#03-3517 Amendment 7 (Greeley & Hansen, LLC)
EXHIBIT A-7: Amendment 7 to Contract 03-3517
"Professional Engineering Services for Water Main Projects"
This amendment, dated M.. y c ~ ;1.5 , 2008 to the referenced agreement shall be by and
between the parties to the original Agreement, Greeley and Hansen LLC, (to be referred to as
"Consultant") and Collier County, Florida, (to be referred to as "Owner").
Statement of Understanding
RE: Contract 03-3517 "Professional Engineering Services for Water Main Projects"
In order to continue the services provided for in the original Contract document referenced
above, the Consultant agrees to amend the above referenced Contract as follows.
Perform the additional tasks identified on the attached page.
The Consultant agrees that this amends the original Contract and that the Consultant agrees to
complete said services in the amount of two hundred thirty thousand five hundred twenty dollars
($230,520).
All other terms and conditions of the agreement shall remain in force.
IN WITNESS WHEREOF, the Consultant and the County have each, respectively, by an
authorized person or agent, hereunder set their hands and seals on the date(s) indicated below.
CONSULTANT:
.~ ~A..l1
Greeley and Hansen LLC
Co
By:
Dated:
"2. " ("ou')
~ J I 0:- c.
By:
Title:
Dated:
j{~ H{~ldl
A l, <,r)( i Clt<.-
-S;, vt .....<<.rv :,. "2DO\'
CORPORATE SEAL
ATTEST:
OWNER:
(1uu 1afr:~o'c,
, IlwlQ.htE. Bro ~2e
.~..to_ I
1'.n'~'.l" .
BOA~D 0 COUNT COMMISSIONERS
COLLIE COUN FLORIDA
.
By: . 'DL--"
n
Approved as to form and
Legal sufficiency:
ASS~~~
COLLIER COUNTY GOVERNMENT
PUBLIC UTILITIES ENGINEERING DEPARTMENT
CONTRACT NO. 03-3517
County Road 951 and US 41 Water Mains
Professional Services Agreement Amendment NO.7
Greeley and Hansen LLC
November 9, 2007
Amendment No.7 is for additional engineering services during construction related to
the additional construction contract completion time provided to the Contractor and for night-
time construction. The following are descriptions and additional engineering costs for
Amendment No.7 additional tasks not included in the original Scope of Services or in
Amendments 1,2,34,5, and 6:
Task No.
Task Description
Additional
Engineering Cost
A.7.I-a
1,860 additional hours for providing construction
observation services during the additional 147 days added
to the Contractor's schedule.
$137,280
A.7.l-b
1,260 additional hours for providing construction
observation services during night time construction.
$93,240
TOTAL FOR AMENDMENT NO.7:
$230,520 T&M
Page I of I