Agenda 03/10/2026 Item #16A 1 (Final acceptance of the potable water utility facilities for St. Katherine’s Greek Orthodox Church – Phase 2, PL20250015142)3/10/2026
Item # 16.A.1
ID# 2026-177
Executive Summary
Recommendation to approve final acceptance of the potable water utility facilities for St. Katherine's Greek Orthodox
Church — Phase 2, PL20250015142.
OBJECTIVE: To have the Board of County Commissioners, as Ex-Officio Governing Board of the Collier County
Water -Sewer District, approve final acceptance of the potable water facilities, in accordance with the Collier County
Utility Standards and Procedures, Ordinance No. 2004-31.
CONSIDERATIONS:
1. The Developer of St. Katherine's Greek Orthodox Church — Phase 2 constructed the potable water facilities
within dedicated easements to serve this private development (see attached location map).
2. A final inspection to discover defects in materials and workmanship was conducted by staff on January 20,
2026, in coordination with Public Utilities, and these facilities are satisfactory and acceptable.
3. Staff recommends final acceptance of the subject potable water utility facilities. The subject potable water
facilities are owned and maintained by the developer.
4. This final acceptance is in accordance with Collier County, Ordinance No. 2004-31, as amended.
5. Staff is unaware of any issues that would serve to negate the recommendation to release the project.
This item is consistent with the Collier County strategic plan objective to operate an efficient and customer -focused
permitting process.
FISCAL IMPACT: Review and inspection fees in the amount of $1,396.63 were paid under the original application,
SDPA PL20230015432, and deposited in Planning Fund (1014).
GROWTH MANAGEMENT IMPACT: There is no growth management impact associated with this action.
LEGAL CONSIDERATIONS: This item has been approved as to form and legality, and requires a majority vote for
Board approval. — SAA
RECOMMENDATION(S): To approve final acceptance of the potable water and sewer utility facilities for St.
Katherin's Greek Orthodox Church — Phase 2, PL20250015142.
PREPARED BY: Lucia S. Martin, Project Manager I, Development Review Division
ATTACHMENTS:
Location Map
Verification of Final Cost
ST. KATHERINE' S GREEK ORTHODOX
CHURCH - PHASE 2
LOCATION MAP
VERIFICATION OF FINAL COST
PROJECT NAME: St. Katherine's Greek Orthodox Church Phase 2
LOCATION: Section 16 Township 48 S Range 28 E
Collier County, Florida
NAME A ADDRESS OF OWNER: St. Katherine's Greek Orthodox Church, Inc.
7100 Airport Pulling Road, N.
Naples, FL 34109
TYPE OF UTILITY SYSTEM: POTABLE WATER (Material & Services)
ite
Wks, u nti Units
ost
ofa/
PVC DR 14 PVC Fire Line
4" 74 LF
$22.09
$1,634.66
PIV
4" 1 EA
$4,551.39
$4,551.39
Check Valve
4" 1 FA
$2,178.88
$2,178.88
FDC
4" 1 EA
$2,777.80
$2,777.80
TOTAL COST
$11,142.73
I do hereby certify that the quantities of material and services described above are true and an accurate
accurate represe"ion optfe as -installed cost of the system.
rresiaent
OF: y JENSEN UNDERGROUND UTILITIES, INC.
5586 Taylor Road
Naples, Florida 34109
STATE OF FLORIDA
) SS:
COUNTY OF COLLIER )
Sworn to and Subscribed before me means ofphy
sical presence or online notarization this
18th day of Decemper, 2025, by Kevinensen , Personally known to me. _
6129-MVIMMIFF SEAL:
Public 0
DONNA L. VENTRE
F"y COI' MISSION # HH 313MO
EXPIRES: June 1, 2027