyorsƔPlannersƔLandscape ArchitectsCERT. OF AUTH. EB 0005151CERT. OF AUTH. LB 0005151BUSINESS LC 26000266Bonita Springs239.947.1144Fort Myers239.690.4380North Port941.426.5858Naples239.444.2397www.GradyMinor.com Q. Grady Minor and Associates, P.A.$16#0+%#.2.#%'#'#$#%1$#;%16.B.1.bPacket Pg. 1077Attachment: Technical Memo and Construction Estimates Fire Suppression (9625 : Fire Suppression Phase 3-Interlocal Agreement) GradyMinorCivil EngineersƔLand SurveyorsƔPlannersƔLandscape ArchitectsCERT. OF AUTH. EB 0005151CERT. OF AUTH. LB 0005151BUSINESS LC 26000266Bonita Springs239.947.1144Fort Myers239.690.4380North Port941.426.5858Naples239.444.2397www.GradyMinor.com Q. Grady Minor and Associates, P.A.#$)18'40/'06%1/2.':#4'#'#561(#+42146Ä27..+0)41#&%&&#'$%''&#*#4/10;5*14'516.B.1.bPacket Pg. 1078Attachment: Technical Memo and Construction Estimates Fire Suppression (9625 : Fire Suppression Phase 3-Interlocal Agreement) TABLE NO. 1BAYSHOTE GATEWAY TRIANGLE CRA BUDGET COST ESTIMATES FOR WATER SYSTEM IMPROVEMENTS FOR FIRE PROTECTIONFIRE HYRDANTSINTERCONNECTSINTERIM FIRE SYSTEM UPGRADECOUNT UNIT COST COUNT UNIT COST TOTAL COSTSEA $/EA EA $/EAAddition of fire hydrant on existing main (may include minor main extension)and addition of interconnects between smaller and larger iameter mains 25 7,200.00$ 7 25,000.00$ 355,000.00$ Design, Permitting, Etc.$35,500.00CEI$35,500.00426,000.00$ 6-IN 8-IN INTERCONNECTSSTREET LENGTH UNIT COST LENGTH UNIT COST COUNT UNIT COST COUNT UNIT COSTTOTAL COSTSSEGMENTLF$/LF LF $/LF EA $/EAEA$/EAAREA 1APETERS45.00$ 1500 50.00$ 4 4,700.00$ 17,500.00$ 101,300.00$ GORDON45.00$ 1230 50.00$ 3 4,700.00$ 17,500.00$ 83,100.00$ COLLEE45.00$ 300 50.00$ 0 4,700.00$ 07,500.00$ 15,000.00$ US 41 Interconnect10-in700 90.00$ 3 4,700.00$ 130,000.00$ 107,100.00$ 306,500.00$ Contigencies45,975.00$ 352,475.00$ Design, Permitting, Etc.35,247.50$ CEI35,247.50$ 422,970.00$ AREA 1BWEEKS45.00$ 1270 50.00$ 4 4,700.00$ 17,500.00$ 89,800.00$ BECCA45.00$ 1270 50.00$ 4 4,700.00$ 17,500.00$ 89,800.00$ PINE45.00$ 1200 50.00$ 4 4,700.00$ 17,500.00$ 86,300.00$ ARBUTUS420 45.00$ 50.00$ 4 4,700.00$ 07,500.00$ 37,700.00$ MANGROVE45.00$ 325 50.00$ 1 4,700.00$ 07,500.00$ 20,950.00$ 324,550.00$ Contigencies48,682.50$ 373,232.50$ Design, Permitting, Etc.37,323.25$ CEI37,323.25$ 447,879.00$ AREA 1CGULF GATE PLAZA10-in1800 65.00$ 3 4,700.00$ 130,000.00$ 161,100.00$ Contigencies24,165.00$ 185,265.00$ Design, Permitting, Etc.18,526.50$ CEI18,526.50$ 222,318.00$ AREA 1DHARMONY45.00$ 3300 50.00$ 7 4,700.00$ 115,000.00$ 212,900.00$ SHORES MHP(backflow assembly)Contigencies31,935.00$ 244,835.00$ Design, Permitting, Etc.24,483.50$ CEI24,483.50$ 293,802.00$ FIRE HYRDANTSPage 116.B.1.bPacket Pg. 1079Attachment: Technical Memo and Construction Estimates Fire Suppression (9625 : Fire Suppression TABLE NO. 1BAYSHOTE GATEWAY TRIANGLE CRA BUDGET COST ESTIMATES FOR WATER SYSTEM IMPROVEMENTS FOR FIRE PROTECTION6-IN8-ININTERCONNECTSSTREETLENGTH UNIT COST LENGTH UNIT COST COUNT UNIT COST COUNT UNIT COSTTOTAL COSTSSEGMENTLF$/LF LF $/LF EA $/EAEA$/EAFIRE HYRDANTSAREA 2ABAYVIEW45.00$ 800 50.00$ 2 4,700.00$ 17,500.00$ 56,900.00$ SHOREVIEW45.00$ 700 50.00$ 2 4,700.00$ 17,500.00$ 51,900.00$ GULFVIEW45.00$ 670 50.00$ 2 4,700.00$ 17,500.00$ 50,400.00$ RIVERVIEW45.00$ 800 50.00$ 2 4,700.00$ 17,500.00$ 56,900.00$ LAKEVIEW45.00$ 1100 50.00$ 5 4,700.00$ 17,500.00$ 86,000.00$ 302,100.00$ Contigencies45,315.00$ 347,415.00$ Design, Permitting, Etc.34,741.50$ CEI34,741.50$ 416,898.00$ AREA 2BCOCO45.00$ 0 50.00$ 1 4,700.00$ 17,500.00$ 12,200.00$ ARECA45.00$ 1400 50.00$ 5 4,700.00$ 17,500.00$ 101,000.00$ CAPTAINS45.00$ 050.00$ 0 4,700.00$ 07,500.00$ -$ CANAL45.00$ 050.00$ 0 4,700.00$ 07,500.00$ -$ 113,200.00$ Contigencies16,980.00$ 130,180.00$ Design, Permitting, Etc.13,018.00$ CEI13,018.00$ 156,216.00$ AREA 2CBARRETT (E)45.00$ 1400 50.00$ 3 4,700.00$ 17,500.00$ 91,600.00$ BARRETT (W)45.00$ 1250 50.00$ 3 4,700.00$ 17,500.00$ 84,100.00$ STORTER45.00$ 1400 50.00$ 3 4,700.00$ 17,500.00$ 91,600.00$ VAN BUREN (E)45.00$ 150 50.00$ 2 4,700.00$ 17,500.00$ 24,400.00$ VAN BUREN (W)45.00$ 1400 50.00$ 3 4,700.00$ 17,500.00$ 91,600.00$ LINDA45.00$ 0 50.00$ 2 4,700.00$ 17,500.00$ 16,900.00$ LUNAR45.00$ 1200 50.00$ 2 4,700.00$ 17,500.00$ 76,900.00$ FULL MOON45.00$ 050.00$ 0 4,700.00$ 07,500.00$ -$ NEW MOON20045.00$ 500 50.00$ 1 4,700.00$ 07,500.00$ 38,700.00$ HARVEST45.00$ 500 50.00$ 1 4,700.00$ 07,500.00$ 29,700.00$ JEEPERS25045.00$ 50.00$ 1 4,700.00$ 07,500.00$ 15,950.00$ 561,450.00$ Contigencies84,217.50$ 645,667.50$ Design, Permitting, Etc.64,566.75$ CEI64,566.75$ 774,801.00$ Page 216.B.1.bPacket Pg. 1080Attachment: Technical Memo and Construction Estimates Fire Suppression (9625 : Fire Suppression TABLE NO. 1BAYSHOTE GATEWAY TRIANGLE CRA BUDGET COST ESTIMATES FOR WATER SYSTEM IMPROVEMENTS FOR FIRE PROTECTION6-IN8-ININTERCONNECTSSTREETLENGTH UNIT COST LENGTH UNIT COST COUNT UNIT COST COUNT UNIT COSTTOTAL COSTSSEGMENTLF$/LF LF $/LF EA $/EAEA$/EAFIRE HYRDANTSAREA 2DMOOREHEAD45.00$ 2500 50.00$ 7 4,700.00$ 215,000.00$ 187,900.00$ MANNER(backflow assembly)Contigencies28,185.00$ 216,085.00$ Design, Permitting, Etc.21,608.50$ CEI21,608.50$ 259,302.00$ AREA 4ALINWOOD45.00$ 2700 50.00$ 6 4,700.00$ 17,500.00$ 170,700.00$ SHADOWLAWN45.00$ 3050 50.00$ 7 4,700.00$ 27,500.00$ 200,400.00$ CONNECTICUT45.00$ 1350 50.00$ 3 4,700.00$ 17,500.00$ 89,100.00$ FRANCIS45.00$ 1850 50.00$ 4 4,700.00$ 17,500.00$ 118,800.00$ MANORCA45.00$ 350 50.00$ 1 4,700.00$ 07,500.00$ 22,200.00$ PINELAND45.00$ 1475 50.00$ 4 4,700.00$ 17,500.00$ 100,050.00$ PELTON 45.00$ 1025 50.00$ 3 4,700.00$ 17,500.00$ 72,850.00$ WINIFRED45.00$ 050.00$ 1 4,700.00$ 07,500.00$ 4,700.00$ LEE20045.00$ 50.00$ 1 4,700.00$ 07,500.00$ 13,700.00$ WALKER20045.00$ 50.00$ 1 4,700.00$ 17,500.00$ 21,200.00$ CALDONIA45.00$ 675 50.00$ 2 4,700.00$ 17,500.00$ 50,650.00$ CALUSA45.00$ 675 50.00$ 2 4,700.00$ 17,500.00$ 50,650.00$ BAYSIDE45.00$ 975 50.00$ 3 4,700.00$ 17,500.00$ 70,350.00$ ANDREW45.00$ 1775 50.00$ 3 4,700.00$ 27,500.00$ 117,850.00$ 1,103,200.00$ Contigencies165,480.00$ 1,268,680.00$ Design, Permitting, Etc.126,868.00$ CEI126,868.00$ 1,522,416.00$ AREA 4B10-INLINWOOD1200 65.00$ 5 4,700.00$ 07,500.00$ 101,500.00$ COMMERCIAL950 65.00$ 4 4,700.00$ 27,500.00$ 95,550.00$ KIRKWOOD1100 65.00$ 5 4,700.00$ 07,500.00$ 95,000.00$ LINWOOD WY1200 65.00$ 4 4,700.00$ 07,500.00$ 96,800.00$ 388,850.00$ Contigencies58,327.50$ 447,177.50$ Design, Permitting, Etc.44,717.75$ CEI44,717.75$ 536,613.00$ AREADAVIS BLVD4 7,500.00$ 30,000.00$ Contigencies4,500.00$ 34,500.00$ Design, Permitting, Etc.3,450.00$ CEI3,450.00$ 41,400.00$ Grand Total 5,520,615.00$ Page 316.B.1.bPacket Pg. 1081Attachment: Technical Memo and Construction Estimates Fire Suppression (9625 : Fire Suppression