#09-5264 (Commercial Land Maintenance, Inc.)
A G R E E MEN T 09-5264
For
Immokalee Road MSTUlMSTD Landscape Maintenance
THIS AGREEMENT is made and entered into this ~l4\ day of ~Foe.br-~~_, 2010, by and
between the Board of County Commissioners for Collier County, Florida, a politiCal subdivision of the
State of Florida (hereinafter referred to as the "County" or "Owner") and Florida Land Maintenance,
Inc., d/b/a Commercial Land Maintenance authorized to do business in the State of Florida, whose
business address is 3980 Exchange Avenue, Florida 34104 (hereinafter referred to as the
"Contractor").
WIT N E SSE T H:
1. COMMENCEMENT: The contract shall be for a one year (1) year period from the date of Notice
to Proceed, with three (3) one (1) year renewal options. The County Manager, or his designee,
may, at his discretion, extend the Agreement under all of the terms and conditions contained in
this Agreement for up to one hundred eighty (180) days. The County Manager, or his designee,
shall give the Contractor written notice of the County's intention to extend the Agreement term not
less than ten (10) days prior to the end of the Agreement term then in effect.
2. STATEMENT OF WORK: The Board of County Commissioners deemed one (1) firm to be pre-
qualified and awarded a Contract to one (1) firm. The awardee will enter into an Agreement to
provide complete services for Immokalee Road MSTUlMSTD Landscape Maintenance on an
as-needed basis as may be required by the Owner in accordance with the terms and conditions of
Bid #09-5264 and the Contractor's proposal, which is incorporated by reference and made an
integral part of this Agreement. The execution of this Agreement shall not be a commitment to the
Contractor that any work will be awarded to the Contractor. Rather, this Agreement governs the
rights and obligation of the Quotation procedure outlined in the next paragraphs and all Work
undertaken by Contractor for Owner pursuant to this Agreement and that procedure during the
term and any extension of the term of this Agreement.
Prior to the issuance of a Purchase Order, the Owner shall provide a summary of Work to be
performed to the Contractor who will have the opportunity to submit a formal quotation for the
Work based upon the unit prices provided in the bid. The Contractor shall respond with the
information sought within seven (7) working days.
In each Request for Quotation, the Owner reserves the right to specify the period of completion
and the collection of liquidated damages in the event of late completion.
3. COMPENSATION: The Owner shall pay the Contractor for the performance of the Agreement
pursuant to the unit price schedule offered by the Contractor in his bid, together with the cost of
any other charges/fees submitted in the proposal. In such instances, the Contractor shall submit a
copy of the appropriate pages from said price list with the invoice for the non-bid items. Payment
will be made upon receipt of a proper invoice and upon approval by the Project Manager or his
designee, and in compliance with Section 218.70, Fla. Stats., otherwise known as the "Local
Government Prompt Payment Act". Any County agency may utilize the services offered under this
contract, provided sufficient funds are included in its budget(s). Requests for consideration of a
price adjustment must be made on contract anniversary date, in writing, to the Purchasing Director
and, if approved by using Department (price adjustments are dependent upon budget availability
Page -1-
and program manager approval), must be based upon South Urban Consumer Price Index (CPI)
based on the previous twelve (12) months. Any upward price adjustment approved by the County
shall impose upon the Contractor the requirement to advise and extend credit to the County when
costs' similarly decrease. Surcharges, if applicable, will not be accepted in conjunction with this
contract, and such charges should be incorporated into the pricing structures.
4. NOTICES: All notices required or made pursuant to this Agreement to be given by the County to
the Contractor shall be made in writing and shall be delivered by hand, by fax, e-mail, or by the
United States Postal Service Department, first class mail service, postage prepaid, addressed to
the following Contractor's address of record:
Florida Land Maintenance, Inc.
d/b/a Commercial Land Maintenance
3980 Exchange Avenue, Naples, FL 34104
239-643-6205 Telephone
239-643-5012 Fax
Robert Kindelan, President
All notices required or made pursuant to this Agreement to be given by the Contractor to the
County shall be in writing and shall be delivered by hand, by fax, e-mail, or by United States
Postal Service Department, first class mail service, postage prepaid, addressed to the following
County's address of record:
Collier County Government Complex
Purchasing Department
3301 East Tamiami Trail
Purchasing Building G
Naples, Florida 34112
Attention: Stephen Y. Carnell
Purchasing/General Services Director
Phone: 239-252-8371
Fax: 239-252-6584
The Contractor and the County may change the above mailing address at any time upon giving
the other party written notification. All notices under this Service Agreement must be in writing.
5. NO PARTNERSHIP: Nothing herein contained shall create or be construed as creating a
partnership between the County and the Contractor or to constitute the Contractor as an agent of
the County.
6. PERMITS: LICENSES: TAXES: In compliance with Section 218.80, Florida Statutes, all permits
necessary for the prosecution of the Work shall be obtained by the Contractor. Payment for all
such permits issued by the County shall be processed internally by the County. Contractor is not
responsible for paying for permits issued by Collier County, but is responsible for acquiring all
permits. Owner may require the Contractor to deliver internal budget transfer documents to
applicable Collier county agencies when the Contractor is acquiring permits.
All permits, fees and licenses necessary for the prosecution of the Work which are not issued by
Collier County shall be acquired and paid for by the Contractor. Contractor shall pay all sales,
consumer, use and other similar taxes associated with the Work or portions thereof, which are
applicable during the performance of the Work.
Page -2-
7. NO IMPROPER USE: The Contractor will not use, nor suffer or permit any person to use in any
manner whatsoever, county facilities for any improper, immoral or offensive purpose, or for any
purpose in violation of any federal, state, county or municipal ordinance, rule, order or regulation,
or of any governmental rule or regulation now in effect or hereafter enacted or adopted. In the
event of such violation by the Contractor or if the County or its authorized representative shall
deem any conduct on the part of the Contractor to be objectionable or improper, the County shall
have the right to suspend the Contract of the Contractor. Should the Contractor fail to correct any
such violation, conduct, or practice to the satisfaction of the County within twenty-four (24) hours
after receiving notice of such violation, conduct, or practice, such suspension to continue until the
violation is cured. The Contractor further agrees not to commence operation during the
suspension period until the violation has been corrected to the satisfaction of the County.
8. TERMINATION: Should the Contractor be found to have failed to perform his services in a
manner satisfactory to the County and requirements of this Agreement, the County may terminate
said Agreement immediately for cause; further the County may terminate this Agreement for
convenience with a thirty (30) day written notice. The County shall be sole judge of non-
performance.
9. NO DISCRIMINATION: The Contractor agrees that there shall be no discrimination as to race,
sex, color, creed or national origin.
10. INSURANCE: The Contractor shall provide insurance as follows:
A. Commercial General Liabilitv: Coverage shall have minimum limits of $2,000,000 Per
Occurrence, Combined Single Limit for Bodily Injury Liability and Property Damage Liability.
This shall include Premises and Operations; Independent contractors; Products and
Completed Operations and Contractual Liability.
B. Business Auto Liabilitv: Coverage shall have minimum limits of $2,000,000 Per
Occurrence, Combined Single Limit for Bodily Injury Liability and Property Damage Liability.
This shall include Owned Vehicles, Hired and Non-Owned Vehicles and Employee Non-
Ownership.
C. Workers' Compensation: Insurance covering all employees meeting Statutory Limits in
compliance with the applicable state and federal laws. The coverage must include Employers'
Liability with a minimum limit of $1 ,000,000 for each accident.
Special Requirements: Collier County Board of County Commissioners shall be listed as the
Certificate Holder and included as an Additional Insured on the Comprehensive General
Liability.
Current, valid insurance policies meeting the requirement herein identified shall be maintained
by Contractor during the duration of this Agreement. Renewal certificates shall be sent to the
County thirty (30) days prior to any expiration date. There shall be a thirty (30) day
notification to the County in the event of cancellation or modification of any stipulated
insurance coverage.
Contractor shall insure that all subcontractors comply with the same insurance requirements
that he is required to meet. The same Contractor shall provide County with certificates of
insurance meeting the required insurance provisions.
Page -3-
11. INDEMNIFICATION: To the maximum extent permitted by Florida law, the
ContractorNendor/Consultant shall indemnify and hold harmless Collier County, its officers and
employees from any and all liabilities, damages, losses and costs, including, but not limited to,
reasonable attorneys' fees and paralegals' fees, to the extent caused by the negligence,
recklessness, or intentionally wrongful conduct of the Contractor anyone employed or utilized by
the Contractor in the performance of this Agreement. This indemnification obligation shall not be
construed to negate, abridge or reduce any other rights or remedies which otherwise may be
available to an indemnified party or person described in this paragraph.
This section does not pertain to any incident arising from the sole negligence of Collier County.
12. PAYMENTS. Generally, the Contractor will be paid upon completion: however, for
Work in excess of thirty (30) days, the Contractor may indicate on his response to the Request
for Quotation his wish to receive Progress Payments. Subsequent to the first payment,
Contractor must provide Owner with a fully executed Release and Affidavit in the form attached
hereto as Exhibit "B" as a condition precedent to release of each progress payment. All
applications for payment, whether for full payment or a progress payment shall be in writing,
and in substantially the form attached hereto as Exhibit "C".
13. PAYMENTS WITHHELD. Owner may decline to approve any Application for Payment,
or portions thereof, because of defective or incomplete work, outstanding items, subsequently
discovered evidence or subsequent inspections. The Owner may nullify the whole or any part
of any approval for payment previously issued and Owner may withhold any payments
otherwise due Contractor under this Agreement or any other agreement between Owner and
Contractor, to such extent as may be necessary in the Owner's opinion to protect it from loss
because of: (a) defective Work not remedied; (b) third party claims failed or reasonable
evidence indicating probable fling of such claims; (c) failure of Contractor to make payment
properly to subcontractors or for labor, materials or equipment; (d) reasonable doubt that the
Work can be completed for the unpaid balance of the Contract Amount; (e) reasonable
indication that the Work will not be completed within the Contract Time; (f) unsatisfactory
prosecution of the Work by the Contractor; or (g) any other material breach of the Contract
Documents.
If any conditions described above are not remedied or removed, Owner may, after three (3)
days written notice, rectify the same at Contractor's expense. Owner also may offset against
any sums due Contractor the amount of any liquidated or unliquidated obligations of Contractor
to Owner, whether relating to or arising out of this Agreement or any other agreement between
Contractor and Owner.
14.SUBMITTALS AND SUBSTITUTIONS. Any substitution of products/materials from
specifications shall be approved in writing by Owner in advance.
15. CONTRACT TIME AND TIME EXTENSIONS.
A. Time is of the essence in the performance of any Work under this Agreement and Contractor
shall diligently pursue the completion of the Work. Subcontractors will not be allowed in this
contract. Contractor shall be solely responsible for all construction means, methods,
techniques, sequences, and procedures as well as coordination of all portions of the Work
under the Contract Documents, and the coordination of Owner's supplies and contractors.
B. Should Contractor be obstructed or delayed in the prosecution of or completion of the Work as
a result of unforeseeable causes beyond the control of Contractor, and not due to its fault or
Page -4-
neglect, including but not restricted to acts of Nature or of the public enemy, acts of
Government, fires, floods, epidemics, quarantine regulation, strikes or lockouts, Contractor
shall notify the Owner in writing within forty-eight (48) hours after the commencement of such
delay, stating the cause or causes thereof, or be deemed to have waived any right which
Contractor may have had to request a time extension.
C. No interruption, interference, inefficiency, suspension or delay in the commencement or
progress of the Work from any cause whatever, including those for which Owner may be
responsible, in whole or in part, shall relieve Contractor of his duty to perform or give rise to
any right to damages or additional compensation from Owner. Contractor expressly
acknowledges and agrees that it shall receive no damages for delay. Contractor's sole
remedy, if any, against Owner will be the right to seek an extension to the Contract Time;
provided, however, the granting of any such time extension shall not be a condition precedent
to the aforementioned "No Damage for Delay" provision. This paragraph shall expressly apply
to claims for early completion, as well as to claims based on late completion.
16. CHANGES IN THE WORK. Owner shall have the right at any time during the progress of the
Work to increase or decrease the Work. Promptly after being notified of a change, Contractor
shall submit an itemized estimate of any cost or time increases or savings it foresees as a result
of the change. Except in an emergency endangering life or property, or as expressly set forth
herein, no addition or changes to the Work shall be made except upon written order of Owner,
and Owner shall not be liable to the Contractor for any increased compensation without such
written order. No officer, employee or agent of Owner is authorized to direct any extra or
changed work orally. Any modifications to this Contract shall be in compliance with the County
Purchasing Policy and Administrative Procedures in effect at the time such modifications are
authorized.
A Change Order in the form attached as Exhibit "C" to this Agreement, shall be issued and
executed promptly after an agreement is reached between Contractor and Owner concerning
the requested changes. Contractor shall promptly perform changes authorized by duly
executed Change Orders. The Contract Amount and Contract Time shall be adjusted in the
Change order in the manner as Owner and Contractor shall mutually agree.
17. COMPLIANCE WITH LAWS. Contractor agrees to comply, at its own expense, with all federal,
state and local laws, codes, statutes, ordinances, rules, regulations and requirements
applicable to the Project, including but not limited to those dealing with taxation, workers'
compensation, equal employment and safety (including, but not limited to, the Trench Safety
Act, Chapter 553, Florida Statutes). If Contractor observes that the Contract Documents are at
variance therewith, it shall promptly notify Owner in writing.
18. CLEAN UP. Contractor agrees to keep the Project site clean at all times of debris, rubbish and
waste materials arising out of the Work. At the completion of the Work, Contractor shall remove
all debris, rubbish and waste materials from and about the Project site, as well as all tools,
appliances, construction equipment and machinery and surplus materials, and shall leave the
Project site clean and ready for occupancy by Owner.
19. ASSIGNMENT. Contractor shall not assign this Agreement or any part thereof, without the
prior consent in writing of Owner. If Contractor does, with approval, assign this Agreement or
any part thereof, it shall require that its assignee be bound to it and to assume toward
Contractor all of the obligations and responsibilities that Contractor has assumed toward
Owner.
Page -5-
20.STANDARDS OF CONDUCT: PROJECT MANAGER, SUPERVISOR, EMPLOYEES. The
Contractor shall employ people to work on County projects who are neat, clean, well-groomed
and courteous. Subject to the American with Disabilities Act, Contractor shall supply competent
employees who are physically capable of performing their employment duties. The County may
require the Contractor to remove an employee it deems careless, incompetent, insubordinate or
otherwise objectionable and whose continued employment on Collier County projects is not in
the best interest of the County.
21. TESTS AND INSPECTIONS. If the Contract Documents or any codes, laws, ordinances, rules
or regulations of any public authority having jurisdiction over the Project requires any portion of
the Work to be specifically inspected, tested or approved, Contractor shall assume full
responsibility therefore, pay all costs in connection therewith and furnish to the Owner the
required certificates of inspection, testing or approval. All inspections, tests or approvals shall
be performed in a manner and by organizations acceptable to the Owner.
22. EMERGENCIES. In the event of any emergency affecting the safety or protection of persons or
the Work or property at the Project site or adjacent thereto, Contractor, without special
instruction or authorization from Owner is obligated to act to prevent threatened damage, injury
or loss. Contractor shall give the Owner written notice within forty-eight (48) hours after the
occurrence of the emergency, if Contractor believes that any significant changes in the Work or
variations from the Contract Documents have been caused thereby.
If the Owner determines that a change in the Contract Documents is required because of the
action taken in response to an emergency, a Change Order shall be issued to document the
consequences of the changes or variations.
If Contractor fails to provide the forty-eight (48) hour written notice noted above, the Contractor
shall be deemed to have waived any right it otherwise may have had to seek an adjustment to
the Contract Amount or an extension to the Contract Time.
23. COMPLETION. When the entire Work (or any portion thereof designated in writing by Owner)
is ready for its intended use, Contractor shall notify Owner in writing that the entire Work (or
such designated portion) is substantially complete and request that Owner issue a Certificate of
Substantial Completion. Within a reasonable time thereafter, Owner and Contractor shall make
an inspection of the Work (or designated portion thereof) to determine the status of completion.
If Owner does not consider the Work (or designated portion) substantially complete, the Owner
shall notify Contractor in writing giving the reasons therefore.
If Owner considers the Work (or designated portion) substantially complete, Owner shall
prepare and deliver to Contractor a Certificate of Substantial Completion, Exhibit E, which shall
fix the date of Substantial Completion for the entire Work (or designated portion thereof) and
include a tentative punchlist of items to be completed or corrected by Contractor before final
payment.
Owner shall have the right to exclude Contractor from the Work and Project site (or designated
portions thereof) after the date of Substantial Completion, but Owner shall allow Contractor
reasonable access to complete or correct items on the tentative punch list.
Upon receipt of written certification by Contractor that the Work is completed in accordance
with the Contract Documents and is ready for final inspection and acceptance, Owner will
Page -6-
make such inspection and, if Owner finds the Work acceptable and fully performed under the
Contract Documents, he shall promptly issue a Certificate of Final Completion, Exhibit F,
recommending that on the basis of his observations and inspections, and the Contractor's
certification that the Work has been completed in accordance with the terms and conditions of
the Contract Documents, that the entire balance found to be due Contractor is due and
payable. Final payment shall not become due and payable until Contractor submits:
(1) The Release and Affidavit in the form attached as Exhibit "B".
(2) Consent of Surety (if applicable) to final payment.
(3) If required by Owner, other data establishing payment or satisfaction of all obligations,
such as receipt, releases and waivers of liens, arising out of the Contract Documents, to the
extent and in such form as may be designated by Owner.
Owner reserves the right to inspect the Work and make an independent determination as to
the acceptability of the Work. Unless and until the Owner is completely satisfied, the final
payment shall not become due and payable.
24.CONTRACT ADMINISTRATION. This Agreement shall be administered on behalf of the
County by the Alternative Transportation Modes Department.
25. COMPONENT PARTS OF THIS CONTRACT. This Contract consists of the attached or
referenced component parts, all of which are as fully a part of the Agreement as if herein set out
verbatim, including: Contractor's Proposal, Insurance Certificate, Bid No. 09-5264, any
addenda, any Quotation/Purchase Order made or issued pursuant to this Agreement, and any
related plans or specifications for any such Quotations or Purchase Orders.
26. PROHIBITION OF GIFTS TO COUNTY EMPLOYEES. No organization or individual shall offer
or give, either directly or indirectly, any favor, gift, loan, fee, service or other item of value to any
County employee, as set forth in Chapter 112, Part III, Florida Statutes, Collier County Ethics
Ordinance No. 2004-05, and County Administrative Procedure 5311. Violation of this provision
may result in one or more of the following consequences: a. Prohibition by the individual, firm,
and/or any employee of the firm from contact with County staff for a specified period of time; b.
Prohibition by the individual and/or firm from doing business with the County for a specified
period of time, including but not limited to: submitting bids, RFP, and/or quotes; and, c.
immediate termination of any contract held by the individual and/or firm for cause.
27. SUBJECT TO APPROPRIATION. It is further understood and agreed, by and between the
parties herein that this Agreement is subject to appropriation by the Board of County
Commissioners.
28. SALES TAX. Contractor shall pay all sales, consumer, use and other similar taxes associated
with the Work or portions thereof, which are applicable during the performance of the Work. No
markup shall be applied to sales tax.
29.IMMIGRATION LAW COMPLIANCE: By executing and entering into this agreement, the
Contractor is formally acknowledging without exception or stipulation that it is fully responsible
for complying with the provisions of the Immigration Reform and Control Act of 1986 as located
at 8 U.S.C. 1324, et seq. and regulations relating thereto, as either may be amended. Failure
by the Contractor to comply with the laws referenced herein shall constitute a breach of this
agreement and the County shall have the discretion to unilaterally terminate this agreement
immediately.
Page -7-
30. VENUE: Any suit or action brought by either party to this Agreement against the other party
relating to or arising out of this Agreement must be brought in the appropriate federal or state
courts in Collier County, Florida, which courts have sole and exclusive jurisdiction on all such
matters.
31.AGREEMENT TERMS:
otherwise unenforceable,
remain in effect.
If any portion of this Agreement is held to be void, invalid, or
in whole or in part, the remaining portion of this Agreement shall
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
Page -8-
IN WITNESS WHEREOF, the Contractor and the County, have each, respectively, by an authorized
person or agent, hereunder set their hands and seals on the date and year first above written.
ATTEST:
Dwight E. Brock, Clerk of Courts
~c
By: .'. . .
'):-' .' ....
Dated: . co' ...'..-....: ....~~O
, :-(SeaJt .' ::~: . -:
Attetf-u te-CIlir.~ .V..
.t"lt~t .'.iF~" )'
. j,
~
--r;:sh( A
Type/Print Witness Name
~
Se Witness
rv\ To~"-
Type/Print Witness Name
Approved as to form and
le~m
~-~L
Assistal'lt County Attorney ,
~
BOARD OF COUNTY COMMISSIONERS
COLLIER COUNTY, FLORIDA
By: ~..L w. C~~
Fred W. Coyle, Chairman
Florida Land Maintenance, Inc.
d/b/a Commercial Land Maintenance
contract~~.
By: ~ j/;(;//?
. Signature
K0I}~,-:- K/FVf)&L--o/-cJ
, Typed Signature
!~;2 f) / v (~v/ / ---
, Title
Page -9-
EXHIBIT A
RELEASE AND AFFIDAVIT FORM
COUNTY OF COLLIER )
STATE OF FLORIDA )
Before me, the undersigned authority personally appeared
who after being duly sworn, deposes and says:
(1) In accordance with the Contract Documents and in consideration of $
paid, ("Contractor") releases and waives for itself and its
subcontractors, material-men, successors and assigns, all claims demands, damages, costs and expenses,
whether in contract or in tort, against the Board of County Commissioners of Collier County, Florida, relating in
any way to the performance of the Agreement between Contractor and Owner, dated
20_ for the period from to
(2) Contractor certifies for itself and its subcontractors, material-men, successors and assigns, that all charges
for labor, materials, supplies, lands, licenses and other expenses for which Owner might be sued or for which a
lien or a demand against any payment bond might be filed, have been fully satisfied and paid.
(3) Contractor agrees to indemnify, defend and save harmless Owner from all demands or suits, actions,
claims of liens or other charges filed or asserted against the Owner arising out of the performance by
Contractor of the Work covered by this Release and Affidavit.
(4) This Release and Affidavit is given in connection with Contractor's [monthly/final] Application for Payment
No._
CONTRACTOR
BY:
ITS:
President
DATE:
Witnesses
[Corporate Seal]
STATE OF
COUNTY OF
The foregoing instrument was acknowledged before me this _ day of
2010, by , as
a corporation, on behalf of the corporation.
produced
oath.
of
He/she is personally known to me or has
as identification and did (did not) take an
My Commission Expires:
(Signature of Notary)
NAME:
(Legibly Printed)
(AFFIX OFFICIAL SEAL)
Notary Public, State of
Commissioner No.:
Page -10-
EXHIBIT B
FORM OF CONTRACT APPLICATION FOR PAYMENT
(County Project Manager)
(County Department)
Collier County Board of County Commissioners (the OWNER) or
Collier County Water-Sewer District (the OWNER)
FROM:
(Contractor's Representative)
(Contractor's Name)
(Contractor's Address)
RE:
Name)
Bid No. 09-5264
Project No.
Application Date
Payment Application No,
for Work accomplished through the Date:
(Project
Original Contract Time:
Revised Contract Time:
Retainage @ 10% thru[insert date] $
Retainage @ _0/0 after [insert date] $
Percent Work completed to Date:
Percent Contract Time completed to Date
%
%
Liquidated Damages to be Accrued $
ATTACH SCHEDULE OF VALUES AND ACCOMPANYING DOCUMENTATION TO THIS APPLICATION
Original Contract Amount: $
Total Change Orders to Date $
Revised Contract Amount $
Total value of Work Completed
and stored to Date $
Less previous payment (s) $
AMOUNT DUE THIS
APPLICATION: $
CONTRACTOR'S CERTIFICATION: The undersigned CONTRACTOR certifies that: (1) all previous progress payments
received from OWNER on account of Work done under the Contract referred to above have been applied to discharge in
full all obligations of CONTRACTOR incurred in connection with Work covered by prior Applications for Payment
numbered 1 through _ inclusive: (2) title to all materials and equipment incorporated in said Work or otherwise listed
in or covered by this Application for Payment will pass to OWNER at time of payment free and clear of all liens, claims,
security interests and encumbrances (except such as covered by Bond acceptable to OWNER); (3) all amounts have
been paid for work which previous payments were issued and received from the OWNER and that current payment is now
due: (4) and CONTRACTOR agrees that all overruns as shown on the monthly estimate summary shall, in fact, be added
to the revised contract and shall be incorporated into a future Change Order:
(Contractor's Name)
(Signature)
(Type Name & Title)
(shall be signed by a duly authorized representative of CONTRACTOR)
By CONTRACTOR:
DATE:
Payment to the CONTRACTOR for the above AMOUNT DUE THIS APPLICATION is recommended:
(DP's Name)
(Signature) DATE:
(Type Name & Title)
Payment to the CONTRACTOR for the above AMOUNT DUE THIS APPLICATION is approved:
By Design Professional:
By OWNER'S Project Manager:
(Signature) DATE:
(Type Name and Title)
Page -11-
EXHIBIT C
CHANGE ORDER
CHANGE ORDER NO,
CONTRACT NO, 09-5264
TO:
DATE:
PROJECT NAME:
PROJECT NO,:
Under our AGREEMENT dated
,20_.
You hereby are authorized and directed to make the following change(s) in accordance with terms and conditions
of the Agreement:
FOR THE (Additive) (Deductive)
Sum of: $
($
Original Agreement Amount $
Sum of Previous Changes $
This Change Order (Add) (Deduct) $
Present Agreement Amount $
The time for completion shall be (increased/decreased) by calendar days due to this Change Order. Accordingly,
the Contract Time is now L-) calendar days. The substantial completion date is and the
final completion date is . Your acceptance of this Change Order shall constitute a modification to our
Agreement and will be performed subject to all the same terms and conditions as contained in our Agreement indicated above.
as fully as if the same were repeated in this acceptance, The adjustment, if any. to the Agreement shall constitute a full and
final settlement of any and all claims of the Contractor arising out of or related to the change set forth herein. including claims
for impact and delay costs.
Accepted:
.2010
CONTRACTOR:
OWNER:
BOARD OF COUNTY COMMISSIONERS
OF COLLIER COUNTY. FLORIDA
By:
By:_
DESIGN PROFESSIONAL:
By:
Page -12-
EXHIBIT 0
WARRANTY
In consideration of ten dollars, ($10.00), receipt of which is hereby acknowledged, the undersigned
CONTRACTOR does hereby provide, warrant and guarantee all work done and executed under the
contract either directly performed by the CONTRACTOR or at the express request of the
CONTRACTOR by a SUBCONTRACTOR or CONSULTANT.
Project Name:
Date of Final Completion:
Name and Address of CONTRACTOR:
CONTRACTOR warrants and guarantees the work performed pursuant to the contract shall be free of
all defects of materials and workmanship for a period of one year from the DATE OF FINAL
COMPLETION.
The undersigned party further agrees that it will, at its own expense, replace and/or repair all
defective work and materials and all other work damaged by any defective work upon written demand
by the COUNTY. It is further understood that further consideration for this warranty and guaranty is
the consideration given for the requirement pursuant to the general conditions and specifications
under which the contract was let that such warranty and guaranty would be given.
This warranty and guaranty is in addition to any other warranties or guaranties for the work performed
under the contract and does not constitute a waiver of any rights provided pursuant to F/orida
Statutes, Chapter 95, et seq.
DATE:
CONTRACTOR
BY:
Attest:
Page -13-
,~"
ACORD
I........---"
CERTIFICATE OF LIABILITY INSURANCE
DATE (MMIDDNYVY)
PRODUCER Phone: 239-262-5143 Fax:
Brown & Brown of Florida, Inc.
999 Vanderbilt Beach Road, #507
Naples FL 34108-3507
239-261-8265
2 11 2010
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
INSURERS AFFORDING COVERAGE
NAIC#
INSURED
FL Land Maintenance Ine dba
Commercial Land Maintenance
3980 Exchange Avenue
Naples FL 34104
: I~?_URER A: Fc:<::t~omrTl~rc=i_g.__L~ns1JxaIJC_~_ Com,_
',_.!!"?URER 1?:NatJoDi!l .Tr-yg;.t Inl2.1!J::an.c_e cOffiu_1
1.!:J~uRE~fc:c:(_IDSUr9,nC~___ COffiDany ----t--
~~~RER_QJ.J9:(t~ RiY~:r rD-~Q..,___ _____ ___
INSURER E
COVERAGES
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED.
NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE iNSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE
TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
1~;:AD~r--TV~~-~ - -- POLlCY-NUMB~~ ------Tk2LICYEFFECTIVE-lb~~icYEXPIRATlON--- - --- -~~ITS ----
A X !GENERALLlABILITY GL00074082 17/1/2009 ,,7/1/2010 I EACH OCCURRENCE _, s ~LQ~Q_Q__
P' [ oAMAGE TO RENTED
X COMMERCIAL GENERAL L1ABILlTYPREMlsE_:'ilEa occurrence) $ 3 QO----'_~___
, - -l CLAIMS MADE EJ OCCUR , 11_~_E.r?EXP(,,_~y'one person) $ 10, .D 0 0
. I
_ _I ____ _____ _FERSONAL &_A.Q~_!NJURY $), 1 90_0 . 000
I GENERAL AGGREGATE ~_$_2J OQO. 000
1-_gEN'~-::-GGRE~~~ lIM;T AP~S p~~ ~RODU'2:~ -COMP/OP AGG S 2 ,_QO 0 J__Q_Q_~
, POLICY iX I ~~.9.;: Ix : LOC ! :
! AUTOMOBILE LIABILITY iCAOOl1222 7/1/2009 7/1/2010
'~ ANY AUTO
ALL OWNED AUTOS
_.. SCHEDULED AUTOS
~ HIRED AUTOS
L NON-OVIINED AUTOS
i
,"
,
B
COMBINED SINGLE LIMIT ! $ 1 000 000
(EaaccldentJ , I
..---..-- . ----..---
BODILY INJURY
{Per person)
PROPERTY DAMAGE
(Per accident)
I ,
---l
I '
BODILY INJURY
I (Per accident)
~RAGE LIABILITY
ANY AUTO
!
7/1/2009 7/1/2010
i
,
I
1/1/2010 1/1/2011
A.~T? ONLY~ _E!, ACCIDENT ~_ ___
OTHER THAN __~A ACC : $
AUTO ONLY AGG $
-.
c
I
X ~ESS I UMBRELLA LIABILITY !55 3 0 9 2 5 3 8 5
!------' OCCUR L; CLAIMS MADE
... IDEDUCTlBLE
X RETENTION $ (1
WORKERS COMPENSATION 01WCI0A63317
AND EMPLOYERS' LIABILITY Y I N
ANY PROPRIETOR/PARTNER/EXECUTIVE D :
OFFICER/MEMBER EXCLUDED? !
(MandatorylnNH)
If yes, describe under
SPECIAL PROVISIONS below
OTHER
f' E, ACH OCCURRENCE - -
AGGREGATE
-----------
1-
~-_._._-
;
,S5~000. 000
,. i '10LOOO. 000
-i'---- ,
j.!..-
1$
,I.WCSTATU-:..I OTH-'
1\_l.IOBYI..LMITS I ___ER1_____ _
_~L~ACH ACCIDENT _ ___-'-_!_LLQ_Q_Q_-'- 00 0
E,L DISEASE _~_A EMPLOYEE $ LOQO, Q_Q_Q ___
E.L DISEASE - POLICY LIMIT $ 1 000 000
D
I
,
I
DESCRIPTION OF OPERA TlONS I lOCATIONS I VEHICLES I EXCLUSIONS ADDED BY ENDORSEMENT I SPECIAL PROVISIONS
andscaping Contractor.
*10 Days Notice Given for Non-Payment of Premium, Workers Compensation 30 days except 10 days for non payment.
ertificate Holder is included as additional insured per form # CGL021 (11-08) Additional Insured Owner's, Lessees,
r Contractors - Scheduled Person or Organization when required under a written contract or agreement. Waiver of
ubrogation applies when required under written contract per form # CGL004 (11-08}GeneraI Liability Advantage
ndorsement. Workers Compensation includes Blanket Waiver of Subrogation when required by written contract~
CERTIFICA TE HOLDER
CANCELLATION
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED
BEFORE THE EXPIRATION DATE THEREOF, THE ISSUING INSURER
WILL ENDEAVOR TO MAIL '45 DAYS WRITTEN NOTICE TO THE
Collier County Board of County CERTIFICATE HOl,DER NAMED TO THE LEFT, BUT FAILURE TO DO SO
Commissioners SHALL IMPOSE NO OBLIGATION OR LIABILITY OF ANY KIND UPON
3301 East Tamiami Trail THE INSURER, I'::'S AGENTS OR REPRESENTATIVES.
Naples FL 34112
AUTHORIZED REPRESENTATIVE d.JJ,A,,f~,!idr
ACORD 25 (2009/01)
@ 1988-2009 ACORD CORPORATION. All rights reserved.
The ACORD name and logo are registered marks of ACORD
IMPORTANT
If the certificate holder is an ADDITIONAL INSURED, the pollcy(ies) must be endorsed, A statement
on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s),
If SUBROGA nON IS WAIVED, subject to the terms and conditions of the policy, certain policies may
require an endorsement A statement on this certificate does not confer rights to the certificate
holder in lieu of such endorsement(s)
DISCLAIMER
This Certificate of Insurance does not constitute a contract between the issuing insurer(s}, authorized
representative or producer, and the certificate holder, nor does it affirmatively or negatively amend,
extend or alter the coverage afforded by the policies listed thereon,
ACORD 25 (2009/01)
DESCRIPTIONS Continued.
Endorsemenc. Workers Compensation includes Blanket waiver of Subrogation when required by written contract.
Bid # 09-5264, "lmmokalee Road MSTU/MSTD Landscape Maintenance"