#09-5121 (Aztek CO #1)
CHANGE ORDER
CHANGE ORDER NO.
CONTRACT NO. 09-5121
BCC Date: 1/27/2009
Agenda Item: 16B2
TO: Aztek Communications Technology
4730 Enterprise Ave
Naples, FL 34104
DATE: 4/12/10
PROJECT NAME: Oil Well Road Fiber Installation
Purchase Order NO.: 4500113459
Under our AGREEMENT dated February 28,2010
You hereby are authorized and directed to make the following change(s) in accordance with
terms and conditions of the Agreement: See attached Exhibit "A"
FOR THE Additive Sum of: One hundred and four thousand three hundred and six and seven
cents. ($104,306.07).
Original Agreement Amount
$198,058.84
Sum of Previous Changes
This Change Order Add $85,142.83-Phase 3
$71,400.74-Phase 4 Associated Changes
Subtract $52,237.50-deduct from original amount
----------------------------------------------------...-...
$ 104,306.07
Present Agreement Amount
$302.364.91
The time for completion shall be increased by 60 calendar days due to this Change Order. The
substantial completion date is May 15, 2010 and the final completion date is June 30, 2010. Your
acceptance of this Change Order shall constitute a modification to our Agreement and will be
performed subject to all the same terms and conditions as contained in our Agreement indicated
above, as fully as if the same were repeated in this acceptance. The adjustment, if any, to the
Agreement shall constitute a full and final settlement of any and all claims of the Contractor arising out
of or related to the change set forth herein, including claims for impact and delay costs.
Accepted: ~ f.J.. 7 ,2010
CONTRACTOR:
Aztek Communications
By lMI-/,4
~ike Leed
OWNER:
BOARD OF COUNTY COMMISSIONERS
OF COLLIER COUNTY, FLORIDA
BY:~
Mike Berrios, Project Manager
By:
Bar
Change Order #1
Oil Well Road Fiber Installation
Work OrderIPurchase Order 4500113459
#.~
ATTEST: '.
~
8]:: . . .....'
D.te.d. .. .. .. ..... ... -
~ffiEAL .:
~f - . ..~._.:\eiet-....- ,
.. a.d.~.' ,-,. "...w
." .......-. on. ~
Approved as to form and
<:fi~~~L
~ County Attorney
Sc.o\"t' ~.\ eneh
Print Name
Change Order #1
Oil Well Road Fiber Installation 2
Work OrderIPurchase Order 4500113459
BOARD OF COUNTY COMMISSIONERS
COLLIER COUNTY, FLORIDA
By:
Agenda Item No. 16E9
April 27, 2010
Page 6 of 14
.
Collier County IT Department
PROPOSED PROJECT:
Oil Well Road
Conduit and Fiber for Phase 4
Reduced Pricing
Presented by
Tim Beckman, ReDD
tbeckman@aztek-naDles.com
4730 Enterprise Ave. · Suite 308 · Naples, FL . 34104
Phone: 239-659-0017 · Fax: 239-659-0018
FEBRUARY 28,2010
~-a
Agenda Item No. 16E9
April 27, 2010
Page 7 of 14
CCIT
Oil Well Rd. - Phase 4
SCOPE OF SERVICES
OIL WELL RD. - CONDUIT AND FIBER (pHASE 4)
REDUCED PRICING
We are pleased to submit the following quotation for the project requirements to install conduit
and fiber cabling along the south side of on Well Road from Oil Well Grade Rd. to Camp Kea.is
in conjunction with Phase 4 of the road widening project. This pricing reflects the cost savings of
installing the conduit along with CCPS and US Metro. Aztek Communication Technologies shall
furnish Labor and Material for this project. The Scope of Work will consist of the following:
PRICING:
eonduit InstaUation (F &1 via Directional Bore)
SDR-13.5 Conduit (2") - 550 ft. @ $6. 131ft.
Condnit Installation (F &1 via Trenching - >5,OOOft)
SDR-13.5 Conduit (2") - 22,200 ft. @ $3.27/ft.
Fiber Installation (one cable in conduit)
48-strand Fiber Cable - 24,200 ft. @ SI.13/ft.
Materials
48-strand Fiber Cable - 24,200 ft. @ $0.49/ft.
Hand-holes - 28 @ $680.53/ea.
Fiber Optic Marker Posts - 28 @ $24.50
Tracer Line - 24,200 @ $0.1 O/ft.
Fiber SDUeme:
Fiber Splicing - 96-strands (48 x 2) @ $21/ea.
Fiber Splice Cases - 2 @ S420.00/ea.
OTDR Testin2 (48-strands each direction)
OTDR Testing - 96-strands @ $1 Olea.
HourlY Serviees
Permit and Drawings - 40 hours @ $85/hr.
As-buNt drawings and documentation - 15 hours @ $85/hr.
$3,371.50
$72,594.00
$27,346.00
$11,858.00
$19,054.84
$686.00
$2,420.00
$2,016.00
$840.00
$960.00
$3,400.00
$1.275.00
(Total) $145,821.34
Aztek Communication Technologies will perform the prescribed work as outlined in this
document for a fixed price of 5145,821.34 (One Hundred Forty-five Thousand, Eight Hundred
Twenty-one dollars and Thirty-four cents).
Confidential
Page 2
4/1312010
~a
Agenda Item No. 16E9
April 27, 2010
Page 8 of 14
CCIT
011 Well Rd. - Phase 4
Again, thank you for the opportunity to service Collier Count IT on this project. Please let me
know if you have any additional questions and/or requirements.
Kind regards,
Tim Beckman, RCDD
Confidential
Page 3
4/13/2010
~~~
Agenda Item No. 16E9
April 27,2010
Page 9 of 14
CCIT
Oil Well ReI. - Phase 4
SIGNATURE PAGE
The undersigned authorized representative of Client agrees that the services described in this
proposal accurately describe the scope of the work required and authorizes AZTEK to begin
work under the terms and conditions described in this document.
Please return signed acknowledgment copy promptly.
Collier County IT
Aztek eommunication Technologies
Authorized Client Representative
Tim Beckman, RCDD
Title
President
Title
Date
February 28. 2010
Date
The services and pricing outlined in this proposal will expire sixty (60) days from the date of this
proposal unless extended in writing by Aztek Communication Technologies.
Any applicable Federal, state, and local taxes have been excluded from the charges quoted in this
proposal.
Please contact me if you have any questions.
Thank you,
Tim Beckman. RCDD
Aztek Communication Technologies
4730 Enterprise Ave.
Suite #308
Naples, FL 34104
239-659-0017 OFFICE
239-659-0018 FAX
239-494-7411 CELL
tbeckman@aztek-naples.com
www.aztek-naples.com
Confidential
Page 4
4/1312010
~a
Agenda Item No. 16E9
April 27,2010
Page 10 of 14
CCIT
011 Well Rd. - Phase 4
SCOPE OF SERVICES
OIL WELL RD. - eONDUIT AND FIBER (pHASE 4) - CHANGE ORDER #1
REDUCED PRICING
We are pleased to submit the following quotation for the Change Order requirements to extend
the conduit and fiber cabling 3,000 ft. south on Everglades Blvd. from Oil Well Road, 3,000 ft.
east on Oil Well Road from Everglades Blvd. and 3,000 ft. west on Everglades Blvd. from Oil
Well Grade Rd. This pricing reflects a cost savings of installing the conduit along with CCPS
and US Metro. Aztek Communication Technologies shall furnish Labor and Material for this
project. The Scope of Work will consist of the following:
PRICING:
Conduit Installation (F&I via Directional Bore)
SDR-13.5 Conduit (2") -1,200 ft. @ $6.13/ft.
Conduit Installation (F &1 via Trenching - >5,000ft)
SDR-13.5 Conduit (2" - 9,550 ft. @ $3.27/ft.
$7,356.00
$31,228.50
Fiber Installation (one cable in conduit)
48-strand Fiber Cable-15,800 ft. @$1.13/ft.
Materials
48-strand Fiber Cable -15,800 ft. @ $0.49/ft.
Hand-holes - 8 @ $680.53/ea
Fiber Optic Marker Posts - 8 @ $24.50
Tracer Line-15,8oo@ $0. 101ft.
$17,854.00
$7,742.00
$5A44.24
$196.00
$1,580.00
(Total) $71,400.74
Aztek Communication Technologies will perform the prescribed work as outlined in this
document for a fixed price of $71,400.74 (Seventy-one Thousand, Four HWldred dollars and
Seventy-four cents).
Again, thank you for the opportunity to service Collier Count IT on this project. Please let me
know if you have any additional questions and/or requirements.
Kind regards,
~
--
-
Tim Beckman, RCDO
Confidential
Page 2
31212010
~~i
Agenda Item No. 16E9
April 27,2010
Page 11 of 14
CCIT
011 Well Rd. - Phase 4
SIGNATURE PAGE
The undersigned authorized representative of Client agrees that the services described in this
proposal accurately describe the scope of the work required and authorizes AZTEK to begin
work under the terms and conditions described in this document.
Please return signed acknowledgment copy promptly.
Collier County IT
Aztek Communication Technologies
Authorized Client Representative
Tim Beckman, RCDD
Title
President
Title
Date
February 28.2010
Date
The services and pricing outlined in this proposal will expire sixty (60) days from the date of this
proposal unless extended in writing by Aztek Communication Technologies.
Any applicable Federal, state, and local taxes have been excluded from the charges quoted in this
proposal.
Please contact me if you have any questions.
Thank you,
Tim Beckman, RCDD
Aztek Communication Technologies
4730 Enterprise Ave.
Suite #308
Naples, FL 34104
239-659-0017 OFFICE
239-659-0018 FAX
239-494-7411 CELL
tbeckman@aztek-naples.com
www.aztek-naples.com
Confidential
Page 3
3/212010
Agenda Item No. 16E9
April 27, 2010
Page 12 of 14
REQUEST FOR PROPOSAL RESPONSE TO
Collier County IT Department
PROPOSED PROJECT:
Oil Well Road
Conduit and Fiber for Phase 3
(Joint Installation wI CCPS and US Metro)
Presented by
Tim. Beckman, ReDO
tbeckman@aztek-nao]es.com
4730 Enterprise Ave. · Suite 308 · Naples, FL . 34104
Phone: 239-659-0017 · Fax: 239-659-0018
FEBRUARY 28,2010
~
Agenda Item No. 16E9
April 27, 2010
Page 13 of 14
CCIT
Oil Well Rd. - Phase 3
SCOPE OF SERVICES
OIL WELL RD. - CONDUIT AND FIBER - PHASE 3
We are pleased to submit Optional Pricing to install conduit and fiber cabling along the entire
south side of Oil Well Road from Everglades Blvd. to Oil Well Grade Rd. for the portion that
was originally to remain on the north side. This pricing reflects the cost savings of installing the
conduit along with CCPSand US Metro. Aztek Communication Technologies shall furnish
Labor and Material for this project. The Scope of Work will consist of the following:
PRICING: (This reflects a reduced price to be installed wI CCPS and US Metro)
Conduit Installation (F&I via Trenching - >5,000ft)
SDR-13.5 Conduit (2") - 15,250 ft. @ S3.27/ft. S49,867.50
Fiber Installation (one cable in conduit)
48-strand Fiber Cable-16,000 ft. @ $1. 131ft.
Materials
48-strand Fiber Cable - 16,000 ft. @ SO.49/ft.
Hand-holes - 11 @ S680.53/ea.
Fiber Optic Marke,. Posts - 11 @ S24.50
Tracer Line -16,000 @ SO.10/ft.
$18,080.00
S7,840.00
S7,485.83
$269.50
$1.600.00
(Total) $85,142.83
Aztek Communication Technologies will perform the prescribed work as outlined in this
document for a fixed price of $85,142.83 (Eighty-five Thousand, One Hundred Forty-two dollars
and Eighty-three cents).
Again, thank you for the opportunity to service Collier Count IT on this project. Please let me
know if you have any additional questions and/or requirements.
Kind regards,
~-
--
-
Tim Beckman, RCDD
Confidential
Page 2
31212010
~~-.
Agenda Item No. 16E9
April 27, 2010
Page 14 of 14
CCIT
Oil Well Rd. - Phase 3
SIGNATURE PAGE
The undersigned authorized representative of Client agrees that the services described in this
proposal accurately describe the scope of the work required and authorizes AZTEK to begin
work under the terms and conditions described in this document.
Please return signed acknowledgment copy promptly.
Collier County IT
Aztek Communication Technologies
Authorized Client Representative
Tim Beckman, RCDD
Title
Title
President
Date
February 28. 2010
Date
The services and pricing outlined in this proposal will expire sixty (60) days from the date of this
proposal unless extended in writing by Aztek Communication Technologies.
Any applicable Federal, state, and local taxes have been excluded from the charges quoted in this
proposal.
Please contact me if you have any questions.
Thank you,
Tim Beckman, RCDD
Aztek Communication Technologies
4730 Enterprise Ave.
Suite #308
Naples, FL 34104
239-659-0017 OFFICE
239-659-0018 FAX
239-494-7411 CELL
tbeckman@aztek-naples.com
www.aztek-naples.com
Confidential
Page 3
31212010
() ~ J~t
Jr7 tJ p~ ~ V,.-- \
ITEMNO.:LO-Pl2L-CJllPOL/"1V ~ DATE RECE~ED:
FILE NO.: -t 1Jp.,aY- e-.? dO ~
ROUTED TO: 0" (3 It'lyl, ~
DO NOT WRITE ABOVE THIS LINE ~~ ) I t) ~
REQUEST FOR LEGAL SERVICES
';-:-'; ,
"'-"'" ....."
"...- -
'- .
--;? --r
==~
--<
~};/\
-.
-\
'--.J ..'"
:::0 -,
2fT-
t:Q
Date: April 27, 2010
To:
Colleen Greene
Assistant County Attorney
'Sf;T
~~ tt CD
eta
From:
Lyn M. Wood, C.P.M., Contract Specialist
Purchasing Department, Extension 2667
1~
Re: Contract: 09-5121 "Fiber Optic Installation, Maintenance and Repair"
Contractor: Aztec Communications of South Florida, Inc.
BACKGROUND OF REQUEST:
The attached change order was approved by the BCC on April 27/5 y
2010, Agenda Item 16.E.9. V 5~
You initialed the change order prior to the Executive Summary
being placed in Novus.
ACTION REQUESTED:
Change order review and approval.
OTHER COMMENTS:
Please forward to BCC for signature after approval. If there are any
questions concerning the document, please contact me. Purchasing would
appreciate notification when the documents exit your office. Thank you.