CCAA Resolution 2010-018Agenda Item No. 16G2
February 9, 2010
Page 4 of 7
RESOLUTION NO. 10 -18
RESOLUTION OF THE COLLIER COUNTY AIRPORT AUTHORITY APPROVING AND
AUTHORIZING THE AUTHORITY'S INTERIM DIRECTOR TO EXECUTE CHANGE
ORDER #3 TO CORAL SANDS CONSTRUCTION LLC CONTRACT #09 -5209 IN THE
AMOUNT OF $83,313.30 FOR ELECTRICAL WORK REQUIRED IN THE
RECONSTRUCTION OF THE T HANGAR BUILDING AT EVERGLADES AIRPARK,
PENDING BCC APPROVAL TO UTILIZE FUNDS FROM IMMOKALEE INFRASTRUCTURE
FUND 497 TO COMPLETE THIS PROJECT.
WHEREAS, the Collier County Airport Authority (Authority) approved Coral Sands
Construction LLC (Contractor) contract 909 -5209 in the amount of $299,984.50 on April 13, 2009
(Resolution No. 09 -29) for the reconstruction of the T hangar building at Everglades Airpark damaged
by Hurricane Wilma; and
WHEREAS, change order 91 to Contract #09 -5209 is for a time extension only; and
WHEREAS, change order #2, in the amount of $11,959.95, is for building modifications; and
WHEREAS, the Authority requested that the electrical work for the T hangar building be
separated out when the contract was bid; and
WHEREAS, only one bid was received for the electrical work; and
WHEREAS, that bid was deemed "non- responsive; and
WHEREAS, the Authority requested that the Contractor obtain competitive pricing for the
electrical work for this project; and
WHEREAS, the total cost for the Contractor to complete the required electrical work is
$83,313.30; and
WHEREAS, $47,948 is available in fund 496; and
WHEREAS, the remaining funds of $35,365.30 needed to complete the electrical work are
available from the Immokalee Infrastructure Fund 497, pending BCC approval to utilize funds from
Fund 497 for this project; and
WHEREAS, the Authority recommends the BCC authorize the Authority to utilize $35,365.30
from the Immokalee Infrastructure Fund 497 to complete electrical work required to complete the
construction of the T hangar building at Everglades Airpark.
NOW, THEREFORE, IT IS HEREBY RESOLVED BY THE COLLIER COUNTY
AIRPORT AUTHORITY, that the Authority approves and authorizes its Interim Director to execute
Change Order #3 to Coral Sands Contract 909 -5209 in the amount of $83,313.30 for electrical work
required in the reconstruction of the T hangar building at Everglades Airpark, pending BCC approval to
utilize funds from Immokalee Infrastructure Fund 497 to complete this project.
February 9, 2010
Page 5 of 7
Resolution 10 -18 Page 2 of 2
PASSED AND DULY ADOPTED by affirmative majority vote of the Collier County Airport
Authority this I I th day of Jp—uqa 2010.
ATTEST:
COLLIER COUNTY AIRPORT AUTHORITY
COLLIER COUNTY, FLORIDA
Debbie Brueggeman, Interim Director Byron Meade, Chairman
Approved as to form and legal sufficiency
Jennifer B, 'te, Assistant County Attorney
C. Wamweuaavw ! 10.18Eke&icaljarX01T-
hangars Coral Sands CO #3 1 -11 -10 mtg.doex