Loading...
Agenda 02/12/2019 Item #16A 802/12/2019 EXECUTIVE SUMMARY Recommendation to award a Work Order to Bonness, Inc., for construction of the “Immokalee Road at Valewood Drive and Oakes Boulevard Intersection Improvements” project in the amount of $295,794.72 (Project #60016.29). OBJECTIVE: To approve a Work Order for roadway safety improvements to extend the existing east bound left turn lane from Immokalee Road onto Valewood Drive and to prohibit west bound left turns from Immokalee Road onto Oakes Boulevard. CONSIDERATION: On December 3, 2018, Transportation Engineering staff sent construction plans and a bid schedule to four (4) construction companies under contract with the County under Agreement #16-6663 for Roadway Contractors. Staff requested quotations for construction services for the Immokalee Road at Valewood Drive and Oakes Boulevard Intersection Improvement project utilizing that Agreement. On December 20, 2018, the County received four (4) bids, as follows: Contractor Bid 1 Bonness, Inc. $295,794.72 2 Ajax Paving Industries of Florida, LLC $386,797.25 3 Wright Construction Group, Inc. $449,451.22 4 Preferred Materials, Inc. $483,388.22 Staff determined the lowest bid was fair and reasonable and recommend awarding the work order to Bonness, Inc. The Procurement Services Division concluded that bidding was competitive. Bonness’ bid is 9 % lower than the engineer’s estimate of $324,066.75. The work order and bid analysis is attached. FISCAL IMPACT: The anticipated cost for this roadway improvement project is $295,794.72. Funding is available within Transportation Gas Tax fund 313, project 60016. The estimated useful life of a roadway improvements is 20 years, with minimal to no repair cost during that duration of time. GROWTH MANAGEMENT IMPACT: This project is consistent with the Transportation Element of the Growth Management Plan. LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for Board approval. -SRT RECOMMENDATION: To award a Work Order for “Immokalee Road at Valewood Dri ve and Oakes Boulevard Intersection Improvements” to Bonness, Inc., in the amount of $295,794.72, and authorize the Chair to execute the attached Work Order. Prepared by: Mark McCleary, P.E., P.S.M., Principal Project Manager, Transportation Engineering Division, Growth Management Department ATTACHMENT(S) 1. 60016.29 Bid Analysis (PDF) 2. Work Order 16-6663 (PDF) 3. 60016.29 Plan View (PDF) 16.A.8 Packet Pg. 556 02/12/2019 COLLIER COUNTY Board of County Commissioners Item Number: 16.A.8 Doc ID: 7714 Item Summary: Recommendation to award a Work Order to Bonness, Inc., for construction of the “Immokalee Road at Valewood Drive and Oakes Boulevard Intersection Improvements” project in the amount of $295,794.72 (Project #60016.29). Meeting Date: 02/12/2019 Prepared by: Title: Project Manager – Transportation Engineering Name: Mark McCleary 01/10/2019 3:00 PM Submitted by: Title: Division Director - Transportation Eng – Transportation Engineering Name: Jay Ahmad 01/10/2019 3:00 PM Approved By: Review: Growth Management Department Anthony Khawaja Additional Reviewer Completed 01/10/2019 3:11 PM Procurement Services Opal Vann Level 1 Purchasing Gatekeeper Completed 01/10/2019 4:59 PM Growth Management Operations Support Christopher Johnson Additional Reviewer Completed 01/14/2019 8:40 AM Capital Project Planning, Impact Fees, and Program Management Rookmin Nauth Additional Reviewer Completed 01/14/2019 2:12 PM Growth Management Department Gene Shue Additional Reviewer Completed 01/15/2019 5:19 PM Transportation Engineering Jay Ahmad Additional Reviewer Completed 01/16/2019 7:15 AM Growth Management Department Christine Arnold Level 1 Reviewer Completed 01/18/2019 10:00 AM Procurement Services Evelyn Colon Additional Reviewer Completed 01/22/2019 8:46 AM Procurement Services Swainson Hall Additional Reviewer Completed 01/22/2019 8:59 AM Procurement Services Ted Coyman Additional Reviewer Completed 01/22/2019 9:14 AM Growth Management Department Thaddeus Cohen Department Head Review Completed 01/23/2019 9:42 AM Growth Management Department James C French Deputy Department Head Review Completed 01/23/2019 7:18 PM County Attorney's Office Scott Teach Level 2 Attorney Review Completed 01/24/2019 1:58 PM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 01/24/2019 4:26 PM Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 01/24/2019 4:52 PM Office of Management and Budget Susan Usher Additional Reviewer Completed 02/01/2019 10:58 AM 16.A.8 Packet Pg. 557 02/12/2019 County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 02/04/2019 3:39 PM Board of County Commissioners MaryJo Brock Meeting Pending 02/12/2019 9:00 AM 16.A.8 Packet Pg. 558 Bid Analysis No. 60016.29Imm Rd at Valewood Dr and Oakes BlvdDESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT COST TOTAL COST Low Bid Eng. Est. Average Eng. Est. Average1 101-1 MOBILIZATIONLS 1 $42,953.57 $42,953.57 $15,000.00 $15,000.00 $98,435.96 $98,435.96$83,125.00 $83,125.00$22,000.00$22,000.00 $42,953.57 $22,000.00 $59,878.63 195% 72%2102-1 MAINTENANCE OF TRAFFIC LS 1$17,142.48 $17,142.48 $65,000.00 $65,000.00 $83,638.56 $83,638.56 $70,345.00 $70,345.00$31,000.00$31,000.00 $17,142.48 $31,000.00 $59,031.51 55% 29%3110-1-1 STANDARD CLEARING & GRUBBING LS 1$5,985.01 $5,985.01 $10,000.00 $10,000.00 $15,673.40 $15,673.40 $28,000.00 $28,000.00$8,000.00$8,000.00 $5,985.01 $8,000.00 $14,914.60 75% 40%4110-4-10 REMOVAL OF EXISITNG CONCRETE SY 294$40.19 $11,815.86 $50.00 $14,700.00 $66.20 $19,462.80 $23.95 $7,041.30$27.00$7,938.00 $40.19 $27.00 $45.09 149% 89%5120-1 EXCAVATION CY 464$17.77 $8,245.28 $75.00 $34,800.00 $35.77 $16,597.28 $30.50 $14,152.00$75.00$34,800.00 $17.77 $75.00 $39.76 24% 45%6120-6 EMBANKMENT CY 262$27.25 $7,139.50 $80.00 $20,960.00 $64.76 $16,967.12 $41.70 $10,925.40$100.00$26,200.00 $27.25 $100.00 $53.43 27% 51%7245-7-15 OPTIONAL BASE GROUP 15 (9" THICK) SY 633$48.23 $30,529.59 $115.00 $72,795.00 $48.23 $30,529.59 $67.00 $42,411.00$60.00$37,980.00 $48.23 $60.00 $69.62 80% 69%8327-70-1MILLING EXISTING PAVEMENT (1.0" THICK AVE.) (1' MIN WIDE) SY 727$15.46 $11,239.42 $11.50 $8,360.50 $15.46 $11,239.42 $13.70 $9,959.90$14.00$10,178.00 $15.46 $14.00 $14.03 110% 110%9334-1-12 SUPERPAVE ASPH. CONC. TYPE SP 12.5 (TRAFFIC C, 2" THICK) TN 58$124.62 $7,227.96 $220.00 $12,760.00 $124.62 $7,227.96 $265.79 $15,415.82$200.00$11,600.00 $124.62 $200.00 $183.76 62% 68%10337-7-42 ASPH. CONC. FRICTION COURSE 9.5 (TRAFFIC C, 1") (INC 1" RESURF.) TN 73$119.70 $8,738.10 $300.00 $21,900.00 $119.70 $8,738.10 $300.00 $21,900.00$300.00$21,900.00 $119.70 $300.00 $209.85 40% 57%11425-6ADJUST VALVE BOXES (WATER & SEWER) EA4$285.98 $1,143.92 $400.00 $1,600.00 $750.00 $3,000.00 $730.00 $2,920.00 $500.00 $2,000.00 $285.98 $500.00 $541.50 57% 53%12520-1-10 CONCRETE CURB & GUTTER TYPE "F" LF 1,135$37.04 $42,040.40 $25.00 $28,375.00 $37.04 $42,040.40 $27.00 $30,645.00$18.00$20,430.00 $37.04 $18.00 $31.52 206% 118%13522-2 CONCRETE (1' THICK)SY 2$1,194.89 $2,389.78 $120.00 $240.00 $1,194.89 $2,389.78 $145.00 $290.00$100.00$200.00 $1,194.89 $100.00 $663.70 1195% 180%14526-1-1 BRICK PAVERS SY 157$114.15 $17,921.55 $65.00 $10,205.00 $116.10 $18,227.70 $255.00 $40,035.00$90.00$14,130.00 $114.15 $90.00 $137.56 127% 83%15700-1-11-(SBA)SIGN, SINGLE POST W/ (SPECIAL) SLIP BASE ASSEMBLY EA 4$611.26 $2,445.04 $650.00 $2,600.00 $611.26 $2,445.04 $790.00 $3,160.00$450.00$1,800.00 $611.26 $450.00 $665.63 136% 92%16700-1-60 SIGN, SINGLE POST (REMOVE) EA 6$120.42 $722.52 $65.00 $390.00 $120.42 $722.52 $285.00 $1,710.00$85.00$510.00 $120.42 $85.00 $147.71 142% 82%17706-3 REFLECTIVE PAVEMENT MARKERS EA 73$4.52 $329.96 $5.25 $383.25 $4.52 $329.96 $6.00 $438.00$80.00$5,840.00 $4.52 $80.00 $5.07 6% 89%18710-11-29 PAINTED (ISLAND NOSE) (YELLOW) SY 2$5.65 $11.30 $6.50 $13.00 $5.65 $11.30 $30.00 $60.00$3.50$7.00 $5.65 $3.50 $11.95 161% 47%19711-11-121 TRAFFIC STRIPE, SOLID, THERMOPLASTIC (6" WHITE) LF 265$1.13 $299.45 $1.30 $344.50 $1.13 $299.45 $1.50 $397.50$2.00$530.00 $1.13 $2.00 $1.27 57% 89%20711-11-122 TRAFFIC STRIPE, SOLID, THERMOPLASTIC (8" WHITE) LF 794$1.53 $1,214.82 $1.75 $1,389.50 $1.53 $1,214.82 $1.60 $1,270.40$5.00$3,970.00 $1.53 $5.00 $1.60 31% 95%21711-11-124 TRAFFIC STRIPE, SOLID, THERMOPLASTIC (18" WHITE) LF 73$4.52 $329.96 $5.25 $383.25 $4.52 $329.96 $4.25 $310.25$6.00$438.00 $4.52 $6.00 $4.64 75% 98%22711-11-125 TRAFFIC STRIPE, SOLID, THERMOPLASTIC (24" WHITE) LF 34$6.78 $230.52 $7.85 $266.90 $6.78 $230.52 $6.35 $215.90$15.00$510.00 $6.78 $15.00 $6.94 45% 98%23711-11-170 DIRECTIONAL ARROWS (THERMOPLASTIC) EA 9$67.80 $610.20 $80.00 $720.00 $67.80 $610.20 $200.00 $1,800.00$135.00$1,215.00 $67.80 $135.00 $103.90 50% 65%24711-11-221 TRAFFIC STRIPE, SOLID, THERMOPLASTIC (6" YELLOW) LF 1087$1.13 $1,228.31 $1.30 $1,413.10 $1.13 $1,228.31 $1.50 $1,630.50$2.50$2,717.50 $1.13 $2.50 $1.27 45% 89%25711-11-224 TRAFFIC STRIPE, SOLID, THERMOPLASTIC (18" YELLOW) LF 11$4.52 $49.72 $5.25 $57.75 $4.52 $49.72 $4.25 $46.75$2.50$27.50 $4.52 $2.50 $4.64 181% 98%26711-11-241 TRAFFIC STRIPE, SKIP, (2'-4' ) DOTTED GUIDELINE, THERMOPLASTIC (6" YELLOW) LF 230$1.13 $259.90 $1.30 $299.00 $1.13 $259.90 $1.10 $253.00$1.50$345.00 $1.13 $1.50 $1.17 75% 97%27711-17 REMOVE EXIST. PAVEMENT MARKINGS (GRIND) LS 1$1,412.46 $1,412.46 $1,650.00 $1,650.00 $1,412.46 $1,412.46 $8,000.00$8,000.00$1,500.00$1,500.00 $1,412.46 $1,500.00 $3,118.73 94% 45%28$223,656.58 $326,605.75 $383,312.23 $396,457.72 $267,766.0029CC-10000 ROADWAY ALLOWANCEFixed 1 $20,000.00 $20,000.00 $20,000.00 $20,000.00 $20,000.00 $20,000.00 $20,000.00 $20,000.00 $20,000.00 $20,000.00 $20,000.00 $20,000.00$20,000.0031$243,656.58 $346,605.75 $403,312.23 $416,457.72 $287,766.0032 Plants33 1 Veitchia montgomeryana EA 7 $849.73 $5,948.11 $550.00 $3,850.00 $752.00 $5,264.00 $845.00 $5,915.00 400.00$ $2,800.00 $849.73 $400.00 $749.18 212% 113%34 2 Existing Veitchia montgomeryana EA 7 $553.68 $3,875.76 $550.00 $3,850.00 $490.00 $3,430.00 $1,125.00 $7,875.00 400.00$ $2,800.00 $553.68 $400.00 $679.67 138% 81%35 3 Dianella tasmanica 'Variegata' EA 42 $18.22 $765.24 $10.00 $420.00$16.12 $677.04 $18.00 $756.00 16.00$ $672.00 $18.22 $16.00 $15.59 114% 117%36 4 Carissa macrocarpa 'Emerald Blanket' EA 42 $18.22 $765.24 $26.00 $1,092.00 $16.12 $677.04 $18.00 $756.00 16.00$ $672.00 $18.22 $16.00 $19.59 114% 93%37 5 Arachis pintoi 'Golden Glory' EA 683 $8.09 $5,525.47 $6.50 $4,439.50 $7.16 $4,890.28 $8.00 $5,464.00 4.25$ $2,902.75 $8.09 $4.25 $7.44 190% 109%38 6 Existing Crown of Thorn EA 1 $1,762.75 $1,762.75 $100.00 $100.00 $1,560.00 $1,560.00 $1,700.00 $1,700.00 500.00$ $500.00 $1,762.75 $500.00 $1,280.69 353% 138%39 7 MulchCY 35 $117.01 $4,095.35 $105.00 $3,675.00 $103.55 $3,624.25 $75.00 $2,625.00 75.00$ $2,625.00 $117.01 $75.00 $100.14 156% 117%40 8 SoilCY 138 $42.94 $5,925.72 $50.00 $6,900.00 $38.00 $5,244.00 $135.00 $18,630.00 13.00$ $1,794.00 $42.94 $13.00 $66.49 330% 65%41 Irrigation$28,663.64 $24,326.50 $25,366.61 $43,721.00 $14,765.7542 9 Spray nozzlesEA 24 $79.23 $1,901.52 $6.50 $156.00 $70.12 $1,682.88 $78.00 $1,872.00 60.00$ $1,440.00 $79.23 $60.00 $58.46 132% 136%43 10 Irritrol BubblersEA 28 $40.68 $1,139.04 $15.00 $420.00 $36.00 $1,008.00 $40.00 $1,120.00 6.25$ $175.00 $40.68 $6.25 $32.92 651% 124%44 11 Control ValveEA 4 $980.81 $3,923.24 $650.00 $2,600.00 $868.00 $3,472.00 $965.00 $3,860.00 775.00$ $3,100.00 $980.81 $775.00 $865.95 127% 113%45 12 WiringLF 800 $0.78 $624.00 $2.00 $1,600.00 $0.69 $552.00 $0.75 $600.00 0.30$ $240.00 $0.78 $0.30 $1.06 260% 74%46 13 WiringLF 800 $0.51 $408.00 $2.00 $1,600.00 $0.45 $360.00 $0.50 $400.00 0.15$ $120.00 $0.51 $0.15 $0.87 340% 59%47 14 3" Class 200 PVC Mainline LF 250 $6.59 $1,647.50 $13.00 $3,250.00 $5.83 $1,457.50 $6.35 $1,587.50 6.00$ $1,500.00 $6.59 $6.00 $7.94 110% 83%48 15 3" HDPE pipeLF 340 $27.12 $9,220.80 $10.50 $3,570.00 $24.00 $8,160.00 $27.00 $9,180.00 22.00$ $7,480.00 $27.12 $22.00 $22.16 123% 122%49 16 2" HDPE pipeLF 340 $13.56 $4,610.40 $7.85 $2,669.00 $12.00 $4,080.00 $13.50 $4,590.00 22.00$ $7,480.00 $13.56 $22.00 $11.73 62% 116%50$23,474.50 $15,865.00 $20,772.38 $23,209.50 $21,535.0051 TOTAL$295,794.72 $386,797.25 $449,451.22 $483,388.22 $324,066.75Low Bid / Eng Est91%Bonness, Inc. Ajax Paving Ind of FL,LLC Wright Construction Prefered Materials,IncEngineer's EstimateUnit Price Comparison Low Bid Low Bid16.A.8.aPacket Pg. 559Attachment: 60016.29 Bid Analysis (7714 : Immokalee Road at Valewood Drive and Oakes Blvd Intersection Improvements) 16.A.8.b Packet Pg. 560 Attachment: Work Order 16-6663 (7714 : Immokalee Road at Valewood Drive and Oakes Blvd Intersection Improvements) 16.A.8.b Packet Pg. 561 Attachment: Work Order 16-6663 (7714 : Immokalee Road at Valewood Drive and Oakes Blvd Intersection Improvements) 16.A.8.b Packet Pg. 562 Attachment: Work Order 16-6663 (7714 : Immokalee Road at Valewood Drive and Oakes Blvd Intersection Improvements) 16.A.8.b Packet Pg. 563 Attachment: Work Order 16-6663 (7714 : Immokalee Road at Valewood Drive and Oakes Blvd Intersection Improvements) 16.A.8.b Packet Pg. 564 Attachment: Work Order 16-6663 (7714 : Immokalee Road at Valewood Drive and Oakes Blvd Intersection Improvements) 16.A.8.b Packet Pg. 565 Attachment: Work Order 16-6663 (7714 : Immokalee Road at Valewood Drive and Oakes Blvd Intersection Improvements) BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT SS BT BT BT BT BT BT BT BT BT BT BT BT BT FO FO FO FO FO FO FO FO FO FO FO FO FO FO6FM6FM6FM6FM6FM6FM6FM6FM6FM6FM FO BT BT BT STOP ONLY BTBTBTBTBTBT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT BT SSSSSSSSSSSSSSSSSSSSSSSSSSSSBTBTBTONE WAYENTERDO NOTBT BT BT BT BT BT BT BT BT BT BTSSSSSSSSSS G:\Transportation Engineering\Design Team\ROADWAY PROJECTS\Intersections\FY17\IMM RD AT OAKS BLVD VALEW DR\PLAN & DETAILS\100% PLANS\06 IMMOK AT VALEWOOD PL6.dwg - 12/3/2018 1:01 PMSHEET OF TITLEPROJECTBY:REVISIONS 2 No. 1 DATE 3 4 16.A.8.d Packet Pg. 566 Attachment: 60016.29 Plan View (7714 : Immokalee Road at Valewood Drive and Oakes Blvd Intersection Improvements)