Agenda 03/27/2018 Item #16A1703/27/2018 EXECUTIVE SUMMARY Recommendation to approve Change Order No. 1 to Contract No. 17-7041 in the amount of $206,443.68 with Thomas Marine Construction, Inc. for the Haldeman Creek Weir (Project No. 60103) ____________________________________________________________________________ OBJECTIVE: To complete the remainder of the construction of the Haldeman Creek Weir replacement project. CONSIDERATIONS: On June 1, 2017, a notice-to-proceed was issued to Thomas Marine Construction, Inc. under contract number 17-7041 to begin construction of a replacement weir for the existing facility on Haldeman Creek in the general area of the intersection of US 41 and Airport-Pulling Road. The summer of 2017 had significantly more rain than the same period of the past 20 years; the month of June alone had rainfall roughly equal to 2 ½ times a typical June in Naples. There was also a direct -hit, major hurricane in September adding to the overall construction suspensions and subsequent equipment remobilizations. The County bid the construction project with the best available information from Geotechnical exploration. The Geotech report showed very little rock in a location abutting the weir site. The contractor encountered extremely hard rock in great quantity directly under the weir site. Given the unexpected site conditions, construction could not proceed as planned. Sheet pile (part of the original weir design) to create a cofferdam for dewatering could not be utilized but rather was eliminated; instead a portable dam system had to be used as a temporary measure to continue construction. As a result, additional heavy equipment and labor costs have escalated beyond original projections. Staff is requesting an additional $206,443.68 for the net construction overruns mainly due to the unexpected geotechnical site conditions. This request represents a 12.77% increase to the overall contract, and has been reviewed and approved by the South Florida Water Management District. In conclusion, due to the excessive rain this past wet season, impacts of Hurricane Irma, and variations in the Geotech in the construction area, staff believes this change order is warranted. This determination is also supported by the Engineer of Record as detailed in the attached letter. FISCAL IMPACT: Total cost is $206,443.68. SFWMD grant funds in the amount of $82,577.47, 40% of eligible expenses, are available within GMD Grant Fund (711), Project 60103. Match funds in the amount of $71,225 are available within GMD Grant Match Fund (712), Proje ct 60103. A budget amendment in the amount of $52,641.21 is required to appropriate additional budget, from the Storm water Capital Improvement Fund (325) to GMD Grant Match Fund (712), Project 60103. This will allow the county to provide the 60% required match for Change Order No. 1. LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for Board approval. -SRT GROWTH MANAGEMENT IMPACT: The project has no impact on the Growth Management Plan. RECOMMENDATION: To approve Change Order No. 1 to Contract No. 17-7041 with Thomas Marine Construction, Inc. in the amount of $206,443.68 and authorize the necessary budget 16.A.17 Packet Pg. 803 03/27/2018 amendments. Prepared by: Shane Cox, P.E., Sr. Project Manager, Capital Project Planning, Impact Fees & Program Management Division ATTACHMENT(S) 1. RE Haldemen Creek ChangeOrder#1 Grant Agreement 4600003476 (MSG) 2. CO #1 Thomas Marine (PDF) 3. Engineer of Record letter (PDF) 16.A.17 Packet Pg. 804 03/27/2018 COLLIER COUNTY Board of County Commissioners Item Number: 16.A.17 Doc ID: 4694 Item Summary: Recommendation to approve Change Order No. 1 to Contract No. 17-7041 in the amount of $206,443.68 with Thomas Marine Construction, Inc. for the Haldeman Creek Weir (Project No. 60103). Meeting Date: 03/27/2018 Prepared by: Title: Project Manager, Senior – Capital Project Planning, Impact Fees, and Program Management Name: Shane Cox 02/09/2018 11:46 AM Submitted by: Title: Division Director - IF, CPP & PM – Capital Project Planning, Impact Fees, and Program Management Name: Amy Patterson 02/09/2018 11:46 AM Approved By: Review: Procurement Services Opal Vann Level 1 Purchasing Gatekeeper Completed 02/09/2018 2:36 PM Growth Management Department Judy Puig Level 1 Reviewer Completed 02/12/2018 10:26 AM Growth Management Department Lisa Taylor Additional Reviewer Completed 02/15/2018 1:04 PM Growth Management Operations Support Allison Kearns Additional Reviewer Completed 02/16/2018 1:41 PM Procurement Services Ted Coyman Additional Reviewer Completed 02/17/2018 2:27 PM Capital Project Planning, Impact Fees, and Program Management Amy Patterson Additional Reviewer Completed 02/21/2018 2:52 PM Procurement Services Catherine Bigelow Additional Reviewer Completed 02/26/2018 2:50 PM Growth Management Department James French Deputy Department Head Review Skipped 02/19/2018 2:53 PM Growth Management Department Thaddeus Cohen Department Head Review Completed 03/01/2018 9:23 AM Grants Edmond Kushi Level 2 Grants Review Completed 03/01/2018 11:27 AM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 03/02/2018 10:22 AM Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 03/06/2018 11:01 AM Grants Therese Stanley Additional Reviewer Completed 03/06/2018 12:59 PM Office of Management and Budget Susan Usher Additional Reviewer Completed 03/06/2018 5:28 PM County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 03/21/2018 3:17 PM Board of County Commissioners MaryJo Brock Meeting Pending 03/27/2018 9:00 AM 16.A.17 Packet Pg. 805 1 CoxMichael From:Taylor, Roxanne <rltaylor@sfwmd.gov> Sent:Wednesday, February 14, 2018 4:34 PM To:CoxShane Cc:PattersonAmy Subject:RE: Haldemen Creek ChangeOrder#1 Grant Agreement 4600003476 Hi Shane, The grant agreement allows for the SFWMD to pay 40% or $800,000 of eligible expenses, whichever is less.Based on the attachments, the additional expenditures specific to construction cost would be considered eligible expenses under the current agreement. Let me know if you need anything else.Thanks! Sincerely, Roxanne Taylor, PWS Everglades Policy & Coordination South Florida Water Management District (239) 263-7615 x7615 rltaylor@sfwmd.gov Compute Your Use by clicking here! From:CoxShane [mailto:Shane.Cox@colliercountyfl.gov] Sent:Wednesday, February 07, 2018 12:05 PM To:Taylor, Roxanne <rltaylor@sfwmd.gov> Cc:PattersonAmy <Amy.Patterson@colliercountyfl.gov> Subject:FW: Haldemen Creek ChangeOrder#1 Grant Agreement 4600003476 Importance:High Hi Roxanne, I have a request-- We are processing a change order for the weir project. Please review the attachments and if you concur, give us an approval statement about the change complying with the grant.(see Lisa Taylor’s request below) I also need to respectfully request you have this completed in the next couple days--- Thanks! Shane Cox, PE Sr Project Manager 16.A.17.a Packet Pg. 806 Attachment: RE Haldemen Creek ChangeOrder#1 Grant Agreement 4600003476 (4694 : -Haldeman Creek Weir Construction Change Order No.1) 2 Capital Project Planning, Impact Fees & Program Management Collier County Government From:TaylorLisa Sent:Wednesday, February 07, 2018 9:02 AM To:CoxShane <Shane.Cox@colliercountyfl.gov> Cc:KearnsAllison <Allison.Kearns@colliercountyfl.gov>; PattersonAmy <Amy.Patterson@colliercountyfl.gov>; StanleyTherese <Therese.Stanley@colliercountyfl.gov>; KushiEdmond <Edmond.Kushi@colliercountyfl.gov> Subject:FW: Haldemen Creek ChangeOrder#1 Grant Agreement 4600003476 Importance:High Shane, We will need SFWMD approval to pay a 40% portion of this change order in writing.Please work with SFWMD to get this approval as soon as possible to keep this moving. It can be an email from an authorized person maybe Lisa Koehler.The original agreement allowed up to $ 800,000 40% contribution as long as we match to 60%. So with their approval we can split this change order as follows: 40% SFWMD 83,595.84 60% Match 125,393.76 Respectfully, Lisa Taylor, CSM Senior Management Budget Analyst Growth Management 2885 S Horseshoe Drive Naples, FL 34101 Phone: (239) 252-5813 Fax: (239) 252-6617 From:TaylorLisa Sent:Wednesday, February 07,2018 7:31 AM To:CoxShane <Shane.Cox@colliercountyfl.gov> Cc:'AmyPatterson@colliergov.net' <AmyPatterson@colliergov.net>; KearnsAllison <Allison.Kearns@colliercountyfl.gov> Subject:FW: Haldemen Creek ChangeOrder#1 (AP).docx Importance:High Shane, For me to move forward with this you will need to get signatures from everyone except Mr. Cohen and purchasing.Send to me as soon as you have those signatures and I will get Mr. Cohen and forward to purchasing. Respectfully, 16.A.17.a Packet Pg. 807 Attachment: RE Haldemen Creek ChangeOrder#1 Grant Agreement 4600003476 (4694 : -Haldeman Creek Weir Construction Change Order No.1) 3 Lisa Taylor, CSM Senior Management Budget Analyst Growth Management 2885 S Horseshoe Drive Naples, FL 34101 Phone: (239) 252-5813 Fax: (239) 252-6617 From:CoxShane Sent:Tuesday, February 06, 2018 4:32 PM To:TaylorLisa <Lisa.Taylor@colliercountyfl.gov> Cc:PattersonAmy <Amy.Patterson@colliercountyfl.gov>; KearnsAllison <Allison.Kearns@colliercountyfl.gov> Subject:FW: Haldemen Creek ChangeOrder#1 (AP).docx Importance:High Lisa, please review and act appropriately (preliminarily approve or request changes) on this change order that Allison and Amy Patterson have finalized. Shane Cox, PE Sr Project Manager Capital Project Planning, Impact Fees & Program Management Collier County Government From:PattersonAmy Sent:Tuesday, February 06, 2018 4:19 PM To:CoxShane <Shane.Cox@colliercountyfl.gov> Cc:KurtzGerald <Gerald.Kurtz@colliercountyfl.gov>; KearnsAllison <Allison.Kearns@colliercountyfl.gov> Subject:FW: Haldemen Creek ChangeOrder#1 (AP).docx Importance:High Shane, Please see the attached change order that has been reviewed by Allison and me.Please forward this on to Lisa Taylor and separately to Procurement.Please ask them to assist us with the initial review to keep this moving forward to the March 13th meeting, understanding that they will see this again through the Accela. Thank you, Amy Amy Patterson Director, Capital Project Planning, Impact Fees and Program Management 2685 South Horseshoe Drive, Unit 103 Naples, FL 34104 239-252-5721 16.A.17.a Packet Pg. 808 Attachment: RE Haldemen Creek ChangeOrder#1 Grant Agreement 4600003476 (4694 : -Haldeman Creek Weir Construction Change Order No.1) 4 From:KearnsAllison Sent:Tuesday, February 06, 2018 3:19 PM To:PattersonAmy <Amy.Patterson@colliercountyfl.gov> Subject:Haldemen Creek ChangeOrder#1 (AP).docx Under Florida Law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by telephone or in writing. 16.A.17.a Packet Pg. 809 Attachment: RE Haldemen Creek ChangeOrder#1 Grant Agreement 4600003476 (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 810 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 811 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 812 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 813 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 814 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 815 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 816 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 817 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 818 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 819 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 820 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 821 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 822 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 823 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 824 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 825 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 826 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 827 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 828 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 829 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 830 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) 16.A.17.b Packet Pg. 831 Attachment: CO #1 Thomas Marine (4694 : -Haldeman Creek Weir Construction Change Order No.1) Registered office: 4030 West Boy Scout Boulevard, Suite 700, Tampa FL 33607, United States Atkins North America, Inc. 4030 West Boy Scout Boulevard Suite 700 Tampa FL 33607 Tel: +1 813 282 7275/'+1 800 477 7275 Project No.: 60103 Direct no: (813) 281-7369 Mr. Shane Cox, P.E. Senior Project Manager Stormwater Management Section 2685 Horseshoe Drive South Suite 103 Naples, FL 34104 info@atkinsglobal.com www.atkinsglobal.com/northamerica 21 Mar 2018 Haldeman Creek Weir Replacement - Geotechnical Exploration Dear Mr. Cox Atkins North America was contracted to perform design and permitting services for the subject project. The services for the project required acquisition of geotechnical data to obtain design parameters for the structural design of the weir, and Tierra, Inc. was subcontracted for the geotechnical services. Borings were conducted on the banks on either side of Haldeman Creek near the proposed structure and along the proposed maintenance road (5 borings in total). Borings were not conducted in the channel at the location of the proposed structure because costs of the geotechnical services would have been roughly threefold, and borings located along the bank are typically adequate for project design, particularly when the channel is man-made, like the Haldeman Creek channel is at this location. However, subsurface conditions are known to vary, even within close proximities. Regarding the proposed Haldeman Creek Weir site, Tierra, Inc. indicated, During the subsurface exploration in 2015 the shallow limestone encountered by the contractor was found to vary across the site. The limestone in this area was encountered from 6 to 15’ below ground surface and is illustrated in the soil profiles (in the report). The borings were performed on dry land, so it is reasonable that the contractor encountered the limestone at shallower depths within the Haldeman Creek. The Tierra, Inc. geotechnical report also indicates that variations in the depth and consistency of this material should be anticipated. Considering these circumstances, and the significant weather factors, we feel a change order is reasonable. Regards, Mark Erwin, P.E, CFM 16.A.17.c Packet Pg. 832 Attachment: Engineer of Record letter (4694 : -Haldeman Creek Weir Construction Change Order No.1)