Loading...
#24-8233 (Marquee Development, Inc) CONSTRUCTION AGREEMENT THE BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY, FLORIDA, ("County" or "Owner") hereby contracts with Marquee Development, Inc ("Contractor") of 4801 Troydale Road, Tampa, FL 33615, a Florida Profit Corporation, authorized to do business in the State of Florida, to perform all work ("Work") in connection with Immokalee Sidewalks Phase III, Invitation to Bid No. 24-8233 ("Project"), as said Work is set forth in the Plans and Specifications prepared by LJA Engineering, Inc. FKA Agnoli, Barber and Brundage, the Engineer and/or Architect of Record ("Design Professional") and other Contract Documents hereafter specified. Owner and Contractor, for the consideration herein set forth, agree as follows: Section 1. Contract Documents. A. The Contract Documents consist of this Agreement, the Exhibits described in Section 6 hereof, the Legal Advertisement, the Bidding Documents and any duly executed and issued addenda, Change Orders, Work Directive Changes, Field Orders, and amendments relating thereto. All of the foregoing Contract Documents are incorporated by reference and made a part of this Agreement (all of said documents including the Agreement sometimes being referred to herein as the "Contract Documents" and sometimes as the "Agreement" and sometimes as the "Contract"). A copy of the Contract Documents shall be maintained by Contractor at the Project site at all times during the performance of the Work. B. Owner shall furnish to the Contractor one reproducible set of the Contract Documents and the appropriate number of sets of the Construction Documents, signed and sealed by the Design Professional, as are reasonably necessary for permitting. Section 2. Scope of Work. Contractor agrees to furnish and pay for all management, supervision, financing, labor, materials, tools, fuel, supplies, utilities, equipment and services of every kind and type necessary to diligently, timely, and fully perform and complete in a good and workmanlike manner the Work required by the Contract Documents. Section 3. Contract Amount. In consideration of the faithful performance by Contractor of the covenants in this Agreement to the full satisfaction and acceptance of Owner, Owner agrees to pay, or cause to be paid, to Contractor the following amount (herein "Contract Amount"), in accordance with the terms of this Agreement: One Million One Hundred One Thousand One Hundred Seventy-Nine Dollars and Fifty Cents ($1,101,179.50). The amount of Eighty-five Thousand Dollars ($85,000.00) has been allocated as an Owner's Allowance. Any allowance dollar amount that has been included in the Contractor's Bid Schedule amount is not a guaranteed portion of the aforementioned Contract Amount but rather is only eligible for reimbursement by the Owner if and subject to whether a specific dollar amount of the allowance is expressly authorized by the Owner and formally agreed upon and memorialized by the Parties in writing (the "Owner's Allowance"). Any dollar portion of an Owner's Allowance that is not authorized by the Owner and memorialized by the Parties in writing, via Change Order, shall not be eligible for reimbursement/payment by the Owner as part of a Payment Application submitted by the Contractor. Construction Services Agreement:[2024_ver.3] Section 4. Bonds. A. If applicable, the Contractor shall provide Performance and Payment Bonds, in the form prescribed in Exhibit B-1 and B-2, in the amount of 100% of the Contract Amount, plus any approved allowance as provided in Section 3, the costs of which are to be paid by Contractor. The Performance and Payment Bonds shall be underwritten by a surety authorized to do business in the State of Florida and otherwise acceptable to Owner; provided, however, the surety shall meet the requirements of the Department of the Treasury Fiscal Service, "Companies Holding Certificates of Authority as Acceptable Sureties on . Federal Bonds and as Acceptable Reinsurance Companies" circular. This circular may be accessed via the web at https://fiscal.treasurv.aov/surety-bonds/list-certified-companies.html. Should the Contract Amount be less than $500,000,the requirements of Section 287.0935, F.S. shall govern the rating and classification of the surety. B. If the surety for any bond furnished by Contractor is declared bankrupt, becomes insolvent, its right to do business is terminated in the State of Florida, or it ceases to meet the requirements imposed by the Contract Documents, the Contractor shall,within five(5)calendar days thereafter, substitute at its cost and expense another bond and surety, both of which shall be subject to the Owner's approval. Section 5. Contract Time and Liquidated Damages. A. Time of Performance. Time is of the essence in the performance of the Work under this Agreement. The "Commencement Date" shall be established in the written Notice to Proceed to be issued by the Project Manager, as hereinafter defined. Contractor shall commence the Work within five (5) calendar days from the Commencement Date. No Work shall be performed at the Project site prior to the Commencement Date. Any Work performed by Contractor prior to the Commencement Date shall be at the sole risk of Contractor. Contractor shall achieve Substantial Completion within Two Hundred Ten(210)calendar days from the Commencement Date(herein "Contract Time"). The date of Substantial Completion of the Work(or designated portions thereof) is the date certified by the Design Professional when construction is sufficiently complete, in accordance with the Contract Documents, so Owner can occupy or utilize the Work(or designated portions thereof)for the use for which it is intended, as more particularly defined herein at Section 16, Defined Terms. Contractor shall achieve Final Completion within Thirty (30) calendar days after the date the Punch List is delivered to the Contractor. Final Completion shall occur when the Agreement is completed in its entirety, is accepted by the Owner as complete and is so stated by the Owner as completed. As used herein and throughout the Contract Documents, the phrase "Project Manager" refers to the Owner's duly authorized representative and shall mean the Department Administrator or Division Director, as applicable, acting directly or through duly authorized representatives. B. Liquidated Damages in General. Owner and Contractor recognize that, since time is of the essence for this Agreement, Owner will suffer financial loss if Contractor fails to achieve Substantial Completion within the time specified above, as said time may be adjusted as provided for herein. In such event, the total amount of Owner's damages, will be difficult, if not impossible, to definitely ascertain and quantify. Should Contractor fail to achieve Substantial Completion within the number of calendar days established herein, Owner shall be entitled to assess, as liquidated damages, but not as a penalty, One Thousand Six Hundred Ninety-Nine Dollars ($1,699.00)for each calendar day thereafter until Substantial Completion is achieved. Further, in the event Substantial Completion is reached, but the Contractor fails to reach Final Completion within the required time period, Owner shall also be entitled to assess, and Contractor shall be liable for all actual damages incurred by Owner as 2 Construction Services Agreement:[2024_ver.3] a result of Contractor failing to timely achieve Final Completion. The Project shall be deemed to be substantially completed on the date specified by the Project Manager (or at his/her direction, the Design Professional) as memorialized in the Certificate of Substantial Completion issued pursuant to the terms hereof, and as more particularly defined herein at Section 16, Defined Terms. Contractor hereby expressly waives and relinquishes any right which it may have to seek to characterize the above noted liquidated damages as a penalty, which the parties agree represents a fair and reasonable estimate of the Owner's actual damages at the time of contracting if Contractor fails to Substantially or Finally Complete the Work within the required time periods. C. Computation of Time Periods. When any period of time is referenced by days herein, it shall be computed to exclude the first day and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day shall be omitted from the computation, and the last day shall become the next succeeding day which is not a Saturday, Sunday, or legal holiday. D. Determination of Number of Days of Default. For all contracts, the Owner will count default days in calendar days. E. Right of Collection. The Owner has the right to apply any amounts due Contractor under this Agreement or any other agreement between Owner and Contractor, as payment on such liquidated damages due under this Agreement in Owner's sole discretion. Notwithstanding anything herein to the contrary, Owner retains its right to liquidated damages due under this Agreement even if Contractor, at Owner's election and in its sole discretion, is allowed to continue and to finish the Work, or any part of it, after the expiration of the Contract Time including granted time extensions. F. Completion of Work by Owner. In the event Contractor defaults on any of its obligations under the Agreement and Owner elects to complete the Work, in whole or in part, through another contractor or its own forces, the Contractor and its surety shall continue to be liable for the liquidated damages under the Agreement until Owner achieves Substantial and Final Completion of the Work, as more particularly defined herein at Section 16, Defined Terms. Owner will not charge liquidated damages for any delay in achieving Substantial or Final Completion as a result of any unreasonable action or delay on the part of the Owner. G. Final Acceptance by Owner. The Owner shall consider the Agreement complete when the Contractor has completed in its entirety all of the Work and the Owner has accepted all of the Work and notified the Contractor in writing that the Work is complete. Once the Owner has approved and accepted the Work, Contractor shall be entitled to final payment in accordance with the terms of the Contract Documents. H. Recovery of Damages Suffered by Third Parties. Contractor shall be liable to Owner to the extent Owner incurs damages from a third party as a result of Contractor's failure to fulfill all of its obligations under the Contract Documents. Owner's recovery of any delay related damages under this Agreement through the liquidated damages does not preclude Owner from recovering from Contractor any other non-delay related damages that may be owed to it arising out of or relating to this Agreement. 3 Construction Services Agreement:[2024_ver.3] Section 6. Exhibits Incorporated. Exhibits Incorporated: The following documents are expressly agreed upon, attached hereto, and made a part of this Agreement for Solicitation 24-8233 Immokalee Sidewalks Phase Ill. Exhibit A-1: Contractor's Bid Schedule Exhibit A-2: Contractor's Bid Submittal Forms and Addendums Exhibit A-3: Contractor's List of Key Personnel Assigned to the Project Exhibit B-1: Payment Bond Form ❑ Not Applicable Exhibit B-2: Performance Bond Form ❑ Not Applicable Exhibit B-3: Insurance Requirements Exhibit C: Release and Affidavit Form Exhibit D-1: Contractor Application for Payment Form Exhibit D-2: Schedule of Values Exhibit D-3: Stored Materials Record Exhibit E-1: Change Order Form Exhibit E-2 Work Directive Form Exhibit F-1: Certificate of Substantial Completion Form Exhibit F-2: Certificate of Final Completion Exhibit F-3: Punch List Form Exhibit G-1: Final Payment Checklist Exhibit G-2: Warranty Exhibit H: General Terms and Conditions Exhibit I: Supplemental Terms and Conditions ® Applicable [' Not Applicable The following documents are expressly agreed to be incorporated by reference and made a part of this Agreement for Solicitation 24-8233 Immokalee Sidewalks Phase Ill. The complete contract documents, including Addendum with attachments, are available on the County's on-line bidding system, which the parties agree comprise the final integrated agreement executed by the parties. Sections corresponding to any checked box ( ® ) expressly apply to the terms of this Agreement and are available through the County's on-line bidding. ❑Exhibit J: Technical Specifications ❑Exhibit K: Permits ['Exhibit L: Standard Details ®Exhibit M: Plans and Specifications prepared by: LJA Engineering, Inc. ®Exhibit N: Environmental Health and Safety Requirements for Construction Projects Section 7. Notices A. All notices required or made pursuant to this Agreement by the Contractor to the Owner shall be deemed duly served if delivered by U.S. Mail or E-mail, addressed to the following: Collier County Board of County Commissioners, FL do Community Redevelopment Agency 3299 Tamiami Trail E. Naples, FL 34112 Attn: Christie Betancourt, CRA Assistant Director Phone: 239-867-0028 4 Construction Services Agreement:[2024_ver.3] Email: Christie.Betancourt@colliercountyfl.gov B. All notices required or made pursuant to this Agreement by Owner to Contractor shall be made in writing and shall be deemed duly served if delivered by U.S. Mail, or E-mail, addressed to the following: Marquee Development, Inc. 4801 Troydale Rd. Tampa, FL 33615 Attn: Garnett Craig, President Phone: 813-758-4195 Email: marqueedev@aol.com C. Either party may change its above noted address by giving written notice to the other party in accordance with the requirements of this Section. Section 8. PUBLIC ENTITY CRIMES. 8.1 By its execution of this Contract, Construction Contractor acknowledges that it has been informed by Owner of the terms of Section 287.133(2)(a) of the Florida Statutes which read as follows: "A person or affiliate who has been placed on the convicted vendor list following a conviction for a public entity crime may not submit a bid on a contract to provide any goods or services to a public entity for the construction or repair of a public building or public work, may not submit bids on leases of real property to a public entity, may not be awarded or perform work as a contractor, supplier, subcontractor, or consultant under a contract with any public entity in excess of the threshold amount provided in s. 287.017 for CATEGORY TWO for a period of 36 months from the date of being placed on the convicted vendor list." Section 9. Modification. No modification or change to the Agreement shall be valid or binding upon the parties unless in writing and executed by the party or parties intended to be bound by it. Section 10. Successors and Assigns. Subject to other provisions hereof, the Agreement shall be binding upon and shall inure to the benefit of the successors and assigns of the parties to the Agreement. Section 11. Governing Law. The Agreement shall be interpreted under, and its performance governed by the laws of the State of Florida. Section 12. No Waiver. The failure of the Owner to enforce at any time or for any period of time any one or more of the provisions of the Agreement shall not be construed to be and shall not be a waiver of any such provision or provisions or of its right thereafter to enforce each and every such provision. 5 Construction Services Agreement:[2024_ver.3] Section 13. Entire Agreement. Each of the parties hereto agrees and represents that the Agreement comprises the full and entire agreement between the parties affecting the Work contemplated, and no other agreement or understanding of any nature concerning the same has been entered into or will be recognized, and that all negotiations, acts, work performed, or payments made prior to the execution hereof shall be deemed merged in, integrated, and superseded by the Agreement. Section 14. Severability. Should any provision of the Agreement be determined by a court to be unenforceable, such a determination shall not affect the validity or enforceability of any other section or part thereof. Section 15. Change Order Authorization. The Project Manager shall have the authority on behalf of the Owner to execute all Change Orders and Work Directive Changes to the Agreement to the extent provided for under the Owner's Procurement Ordinance, as amended, and the terms of the Contract Documents. Section 16. Construction. (i) Any doubtful or ambiguous language contained in this Agreement shall not be construed against the party who physically prepared this Agreement. The rule sometimes referred to as "fortius contra proferentum" (pursuant to which ambiguities in a contractual term which appears on its face to have been inserted for the benefit of one of the parties shall be construed against the benefited party) shall not be applied to the construction of this Agreement. (ii) Defined Terms: The following Defined Terms used in the Agreement shall be understood to be defined as expressly set forth below. Other terms referenced in the Agreement shall be understood as they may separately be defined herein or if not so defined shall be understood consistent with their natural and ordinary meaning. (a) "Application for Payment" shall mean the form provided by the Owner that is to be used by the Contractor in requesting a progress or final payment and which is to include such supporting documentation as is required by the Contract Documents. (b) "Construction Project" shall mean a Project, funded by Owner funds that involves the process of building, altering, repairing, improving, or demolishing any public structure or building, or other public improvements of any kind to any real property owned or under the control of the Owner, which Work is being performed under a Construction Contract. (c) "Construction Services" shall mean all labor and materials to be provided by Contractor in connection with the construction, alteration, repair, demolition, reconstruction, or any other improvements to real property. Construction Services also means Work. (d) "Contract" or "Contract Documents" shall refer to those documents described in Section 1, subsection A of the Agreement. 6 Construction Services Agreement:[2024_ver.3] (e) "Defective" shall mean an adjective which, when modifying the Work, refers to Work that is unsatisfactory, faulty, deficient or otherwise does not conform to the Contract Documents. (f) "Department" shall mean the Department or Division initiating and managing the Project on behalf of the Owner. (g) "Director" shall mean the Director or Administrator of the Department or Division initiating and managing the Project on behalf of the Owner. (h) "Final Acceptance"shall mean acceptance of the Work by the Owner as evidenced by the signature of the Project Manager or Design Professional upon the Certificate of Final Completion form, Exhibit F-2. Final Acceptance shall be deemed to have taken place only if and when such signature is affixed to such certificate. The Certificate of Final Completion shall be signed only after the Project Manager has assurance by tests, inspection, or otherwise that all of the provisions of the Contract Documents have been carried out, including completion of the Punch List form, Exhibit F-3. (i) "Professional" or "Design Professional" shall mean the professional architectural/engineering firm designated to perform the design, Construction Engineering and Inspection ("CEI") services, by an existing agreement, or resident in-house Owner engineering services for the Work. At times, Owner staff may perform the design for the Work in-house and shall be considered the Professional in relation to the Work or a particular portion of the Work. (j) "Project" shall mean the total construction, of which the Work to be provided under the Contract Documents may be the whole or a part as indicated elsewhere in the Contract Documents. (k) "Project Manager" shall mean an individual employed by the Owner and assigned to manage and administer the Project which is the subject of the Contract Documents. (I) "Proper Invoice" shall mean an invoice that conforms with all statutory requirements and all requirements specified in the Contract Documents. (m)"Punch List" shall mean the approved list of incomplete and/or deficient Work that shall be completed by the Contractor after Substantial Completion but before the Final Acceptance can be certified by the Project Manager. The Punch List enumerates the items required to render complete, satisfactory and acceptable all Work by the Contractor. The Punch List is developed by the Contractor, Owner and Professional (if any) in accordance with the provisions of the Contract and within the time frames required therein. The Punch List essentially includes items of a minor nature; major items must be completed before Substantial Completion and cannot be considered to be Punch List work. (n) "Schedule of Values" shall mean a schedule showing all activities of the Work subdivided into component parts in sufficient detail to serve as the basis for measuring quantities in place and/or calculating amounts for progress payments during construction. The Schedule of Values shall be satisfactory in form and substance to the Project Manager. 7 Construction Services Agreement:[2024_ver.3] (o) "Substantial Completion" shall mean the status of completion of the Work which, in the opinion of the Project Manager as evidenced by a definitive Certificate of Substantial Completion, is complete in accordance with the Contract Documents, except for minor outstanding items listed on the Punch List. Substantial Completion includes, but is not limited to, the following occurring: (1)the Work can be safely utilized for the purposes for which it was intended; (2) all regulatory agency requirements are satisfied, including occupancy permits, operating certificates and similar releases, (3) all operational testing has successfully occurred; (4) all required training has successfully occurred; (5) all close-out documents (such as as-built drawings, certifications, warranties, guaranties, test reports,test logs, operational manuals, etc.) have been provided by the Contractor and accepted by the Owner, and permit acceptance by permitting agencies, if applicable, see Exhibit F-1. (p) "Work" shall mean the Work to be performed under this Agreement and shall consist of furnishing all tools, equipment, materials, supplies, and manufactured articles and for furnishing all transportation and services, including fuel, power, water, and essential communications, and for the performance of all labor, work, or other operations required for the fulfillment of the Agreement in strict accordance with the Specifications, schedules, Drawings, and other Contract Documents as herein defined, all of which are made a part hereof, and including such detailed sketches as may be furnished by the Professional from time to time during construction in explanation of said Contract Documents. The Work shall be complete, and all work, materials, and services not expressly shown or called for in the Contract Documents, which may be necessary for the complete and proper construction of the Work in good faith, shall be performed, furnished, and installed by the Contractor as though originally so specified or shown, at no increase in cost to the Owner. (q) "Written Directive" shall mean a written directive and also referred to as work directive, as required by in Exhibit H, Section 10.1, in the form that appears in Exhibit E-2 that is issued to a Contractor from Owner in instances where the parties cannot agree on price and/or costs associated with work arising from differing, unforeseen or emergency site conditions and the work in question is part of the "critical path" of the contract schedule. A written directive should ultimately be followed up with an agreed upon Change Order. A verbal Work Directive may only be issued in extraordinary emergencies when necessary to protect and promote the public interest, which shall be followed up with a written Work Directive within five (5) business days. Section 17. Order of Precedence In the event of any conflict between or among the terms of any of the Contract Documents, the terms of the Construction Agreement and the General Terms and Conditions shall take precedence over the terms of all other Contract Documents, except the terms of any Supplemental Conditions shall take precedence over the Construction Agreement and the General Terms and Conditions. To the extent any conflict in the terms of the Contract Documents including the Owner's Board approved Executive Summary cannot be resolved by application of the Supplemental Conditions, if any, or the Construction Agreement and the General Terms and Conditions, the conflict shall be resolved by imposing the more strict or costly obligation under the Contract Documents upon the Contractor at Owner's discretion. 8 Construction Services Agreement:[2024_ver.3] IN WITNESS WHEREOF, the parties have executed this Agreement on the date(s) indicated below, CONTRACTOR: TWO WITNESSES: Marquee Development, Inc. / -_ - Fr T�VJyITNESS/� ( (Ql'I! (_� IC By: Pript Name ''/ li " Print Name and Title SEG ND WIT S . Lon (r-ira 1 Date: 1 ll> Z-5 Print Name ATTEST: OWNER: Crystal K. Kinzel, Clerk of Courts BOARD OF COUNTY COMMISSIONERS &Comptroller OF COLLIER COUNTY FLORIDA k ..a, ;�-BY: 1)/ BY:� st 3B to Chairmat;+ /Se.f.,ero.,:erm4llwa- ° allChairman .,r,; ;�3`,-., signature only. Date: ;i _-' Ap oved as to For and egality: 4 „...a.A.....„ County Attorney S&of 2 T41.1._ Print Name s 4.4 Construction Services Agreement;[2024_ver.3] EXHIBIT A-1: CONTRACTOR'S BID SCHEDULE (FOLLOWING THIS PAGE) 10 Construction Services Agreement:[2024_ver.3] Immokalee Sidewalks Phase Ill Construction ITB 24-8233 BID SCHEDULE ITEM NO. DESCRIPTION UNIT QTY UNIT COST TOTAL COST ROADWAY 1 MOBILIZATION(Not to Exceed 10%of Total Old Amount) LS 1 $100,000.00 $100,000.00 2 PROVIDE CONSTRUCTION SURVEYING AND LAYOUT LS 1 $18,000.00 $18,000.00 3 MAINTENANCE OF TRAFFIC LS 1 $35,000.00 $35,000.00 4 COMMERCIAL MATERIAL FOR DRIVEWAY MAINTENANCE CY 320 $22.00 $7,040.00 5 PRECONSTRUCTION VIDEO OF PROJECT LIMITS LS 1 $1,000.00 $1,000.00 6 EROSION CONTROL LS 1 $45,000.00 $45,000.00 7 CLEARING AND GRUBBING(2.36 AC) LS 1 $45,000.00 $45,000.00 8 REMOVAL OF CONCRETE PAVEMENT SY 562 $25.00 $14,050.00 9 •MAILBOX(RELOCATE) EA 15 $350.00 $5,250.00 10 DITCH GRADING LS 1 $85,000.00 $85,000.00 11 CLASS I CONCRETE(DRIVEWAYS)(6"THICK) SY 885 $82.00 $72,570.00 12 MITERED END SECTION(15"RCP) EA 1 $850.00 $850.00, 13 INLETS(DITCH BOTTOM TYPE C)(<10') EA 6 $8,500.00 551,000.00 14 •INLETS(DITCH BOTTOM TYPE C)(3:1 MODIFY)(<10') EA 4 $8,500.00 $34,000.00 15 INLETS(DITCH BOTTOM TYPE C)(<10)-TOP ONLY EA 14 $3,500.00 $49,000.00 16 INLETS(DITCH BOTTOM TYPE D)(<10')-TOP ONLY . EA 15 $3,500.00 , $52,500.00 17 •MANHOLES(P-8)(<10') EA 2 $10,500,00 $21,000.00 18 PIPE CULVERT(CLASS III CONCRETE)(STORM SEWER)(ROUND SHAPE)(18") LF 341 $110.00 $37,510,00 19 CONCRETE PIPE COLLAR(18"PIPE) EA 1 $750.00 $750.00 20 CONCRETE SIDEWALK,6"THICK SY 2,850 $82.00 S233,700.00 21 DETECTABLE WARNING STRIPS(CAST INTO CONCRETE SIDEWALK) SF 527 $40.00 $21,080.00 22 PERFORMANCE TURF(BAHIA SOD)(INCLUDES WATER,FERTILIZER&MOWING) SY 5,634 $5.75 $32.395.50 23 CHAIN LINK FENCE(4'TALL) LF 186 $25.00 $4,700.00 24 DUAL-LEAF GATE(12'WIDE TOTAL)(4'TALL) EA 1 $500.00 $500.00 25 SINGLE POST SIGN AS 2 $650,00 $1,300.00 _ 26 SINGLE POST SIGN(RELOCATE/ADJUST) t EA 5 $250.00 $1,250.00 27 SINGLE POST SIGN(REMOVE) EA 2 $150.00 $300.00 28 RETRO-REFLECTIVE PAVEMENT MARKERS EA 54 $100,00 $5,400.00 29 8"RAISED CERAMIC PAVEMENT MARKERS EA 15 $100.00 $1,500.00 30 THERMOPLASTIC(STANDARD)(WHITE)(SOLID)(12") LF 1,107 $12.00 $13,284.00 31 THERMOPLASTIC(STANDARD)(WHITE)(SOLID)(24") LF 215 $18.00 $3,870.00 32 •THERMOPLASTIC(STANDARD)(YELLOW)(SOLID)(6") LF 887 $7.00 $6,209,00 33 THERMOPLASTIC(REMOVAL) SF 1,002 $8.00 $8,016.00 SUB-TOTAL: $1,008,024.50 �� DRAINAGE 36 6"PVC C-900 DR-18 WATERMAIN LF 93 $120.00 $11,160.00 37 REMOVE/DISPOSE 6"ASBESTOS WATERMAIN LF 93 $15.00 $1,395.00 38 RELOCATE FIRE HYDRANT ASSEMBLY EA 4 $3,000.00 $12,000.00 39 ADJUST WATERMAIN VALVE TO GRADE EA 23 $400.00 $9.200.00 40 ADJUST WATER SERVICE EA 2 $1,200.00 $2,400.00 41 CONNECT WATER SERVICE TO WATERMAIN EA 4 $1,600.00 $6,400,00 42 6"WATERMAIN DEFLECTION EA 2 _ $11,500.00 $23,000.00 43 ADJUST WATER METER EA 20 $500 00 $10,000.00 44 RELOCATE BACKFLOW PREVENTION EA 9 $900.00 $8,100.00, 45 ADJUST MANHOLE EA 1 $1,200.00 $1,200.00 46 ADJUST SANITARY LATERAL EA 2 $75000 $1,500.00 47 ADJUST CLEANOUT EA 2 $400.00 $800.00 48 RELOCATE BOLLARD EA 8 $750.00 $6,000.00 SUB-TOTAL: $93,155.00 TOTAL BID AMOUNT: $1,101,179.50 *Staff has allocated S85,000.00 in Owner's.Allowance-for Owners Use as Directed,This Allowance will be used omy et the Owner's direction to accomplish work due to unforeseen conditions andror by the Owner.Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor wilt be paid any portion or the full amount of the Allowance.Expenditures of Owners Allowance will be made through Charge Order with proper documentation of Time and Materials supporting the change ,/ 1 of 1 ,,,... EXHIBIT A-2: CONTRACTOR'S BID SUBMITTAL FORMS AND ADDENDUM (FOLLOWING THIS PAGE) 11 Construction Services Agreement:[2024_ver.3] FORM 1 -BID RESPONSE FORM BOARD OF COUNTY COMMISSIONERS COLLIER COUNTY,FLORIDA Immokatee Sidewalks Phase III / BID NO.24-8233 Full Name of Bidder I'1/ He Main Business Address 090 !/"L� r r �.• Place of Business -- . a apfiF�.'. — Telephone No. #1 /)/✓' i' / Fax Flo. / '6`"'3? z State Contractor's License# C T C- State of Florida Certificate of Authority Document Number 4#49a''04S11 Federal Tax Identification Number 59 .30 3 DUNS# t/ff 5' 7/79h CCR# Cage Code To: BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY,FLORIDA (hereinafter called the Owner) The undersigned,as Bidder declares that the only person or parties interested in this Bid as principals are those named herein, that this Bid is submitted without collusion with any other person, firm or corporation; that it has carefully examined the location of the proposed Work,the proposed form of Agreement and all other Contract Documents and Bonds,and the Contract Drawings and Specifications. Bidder proposes, and agrees if this Bid is accepted, Bidder will execute the Agreement included in the Bidding Documents, to provide all necessary machinery, tools, apparatus and other means of construction, including utility and transportation services necessary to do all the Work, and furnish all the materials and equipment specified or referred to in the Contract Documents in the manner and time herein prescribed and according to the requirements of the Owner as therein set forth, furnish the Contractor's Bonds and Insurance specified in the General Conditions of the Contract,and to do all other things required of the Contractor by the Contract Documents,and that it will take full payment the sums set forth in the following Bid Schedule: Unit prices shall be provided in no more than two decimal points,and in the case where further decimal points are inadvertently provided,rounding to two decimal points will be conducted by Procurement Services Division staff. Upon notification that its Bid has been awarded,the Successful Bidder will execute the Agreement form attached to the Bidding Documents within ten(10)calendar days and deliver the Surety Bond or Bonds and Insurance Certificates as required by the Contract Documents.The bid security attached is to become the property of the Owner in the event the Agreement,Insurance Certificates and Bonds are not executed and delivered to Owner within the time above set forth,as liquidated damages, for the delay and additional expense to the Owner, it being recognized that,since time is of the essence,Owner will suffer financial loss if the Successful Bidder fails to execute and deliver to Owner the required Agreement, Insurance Certificates and Bonds within the required time period. In the event of such failure, the total amount of Owner's damages,will be difficult, if not impossible,to definitely ascertain and quantify. It is hereby agreed that it is appropriate and fair that Owner receive liquidated damages from the Successful Bidder in the event it fails to execute and deliver the Agreement, Insurance Certificates, and Bonds as required hereunder. The Successful Bidder hereby expressly waives and relinquishes any right which it may have to seek to characterize the Construction Solicitation Doc rev 04152022 above noted liquidated damages as a penalty, which the parties agree represents a fair and reasonable estimate of Owner's actual damages at the time of bidding if the Successful Bidder fails to execute and deliver the Agreement, Insurance Certificates,and Bonds in a timely manner. Upon receipt of the signed and approved agreement and Purchase Order,the undersigned proposes to commence work at the site within five(5)calendar days from the commencement date stipulated in the written Notice to Proceed unless the Project Manager,in writing, subsequently notifies the Contractor of a modified(later)commencement date.The undersigned further agrees to substantially complete all work covered by this Bid within two hundred and ten(210) consecutive calendar days,computed by excluding the commencement date and including the last day of such period, and to be fully completed to the point of final acceptance by the Owner within thirty(30)consecutive calendar days after Substantial Completion,computed by excluding commencement date and including the last day of such period. Acceptance and acknowledged by an Authorize Agent Signature: Title: Date: 415 48Z.(71. Construction Solicitation Doc rev 04152022 FORM 2-CONTRACTOR'S KEY PERSONNEL ASSIGNED TO THE PROJECT Immokalee Sidewalks Phase HI Bid No.24-8233 Name Personnel Category fiQQr� ./J9 Construction Superintendent 4.+t cram Project Manager Construction Solicitation Doc rev 04152022 FORM 3-MATERIAL MANUFACTURERS THIS FORM MUST BE COMPLETED OR BID MAY BE DEEMED NON-RESPONSIVE All Bidders shall confirm by signature that they will provide the manufacturers and materials outlined in this Bid specifications,including compliance with Florida Statute 255.20 to provide lumber,timber and other forest products produced and manufactured in the State of Florida as long as the price,fitness and quality are equal. Exceptions(when equals are acceptable) may be requested by completing the Material Manufacturer Exception List below. If an exception for a manufacturer and/or material is proposed and listed below and is not approved by Engineer/Project Manager,Bidder shall furnish the manufacturer named in the specification.Acceptance of this form does not constitute acceptance of material proposed on this list. Complete and sign section A OR B. Section A(Acceptance of all manufactures and materials in Bid specifications) On behalf of my firm,I confirm that we will use all manufacturers and materials as specifically outlined in the Bid specifications. Company: ! Signature: Date: 1 .'` Section B(Exception requested to Bid specifications manufacturers and materials) EXCEPTION MATERIAL EXCEPTION MANUFACTURER 1. 2. 3. 4. 5. Please insert additional pages as necessary. Company: - Signature: Date Construction Solicitation Doc rev 04152022 FORM 4-LIST OF MAJOR SUBCONTRACTORS THIS FORM MUST BE COMPLETED OR BID MAY BE DEEMED NON-RESPONSIVE The undersigned states that the following is a list of the proposed subcontractors for the major categories outlined in the requirements of the Bid specifications. The undersigned acknowledges its responsibility for ensuring that the Subcontractors for the major categories listed herein arc"qualified"(as defined in Ordinance 2017-08 and Section 15 of Instructions to Bidders)and meet all legal requirements applicable to and necessitated by the Contract Documents,including,but not limited to proper licenses, certifications, registrations and insurance coverage. The Owner reserves the right to disqualify any Bidder who includes non-compliant or non-qualified Subcontractors in its bid offer.Further,the Owner may direct the Successful Bidder to remove/replace any Subcontractor,at no additional cost to Owner,which is found to be non-compliant with this requirement either before or after the issuance of the Award of Contract by Owner.(Attach additional sheets as needed). Further, the undersigned acknowledges and agrees that promptly after the Award of Contract, and in. accordance with the requirements of the Contract Documents,the Successful Bidder shall identify all.Subcontractors it intends to use on the Project. The undersigned further agrees that all Subcontractors subsequently identified for any portion of work on this Project must be qualified as noted above. Major Category of Work j� Subcontractor and Address 1. llaotri a1„ ` ✓' . c.-•iegef K fripcxterf 4 2. Mechanical A 4. Site Work 5. Identify other subcontractors that represent more than 10% of price or that affect the critical path of the schedule Company:19' fs� �• Signature: Date:_i_ d Construction Solicitation Doc rev 04152022 FORM 5-STATEMENT OF EXPERIENCE OF BIDDER TI3IS FORM MUST BE COMPLETED OR BID MAY BE DEEMED NON-RESPONSIVE/NON- RESPONSIBLE. The Bidder is required provide five(5)project references,stated below,of what work of similar magnitude completed within the last five (5) years is a judge of its experience, skill and business standing and of its ability to conduct the work as completely and as rapidly as required under the terms of the Agreement. y:_. relp4e 09 (project name)_ (project owner) 'CZ , 5 _ ",' (project location j (Owner's addr ss) 1 (project d cri non) Owner's contact person) (title) .wea7 I . ei_644414,314 (project sta /com letion dates) (contront .e� (ph nc3ne) email p ) ) (email)2. Not/k/ /'._.'/ .;_#4/07./0/15/ 1(04, ,C'. (project name) • it (project owner) Z ,//e•° _.„ -ix, ------."' ig."54Z (pro. - oca on) (Owner's address) ca A0071:1:e“ /I A. . _ , . . .4974,7....., (project descripti n) (0 r''contact person) (ti s if r, 1 4 ff, 6 F- .4(."7.6 ,./-0--... ,- „ (project start completion dates) (contr'ttcr value) (ph nc) (email) 7 )4 3. 44 (project name)_ it�'r'.t' (project owner) fn€�✓ / e I- offieR6WG:- 01 e (pr)'ect loc ion) .14/;Mil (Owner's address) CZ.F1,04 ..c _ (project escriptio. ma Orr is contact person) (t. ) ii. *:_,./..?_7_, _• . (project start/completion dates) (contract value) (pht(f (kc c) (ens Construction Solicitation Doc rev 04152022 FORM 5-STATEMENT OF EXPERIENCE OF BIDDER 4. ` bWá4ik' Jj # (project name) / (project ow? /�. 1507, 601/14 g„„g* t*Ig projçtrn1 (Ownersl ½4'''' ifi____K, /::__. # # ____14,4 (project description) (Owner's contact person) (title) 1 • ( . - ,a 5e. .( (project ompletion date) (c ntrac value) (phone) (email) s. • W _r ef. 4 z�_. (project name) (project owner fr44/1 gNbel ' 4#iS4 j. _ ! v—t a A . ___L, / • ' ~ ,ice (proje t des~ iption) (Owner's contact son) (title) "7-7-471 41 /E—W -4-051-44 .69—•-&4414117//64 (p ojec completion date) (contract value) ( honef (email) NV y.Company: Me,/ .. Signature: ' Date:--- '' . Construction Solicitation Doc rev 04152022 FORM 6-TRENCH SAFETY ACT THIS FORM MUST BE COMPLETED OR BID MAY BE DEEMED NON-RESPONSIVE. Bidder acknowledges that included in the various items of the bid and in the Total Bid Price are costs for complying with the Florida Trench Safety Act(90-96,Laws of Florida)effective October 1, 1990.The Bidder further identifies the cost to be summarized below: Trench Safety Units of Unit Unit Extended Cost Measure Measure (Quantity) Cost (Description) (LF,SY) r. CA YI LF Z50 /75ff#. ' 2. 3. 4. s. • TOTAL $ .75' 67#7 Company: 0 1:2 '''ram ne. C ' Signature: Date: f rr Construction Solicitation Doc rev 04152022 Bond Number:N/A FORM 7-BID BOND THIS FORM MUST BE COMPLETED OR BID MAY BE DEEMED NON-RESPONSIVE/NON_ RESPONISBLE KNOW ALL MEN BY THESE PRESENTS, that we Marquee Development,Inc. (herein after called the Principal) and Nationwide Mutual Insurance Company , (herein called the Surety), a corporation chartered and existing under the laws of the State of OH with its principal offices in the city of Des Moines,IA and authorized to do business in the State of Florida are held and firmly bound unto the Collier County Board of CountyCommissioners (hereinafter called the Owner),in the full and just sum of Five Percent of Total Amount Bid in U.S. dollars $5�ti ( ----)good and lawful money of the United States of America,to be paid upon demand of the Owner,to which payment well and truly to be made,the Principal and the Surety bind themselves,their heirs,and executors,administrators,and assigns,jointly and severally and firmly by these presents. Whereas, the Principal is about to submit, or has submitted to the Owner, a Bid for furnishing all labor, materials, equipment and incidentals necessary to furnish,install,and fully complete the Work on the Project known as Bid No, 24-8233. NOW,THEREFORE, if the Owner shall accept the Bid of the PRINCIPAL and the PRINCIPAL shall enter into the required Agreement with the Owner and within ten days after the date of a written Notice of Award in accordance with the terms of such Bid,and give such bond or bonds in an amount of 100%the total Contract Amount as specified in the Bidding Documents or Contract Documents with good and sufficient surety for the faithful performance of the Agreement and for the prompt payment of labor,materials and supplies furnished in the prosecution thereof or, in the event of the failure of the PRINCIPAL to enter into such Agreement or to give such bond or bonds,and deliver to Owner the required certificates of insurance,if the PRINCIPAL shall pay to the OBLIGEE the fixed sum of$5% noted above as liquidated damages,and not as a penalty,as provided in the Bidding Documents,then this obligation shall be null and void,otherwise to remain in full force and effect. IN TESTIMONY Thereof, the Principal and Surety have caused these presents to be duly signed and sealed this 3rd day of September ,20 24 . Marquee Development,Inc. Principal • CORPORATE SEAL 1994 BY FLORIDA (Seal) Nationwide Mutual Insurance Company +►W% 4/P.0uir. Surety AS ' i* SEAL:,0' BYt'—') ` .; (Seal) David B.Shick,Attorney-In-Fact& 4 44 roll i +�' Licensed FL Resident Agent#A241176 Countersigned N/A Appointed Producing Agent for N/A 3 Power of Attorney 00000 944 KNOW ALL MEN BY THESE PRESENTS THAT: Nationwide Mutual Insurance Company,an Ohio corporation hereinafter referred to severally as the"Company"and collectively as"the Companies"does hereby make,constitute and appoint: DAVID BRYAN SH1CK; each in their individual capacity,its true and lawful attorney-in-fact,with full power and authority to sign,seal,and execute on its behalf any and all bonds and undertakings,and other obligatory instruments of similar nature,in penalties not exceeding the sum of FOUR MILLION AND NO/100 DOLLARS ($4,000,000.00) and to bind the Company thereby,as fully and to the same extent as if such instruments were signed by the duly authorized officers of the Company;and all acts of said Attorney pursuant to the authority given are hereby ratified and confirmed. This power of attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the board of directors of the Company: "RESOLVED,that the president,or any vice president be,and each hereby is,authorized and empowered to appoint attorneys-in-fact of the Company, and to authorize them to execute and deliver on behalf of the Company any and all bonds,forms,applications,memorandums,undertakings, recognizances,transfers,contracts of indemnity,policies,contracts guaranteeing the fidelity of persons holding positions of public or private trust,and other writings obligatory in nature that the business of the Company may require;and to modify or revoke,with or without cause,any such appointment or authority;provided,however,that the authority granted hereby shall in no way limit the authority of other duly authorized agents to sign and countersign any of said documents on behalf of the Company." "RESOLVED FURTHER,that such attorneys-in-fact shall have full power and authority to execute and deliver any and all such documents and to bind the Company subject to the terms and limitations of the power of attorney issued to them,and to affix the seal of the Company thereto;provided,however,that said seal shalt not be necessary for the validity of any such documents." This power of attorney is signed and sealed under and by the following bylaws duly adopted by the board of directors of the Company. Execution of Instruments.Any vice president,any assistant secretary or any assistant treasurer shall have the power and authority to sign or attest all approved documents,instruments,contracts,or other papers in connection with the operation of the business of the company in addition to the chairman of the board,the chief executive officer,president,treasurer or secretary;provided,however,the signature of any of them may be printed,engraved,or stamped on any approved document,contract,instrument,or other papers of the Company. IN WITNESS WHEREOF,the Company has caused this instrument to be sealed and duly attested by the signature of its officer the 20th day of August,2021. Antonio C.Albanese,Vice President of Nationwide Mutual Insurance Company ACKNOWLEDGMENT I�111* uuiwr ® STATE OF NEW YORK COUNTY OF NEW YORK:as A'a '' F On this 20th day of August,2021,before me came the above-named officer for the Company aforesaid,to me personally known to be the officer described in and who executed the preceding instrument,and he acknowledged the execution of the same,and being by me duly 04='` sworn,deposes and says,that he is the officer of the Company aforesaid,that the seal affixed ®�orifie ;�,i hereto is the corporate seal of said Company,and the said corporate seal and his signature were ��► duly affixed and subscribed to said instrument by the authority and direction of said Company. Stephanie Rubfno McArthur ittc4e4A,aaCkeaw~ Notary Futile,Stato of Now York No.02MCO270117 Ouai;feo 40 New York County rsmary autn'ic Commission Expires Ooiober 19,2024 ray Cammiaaion Expires CERTIFICATE October 19.2024 I,Laura B.Guy,Assistant Secretary of the Company,do hereby certify that the foregoing is a full,true and correct copy of the original power of attorney issued by the Company;that the resolution included therein is a true and correct transcript from the minutes of the meetings of the boards of directors and the same has not been revoked or amended in any manner;that said Antonio C.Albanese was on the date of the execution of the foregoing power of attorney the duly elected officer of the Company,and the corporate seal and his signature as officer were duly affixed and subscribed to the said instrument by the authority of said board of directors;and the foregoing power of attorney is still in full force and effect. IN WITNESS WHEREOF,t have hereunto subscribed my name as Assistant Secretary,and affixed the corporate seal of said Company this 3 day of September 2024 Walt a44.0.. 3 �/�p,11SUh114Syq��iy Assistant Secretary BDJ 1(08-21)00 irk; FORM 8-INSURANCE AND BONDING REQUIREMENTS The Vendor shall at its own expense, carry and maintain insurance coverage from responsible companies duly authorized to do business in the State of Florida as set forth in FORM 8 of this solicitation. The Vendor shall procure and maintain property insurance upon the entire project,if required,to the full insurable value of the scope of work. The County and the Vendor waive against each other and the County's separate Vendors, Contractors, Design Consultant,Subcontractors,agents and employees of each and all of them,all damages covered by property insurance provided herein,except such rights as they may have to the proceeds of such insurance. The Vendor and County shall, where appropriate,require similar waivers of subrogation from the County's separate Vendors, Design Consultants and Subcontractors and shall require each of them to include similar waivers in their contracts. Collier County shall be responsible for purchasing and maintaining its own liability insurance. Certificates issued as a result of the award of this solicitation must identify"For any and all work performed on behalf of Collier County",or,the specific solicitation number and title. The General Liability Policy provided by Vendor to meet the requirements of this solicitation shall name Collier County, Florida, as an additional insured as to the operations of Vendor under this solicitation and shall contain a severability of interests provisions. The Certificate Holder shall be named as Collier County Board of County Commissioners, OR, Board of County Commissioners in Collier County,OR Collier County Government,OR Collier County.The Certificates of Insurance must state the Contract Number, or Project Number, or specific Project description,or must read: For any and all work performed on behalf of Collier County. The amounts and types of'insurance coverage shall conform to the minimum requirements set forth in FORM 8 with the use of Insurance Services Office (ISO) forms and endorsements or their equivalents. If Vendor has any self- insured retentions or deductibles under any of the below listed minimum required coverage,Vendor must identify on the Certificate of Insurance the nature and amount of such self-insured retentions or deductibles and provide satisfactory evidence of financial responsibility for such obligations. All self-insured retentions or deductibles will be Vendor's sole responsibility. Coverage(a)shall be maintained without interruption from the date of commencement of the Work until the date of completion and acceptance of the scope of work by the County or as specified in this solicitation,whichever is longer. The Vendor and/or its insurance carrier shall provide thirty (30) days written notice to the County of policy cancellation or non-renewal on the part of the insurance carrier or the Vendor. The Vendor shall also notify the County,in a like manner,within twenty-four(24)hours after receipt,of any notices of expiration,cancellation,non- renewal or material change in coverage or limits received by Vendor from its insurer and nothing contained herein shall relieve Vendor of this requirement to provide notice. In the event of a reduction in the aggregate limit of any policy to be provided by Vendor hereunder,Vendor shall immediately take steps to have the aggregate limit reinstated to the full extent permitted under such policy. Should at any time the Vendor not maintain the insurance coverage( required herein,the County may terminate the Agreement or at its sole discretion shall be authorized to purchase such coverageal and charge the Vendor for such coverageW purchased. If Vendor fails to reimburse the County for such costs within thirty(30) days after demand, the County has the right to offset these costs from any amount due Vendor under this Agreement or any other agreement between the County and Vendor.The County shall be under no obligation to purchase such insurance,nor shall it be responsible for the coverage(s)purchased or the insurance company or companies used. The decision of the County to purchase such insurance coverage()shall in no way be construed to be a waiver of any of its rights under the Contract Documents. If the initial or any subsequently issued Certificate of Insurance expires prior to the completion of the scope of work, the Vendor shall furnish to the County renewal or replacement Certificate(s) of Insurance not later than ten (10) calendar days after the expiration date on the certificate. Failure of the Vendor to provide the County with such renewal certificate(s)shall be considered justification for the County to terminate any and all contracts. Collier County Florida Insurance and Bonding Requirements Insurance/Bond Type Required Limits 1. Worker's Compensation Statutory Limits of Florida Statutes, Chapter 440 and all Federal Government Statutory Limits and Requirements Evidence of Workers'Compensation coverage or a Certificate of Exemption issued by the State of Florida is required. Entities that are formed as Sole Proprietorships shall not be required to provide a proof of exemption.An application for exemption can be obtained online at 1ittns://apps.tld fs.comibocexempS. 2. ®Employer's Liability $_1,000,000_single limit per occurrence 3. Al Commercial General Bodily Injury and Property Damage Liability(Occurrence Form)patterned after the $ 1,000,000 single limit per occurrence, $2,000,000 aggregate for Bodily current ISO form Injury Liability and Property Damage Liability. The General Aggregate Limit Shall be endorsed to apply per project. This shall include Premises and Operations; Independent Contractors; Products and Completed Operations and Contractual Liability. 4. /!t Indemnification To the maximum extent permitted by Florida law, the Contractor/Vendor shall defend,indemnify and hold harmless Collier County,its officers and employees from any and all liabilities, damages, losses and costs, including, but not limited to, reasonable attorneys'fees and paralegals'fees,to the extent caused by the negligence, recklessness,or intentionally wrongful conduct of the Contractor/Vendor or anyone employed or utilized by the Contractor/Vendor in the performance of this Agreement. 5. ®Automobile Liability $_1,000,000 Each Occurrence; Bodily Injury & Property Damage, Owned/Non-owned/Hired;Automobile Included 6. ❑ Other insurance as ❑Watercraft $ Per Occurrence noted: ❑ United States Longshoreman's and Harborworker's Act coverage shall be maintained where applicable to the completion of the work. $ Per Occurrence ❑ Maritime Coverage (Jones Act) shall be maintained where applicable to the completion of the work. $ Per Occurrence ❑ Aircraft Liability coverage shall be carried in limits of not less than$5,000,000 each occurrence if applicable to the completion of the Services under this Agreement. $ Per Occurrence ❑Pollution $ Per Occurrence ❑Professional Liability $ Per claim&in the aggregate ❑Project Professional Liability $ Per Occurrence ❑Valuable Papers Insurance $ Per Occurrence ❑Cyber Liability $ Per Occurrence 0 Technology Errors&Omissions $ Per Occurrence 7. El Bid bond Shall be submitted with proposal response in the form of certified funds, cashiers' check or an irrevocable letter of credit,a cash bond posted with the County Clerk,or proposal bond in a sum equal to 5%of the cost proposal.All checks shall be made payable to the Collier County Board of County Commissioners on a bank or trust company located in the State of Florida and insured by the Federal Deposit Insurance Corporation. 8. ®Performance and For projects in excess of$200,000, bonds shall be submitted with the executed Payment Bonds contract by Proposers receiving award, and written for 100%of the Contract award amount, the cost borne by the Proposer receiving an award. The Performance and Payment Bonds shall be underwritten by a surety authorized to do business in the State of Florida and otherwise acceptable to Owner; provided, however, the surety shall be rated as "A-" or better as to general policy holders rating and Class V or higher rating as to financial size category and the amount required shall not exceed 5%of the reported policy holders' surplus, all as reported in the most current Best Key Rating Guide,published by A.M.Best Company, Inc. of 75 Fulton Street,New York,New York 10038. 9. ® Vendor shall ensure that all subcontractors comply with the same insurance requirements that he is required to meet. The same Vendor shall provide County with certificates of insurance meeting the required insurance provisions. 10. Collier County must be named as"ADDITIONAL INSURED"on the Insurance Certificate for Commercial General Liability where required.This insurance shall be primary and non-contributory with respect to any other insurance maintained by,or available for the benefit of,the Additional insured and the Vendor's policy shall be endorsed accordingly. 11. ►I1 The Certificate Holder shall be named as Collier County Board of County Commissioners, OR, Board of County Commissioners in Collier County,OR Collier County Government,OR Collier County. The Certificates of Insurance must state the Contract Number,or Project Number,or specific Project description,or must read: For any and all work performed on behalf of Collier County. 12. ® On all certificates, the Certificate Holder must read: Collier County Board of Commissioners, 3295 Tamiami Trail East,Naples,FL 34112 13. ® Thirty(30)Days Cancellation Notice required. 14. Collier County shall procure and maintain Builders Risk Insurance on all construction projects where it is deemed necessary. Such coverage shall be endorsed to cover the interests of Collier County as well as the Contractor. Premiums shall be billed to the project and the Contractor shall not include Builders Risk premiums in its project proposal or project billings. All questions regarding Builder's Risk Insurance will be addressed by the Collier County Risk Management Division. GG— 1/19/2024 Vendor's Insurance Acceptance By submission of the bid Vendor accepts and understands the insurance requirements of these specifications,agrees to maintain these coverages through the duration of the agreement and/or work performance period,and that the evidence of insurability may be required within five(5)days of notification of recommended award of this solicitation. Co Ter County Procurement Services Division FORM 9—CONFLICT OF INTEREST AFFIDAVIT The Vendor certifies that, to the best of its knowledge and belief, the past and current work on any Collier County project affiliated with this solicitation does not pose an organizational conflict as described by one of the three categories below: Biased ground rules—The firm has not set the"ground rules"for affiliated past or current Collier County project identified above (e.g., writing a procurement's statement of work, specifications, or performing systems engineering and technical direction for the procurement)which appears to skew the competition in favor of my firm. Impaired objectivity—The firm has not performed work on an affiliated past or current Collier County project identified above to evaluate proposals/past performance of itself or a competitor,which calls into question the contractor's ability to render impartial advice to the government. Unequal access to information —The firm has not had access to nonpublic information as part of its performance of a Collier County project identified above which may have provided the contractor(or an affiliate)with an unfair competitive advantage in current or future solicitations and contracts. In addition to this signed affidavit,the contractor/vendor must provide the following: I. All documents produced as a result of the work completed in the past or currently being worked on for the above- mentioned project;and, 2. Indicate if the information produced was obtained as a matter of public record(in the"sunshine")or through non- public(not in the"sunshine")conversation(s),meeting(s),document(s)and/or other means. Failure to disclose all material or having an organizational conflict in one or more of the three categories above be identified,may result in the disqualification for future solicitations affiliated with the above referenced project(s). By the signature below,the firm(employees, officers and/or agents)certifies, and hereby discloses,that, to the best of their knowledge and belief, all relevant facts concerning past, present, or currently planned interest or activity (financial, contractual, organizational, or otherwise) which relates to the project identified above has been fully disclosed and does not pose an organizational conflict. dei 4'Ai ', `ompany ame gnaqure f/- j�,f CiG Print Name and Title State of J ff County of rif( j'Okpfl The for going instru ent was acknowledge before me by means 9,t?I physical presence or 0 online notarization, this day pf {month), fir! `� _(year),by � +�+�. t_l +%5 (name of person acknowledging). -) ( ' atu e of otary Public-State of Florida) [4 c i , G o,?&' 1 (fl c:i - (Print,Type,or Stamp Commissione Name.cfl Nmary Public) Personally /.w n �O�R Produced Identification f l t 0 —?q C,f Type of Identification Produced / rt— / Zaddielys M. o ice.13Urfaics z`1 , ,`'' Notary public 6 _ State of Flortdu 4 Comm#HH478817 4<.r. wa , Expires 11i1120 C.O ier Co"N 2Cv Prom rrement&owes L%wsr FORM 10—VENDOR DECLARATION STATEMENT BOARD OF COUNTY COMMISSIONERS Collier County Government Complex Naples,Florida 34112 Dear Commissioners: The undersigned, as Vendor declares that this response is made without connection or arrangement with any other person and this proposal is in every respect fair and made in good faith,without collusion or fraud. The Vendor hereby declares the instructions,purchase order terms and conditions,requirements,and specifications/scope of work of this solicitation have been fully examined and accepted. The Vendor agrees,if this solicitation submittal is accepted,to execute a Collier County document for the purpose of establishing a formal contractual relationship between the firm and Collier County, for the performance of all requirements to which the solicitation pertains. The Vendor states that the submitted is based upon the documents listed by the above referenced Solicitation. Further,the vendor agrees that if awarded a contract for these goods and/or services,the vendor will not be eligible to compete,submit a proposal,be awarded,or perform as a sub- vendor for any future associated with work that is a result of this awarded contract. IN WITNESS W,11 +R OF,WE ave hereunto subset' ed our names on this J day of. ✓ Agin the County of tjF/'/Jlft,;, ,in the State of�. Firm's Legal N e - P€l f ,, 17 , Name: G !ji - / / / Address: L/ Ji - City,State,Zip i // "FL �5 Code: � Florida Certificate of POpaffrK,670Authority Document Number y ® Federal Tax Identification Number *CCR#or CAGE Code *Only if Grant Funded (9J) Telephone: 795-� /9Email: /77 addC2/i Signature M& a"' (Typed and written) PregidelTitle: g Additional Contact to •rmation Send payments to: / (required if different Compai name used as payee •/ from above) Contact name: Title: fr:40 Address: 7 / Xte City,State,ZIP �►� //� 'y� . �. Telephone: Jl 790-0f9 Email: /1/GtJ leae� r 0/4'. /t Office servicing Collier County to place orders (required if different from above) Contact name: Title: Address: City,State,ZIP Telephone: Email: Secondary Contact for this Solicitation: Email: Phone: Co ler County Procurement Services Division FORM 11-IMMIGRATION AFFIDAVIT CERTIFICATION This Affidavit is required and should be signed,notarized by an authorized principal of the firm and submitted with formal solicitation submittals. Further, Vendors are required to be enrolled in the E-Verify program, and provide acceptable evidence of their enrollment, at the time of the submission of the Vendor's bid. Acceptable evidence consists of a copy of the properly completed E-Verify Company Profile page or a copy of the fully executed E-Verify Memorandum of Understanding for the company which will be produced at the time of the submission of the Vendor's bid or within five(5)day of the County's Notice of Recommend Award. FAILURE TO EXECUTE THIS AFFIDAVIT CERTIFICATION AND SUBMIT WITH VENDOR'S PROPOSAL/BID MAY DEEM THE VENDOR NON-RESPONSIVE. Collier County will not intentionally award County contracts to any Vendor who knowingly employs unauthorized alien workers,constituting a violation of the employment provision contained in 8 U.S.C. Section 1324 a(e) Section 274A(e)of the Immigration and Nationality Act("INA"). Collier County may consider the employment by any Vendor of unauthorized aliens a violation of Section 274A(e) of the INA. Such Violation by the recipient of the Employment Provisions contained in Section 274A(e)of the INA shall be grounds for unilateral termination of the contract by Collier County. Vendor attests that they are fully compliant with all applicable immigration laws(specifically to the 1986 Immigration Act and subsequent Amendment(s)) that it is aware of and in compliance with the requirements set forth in Florida Statutes§448.095,and agrees to comply with the provisions of the Memorandum of Understanding with E-Verify and to provide proof of enrollment in The Employment Eligibility Verification System (E-Verify), operated by the Department of Homeland Security in partnership with the Social Security Administration at the time of submission of the Vendor's proposal/bid. f 2/4 f eei elf // y, ,,/9 Company Name Sip attire car/ : Cary rState of F/0 i 49rint Name and Title County of H1(if J'Uri)l 'i The foregoing instru ent was acknowledged,beire me by means C $ysical prese,�or 0 online notarization, this j' day of v '(month),L04 `I (year),by L /jt-f.l' c>z ,' (name of person acknowledging). b(*. attire of Notary Publicr.State of Florida) (Print,Type,qt S amp Commissioned Name of Nn ry Public) Personally Known OR Produced Identification YPe f Identification Produced "' Notary Public State• of Florida 0 * tamm#HH47•t17 +' '' Expires 1/9/2028 • u k111— eri Company ID Number: 487970 THE E-VERIFY PROGRAM FOR EMPLOYMENT VERIFICATION MEMORANDUM OF UNDERSTANDING ARTICLE I PURPOSE AND AUTHORITY This Memorandum of Understanding (MOU) sets forth the points of agreement between the Department of Homeland Security (DHS) and Marquee Devcloument,1nc. (Employer) regarding the Employer's participation in the Employment Eligibility Verification Program (E-Verify). This MOU explains certain features of the E-Verify program and enumerates specific responsibilities of DHS, the Social Security Administration (SSA), and the Employer. E-Verify is a program that electronically confirms an employee's eligibility to work in the United States after completion of the Employment Eligibility Verification Form (Form 1-9). For covered government contractors, E- Verify is used to verify the employment eligibility of all newly hired employees and all existing employees assigned to Federal contracts or to verify the entire workforce if the contractor so chooses. Authority for the E-Verify program is found in Title IV, Subtitle A, of the Illegal Immigration Reform and Immigrant Responsibility Act of 1996 (IIRIRA), Pub. L. 104-208, 110 Stat. 3009, as amended (8 U.S.C. § 1324a note). Authority for use of the E-Verify program by Federal contractors and subcontractors covered by the terms of Subpart 22.18, "Employment Eligibility Verification", of the Federal Acquisition Regulation (FAR) (hereinafter referred to in this MOU as a "Federal contractor with the FAR E-Verify clause") to verify the employment eligibility of certain employees working on Federal contracts is also found in Subpart 22.18 and in Executive Order 12989, as amended. ARTICLE II FUNCTIONS TO BE PERFORMED A. RESPONSIBILITIES OF SSA 1. SSA agrees to provide the Employer with available information that allows the Employer to confirm the accuracy of Social Security Numbers provided by all employees verified under this MOU and the employment authorization of U.S. citizens. 2. SSA agrees to provide to the Employer appropriate assistance with operational problems that may arise during the Employer's participation in the E-Verify program. SSA agrees to provide the Employer with names, titles, addresses, and telephone numbers of SSA representatives to be contacted during the E-Verify process. 3. SSA agrees to safeguard the information provided by the Employer through the E-Verify program procedures, and to limit access to such information, as is appropriate by law, to individuals responsible for the verification of Social Security Numbers and for evaluation of the E-Verify program or such other persons or entities who may be authorized by SSA as governed Page 1 of 13 I E-Verify MOU for Employer I Revision Date 09r01109 www.dhs.gov/E-Verify Company ID Number: 487970 by the Privacy Act (5 U.S.C. § 552a), the Social Security Act (42 U.S.C. 1306(a)), and SSA regulations (20 CFR Part 401). 4. SSA agrees to provide a means of automated verification that is designed (in conjunction with DHS's automated system if necessary) to provide confirmation or tentative nonconfirmation of U.S. citizens'employment eligibility within 3 Federal Government work days of the initial inquiry. 5. SSA agrees to provide a means of secondary verification (including updating SSA records as may be necessary) for employees who contest SSA tentative nonconfirmations that is designed to provide final confirmation or nonconfirmation of U.S. citizens' employment eligibility and accuracy of SSA records for both citizens and non-citizens within 10 Federal Government work days of the date of referral to SSA, unless SSA determines that more than 10 days may be necessary. In such cases, SSA will provide additional verification instructions. B.RESPONSIBILITIES OF DHS 1. After SSA verifies the accuracy of SSA records for employees through E-Verify, DHS agrees to provide the Employer access to selected data from DHS's database to enable the Employer to conduct, to the extent authorized by this MOU: •Automated verification checks on employees by electronic means, and • Photo verification checks(when available)on employees. 2. DHS agrees to provide to the Employer appropriate assistance with operational problems that may arise during the Employer's participation in the E-Verify program. DHS agrees to provide the Employer names, titles, addresses, and telephone numbers of DHS representatives to be contacted during the E-Verify process. 3. DHS agrees to make available to the Employer at the E-Verify Web site and on the E-Verify Web browser, instructional materials on E-Verify policies, procedures and requirements for both SSA and DHS, including restrictions on the use of E-Verify. DHS agrees to provide training materials on E-Verify. 4. DHS agrees to provide to the Employer a notice,which indicates the Employer's participation in the E-Verify program. OHS also agrees to provide to the Employer anti-discrimination notices issued by the Office of Special Counsel for Immigration-Related Unfair Employment Practices (OSC), Civil Rights Division, U.S. Department of Justice. 5. OHS agrees to issue the Employer a user identification number and password that permits the Employer to verify information provided by employees with DHS's database. 6. DHS agrees to safeguard the information provided to DHS by the Employer, and to limit access to such information to individuals responsible for the verification of employees' employment eligibility and for evaluation of the E-Verify program, or to such other persons or entities as may be authorized by applicable law. Information will be used only to verify the accuracy of Social Security Numbers and employment eligibility, to enforce the Immigration and Page 2 of 13 I E-Verify MOU for Employer I Revision Date 09/01/09 www.dhs.g°WWE-Verify mirky Company ID Number: 487970 Nationality Act (INA) and Federal criminal laws, and to administer Federal contracting requirements. 7. DHS agrees to provide a means of automated verification that is designed (in conjunction with SSA verification procedures) to provide confirmation or tentative nonconfirmation of employees' employment eligibility within 3 Federal Government work days of the initial inquiry. 8. DHS agrees to provide a means of secondary verification (including updating OHS records as may be necessary) for employees who contest DHS tentative nonconfirmations and photo non- match tentative nonconfirmations that is designed to provide final confirmation or nonconfirmation of the employees' employment eligibility within 10 Federal Government work days of the date of referral to DHS, unless DHS determines that more than 10 days may be necessary. in such cases, DHS will provide additional verification instructions. C. RESPONSIBILITIES OF THE EMPLOYER 1. The Employer agrees to display the notices supplied by DHS in a prominent place that is clearly visible to prospective employees and all employees who are to be verified through the system. 2. The Employer agrees to provide to the SSA and OHS the names, titles, addresses, and telephone numbers of the Employer representatives to be contacted regarding E-Verify. 3. The Employer agrees to become familiar with and comply with the most recent version of the E-Verify User Manual. 4. The Employer agrees that any Employer Representative who will perform employment verification queries will complete the E-Verify Tutorial before that individual initiates any queries. A. The Employer agrees that all Employer representatives will take the refresher tutorials initiated by the E-Verify program as a condition of continued use of E-Verify. B. Failure to complete a refresher tutorial will prevent the Employer from continued use of the program. 5. The Employer agrees to comply with current Form 1-9 procedures,with two exceptions: o If an employee presents a"List B" identity document, the Employer agrees to only accept"List B"documents that contain a photo. (List B documents identified in 8 C.F.R. §274a.2(b)(1)(B)) can be presented during the Form 1-9 process to establish identity.) If an employee objects to the photo requirement for religious reasons, the Employer should contact E-Verify at 888-464-4218. • If an employee presents a OHS Form 1-551 (Permanent Resident Card) or Form 1-766 (Employment Authorization Document)to complete the Form 1-9,the Employer agrees to make a photocopy of the document and to retain the photocopy with the employee's Form 1-9. The photocopy must be of sufficient quality to allow for verification of the photo Page 3 of 13 I E-Verify MOU for Employer I Revision Date 09/01/09 www.dhs.gov/E-Verify ,v, .... ...[ ..,....c. , r. ,,A-Ve .111y ari ,„j Company ID Number:487970 and written information. The employer will use the photocopy to verify the photo and to assist DHS with its review of photo non-matches that are contested by employees. Note that employees retain the right to present any List A, or List B and List C, documentation to complete the Form 1-9. OHS may in the future designate other documents that activate the photo screening tool. 6. The Employer understands that participation in E-Verify does not exempt the Employer from the responsibility to complete, retain, and make available for inspection Forms 1-9 that relate to its employees, or from other requirements of applicable regulations or laws, including the obligation to comply with the antidiscrimination requirements of section 274E of the INA with respect to Form 1-9 procedures, except for the following modified requirements applicable by reason of the Employer's participation in E-Verify: (1) identity documents must have photos, as described in paragraph 5 above; (2) a rebuttable presumption is established that the Employer has not violated section 274A(a)(1)(A) of the Immigration and Nationality Act(INA) with respect to the hiring of any individual if it obtains confirmation of the identity and employment eligibility of the individual in good faith compliance with the terms and conditions of E-Verify; (3) the Employer must notify OHS if it continues to employ any employee after receiving a final nonconfirmation, and is subject to a civil money penalty between $550 and $1,100 for each failure to notify OHS of continued employment following a final nonconfirmation; (4) the Employer is subject to a rebuttable presumption that it has knowingly employed an unauthorized alien in violation of section 274A(a)(1)(A) if the Employer continues to employ an employee after receiving a final nonconfirmation; and (5) no person or entity participating in E-Verify is civilly or criminally liable under any law for any action taken in good faith based on information provided through the confirmation system. DHS reserves the right to conduct Form 1-9 and E-Verify system compliance inspections during the course of E-Verify, as well as to conduct any other enforcement activity authorized by law. 7. The Employer agrees to initiate E-Verify verification procedures for new employees within 3 Employer business days after each employee has been hired (but after the Form 1-9 has been completed), and to complete as many (but only as many) steps of the E-Verify process as are necessary according to the E-Verify User Manual, or in the case of Federal contractors with the FAR E-Verify clause, the E-Verify User Manual for Federal Contractors. The Employer is prohibited from initiating verification procedures before the employee has been hired and the Form 1-9 completed. If the automated system to be queried is temporarily unavailable, the 3-day time period is extended until it is again operational in order to accommodate the Employer's attempting, in good faith, to make inquiries during the period of unavailability. Employers may initiate verification by notating the Form 1-9 in circumstances where the employee has applied for a Social Security Number (SSN) from the SSA and is waiting to receive the SSN, provided that the Employer performs an E-Verify employment verification query using the employee's SSN as soon as the SSN becomes available. 8. The Employer agrees not to use E-Verify procedures for pre-employment screening of job applicants, in support of any unlawful employment practice, or for any other use not authorized by this MOU. Employers must use E-Verify for all new employees, unless an Employer is a Federal contractor that qualifies for the exceptions described in Article 11.0.1.c. Except as provided in Article II.D, the Employer will not verify selectively and will not verify employees hired before the effective date of this MOU. The Employer understands that if the Employer Page 4 of 13 1 E-Verify MOU for Employer I Revision Date 09f01/08 www.dhs.gov/E-Verify Zrtli /I tif4 Company ID Number: 487970 uses the E-Verify system for any purpose other than as authorized by this MOU, the Employer may be subject to appropriate legal action and termination of its access to SSA and OHS information pursuant to this MOU. 9. The Employer agrees to follow appropriate procedures (see Article Ill, below) regarding tentative nonconfirmations, including notifying employees in private of the finding and providing them written notice of the findings, providing written referral instructions to employees, allowing employees to contest the finding, and not taking adverse action against employees if they choose to contest the finding. Further, when employees contest a tentative nonconfirmation based upon a photo non-match, the Employer is required to take affirmative steps (see Article 111.B. below)to contact OHS with information necessary to resolve the challenge. 10. The Employer agrees not to take any adverse action against an employee based upon the employee's perceived employment eligibility status while SSA or DHS is processing the verification request unless the Employer obtains knowledge (as defined in 8 C.F.R. § 274a.1(1)) that the employee is not work authorized. The Employer understands that an initial inability of the SSA or OHS automated verification system to verify work authorization, a tentative nonconfirmation, a case in continuance (indicating the need for additional time for the government to resolve a case), or the finding of a photo non-match, does not establish, and should not be interpreted as evidence, that the employee is not work authorized. in any of the cases listed above, the employee must be provided a full and fair opportunity to contest the finding, and if he or she does so, the employee may not be terminated or suffer any adverse employment consequences based upon the employee's perceived employment eligibility status (including denying, reducing, or extending work hours, delaying or preventing training, requiring an employee to work in poorer conditions, refusing to assign the employee to a Federal contract or other assignment, or otherwise subjecting an employee to any assumption that he or she is unauthorized to work) until and unless secondary verification by SSA or OHS has been completed and a final nonconfirmation has been issued. If the employee does not choose to contest a tentative nonconfirmation or a photo non-match or if a secondary verification is completed and a final nonconfirmation is issued, then the Employer can find the employee is not work authorized and terminate the employee's employment. Employers or employees with questions about a final nonconfirmation may call E-Verify at 1-888-464-4218 or OSC at 1-800- 255-8155 or 1-800-237-2515 (TDD). 11. The Employer agrees to comply with Title VII of the Civil Rights Act of 1964 and section 274B of the INA, as applicable, by not discriminating unlawfully against any individual in hiring, firing, or recruitment or referral practices because of his or her national origin or, in the case of a protected individual as defined in section 274B(a)(3) of the INA, because of his or her citizenship status. The Employer understands that such illegal practices can include selective verification or use of E-Verify except as provided in part D below, or discharging or refusing to hire employees because they appear or sound "foreign" or have received tentative nonconfirmations. The Employer further understands that any violation of the unfair immigration- related employment practices provisions in section 274E of the INA could subject the Employer to civil penalties, back pay awards, and other sanctions, and violations of Title ViI could subject the Employer to back pay awards, compensatory and punitive damages. Violations of either section 274E of the INA or Title VII may also lead to the termination of its participation in E- Page 5 of 13 I E-Verify MOU for Employer I Revision Date 09f01109 www.dhs.gov/E-Verify EVenly i hn1** Company ID Number: 487970 Verify. If the Employer has any questions relating to the anti-discrimination provision, it should contact OSC at 1-800-255-8155 or 1-800-237-2515 (TDD). 12. The Employer agrees to record the case verification number on the employee's Form 1-9 or to print the screen containing the case verification number and attach it to the employee's Form 1-9. 13. The Employer agrees that it will use the information it receives from SSA or OHS pursuant to E-Verify and this MOU only to confirm the employment eligibility of employees as authorized by this MOU. The Employer agrees that it will safeguard this information, and means of access to it (such as PINS and passwords) to ensure that it is not used for any other purpose and as necessary to protect its confidentiality, including ensuring that it is not disseminated to any person other than employees of the Employer who are authorized to perform the Employer's responsibilities under this MOU, except for such dissemination as may be authorized in advance by SSA or OHS for legitimate purposes. 14.The Employer acknowledges that the information which it receives from SSA is governed by the Privacy Act (5 U.S.C. § 552a(i)(1) and (3)) and the Social Security Act (42 U.S.C. 1306(a)), and that any person who obtains this information under false pretenses or uses it for any purpose other than as provided for in this MOU may be subject to criminal penalties. 15. The Employer agrees to cooperate with OHS and SSA in their compliance monitoring and evaluation of E-Verify, including by permitting DHS and SSA, upon reasonable notice, to review Forms 1-9 and other employment records and to interview it and its employees regarding the Employer's use of E-Verify, and to respond in a timely and accurate manner to OHS requests for information relating to their participation in E-Verify. D. RESPONSIBILITIES OF FEDERAL CONTRACTORS WITH THE FAR E-VERIFY CLAUSE 1. The Employer understands that if it is a subject to the employment verification terms in Subpart 22.18 of the FAR, it must verify the employment eligibility of any existing employee assigned to the contract and all new hires, as discussed in the Supplemental Guide for Federal Contractors. Once an employee has been verified through E-Verify by the Employer, the Employer may not reverify the employee through E-Verify. a, Federal contractors with the FAR E-Verify clause agree to become familiar with and comply with the most recent versions of the E-Verify User Manual for Federal Contractors and the E-Verify Supplemental Guide for Federal Contractors. b. Federal contractors with the FAR E-Verify clause agree to complete a tutorial for Federal contractors with the FAR E-Verify clause. c. Federal contractors with the FAR E-Verify clause not enrolled at the time of contract award: An Employer that is not enrolled in E-Verify at the time of a contract award must enroll as a Federal contractor with the FAR E-Verify clause in E-Verify within 30 calendar days of contract award and, within 90 days of enrollment, begin to use E-Verify to initiate verification of employment eligibility of new hires of the Employer who are working in the United States, Page 6 of 13 I E-Verify MOU for Employer Revision Date 09/01109 www.dhs.gov/E-Verify eWPAZ-t- Company ID Number: 487970 whether or not assigned to the contract. Once the Employer begins verifying new hires, such verification of new hires must be initiated within 3 business days after the date of hire. Once enrolled in E-Verify as a Federal contractor with the FAR E-Verify clause, the Employer must initiate verification of employees assigned to the contract within 90 calendar days from the time of enrollment in the system and after the date and selecting which employees will be verified in E-Verify or within 30 days of an employee's assignment to the contract,whichever date is later. d. Employers that are already enrolled in E-Verify at the time of a contract award but are not enrolled in the system as a Federal contractor with the FAR E-Verify clause: Employers enrolled in E-Verify for 90 days or more at the time of a contract award must use E-Verify to initiate verification of employment eligibility for new hires of the Employer who are working in the United States, whether or not assigned to the contract, within 3 business days after the date of hire. Employers enrolled in E-Verify as other than a Federal contractor with the FAR E-Verify clause, must update E-Verify to indicate that they are a Federal contractor with the FAR E- Verify clause within 30 days after assignment to the contract. If the Employer is enrolled in E- Verify for 90 calendar days or less at the time of contract award, the Employer must, within 90 days of enrollment, begin to use E-Verify to initiate verification of new hires of the contractor who are working in the United States, whether or not assigned to the contract. Such verification of new hires must be initiated within 3 business days after the date of hire. An Employer enrolled as a Federal contractor with the FAR E-Verify clause in E-Verify must initiate verification of each employee assigned to the contract within 90 calendar days after date of contract award or within 30 days after assignment to the contract,whichever is later. e. Institutions of higher education, State, local and tribal governments and sureties: Federal contractors with the FAR E-Verify clause that are institutions of higher education (as defined at 20 U.S.C. 1001(a)), State or local governments, governments of Federally recognized Indian tribes, or sureties performing under a takeover agreement entered into with a Federal agency pursuant to a performance bond may choose to only verify new and existing employees assigned to the Federal contract. Such Federal contractors with the FAR E-Verify clause may, however, elect to verify all new hires, and/or all existing employees hired after November 6, 1986. The provisions of Article II.D, paragraphs 1.a and 1.b of this MOU providing timeframes for initiating employment verification of employees assigned to a contract apply to such institutions of higher education, State, local and tribal governments, and sureties. f.Verification of all employees: Upon enrollment, Employers who are Federal contractors with the FAR E-Verify clause may elect to verify employment eligibility of all existing employees working in the United States who were hired after November 6, 1986, instead of verifying only new employees and those existing employees assigned to a covered Federal contract. After enrollment, Employers must elect to do so only in the manner designated by DHS and initiate E- Verify verification of all existing employees within 180 days after the election. g. Form 1-9 procedures for existing employees of Federal contractors with the FAR E- Verify clause: Federal contractors with the FAR E-Verify clause may choose to complete new Forms 1-9 for all existing employees other than those that are completely exempt from this process. Federal contractors with the FAR E-Verify clause may also update previously completed Forms 1-9 to initiate E-Verify verification of existing employees who are not. completely exempt as long as that Form 1-9 is complete (including the SSN), complies with Page 7 of 13 I E-Verify MOU for Employer i Revision Date 09/01/09 www.dhs.govlE-Verify YR: ,,,,„, „„i' ,..„ _ eri vr Company ID Number: 487970 Article II.C.5, the employee's work authorization has not expired, and the Employer has reviewed the information reflected In the Form 1-9 either in person or in communications with the employee to ensure that the employee's stated basis in section 1 of the Form 1-9 for work authorization has not changed (including, but not limited to, a lawful permanent resident alien having become a naturalized U.S. citizen). If the Employer is unable to determine that the Form 1-9 complies with Article II.C.5, if the employee's basis for work authorization as attested in section 1 has expired or changed, or if the Form 1-9 contains no SSN or is otherwise incomplete, the Employer shall complete a new 1-9 consistent with Article li.C.5, or update the previous 1-9 to provide the necessary information. If section 1 of the Form 1-9 is otherwise valid and up-to- date and the form otherwise complies with Article II.C.5, but reflects documentation (such as a U.S. passport or Form 1-551) that expired subsequent to completion of the Form 1-9, the Employer shall not require the production of additional documentation, or use the photo screening tool described in Article II.C.5, subject to any additional or superseding instructions that may be provided on this subject in the Supplemental Guide for Federal Contractors. Nothing in this section shall be construed to require a second verification using E-Verify of any assigned employee who has previously been verified as a newly hired employee under this MOU, or to authorize verification of any existing employee by any Employer that is not a Federal contractor with the FAR E-Verify clause. 2. The Employer understands that if it is a Federal contractor with the FAR E-Verify clause, its compliance with this MOU is a performance requirement under the terms of the Federal contract or subcontract, and the Employer consents to the release of information relating to compliance with its verification responsibilities under this MOU to contracting officers or other officials authorized to review the Employer's compliance with Federal contracting requirements. ARTICLE Ill REFERRAL OF INDIVIDUALS TO SSA AND DHS A. REFERRAL TO SSA 1. If the Employer receives a tentative nonconfirmation issued by SSA, the Employer must print the notice as directed by the E-Verify system and provide it to the employee so that the employee may determine whether he or she will contest the tentative nonconfirmation. The Employer must review the tentative nonconfirmation with the employee in private. 2. The Employer will refer employees to SSA field offices only as directed by the automated system based on a tentative nonconfirmation, and only after the Employer records the case verification number, reviews the input to detect any transaction errors, and determines that the employee contests the tentative nonconfirmation. The Employer will transmit the Social Security Number to SSA for verification again if this review indicates a need to do so. The Employer will determine whether the employee contests the tentative nonconfirmation as soon as possible after the Employer receives it. 3. If the employee contests an SSA tentative nonconfirmation, the Employer will provide the employee with a system-generated referral letter and instruct the employee to visit an SSA office within 8 Federal Government work days. SSA will electronically transmit the result of the referral to the Employer within 10 Federal Government work days of the referral unless it Page 8 of 13 I E-Verify MOU for Employer i Revision Date 09/01/09 www.dhs.gov/E-Verify 1 ,,,, ..... .... . e q. ig r �'y.7iiL4S ,,,,,, ,, p.,**,, Company ID Number: 487970 determines that more than 10 days is necessary.The Employer agrees to check the E-Verify system regularly for case updates. 4. The Employer agrees not to ask the employee to obtain a printout from the Social Security Number database (the Numident) or other written verification of the Social Security Number from the SSA. B. REFERRAL TO OHS 1. If the Employer receives a tentative nonconfirmation issued by DHS, the Employer must print the tentative nonconfirmation notice as directed by the E-Verify system and provide it to the employee so that the employee may determine whether he or she will contest the tentative nonconfirmation, The Employer must review the tentative nonconfirmation with the employee in private. 2. If the Employer finds a photo non-match for an employee who provides a document for which the automated system has transmitted a photo, the employer must print the photo non-match tentative nonconfirmation notice as directed by the automated system and provide it to the employee so that the employee may determine whether he or she will contest the finding. The Employer must review the tentative nonconfirmation with the employee in private. 3.The Employer agrees to refer individuals to OHS only when the employee chooses to contest a tentative nonconfirmation received from DHS automated verification process or when the Employer issues a tentative nonconfirmation based upon a photo non-match, The Employer will determine whether the employee contests the tentative nonconfirmation as soon as possible after the Employer receives it. 4. If the employee contests a tentative nonconfirmation issued by DHS, the Employer will provide the employee with a referral letter and instruct the employee to contact DHS through its toll-free hotline (as found on the referral letter)within 8 Federal Government work days. 5. If the employee contests a tentative nonconfirmation based upon a photo non-match,the Employer will provide the employee with a referral letter to DHS. OHS will electronically transmit the result of the referral to the Employer within 10 Federal Government work days of the referral unless it determines that more than 10 days is necessary. The Employer agrees to check the E- Verify system regularly for case updates. 6.The Employer agrees that if an employee contests a tentative nonconfirmation based upon a photo non-match, the Employer will send a copy of the employee's Form 1-551 or Form 1-766 to OHS for review by: • Scanning and uploading the document, or • Sending a photocopy of the document by an express mail account(paid for at employer expense). 7. If the Employer determines that there is a photo non-match when comparing the photocopied List B document described in Article II.C.5 with the image generated in E-Verify,the Employer must forward the employee's documentation to DHS using one of the means described in the preceding paragraph, and allow DHS to resolve the case. Page 9 of 13 I E-Verify MOU for Employer I Revision Date 09/01109 UMW.dhs.gov/E-Verify es.`j' '. 'E .0, 4N. °' Company ID Number: 487970 ARTICLE IV SERVICE PROVISIONS SSA and DHS will not charge the Employer for verification services performed under this MOU. The Employer is responsible for providing equipment needed to make inquiries. To access E- Verify, an Employer will need a personal computer with Internet access. ARTICLE V PARTIES A. This MOU is effective upon the signature of all parties, and shall continue in effect for as long as the SSA and DHS conduct the E-Verify program unless modified in writing by the mutual consent of all parties, or terminated by any party upon 30 days prior written notice to the others. Any and all system enhancements to the E-Verify program by DHS or SSA, including but not limited to the E-Verify checking against additional data sources and instituting new verification procedures, will be covered under this MOU and will not cause the need for a supplemental MOU that outlines these changes. DHS agrees to train employers on all changes made to E- Verify through the use of mandatory refresher tutorials and updates to the E-Verify User Manual, the E-Verify User Manual for Federal Contractors or the E-Verify Supplemental Guide for Federal Contractors. Even without changes to E-Verify, DHS reserves the right to require employers to take mandatory refresher tutorials. An Employer that is a Federal contractor with the FAR E-Verify clause may terminate this MOU when the Federal contract that requires its participation in E-Verify is terminated or completed. In such a circumstance, the Federal contractor with the FAR E-Verify clause must provide written notice to DHS. If an Employer that is a Federal contractor with the FAR E-Verify clause fails to provide such notice, that Employer will remain a participant in the E-Verify program, will remain bound by the terms of this MOO that apply to participants that are not Federal contractors with the FAR E-Verify clause, and will be required to use the E-Verify procedures to verify the employment eligibility of all newly hired employees. B. Notwithstanding Article V, part A of this MOO, DHS may terminate this MOU if deemed necessary because of the requirements of law or policy, or upon a determination by SSA or DHS that there has been a breach of system integrity or security by the Employer, or a failure on the part of the Employer to comply with established procedures or legal requirements. The Employer understands that if it is a Federal contractor with the FAR E-Verify clause, termination of this MOO by any party for any reason may negatively affect its performance of its contractual responsibilities. C. Some or all SSA and DHS responsibilities under this MOU may be performed by contractor(s), and SSA and DHS may adjust verification responsibilities between each other as they may determine necessary. By separate agreement with DHS, SSA has agreed to perform its responsibilities as described in this MOO. Page 10 of 13 I&Verify MOU for Employer I Revision Date 09101/09 www,dhs.gov!E-Verify E-Verilvt. 1Y[hA Company ID Number:487970 D. Nothing in this MOU is intended, or should be construed, to create any right or benefit, substantive or procedural, enforceable at law by any third party against the United States, its agencies, officers, or employees, or against the Employer, its agents, officers, or employees. E. Each party shall be solely responsible for defending any claim or action against it arising out of or related to E-Verify or this MOU, whether civil or criminal, and for any liability wherefrom, including (but not limited to) any dispute between the Employer and any other person or entity regarding the applicability of Section 403(d) of IIRIRA to any action taken or allegedly taken by the Employer. F. The Employer understands that the fact of its participation in E-Verify is not confidential information and may be disclosed as authorized or required by law and DHS or SSA policy, including but not limited to, Congressional oversight, E-Verify publicity and media inquiries, determinations of compliance with Federal contractual requirements, and responses to inquiries under the Freedom of Information Act(FOIA). G. The foregoing constitutes the full agreement on this subject between DHS and the Employer. H. The individuals whose signatures appear below represent that they are authorized to enter into this MOU on behalf of the Employer and DHS respectively. Page 11 of 13 I E-Verify MOtJ for Employer I Revision Date 09/01/00 www.dhs.govlE-Verify INN , ... e r 1 V ,,s.‘„,, ap, ",,,,, Company ID Number: 487970 To be accepted as a participant in E-Verify, you should only sign the Employer's Section of the signature page. If you have any questions,contact E-Verify at 888-464-4218. ''Employer Marquee Development,Inc. _.m. ...___.._ Igarnett craig Name(Please Type or Print) Title __.. ... ....w ��__,..... lectrartically Slgned 01111/2012 igriatiire Date •:partment of Homeland Security—Verification Division SCIS Verification Division ._.. _.. _w._. Name(Please Type or Print) Title E1ectronicaliy Signed 01/1112012 Date _._.,..... .�...__...w..,..ignature1 Information Required for the E-Verify Program nformatlon relating to your Company: Company, Name:Marquee Development,Inc. Compan Facility Address:A801 Troydale Rd Tampa,FL 33616 Company Alternate Address: County or Parish: HILLSBOROUGH Employer Identification Number: 593382032 Page 12 of 13 I E-Verify MOU for Employer I Revision Date 09/01/09 www.dhs.goviE-Verify K, -Verm Company ID Number:487970 North American industry Classification Systems Code: 238 Administrator: Number of Employees: 5 to 9 Number of Sites Verified for: 1 Are you verifying for more than 1 site?If yes,please provide the number of sites verified for in each State: FLORIDA I site(s) Information relating to the Program Administrator(s)for your Company on policy questions or operational problems: Name: garnett s Craig Telephone Number: (813)758-4195 Fax Number: (813)886-3982 E-mail Address: marqueedev(a)aot.com Page 13 of 13 I E-Verify MOU for Employer I Revision Date 09/01/09 www.dhs.gov/E-Verify DtviSiroN OF Col POORATiON, 1 /. rg pgr rthwnt of Sj, Sf.%. / piyi ion of Corporatioj / Search Record 1 Board.)tmEnlitalauft / Detail by Entity Name Florida Profit Corporation MARQUEE DEVELOPMENT, INC. Filing Information Document Number P96000049514 FEUEIN Number 59-3382032 Date Filed 06/07/1996 State FL Status ACTIVE Last Event REINSTATEMENT Event Date Filed 12/29/2016 Principal Address 4801 TROYDALE RD. TAMPA,FL 33615 Changed:06/18/2010 Mailing Address 4801 TROYDALE RD. TAMPA, FL 33615 Changed: 06/18/2010 Registered Agent Name&Addrese CRAIG,Garnett 4801 TROYDALE ROAD TAMPA, FL 33635 Name Changed: 02/12/2017 Address Changed:09/08/2010 Officer/Director Detail Name&Address Title PD CRAIG,GARNETT S 4801 TROYDALE RD. TAMPA,FL 33615 Title TRES.,SECRY CRAIG, LORI 4801 TROYDALE RD. TAMPA, FL 33615 Annual Reports Report Year Filed Date 2021 01/18/2021 2022 02/04/2022 2023 01/29/2023 Document Imams. Q1129/2023-.ANNUAL REPORT View image in PDF format • Q21Q4/2029--ANNUAL REPQR.1 View image In POE format 01/18/2021--ANNUAL REPORT View image in PDF format 41L17/2020--ANNUAL REPORT View Image In PDF format Q LQQ12Q19 .fJ tUAL,REPQRJ View Image In PDF format 0t/041 (f1 =ANNUAL.REPORT View image in PDF format Q2 2 2Q_1.7._::A 11Ak EP'ORT View image in PDF format 1212212016--Bejg5.t/itein t View image in PDF format 10/22/2015—FtEUy$,IATEM.ENI View image In PDF format 901/201,4—ANNUAL REP_QR.I View image in PDF format 0.12312.Q1,...::..ANNUAL REPORT View Image in PDF format Q4/,2./2Q12--ANNUAL RE_I ORT View image in PDF format 04/28/2011 ANNUAL REPORI View image in PDF format 0QLLQEl1 Q1 •-ANNUAL REPORT View image in PDF format 07/202009 NN.IIAL REPORT View image in PDF format 2i/'f1aaL=ANN 1 1 1tEPORT View image in PDF format 05/30/2007—ANNUAL iffiEDRT View image in PDF format 0$1A$/2006—ANNUAL REPORT View Image in PDF format 07/10/2005—ANNUAL REpQ131 View image In PDF format 09P / 004—A N "Qg"f. View image in PDF format 06/01/20Q3--ANNUAL R POR7 View image in PDF format Q3/2312002--ANNUAL REPQ.E1 View image in PDF format 05/11/2001--ANNUAL REPORT View image in PDF format 09/05/2000-ANNUAL REPORT View image in PDF format 10/22/1999 REINSTATEMENT View Image in PDF format 04/20/199A--ANNUAL_REPORT View Image In PDF format 05/15/1997--ANNUAL REPORT View image in PDF format 06/07/1996—DOCUMENTS PRIOR TO 1997 View Image in PDF format 8)V“, Ron DeSantis,Governor Melanie S.Griffin,Secretary 4 *Os "'s\ bpr ' STATE OF FLORIDA DEPARTMENT OF V3USINESS AND PROFESSIONAL REGULATION CONSTRUCTION INDUSTRY LICENSING BOARD THE GENERAL CONTRACTOR HEREIN IS CERTIFIED UNDER THE PROVISIONS OF CHAPTER 489, FLORIDA STATUTES CRAIG, GARNETT SOLOMON MARQUEE DEVELOPMENT INC 4801 TROYDALE ROAD TAMPA FL 33615 LICENSE NUMBER:CGC1518689 EXPIRATION DATE: AUGUST 31,2026 Always verify licenses online at MyFloridaLicense.com ON*012 ISSUED:09/04/2024 Do not alter this document in any form. • This is your license. It is unlawful for anyone other than the licensee to use this document. 0 STATE OF FLORIDA .2 DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION 2601 BLAIR STONE ROAD TALLAHASSEE FL 32399-0783 Congratulations! With this license you become one of the nearly one million Floridians licensed by the Department of Business and Professional Regulation. Our professionals and businesses range from architects to yacht brokers,from boxers to barbeque restaurants, STATE OF FLORIDA DEPARTMENT and they keep Florida's economy strong. dbpi — OF BUSINESS AND PROFESSIONAL REGULATION Every day we work to improve the way we do business CGC1518689 ISSUED:09/04/2024 in order to serve you better. For information about our CERTIFIED GENERAL CONTRACTOR services, please log onto www.myfloridaIicense.com. CRAIG,GARNETT SOLOMON There you can find more information about our MARQUEE DEVELOPMENT INC divisions and the regulations that impact you, subscribe to department newsletters and learn more about the Department's initiatives. Signature LICENSED UNDER CHAPTER 489,FLORIDA STATUTES Our mission at the Department is: License Efficiently, EXPIRATION DATE: AUGUST 31,2026 Regulate Fairly. We constantly strive to serve you better so that you can serve your customers.Thank you for doing business in Florida,and congratulations on your new license! Ron DeSaritis, Governor Melanie S.Griffin,Secretary STATE OF FLORIDA DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION CONSTRUCTION INDUSTRY LICENSING BOARD LICENSE NUMBER: CGC1518689 EXPIRATION DATE: AUGUST 31,2026 THE GENERAL CONTRACTOR HEREIN IS CERTIFIED UNDER THE PROVISIONS OF CHAPTER 489, FLORIDA STATUTES CRAIG, GARNETT SOLOMON El. MARQUEE DEVELOPMENT INC - 44-50 4801 TROYDALE ROAD W it TAMPA FL 33615 ISSUED.091C4/2024 Always verify licenses online at MyFloridaLicense.com Do not alter this document in any form. This is your license.It is unlawful for anyone other than the licensee to use this document. ;01', 'ire, Ron DeSantis,Governor Melanie S.Griffin,Secretary FVE a ' ' r.' 111 PRO�FRIE IigABOARD OF STATE OF FLORIDA Tr- BOARD OF PROFESSIONAL ENGINEERS THE PROFESSIONAL ENGINEER HEREIN IS LICENSED UNDER THE PROVISIONS OF CHAPTER 471, FLORIDA STATUTES CRAIG, GARN SOLOMON 4801 TROYDALE RD TAMPA FL 336154801 LICENSE NUMBER:PE85948 EXPIRATION DATE: FEBRUARY 28,2025 Always verify licenses online at MyFloridaLicense.com ' El 9 k•T� a }.•,• Do not alter this document in'any form. F."' re o This is your license.It is unlawful for anyone other than the licensee to use this document. Form W-9 Request for Taxpayer (Rev.October2016) Identification Number and Certification Give Form to the Department of the Denary requester.Do not intense Revenue Service ►Go to www,lrm.gov/Formw9 fed Instructions and the latest informattctt. t Name(as shown on send to the IRS. your income tot return).Name le requi on this roue: not leave thus urea blank Mar utee LI elopmcnt,Inc. 2 Business nameldisregarded entity name,if different from above to ti 3 Check appropriate briefer federal tax Gasafkeasion cf�aareon whose name�entered on line 1.Check only one of the 4 Exemptions(coda* !allowing sew boxes spiteale:see 5 certain entities,not individuals;sae ❑ k+dlvkiuelfsele proprietor or 0 C Corporation Q S Corporationinstructions on page 3): $p. n single-member LLC ❑ Panne p 0 Trust/estote F ❑ Limited liability company Enter the tax clesalfication(C=C corporation, Exempt payee code(if any) tg Nate:mit Check the S=S corporation.P=Parinership)► appropriate box in the line above forthe tax ciassihcat on of the angle-member owner. Do not check &omoton from FATCA reporting LLC if the LLC is classified as a singe member LLC that is disregarded from the owner unless the owner of the LLC Is rs another LLC that not dtaregerded from the owner for U.S.federal tax Po is disregarded from the owner should check the ax does.Othanv 1t a single-nmmhar Lt C that �e"y) appropriate box for the tax etassrricaton of its owner. Oilier(sea Instru boats) 5 Address(number,Street and apt,or suite na)See instruot(ans, Aeon.mentirr ruecadeiceds tea(AS) t 4841 TrOydale Rd. Requester's name and address(wrtianslj e City,state,and ZIP code Tampa,FL 33615 7 List account numbers)here(optional) T21 axpttyutiv taertt(ftct3titxt Numbtor MN) Enter your TIN in the appropriate box.The TIN provided must match the name given on line 1 to avoid I Social awoke backup withholding,For individuals,this is generally your social security number(SSN).However,for a uri4'number ,- resident alien,sole proprietor,or disregarded entity,see the instructions for Part I.later.For other r"[— -t - - entitles,it Is your employer Identification number(EIN).If you do not have a number,sea How to gat a J( #� IJ i) TIN,later. or Note:If the account is in more than one name,see the instructions for line 1.Also sea What Name and Employer wentifle n number Number To Give the Requester for guidelines on whose number to enter. j 5 9 - 3 3 8 2 '0 3 2 Part 11 Certification Under penalties of perjury,I certify that 1.The number shown on this form is my correct taxpayer identification number(or I am wailing for a number to be issued to me);and 2.I am not subject to backup withholding because:(a)I am exempt from backup withholding,or(to)I have not been notified by the Internal Revenue Service(IRS)that I am subject to backup withhotd;ng as a result of a failure to report all interest or dividends,or(c)the IRS has notified ma that lam no longer subject to backup withholding;and 9.I am a U.S.citizen or other U.S.person(defined below);and 4.The FATCA code(s)entered on this form!et any)Indicating that I am exempt from FATCA reporting is correct. Certification instructions.You must cross cut item 2 above If you have been notified by the IRS that you are currently subject to backup withholding because you have fated to report all Interest and dividends on your tax return.For real estate transactions,item 2 does not apply.For mortgage Interest paid, acquisition or abandonment of secured property,cancellation of debt,contributions to an Individual retirement arrangement t other than Interest and dividends,you areitot required to sign the eellificaton,but you must provide your correct TIN.See the instructions for generally. lyj,,lja r. Hare .. ►Sign store or Bataan }/r�^ . . r ' c, Oa i General Instructions a Form 1099-11N(dividends,I chiding those from stocks or mutual Section references are to tree Internal Revenue Code unless otherwise funds) noted. •Form 1099-MISC(various types of Income,prizes,awards,or gross Future developments.Far the latest Information about developments proceeds) related to Form W-9 and its Instructions,such es legislation enacted •Farm 1099 H(woke or mutual fund sales and certain other after they were published,go to www.Ins.gov/FormW9. transactions by brokers) Purpose of Form •Form 1099-S(proceeds from real estate transactions) An individual or entityrequested •Form 1099-K(merchant card and third party network transactions) information return htthe IRS must obtain your correct requiredpayer 1098 T(tuitiii Form on) Identification mortgage interest), rigs-E(student loan interest), Identification number(TIN)which may be your social security number • (SSN),Individual taxpayer Identification number(MN),adoption Form 1099-C(canceled debt) taxpayer Identification number(ATIN),or employer Identification number •Form 1099-A(acquisition or abandonment of secured property) (EN),to report on an information return the amount paid to you,or other Use Form W-s onlyIf amount reportable on an information return.Examples of Information alien),to provide you correct are u U.S.person(Including a resident returns Include,but are not limited to,the following, •Form 1099-1NT(interest a rred or paid) If you do not return Form W-9 to the requester with a 7ih,you might be subject fo backup withholding.See Whit a backup withholding, later. Cal No.10231X Form W-9(Aev,to-2oia1 jti 0l p ei,4a iS� i •0° g �j. 'p\ Marion tlrltaty ilf Honti of ("nullify Cttutirsiotter>a ) II � . ; .6) . . G "/ i )i1►c,,,,[' i11+.'t .c)ttitiv g !'tt;,,lt7c;N• ��vtC0.r 11 :{1i `si1,,1r.•,•. .rorc)1t1a, 17, 4.1} , Ol_t .t 1'lulia.! l'i)..t,• t 4ti,tai P T. 0 R I 1.7 A Fan: 1',L.li'i 1•ti(i.`;i July 9,2013 RE: Letter of Recommendation-Marquee Development To Whom It May Concern: Marquee Development has performed business with Marion County on the Marion Oaks Trails Sidewalk—Phase II project in May of 2011 and successfully completed the construction project with the expected quality and professionalism. Disputes and conflicts were resolved in an amicable manner with a partnership approach. Marquee Development was very responsive to the County's requests and directives. I recommend Marquee Development, without any reservation. Please do not hesitate to c ntact the at (352) 671-8686 if you need additional information or if you wish to discuss this matter further. Sincerely, Michael O. Butzcr Construction Manager MOB/jih cc: File "Meeting Needs by Exceeding Expectations" www.imuicmccuuuytl.org Ca , County Email: Matthew Webstera@colliercountyfl.gov Telephone: (239) 252-8491 Procurement Serves Division Addendum#1 Date: August 5,2024 From: Matthew Webster,Procurement Strategist To: Interested Bidders Subject: Addendum#1 Solicitation#24-8233 --Immokalee Sidewalks Phase III The following clarifications are issued as an addendum: ADDITION: A copy of the"Pre-Bid Sign-In Sheet"has been uploaded to OpenGov. Please see: 24-8233 Pre-Bid Sign In Sheets.pd'in the attachments section of the solicitation. If you require additional information,please post a question on our Bid Sync(www.bidsync.con)bidding platform under the solicitation for this project. Please sign below and return a copy of this Addendum with your submittal for the above referen •olicitati , 70 ignature) .- Date (Name of rm) Email: Rita.Iglesias(c)colliercountyfl.gov Co le-r County Telephone: (239)252-1033 Procurement Srvices Da nsion Addendum 142 Date: August 27,2024 From: Rita.Iglesias,Procurement Strategist To: Interested Bidders Subject: Addendum#2 Solicitation#24-8233 -Immokalee Sidewalks Phase III This Addendum has been issued for the following items identifying clarifications,changes,deletions, and/or additions to the original solicitation documents and bid schedule for the above referenced solicitation: Change: Extend Question&Answer Deadline and Bid Due Date: QUESTION&ANSWER , ,Wednesday,September 10,2024,at 5:00 PM DEADLINE: EST BID OPENING DAY/DATE/TIME: Tuesday,September 034,Wednesday,September 17,2024,at 3:00 PM EST If you require additional information,please post a question on our OpenGov (lutps i procurement.openeov com)bidding platform under the solicitation for this project. Please sign be w and return a copy of this Addendum with your submittal for the above referenced' Ici ati , G { nature Date (Name of I?i ) 1 ,f, Email: Rita.Iglesias@colliercountyfl.gov y Telephone: (239)252-1033 Procurement Services Division Addendum#3 Date: August 27,2024 From: Rita Iglesias,Procurement Strategist To: Interested Bidders Subject: Addendum#3 Solicitation#24-8233 -Immokalec Sidewalks Phase III This Addendum has been issued for the following items identifying clarifications,changes,deletions, and/or additions to the original solicitation documents and bid schedule for the above referenced. solicitation: Change 1: 21 4213 Solicitation--is being replaced by 24-8243 Solicitation Rev.1 Summary of Changes: Form 12—Bidders Checklist—9.d.Any required professional licenses—valid and current (mytloridalicense.com)(ie: General Contractors license,Underground Utility and Excavation,Builders, Trade Contractors,etc.,as applicable,requested and/or required.) REQUIRED: General Contractors License OR Building Contractor License If you require additional information, please post a question on our OpcnGov (https:llprocurement.opengov.coni)bidding platform under the solicitation for this project. Please sign b I w and return a copy of this Addendum with your submittal for the above reference s icitation. } (Stare) Date (Name of Firm / Email: Rita.Iglesias@colliercountyfl.gov o er Count Telephone: (239)252-1033 Procurement Services Division Addendum#4 Date: September 5,2024 From: Rita Iglesias, Procurement Strategist To: Interested Bidders Subject: Addendum #4 Solicitation#24-8233-Immokalee Sidewalks Phase III This Addendum has been issued for the following items identifying clarifications,changes,deletions, and/or additions to the original solicitation documents and bid schedule for the above referenced solicitation: There are material changes for this Addendum. This Addendum is to correct a clerical error in Addendum #3, as follows: Change 1: 24 8213 24-8233 Solicitation is being replaced by 21 8243 24-8233 Solicitation Rev.I If you require additional information,please post a question on our OpenGov (1https:i/procurcmcnt.operneov.com)bidding platform under the solicitation for this project. Please sign belo., and return a copy of this Addendum with your submittal for the above referenced 'citation. (Si_ attire ate fidegee 1--7/1/176)A-74i ._. ,e'.' lei _ • (Name of F. ' ) �' rr EXHIBIT A-3: CONTRACTOR'S KEY PERSONNEL ASSIGNED TO THE PROJECT Name Personnel Category [Thomas Arevalo] Construction Superintendent [Garnett Craig] Project Manager 12 Construction Services Agreement:[2024_ver.3] EXHIBIT B-1: PUBLIC PAYMENT BOND (Following This Page) 13 Construction Services Agreement:[2024_ver.3] EXHIBIT B— 1: PUBLIC PAYMENT BOND Bond No. S-345256 Contract No. 24-8233 KNOW ALL MEN BY THESE PRESENTS: That Marquee Development, Inc. as Principal/Contractor, and NGM Insurance Company , as Surety, located at 4601 Touchton Road East, Suite 3400, Jacksonville, FL 32245 (Business Address) are held and firmly bound to Collier County Board of County Commissioners aS Oblige in the SUM Of One Million One Hundred Eighty-Six Thousand One Hundred Seventy-Nine&50/100 ($1,186,179.50 ), this includes allowance for the payment whereof we bind ourselves, our heirs, executors, personal representatives, successors, and assigns,jointly and severally. WHEREAS, Principal has entered into a contract dated as of the o day of --1C,. , 2025 with Oblige for Immokalee Sidewalks Phase III (Project) in accordance with drawings and specifications, which contract is incorporated by reference and made a part hereof and is referred to as the Contract. THE CONDITION OF THIS BOND is that if Principal: Promptly makes payment to all claimants as defined in Section 255.05(1), Florida Statutes, supplying Principal with labor, materials, or supplies, used directly or indirectly by Principal in the prosecution of the work provided for in the contract, then this bond is void; otherwise, it remains in full force. Any changes in or under the Contract and compliance or noncompliance with any formalities connected with the Contract or the changes do not affect sureties' obligation under this Bond. The provisions of this bone are subject to the time limitations of Section 255.0592. In no event will the Surety be liable in the aggregate to claimants for more than the penal sum of this Payment Bond, regardless of the number of suits that may be filed by claimants. IN WITLESS WHEREOF, the above parties have executed this instrument this " day of ;--Jent Vt1 "..1 , 2025, the name of undersigned representative, pursuant to authority of its governing body. Signed, sealed and delivered in the presence of: PRI A CO ACTOR: Marquee Development, Inc. ,r nature 1 �l (Tnat u)P-f"7 (i/ {l, ' p d i_ uwiccSta "a Name and Title KellytsutHven My Commission HH 138915 p F I • Expires08I0812025 STATE OF FIb O' COUNTY OF Rt l ' .0(Cg4---- The foregoing instrument was acknowledged before me by means of " physical presence or online otarization, this / day of T �ArLi..t 2025 by eTriii. -)e:H- C r a_i , as VIP S i ole,r)f—f)L _1 of Marquee Development, Inc. a Florida corporation, on behalf of the corporation. +HeII __ is__personally known to met OR has produced identification and di Id not) take an oath. My Commission Expires: 4e � (AFFIX OFFICIAL SEAL) �r ��� SURETY: (Sig 9ture of otary) z` //c . . ,I.1. /lrVa-c.J') NGM Insurance Company (Legibly Pried) ►+ e Notary Public, State of =4.°""°°Fos.,= Commission No.: N` /,3 9/ Di Y' z( 1923 ,1 t� ; 4601 Touchton Road East, Suite 3400 Authorized Signature '41/111Dt Jacksonville, FL 32245 David B. Shick, Attorney-In-Fact & (Business Address) Licensed FL Resident Agent#A241176 (Printed Name) STATE OF FLORIDA COUNTY OF HILLSBOROUGH The foregoing instrument was acknowledged before me by means of X physical presence or online notarization, this 21st day of January 2025 by David B. Shick, as Attorney-In-Fact of NGM Insurance Company a FL corporation, on behalf of the corporation. He/She is personally known to me OR has produced N/A identification and did (did not)take an oath. f`, My Commission Expires: 12/18/2026 IV , ' rtNdik.C!!'e1' (Signature of Notary) : ""'x``-'�e,: DANIELLE WHALEN Danielle Whalen .: " :+• MY COMMISSION#HH 335603 (Legibly Printed,) `''` ..t., ,, EXPIRES:December 18,2026 ""tffe.^°`" Notary Public, State of Florida Commission No.: HH 335603 OR POWER OF ATTORNEY IN FACT EXHIBIT B-2: PUBLIC PERFORMANCE BOND (Following This Page) 14 Construction Services Agreement:[2024_ver.3] EXHIBIT B—2: PUBLIC PERFORMANCE BOND Bond No. S-345256 Contract No. 24-8233 KNOW ALL MEN BY THESE PRESENTS: That Marquee Development, Inc. as Principal/Contractor, and NGM Insurance Company , as Surety, located at 4601 Touchton Road East, Suite 3400, Jacksonville, FL 32245 (Business Address) are held and firmly bound to Collier County Board of County Commissioners as Oblige in the SUM of One Million One Hundred Eighty-Six Thousand One Hundred Seventy-Nine&50/100 ($1,186,179.50 ), this includes allowance for the payment whereof we bind ourselves, our heirs, executors, personal representatives, successors, and assigns,jointly and severally. WHEREAS, Principal has entered into a contract dated as of the $41‘ day of ,or;1 , 2025 with Oblige for Immokalee Sidewalks Phase III (Project) in accordance with drawings and specifications, which contract is incorporated by reference and made a part hereof and is referred to as the Contract. THE CONDITION OF THIS BOND is that if Principal: 1. Performs the Contract at the times and in the manner prescribed in the Contract; and 2. Pays Obligee any and all losses, damages, costs, and attorneys' fees that Obligee sustains because of any default by Principal under the Contract, including, but not limited to, all delay damages, whether liquidated or actual, incurred by Obligee; and 3. Performs the guarantee of all work and materials furnished under the Contract for the time specified in the Contract, then this bond is void; otherwise, it remains in full force. Any changes in or under the Contract and compliance or noncompliance with any formalities connected with the Contract or the changes do not affect Sureties obligation under this Bond. The Surety, for value received, hereby stipulates and agrees:hat no changes, extensions of time, alterations or additions to the terms of the Contract or other work to be performed hereunder, or the specifications referred to therein shall in anywise affect its obligations under this bond, and it does hereby waive notice of any such changes, extensions of time, alterations or additions to the terms of the Contract or to work or to the specifications. This instrument shall be construed in all respects as a common law bond. It is expressly understood that the time provisions and statute of limitations under Section 255.05, Florida Statutes, shall not apply to this bond. In no event will the Surety be liable in the aggregate to Obligee for more than the penal sum of this Performance Bond regardless of the number of suits that may be filed by Obligee. IN WITNESS WHEREOF, the above parties have executed this instrument this //2 / day of ){/1acArt,4 , 2025, the name of each party being affixed, and these presents duly signed by its undersigned representative, pursuant to authority of its governing body. Signed, sealed and delivered in the presence of: PRI CIP /C TRACTOR: Marquee Development, Inc. Si nature • -� •4-4i _ L !'YI / �u/6- "t' ' N Public nor Florida Name and Title ,vi.�`'q `` Ke+ry M Suitivan {� My Commission HH 138915 { ,,t ,, w00 Expires 0610812025 i STATE OF FlogiLa*-- A ,r COUNTY OF j/jc{ry)'��u�L-- The foregoing instrument was acknowledged before me by means of 1/ physical presence or online ,notarization, this / day of -J - 2025 by 6 t.Pat E_-!-4. e%'oLo , as ikt c,i le!'7 of Marquee Development,_Lnc, ___ Florida corporation, on behalf of the corporation. (He/flise is personally known to me)OR has produced identification and did (did not)take an oath. My Commission Expires: (AFFIX OFFICIAL SEAL) 2e116/ in2JA.—j (Signature f Kota ) SURETY: k/16 14; /-. .,LU/rI ) NGM Insurance Company (Legibly Printed) ° nF�� Notary Public, State of F/jJA CA-- (,� 'e F°'�"OEo�*a Commission No.: }� f, /6 ,} 1 "1' - =ç1923 ) L ir- s. f s 4601 To uchton Road East, Suite 3400 Authorized Signature '" f°!!„It Jacksonville, FL 32245 David B. Shick, Attorney-In-Fact & (Business Address) Licensed FL Resident Agent#A24 1176 (Printed Name) STATE OF FLORIDA COUNTY OF HILLSBOROUGH The foregoing instrument was acknowledged before me by means of X physical presence or online notarization, this 21st day of January 2025 by David B. Shick, as Attorney-In-Fact of NGM Insurance Company a FL corporation, on behalf of the corporation. He/She is personally known to me OR has produced N/A identification and did (did not)take an oath. r, au f. My Commission Expires: 12/18/2026 )�\)}1'1` � �. .., (Signature of Notary) / ' -; DANIELLEWHALEN Danielle Whalen .: :*_ MY COMMISSION (Legibly Printed) `7r���`'P°' EXPIRES:December 18,2026 .F°4►�°." Notary Public, State of Florida Commission No.: HH 335603 OR POWER OF ATTORNEY IN FACT MAIN a \ STREET Trusted POWER OF ATTORNEY AMERICA (choke INSURANCE -_ KNOW ALL MEN BY THESE PRESENTS: That NGM Insurance Company,a Florida corporation having its principal office in the City of Jacksonville, State of Florida,pursuant to Article IV,Section 2 of the By-Laws of said Company,to wit: "Article IV, Section 2. The board of directors, the president, any vice president, secretary, or the treasurer shall have the power and authority to appoint attorneys-in-fact and to authorize them to execute on behalf of the company and affix the seal of the company thereto, bonds, recognizances.contracts of indemnity or writings obligatory in the nature of a bond, recognizance or conditional undertaking and to remove any such attorneys-in-fact at any time and revoke the power and authority given to them. " does hereby make,constitute and appoint Brandy Balch,David B.Shick its true and lawful Attorneys-in-fact,to make,execute,seal and deliver for and on its behalf,and as its act and deed, bonds. undertakings, recognizances,contracts of indemnity,or other writings obligatory in nature of a bond subject to the following limitation: 1. No one bond to exceed Five Million Dollars ($5,000,000) and to bind NGM Insurance Company thereby as fully and to the same extent as if such instruments were signed by the duly authorized officers of NGM Insurance Company;the acts of said Attorney are hereby ratified and confirmed. This power of attorney is signed and sealed by facsimile under and by the authority of the following resolution adopted by the Directors of NGM Insurance Company at a meeting duly called and held on the 2nd day of December 1977. Voted:That the signature of any officer authorized by the By-Laws and the company seal may be affixed by facsimile to any power of attorney or special power of attorney or certification of either given for the execution of any bond, undertaking,recognizance or other written obligation in the nature thereof; such signature and seal,when so used being hereby adopted by the company as the original signature of such office and the original seal of the company,to be valid and binding upon the company with the same force and effect as though manually affixed. IN WITNESS WHEREOF, NGM Insurance Company has caused these presents to be signed by its Assistant Secretary and its corporate seal to be hereto affixed this 24th day of August,2023. NGM INSURANCE COMPANY By: ; " �04 Lauren K.Powell :Z tK Assistant Secretary ''',41CciON State of Wisconsin. County of Dane. On this 24th day of August. 2023, before the subscriber a Notary Public of State of Wisconsin in and for the County of Dane duly commissioned and qualified,came Lauren K. Powell of NUM Insurance Company, to me personally known to be the officer described herein,and who executed the preceding instrument,and she acknowledged the execution of same,and being by me fully sworn,deposed and said that she is an officer of said Company, aforesaid: that the seal affixed to the preceding instrument is the corporate seal of said Company,and the said corporate seal and her signature as officer were duly affixed and subscribed to the said instrument by the authority and direction of the said Company:that Article IV.Section 2 of the By-Laws of said Company is now in force. IN WITNESS WHEREOF,I have hereunto set my hand and affixed my official seal at Madison,Wisconsin this 24th day of August, 2023. soc,yy A/y 1 t/- .0"f \, I,Andrew Rose.Vice President of NGM Insurance Company,do hereby certify that the above and foregoing is a true and correct copy of a Power of Attorney executed by said Company which is still in full force and effect. IN WITNESS WHEREOF,I have hereunto set my hand and affixed the seal of said Company at Madison.Wisconsin this 2-ji±day of AA • 7 C2ZS . (.6,teet.6(4-) L L s "-4 7y; Andrew Rose.Vice President _( 19230)7`. s\� WARNING:Any unauthorized reproduction or alteration of this document is prohibited. '', oRIo /1 TO CONFIRM VALIDITY of the attached bond please call I-60J-354.5281. TO SUBMIT A CLAIM:Send all correspondence to 55 West Street.Keene.NH 03431 Attn:Bond Claim Dept.or call our Bond Claim Dept.at 1-603-358-1437. Marquee Development, Inc. April 19, 2025 Re: lmmokalee Sidewalks Phase III Project ID: 24-8233 Construction Agreement- Contract Date To whom it may concern: By copy of this letter, Marquee Development, Inc. hereby provides consent to Collier County Procurement Services to date the above referenced Construction Agreement between Collier County BOCC and Marquee Development, Inc.. If you have any questions, please do not hesitate to call me at (813) 758-4195. Since,r, ly, Garnett Craig, President 4801 Troydale Road,Tampa,FL 33615 (813) 886-3982 Fax (813) 758-4195 Telephone EXHIBIT B-3: INSURANCE REQUIREMENTS (Following This Page) 15 Construction Services Agreement:[2024_ver.3] EXHIBIT B-3: INSURANCE REQUIREMENTS The Contractor shall at its own expense, carry and maintain insurance coverage from responsible companies duly authorized to do business in the State of Florida as set forth herein. The Contractor shall procure and maintain property insurance upon the entire project, if required, to the full insurable value of the scope of work. The County and the Contractor waive against each other and the County's separate Contractors, Design Consultant, Subcontractors, agents and employees of each and all of them, all damages covered by property insurance provided herein, except such rights as they may have to the proceeds of such insurance. The Contractor and County shall, where appropriate, require similar waivers of subrogation from the County's separate Contractors, Design Consultants and Subcontractors and shall require each of them to include similar waivers in their contracts. Collier County shall be responsible for purchasing and maintaining its own liability insurance. Certificates issued as a result of the award of this solicitation must identify "For any and all work performed on behalf of Collier County", or the specific solicitation number/contract number and title. The General Liability Policy provided by Contractor to meet the requirements of this solicitation shall name Collier County, Florida, as an additional insured as to the operations of Contractor under this solicitation and shall contain a severability of interests provisions. The Certificate Holder shall be named as Collier County Board of County Commissioners, OR, Board of County Commissioners in Collier County, OR Collier County Government, OR Collier County. The Certificates of Insurance must state the Contract Number, or Project Number, or specific Project description, or must read: For any and all work performed on behalf of Collier County. The amounts and types of insurance coverage shall conform to the minimum requirements set forth herein with the use of Insurance Services Office (ISO) forms and endorsements or their equivalents. If Contractor has any self-insured retentions or deductibles under any of the below listed minimum required coverage, Contractor must identify on the Certificate of Insurance the nature and amount of such self- insured retentions or deductibles and provide satisfactory evidence of financial responsibility for such obligations. All self-insured retentions or deductibles will be Contractor's sole responsibility. Coverage(s) shall be maintained without interruption from the date of commencement of the Work until the date of completion and acceptance of the scope of work by the County or as specified in this solicitation, whichever is longer. The Contractor and/or its insurance carrier shall provide thirty(30)days written notice to the County of policy cancellation or non-renewal on the part of the insurance carrier or the Contractor. The Contractor shall also notify the County, in a like manner, within twenty-four (24) hours after receipt, of any notices of expiration, cancellation, non-renewal or material change in coverage or limits received by Contractor from its insurer and nothing contained herein shall relieve Contractor of this requirement to provide notice. In the event of a reduction in the aggregate limit of any policy to be provided by Contractor hereunder, Contractor shall immediately take steps to have the aggregate limit reinstated to the full extent permitted under such policy. Should at any time the Contractor not maintain the insurance coverage(s) required herein, the County may terminate the Agreement or at its sole discretion shall be authorized to purchase such coverage(s) and charge the Contractor for such coverage(s) purchased. If Contractor fails to reimburse the County for such costs within thirty (30) days after demand, the County has the right to offset these costs from any amount due Contractor under this Agreement or any other agreement between the County and Contractor. The County shall be under no obligation to purchase such insurance, nor shall it be responsible for the coverage(s) purchased or the insurance company or companies used. The decision of the County to purchase such insurance coverage(s) shall in no way be construed to be a waiver of any of its rights under the Contract Documents. If the initial or any subsequently issued Certificate of Insurance expires prior to the completion of the scope of work,the Contractor shall furnish to the County renewal or replacement Certificate(s)of Insurance not later than ten (10) calendar days after the expiration date on the certificate. Failure of the Contractor to provide the County with such renewal certificate(s) shall be considered justification for the County to terminate any and all contracts. [2024_ver.1] Collier County Florida Insurance and Bonding Requirements Insurance/Bond Type Required Limits 1. ®Worker's Compensation Statutory Limits of Florida Statutes, Chapter 440 and all Federal Government Statutory Limits and Requirements Evidence of Workers' Compensation coverage or a Certificate of Exemption issued by the State of Florida is required.Entities that are formed as Sole Proprietorships shall not be required to provide a proof of exemption.An application for exemption can be obtained online at https://apps.fldfs.com/bocexempt/ 2. ®Employer's Liability $_1,000,000_single limit per occurrence 3. ®Commercial General Bodily Injury and Property Damage Liability(Occurrence Form)patterned after the $_1,000,000 single limit per occurrence, $2,000,000 aggregate for Bodily current ISO form Injury Liability and Property Damage Liability. The General Aggregate Limit Shall be endorsed to apply per project. This shall include Premises and Operations; Independent Contractors; Products and Completed Operations and Contractual Liability. 4. ®Indemnification To the maximum extent permitted by Florida law, the ContractorNendor shall defend,indemnify and hold harmless Collier County,its officers and employees from any and all liabilities, damages, losses and costs, including, but not limited to, reasonable attorneys'fees and paralegals'fees,to the extent caused by the negligence, recklessness,or intentionally wrongful conduct of the Contractor/Vendor or anyone employed or utilized by the ContractorNendor in the performance of this Agreement. 5. ®Automobile Liability $_1,000,000 Each Occurrence; Bodily Injury & Property Damage. Owned/Non-owned/Hired;Automobile Included 6. ❑ Other insurance as ❑Watercraft $ Per Occurrence noted: ❑ United States Longshoreman's and Harborworker's Act coverage shall be maintained where applicable to the completion of the work. $ Per Occurrence ❑ Maritime Coverage (Jones Act) shall be maintained where applicable to the completion of the work. $ Per Occurrence ❑ Aircraft Liability coverage shall be carried in limits of not less than $5,000,000 each occurrence if applicable to the completion of the Services under this Agreement. $ Per Occurrence ❑Pollution $ Per Occurrence ❑Professional Liability $ Per claim&in the aggregate ❑Project Professional Liability $ Per Occurrence ❑Valuable Papers Insurance $ Per Occurrence ❑Cyber Liability $ Per Occurrence 0 Technology Errors&Omissions $ Per Occurrence 7. ® Bid bond Shall be submitted with proposal response in the form of certified funds, cashiers' check or an irrevocable letter of credit,a cash bond posted with the County Clerk,or proposal bond in a sum equal to 5%of the cost proposal. All checks shall be made payable to the Collier County Board of County Commissioners on a bank or trust company located in the State of Florida and insured by the Federal Deposit Insurance Corporation. 8. ®Performance and For projects in excess of $200,000, bonds shall be submitted with the executed Payment Bonds contract by Proposers receiving award, and written for 100%of the Contract award amount, the cost borne by the Proposer receiving an award. The Performance and Payment Bonds shall be underwritten by a surety authorized to do business in the State of Florida and otherwise acceptable to Owner; provided, however, the surety shall be rated as "A-" or better as to general policy holders rating and Class V or higher rating as to financial size category and the amount required shall not exceed 5%of the reported policy holders' surplus, all as reported in the most current Best Key Rating Guide,published by A.M.Best Company,Inc.of 75 Fulton Street,New York,New York 10038. 9. ® Vendor shall ensure that all subcontractors comply with the same insurance requirements that he is required to meet. The same Vendor shall provide County with certificates of insurance meeting the required insurance provisions. 10. ® Collier County must be named as"ADDITIONAL INSURED"on the Insurance Certificate for Commercial General Liability where required.This insurance shall be primary and non-contributory with respect to any other insurance maintained by,or available for the benefit of,the Additional Insured and the Vendor's policy shall be endorsed accordingly. 11. ® The Certificate Holder shall be named as Collier County Board of County Commissioners, OR, Board of County Commissioners in Collier County,OR Collier County Government,OR Collier County. The Certificates of Insurance must state the Contract Number,or Project Number,or specific Project description,or must read: For any and all work performed on behalf of Collier County. 12. ® On all certificates, the Certificate Holder must read: Collier County Board of Commissioners, 3295 Tamiami Trail East,Naples,FL 34112 13. ® Thirty(30)Days Cancellation Notice required. 14. Collier County shall procure and maintain Builders Risk Insurance on all construction projects where it is deemed necessary. Such coverage shall be endorsed to cover the interests of Collier County as well as the Contractor. Premiums shall be billed to the project and the Contractor shall not include Builders Risk premiums in its project proposal or project billings. All questions regarding Builder's Risk Insurance will be addressed by the Collier County Risk Management Division. GG—1/19/2024 Vendor's Insurance Acceptance By submission of the bid Vendor accepts and understands the insurance requirements of these specifications,agrees to maintain these coverages through the duration of the agreement and/or work performance period,and that the evidence of insurability may be required within five(5)days of notification of recommended award of this solicitation. EXHIBIT C RELEASE AND AFFIDAVIT FORM (Template Form Following This Page) 16 Construction Services Agreement:[2024_ver.3] EXHIBIT C: RELEASE AND AFFIDAVIT FORM COUNTY OF ( STATE OF( Before me, the undersigned authority, personally appeared who after being duly sworn, deposes and says: (1) In accordance with the Contract Documents and in consideration of $ to be received, ("Contractor") releases and waives for itself and its subcontractors, material-men, successors and assigns, all claims demands, damages, costs and expenses,whether in contract or in tort, against the Board of County Commissioners of Collier County, Florida, relating in any way to the performance of the Agreement between Contractor and Owner, dated , 20 for the period from to . This partial waiver and release is conditioned upon payment of the consideration described above. It is not effective until said payment is received in paid funds. (2) Contractor certifies for itself and its subcontractors, material-men, successors and assigns, that all charges for labor, materials, supplies, lands, licenses and other expenses for which Owner might be sued or for which a lien or a demand against any payment bond might be filed, shall be fully satisfied and paid upon Owner's payment to Contractor. (3) Contractor agrees to indemnify, defend and save harmless Owner from all demands or suits, actions, claims of liens or other charges filed or asserted against the Owner arising out of the performance by Contractor of the Work covered by this Release and Affidavit. (4) This Release and Affidavit is given in connection with Contractor's[monthly/final]Application for Payment No. Contractor's Signature Name and Title STATE OF COUNTY OF The foregoing instrument was acknowledged before me by means of_ physical presence or_ online notarization, this_day of 20_ by , as of a corporation, on behalf of the corporation. He/She is personally known to me OR has produced identification and did (did not)take an oath. My Commission Expires: (Signature of Notary) (AFFIX OFFICIAL SEAL) (Legibly Printed) Notary Public, State of Commission No.: [2024_ver.1] EXHIBIT D-1 CONTRACTOR APPLICATION FOR PAYMENT FORM (Template Form Following This Page) 17 Construction Services Agreement:[2024_ver.3) EXHIBIT D-1 FORM OF CONTRACT APPLICATION FOR PAYMENT Collier County Board of County Commissioners(the OWNER) or Collier County Water-Sewer Owner's Project Bid No. Manager's Name: Project No. County's Division Name Purchase Order No. Submitted by Contractor Application Date: Representative: Name Contractor's Name& Payment Application No. Address: Original Contract Time: Original Contract Price: $ Revised Contract Time: Total Change Orders to Date: $ Revised Contract Amount: $ Total Value of Work Completed & $ Stored to Date: Retainage ©5% $ Retainage @ 5% through [Insert $ through [Insert Date] date] Retainage @ % $ Less Retainage $ after[Insert date] Total Earned Less Retainage $ Less previous payment(s) Percent Work Completed % AMOUNT DUE THIS $ to Date: APPLICATION: Percent Contract Time Completed to Date: Liquidated Damages to $ Remaining Contract Balance $ Be Accrued ATTACH SCHEDULE OF VALUES AND ACCOMPANYING DOCUMENTATION TO THIS APPLICATION CONTRACTOR'S CERTIFICATION: The undersigned CONTRACTOR certifies that: (1) all previous progress payments received from OWNER on account of Work done under the Contract referred to above have been applied to discharge in full all obligations of CONTRACTOR incurred in connection with Work covered by prior Applications for Payment numbered 1 through inclusive; (2) title to all materials and equipment incorporated in said Work or otherwise listed in or covered by this Application for Payment will pass to OWNER at time of payment free and clear of all liens, claims, security interests and encumbrances(except such as covered by Bond acceptable to OWNER); (3) all amounts have been paid for work which previous payments were issued and received from the OWNER and that current payment is now due; and (4) CONTRACTOR has only included amounts in this Application for Payment properly due and owing and CONTRACTOR has not included within the above referenced amount any claims for unauthorized or changed Work that has not been properly approved by Owner in writing and in advance of such Work. Contractor's Name Contractor's Signature: Date: Type Title: Shall be signed by an authorized representative of the Contractor. Payment to the CONTRACTOR for the above AMOUNT DUE THIS APPLICATION is recommended by: Design Professional's Name: Signature: Date: Payment to the CONTRACTOR for the above AMOUNT DUE THIS APPLICATION is recommended by: Owner's Project Manager Name: Signature: Date: [2024_ver.11 EXHIBIT D-2 SCHEDULE OF VALUES (Template Form Following This Page) 18 Construction Services Agreement:[2024_ver.3] U ❑ % J• Q w 0 ).. z 2 2 .c 1_ F N IX 3 -c •arI N a 0 a) w -4 m ' Z .7o tu of w 'o ID '.. C. U.1 CZ O c Q c e z V N Q c ~LLI C) I w O N i0 a w 2 w U f/) w QzQ Z o w n is m O CO w - m 2 E IL o • O Z Z F C F- r w J w ❑ U a m a o a a 0 02 . c. L D. ❑ 0 Q- w w H J m Q m OF O ❑ a w O 2 o N N 7 )/) 3 N ❑• > w Q y G V- re N W "' O Ow a N Q m e .2 k a c N w y m a .7 N N U f/) p U 0 O Y N Q_ a.,U U 2 a' F- w a c a N N 8a O °a ui O H m n J z ~ N CU L a 2 0 Q❑ m en N 0U Q Z w 0 r K J Fn- ? 0 a. Q g m w = r a N O QO a LL U 7, N y ❑ t. 0 J w =❑ > > 3 U w Q p in 2 > _ U m N y E `o c II z t0 N O _ N a a ri o N• U >.« fn 2?w❑ 0 m c N w om E 0 E z z CCo w m p Li w g v E cc z o a u EXHIBIT D-3 STORED MATERIALS (Template Form Following This Page) 19 Construction Services Agreement:[2024_ver.3] / 2 q \ • zr L.: _J IZ , • • • @ ( E § \ -I § a z • • • § / § ) i § \ §• • 2 k / ] a § c L ® > _ e u � O I §111 2 ƒ Aa 0 - e � -J Q / § § 7o � b c w 3 � i ] / Lu § ] _ § 3 $ \ \ m \ ) 0 0 - a. § 2 C § ƒ § L « 0 c ƒ EXHIBIT E-1: CHANGE ORDER (Template Form Following This Page) 20 Construction Services Agreement:[2024_ver.3] Co xr County Procurement Services Change Order Form Contract# CO# PO# Project#: Project Name: Contractor/Consultant Name: Select One: ❑ Contract Modification(Construction or Project Specific) El Work Order Modification Project Manager Name: Division Name: Original Contract/Work Order Amount Original BCC Approval Date;Agenda Item# Current BCC Approved Amount Last BCC Approval Date; Agenda Item# Current Contract/Work Order Amount SAP Contract Expiration Date(MASTER) Dollar Amount of this Change o.00°%o Total%Change from Original Amount Revised Contract/Work Order Total $o.00 o.00°i %Change from Current BCC Approved Amount Total Cumulative Changes $o.00 o.00%o % Change from Current Amount Notice to Proceed Original NTP Original Final Last Final Date #of Days Completion Date Approved Date #of Days Added Revised Final Date Current Substantial Completion Date (includes this change) (if applicable) Provide responses after each question in box below (Responses should be brief and specific). Attach additional information and/or documentation from the Design Professional and/or Contractor, if needed, with your submission of this Change Order and complete summary on next page. Check all that apply to this Change Order request: El Add Time; ❑Add funds; ❑ Use of Allowance; El Modify/Delete existing Task(s); ❑Add new Task(s); El Reallocate funds; El Other(must be explained in detail below) 1.) Detail of change/s to be made through this Change Order. 2.) If this Change Order is currently under a Stop Work, please identify the date issued and number of days remaining or "N/A" if not applicable. 3.) Explain why this change was not included in the original contract/Work Order. 4.) Describe the impact if this change is not processed. Page 1 of 4 Change Order Form(2024_ver.1) Cott County Procurement Services Change Order Form Contract# CO# PO# Project#: Project Name: Contractor/Consultant Name: Change Order/Amendment Summary (If additional spaces needed, attached a separate Summary page to this amendment request) COST TIME CO# AMD# Description Additive Deductive Days Total New Justification (+) (-) Added Time ❑ Check here if additional summary page/s are attached to this Change Order Page 2 of 4 Change Order Form(2023_ver.1) Co ter County Procurement Services Change Order Form Contract# CO# PO# Project#: Project Name: Contractor/Consultant Name: Acceptance of this Change Order shall constitute a modification to contract/work order identified above and will be subject to all the same terms and conditions as contained in the contract/work order indicated above,as fully as if the same were stated in this acceptance. The adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor/Vendor/Consultant/Design Professional arising out of or related to the change set forth herein, including claims for impact and delay costs. Contractor/Consultant/Design Professional signature below must be from an authorized person/officer/director of the Company or listed as the qualified licensed Professional"Project Coordinator"or Design/Engineer Professional under the agreement. Signature authority of person signing will be verified through the contract OR through the Florida Department of State, Division of Corporations (Sunbiz) website (https://dos.myflorida.com%sunbiz/search/). If the person signing is not listed, we will require signature authority by one of the listed officers/directors of the company giving that person signature authority. Prepared by: Date: Signature-Division Project Manager Printed Name Accepted by: Date: Signature-Design/Engineer Professional(if applicable) Printed Name/Title/Company Name Accepted by: Date: Signature-Contractor/Consultant/Vendor Printed Name/Title/Company Name Approved by: Date: Signature-Division Manager or Designee(Optional) Printed Name Approved by: Date: Signature-Division Director or Designee(Optional) Printed Name Approved by: Date: Signature-Division Administrator or Designee(Optional) Printed Name Page 3 of 4 Change Order Form(2024_ver.1) Cotter County Procurement Services Change Order Form Contract# CO# PO# Project#: Project Name: Contractor/Consultant Name: FOR PROCURMENT USE ONLY FY_ CHO Request# Approved by: Signature-Procurement Professional Signature/Date Approved by: Signature-Procurement Manager/Director(OPTIONAL) APPROVAL TYPE: ❑ Administrative ❑ Administrative-BCC Report ❑ BCC Stand-Alone ES (BCC Approval Required) BCC APPROVAL ATTEST: Crystal K. Kinzel, Clerk of the Circuit Court BOARD OF COUNTY COMMISSIONERS and Comptroller COLLIER COUNTY, FLORIDA By: By: , Chairman Dated: Date: (SEAL) Agenda# Approved as to Form and Legality: Deputy County Attorney Print Name Page 4 of 4 Change Order Form(2024_ver.1) EXHIBIT E-2: WORK DIRECTIVE FORM (Template Form Following This Paqe) 21 Construction Services Agreement:[2024_ver.3] EXHIBIT E-2 WORK DIRECTIVE CHANGE PROJECT NAME: CHANGE # DATE OF ISSUANCE: EFFECTIVE DATE: OWNER: Collier County Board of Commissioners PROJECT#: CONTRACTOR: ENGINEER: You are directed to proceed promptly with the following change(s): Description: Purpose of Work Directive Change: Attachments: If a claim is made that the above change(s)have affected Contract amount or Contract Times any claim for a Change Order based thereon will involve one or more of the following methods of determining the effect of the changes(s). Method of determining change in Contract amount: Method of determining change in Contract Times: ❑ Unit Prices ❑ CONTRACTOR's records ❑ Lump Sum E Engineer's record ❑ Other ❑ Other A not-to-exceed itemized estimated increase Estimated change in Contract Time: (decrease)in Contract amount: $ Increase or decrease by calendar days. RECOMMENDED: AUTHORIZED: By: By: Engineer/Design Professional Owner's Representative [2024 ver.1] EXHIBIT F-1 CERTIFICATE OF SUBSTANTIAL COMPLETION FORM (Template Form Following This Page) 22 Construction Services Agreement:[2024_ver.3] EXHIBIT F-1 CERTIFICATE OF SUBSTANTIAL COMPLETION OWNER'S Project No. Design Professional Project No. PROJECT: CONTRACTOR Contract For Contract Date This Certificate of Substantial completion applies to all Work under the Contract documents or to the following specified parts thereof: To OWNER And To Substantial Completion is the state in the progress of the Work when the Work (or designated portion) is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use. The Work to which this Certificate applies has been inspected by authorized representatives of OWNER, CONTRACTOR AND DESIGN PROFESSIONAL, and that Work is hereby declared to be substantially complete in accordance with the requirements of the Contract Documents on: DATE OF SUBSTANTIAL COMPLETION [2024_ver.1] This list may not be all-inclusive, and the failure to include an item in it does not alter the responsibility of CONTRACTOR to complete all the Work in accordance with the Contract Documents. The items in the final punch list shall be completed or corrected by CONTRACTOR within days of the above date of Substantial Completion and Contractor shall provide Owner with written notice that all punch list items have been completed. The responsibilities between OWNER and CONTRACTOR for security, operation, safety, maintenance, heat, utilities, insurance, and warranties shall be as follows: RESPONSIBILITIES: OWNER: CONTRACTOR: The following documents are attached to and made a part of this Certificate: This certificate does not constitute an acceptance of Work not in accordance with the Contract Documents nor is it a release of CONTRACTOR'S obligation to complete the Work in accordance with the Contract Documents. Executed by Design Professional on , 20 Signature of Design Professional Type Name and Title CONTRACTOR accepts this Certificate of Substantial Completion on , 20_ and will submit within five calendar days, an approved pay application to bccapclerkcollierclerk.com. The pay application will include regular schedule of value scope work to be billed and all work to be billed for all change orders. Signature of Contractor Type Name and Title OWNER accepts this Certificate of Substantial Completion on , 20 Signature of Owner Type Name and Title [2024_ver.1] EXHIBIT F-2 CERTIFICATE OF FINAL COMPLETION FORM (Template Form Following This Page) 23 Construction Services Agreement:[2024_ver.3] EXHIBIT F-2 CERTIFICATE OF FINAL COMPLETION OWNER'S Project No. Design Professional Project No. PROJECT: CONTRACTOR Contract For Contract Date This Certificate of Final completion applies to all Work under the Contract documents. The warranty in Exhibit G-2 is attached to and made a part of this Certificate. To OWNER And To The Work to which this Certificate applies has been inspected by authorized representatives of OWNER, CONTRACTOR AND DESIGN PROFESSIONAL, and that Work is hereby declared to be finally complete in accordance with the contract documents on: DATE OF FINAL COMPLETION [2024_ver.1] Intentionally left blank Executed by Design Professional on , 20 Signature of Design Professional Type Name and Title CONTRACTOR accepts this Certificate of Final Substantial on this , 20_ Signature of Contractor Type Name and Title OWNER accepts this Certificate of Final Substantial on this , 20 Signature of Owner Type Name and Title [2024_ver.1] EXHIBIT F-3 PUNCH LIST FORM (Template Form Following This Page) 24 Construction Services Agreement:[2024_ver.3] EXHIBIT F-3 PUNCH LIST FORM Item Description Value Completion Date Dated Approved No. by Owner Subtotal x 150% [2024_ver.1] EXHIBIT G-1 FINAL PAYMENT CHECKLIST (Template Form Following This Page) 25 Construction Services Agreement:[2024_ver.3] EXHIBIT G-1: FINAL PAYMENT CHECKLIST Bid No.: Project No.: PO No. _ Date: Contractor: The following items have been secured by the for the Project known as and have been reviewed and found to comply with the requirements of the Contract Documents. Original Contract Amount: Final Contract Amount: Commencement Date: Substantial Completion Time as set forth in the Agreement: Calendar Days. Actual Date of Substantial Completion: Final Completion Time as set forth in the Agreement: Calendar Days. Actual Final Completion Date: YES NO Q 1. All Punch List items completed on I I I-1 2. Warranties and Guarantees assigned to Owner(attach to this form). 3. Effective date of General one year warranty from Contractor is: � 0 4. 2 copies of Operation and Maintenance manuals for equipment and system submitted (list manuals in attachment to this form). I I 5. As-Built drawings obtained and dated: 6. Owner personnel trained on system and equipment operation. 7. Certificate of Occupancy No.: issued on (attach to this form). I 1 EE 8. Certificate of Substantial Completion issued on 9. Final Payment Application and Affidavits received from Contractor on: Hr—i 10. Consent of Surety received on 11. Operating Department personnel notified Project is in operating phase. 12. All Spare Parts or Special Tools provided to Owner: 13. Finished Floor Elevation Certificate provided to Owner: (� 14. Other: If any of the above is not applicable, indicate by N/A. If NO is checked for any of the above, attach explanation. Acknowledgments: Executed by Design Professional on , 20 Signature of Design Professional Type Name and Title Executed by Contractor on , 20 Signature of Contractor Type Name and Title Executed by Owner on , 20 Signature of Owner Type Name and Title [2024_ver.1] EXHIBIT G-2 WARRANTY (Template Form Following This Page) 26 Construction Services Agreement:[2024_ver.3] EXHIBIT G-2 WARRANTY In consideration of ten dollars, ($10.00), receipt of which is hereby acknowledged, the undersigned CONTRACTOR does hereby provide, warrant and guarantee all work done and executed under the contract either directly performed by the CONTRACTOR or at the express request of the CONTRACTOR by a SUBCONTRACTOR or CONSULTANT. Project Name: Date of Substantial Completion: Name and Address of CONTRACTOR: CONTRACTOR warrants and guarantees the work performed pursuant to the contract shall be free of all defects of materials and workmanship for a period of one year from the DATE OF SUBSTANTIAL COMPLETION. The undersigned party further agrees that it will, at its own expense, replace and/or repair all defective work and materials and all other work damaged by any defective work upon written demand by the COUNTY. It is further understood that further consideration for this warranty and guaranty is the consideration given for the requirement pursuant to the general conditions and specifications under which the contract was let that such warranty and guaranty would be given. This warranty and guaranty is in addition to any other warranties or guaranties for the work performed under the contract and does not constitute a waiver of any rights provided pursuant to Florida Statutes, Chapter 95, et seq. CONTRACTOR: WITNESS: Signature Signature Name Printed and Title Name Printed [2024_ver.1] EXHIBIT H: GENERAL TERMS AND CONDITIONS 1. INTENT OF CONTRACT DOCUMENTS. 1.1 It is the intent of the Contract Documents to describe a functionally complete Project (or portion thereof) to be constructed in accordance with the Contract Documents. Any work, materials or equipment that may reasonably be inferred from the Contract Documents as being required to produce the intended result shall be supplied whether or not specifically called for. When words which have a well-known technical or trade meaning are used to describe work, materials or equipment, such words shall be interpreted in accordance with that meaning. Reference to standard specifications, manuals or codes of any technical society, organization, or association or to the laws or regulations of any governmental authority having jurisdiction over the Project, whether such reference be specific or by implication, shall mean the latest standard specification, manual, code, law or regulation in effect at the time the Work is performed, except as may be otherwise specifically stated herein. 1.2 If before or during the performance of the Work Contractor discovers a conflict, error or discrepancy in the Contract Documents, Contractor immediately shall report same to the Project Manager in writing and before proceeding with the Work affected thereby shall obtain a written interpretation or clarification from the Project Manager; said interpretation or clarification from the Project Manager may require Contractor to consult directly with Design Professional or some other third party, as directed by Project Manager. Contractor shall take field measurements and verify field conditions and shall carefully compare such field measurements and conditions and other information known to Contractor with the Contract Documents before commencing any portion of the Work. 1.3 Drawings are intended to show general arrangements, design and extent of Work and are not intended to serve as shop drawings. Specifications are separated into divisions for convenience of reference only and shall not be interpreted as establishing divisions for the Work, trades, subcontracts, or extent of any part of the Work. In the event of a discrepancy between or among the drawings, specifications or other Contract Document provisions, Contractor shall be required to comply with the provision which is the more restrictive or stringent requirement upon the Contractor, as determined by the Project Manager. Unless otherwise specifically mentioned, all anchors, bolts, screws, fittings, fillers, hardware, accessories, trim and other parts required in connection with any portion of the Work to make a complete, serviceable, finished and first quality installation shall be furnished and installed as part of the Work, whether or not called for by the Contract Documents. 2. INVESTIGATION AND UTILITIES. 2.1 Subject to Section 2.3 below, Contractor shall have the sole responsibility of satisfying itself concerning the nature and location of the Work and the general and local conditions, and particularly, but without limitation, with respect to the following: those affecting transportation, access, disposal, handling and storage of materials; availability and quality of labor; water and electric power; availability and condition of roads; work area; living facilities; climatic conditions and seasons; physical conditions at the work-site and the project area as a whole; topography and ground surface conditions; nature and quantity of the surface materials to be encountered; subsurface conditions; equipment and facilities needed preliminary to and during performance of the Work; and all other costs associated with such performance. The failure of Contractor to acquaint itself with any applicable conditions shall not relieve Contractor from any of its responsibilities to perform under the Contract Documents, nor shall it be considered the basis for any claim for additional time or compensation. 27 Construction Services Agreement:[2024_ver.3] 2.2 Contractor shall locate all existing roadways, railways, drainage facilities and utility services above, upon, or under the Project site, said roadways, railways, drainage facilities and utilities being referred to in this Sub-Section 2.2 as the"Utilities". Contractor shall contact the owners of all Utilities to determine the necessity for relocating or temporarily interrupting any Utilities during the construction of the Project. Contractor shall schedule and coordinate its Work around any such relocation or temporary service interruption. Contractor shall be responsible for properly shoring, supporting, and protecting all Utilities at all times during the course of the Work. The Contractor is responsible for coordinating all other utility work so as to not interfere with the prosecution of the Work (except those utilities to be coordinated by the Owner as may be expressly described elsewhere in the Contract Documents). 2.3 Notwithstanding anything in the Contract Documents to the contrary, if conditions are encountered at the Project site which are (i) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (ii) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, and which reasonably should not have been discovered by Contractor as part of its scope of site investigative services required pursuant to the terms of the Contract Documents, then Contractor shall provide Owner with prompt written notice thereof before conditions are disturbed and in no event later than three (3) calendar days after first observance of such conditions. Owner and Design Professional shall promptly investigate such conditions and, if they differ materially and cause an increase or decrease in Contractor's cost of, or time required for, performance of any part of the Work, Owner will acknowledge and agree to an equitable adjustment to Contractor's compensation or time for performance, or both, for such Work. If Owner determines that the conditions at the site are not materially different from those indicated in the Contract Documents or not of an unusual nature or should have been discovered by Contractor as part of its investigative services, and that no change in the terms of the Agreement is justified, Owner shall so notify Contractor in writing, stating its reasons. Claims by Contractor in opposition to such determination by Owner must be made within seven (7) calendar days after Contractor's receipt of Owner's written determination notice. If Owner and Contractor cannot agree on an adjustment to Contractor's cost or time of performance, the dispute resolution procedure set forth in the Contract Documents shall be complied with by the parties. 3. SCHEDULE. 3.1 The Contractor, within ten (10)calendar days after the Board's award of the Agreement, shall prepare and submit to Project Manager, for their review and approval, a progress schedule for the Project (herein "Progress Schedule"). The Progress Schedule shall relate to all Work required by the Contract Documents and shall utilize the Critical Path method of scheduling and shall provide for expeditious and practicable execution of the Work within the Contract Time. The Progress Schedule shall indicate the dates for starting and completing the various stages of the Work. 3.2 The Progress Schedule shall be updated monthly by the Contractor. All monthly updates to the Progress Schedule shall be subject to the Project Manager's review and approval. Contractor shall submit the updates to the Progress Schedule with its monthly Applications for Payment noted below. The Project Manager's review and approval of the submitted Progress Schedule updates shall be a condition precedent to the Owner's obligation to pay Contractor. 3.3 All work under this Agreement shall be performed in accordance with the requirements of all Collier County Noise Ordinances then in effect. Unless otherwise specified, work will generally be 28 Construction Services Agreement:[2024_ver.3] limited to the hours of 7 a.m. to 7 p.m., Monday through Saturday. No work shall be performed outside the specified hours without the prior approval of the Project Manager. 4. PROGRESS PAYMENTS. 4.1 At least ten (10) days prior to submitting the monthly Application for Payment, the Contractor shall submit to the Project Manager a final Schedule of Values. The Schedule of Values shall be satisfactory in form and substance to the Project Manager and shall subdivide the Work into component parts in sufficient detail to serve as the basis for measuring quantities in place and calculating amounts for the Contractor's monthly progress payments during construction. Further, it shall include the list of its Subcontractors and materialmen submitted with its Bid showing the work and materials involved and the dollar amount of each subcontract and purchase order. Contractor acknowledges and agrees that any modifications to the list of Subcontractors submitted with Contractor's Bid and any subsequently identified Subcontractors are subject to Owner's prior written approval. Unsupported or unreasonable allocation of the Contract Price to any one activity shall be justification for rejection of the Schedule of Values. The Contractor shall not submit an unbalanced Schedule of Values which provides for overpayment to the Contractor on activities that would be performed first. The Schedule of Values shall be revised and resubmitted until acceptable to the Project Manager. Once the schedule has been accepted by the Project Manager, the Owner reserves the right (at its option) throughout the Contract to require that the Contractor honor a particular price contained in the Schedule of Values, if the activity pertaining to it is being deleted or modified. Upon approval of the Schedule of Values by the Project Manager, it shall be incorporated into the form of Application for Payment attached to the Agreement as Exhibit D and shall be used as the basis for the Contractor's monthly Applications for Payment. The schedule shall be updated and submitted each month along with a completed copy of the Application for Payment form signed by the Contractor's authorized representative. 4.2 The first Application for Payment shall be submitted no earlier than thirty (30) days after the Commencement Date, and monthly thereafter, but not more often than once a month or prior to substantial completion being met. Notwithstanding anything herein to the contrary, if approved by Owner in its sole discretion, Contractor may submit its invoice for any required Payment and Performance Bonds prior to the first Application of Payment provided that Contractor has furnished Owner certified copies of the receipts evidencing the premium paid by Contractor for the bonds. 4.3 Unless expressly approved by Owner in advance and in writing, said approval at Owner's sole discretion, Owner is not required to make any payment for materials or equipment that have not been incorporated into the Project. If payment is requested on the basis of materials and equipment not incorporated into the Project, but delivered and suitably stored at the site or at another location agreed to by the Owner in writing, the Application for Payment shall also be accompanied by a bill of sale, invoice or other documentation warranting that the Owner has received the materials and equipment free and clear of all liens, charges, security interests and encumbrances, together with evidence that the materials and equipment are covered by appropriate property insurance and other arrangements to protect Owner's interest therein, all of which shall be subject to the Owner's satisfaction. Thereafter, with each Application for Payment, Contractor also shall complete and submit to Owner as part of its Application for Payment, the Stored Materials Record form attached hereto and made a part hereof as Exhibit D-3. 29 Construction Services Agreement:[2024_ver.3] 4.4 Contractor shall submit its monthly Application for Payment to the Project Manager or his or her designee, as directed by Owner (which designee may include the Design Professional). Within twenty (20) business days after the date of each Application for Payment is stamped as received, and within the timeframes set forth in Section 218.735 F.S., the Project Manager, or Design Professional, shall either: (1) Indicate its approval of the requested payment; (2) indicate its approval of only a portion of the requested payment, stating in writing its reasons therefor; or (3) return the Application for Payment to the Contractor indicating, in writing, the reason for refusing to approve payment. Payments of proper invoices shall be processed in accordance with Section 218.735, F.S. and the terms of the Contract Documents. 4.5 In the event of a total denial by Owner and return of the Application for Payment by the Project Manager, the Contractor may make the necessary corrections and re-submit the Application for Payment. The Owner shall, within ten (10) business days after the Application for Payment is stamped and received and after Project Manager approval of an Application for Payment, pay the Contractor the amounts so approved. 4.6 Owner shall withhold retainage on the gross amount of each monthly progress payment in the amount of five percent (5%), as permitted by Section 255.078, Florida Statutes. The foregoing does not prohibit Owner from withholding retainage at a rate less than five percent (5%) of each monthly progress payment as otherwise allowable under Section 255.078, Florida Statutes. Any reduction in retainage below the maximum amount set forth in Section 255.078, Florida Statutes shall be at the sole discretion of the Owner. Such retainage shall be accumulated and not released to Contractor until final payment is due unless otherwise agreed to by the Owner in accordance with Florida Statute 255.078. Any interest earned on retainage shall accrue to the benefit of the Owner. 4.7 Monthly payments to Contractor shall in no way imply approval or acceptance of Contractor's Work. 4.8 Each Application for Payment, subsequent to the first pay application, shall be accompanied by a Release and Affidavit, in the form attached as Exhibit C, acknowledging Contractor's receipt of payment in full for all materials, labor, equipment and other bills that are then due and payable by Owner with respect to the current Application for Payment. Further, to the extent directed by Owner and in Owner's sole discretion, Contractor shall also submit a Release and Affidavit from each Subcontractor, sub-subcontractor, or supplier in the form attached as Exhibit C acknowledging that each Subcontractor, sub-subcontractor, or supplier has been paid in full through the previous month's Application for Payment. The Owner shall not be required to make payment until and unless these affidavits are furnished by Contractor. 4.9 Contractor agrees and understands that funding limitations exist and that the expenditure of funds must be spread over the duration of the Project at regular intervals based on the Contract Amount and Progress Schedule. 4.10 Notwithstanding anything in the Contract Documents to the contrary, Contractor acknowledges and agrees that in the event of a dispute concerning payments for Work performed under this Agreement, Contractor shall continue to perform the Work required of it under this Agreement pending resolution of the dispute provided that Owner continues to pay Contractor all amounts that Owner does not dispute are due and payable. 4.11 Payments will be made for services furnished, delivered, and accepted, upon receipt and approval of invoices submitted on the date of services or within six (6) months after completion of contract. Any untimely submission of invoices beyond the specified deadline period is subject to non- 30 Construction Services Agreement:[2024_ver.3] payment under the legal doctrine of "laches" as untimely submitted. Time shall be deemed of the essence with respect to the timely submission of invoices under this agreement. 4.12 The Owner may, at its discretion, use VISA/MASTER card credit network as a payment vehicle for goods and/or services purchased as a part of this contract. The Owner may not accept any additional surcharges (credit card transaction fees) as a result of using the Owner's credit card for transactions relating to this agreement. 5. PAYMENTS WITHHELD. 5.1 The Project Manager may decline to approve any Application for Payment, or portions thereof, because of subsequently discovered evidence or subsequent inspections that reveal non- compliance with the Contract Documents. The Project Manager may nullify the whole or any part of any approval for payment previously issued and Owner may withhold any payments otherwise due Contractor under this Agreement or any other agreement between Owner and Contractor, to such extent as may be necessary in the Owner's opinion to protect it from loss because of: (a) Defective Work not remedied; (b)third party claims filed or reasonable evidence indicating probable filing of such claims; (c) failure of Contractor to make payment properly to subcontractors or for labor, materials or equipment; (d) reasonable doubt that the Work can be completed for the unpaid balance of the Contract Amount; (e) reasonable indication that the Work will not be completed within the Contract Time; (f) unsatisfactory prosecution of the Work by the Contractor; or (g) any other material breach of the Contract Documents by Contractor. 5.2 If any conditions described in 5.1. are not remedied or removed, Owner may, after three (3) days written notice, rectify the same at Contractor's expense. Provided however, in the event of an emergency, Owner shall not be required to provide Contractor any written notice prior to rectifying the situation at Contractor's expense. Owner also may offset against any sums due Contractor the amount of any liquidated or non-liquidated obligations of Contractor to Owner, whether relating to or arising out of this Agreement or any other agreement between Contractor and Owner. 5.3 In instances where the Contractor may owe debts (including, but not limited to taxes or other fees) to Collier County and the contractor has not satisfied nor made arrangement to satisfy these debts, the County reserves the right to off-set the amount owed to the County by applying the amount owed to the vendor or contractor for services performed of for materials delivered in association with a contract. 5.4 If a subcontractor is a related entity to the Contractor, then the Contractor shall not mark-up the subcontractor's fees. A related entity shall be defined as any Parent or Subsidiary of the Company and any business, corporation, partnership, limited liability company or other entity in which the Company or a Parent or a Subsidiary of the Company holds any ownership interest, directly or indirectly. 6. FINAL PAYMENT. 6.1 Owner shall make Final Payment to Contractor in accordance with Section 218.735, F.S. and the terms of the Contract Documents after the Work is finally inspected and accepted by Project Manager as set forth with Section 20.1 herein, provided that Contractor first, and as an explicit condition precedent to the accrual of Contractor's right to Final Payment, shall have furnished Owner with a properly executed and notarized copy of the Release and Affidavit form attached as Exhibit C, as well as, a duly executed copy of the Surety's consent to Final Payment and such other 31 Construction Services Agreement:[2024_ver.3] documentation that may be required by the Contract Documents and the Owner. Prior to release of Final Payment and final retainage, the Contractor's Representative and the Project Manager shall jointly complete the Final Acceptance and Final Payment Checklist, a representative copy of which is attached to this Agreement as Exhibit G. 6.2 Contractor's acceptance of final payment shall constitute a full waiver of any and all claims by Contractor against Owner arising out of this Agreement or otherwise relating to the Project, except those previously made in writing in accordance with the requirements of the Contract Documents and identified by Contractor as unsettled in its final Application for Payment. Neither the acceptance of the Work nor payment by Owner shall be deemed to be a waiver of Owner's right to enforce any obligations of Contractor hereunder or to the recovery of damages for defective Work not discovered by the Design Professional or Project Manager at the time of final inspection. 7. SUBMITTALS AND SUBSTITUTIONS. 7.1 Contractor shall carefully examine the Contract Documents for all requirements for approval of materials to be submitted such as shop drawings, data, test results, schedules and samples. Contractor shall submit all such materials at its own expense and in such form as required by the Contract Documents in sufficient time to prevent any delay in the delivery of such materials and the installation thereof. 7.2 Whenever materials or equipment are specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular supplier, the naming of the item is intended to establish the type, function and quality required. Unless the name is followed by words indicating that no substitution is permitted, materials or equipment of other suppliers may be accepted by Owner if sufficient information is submitted by Contractor to allow the Owner to determine that the material or equipment proposed is equivalent or equal to that named. Requests for review of substitute items of material and equipment will not be accepted by Owner from anyone other than Contractor and all such requests must be submitted by Contractor to Project Manager within thirty (30) calendar days after Notice to Proceed is received by Contractor, unless otherwise mutually agreed in writing by Owner and Contractor. 7.3 If Contractor wishes to furnish or use a substitute item of material or equipment, Contractor shall make application to the Project Manager for acceptance thereof, certifying that the proposed substitute shall adequately perform the functions and achieve the results called for by the general design, be similar and of equal substance to that specified and be suited to the same use as that specified. The application shall state that the evaluation and acceptance of the proposed substitute will not prejudice Contractor's achievement of substantial completion on time, whether or not acceptance of the substitute for use in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with Owner for the Project) to adapt the design to the proposed substitute and whether or not incorporation or use by the substitute in connection with the Work is subject to payment of any license fee or royalty. All variations of the proposed substitute from that specified will be identified in the application and available maintenance, repair and replacement service shall be indicated. The application also shall contain an itemized estimate of all costs that will result directly or indirectly from acceptance of such substitute, including costs for redesign and claims of other contractors affected by the resulting change, all of which shall be considered by the Project Manager in evaluating the proposed substitute. The Project Manager may require Contractor to furnish at Contractor's expense additional data about the proposed substitute. 32 Construction Services Agreement:[2024_ver.3] 7.4 If a specific means, method, technique, sequence or procedure of construction is indicated in or required by the Contract Documents, Contractor may furnish or utilize a substitute means, method, sequence, technique or procedure of construction acceptable to the Project Manager, if Contractor submits sufficient information to allow the Project Manager to determine that the substitute proposed is equivalent to that indicated or required by the Contract Documents. The procedures for submission to and review by the Project Manager shall be the same as those provided herein for substitute materials and equipment. 7.5 The Project Manager shall be allowed a reasonable time within which to evaluate each proposed substitute and, if need be, to consult with the Design Professional. No substitute will be ordered, installed or utilized without the Project Manager's prior written acceptance which shall be evidenced by a Change Order, a Work Directive Change, a Field Order or an approved Shop Drawing. The Owner may require Contractor to furnish at Contractor's expense a special performance guarantee or other surety with respect to any substitute. The Project Manager will record time required by the Project Manager and the Project Manager's consultants in evaluating substitutions proposed by Contractor and making changes in the Contract Documents occasioned thereby. Whether or not the Owner accepts a proposed substitute, Contractor shall reimburse Owner for the charges of the Design Professional and the Design Professional's consultants for evaluating each proposed substitute. 8. DAILY REPORTS, SIGNED AND SEALED AS-BUILTS AND MEETINGS. 8.1 Unless waived in writing by Owner, Contractor shall complete and submit to Project Manager on a weekly basis a daily log of the Contractor's work for the preceding week in a format approved by the Project Manager. The daily log shall document all activities of Contractor at the Project site including, but not limited to, the following: 8.1.1 Weather conditions showing the high and low temperatures during work hours, the amount of precipitation received on the Project site, and any other weather conditions which adversely affect the Work; 8.1.2 Soil conditions which adversely affect the Work; 8.1.3 The hours of operation by Contractor's and Sub-Contractor's personnel; 8.1.4 The number of Contractor's and Sub-Contractor's personnel present and working at the Project site, by subcontract and trade; 8.1.5 All equipment present at the Project site, description of equipment use and designation of time equipment was used (specifically indicating any down time); 8.1.6 Description of Work being performed at the Project site; 8.1.7 Any unusual or special occurrences at the Project site; 8.1.8 Materials received at the Project site; 8.1.9 A list of all visitors to the Project 8.1.10 Any problems that might impact either the cost or quality of the Work or the time of performance. 33 Construction Services Agreement:[2024_ver.3] The daily log shall not constitute nor take the place of any notice required to be given by Contractor to Owner pursuant to the Contract Documents. 8.2 Contractor shall maintain in a safe place at the Project site one record copy of the Contract Documents, including, but not limited to, all drawings, specifications, addenda, amendments, Change Orders, Work Directive Changes and Field Orders, as well as all written interpretations and clarifications issued by the Design Professional, in good order and annotated to show all changes made during construction. The annotated drawings shall be continuously updated by the Contractor throughout the prosecution of the Work to accurately reflect all field changes that are made to adapt the Work to field conditions, changes resulting from Change Orders, Work Directive Changes and Field Orders, and all concealed and buried installations of piping, conduit, and utility services. All buried and concealed items, both inside and outside the Project site, shall be accurately located on the annotated drawings as to depth and in relationship to not less than two (2) permanent features (e.g. interior or exterior wall faces). The annotated drawings shall be clean, and all changes, corrections and dimensions shall be given in a neat and legible manner in a contrasting color. The "As-Built" record documents, together with all approved samples and a counterpart of all approved shop drawings shall be available to the Project Manager or Design Professional for reference. Upon completion of the Work and as a condition precedent to Contractor's entitlement to final payment, these "As-Built" record documents, samples and shop drawings shall be delivered to Project Manager by Contractor for Owner. 8.3 Contractor shall keep all records and supporting documentation, which concern or relate to the Work hereunder for a minimum of five (5) years from the date of termination of this Agreement or the date the Project is completed, or such longer period as may be required by law, whichever is later, pursuant to Florida Public Records Law Chapter 119 and comply with specifically those contractual requirements in 119.0701(2)(a)-(b) as follows: IF THE CONTRACTOR HAS QUESTIONS REGARDING THE APPLICATION OF CHAPTER 119, FLORIDA STATUTES, TO THE CONTRACTOR'S DUTY TO PROVIDE PUBLIC RECORDS RELATING TO THIS CONTRACT, CONTACT THE CUSTODIAN OF PUBLIC RECORDS AT: Division of Communications, Government and Public Affairs 3299 Tamiami Trail East, Suite 102 Naples, FL 34112-5746 Telephone: (239) 252-8999 Email: PublicRecordRequest(acolliercountvfl.gov The Contractor must specifically comply with the Florida Public Records Law to: 1. Keep and maintain public records required by the public agency to perform the service. 2. Upon request from the public agency's custodian of public records, provide the public agency with a copy of the requested records or allow the records to be inspected or copied within a reasonable time at a cost that does not exceed the cost provided in this chapter or as otherwise provided by law. 3. Ensure that public records that are exempt or confidential and exempt from public records disclosure requirements are not disclosed except as authorized by law for the duration of the contract term and following completion of the contract if the Contractor does not transfer the records to the public agency. 34 Construction Services Agreement:[2024_ver.3) 4. Upon completion of the contract, transfer, at no cost, to the public agency all public records in possession of the Contractor or keep and maintain public records required by the public agency to perform the service. If the Contractor transfers all public records to the public agency upon completion of the contract, the Contractor shall destroy any duplicate public records that are exempt or confidential and exempt from public records disclosure requirements. If the Contractor keeps and maintains public records upon completion of the contract, the Contractor shall meet all applicable requirements for retaining public records. All records stored electronically must be provided to the public agency, upon request from the public agency's custodian of public records, in a format that is compatible with the information technology systems of the public agency. 9. CONTRACT TIME AND TIME EXTENSIONS. 9.1 Contractor shall diligently pursue the completion of the Work and coordinate the Work being done on the Project by its subcontractors and materialmen, as well as coordinating its Work with all work of others at the Project Site, so that its Work or the work of others shall not be delayed or impaired by any act or omission by Contractor. Contractor shall be solely responsible for all construction means, methods, techniques, sequences, and procedures, as well as coordination of all portions of the Work under the Contract Documents, and the coordination of Owner's suppliers and contractors as set forth in Paragraph 12.2. herein. 9.2 Should Contractor be obstructed or delayed in the prosecution of or completion of the Work as a result of unforeseeable causes beyond the control of Contractor, and not due to its fault or neglect, including but not restricted to acts of Nature or of the public enemy, acts of government, fires, floods, epidemics, quarantine regulation, strikes or lockouts, Contractor shall notify the Owner in writing within forty-eight (48) hours after the commencement of such delay, stating the cause or causes thereof, or be deemed to have waived any right which Contractor may have had to request a time extension. 9.3 No interruption, interference, inefficiency, suspension or delay in the commencement or progress of the Work from any cause whatever, including those for which Owner may be responsible, in whole or in part, shall relieve Contractor of its duty to perform or give rise to any right to damages or additional compensation from Owner. Contractor expressly acknowledges and agrees that it shall receive no damages for delay. Contractor's sole remedy, if any, against Owner will be the right to seek an extension to the Contract Time; provided, however, the granting of any such time extension shall not be a condition precedent to the aforementioned "No Damage For Delay" provision. This paragraph shall expressly apply to claims for early completion, as well as to claims based on late completion. 9.4 In no event shall any approval by Owner authorizing Contractor to continue performing Work under this Agreement or any payment issued by Owner to Contractor be deemed a waiver of any right or claim Owner may have against Contractor for delay damages hereunder. 10. CHANGES IN THE WORK. 10.1 Owner shall have the right at any time during the progress of the Work to increase or decrease the Work. Promptly after being notified of a change, Contractor shall submit an itemized estimate of any cost or time increases or savings it foresees as a result of the change. Except in an emergency endangering life or property, or as expressly set forth herein, no addition or changes to the Work shall be made except upon written order of Owner in the form of a Work Directive, Exhibit E-2, and Owner shall not be liable to the Contractor for any increased compensation without such 35 Construction Services Agreement:[2024_ver.3] written order. No officer, employee or agent of Owner is authorized to direct any extra or changed work orally. Any alleged changes must be approved by Owner in writing prior to starting such items. Owner will not be responsible for the costs of any changes commenced without Owner's express prior written approval. Failure to obtain such prior written approval for any changes will be deemed: (i) a waiver of any claim by Contractor for such items and (ii) an admission by Contractor that such items are in fact not a change but rather are part of the Work required of Contractor hereunder. 10.2 A Change Order, in the form attached as Exhibit E to this Agreement, shall be issued and executed promptly after an agreement is reached between Contractor and Owner concerning the requested changes. Contractor shall promptly perform changes authorized by duly executed Change Orders. The Contract Amount and Contract Time shall be adjusted in the Change Order in the manner as Owner and Contractor shall mutually agree. 10.3 If Owner and Contractor are unable to agree on a Change Order for the requested change, Contractor shall, nevertheless, promptly perform the change as directed by Owner in a written Work Directive. In that event, the Contract Amount and Contract Time shall be adjusted as directed by Owner. If Contractor disagrees with the Owner's adjustment determination, Contractor must make a claim pursuant to Section 11 of these General Conditions or else be deemed to have waived any claim on this matter it might otherwise have had. 10.4 In the event a requested change results in an increase to the Contract Amount, the amount of the increase shall be limited to the Contractor's reasonable direct labor and material costs and reasonable actual equipment costs as a result of the change (including allowance for labor burden costs) plus a maximum ten percent (10%) markup for all overhead and profit. In the event such change Work is performed by a Subcontractor, a maximum ten percent (10%) markup for all overhead and profit for all Subcontractors' and sub-subcontractors' direct labor and material costs and actual equipment costs shall be permitted, with a maximum five percent (5%) markup thereon by the Contractor for all of its overhead and profit, for a total maximum markup of fifteen percent (15%). All compensation due Contractor and any Subcontractor or sub-subcontractor for field and home office overhead is included in the markups noted above. No markup shall be placed on sales tax, shipping or subcontractor markup. 10.5 Owner, or any duly authorized agents or representatives of the County, shall have the right to conduct an audit of Contractor's books and records to verify the accuracy of the Contractor's claim with respect to Contractor's costs associated with any Payment Application, Change Order or Work Directive Change. 10.6 The Project Manager shall have authority to order minor changes in the Work not involving an adjustment to the Contract Amount or an extension to the Contract Time and not inconsistent with the intent of the Contract Documents. Such changes may be affected by Field Order or by other written order. Such changes shall be binding on the Contractor. 10.7 Any modifications to this Contract shall be in compliance with the County Procurement Ordinance, as amended and the terms of the Contract Documents in effect at the time such modifications are authorized. 11. CLAIMS AND DISPUTES. 11.1 Claim is a demand or assertion by one of the parties seeking an adjustment or interpretation of the terms of the Contract Documents, payment of money, extension of time or other relief with respect to the terms of the Contract Documents. The term "Claim" also includes other disputes and 36 Construction Services Agreement:[2024_ver.3] matters in question between Owner and Contractor arising out of or relating to the Contract Documents. The responsibility to substantiate a Claim shall rest with the party making the Claim. 11.2 Claims by the Contractor shall be made in writing to the Project Manager within forty-eight (48) hours from when the Contractor knew or should have known of the event giving rise to such Claim or else the Contractor shall be deemed to have waived the Claim. Written supporting data shall be submitted to the Project Manager within fifteen (15) calendar days after the occurrence of the event, unless the Owner grants additional time in writing, or else the Contractor shall be deemed to have waived the Claim. All Claims shall be priced in accordance with the provisions of Subsection 10.4. 11.3 The Contractor shall proceed diligently with its performance as directed by the Owner, regardless of any pending Claim, action, suit, or administrative proceeding, unless otherwise agreed to by the Owner in writing. Owner shall continue to make payments in accordance with the Contract Documents during the pendency of any Claim. 12. OTHER WORK. 12.1 Owner may perform other work related to the Project at the site by Owner's own forces, have other work performed by utility owners or let other direct contracts. If the fact that such other work is to be performed is not noted in the Contract Documents, written notice thereof will be given to Contractor prior to starting any such other work. If Contractor believes that such performance will involve additional expense to Contractor or require additional time, Contractor shall send written notice of that fact to Owner and Design Professional within forty-eight (48) hours of being notified of the other work. If the Contractor fails to send the above required forty-eight (48) hour notice, the Contractor will be deemed to have waived any rights it otherwise may have had to seek an extension to the Contract Time or adjustment to the Contract Amount. 12.2 Contractor shall afford each utility owner and other contractor who is a party to such a direct contract (or if Owner is performing the additional work with Owner's employees) proper and safe access to the site and a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such work and shall properly connect and coordinate its Work with theirs. Contractor shall do all cutting, fitting, and patching of the Work that may be required to make its several parts come together properly and integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering their work and will only cut or alter their work with the written consent of the Project Manager and the others whose work will be affected. The duties and responsibilities of Contractor under this paragraph are for the benefit of such utility owners and other Contractors to the extent that there are comparable provisions for the benefit of Contractor in said direct contracts between Owner and such utility owners and other contractors. 12.3 If any part of Contractor's Work depends for proper execution or results upon the work of any other contractor or utility owner (or Owner), Contractor shall inspect and promptly report to Project Manager in writing any delays, defects or deficiencies in such work that render it unavailable or unsuitable for such proper execution and results. Contractor's failure to report will constitute an acceptance of the other work as fit and proper for integration with Contractor's Work. 13. INDEMNIFICATION AND INSURANCE. 13.1 To the maximum extent permitted by Florida law, the Contractor shall defend, indemnify, and hold harmless Collier County, its officers and employees from any and all liabilities, damages, losses 37 Construction Services Agreement:[2024_ver.3] and costs, including, but not limited to, reasonable attorneys'fees and paralegals'fees, to the extent caused by the negligence, recklessness, or intentionally wrongful conduct of the Contractor or anyone employed or utilized by the Contractor in the performance of this Agreement. 13.2 The duty to defend under this Article 13 is independent and separate from the duty to indemnify, and the duty to defend exists regardless of any ultimate liability of the Contractor, Owner, and any indemnified party. The duty to defend arises immediately upon presentation of a claim by any party and written notice of such claim being provided to Contractor. Contractor's obligation to indemnify and defend under this Article 13 will survive the expiration or earlier termination of this Agreement until it is determined by final judgment that an action against the Owner or an indemnified party for the matter indemnified hereunder is fully and finally barred by the applicable statute of limitations. 13.3 Contractor shall obtain and carry, at all times during its performance under the Contract Documents, insurance of the types and in the amounts set forth in the Insurance and Bonding Requirements form Exhibit B-3 to the Agreement. Further, the Contractor shall at all times comply with all of the terms, conditions, requirements and obligations set forth under Exhibit B-3. 14. COMPLIANCE WITH LAWS. 14.1 Contractor agrees to comply, at its own expense,with all federal, state and local laws, codes, statutes, ordinances, rules, regulations and requirements applicable to the Project, including but not limited to those dealing with taxation, worker's compensation, equal employment and safety (including, but not limited to, the Trench Safety Act, Chapter 553, Florida Statutes). If Contractor observes that the Contract Documents are at variance therewith, it shall promptly notify Project Manager in writing. To the extent any law, rule, regulation, code, statute, or ordinance requires the inclusion of certain terms in this Agreement in order for this Agreement to be enforceable, such terms shall be deemed included in this Agreement. Notwithstanding anything in the Contract Documents to the contrary, it is understood and agreed that in the event of a change in any applicable laws, ordinances, rules or regulations subsequent to the date this Agreement was executed that increases the Contractor's time or cost of performance of the Work, Contractor is entitled to a Change Order for such increases, except to the extent Contractor knew or should have known of such changes prior to the date of this Agreement. 14.2 By executing and entering into this agreement, the Contractor is formally acknowledging without exception or stipulation that it is fully responsible for complying with the provisions of the Immigration Reform and Control Act of 1986 as located at 8 U.S.C. 1324, et seq. and regulations relating thereto, as either may be amended. Failure by the Contractor to comply with the laws referenced herein shall constitute a breach of this agreement and the County shall have the discretion to unilaterally terminate this agreement immediately. 14.3 Statutes and executive orders require employers to abide by the immigration laws of the United States and to employ only individuals who are eligible to work in the United States, including the requirements set forth in Florida Statute, §448.095. The Employment Eligibility Verification System (E-Verify) operated by the Department of Homeland Security (DHS) in partnership with the Social Security Administration (SSA), provides an Internet- based means of verifying employment eligibility of workers in the United States; it is not a substitute for any other employment eligibility verification requirements. The program will be used for Collier County formal Invitations to Bid (ITB) and Request for Proposals (RFP) including professional services and construction services. 38 Construction Services Agreement:I2024_ver.3] Contractors/Bidders are required to enroll in the E-Verify program, and provide acceptable evidence of their enrollment, at the time of the submission of the Contractor's/bidder's proposal. Acceptable evidence consists of a copy of the properly completed E-Verify Company Profile page or a copy of the fully executed E-Verify Memorandum of Understanding for the company. Contractors are also required to provide the Collier County Procurement Services Division an executed affidavit certifying they shall comply with the E-Verify Program. The affidavit is attached to the solicitation documents. If the Bidder/Contractor does not comply with providing both the acceptable E-Verify evidence and the executed affidavit the bidder's/Contractor's proposal may be deemed non- responsive. Additionally, Contractors shall require all subcontracted Contractors to use the E-Verify system for all purchases not covered under the "Exceptions to the program" clause above. For additional information regarding the Employment Eligibility Verification System (E-Verify) program visit the following website: http://www.dhs.gov/E-Verify. It shall be the Contractor's responsibility to familiarize themselves with all rules and regulations governing this program. Contractor acknowledges, and without exception or stipulation, any firm(s) receiving an award shall be fully responsible for complying with the provisions of the Immigration Reform and Control Act of 1986 as located at 8 U.S.C. 1324, et seq. and regulations relating thereto, as either may be amended and with the provisions contained within this affidavit. Failure by the awarded firm(s) to comply with the laws referenced herein or the provisions of this affidavit shall constitute a breach of the award agreement and the County shall have the discretion to unilaterally terminate said agreement immediately. 15. CLEANUP AND PROTECTIONS. 15.1 Contractor agrees to keep the Project site clean at all times of debris, rubbish and waste materials arising out of the Work. At the completion of the Work, Contractor shall remove all debris, rubbish and waste materials from and about the Project site, as well as all tools, appliances, construction equipment and machinery and surplus materials, and shall leave the Project site clean and ready for occupancy by Owner. 15.2 Any existing surface or subsurface improvements, including, but not limited to, pavements, curbs, sidewalks, pipes, utilities, footings, structures, trees and shrubbery, not indicated in the Contract Documents to be removed or altered, shall be protected by Contractor from damage during the prosecution of the Work. Subject to the Section 2.3 above, any such improvements so damaged shall be restored by Contractor to the condition equal to that existing at the time of Contractor's commencement of the Work. 16. ASSIGNMENT. 16.1 Contractor shall not assign this Agreement or any part thereof, without the prior consent in writing of Owner. Any attempt to assign or otherwise transfer this Agreement, or any part herein, without the Owner's consent, shall be void. If Contractor does, with approval, assign this Agreement or any part thereof, it shall require that its assignee be bound to it and to assume toward Contractor all of the obligations and responsibilities that Contractor has assumed toward Owner. 17. PERMITS, LICENSES AND TAXES. 39 Construction Services Agreement:[2024_ver.3] 17.1 Pursuant to Section 218.80, F.S., Owner will pay for all Collier County permits and fees, including license fees, permit fees, impact fees or inspection fees applicable to the Work through an internal budget transfer(s). Contractor is not responsible for paying for permits issued by Collier County, but Contractor is responsible for acquiring all permits. Owner may require the Contractor to deliver internal budget transfer documents to applicable Collier County agencies when the Contractor is acquiring permits. Owner will not be obligated to pay for any permits obtained by Subcontractors. 17.2 All permits, fees and licenses necessary for the prosecution of the Work which are not issued by Collier County shall be acquired and paid for by the Contractor. 17.3 Contractor shall pay all sales, consumer, use and other similar taxes associated with the Work or portions thereof, which are applicable during the performance of the Work. 18. TERMINATION FOR DEFAULT. 18.1 Contractor shall be considered in material default of the Agreement and such default shall be considered cause for Owner to terminate the Agreement, in whole or in part, as further set forth in this Section, if Contractor: (1) fails to begin the Work under the Contract Documents within the time specified herein; or (2) fails to properly and timely perform the Work as directed by the Project Manager or as provided for in the approved Progress Schedule; or(3) performs the Work unsuitably or neglects or refuses to remove materials or to correct or replace such Work as may be rejected as unacceptable or unsuitable; or (4) discontinues the prosecution of the Work; or (5) fails to resume Work which has been suspended within a reasonable time after being notified to do so; or (6) becomes insolvent or is declared bankrupt, or commits any act of bankruptcy; or(7) allows any final judgment to stand against it unsatisfied for more than ten (10) days; or(8) makes an assignment for the benefit of creditors; or (9) fails to obey any applicable codes, laws, ordinances, rules or regulations with respect to the Work; or(10) materially breaches any other provision of the Contract Documents. 18.2 Owner shall notify Contractor in writing of Contractor's default(s). If Owner determines that Contractor has not remedied and cured the default(s)within seven (7)calendar days following receipt by Contractor of said written notice or such longer period of time as may be consented to by Owner in writing and in its sole discretion, then Owner, at its option, without releasing or waiving its rights and remedies against the Contractor's sureties and without prejudice to any other right or remedy it may be entitled to hereunder or by law, may terminate Contractor's right to proceed under the Agreement, in whole or in part, and take possession of all or any portion of the Work and any materials, tools, equipment, and appliances of Contractor, take assignments of any of Contractor's subcontracts and purchase orders, and complete all or any portion of Contractor's Work by whatever means, method or agency which Owner, in its sole discretion, may choose. 18.3 If Owner deems any of the foregoing remedies necessary, Contractor agrees that it shall not be entitled to receive any further payments hereunder until after the Project is completed. All moneys expended and all of the costs, losses, damages and extra expenses, including all management, administrative and other overhead and other direct and indirect expenses (including Design Professional and attorneys' fees) or damages incurred by Owner incident to such completion, shall be deducted from the Contract Amount, and if such expenditures exceed the unpaid balance of the Contract Amount, Contractor agrees to pay promptly to Owner on demand the full amount of such excess, including costs of collection, attorneys' fees (including appeals) and interest thereon at the maximum legal rate of interest until paid. If the unpaid balance of the Contract Amount exceeds all such costs, expenditures and damages incurred by the Owner to complete the Work, such excess 40 Construction Services Agreement:[2024_ver.3] shall be paid to the Contractor. The amount to be paid to the Contractor or Owner, as the case may be, shall be approved by the Project Manager, upon application, and this obligation for payment shall survive termination of the Agreement. 18.4 The liability of Contractor hereunder shall extend to and include the full amount of any and all sums paid, expenses and losses incurred, damages sustained, and obligations assumed by Owner in good faith under the belief that such payments or assumptions were necessary or required, in completing the Work and providing labor, materials,equipment, supplies, and other items therefore or re-letting the Work, and in settlement, discharge or compromise of any claims, demands, suits, and judgments pertaining to or arising out of the Work hereunder. 18.5 If, after notice of termination of Contractor's right to proceed pursuant to this Section, it is determined for any reason that Contractor was not in default, or that its default was excusable, or that Owner is not entitled to the remedies against Contractor provided herein, then the termination will be deemed a termination for convenience and Contractor's remedies against Owner shall be the same as and limited to those afforded Contractor under Section 19 below. 18.6 In the event (i) Owner fails to make any undisputed payment to Contractor within thirty (30) days after such payment is due or Owner otherwise persistently fails to fulfill some material obligation owed by Owner to Contractor under this Agreement, and (ii) Owner has failed to cure such default within fourteen (14) days of receiving written notice of same from Contractor, then Contractor may stop its performance under this Agreement until such default is cured, after giving Owner a second fourteen (14) days written notice of Contractor's intention to stop performance under the Agreement. If the Work is so stopped for a period of one hundred and twenty (120) consecutive days through no act or fault of the Contractor or its Subcontractors or their agents or employees or any other persons performing portions of the Work under contract with the Contractor or any Subcontractor, the Contractor may terminate this Agreement by giving written notice to Owner of Contractor's intent to terminate this Agreement. If Owner does not cure its default within fourteen (14) days after receipt of Contractor's written notice, Contractor may, upon fourteen (14) additional days' written notice to the Owner, terminate the Agreement and recover from the Owner payment for Work performed through the termination date, but in no event shall Contractor be entitled to payment for Work not performed or any other damages from Owner. 19. TERMINATION FOR CONVENIENCE AND RIGHT OF SUSPENSION. 19.1 Owner shall have the right to terminate this Agreement without cause upon seven (7) calendar days written notice to Contractor. In the event of such termination for convenience, Contractor's recovery against Owner shall be limited to that portion of the Contract Amount earned through the date of termination, together with any retainage withheld and reasonable termination expenses incurred, but Contractor shall not be entitled to any other or further recovery against Owner, including, but not limited to, damages or any anticipated profit on portions of the Work not performed. 19.2 Owner shall have the right to suspend all or any portions of the Work upon giving Contractor not less than two (2) calendar days' prior written notice of such suspension. If all or any portion of the Work is so suspended, Contractor's sole and exclusive remedy shall be to seek an extension of time to its schedule in accordance with the procedures set forth in the Contract Documents. In no event shall the Contractor be entitled to any additional compensation or damages. Provided, however, if the ordered suspension exceeds six (6) months, the Contractor shall have the right to terminate the Agreement with respect to that portion of the Work which is subject to the ordered suspension. 41 Construction Services Agreement:[2024_ver.3] 20. COMPLETION. Substantial Completion and Development of the Punch List 20.1 Substantial Completion is as defined in the Defined Terms section of this Agreement. When the Contractor believes Substantial Completion has been achieved, it shall certify in writing to the Project Manager that the Project is Substantially Complete in accordance with the Contract Documents and request the Project Manager to inspect the Work and to issue a Certificate of Substantial Completion. Prior to making such a request the Contractor must: a) Complete all Work necessary for the safe, proper and complete use or operation of the Project as intended, including: all regulatory agency requirements are satisfied, including occupancy permits; operating certificates and similar releases; all operational testing has successfully occurred; all required training has successfully occurred; all close-out documents (such as as-built drawings, certifications, warranties, guaranties, test reports test logs, operational manuals, etc.) have been provided by Contractor and accepted by Owner. b) Prepare a Contractor-generated punch list(i.e., a list of all items required to render the Project complete, satisfactory, and acceptable, for submission with the request for inspection and issuance of a certificate of Substantial Completion), which shall include and list separately the estimated cost to complete each remaining unfinished item included on the list with an explanation as to the basis for those costs, substantiated by the Schedule of Values, subject to the Owner's final review and approval as stated below. c) Upon receipt of the request from the Contractor, the Project Manager, assisted by the Professional, if any, and other Owner personnel, as appropriate, shall review the request, the Work and the Contractor-generated Punch List to determine whether the Work is ready for Substantial Completion inspection. If this review fails to support Substantial Completion inspection, the Project Manager shall so notify the Contractor citing the reasons for rejection. If the Project Manager and Professional (if any) determine the Work is ready for Substantial Completion inspection, the following procedures will be followed: 1. The Project Manager will, within a reasonable time, schedule, and conduct inspection(s) of the Work with the Professional (if any), other Owner personnel as required, and the Contractor for the purpose of formally reviewing the status of completion of the Work, the readiness of the Project for use and the Contractor-generated Punch List. A copy of the Contractor- generated punch list will be provided to all participants and any additional items noted during the inspection will be added to the list. The Project Manager, the Professional, their representatives and other Owner representatives will review the Work and the Contractor-generated punch list to assure all deficiencies are noted on a final document (Exhibit F-3 Punch List Form). The Punch List must include all items required to render the Project complete, satisfactory and acceptable. If Project Manager and Contractor disagree on whether an item belongs on the Punch List, the Project Manager has the final say on whether the item is included or not. The Punch List shall be finalized and issued to the Contractor by the Owner within the time frames indicated below. 42 Construction Services Agreement:[2024_ver.3] 2. If upon completion of the inspection(s) the Owner does not consider the Project Substantially Complete, the Project Manager will notify the Contractor in writing giving reasons why the Project is not Substantially Complete. 3. If, upon completion of the inspection(s), the Owner considers the Project Substantially Complete, the Project Manager shall prepare a Certificate of Substantial Completion to establish the date for Substantial Completion as the date of the completed inspection(s). The Certificate of Substantial Completion shall be approved by the Owner upon the signature of both the Project Manager and the Professional and shall be issued to the Contractor. The Certificate shall fix the date of Substantial Completion. 4. Substantial Completion cannot occur until all conditions necessary for safe and proper use, occupancy, maintenance, and operations are in place. 20.2 Time Frames for Issuance of the Punch List (a) The Owner shall issue the Punch List to the Contractor within the time frames described below, provided that the Contractor has completed its obligations in providing a proper contractor-generated Punch List prior to the Substantial Completion inspection. (b) For construction estimated to cost less than ten million dollars ($10,000,000.00), the Punch List must be finalized within thirty (30) Days after the Substantial Completion date. (c) For construction projects estimated to cost more than ten million dollars ($10,000,000.00), the Punch List must be finalized and issued within forty-five (45) Days after the Substantial Completion date. (d) For construction projects involving more than one building or structure or multiple phases, the Punch List must be prepared for each building, structure or phase within thirty (30) Days of the Substantial Completion date of a particular building, structure or phase if it is estimated to cost less than ten million dollars ($10,000,000.00) or within forty-five (45) Days if it is estimated to cost more than ten million dollars ($10,000,000.00). (e) If the development of the Punch List takes the full amount of time designated (or a portion thereof) and includes a tentative punch-list based upon the above dollar amount thresholds, the delivery of the Punch List of items shall be delivered by the Owner no later than five (5) business days thereafter. Within twenty (20) business days after the delivery of the Punch List to the Contractor, the Owner must pay the Contractor the remaining contract balance owed, that includes all retainage previously withheld by Owner less an amount equal to 150 percent (150%) of the estimated cost to complete the items on the Punch List. At the same time the Owner delivers the Punch List Contractor shall submit a payment application requesting that Owner pay the Contractor the remaining contract balance owed including all retainage previously held by Owner less an 43 Construction Services Agreement:[2024_ver.3] amount equal to 150 percent(150%)of the estimated cost to complete the items on the Punch List. (f) The failure to include any corrective work or pending items not yet completed on the Punch List does not alter the responsibility of Contractor to complete all the construction services purchased pursuant to the Contract Documents. (g) Owner shall have the right to exclude Contractor from the Work and Project site (or designated portion thereof) after the date of Substantial Completion, but Owner shall allow Contractor reasonable access to complete or correct items on the Punch List. The Project Manager, shall coordinate with the Contractor the return of any surplus assets, including materials, supplies, and equipment. 20.3 Completion of Punch List Work and Release of Remaining Contract Balance (a) Upon completion of the Punch List Work, the Contractor shall certify in writing to the Project Manager that all Punch List Work has been completed in accordance with the Contract Documents and request the Project Manager to inspect the Work and to approve Punch List completion. If, in the Project Manager's opinion, the Work is not ready for such inspection, the Project Manager will so inform the Contractor, giving reasons for such opinion. If the Project Manager is satisfied that an inspection is warranted, the Project Manager will, within a reasonable time, schedule and conduct inspection(s) of the facility with representatives of the Owner's user department, the Professional (if any), and the Contractor, for the purpose of formally reviewing the completion of Punch List Work. If the Project Manager and the Contractor disagree on whether an item remains incomplete, the Project Manager has the final say on whether the item is complete or not. (b) If, upon completion of the inspection(s)the Owner does not consider the Punch List Work complete, the Project Manager will notify the Contractor in writing giving specific reasons why the Punch List Work is not complete. (c) Upon completion of all items on the Punch List, the Contractor may submit a Payment Request for the remaining amount withheld by the Owner. If a good- faith dispute exists as to whether one or more items identified on the list have been completed pursuant to the Contract Documents, the Owner may continue to withhold an amount not to exceed one hundred and fifty percent (150%) of the total costs to complete such items. This remaining balance of retainage may be requested by the Contractor in its Application for Final Payment after Final Acceptance of the Work by Owner (Exhibit F-2 Certificate of Final Completion). (d) All items that require correction under the Contract Documents and that are identified after the preparation and delivery of the Punch List shall remain the obligation of the Contractor. (e) Warranty Items may not affect the Final Payment of retainage pursuant to Section 218.735(7)(f), Florida Statutes. 44 Construction Services Agreement:[2024_ver.3] (f) If the Owner fails to comply with its responsibilities to assist in developing the Punch List within the time frame applicable to the Project(as described above), the Contractor may submit a request for all remaining retainage withheld by the Owner. The Owner need not pay or process any payment request for retainage if Contractor has, in whole or part, failed to cooperate with the Owner in development of the Punch List or failed to perform its contractual responsibilities with regard to development of the Punch List. Additionally, the Owner does not have to pay or release any amounts that are the subject of a good-faith dispute, the subject of a claim brought pursuant to Section 255.05, Florida Statutes, or otherwise the subject of a claim or demand by the Owner or Contractor. 20.4 Final Completion (a) Upon written notice from the Contractor that the Project is complete, the Project Manager shall schedule a final inspection with the Contractor, the Design Professional, and any other personnel requested by the Project Manager. The Project Manager shall notify the Contractor in writing of any Work this inspection reveals to be defective, or otherwise not in accordance with the Contract Documents. The Contractor shall immediately take such action as may be necessary to remedy such defects and bring the Project into full compliance with the Contract Documents and then request another inspection. (b) Final Completion of the Work shall be achieved by the Contractor when all the Work required under the Contract Documents has been satisfactorily completed, including all Punch List work, and specifically as noted in .the Specifications section. (c) After the Project Manager has determined that all Work has been completed, the Project Manager will issue a Certificate of Final Completion Exhibit F-2 for the Work. 20.5 Application for Final Payment After the Certificate of Final Completion, Exhibit F-2 for the Work has been issued by the Project Manager, the Contractor may make Application for Final Payment following the procedure for progress payments. As an explicit condition precedent to the accrual of Contractor's right to Final Payment, Contractor shall have furnished Owner with a properly executed and notarized copy of the Release and Affidavit form attached as Exhibit C, as well as a duly executed copy of the Surety's consent to Final Payment and such other documentation that may be required by the Contract Documents, including but not limited to: (1) Receipt of Contractor's Final Application for Payment. (2) The Release and Affidavit in the form attached as Exhibit C. (3) Consent of surety to Final Payment. (4) Receipt of the Final Payment Check list, Exhibit G-1. (5) If required by Owner, other data establishing payment or satisfaction of all obligations, such as receipts, releases and waivers of liens, arising out of the Contract Documents, to the extent and in such form as may be designated by Owner. 45 Construction Services Agreement:[2024_ver.3] Prior to release of Final Payment and final retainage, the Contractor's Representative and the Project Manager shall jointly complete the Final Payment Checklist, a representative copy of which is attached to this Agreement as Exhibit G-1. 20.6 Approval of Final Payment (a) If, on the basis of the Project Manager's observations and review of Work during Construction, final inspection, and review of the Application for Final Payment (all as required by the Contract Documents), the Project Manager is satisfied that the Work has been completed and the Contractor has fulfilled all of its obligations under the Contract Documents, the Project Manager will, within ten (10) days after receipt of the Application for Final Payment, indicate in writing that the entire remaining balance is found to be due and payable to the Contractor and approve payment. Otherwise, the Project Manager will return the Application to the Contractor, indicating in writing the reason for refusing to approve for Final Payment, in which case the Contractor will make the necessary corrections and resubmit the Application. Owner reserves the right to inspect the Work and make an independent determination as to the Work's acceptability, even though the Design Professional may have issued its recommendations. (b) Contractor's acceptance of Final Payment shall constitute a full waiver of any and all claims by Contractor against Owner arising out of this Agreement or otherwise relating to the Project, except those previously made in writing in accordance with the requirements of the Contract Documents and identified by Contractor as unsettled in its final Application for Payment. Neither the acceptance of the Work nor payment by Owner shall be deemed to be a waiver of Owner's right to enforce any obligations of Contractor hereunder or to the recovery of damages for defective Work not discovered by the Design Professional or Project Manager at the time of final inspection. (c) The Contractor's obligation to perform the Work and complete the Project in accordance with the Contract Documents shall be absolute. Neither approval of any progress or Final Payment, the issuance of a Certificate of Substantial Completion, any payment by the Owner to the Contractor under the Contract Documents, any use or occupancy of the Project or any part thereof by the Owner,the issuance of a Final Completion, any act of acceptance by the Owner, any failure to do so, nor any correction of defective Work by the Owner shall constitute an acceptance of Work not in accordance with the Contract Documents. 21. WARRANTY. 21.1 Contractor shall obtain and assign to Owner all express warranties given to Contractor or any subcontractors by any subcontractor or material men supplying materials, equipment or fixtures to be incorporated into the Project. Contractor warrants to Owner that any materials and equipment furnished under the Contract Documents shall be new unless otherwise specified, and that all Work shall be of good quality, free from all defects and in conformance with the Contract Documents. Contractor further warrants to Owner that all materials and equipment furnished under the Contract 46 Construction Services Agreement:[2024_ver.3] Documents shall be applied, installed, connected, erected, used, cleaned and conditioned in accordance with the instructions of the applicable manufacturers,fabricators,suppliers or processors except as otherwise provided for in the Contract Documents. If, within one (1)year after Substantial Completion, any Work is found to be defective or not in conformance with the Contract Documents, Contractor shall correct it promptly after receipt of written notice from Owner. Contractor shall also be responsible for and pay for replacement or repair of adjacent materials or Work which may be damaged as a result of such replacement or repair. Further, in the event of an emergency, Owner may commence to correct any defective Work, without prior notice to Contractor, at Contractor's expense. These warranties are in addition to those implied warranties to which Owner is entitled as a matter of law. 21.2 No later than 30 days prior to expiration of the warranty, the Project Manager, or another representative of the Owner, shall conduct an inspection of the warranted work to verify compliance with the requirements of the Agreement. The Contractor's Representative shall be present at the time of inspection and shall take remedial actions to correct any deficiencies noted in the inspection. Failure of the Contractor to correct the cited deficiencies shall be grounds for the Owner to disqualify the Contractor from future bid opportunities with the Owner, in addition to any other rights and remedies available to Owner. 22 TESTS AND INSPECTIONS. 22.1 Owner, Design Professional, their respective representatives, agents and employees, and governmental agencies with jurisdiction over the Project shall have access at all times to the Work, whether the Work is being performed on or off of the Project site, for their observation, inspection and testing. Contractor shall provide proper, safe conditions for such access. Contractor shall provide Project Manager with timely notice of readiness of the Work for all required inspections,tests or approvals. 22.2 If the Contract Documents or any codes, laws, ordinances, rules or regulations of any public authority having jurisdiction over the Project requires any portion of the Work to be specifically inspected, tested or approved, Contractor shall assume full responsibility therefore, pay all costs in connection therewith and furnish Project Manager the required certificates of inspection, testing or approval. All inspections, tests or approvals shall be performed in a manner and by organizations acceptable to the Project Manager. 22.3 Contractor is responsible, without reimbursement from Owner, for re-inspection fees and costs; to the extent such re-inspections are due to the fault or neglect of Contractor. 22.4 If any Work that is to be inspected, tested or approved is covered without written concurrence from the Project Manager, such work must, if requested by Project Manager, be uncovered for observation. Such uncovering shall be at Contractor's expense unless Contractor has given Project Manager timely notice of Contractor's intention to cover the same and Project Manager has not acted with reasonable promptness to respond to such notice. If any Work is covered contrary to written directions from Project Manager, such Work must, if requested by Project Manager, be uncovered for Project Manager's observation, and be replaced at Contractor's sole expense. 22.5 The Owner shall charge to Contractor and may deduct from any payments due Contractor all engineering and inspection expenses incurred by Owner in connection with any overtime work. Such overtime work consisting of any work during the construction period beyond the regular eight(8)hour day and for any work performed on Saturday, Sunday, or holidays. 47 Construction Services Agreement:[2024_ver.3] 22.6 Neither observations nor other actions by the Project Manager or Design Professional nor inspections, tests or approvals by others shall relieve Contractor from Contractor's obligations to perform the Work in accordance with the Contract Documents. 23. DEFECTIVE WORK. 23.1 Work not conforming to the requirements of the Contract Documents or any warranties made or assigned by Contractor to Owner shall be deemed defective Work. If required by Project Manager, Contractor shall, as directed, either correct all defective Work, whether or not fabricated, installed or completed, or if the defective Work has been rejected by Project Manager, remove it from the site and replace it with non-defective Work. Contractor shall bear all direct, indirect, and consequential costs of such correction or removal (including, but not limited to fees and charges of engineers, architects, attorneys, and other professionals) made necessary thereby, and shall hold Owner harmless for same. 23.2 If the Project Manager considers it necessary or advisable that covered Work be observed by Design Professional or inspected or tested by others and such Work is not otherwise required to be inspected or tested, Contractor, at Project Manager's request, shall uncover, expose or otherwise make available for observation, inspection or tests as Project Manager may require, that portion of the Work in question, furnishing all necessary labor, material and equipment. If it is found that such Work is defective, Contractor shall bear all direct, indirect, and consequential costs of such uncovering, exposure, observation, inspection and testing and of satisfactory reconstruction (including, but not limited to, fees and charges of engineers, architects, attorneys, and other professionals), and Owner shall be entitled to an appropriate decrease in the Contract Amount. If, however, such Work is not found to be defective, Contractor shall be allowed an increase in the Contract Amount and/or an extension to the Contract Time, directly attributable to such uncovering, exposure, observation, inspection, testing and reconstruction. 23.3 If any portion of the Work is defective, or if Contractor fails to supply sufficient skilled workers, suitable materials or equipment or fails to finish or perform the Work in such a way that the completed Work will conform to the Contract Documents, Project Manager may order Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated. The right of Project Manager to stop the Work shall be exercised, if at all, solely for Owner's benefit and nothing herein shall be construed as obligating the Project Manager to exercise this right for the benefit of Design Engineer, Contractor, or any other person. 23.4 Should the Owner determine, at its sole opinion, it is in the Owner's best interest to accept defective Work, the Owner may do so. Contractor shall bear all direct, indirect, and consequential costs attributable to the Owner's evaluation of and determination to accept defective Work. If such determination is rendered prior to Final Payment, a Change Order shall be executed evidencing such acceptance of such defective Work, incorporating the necessary revisions in the Contract Documents, and reflecting an appropriate decrease in the Contract Amount. If the Owner accepts such defective Work after Final Payment, Contractor shall promptly pay Owner an appropriate amount to adequately compensate Owner for its acceptance of the defective Work. 23.5 If Contractor fails, within a reasonable time after the written notice from Project Manager, to correct defective Work or to remove and replace rejected defective Work as required by Project Manager or Owner, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any of the provisions of the Contract Documents, Owner may, after seven (7) days written notice to Contractor, correct and remedy any such deficiency. Provided, however, Owner shall not be required to give notice to Contractor in the event 48 Construction Services Agreement:[2024_ver.3] of an emergency. To the extent necessary to complete corrective and remedial action, Owner may exclude Contractor from any or all of the Project site, take possession of all or any part of the Work, and suspend Contractor's services related thereto,take possession of Contractor's tools, appliances, construction equipment and machinery at the Project site and incorporate in the Work all materials and equipment stored at the Project site or for which Owner has paid Contractor but which are stored elsewhere. Contractor shall allow Owner, Design Professional and their respective representatives, agents, and employees such access to the Project site as may be necessary to enable Owner to exercise the rights and remedies under this paragraph. All direct, indirect, and consequential costs of Owner in exercising such rights and remedies shall be charged against Contractor, and a Change Order shall be issued, incorporating the necessary revisions to the Contract Documents, including an appropriate decrease to the Contract Amount. Such direct, indirect, and consequential costs shall include, but not be limited to, fees and charges of engineers, architects, attorneys and other professionals, all court costs and all costs of repair and replacement of work of others destroyed or damaged by correction, removal, or replacement of Contractor's defective Work. Contractor shall not be allowed an extension of the Contract Time because of any delay in performance of the Work attributable to the exercise by Owner of Owner's rights and remedies hereunder. 24. SUPERVISION AND SUPERINTENDENTS. 24.1 Contractor shall plan, organize, supervise, schedule, monitor, direct and control the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract Documents. Contractor shall be responsible to see that the finished Work complies accurately with the Contract Documents. Contractor shall keep on the Work at all times during its progress a competent resident superintendent, who shall be subject to Owner's approval and not be replaced without prior written notice to Project Manager except under extraordinary circumstances. The superintendent shall be employed by the Contractor and be the Contractor's representative at the Project site and shall have authority to act on behalf of Contractor. All communications given to the superintendent shall be as binding as if given to the Contractor. Owner shall have the right to direct Contractor to remove and replace its Project superintendent, with or without cause. Attached to the Agreement as Exhibit A-3 is a list identifying Contractor's Project Superintendent and all of Contractor's key personnel who are assigned to the Project; such identified personnel shall not be removed without Owner's prior written approval, and if so removed must be immediately replaced with a person acceptable to Owner. 24.2 Contractor shall have a competent superintendent on the project at all times whenever Contractor's work crews, or work crews of other parties authorized by the Project Manager are engaged in any activity whatsoever associated with the Project. Should the Contractor fail to comply with the above condition, the Project Manager shall, at his discretion, deduct from the Contractor's monthly pay estimate, sufficient moneys to account for the Owner's loss of adequate project supervision, not as a penalty, but as liquidated damages, separate from the liquidated damages described in Section 5.B, for services not rendered. 25. PROTECTION OF WORK. 25.1 Contractor shall fully protect the Work from loss or damage and shall bear the cost of any such loss or damage until final payment has been made. If Contractor or any one for whom Contractor is legally liable for is responsible for any loss or damage to the Work, or other work or materials of Owner or Owner's separate contractors, Contractor shall be charged with the same, and any moneys necessary to replace such loss or damage shall be deducted from any amounts due Contractor. 49 Construction Services Agreement:[2024_ver.3] 25.2 Contractor shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall Contractor subject any part of the Work or adjacent property to stresses or pressures that will endanger it. 25.3 Contractor shall not disturb any benchmark established by the Owner or Design Professional with respect to the Project. If Contractor, or its subcontractors, agents, or anyone for whom Contractor is legally liable, disturbs the Owner or Design Professional's benchmarks, Contractor shall immediately notify Project Manager and Design Professional. The Owner or Design Professional shall re-establish the benchmarks and Contractor shall be liable for all costs incurred by Owner associated therewith. 26. EMERGENCIES. 26.1 In the event of an emergency affecting the safety or protection of persons or the Work or property at the Project site or adjacent thereto, Contractor,without special instruction or authorization from Owner or Design Professional is obligated to act to prevent threatened damage, injury, or loss. Contractor shall give Project Manager written notice within forty-eight (48) hours after Contractor knew or should have known of the occurrence of the emergency, if Contractor believes that any significant changes in the Work or variations from the Contract Documents have been caused thereby. If the Project Manager determines that a change in the Contract Documents is required because of the action taken in response to an emergency, a Change Order shall be issued to document the consequences of the changes or variations. If Contractor fails to provide the forty-eight (48) hour written notice noted above, the Contractor shall be deemed to have waived any right it otherwise may have had to seek an adjustment to the Contract Amount or an extension to the Contract Time. 27. USE OF PREMISES. 27.1 Contractor shall maintain all construction equipment, the storage of materials and equipment and the operations of workers to the Project site and land and areas identified in and permitted by the Contract Documents and other lands and areas permitted by law, rights of way, permits and easements, and shall not unreasonably encumber the Project site with construction equipment or other material or equipment. Contractor shall assume full responsibility for any damage to any such land or area, or to the owner or occupant thereof, or any land or areas contiguous thereto, resulting from the performance of the Work. 28. SAFETY. 28.1 Contractor shall be responsible for initiating, maintaining, and supervising all safety precautions and programs in connection with the Work. Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to: 28.1.1 All employees on or about the project site and other persons and/or organizations who may be affected thereby; 28.1.2 All the Work and materials and equipment to be incorporated therein, whether in storage on or off the Project site; and 50 Construction Services Agreement:[2024_ver.3] 28.1.3 Other property on Project site or adjacent thereto, including trees, shrubs, walks, pavements, roadways, structures, utilities and any underground structures or improvements not designated for removal, relocation, or replacement in the Contract Documents. 28.2 Contractor shall comply with all applicable codes, laws, ordinances, rules, and regulations of any public body having jurisdiction for the safety of persons or property or to protect them from damage, injury, or loss. Contractor shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall notify owners of adjacent property and of underground structures and improvements and utility owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal, relocation, or replacement of their property. Contractor's duties and responsibilities for the safety and protection of the Work shall continue until such time as the Work is completed and final acceptance of same by Owner has occurred. All new electrical installations shall incorporate NFPA 70E Short Circuit Protective Device Coordination and Arc Flash Studies where relevant as determined by the engineer. All electrical installations shall be labeled with appropriate NFPA 70E arch flash boundary and PPE Protective labels. 28.3. Contractor shall designate a responsible representative located on a full-time basis at the Project site whose duty shall be the prevention of accidents. This person shall be Contractor's superintendent unless otherwise designated in writing by Contractor to Owner. 28.4 Alcohol, drugs and all illegal substances are strictly prohibited on any Owner property. All employees of Contractor, as well as those of all subcontractors and those of any other person or entity for whom Contractor is legally liable (collectively referred to herein as "Employees"), shall not possess or be under the influence of any such substances while on any Owner property. Further, Employees shall not bring on to any Owner property any gun, rifle or other firearm, or explosives of any kind. 28.5 Contractor acknowledges that the Work may be progressing on a Project site which is located upon or adjacent to an existing Owner facility. In such event, Contractor shall comply with the following: 28.5.1 All Owner facilities are smoke free. Smoking is strictly prohibited; 28.5.2 All Employees shall be provided an identification badge by Contractor. Such identification badge must be prominently displayed on the outside of the Employees' clothing at all times. All Employees working at the Project site must log in and out with the Contractor each day; 28.5.3 Contractor shall strictly limit its operations to the designated work areas and shall not permit any Employees to enter any other portions of Owner's property without Owner's expressed prior written consent; 28.5.4 All Employees are prohibited from distributing any papers or other materials upon Owner's property, and are strictly prohibited from using any of Owner's telephones or other office equipment; 28.5.5 All Employees shall at all times comply with the OSHA regulations with respect to dress and conduct at the Project site. Further, all Employees shall comply with the dress, conduct 51 Construction Services Agreement:[2024_ver.3] shall review the costs of those proposals and advise Owner and Design Professional of their validity and reasonableness, acting in Owner's best interest, prior to requesting approval of any Change Order from Owner. All Subcontractors performing any portion of the Work on this Project must be "qualified" as defined in Collier County Ordinance 2013-69, meaning a person or entity that has the capability in all respects to perform fully the Agreement requirements with respect to its portion of the Work and has the integrity and reliability to assure good faith performance. 33.3 In addition to those Subcontractors identified in Contractor's bid that were approved by Owner, Contractor also shall identify any other Subcontractors, including their addresses, licensing information and phone numbers, it intends to utilize for the Project prior to entering into any subcontract or purchase order and prior to the Subcontractor commencing any work on the Project. The list identifying each Subcontractor cannot be modified, changed, or amended without prior written approval from Owner. Any and all Subcontractor work to be self-performed by Contractor must be approved in writing by Owner in its sole discretion prior to commencement of such work. Contractor shall continuously update that Subcontractor list, so that it remains current and accurate throughout the entire performance of the Work. 33.4 Contractor shall not enter into a subcontract or purchase order with any Subcontractor, if Owner reasonably objects to that Subcontractor. Contractor shall not be required to contract with anyone it reasonably objects to. Contractor shall keep on file a copy of the license for every Subcontractor and sub-subcontractor performing any portion of the Work, as well as maintain a log of all such licenses.All subcontracts and purchase orders between Contractor and its Subcontractors shall be in writing and are subject to Owner's approval. Further, unless expressly waived in writing by Owner, all subcontracts and purchase orders shall (1) require each Subcontractor to be bound to Contractor to the same extent Contractor is bound to Owner by the terms of the Contract Documents, as those terms may apply to the portion of the Work to be performed by the Subcontractor, (2)provide for the assignment of the subcontract or purchase order from Contractor to Owner at the election of Owner upon termination of Contractor, (3) provide that Owner will be an additional indemnified party of the subcontract or purchase order, (4) provide that Owner, Collier County Government, will be an additional insured on all liability insurance policies required to be provided by the Subcontractor except workman's compensation and business automobile policies, (5) assign all warranties directly to Owner, and (6) identify Owner as an intended third-party beneficiary of the subcontract or purchase order. Contractor shall make available to each proposed Subcontractor, prior to the execution of the subcontract, copies of the Contract Documents to which the Subcontractor will be bound. Each Subcontractor shall similarly make copies of such documents available to its sub- subcontractors. 33.5 Each Subcontractor performing work at the Project Site must agree to provide field (on-site) supervision through a named superintendent for each trade (e.g., general concrete forming and placement, masonry, mechanical, plumbing, electrical and roofing) included in its subcontract or purchase order. In addition, the Subcontractor shall assign and name a qualified employee for scheduling direction for its portion of the Work. The supervisory employees of the Subcontractor (including field superintendent, foreman and schedulers at all levels) must have been employed in a supervisory (leadership) capacity of substantially equivalent level on a similar project for at least two years within the last five years. The Subcontractor shall include a resume of experience for each employee identified by it to supervise and schedule its work. 33.6 Unless otherwise expressly waived by Owner in writing, all subcontracts and purchase orders shall provide: 54 Construction Services Agreement:[2024_ver.3] 33.6.1 That the Subcontractor's exclusive remedy for delays in the performance of the subcontract or purchase order caused by events beyond its control, including delays claimed to be caused by Owner or Design Professional or attributable to Owner or Design Professional and including claims based on breach of contract or negligence, shall be an extension of its contract time. 33.6.2 In the event of a change in the work, the Subcontractor's claim for adjustments in the contract sum are limited exclusively to its actual costs for such changes plus no more than 10% for overhead and profit. 33.6.3 The subcontract or purchase order, as applicable, shall require the Subcontractor to expressly agree that the foregoing constitute its sole and exclusive remedies for delays and changes in the Work and thus eliminate any other remedies for claim for increase in the contract price, damages, losses or additional compensation. Further, Contractor shall require all Subcontractors to similarly incorporate the terms of this Section 33.6 into their sub- subcontracts and purchase orders. 33.6.4 Each subcontract and purchase order shall require that any claims by Subcontractor for delay or additional cost must be submitted to Contractor within the time and in the manner in which Contractor must submit such claims to Owner, and that failure to comply with such conditions for giving notice and submitting claims shall result in the waiver of such claims. 34. CONSTRUCTION SERVICES. 34.1 Contractor shall maintain at the Project site, originals or copies of, on a current basis, all Project files and records, including, but not limited to, the following administrative records: 34.1.1 Subcontracts and Purchase Orders 34.1.2 Subcontractor Licenses 34.1.3 Shop Drawing Submittal/Approval Logs 34.1.4 Equipment Purchase/Delivery Logs 34.1.5 Contract Drawings and Specifications with Addenda 34.1.6 Warranties and Guarantees 34.1.7 Cost Accounting Records 34.1.8 Labor Costs 34.1.9 Material Costs 34.1.10 Equipment Costs 34.1.11 Cost Proposal Request 34.1.12 Payment Request Records 34.1.13 Meeting Minutes 34.1.14 Cost-Estimates 34.1.15 Bulletin Quotations 34.1.16 Lab Test Reports 34.1.17 Insurance Certificates and Bonds 34.1.18 Contract Changes 34.1.19 Permits 34.1.20 Material Purchase Delivery Logs 34.1.21 Technical Standards 34.1.22 Design Handbooks 34.1.23 "As-Built" Marked Prints 34.1.24 Operating & Maintenance Instruction 55 Construction Services Agreement:[2024_ver.3] 34.1.25 Daily Progress Reports 34.1.26 Monthly Progress Reports 34.1.27 Correspondence Files 34.1.28 Transmittal Records 34.1.29 Inspection Reports 34.1.30 Punch Lists 34.1.31 PM IS Schedule and Updates 34.1.32 Suspense (Tickler) Files of Outstanding Requirements The Project files and records shall be available at all times to Owner and Design Professional or their designees for reference, review or copying. 34.2 Contractor Presentations At the discretion of the County, the Contractor may be required to provide a brief update on the Project to the Collier County Board of County Commissioners, "Board", up to two (2) times per contract term. Presentations shall be made in a properly advertised Public Meeting on a schedule to be determined by the County Manager or his designee. Prior to the scheduled presentation date, the Contractor shall meet with appropriate County staff to discuss the presentation requirements and format. Presentations may include, but not be limited to, the following information: Original contract amount, project schedule, project completion date and any changes to the aforementioned since Notice to Proceed was issued. 35. SECURITY. The Contractor is required to comply with County Ordinance 2004-52, as amended. Background checks are valid for five (5) years and the Contractor shall be responsible for all associated costs. If required, Contractor shall be responsible for the costs of providing background checks by the Collier County Facilities Management Division for all employees that shall provide services to the County under this Agreement. This may include, but not be limited to, checking federal, state and local law enforcement records, including a state and FBI fingerprint check, credit reports, education, residence and employment verifications and other related records. Contractor shall be required to maintain records on each employee and make them available to the County for at least four(4) years. All of Contractor's employees and subcontractors must wear Collier County Government Identification badges at all times while performing services on County facilities and properties. Contractor ID badges are valid for one (1)year from the date of issuance and can be renewed each year at no cost to the Contractor during the time period in which their background check is valid, as discussed below. All technicians shall have on their shirts the name of the contractor's business. The Contractor shall immediately notify the Collier County Facilities Management Division via e-mail (DL-FMOPS aC colliercountvfl.gov)whenever an employee assigned to Collier County separates from their employment. This notification is critical to ensure the continued security of Collier County facilities and systems. Failure to notify within four (4) hours of separation may result in a deduction of$500 per incident. CCSO requires separate fingerprinting prior to work being performed in any of their locations. This will be coordinated upon award of the contract. If there are additional fees for this process, the Contractor is responsible for all costs. 36. VENUE. 56 Construction Services Agreement:[2024_ver.3] Any suit or action brought by either party to this Agreement against the other party relating to or arising out of this Agreement must be brought in the appropriate federal or state courts in Collier County, Florida, which courts have sole and exclusive jurisdiction on all such matters. 37. VALUE ENGINEERING. All projects with an estimated cost of $10 million or more shall be reviewed for consideration of a Value Engineering (VE) study conducted during project development. A"project" shall be defined as the collective contracts, which may include but not be limited to: design, construction, and construction, engineering and inspection (CEI) services. Additionally, any project with an estimated construction value of$2 million or more may be reviewed for VE at the discretion of the County. 38. ABOVEGROUND/UNDERGROUND TANKS. 38.1 The contractor shall ensure compliance with all NFPA regulations: specifically 110 & 30/30A; FDEP chapter 62 regulations: specifically 761, 762, 777, and 780; 376 & 403 Florida Statutes; and STI, UL, PEI, ASME, NACE, NLPA, NIST & API referenced standards pertaining to the storage of hazardous materials and petroleum products. 38.2 The contractor shall notify the Solid & Hazardous Waste Management Department (SHWMD) prior to the installation, removal, or maintenance of any storage tank, including day tanks for generators, storing/will be storing petroleum products or hazardous materials. The contractor shall provide a 10 day and 48-hour notice to SHWMD 239-252-2508 prior to commencement. The contractor shall provide the plans pertaining to the storage tank systems containing hazardous materials/petroleum products to the SHWMD prior to plans submittal to a permitting entity and then SHWMD must approve the plans prior to contractor's submittal for permitting. 39. STANDARDS OF CONDUCT: PROJECT MANAGER, SUPERVISOR, EMPLOYEES. The Contractor shall employ people to work on Owner's projects who are neat, clean, well-groomed and courteous. Subject to the Americans with Disabilities Act, Contractor shall supply competent employees who are physically capable of performing their employment duties. The Owner may require the Contractor to remove an employee it deems careless, incompetent, insubordinate or otherwise objectionable and whose continued employment on Owner's projects is not in the best interest of the County. 40. DISPUTE RESOLUTION. A. Prior to the initiation of any action or proceeding permitted by this Agreement to resolve disputes between the parties, the parties shall make a good faith effort to resolve any such disputes by negotiation. The negotiation shall be attended by representatives of Contractor with full decision-making authority and by Owner's staff person who would make the presentation of any settlement reached during negotiations to Owner for approval. Failing resolution, and prior to the commencement of depositions in any litigation between the parties arising out of this Agreement, the parties shall attempt to resolve the dispute through Mediation before an agreed-upon Circuit Court Mediator certified by the State of Florida. The mediation shall be attended by representatives of Contractor with full decision-making authority and by Owner's staff person or designee who would make the presentation of any settlement reached at mediation to Owner's Board for approval. Should either party fail to 57 Construction Services Agreement:[2024_ver.3] submit to mediation as required hereunder, the other party may obtain a court order requiring mediation under Section 44.102, Fla. Stat. Any suit or action brought by either party to this Agreement against the other party relating to or arising out of this Agreement must be brought in the appropriate federal or state courts in Collier County, Florida, which courts have sole and exclusive jurisdiction on all such matters. 58 Construction Services Agreement:[2024_ver.3] EXHIBIT I: SUPPLEMENTAL TERMS AND CONDITIONS ® Attached hereto, following this page ❑ Not Applicable 59 Construction Services Agreement:[2024_ver.3] EXHIBIT I FEDERAL CONTRACT PROVISIONS FEDERAL HOUSING AND URBAN DEVELOPMENT The supplemental conditions contained in this section are intended to cooperate with, to supplement, and to modify the general conditions and other specifications, In cases of disagreement with any other section of this contract, the Supplemental Conditions shall govern. Contractor means an entity that receives a contract. The services performed by the awarded Contractor shall be in compliance with all applicable grantor regulations/requirements, and additional requirements specified in this document. It shall be the awarded Contractor's responsibility to acquire and utilize the necessary manuals and guidelines that apply to the work required to complete this project. In general, 1) The contractor (including all subcontractors) must insert these contract provisions in each lower tier contracts(e.g., subcontract or sub-agreement); 2)The contractor(or subcontractor)must incorporate the applicable requirements of these contract provisions by reference for work done under any purchase orders, rental agreements and other agreements for supplies or services; 3) The prime contractor is responsible for compliance with these contract provisions by any subcontractor, lower-tier subcontractor, or service provider. ® 1. Access to Records ® 2. Administrative, Contractual or Legal Remedies ® 3, Conflict of Interest ® 4. Debarment ® 5. Domestic Preference ® 6. Energy Efficiency ® 7, Environmental Compliance (Clean Air and Water Acts) ® 8. E-Verify ® 9. Equal Opportunity Provisions ® 10. Section 3 ® 11. Utilization of Minority and Women's Businesses ❑ 12. Federal Labor Standards Provisions (Davis Bacon, Copeland) ® Federal Labor Standards Provisions (Contract Work Hours Act) ® 13. Guidance to Contractor for Compliance With Labor Standard Provisions ® 14. Grantee Recognition (Advertisement) ® 15. Historic Preservation ® 16. Lobbying Prohibition Z 17. Procurement of Recovered Materials ® 18. Prohibition of Certain Telecommunications and Video Equipment ® 19. Record Keeping and Retention ® 20. Religious Organizations ® 21. Copyright and Patent Rights ® 22. Termination FPC- 1 EXHIBIT I FEDERAL CONTRACT PROVISIONS 1. ACCESS TO RECORDS The local government,the U.S. Department of Housing and Urban Development,the Comptroller General of the United States,the Chief Financial Officer of the State of Florida, the Auditor General of the State of Florida,the Florida Office of Program Policy Analysis and Government Accountability, and any of their duly authorized representatives, shall have access to any books,documents, papers, and records of the contractor which are directly pertinent to this contract for the purpose of making audit,examination,excerpts,and transcriptions. Florida Inspector General Cooperation -The Parties agree to comply with Section 20.055(5), Florida Statutes,for the inspector general to have access to any records,data and other information deemed necessary to carry out his or her duties and incorporate into all subcontracts the obligation to comply with Section 20.055(5),Florida Statutes. 2. ADMINISTRATIVE, CONTRACTUAL, OR LEGAL REMEDIES Unless otherwise provided in this contract, all claims, counterclaims,disputes,and other matters in question between the local government and the contractor, arising out of or relating to this contract, or the breach of it,will be decided by arbitration, if the parties mutually agree,or in a Florida court of competent jurisdiction. 3. CONFLICT OF INTEREST OF OFFICERS OR EMPLOYEES OF THE LOCAL JURISDICTION,MEMBERS OF THE LOCAL GOVERNING BODY,OR OTHER PUBLIC OFFICIALS No officer or employee of the local jurisdiction or its designees or agents,no member of the governing body,and no other public official of the locality who exercises any function or responsibility with respect to this contract,during his/her tenure or for one year thereafter, shall have any interest,direct or indirect, in any contract or subcontract, or the proceeds thereof, for work to be performed.Further,the Contractor shall cause to be incorporated in all subcontracts the language set forth in this paragraph prohibiting conflict of interest. 4.DEBARMENT Contract awards that exceed the small purchase threshold and certain other contract awards shall not be made to parties listed on the government wide Excluded Parties List System in the System for Award Management(SAM),in accordance with the OMB guidelines at 2 CFR 180 that implement Executive Orders 12549(3 CFR Part 1986 Comp., p. 189) and 12689 (3 CFR Part 1989 Comp., p. 235), "Debarment and Suspension."The Excluded Parties List System in SAM contains the names of parties debarred,suspended,or otherwise excluded by agencies,as well as parties declared ineligible under statutory or regulatory authority other than Executive Order 12549. The successful bidder, by administering each lower tier subcontract that exceeds $25,000 as a "covered transaction", must verify each lower tier participant of a "covered transaction" under the project is not presently debarred or otherwise disqualified from participation in this federally assisted project. 5. DOMESTIC PREFERENCES FOR PROCUREMENTS: (Reference 2 CRF § 200.322) (a) As appropriate and to the extent consistent with law,the non-Federal entity should,to the greatest extent practicable under a Federal award,provide a preference for the purchase, acquisition, or use of goods, products, or materials produced in the United States(including but not limited to iron, aluminum, steel, cement, and other manufactured products). The requirements of this section must be included in all subawards including all contracts and purchase orders for work or products under this award.(b)For purposes of this section: (1) "Produced in the United States"means,for iron and steel products,that all manufacturing processes,from the initial melting stage through the application of coatings, occurred in the United States. (2) "Manufactured products" means items and construction materials composed in whole or in part of non-ferrous metals such as aluminum; plastics and polymer-based products such as polyvinyl chloride pipe;aggregates such as concrete;glass,including optical fiber;and lumber. 6. ENERGY EFFICIENCY The contractor shall comply with any mandatory standards and policies relating to energy efficiency which are contained in the state energy conservation plan issued in compliance with the Energy Policy and Conservation Act (Public Law 94-163)for the State in which the work under this contract is performed. 7.ENVIRONMENTAL COMPLIANCE If this contract exceeds$150,000,the contractor shall comply with all applicable standards, orders,or requirements issued under section 306 of the Clean Air Act(42 U.S.C. 1857(h),section 508 of the Clean Water Act(33 U.S.C. 1368),Executive Order 11738,and U.S. Environmental Protection Agency regulations(40 C.F.R.Part 15).The contractor shall include this clause in any subcontracts over$150,000. 8. E-VERIFY Vendors/Contractors shall: 1. utilize the U.S. Department of Homeland Security's E:Verify system to verity the employment eligibility of all new employees hired by the Vendor/Contractor during the term of the contract;and 2.expressly require any subcontractors performing work or providing services pursuant to the state contract to likewise utilize the U.S.Department of Homeland Security's E:Verify system to verify the employment eligibility of all new employees hired by the subcontractor during the contract term. FPC-2 EXHIBIT I FEDERAL CONTRACT PROVISIONS 9. EQUAL OPPORTUNITY a. Activities and Contracts Not Subject to Executive Order 11246,as Amend& (Applicable to Federally assisted construction contracts and related subcontracts$10,000 and under.) During the performance of this contract, the Contractor agrees as follows: i.The Contractor shall not discriminate against any employee or applicant for employment because of race, color, religion, sex, or national origin. The Contractor shall take affirmative action to ensure that applicants for employment are employed, and that employees are treated during employment, without regard to their race, color, religion, sex, sexual orientation, gender identity, or national origin. Such action shall include, but not be limited to, the following: employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation;and selection for training, including apprenticeship. ii.The Contractor shall post in conspicuous places, available to employees and applicants for employment, notices to be provided by Contracting Officer seeking forth the provisions of this nondiscrimination clause. The Contractor shall state that all qualified applicants be considered without regard to race, color, religion, sex,sexual orientation,gender identity,or national origin. iii.Contractors shall incorporate foregoing requirements in all subcontracts. b. Executive Order 11246,as Amended(through 2014),Section 202 Equal Opportunity Clause (Applicable to contracts/subcontracts above$10,000) During the performance of this contract,the contractor agrees as follows: i.The Contractor will not discriminate against any employee or applicant for employment because of race, color, religion, sex, sexual orientation, gender identity, or national origin. The Contractor will take affirmative action to ensure that applicants are employed,and that employees are treated during employment,without regard to their race,color,religion,sex,sexual orientation, gender identity,or national origin.Such action shall include,but not be limited to,the following:employment,upgrading,demotion, or transfer;recruitment,or recruitment advertising;layoff or termination,rates of pay or other forms of compensation;and selection for training,including apprenticeship.The Contractor agrees to post in conspicuous places,available to employees and applicants for employment, notices to be provided by the contracting officer setting forth the provisions of this nondiscrimination clause. ii.The Contractor will, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, sexual orientation, gender identity,or national origin. iii.The contractor will not discharge or in any other manner discriminate against any employee or applicant for employment because such employee or applicant has inquired about,discussed,or disclosed the compensation of the employee or applicant or another employee or applicant.This provision shall not apply to instances in which an employee who has access to the compensation information of other employees or applicants as a part of such employee's essential job functions discloses the compensation of such other employees or applicants to individuals who do not otherwise have access to such information,unless such disclosure is in response to a formal complaint or charge, in furtherance of an investigation, proceeding, hearing, or action, including an investigation conducted by the employer,or is consistent with the contractor's legal duty to furnish information." iv,The Contractor will send to each labor union or representative of workers with which he has a collective bargaining agreement or other contract or understanding, a notice, to be provided by the agency contracting officer advising the said labor union or worker's representatives of the Contractor's commitment under Section 202 of Executive Order No.11246 of September 24, 1965 and shall post copies of the notice in conspicuous places available to employees and applicants for employment. v.The Contractor will comply with all provisions of Executive Order 11246 of September 24, 1965,and by the Rules, Regulations, and Relevant Orders of the Secretary of Labor. vi.The Contractor will furnish all information and reports required by Executive Order 11246 of September 24, 1965,and by rules, regulations,and orders of the Secretary of Labor,or pursuant thereto,and will permit access to his books,records,and accounts FPC-3 EXHIBIT I FEDERAL CONTRACT PROVISIONS by the contracting agency and the Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations,and orders. vii.ln the event of the Contractor's noncompliance with the nondiscrimination clauses of this contract or with any of the said rules, regulations, or orders, this contract may be canceled, terminated, or suspended in whole or in part and the contractor may be declared ineligible for further Government contracts in accordance with procedures authorized in Executive Order 11246 of September 24,1965,and such other sanctions may be imposed and remedies invoked as provided in Executive Order No.11246 of September 24, 1965,or by rule,regulation,or order of the Secretary of Labor,or as otherwise provided by law. viii.The Contractor will include the Provisions of paragraphs(1)through(7)in every subcontract or purchase order unless exempted by rules,regulations,or orders of the Secretary of Labor issued pursuant to Section 204 of Executive Order 11246 of September 24, 1965, so that such provisions will be binding upon each subcontractor or vendor.The Contractor will take such action with respect to any subcontract or purchase order as may be directed by the Secretary of Labor as a means of enforcing such provisions, including sanctions for noncompliance. Provided, however,that in the event a Contractor becomes involved in, or is threatened with, litigation with a subcontractor or vendor as a result of such direction, the contractor may request the United States to enter into such litigation to protect the interests of the United States. c. Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity (Executive Order 11246). (Applicable to construction contracts/subcontracts exceeding$10,000.) (a) The Offeror's or Bidder's attention is called to the "Equal Opportunity Clause" and the "Standard Federal Equal Employment Opportunity Construction Contract Specifications"set forth herein. (b) The goals and timetables for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area,are as follows: Female participation:6.9%(statewide) Minority participation:17.1%Collier County These goals are applicable to all Contractor's construction work(whether or not it is federally- assisted) performed in the covered area. If the Contractor performs construction work in a geographic area located outside of the covered area, it shall apply the goals established for such geographic area where the work is actually performed. With regard to this second area, the Contractor also is subject to the goals for both its Federally involved and non-Federally involved construction. The Contractor's compliance with Executive Order and the regulations in 41 CFR Part 60-4 shall be based on its implementation of the Equal Opportunity Clause, specific affirmative action obligations required by the specifications set forth in 41 CFR 60-4.3 (a), and its efforts to meet the goals established or the geographic area where the contract resulting from his solicitation is to be performed. The hours of minority and female employment or training must be substantially uniform throughout the length of the contract and in each trade the Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects.The transfer of minority or female employees or trainees from Contractor to Contractor or from project to project for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, the Executive Order, and the regulations in 41 CFR Part 60-4. Compliance with the goals will be measured against the total work hours performed. (c) The Contractor shall provide written notification to the County within 10 working days of award of any construction subcontract in excess of$10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the name, address, and telephone number of the subcontractor;employer identification number; estimated dollar amount of the subcontract; estimated starting and completion dates of the subcontract; and the geographical area in which the contract is to be performed. Contact Information: Collier County Government—CHS Section 3 Manager 3339 East Tamiami Trail E, STE 211 Ms.Kristi Sonntag Naples,Florida 34112 Telephone:239-252-2486 Telephone 239-252-2273 kristiSonntag@colliergov.net Fax 239-252-2638 FPC-4 EXHIBIT I FEDERAL CONTRACT PROVISIONS Section 3 I Collier County, FL(colliercountyfl.gov) (d) As used in this Notice,and in the contract resulting from the solicitation, the "covered area"is the county in which the contract work is being undertaken. d. 41 CFR 60-4.3 Equal Opportunity Clauses (a). The equal opportunity clause published at 41 CFR 60-1.4(a)of this chapter is required to be included in, and is part of, all nonexempt Federal contracts and subcontracts,including construction contracts and subcontracts.The equal opportunity clause published at 41 CFR 60-1.4(b) is required to be included in, and is a part of, all nonexempt federally assisted construction contracts and subcontracts.In addition to the clauses described above,all Federal contracting officers,all applicants and all non- construction contractors,as applicable,shall include the specifications set forth in this section in all Federal and federally assisted construction contracts in excess of$10,000 to be performed in geographical areas designated by the Director pursuant to§60- 4.6 of this part and in construction subcontracts in excess of$10,000 necessary in whole or in part to the performance of non- construction Federal contracts and subcontracts covered under the Executive order. Standard Federal Equal Employment Opportunity Construction Contract Specifications (Executive Order 11246). 1. As used in these specifications: A. "Covered area" means the geographical area described in the solicitation from which this contract resulted; B. "Director"means Director,Office of Federal Contract Compliance Programs, United States Department of Labor,or any person to whom the Director delegates authority; C. "Employer identification number"means the Federal Social Security number used on the Employer's quarterly Federal Tax Return,U.S.Treasury Department Form 941. D. "Minority"includes: (I) Black (all persons having origins in any of the Black African racial groups not of Hispanic origin); (II) Hispanic(all persons of Mexican, Puerto Rican, Cuban, Central, or South American or other Spanish Culture or origin,regardless of race); (III) Asian and Pacific Islander(all persons having origin in any of the original peoples of the Far East, Southeast Asia,the Indian Subcontinent,or the Pacific Island);and (IV) American Indian or Alaskan Native(all persons having origins in any of the original peoples of North America and maintaining identifiable tribal affiliations through membership and participation or community identification). 2. Whenever the Contractor,or any Subcontractor at any tier, subcontracts a portion of the work involving any construction trade, it shall physically include in each subcontract in excess of$10,000 the provisions of these specifications and the Notice which contains the applicable goals for minority and female participation, which is set forth in the solicitations from which this contract resulted. 3. If the Contractor is participating (pursuant to 41 CFR 60-4.5) in a Hometown Plan approved by the U.S. Department of Labor in the covered area either individually or through an association, its affirmative action obligations on all work in the Plan area (including goals and timetables) shall be in accordance with that Plan for those trades which have unions participating in the Plan. Contractors must be able to demonstrate their participation in and compliance with the provisions of any such Hometown Plan. Each Contractor or Subcontractor participating in an approved Plan is individually required to comply with its obligations under the EEO clause, and to make a good faith effort to achieve each goal under the Plan in each trade in which it has employees. The overall good faith performance by other Contractor's or Subcontractor's toward a goal in an approved Plan does not excuse any covered Contractor's or Subcontractor's failure to take good faith efforts to achieve the Plan goals and timetables 4. The Contractor shall implement the specific affirmative action standards provided in paragraphs(7) (A)through (P), of these specifications.The goals set forth in the solicitation from which this contract resulted are expressed as percentages of the total hours of employment and training of minority and female utilization the Contractor should reasonably be able to achieve in each construction trade in which it has employees in the covered area. Covered construction contractors performing contracts in geographical areas where they do not have a Federal or Federally assisted construction contract shall apply the minority and female goals established for the geographic area where the contract is being performed.Goals are published periodically in the Federal Register in notice form and FPC-5 EXHIBIT I FEDERAL CONTRACT PROVISIONS such notices may be obtained from any Office of Federal Contract Compliance Programs office or from Federal procurement contracting officers.The Contractor is expected to make substantially uniform progress in meeting its goals in each craft during the period specified. 5. Neither the provisions of any collective bargaining agreement, nor the failure by a union with whom the Contractor has a collective bargaining agreement, to refer either minorities or women shall excuse the Contractor's obligations under these specifications,Executive Order 11246,or the regulations promulgated pursuant thereto. 6. In order for the nonworking training hours of apprentices and trainees to be counted in meeting goals,such apprentices and trainees must be employed by the Contractor during the training period,and the Contractor must have made a commitment to employ the apprentices and trainees at the completion of their training,subject to the availability of employment opportunities.Trainees must be trained pursuant to training programs approved by the U.S.Department of Labor. 7. The Contractor shall take specific affirmative actions to ensure equal employment opportunity.The evaluation of the Contractor's compliance with these specifications shall be based upon its effort to achieve maximum results from its actions,The Contractor shall document these efforts fully,and shall implement affirmative action steps at least as extensively as the following: (a) Ensure and maintain a working environment free of harassment, intimidation, and coercion at all sites, and in all facilities at which the Contractor's employees are assigned to work. The Contractor,where possible, will assign two or more women to each construction project. The Contractor shall specifically ensure that all foremen, superintendents, and other on-site supervisory personnel are aware of and carry out the Contractor's obligation to maintain such a working environment, with specific attention to minority or female individuals working at such sites in such facilities. (b) Establish and maintain a current list of minority and female recruitment sources,provide written notification to minority and female recruitment sources and to community organizations when the Contractor or its unions have employment opportunities available,and maintain a record of the organization's responses. (c) Maintain a current file of the names,addresses,and telephone numbers of each minority or female off-the-street applicant and minority or female referral from a union,a recruitment source,or community organization and of what action was taken with respect to each such individual.If such individual was sent to the union hiring hall for referral and was not referred back to the Contractor by the union, or if referred, not employed by the Contractor, this shall be documented in the file with the reason therefore along with whatever additional actions the Contractor may have taken. (d) Provide immediate written notification to the Director when the union or unions with which the Contractor has a collective bargaining agreement has not referred to the Contractor a minority person or woman sent by the Contractor, or when the Contractor has other information that the union referral process has impeded the Contractor's efforts to meet its obligations. (e) Develop on-the-job training opportunities and/or participate in training programs for the areas which expressly include minorities and women, including upgrading programs and apprenticeship and trainee programs relevant to the Contractor's employment needs,especially those programs funded or approved by the Department of Labor.The Contractor shall provide notice of these programs to the sources compiled under 7.(b)above. (f) Disseminate the Contractor's EEO policy by providing notice of the policy to unions and training programs and requesting their cooperation in assisting the Contractor in meeting its EEO obligations;by including it in any policy manual and collective bargaining agreement;by publicizing it in the company newspaper,annual report,etc.; by specific review of the policy with all management personnel and with all minority and female employees at least once a year; and by posting the company EEO policy on bulletin boards accessible to all employees at each location where construction work is performed. (g) Review,at least annually,the company's EEO policy and affirmative action obligations under these specifications with all employees having any responsibility for hiring,assignment,layoff,termination,or other employment decisions including specific review of these items with on-site supervisory personnel such as Superintendents,General Foremen,etc.,prior to the initiation of construction work at any job site. A written record shall be made and maintained identifying the time and place of these meetings,persons attending,subject matter discussed,and disposition of the subject matter. (h) Disseminate the Contractor's EEO policy externally by including it in any advertising in the news media, specifically including minority and female news media,and providing written notification to and discussing the Contractor's EEO policy with FPC-6 EXHIBIT I FEDERAL CONTRACT PROVISIONS other Contractors and Subcontractors with whom the Contractor does or anticipates doing business. (i) Direct its recruitment efforts, both oral and written, to minority, female, and community organizations, to schools with minority and female recruitment students and to minority and female recruitment and training organizations serving the Contractor's recruitment area and employment needs. Not later than one month prior to the date for the acceptance of applications for apprenticeship or other training by any recruitment source, the Contractor shall send written notification to organizations such as the above,describing the openings,screening procedures,and tests to be used in the selection process. (j) Encourage present minority and female employees to recruit other minority persons and women and,where reasonable, provide after school, summer and vacation employment to minority and female youth both on the site and in other areas of a Contractor's work force. (k) Validate all tests and other selection requirements where there is an obligation to do so under 41 CFR 60-3. (I) Conduct, at least annually, an inventory and evaluation at least of all minority and female personnel for promotional opportunities and encourage these employees to seek or to prepare for,through appropriate training,etc.,such opportunities. (m) Ensure that seniority practices, job classifications, work assignments and other personnel practices, do not have a discriminatory effect by continually monitoring all personnel and employment related activities to ensure that the EEO policy and the Contractor's obligations under these specifications are being carried out. (n) Ensure that all facilities and company activities are nonsegregated except that separate or single-user toilet and necessary changing facilities shall be provided to assure privacy between the sexes (o) Document and maintain a record of all solicitations of offers for subcontracts from minority and female construction contractors and suppliers,including circulation of solicitations to minority and female contractor associations and other business associations. (p) Conduct a review,at least annually,of all supervisor's adherence to and performance under the Contractor's EEO policies and affirmative action obligations. (q) become familiar with the HUD"Questions and Answers on Sexual Harassment under the Fair Housing Act."And request a copy from the County if needed. 8. Contractors are encouraged to participate in voluntary associations which assist in fulfilling one or more of their affirmative action obligations(7) (a)through (p).The efforts of a contractor association,joint contractor-union, contractor-community, or other similar group of which the Contractor is a member and participant,may be asserted as fulfilling any one or more of its obligations under(7) (a)through(p)of these Specifications provided that the Contractor actively participates in the group,makes every effort to assure that the group has a positive impact on the employment of minorities and women in the industry,ensures that the concrete benefits of the program are reflected in the Contractor's minority and female workforce participation, makes a good faith effort to meet its individual goals and timetables,and can provide access to documentation which demonstrates the effectiveness of actions taken on behalf of the Contractor.The obligation to comply,however,is the contractor's and failure of such a group to fulfill an obligation shall not be a defense for the Contractor's noncompliance. 9. A single goal for minorities and separate single goal for women have been established.The Contractor,however,is required to provide equal employment opportunity and to take affirmative action for all minority groups,both male and female,and all women,both minority and non-minority.Consequently,the Contractor may be in violation of the Executive Order if a particular group is employed in a substantially disparate manner(for example,even though the Contractor has achieved its goals for women generally,the Contractor may be in violation of the Executive Order if a specific minority group of women is underutilized). 10. The Contractor shall not use the goals and timetables or affirmative action standards to discriminate against any person because of race,color,religion,sex,or national origin. 11. The Contractor shall not enter into any Subcontract with any person or firm debarred from Government contracts pursuant to Executive Order 11246. FPC-7 EXHIBIT I FEDERAL CONTRACT PROVISIONS 12. The Contractor shall carry out sections and penalties for violation of these specifications and of the Equal Opportunity Clause, including suspension,termination and cancellation of existing subcontracts as maybe imposed or ordered pursuant to Executive Order 11246,as amended,and its implementing regulations,by the Office of Federal Contract Compliance Programs.Any Contractor who fails to carry out such sanctions and penalties shall be in violation of these specifications and Executive Order 11246,as amended. 13. The Contractor, in fulfilling its obligations under these specifications,shall implement specific affirmative action steps, at least as extensively as those standards prescribed in paragraph 7 of these specifications,so as to achieve maximum results from its effort to ensure equal employment opportunity.If the Contractor fails to comply with the requirement of the Executive Order,the implementing regulations,or these specifications,the Director shall proceed in accordance with 41 CFR 60-4.8. 14. The contractor shall designate a responsible official to monitor all employment related activity to ensure that the company EEO policy is being carried out, to submit reports relating to the provisions hereof as may be required by the Government and to keep records.Records shall at least include for each employee,the name,address,telephone numbers,construction trade,union affiliation, if any,employee identification number where assigned, social security number,race,sex,status(e.g.,mechanic,apprentice trainee, helper,or laborer),dates of changes in status, hours worked per week in the indicated trade,rate of pay, and location at which the work was performed. Records shall be maintained in an easily understandable and retrievable form; however, to the degree that existing records satisfy this requirement,contractors shall not be required to maintain separate records. 15. Nothing herein provided shall be construed as a limitation upon the application of other laws which establish different standards of compliance and upon the application of requirements for the hiring of local or other area residents(e.g., those under the Public Works Employment Act of 1977 and the Community Development Block Grant Program). E. Certification of Non-Segregated Facilities(Construction Contracts over$10,000) The contractor does not maintain or provide for its employees to perform their services at any location, under its control, where segregated facilities are maintained.The contractor certifies further that it will not maintain or provide for its employees any segregated facilities at any of its establishments,and that it will not permit employees to perform their services at any location, under its control, where segregated facilities are maintained. The contractor agrees that a breach of this certification is a violation of the Equal Opportunity Clause in this contract. As used in this certification, the term "segregated facilities" means any waiting rooms, work areas, rest rooms and wash rooms, restaurants, and other eating areas,time clocks,locker rooms,and other storage or dressing areas,parking lots,drinking fountains, recreation or entertainment areas, transportation and housing facilities which are segregated by explicit directive or are in fact segregated on the basis of race,creed,color,or national origin,because of habit,local custom,or otherwise. The contractor further agrees that(except where it has obtained identical certifications from proposed subcontractors for specific time periods) it will obtain identical certifications from proposed subcontractors prior to the award of subcontractors exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity Clause;that it will retain such certifications in its files;and that it will forward the following notice to such proposed subcontractors(except where the proposed subcontractors have submitted identical certifications for specific time periods). F. Civil Rights Act of 1964 Under Title VI of the Civil Rights Act of 1964, no person shall, on the grounds of race, color, or national origin, be excluded from participation in, be denied the benefits of,or be subjected to discrimination under any program or activity receiving Federal financial assistance. G. Section 109 of the Housing and Community Development Act of 1974 No person in the United States shall on the grounds of race,color,national original,or sex be excluded from participation in,be denied the benefits of,or be subjected to discrimination under any program or activity funded in whole or in part with funds made available under this title. H.Section 503 Handicapped(Contracts$2,500 or Over) (1) The Contractor will not discriminate against any employee or applicant for employment because of physical or mental handicap in regard to any position for which the employee or applicant for employment is qualified. The Contractor agrees to take affirmative action to employ, advance in employment and otherwise treat qualified handicapped individuals without discrimination based upon their physical or mental handicap in all employment practices such as the following: employment, upgrading, demotion or transfer, recruitment, advertising, layoff or termination, rates of pay or other forms of compensation, FPC-8 EXHIBIT I FEDERAL CONTRACT PROVISIONS II. The parties to this contract agree to comply with HUD's regulations in 24 CFR Part 135, which implement section 3.As evidenced by their execution of this contract, the parties to this contract certify that they are under no contractual or other impediment that would prevent them from complying with the Part 135 regulations. III. The contractor agrees to send to each labor organization or representative of workers with which the contractor has a collective bargaining agreement or other understanding, if any, a notice advising the labor organization or workers' representative of the contractor's commitments under this Section 3 clause and will post copies of the notice in conspicuous places at the work site where both employees and applicants for training and employment positions can see the notice. The notice shall describe the S ection 3 preference, shall set forth minimum number and job titles subject to hire, availability of apprenticeship and training positions, the qualifications for each; and the name and location of the person(s)taking applications for each of the positions; and the anticipated date the work shall begin. IV. The contractor agrees to include this S ection 3 clause in every subcontract subject to compliance with regulations in 24 CFR part 135, and agrees to take appropriate action, as provided in an applicable provision of the subcontract or in this section 3 clause,upon a finding that the subcontractor is in violation of the regulations in 24 CFR part 135. The contractor will not subcontract with any subcontractor where the contractor has notice or knowledge that the subcontractor has been found in violation of the regulations in 24 CFR part 135. V. The contractor will certify that any vacant employment positions, including training positions, that are filled (1) after the contractor is selected but before the contract is executed, and (2) with persons other than those to whom the regulations of 24 CFR part 135 require employment opportunities to be directed, were not filled to circumvent the contractor's obligations under 24 CFR part 135. VI. Noncompliance with HUD's regulations in 24 CFR part 135 may result in sanctions, termination of this contract for default,and debarment or suspension from future HUD assisted contracts. VII, With respect to work performed in connection with Section 3 covered Indian housing assistance, section 7(b) of the Indian Self-Determination and Education Assistance Act (25 U.S.C. 450e)also applies to the work to be performed under this contract. Section 7(b) requires that to the greatest extent feasible (i) preference and opportunities for training and employment shall be given to Indians, and (ii) preference in the award of contracts and subcontracts shall be given to Indian organizations and Indian-owned Economic Enterprises. Parties to this contract that are subject to the provisions of section 3 and section 7(b)agree to comply with S ection 3 to the maximum extent feasible, but not in derogation of compliance with section 7(b). Additional Provisions§75.9 Requirements. (a)Employment and training. (1)Consistent with existing Federal,state,and local laws and regulations,PHAs or other recipients receiving public housing financial assistance,and their contractors and subcontractors,must make their best efforts to provide employment and training opportunities generated by the public housing financial assistance to Section 3 workers. (2)PHAs or other recipients,and their contractors and subcontractors,must make their best efforts described in paragraph (a)(1)of this section in the following order of priority: (i)To residents of the public housing projects for which the public housing financial assistance is expended. (ii)To residents of other public housing projects managed by the PHA that is providing the assistance or for residents of Section 8-assisted housing managed by the PHA; (iii)To participants in YouthBuild programs;and (iv)To low-and very low-income persons residing within the metropolitan area(or nonmetropolitan county)in which the assistance is expended. (b)Contracting. (1)Consistent with existing Federal,state,and local laws and regulations,PHAs and other recipients of public housing financial assistance,and their contractors and subcontractors,must make their best efforts to award contracts and subcontracts to business concerns that provide economic opportunities to Section 3 workers. (2)PHAs and other recipients,and their contractors and subcontractors,must make their best efforts described in paragraph(b)(1)of this section in the following order of priority: FPC-10 EXHIBIT I FEDERAL CONTRACT PROVISIONS and selection for training, including apprenticeship. (2) The Contractor agrees to comply with the rules, regulations and relevant orders of the Secretary o f Labor issued pursuant to the Act. (3) In the event of the Contractor's noncompliance with the requirements of this clause, actions for noncompliance may be taken in accordance with the rules, regulations, and relevant orders of the Secretary of Labor issued pursuant to the Act. (4) The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices in a form to be prescribed by the Director, provided by or through the contracting officer. Such notices shall state the Contractor's obligation under the law to take affirmative action to employ and advance in employment qualified handicapped employees and applicants for employment,and the rights of applicants and employees. (5) The Contractor will notify each labor union or representative of workers with which it has a collective bargaining agreement or their contract understanding that the contractor is bound by the terms of Section 503 of the Rehabilitation Act of 1973 and is committed to take affirmative action to employ and advance in employment physically and mentally handicapped individuals. (6) The Contractor will include the provisions of this clause in every subcontract or purchase order of$2,500 or more unless exempted by rules, regulations, or orders of the Secretary issued pursuant to Section 503 of the Act, so that such provisions will be binding upon each subcontractor or vendor. The Contractor will take such action with respect to any subcontract or purchase order as the Director of the Office of Federal Contract Compliance Programs may direct to enforce such provisions,including action for noncompliance. I.Age Discrimination in Employment Act of 1967,as Amended It shall be unlawful for an employer- (1) to fail or refuse to hire or to discharge any individual or otherwise discriminate against any individual with respect to his compensation,terms,conditions,or privileges of employment,because of such individual's age; (2)to limit,segregate,or classify his employees in any way which would deprive or tend to deprive any individual of employment opportunities or otherwise adversely affect his status as an employee,because of such individual's age;or (3)to reduce the wage rate of any employee in order to comply with this chapter. J.Title II of the Genetic Information Nondiscrimination Act of 2008(GINA) (1)Under Title II of the Genetic Information Nondiscrimination Act,it is illegal to discriminate against employees or applicants because of genetic information. Employers are prohibited from using genetic information in making employment decisions. GINA restricts employers and other entities covered by Title II(employment agencies,labor organizations and joint labor- management training and apprenticeship programs-referred to as"covered entities")from requesting, requiring,or purchasing genetic information, and strictly limits the disclosure of genetic information.The law forbids discrimination on the basis of genetic information when it comes to any aspect of employment,including hiring,firing, pay,job assignments,promotions, layoffs,training,fringe benefits,or any other term or condition of employment. (2)"Genetic information"includes information about an individual's genetic tests and the genetic tests of an individual's family members, as well as information about the manifestation of a disease or disorder in an individual's family members(i.e.,family medical history).Family medical history is included in the definition of genetic information because it is often used to determine whether someone has an increased risk of getting a disease,disorder,or condition in the future. 10. "SECTION 3"TRAINING,EMPLOYMENT AND BUSINESS OPPORTUNITIES I. The work to be performed under this contract is subject to the requirements of section 3 of the Housing and Urban Development Act of 1968, as amended, 12U.S.C. 1701u (section 3). The purpose of Section 3 is to ensure that employment and other economic opportunities generated by HUD assistance or HUD- assisted projects covered by section 3, shall, to the greatest extent feasible, be directed to low- and very low-income persons, particularly persons who are recipients of HUD assistance for housing. FPC-9 EXHIBIT I FEDERAL CONTRACT PROVISIONS (i)To Section 3 business concerns that provide economic opportunities for residents of the public housing projects for which the assistance is provided; (ii)To Section 3 business concerns that provide economic opportunities for residents of other public housing projects or Section-8 assisted housing managed by the PHA that is providing the assistance; (iii)To YouthBuild programs;and (iv)To Section 3 business concerns that provide economic opportunities to Section 3 workers residing within the metropolitan area(or nonmetropolitan county)in which the assistance is provided. VIII. UTILIZATION OF MINORITY AND WOMEN FIRMS(M/WBE)The contractor shall take all necessary affirmative steps to assure that M/WBE firms are utilized when possible as suppliers and/or subcontractors,as applicable. Prior to contract award, the contractor shall document efforts to utilize M/WBE firms, including identifying what firms were solicited as suppliers and/or subcontractors, as applicable. Information regarding certified M/WBE firms can be obtained from: • Florida Department of Management Services,Office of Supplier Diversity, • Florida Department of Transportation(construction services,particularly highway), • Minority Business Development Center in most major cities,and • Local government M/WBE programs in many large counties and cities. A firm recognized as an M/WBE by any of the above agencies is acceptable for the CDBG program. IX. FEDERAL LABOR STANDARDS PROVISIONS (Davis-Bacon Act, Copeland Act, and Contract Works Hours&Safety Standards Act) The Project to which the construction work covered by this contract pertains is being assisted by the United States of America and the following Federal Labor Standards Provisions are included in this Contract pursuant to the provisions applicable to such Federal assistance. A. (1) (a) Minimum Wages. All laborers and mechanics employed or working upon the site of the work (or under the United States Housing Act of 1937 or under the Housing Act of 1949 in the construction or development of the project),will be paid unconditionally and not less often than once a week, and without subsequent deduction or rebate on any account(except such payroll deductions as are permitted by regulations issued by the Secretary of Labor under the Copeland Act(29 CFR Part 3), the full amount of wages and bona fide fringe benefits (or cash equivalents thereof) due at time of payment computed at rates not less than those contained in the wage determination of the Secretary of Labor which is attached hereto and made a part hereof, regardless of any contractual relationship which may be alleged to exist between the contractor and such laborers and mechanics. Contributions made or costs reasonably anticipated for bona fide fringe benefits under Section 1(b)(2) of the Davis-Bacon Act on behalf of laborers or mechanics are considered wages paid to such laborers or mechanics, subject to the provisions of 29 CFR 5.5(a)(1)(iv); also, regular contributions made or costs incurred for more than a weekly period (but not less often than quarterly) under plans, funds, or programs, which cover the particular weekly period, are deemed to be constructively made or incurred during such weekly period. Such laborers and mechanics shall be paid the appropriate wage rate and fringe benefits on the wage determination for the classification of work actually performed, without regard to skill, except as provided in 29 CFR Part 5.5(a)(4). Laborers or mechanics performing work in more than one classification may be compensated at the rate specified for each classification for the time actually worked therein; provided, that the employer's payroll records accurately set forth the time spent in each classification in which work is performed. The wage determination (including any additional classification and wage rates conformed under 29 CFR Part 5.5(a)(1)(ii) and the Davis-Bacon poster (WH-1321) shall be posted at all times by the contractor and its subcontractors at the site of the work in a prominent and accessible place where it can be easily seen by the workers. (b) (i) Any class of laborers or mechanics which is not listed in the wage determination and which is to be employed under the contract shall be classified in conformance with the wage determination.HUD shall approve an additional classification and wage rate and fringe benefits; therefore, only when the following criteria have been met: (1) The work to be performed by the classification requested is not performed by a classification in the wage determination;and (2) The classification is utilized in the area by the construction industry;and (3) The proposed wage rate, including any bona fide fringe benefits, bears a reasonable relationship to the wage rates contained in the wage determination. FPC-11 EXHIBIT I FEDERAL CONTRACT PROVISIONS (ii) If the contractor and the laborers and mechanics to be employed in the classification (if known), or their representatives, and HUD or its designee agree on the classification and wage rate(including the amount designated for fringe benefits where appropriate), a report of the action taken shall be sent by HUD or its designee to the Administrator of the Wage and Hour Division, employment Standards Administration, U. S. Department of Labor, Washington, D. C. 20210. The Administrator, or an authorized representative, will approve, modify, or disapprove every additional classification action within 30 days of receipt and so advise HUD or its designee or will notify HUD or its designee within the 30-day period that additional time is necessary. (Approved by the Office of Management and Budget under OMB control number 1215-0140.) (iii) In the event that the Contractor, the laborers, or mechanics to be employed in the Classification or their representatives, and HUD or its designee do not agree on the proposed classification and wage rate (including the amount designed for fringe benefits, where appropriate), HUD or its designee shall refer the questions, including the views of all interested parties and the recommendation of HUD or its designee, to the Administrator for determination. The Administrator, or an authorized representative, will issue a determination within 30 days of receipt and so advise HUD or its designee or will notify HUD or its designee within the 30-day period that the additional time is necessary. (Approved by the Office of Management and Budget under OMB Control Number 215-0140.) (iii) The wage rate (including fringe benefits where appropriate)determined pursuant to subparagraphs(b)(ii)or of this paragraph, shall be paid to all workers performing work in the classification under this contract from the first day on which work is performed in the classification. (c) Whenever the minimum wage rate prescribed in the contract for a class of laborers or mechanics includes a fringe benefit which is not expressed as an hourly rate,the contractor shall either pay the benefit as stated in the wage determination or shall pay another bona fide fringe benefit or an hourly cash equivalent thereof. (d) If the contractor does not make payments to a trustee or other third person, the contractor may consider as part of the wages of any laborer or mechanic the amount of any costs reasonably anticipated in providing bona fide fringe benefits under a plan or program.Provided, that the Secretary of Labor has found, upon the written request of the contractor,that the applicable standards of the Davis-Bacon Act have been met. The Secretary of Labor may require the contractor to set aside, in a separate account, assets for the meeting of obligations under the plan or program. (Approved by the Office of Management and Budget under OMB Control Number 1215-0140.) (2) Withholding. HUD or its designee shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld from the contractor under this contract or any other federal contract with the same prime contractor, or any other Federally-assisted contract subject to Davis-Bacon prevailing wage requirements, which is held by the same prime contractor so much of the accrued payments or advances as may be considered necessary to pay laborers and mechanics, including apprentices, trainees and helpers employed by the contractor or any subcontractor the full amount of wages required by the contract. In the event of failure to pay any laborer or mechanic, including any apprentice,trainee or helper,employed or working on the site of the work (or under the United States Housing Act of 1937 or under the Housing Act of 1949 in the construction or development of the project), all or part of the wages required by the contract, HUD, or its designee may, after written notice to the contractor, sponsor, applicant, or owners, take such action as may be necessary to cause the suspension of any further payment, advance, or guarantee of funds until such violations have ceased. HUD or its designee may, after written notice to the contractor, disburse such amounts withheld for and on account of the contractor or subcontractor to the respective employees to whom they are due. The Comptroller General shall make such disbursements in the case of direct Davis-Bacon Act contracts. (3) (a) Payrolls and Basic Records. Payrolls and basic records relating thereto shall be maintained by the contractor during the course of the work preserved for a period o f three years thereafter for all laborers and mechanics working at the site of the work (or under the United States Housing Act of 1937, or under the Housing Act of 1949, in the construction or development of the project). Such records shall contain the name, address, and social security number of each such worker, his or her correct classification, hourly rates of wages paid (including rates of contributions or costs anticipated for bona fide fringe benefits or cash equivalents thereof of the types described in Section 1(b)(2)(B)of the Davis-Bacon Act),daily and weekly number of hours worked,deductions made, and actual wages paid. Whenever the Secretary of Labor has found under 29 CFR 5.5(a)(1)(iv) that the wages of any laborer or mechanic include the amount of any costs reasonably anticipated in FPC-12 EXHIBIT I FEDERAL CONTRACT PROVISIONS providing benefits under a plan or program described in Section 1(b)(2)(B) of the Davis-Bacon Act, the contractor shall maintain records which show that the commitment to provide such benefits is enforceable,that the plan or program is financially responsible, and that the plan or program has been communicated in writing to the laborers or mechanics affected, and records which show the costs anticipated or the actual cost incurred in providing such benefits. Contractors employing apprentices or trainees under approved programs shall maintain written evidence of the registration of apprenticeship programs and certification of trainee programs, the registration of the apprentices and trainees, and the ratios and wage rates prescribed in the applicable programs. (Approved by the Office of Management and Budget under OMB Control Numbers 1215-0140 and 1215-0017). (b) (i)The contractor shall submit weekly for each week in which any contract work is performed a copy of all payrolls to HUD or its designee if the agency is a party to the contract, but if the agency is not such a party, the contractor will submit the payrolls to the applicant, sponsor, or owners, as the case may be, for transmission to HUD or its designee. The payrolls submitted shall set out accurately and completely all of the information required to be maintained under 29 CFR Part 5.5(a)(3)(I).This information may be submitted in any form desired.Optional Form WH-347 is available for this purpose and may be purchased from the Superintendent of Documents (Federal Stock Number 029-005-00014-1), U. S. Government Printing Office, Washington, DC 20402. The prime contractor is responsible for the submission of copies of payrolls by all subcontractors. (Approved by the Office of Management and Budget under OMB Control Number 1215-0149). (ii) Each payroll submitted shall be accompanied by a "Statement of Compliance", signed by the contractor or subcontractor or his or her agent who pays or supervises the payment of the persons employed under the contract and shall certify the following: (I) That the payroll for the payroll period contains the information required to be maintained under 29 CFR Part 5.5(a)(3)(I)and that such information is correct and complete; (2) That each laborer or mechanic (including each helper, apprentice, and trainee) employed on the contract during the payroll period has been paid the full weekly wages earned,without rebate, either directly or indirectly, and that no deductions have been made either directly or indirectly from the full wages earned, other than permissible deductions as set forth in 29 CFR Part 3; (3) That each laborer or mechanic has been paid not less than the applicable wage rates and fringe benefits or cash equivalents for the classification of work performed, as specified in the applicable wage determination incorporated into the contract. (ii i) The weekly submission of a properly executed certification set forth on the reverse side of Option Form WH- 347 shall satisfy the requirement for submission of the "Statement of Compliance"required by paragraph A(3)(b)(ii)of this section. (iv) The falsification of any of the above certifications may subject the contractor or subcontractor to civil or criminal prosecution under Section 1001 of Title 18 and Section 231 of Title 31 of the United States Code. (c) The contractor or subcontractor shall make the records required under paragraph A(3)(a) of this section available for inspection, copying, or transcription by authorized representatives of HUD or its designee or the Department of Labor,and shall permit such representatives to interview employees during working hours on the job. If the contractor or subcontractor fails to submit the required records or to make them available, HUD or its designee may,after written notice to the contractor, sponsor, applicant, or owner,take such action as may be necessary to cause the suspension of any further payment, advance, or guarantee of funds. Furthermore, failure to submit the required records upon request to make such records available may be grounds for debarment action pursuant to 29 CFR Part 5.12. (4) (a)Apprentices and Trainees. (i) Apprentices. Apprentices will be permitted to work at less than the predetermined rate for the work they performed when they are employed pursuant to and individually registered in a bona fide apprenticeship program FPC-13 EXHIBIT I FEDERAL CONTRACT PROVISIONS (8) Compliance with Davis-Bacon and Related Act Requirements. All rulings and interpretations of the Davis- Bacon and Related Acts contained in 29 CFR Parts 1,3 and 5 are herein incorporated by referenced in this contract. (9) Disputes Concerning Labor Standards. Disputes arising out of the labor standards provisions of this contract shall not be subject to the general disputes clause of this contract. Such disputes shall be resolved in accordance with the procedures of the Department of Labor(USDOL) set forth in 29 CFR Parts 5, 6 and 7. Disputes within the meaning of this clause include disputes between the contractor(or any of its subcontractors) and HUD or its designee, the USDOL, or the employees or their representatives. (10) Certification of Eligibility, (a) By entering into this contract,the contractor certifies that neither it (nor he or she)nor any person or firm who has an interest in the contractor's firm is a person or firm ineligible to be awarded Government contracts by virtue of Section 3(a) of the Davis-Bacon Act or 29 CFR 5.12(a)(1) or to be awarded HUD contracts or participate in HUD programs pursuant to 24 CFR Part 24. (b) No part of this contract shall be subcontracted to any person or firm ineligible for award of a Government contract by virtue of Section 3(a) of the Davis-Bacon Act or 29 CFR 5.12(a)(1) or to be awarded HUD contracts or participate in HUD programs pursuant to 24 CFR Part 24. (c) The penalty for making false statements is prescribed in the U. S. Criminal Code, 18 U. S. C.1001. Additionally, U. S. Criminal Code, Section 1010, Title 18, U. S. C., "Federal Housing Administration transactions",provides in part "Whoever,for the purpose of ... influencing in any way the action of such Administration ... makes, utters or publishes any statement, knowing the same to be false... shall be fined not more than $5,000 or imprisoned not more than two years,or both." (11) Complaints, Proceedings, or Testimony by Employees. No laborer or mechanic to whom the wage, salary, or other labor standards provisions of this contract are applicable shall be discharged or in any other manner discriminated against by the contractor or any subcontractor because such employee has filed any complaint or instituted or caused to be instituted any proceeding or has testified or is about to testify in any proceeding under or relating to the labor standards applicable under this contract to his employer. B. Contract Work Hours and Safety Standards Act. As used in the paragraph,the terms "laborers"and "mechanics"include watchmen and guards. (I) Overtime requirements.No contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in such workweek unless such laborer or mechanic receives compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such workweek. (2) Violation; liability for unpaid wages; liquidated damages. In the event of any violation of the clause set forth in subparagraph (1) of this paragraph, the contractor and any subcontractor responsible therefore shall be liable for the unpaid wages. In addition,such contractor and subcontractor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory,to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic,including watchmen and guards, employed in violation of the clause set forth in subparagraph (1) of this paragraph, in the sum of$10 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in subparagraph(1)of this paragraph. (3) Withholding for unpaid wages and liquidated damages. HUD or its designee shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the contractor or subcontractor under any such contract or any other Federal contract with the same prime contract,or any other Federally-assisted contract subject to the Contract Work Hours and Safety Standards Act , which is held by the same prime contractor such sums as may be determined to be FPC-15 EXHIBIT I FEDERAL CONTRACT PROVISIONS registered with the U. S. Department of Labor, Employment and Training Administration, Bureau of Apprenticeship and Training, or with a State Apprenticeship Agency recognized by the Bureau, or if a person is employed in his or her first 90 days of probationary employment as an apprentice in such an apprenticeship program, who is not individually registered in the program, but who has been certified by the Bureau of Apprenticeship and Training or a State Apprenticeship Agency (where appropriate) to be eligible for probationary employment as an apprentice.The allowable ratio of apprentices to journeymen on the job site in any craft classification shall not be greater than the ratio permitted to the contractor as to the entire work force under the registered program. Any worker listed on a payroll at an apprentice wage rate, who is not registered or otherwise employed as stated above, shall be paid not less than the applicable wage rate on the wage determination for the classification of work actually performed. In addition, any apprentice performing work on the job site in excess of the ratio permitted under the registered program, shall be paid not less than the applicable wage rate on the wage determination for the work actually performed. Where a contractor is performing construction on a project in a locality other than that in which its program is registered,the ratios and wage rates (expressed in percentages of the journeyman's hourly rate) specified in the contractor's or subcontractor's registered program shall be observed. Every apprentice must be paid at not less than the rate specified in the registered program for the apprentice's level of progress, expressed as a percentage of the journeymen hourly rate specified in the applicable wage determination. Apprentices shall be paid fringe benefits in accordance with the provisions of the apprenticeship program. If the apprenticeship program does not specify fringe benefits, apprentices must be paid the full amount of fringe benefits listed on the wage determination for the applicable classification. If the Administrator determines that a different practice prevails for the applicable apprentice classification, fringes shall be paid in accordance with the determination. In the event the Bureau of Apprenticeship and Training, or a State Apprenticeship Agency recognized by the Bureau, withdraws approval of an apprenticeship program, the contractor will no longer be permitted to utilize apprentices at less than the applicable predetermined rate for the work performed until an acceptable program is approved.Trainees. Except as provided in 29 CFR 5.16, trainees will not be permitted to work at less than the predetermined rate for the work performed unless they are employed pursuant to and individually registered in a program which has received prior approval, evidenced by formal certification by the U.S. Department of Labor, Employment and Training Administration.The ratio of trainees to journeymen on the job site shall not be greater than permitted under the plan approved by the Employment and Training Administration. Every trainee must be paid at not less than the rate specified in the approved program for the trainee's level of progress, expressed as a percentage of the journeyman hourly rate specified in the applicable wage determination. (ii) Trainees shall be paid fringe benefits in accordance with the provisions of the trainee program. If the trainee program does not mention fringe benefits, trainees shall be paid the full amount of fringe benefits listed on the wage determination unless the Administrator of the Wage and Hour Division determines that there is an apprenticeship program associated with the corresponding journeyman wage rate on the wage determination which provides for less than full fringe benefits for apprentices.Any employee listed on the payroll at a trainee rate who is not registered and participating in a training plan approved by the Employment and Training Administration shall be paid not less than the applicable wage rate on the wage determination for the work actually performed. In addition, any trainee performing work on the job site in excess of the ratio permitted under the registered program shall be paid not less than the applicable wage rate on the wage determination for the work actually performed. In the event the Employment and Training Administration withdraws approval of a training program the contract will no longer be permitted to utilize trainees at less than the applicable predetermined rate for the work performed until an acceptable program is approved. (iii) Equal Employment Opportunity. The utilization of apprentices, trainees and journeymen under this part shall be in conformity with the equal employment opportunity requirements of Executive Order 11246,as amended,and 29 CFR Part 30. (5) Compliance with Copeland Act Requirements. The contractor shall comply with the requirements of 29 CFR Part 3 which are incorporated by reference in this contract. (6) Subcontracts.The contractor or subcontractor will insert in any subcontracts the clauses contained in 29 CFR 5,5(a)(1) through (10) and such other clauses as HUD or its designee may by appropriate instructions require, and also a clause requiring the subcontractors to include these clauses in any lower tier subcontracts. The prime contract shall be responsible for the compliance by any subcontractor or lower tier subcontractor with all the contract clauses in 29 CFR Part 5.5. (7) Contract Termination, Debarment. A breach of the contract clauses in 29 CFR 5.5 may be grounds for termination of the contract and for debarment as a contractor and a subcontractor as provided in 29 CFR 5.12. FPC-14 EXHIBIT I FEDERAL CONTRACT PROVISIONS necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in subparagraph (2) of this paragraph. (4) Subcontracts. The contractor or subcontractor shall insert in any subcontracts the clauses set forth in subparagraph (1) through (4) of this paragraph and also a clause requiring the subcontractors to include these clauses in any lower tier subcontracts. The prime contractor shall be responsible for compliance by any subcontractor or lower tier subcontractor with the clauses set forth in subparagraphs(1)through(4) of this paragraph. C. Health and Safety (1) No laborer or mechanic shall be required to work in surroundings or under working conditions which are unsanitary, hazardous,or dangerous to his health and safety as determined under construction safety and health standards promulgated by the Secretary of Labor by regulation. (2) The contractor shall comply with all regulations issued by the Secretary of Labor pursuant to Title 29 Part 1926 (formerly part 1518) and failure to comply may result in imposition of sanctions pursuant to the Contract Work Hours and Safety Standards Act(Public Law 91-54.83 State 96). (3) The contractor shall include the provisions of this Article in every subcontract so that such provisions will be binding on each subcontractor. The contractor shall take such action with respect to any subcontract as the Secretary of Housing and Urban Development or the Secretary of Labor shall direct as a means of enforcing such provisions. X. GUIDANCE TO CONTRACTOR FOR COMPLIANCE WITH LABOR STANDARDS PROVISIONS A. Contracts with Two Wage Decisions If the contract includes two wage decisions, the contractor, and each subcontractor who works on the site, must submit either two separate payrolls (one for each wage decision) or one payroll which identifies each worker twice and the hours worked under each wage decision.One single payroll, reflecting each worker once, may be submitted provided the Contractor uses the higher rate in the wage decisions for each identical job classification. However, where a job classification is not listed in a wage decision and is needed for that portion of the work, the classification must be added to the wage decision. A worker may not be paid at the rate for a classification using the hourly rate for that same classification in another wage decision. After the additional classification is approved, the contractor may pay the higher of the two rates and submit one payroll, if desired. B. Complying with Minimum Hourly Amounts (1) The minimum hourly amount due to a worker in each classification is the total of the amounts in the "Rates" and "Fringe Benefits" (if any) columns of the applicable wage decision. (2) The contractor may satisfy this minimum hourly amount by any combination of cash and bona fide fringe benefits, regardless of the individual amounts reflected in the"Rates"and"Fringe Benefits"columns. (3) A contractor payment for a worker which is required by law is not a fringe benefit in meeting the minimum hourly amount due under the applicable wage decision. For example, contractor payments for FICA or unemployment insurance are not a fringe benefit; however, contractor payments for health insurance or retirement are a fringe benefit. Generally,a fringe benefit is bona fide if(a) it is available to most workers and (b)involves payments to a third party. (4) The hourly value of the fringe benefit is calculated by dividing the contractor's annual cost (excluding any amount contributed by the worker)for the fringe benefit by 2080.Therefore,for workers with overtime, an additional payment may be required to meet the minimum hourly wages since generally fringe benefits have no value for any time worked over 40 hours weekly. (If a worker is paid more than the minimum rates required by the wage decision, this should not be a problem. As long as the total wages received by a worker for straight time equals the hours worked times the minimum hourly rate in the wage decision,the requirement of the Davis-Bacon and Related Acts has been satisfied.) C. Overtime For any project work over 40 hours weekly,a worker generally must be paid 150% of the actual hourly cash rate received, not FPC-16 EXHIBIT I FEDERAL CONTRACT PROVISIONS the minimum required by the wage decision. (The Davis-Bacon and related acts only establish minimum rates and does not address overtime;the Contract Work Hours Act contains the overtime requirement and uses"basic rate of pay" as the base for calculation,not the minimum rates established by the Davis-Bacon and related acts.) D. Deductions Workers who have deductions,not required by law,from their pay must authorize these deductions in writing. The authorization must identify the purpose of each deduction and the amount, which may be a specific dollar amount or a percentage. A copy of the authorization must be submitted with the first payroll containing the deduction. If deducted amounts increase, another authorization must be submitted. If deducted amounts decrease, no revision to the original authorization is needed. Court-ordered deductions, such as child support, may be identified by the responsible payroll person in a separate document. This document should identify the worker, the amount deducted and the purpose.A copy ofthe court order should be submitted. E. Classifications Not Included in the Wage Decision If a classification not in the wage decision is required, please advise the owner's representative in writing, and identify the job classification(s)required. In some instances, the State agency may allow the use of a similar classification in the wage decision. Otherwise, the contractor and affected workers must agree on a minimum rate, which cannot be lower than the lowest rate for any trade in the wage decision. Laborers(including any subcategory of the laborer classification)and truck drivers are not considered a trade for this purpose. If the classification involves a power equipment operator, the minimum cannot be lower than the lowest rate for any power equipment operator in the wage decision, The owner will provide forms to document agreement on the minimum rate by the affected workers and contractor. The USDOL must approve the proposed classification and rate. The contractor may pay the proposed rate until the USDOL makes a determination. Should the USDOL require a higher rate, the contractor must make wage restitution to the affected worker(s)for all hours worked under the proposed rate. F. Supervisory Personnel Foremen and other supervisory personnel who spend at least 80% of their time supervising workers are not covered by the Davis-Bacon and Related Acts. Therefore, a wage decision will not include such supervisory classifications and their wages are not subject to any minimums under the Davis-Bacon and Related Act or overtime payments under the Contract Work Hours and Safety Standards Act. However,foremen and other supervisory personnel who spend less than 80% of their time engaged in supervisory activities are considered workers/mechanics for the time spent engaged in manual labor and must be paid at least the minimum in the wage decision for the appropriate classification(s)based on the work performed. G. Sole Proprietorships/Independent Contractors/Leased Workers The nature of the relationship between a prime contractor and a worker does not affect the requirement to comply with the labor standards provisions of this contract. The applicability of the labor standards provisions is based on the nature of the work performed. If the work performed is primarily manual in nature, the worker is subject to the labor standards provisions in this contract, For example, if John Smith is the owner of ABC Plumbing and performs all plumbing work himself, then Mr. Smith is subject to the labor standards provisions, including minimum wages and overtime. His status as"owner"is irrelevant for labor standards purposes. If a worker meets the IRS standards for being an independent contractor,and is employed as such, this means that the worker must submit a separate payroll as a subcontractor rather than be included on some other payroll. The worker is still subject to the labor standards provisions in this contract, including minimum wages and overtime. If a contractor or subcontractor leases its workers, they are subject to the labor standards provisions in this contract, including minimum wages and overtime. The leasing firm must submit payrolls and these payrolls must reflect information required to determine compliance with the labor standards provisions of this contract, including a classification for each worker based on the nature of the work performed, number of regular hours worked, and number of overtime hours worked. H. Apprentices/Helpers A worker may be classified as an apprentice only if participating in a federal or state program. Documentation of FPC-17 EXHIBIT I FEDERAL CONTRACT PROVISIONS participation must be submitted. Generally, the apprentice program specifies that the apprentice will be compensated at a percentage of the journeyman rate. For Davis-Bacon Act purposes, the hourly rate cannot be lower than the percentage of the hourly rate for the classification in the applicable wage decision. If the worker does not participate in a federal or state apprentice program, then the worker must be classified according to duties performed.This procedure may require classification in the"trade"depending on tools used, or as a laborer if specialized tools of the trade are not used. The contractor may want to consult with the Wage and Hour Division of the U.S. Department of Labor located in most large cities regarding the appropriate classification. Presently, no worker may be classified as a "helper". As with apprentices not participating in a formal apprentice program, the worker must be classified according to duties performed and tools used. 13.LOBBY PROHIBITION (a) No funds or other resources received from the Department under this Agreement may be used directly or indirectly to influence legislation or any other official action by the Florida Legislature or any state agency. (b)The contractor/vendor certifies, by its signature to this Agreement,that to the best of his or her knowledge and belief; 1. No Federal appropriated funds have been paid or will be paid, by or on behalf of the Recipient,to any person for influencing or attempting to influence an officer or employee of any agency,"a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with the awarding of any Federal contract, the making of any Federal grant, the making of any Federal loan, the entering into of any cooperative agreement, and the extension,continuation,renewal,amendment or modification of any Federal contract, grant, loan or cooperative agreement. 2. If any funds other than Federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with this Federal contract, grant, loan or cooperative agreement, the Recipient shall complete and submit Standard Form- LLL,"Disclosure Form to Report Lobbying." The contractor/vendor shall require that this certification be included in the award documents for all subawards (including subcontracts,subgrants, and contracts under grants, loans, and cooperative agreements)and that all subrecipients shall certify and disclose.This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by Section 1352, Title 31, U.S. Code.Any person who fails to file the required certification shall be subject to a civil penalty of not less than$10,000 and not more than$100,000 for each such failure. 14. GRANTEE RECOGNITION All facilities purchased or constructed pursuant to this Agreement shall be clearly identified as to the funding source.The Contractor will mount a temporary construction sign for projects funded by Housing Urban Development though Collier County Community and Housing Services.The design concept is intended to disseminate key information regarding the development team as well as Equal Housing Opportunity to the general public. The Construction sign shall comply with applicable County codes. 15. HISTORIC PRESERVATION The Contractor shall comply with the historic preservation requirements of 24 CFR 58.17 and the Secretary of the Interior's Standards for Rehabilitation and Guidelines for Rehabilitating Historic Buildings and with all other environmental regulatory requirements. D. Historic Preservation:The contractor agrees to comply with the Historic Preservation requirements set forth in the National Historic Preservation Act of 1966, as amended (16 USC 470) and the procedures set forth in 36 CFR 800,Advisory Council on Historic reservation Procedures for Protection of Historical Properties. 16.LOBBYING(31 U.S.C. 1352)(Reference 2 CFR§200 Appendix II):Vendors must certify it will not and has not used Federal appropriated funds have been paid or will be paid,by or to any person or organization for influencing or attempting to influence an officer or employee of an agency, a Member of Congress, an officer or employee of Congress,or an employee of a Member of Congress in connection with the awarding of any Federal contract,the making of any Federal grant,the making of any Federal loan, the entering into of any cooperative agreement, and the extension,continuation, renewal, amendment, or modification of any Federal contract,grant,loan,or cooperative agreement.The certification includes any lobbying with non-Federal funds that FPC- 18 EXHIBIT I FEDERAL CONTRACT PROVISIONS takes place in connection with obtaining any Federal award. • 17. NO GOVERNMENT OBLIGATION TO THIRD PARTIES The Federal Government is not a party to this contract and is not subject to any obligations or liabilities to the non-Federal entity, contractor, or any other party pertaining to any matter resulting from the contract." 18. PROCUREMENT OF RECOVERED MATERIALS In the performance of this contract, the Contractor shall make maximum use of products containing recovered materials that are EPA-designated items unless the product cannot be acquired— Competitively within a timeframe providing for compliance with the contract performance schedule; Meeting contract performance requirements;or At a reasonable price.Information about this requirement,along with the list of EPA-designated items,is available at EPA's Comprehensive Procurement Guidelines webpage: https://www.epa.gov/smm/comprehensive- procurement-guideline- cpg-program. The Contractor also agrees to comply with all other applicable requirements of Section 6002 of the Solid Waste Disposal Act. 19. PROGRAM FRAUD AND FALSE OR FRAUDULENT STATEMENTS OF RELATED ACTS The contractor acknowledges that 31 U.S.C.Chap.38(Administrative Remedies for False Claims and Statements)applies to the contractor's actions pertaining to this contract." 20. PROHIBITION ON CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (Reference 2 CFR§ 200.216) The Federal awarding agency prohibits the County to enter into a contract to procure or obtain equipment, services or systems that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. As described in Public Law 115-232, section 889, covered telecommunications equipment is telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities). (i) For the purpose of public safety, security of government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities). (ii) Telecommunications or video surveillance services provided by such entities or using such equipment. (i)(iii) Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of the National Intelligence or the Director of the Federal Bureau of Investigation,reasonably believes to be an entity owned or controlled by,or otherwise connected to,the government of a covered foreign country. (b)In implementing the prohibition under Public Law 115-232,section 889, subsection (f), paragraph(1),heads of executive agencies administering loan,grant, or subsidy programs shall prioritize available funding and technical support to assist affected businesses,institutions and organizations as is reasonably necessary for those affected entities to transition from covered communications equipment and services,to procure replacement equipment and services,and to ensure that communications service to users and customers is sustained.(c)See Public Law 115- 232,section 889 for additional information. 21.RECORD KEEPING AND RETENTION The Recipient,its employees,or agents,including all contractors, subcontractors, or consultants to be paid from funds under this Agreement,shall allow access to its records at reasonable times to the Departments, its employees and agents. "Reasonable" shall ordinarily mean during normal business hours of 8am to 5pm local time, on Monday through Friday. "Agents"shall include, but not be limited to, auditors retained by the Department. The Contractor shall maintain all records required by the grantor.All reports, plans, surveys, information, documents, maps, and other data procedures developed,prepared,assembled,or completed by the Contractor for the purpose of this Agreements shall be made available to the County by the Contractor at any time upon request by the County or HUD. Upon completion of all work contemplated under this agreement copies of all documents and records relating to this agreement shall be surrendered to the County if requested. In any event the contractor shall retain all records relating to this contract for six years after the local government makes final payment and all other pending matters are closed. 22.RELIGIOUS ORGANIZATIONS CDBG funds may not be used for religious activities or provided to primarily religions organizations. Section 24 CFR 570.200(j) specifies the limitations on CDBG funds. 23.COPYRIGHT AND PATENT RIGHTS No reports, maps, or other documents produced in whole or in part under this contract shall be the subject of an application for copyright by or on behalf of the contractor.The US Department of Housing and Urban Development and the grantee shall possess FPC-19 EXHIBIT I FEDERAL CONTRACT PROVISIONS all rights to invention or discovery,as well as rights in data which may arise as a result of the contractor's services. 24.TERMINIATION FOR CAUSE AND I OR CONVENIENCE a. This contract may be terminated in whole or in part in writing by either party in the event of substantial failure by the other party to fulfill its obligations under this contract through no fault of the terminating party, provided that no termination may be affected unless the other party is given: (1)not less than ten (10) calendar days written notice (delivered by certified mail, return receipt requested) of intent to terminate;and (2)an opportunity for consultation with the terminating party prior to termination. b. This contract may be terminated in whole or in part in writing by the local government for its convenience, provided that the other party is afforded the same notice and consultation opportunity specified in 1.(A)above. c. If termination for default is affected by the local government, an equitable adjustment in the price for this contract shall be made,but (1)no amount shall be allowed for anticipated profit on unperformed services or other work,and (2)any payment due to the contractor at the time of termination may be adjusted to cover any additional costs to the local government because of the contractor's default. If termination for convenience is effected by the local government, the equitable adjustment shall include a reasonable profit for services or other work performed for which profit has not already been included in an invoice. For any termination, the equitable adjustment shall provide for payment to the contractor for services rendered and expenses incurred prior to receipt of the notice of intent to terminate, in addition to termination settlement costs reasonably incurred by the contractor relating to commitments(e.g.,suppliers, subcontractors)which had become firm prior to receipt of the notice of intent to terminate. d. Upon receipt of a termination action under paragraphs (a)or(b)above,the contractor shall(1) promptly discontinue all affected work (unless the notice directs otherwise) and(2)deliver or otherwise make available to the local government all data, drawings, reports specifications, summaries, and other such information, as may have been accumulated by the contractor in performing this contract,whether completed or in process. e. Upon termination,the local government may take over the work and may award another party a contract to complete the work described in this contract. f. If, after termination for failure of the contractor to fulfill contractual obligations, it is determined that the contractor had not failed to fulfill contractual obligations,the termination shall be deemed to have been for the convenience of the local government. In such event, adjustment of the contract price shall be made as provided in paragraph(c)above. FPC-20 EXHIBIT I FEDERAL CONTRACT PROVISIONS STATE AND FEDERAL STATUTES AND REGULATIONS By signature of this Agreement,the contractor hereby certifies that it will comply with the following (as applicable)federal and state requirements: 1. Community Development Block Grant Disaster 33. The Wildlife Coordination Act of 1958,as amended; Noise 2. Recovery Emergency Rule 9BER09-2;The Solid Waste Disposal Abatement and Control: Departmental Policy Implementation, Act,as amended by the Resource Conservation and Recovery Responsibilities, and Standards,24 C.F.R.Part 51,Subpart B; Act of 1975(42 U.S.C.,s. 6901 et.seq.); 34. Flood Disaster Protection Act of 1973, P.L 92-234; 3. Florida Small a n d Minority Business Act, s.288.702-288.714, 35. Protection of Historic and Cultural Properties under HUD F.S.; Programs,24 C.F.R.Part 59; 4. Florida Coastal Zone Protection Act,s. 161.52-161,58,F.S.; 36. Coastal Zone Management Act of 1972,P.L 5. Local Government Comprehensive Planning and Land 92-583; Development Regulation Act,Ch. 163,F.S.; 37. Architectural and Construction Standards; 6. Title I of the Housing and Community Development 38. Architectural Barriers Act of 1968,42 U.S.C.4151; 7. Act of 1974,as amended 39. Executive Order 11296,relating to evaluation of flood hazards; 8. Treasury Circular 1075 regarding drawdown of CDBG funds. 40. Executive Order 11288.relating to prevention,control and 9. Sections 290.0401-290.049, F.S.; abatement of water pollution; 10. Rule Chapter 9B-43,Fla.Admin.Code.; 10.Department of 41. Cost-Effective Energy Conservation Standards,24 C.P.R.Part Community Affairs Technical Memorandums; 39; 11. HUD Circular Memorandums applicable to the Small Cities CDBG 42. Section 8 Existing Housing Quality Standards, 24 C.F.R.Part Program; 882; 12. Single Audit Act of 1984; 43. Coastal Barrier Resource Act of 1982; 13. National Environmental Policy Act of 1969 and other provisions 44, Federal Fair Labor Standards Act,29 U.S.C.,s.201 et.seq.; of law which further the purpose of this Act; 45. Title VI of the Civil Rights Act of 1964 Non discrimination; 14. National Historic Preservation Act of 1966(Public Law89-665)as 46, Title VII of the Civil Rights Act of 1968 Non-discrimination in amended and Protection of Historic Properties(24C.F.R.Part housing; 800); 47. Age Discrimination Act of 1975; 15. Preservation of Archaeological and Historical Data Act of 1966; 48. Executive Order 12892-Fair Housing 16. Executive Order 11593-Protection and Enhancement of Cultural 49. Section 109 of the Housing and Community Environment; Development Act of 1974, Non-discrimination; 17. Reservoir Salvage Act; 50. Section 504 of the Rehabilitation Act of 1973 and 24 C.F.R.Part 18. Safe Drinking Water Act of 1974,as amended; 8; 19. Endangered Species Act of 1958, as amended; 51. Executive Order 11063-Equal Opportunity in Housing; 20. Executive Order 12898-Environmental Justice 52. Executive Order 11246-Nondiscrimination; 21. Executive Order 11988 and 24 C.F.R.Part 55-Floodplain 53. Section 3 of the Housing and Urban Development Act of Management; 1968,as amended-Employment Training of Lower Income 22. The Federal Water Pollution Control Act of 1972,as amended(33 Residents and Local Business Contracting; U.S.C.,s. 1251 et.seq.); 54. Uniform Relocation Assistance and Real Property 23. Executive Order 11990-Protection of Wetlands; Acquisition Policies Act of 1970,P.L,, 100-17,and 49 C.F.R. 24. Coastal Zone Management Act of 1968,as amended; Part 24; 25. Wild and Scenic Rivers Act of 1968,as amended; 55. Copeland Anti-Kickback Act of 1934;Hatch Act; 26. Clean Air Act of 1977; 56. Title N Lead-Based Paint Poisoning Prevention Act(42 U.S.C., 27, HUD Environmental Standards(24 C.F.R. Part 58); s. 1251 et.seq.); 28. Farmland Protection Policy Act of 1981; 57. OMB 2 CFR Part 200 29. Clean Water Act of 1977; 58. Administrative Requirements for Grants,24 C.F.R.Part 85; 59. 30. Davis-Bacon Wage Rate Act; Section 02 of the Department of Housing and Urban 31. Contract Work Hours and Safety Standards Act of 1962,40 Development Reform Act of 1989 and 24 C.F.R.Part 12. U.S.C.s.327 et.seq; 32. Florida Statute 287.134,Discriminatory Vendors List FPC-21 EXHIBIT I FEDERAL CONTRACT PROVISIONS SECTION 3 REQUIREMENTS What is Section 3? Section 3 is a provision of the Housing and Urban Development(HUD)Act of 1968 that helps foster local economic development, neighborhood economic improvement,and individual self-sufficiency.The Section 3 program requires that recipients of certain HUD financial assistance,to the greatest extent feasible, provide job training,employment,and contracting opportunities for low-or very- low-income residents in connection with projects and activities in their neighborhoods. How does Section 3 promote self-sufficiency? Section 3 is a starting point to obtain job training,employment and contracting opportunities.From this integral foundation coupled with other resources comes the opportunity for economic advancement and self- sufficiency. • Federal,state,and local programs • Advocacy groups • Community and faith-based organizations How does Section 3 promote homeownership? Section 3 is a starting point to homeownership. Once a Section 3 resident has obtained employment or contracting opportunities, they have begun the first step to self-sufficiency. Remember,"It doesn't have to be fields of dreams". Homeownership is achievable.For more information visit our HUD website. Who are Section 3 residents? Section 3 residents are: • Public housing residents or • Persons who live in the area where a HUD-assisted project is located and who have a household income that falls below HUD's income limits as provided below. SECTION 3 INCOME LIMITS (FY 2024 Income Limits from www.huduser.org) All residents of public housing developments and those participating on the Section 8 program qualify as Section 3 residents.Additionally,individuals residing in Collier County who meet the income limits set forth below also qualify for Section 3 status. A picture identification and proof of current residency is required. Eligibility Guidelines Number in Household Very low-income(50%) Low income(80%) 1 person $36,550 $58,450 2 person $41,750 $66,800 3 person $46,950 $75,150 4 person $52,150 $83,450 5 person $56,350 $90,150 6 person $60,500 $96,850 7 person $64,700 $103,500 8 person $68,850 $110,200 Determining Income Levels • Low income is defined as 80%or below the median income of that area. • Very low income is defined as 50%or below the median income of that area. What is a Section 3 business concern? A business that: • Is 51 percent or more owned by Section 3 residents; • Employs Section 3 residents for at least 30 percent of its full-time,permanent staff;or • Provides evidence of a commitment to subcontract to Section 3 business concerns,25 percent or more of the dollar amount of the awarded contract. FPC-22 EXHIBIT I FEDERAL CONTRACT PROVISIONS What programs are covered? Section 3 applies to HUD-funded Public and Indian Housing assistance for development,operating,and modernization expenditures. Section 3 also applies to certain HUD-funded Housing and Community Development projects that complete housing rehabilitation, housing construction,and other public construction. What types of economic opportunities are available under Section 3? • Job training • Employment • Contracts Any employment resulting from these expenditures, including administration, management, clerical support, and construction, is subject to compliance with Section 3. Examples of Opportunities include but not limited to the list identified: •Accounting • Iron Works •Architecture • Janitorial • Appliance repair • Landscaping • Bookkeeping • Machine Operation • Bricklaying • Manufacturing • Carpentry • Marketing • Carpet Installation • Painting • Catering • Payroll Photography • Cement/Masonry • Plastering • Computer/Information • Plumbing • Demolition • Printing Purchasing • Drywall • Research • Elevator Construction • Surveying • Engineering • Tile setting • Fencing • Transportation • Florists •Word processing • Heating FPC-23 EXHIBIT I FEDERAL CONTRACT PROVISIONS Who will award the economic opportunities? Recipients of HUD financial assistance will award the economic opportunities.They and their contractors and subcontractors are required to provide,to the greatest extent feasible,economic opportunities consistent with existing Federal, State, and local laws and regulations. Who receives priority under Section 3? For training and employment: • Persons in public and assisted housing • Persons in the area where the HUD financial assistance is spent • Participants in HUD Youth build programs • Homeless persons For contracting: Businesses that meet the definition of a Section 3 business concern How can businesses find Section 3 residents to work for them? Businesses can recruit Section 3 residents in public housing developments and in the neighborhoods where the HUD assistance is being spent.Effective ways of informing residents about available training and job opportunities are: • Contacting resident organizations,local community development and employment agencies • Distributing flyers • Posting signs • Placing ads in local newspapers Are recipients, contractors, and subcontractors required to provide long- term employment opportunities, not simply seasonal or temporary employment? Recipients are required,to the greatest extent feasible,to provide all types of employment opportunities to low and very low-income persons,including permanent employment and long-term jobs. Recipients and contractors are encouraged to have Section 3 residents make up at least 30 percent of their permanent, full-time staff. A Section 3 resident who has been employed for 3 years may no longer be counted towards meeting the 30 percent requirement. This encourages recipients to continue hiring Section 3 residents when employment opportunities are available. What if it appears an entity is not complying with Section 3? There is a complaint process. Section 3 residents, businesses, or a representative for either may file a complaint if it seems a recipient is violating Section 3 requirements are being on a HUD-funded project. Will HUD require compliance? Yes.HUD monitors the performance of contractors,reviews annual reports from recipients,and investigates complaints.HUD also examines employment and contract records for evidence that recipients are training and employing Section 3 residents and awarding contracts to Section 3 businesses. FCP-24 EXHIBIT I FEDERAL CONTRACT PROVISIONS How can Section 3 residents or Section 3 business concerns allege Section 3 violations? You can file a written complaint with either the regional or local offices below. ATLANTA REGIONAL OFFICE U.S.Department of Housing and Urban Development Southeast Office 40 Marietta Street Atlanta,GA 30303 (404)331-5140 (800)440-8091 Fax:(404)331-1021 Email:complaints office 04hud.qov LOCAL HUD FIELD OFFICE Public Housing and Community Development 701 NW 1st Court, 16th Floor;Miami,FL 33136 Section3@miamidade.gov A written complaint should contain: • Name and address of the person filing the complaint • Name and address of subject of complaint(HUD recipient,contractor,or subcontractor) • Description of acts or omissions in alleged violation of Section 3 • Statement of corrective action sought i.e.,training,employment,or contracts Additional information may be found at HUD's Section 3 website http://portal.hud.gov/hudportal/HUD?src=/program offices/fair housing equal opp/section3/section3 FCP-25 EXHIBIT I FEDERAL CONTRACT PROVISIONS DAVIS BACON ACT IS APPLICABLE n YES ®NO THIS GRANT PROGRAM IS EXEMPT FROM DAVIS BACON REQUIREMENTS. FCP-26 EXHIBIT I FEDERAL CONTRACT PROVISIONS GRANT CERTIFICATIONS AND ASSURANCES THE FOLLOWING DOCUMENTS ARE REQUIRED TO BE RETURNED WITH THE SOLICIATION RESPONSE Certification Regarding Debarment, Suspension, and Other Responsibility Matters-Primary Covered Transactions VCertification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion Lower Tier Covered Transactions yConflict of Interest yr/Anticipated DBE, M/WBE or VETERAN Participation Statement N./. Bid Opportunity List for Commodities, Contractual Services or Professional Consultant Services Certification Regarding Lobbying Acknowledgement of Religious Organization Requirements 24 CFR 570.200(j) Certification of Payments to Influence Federal Transactions V,B Acknowledgement of Grant Terms and Conditions FCP-27 EXHIBIT I FEDERAL CONTRACT PROVISIONS COLLIER COUNTY Certification Regarding Debarment, Suspension, and Other Responsibility Matters Primary Covered Transactions (1) The prospective primary participant certifies to the best of its knowledge and belief, that it and its principals: (a) Are not presently debarred, suspended, proposed for debarment, declared ineligible,or voluntarily excluded from covered transactions by any Federal department or agency; (b) Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public(Federal, State or local)transaction or contract under a public transaction; violation of Federal or State antitrust statutes or commission of embezzlement,theft,forgery, bribery,falsification or destruction of records, making false statements, or receiving stolen property; (c) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity(Federal, State, or local)with commission of any of the offenses enumerated in paragraph (I)(b)of this certification; and (d) Have not within a three-year period preceding this application/proposal had one or more public transactions(Federal, State, or local)terminated for cause or default. (2) Where the prospective primary participant is unable to certify to any of the statements in this certification, such pros e r"pant shall ttach n explanation this propose fir iirSe 087° Name r Project Name Rizoied 1/' Title Projectd Number , . '� Firm CAGE Number treet Add s SAM.gov Unique Entity ID (UEI) Number City,,• ateip FCP-2g EXHIBIT I FEDERAL CONTRACT PROVISIONS COLLIER COUNTY Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion Lower Tier Covered Transactions (1) The prospective lower tier participant certifies, by submission of this document, that neither it nor its principals is presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from participation in this transaction by any Federal department or agency. (2) Where the prospective lower tier participant is unable to certify to the above statement, the prospective participant shallpttach ar -xplanati• to this form. Na e / /" Local Governmgn J' t Si Titl n r CAGE Number Firm SAM.gov Unique Entity ID (UEI) Number Stre t A ess --re /,, fi' ;i4/5- City , t 4 Zip Date The undersigned .�' - i� ' Vend��� ( or/ Contractor) certifies, to the best of his or her knowledge and elief, that: (1)No Federal appropriated funds have been paid or will be paid,by or on behalf of the undersigned,to any person for influencing or attempting to influence an officer or employee of an agency, a Member of Congress,an officer or employee of Congress,or an employee of a Member of Congress in connection with the awarding of any Federal contract, the making of any Federal grant, the making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any Federal contract, grant, loan, or cooperative agreement. (2) If any funds other than Federal appropriated funds have been paid or will be paid to any person for making lobbying contacts to an officer or employee of any agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with this Federal contract, grant, loan, or cooperative agreement, the undersigned shall complete and submit Standard Form--LLL, "Disclosure Form to Report Lobbying," in accordance with its instructions [as amended by "Government wide Guidance for New Restrictions on Lobbying," 61 Fed. Reg. 1413 (1/19/96). Note: Language in paragraph (2) herein has been modified in accordance with Section 10 of the Lobbying Disclosure Act of 1995(P.L. 104-65,to be codified at 2 U.S.C. 1601, etseq.)] FCP-29 EXHIBIT 1 FEDERAL CONTRACT PROVISIONS COLLIER COUNTY Conflict of Interest Certification Collier County So if citation No. 1, at � a , hereby certify that to the best of my knowledge, neither I nor my spouse, dependent child, general partner,or any organization for which I am serving as an officer, director, trustee, general partner or employee, or any person or organization with whom I am negotiating or have an arrangement concerning prospective employment has a financial interest in this matter. I further certify to the best of my knowledge that this matter will not affect the financial interests of any member of my household.Also,to the best of my knowledge, no member of my household; no relative with whom I have a close relationship; no one with whom my spouse, parent or dependent child has or seeks employment; and no organization with which I am seeking a business relationship nor which I now serve actively or have served within the last year are parties or represent a party to the matter. I also acknowledge my responsibility to disclose the acquisition of any financial or personal interest as described above that would be affected by the matter,and to disclose any interest I,or anyone noted above, has in any person or organization that does become involved i r is affected at a later date by,the conduct of this matter. Name Signature /' / OlittlAZY Position Da Privacy Act Statement Title I of the Ethics in Government Act of 1978 (5 U.S.C. App.), Executive Order 12674 and 5 CFR Part 2634, Subpart I require the reporting of this information. The primary use of the information on this form is for review by officials of The Justice Department to determine compliance with applicable federal conflict of interest laws and regulations.Additional disclosures of the information on this report may be made:(1)to a federal, state or local law enforcement agency if the Justice Department becomes aware of a violation or potential violation of law or regulations;(2)to a court or party in a court or federal administrative proceeding if the government is a party or in order to comply with a judge-issued subpoena; (3) to a source when necessary to obtain information relevant to a conflict of interest investigation or decision; (4)to the National Archives and Records Administration or the General Services Administration in records management inspections; (5) to the Office of Management and Budget during legislative coordination on private relief legislation; and (6)in response to a request for discovery or for the appearance of a witness in a judicial or administrative proceeding, if the information is relevant to the subject matter.This confidential certification will not be disclosed to any requesting person unless authorized by law. See also the OGE/GOVT-2 executive branch-wide Privacy Act system of records, FCP-3fl EXHIBIT I FEDERAL CONTRACT PROVISIONS COLLIER COUNTY ANTICIPATED DISADVANTAGED, MINORITY,WOMEN OR VETERAN PARTICIPATION STATEMENT Status ath be,,,erred LIwer,ate statuses w 1 require me PP ME to either prm.,de a re -,sed statement or provide scurce doctettentation that vaidates a Status A. PRIME VENDOR/CONTRACTOR INFORMATION PZIME r 41E ,P;IME PE 0-.WEEP corrk4cr DDLI-A f AMOUNT tlia ifrfjlee" r ;"'// ).,. ;e. 5,7- Ze2;2.- V/F inw i I,iS THE P/41E.A FLOR,DA-CERT:ED C S40.4%.AGED VETERAN ', N 5 THE A c.- ,i-r,OF^HS OcTRAC , MINOA;Tr"OP V,OMEN trJ s,NESS E.!:TE A RFI'SE? DBE? 0 N co1457-PticriON? 0 N IpetonE,NEE OR HALE A 7.1ALL3ISAIC,A•tTA:IED Sti5"t:ESS;4 CEPTIPXATJON PROM THE Si•,1ALL BLSINE SS '18E' s ri CONSULTAT en? t N A WIN,STOATION? A SERVICE DISABLED v r-EPA..' *Br, i Ti OTKR7 °, N SO.E 04.7 '. NI IS TH S SIBBM,SS.0*.i A REVISicir0 i 1 F)f.5,PEI.'SION%UMBER B. IF PRIME HAS SUBCONTRACTOR OR SUPPUER WHO IS A DISADVANTAGED IVIINORITY,WOMEN-OWNED,SMALL BUSINESS CONCERN OR SERVICE DISABLED VETERAN,PRIME IS TO COMPLETE THIS NEXT SECTION DBE 074,70014 LLSCONTRACTOR OR SUPPUER tYPE OF WORK OR ETHNICITY CODE SUB/SUPPLIER PERCENT OF CONTRACT ' RAF cf717,01,44. spf C1ALTe _ (See Bow) DELAR ANIOUNT DOLLARS II wit , ...4-7/0 tifmtv" "5,409" 1047;=, .... C. SECTION TO BE COMPLETED BY PRIME VENDOR/CONTRACTOR NAME OF SUBMITTE NOTE TM_ OR SUBMITTER -,— / ii"e-i571 74-- NAIL ADDRESS 0/PRIME SUB Eft) TELEPHONE f. MEIER FAX NUMBER 01,teejeti&P/49/7) /150750--WK ,,,,,--I:Th:,,n,c,rnatioi is used to track and 7 sport an cipaled OBE d7 MBE participation it(!al -ft.if:edc o'itr!cts 91:fThe anfcpated DEE or MBE arrioutt is oountary and Lvril not become pa/of the contractua,terms, This;orm!mist be subiltted at c,rre of tesponse to a so'icitatIon f and when ae,arded a Coulto contract the prime will be aged to 4 pdate the Information for the grait comojance¶es. ETHNICITY CODE Zeck American BA t-spanic American hA Native A reeTican f.tibront As a 1 A rvncan Asian-Pacific American APR Non-MincciO:Women NMA, Other.not of any'other g..ratio fisted 0 D.SECTION TO BE COMPLETED BY COLLIER COUNTY DEPARTMENT .AME COL EP CO!;TF AcT A t ES•RER 0,RO,FED GRANT PP OGRALI/CO%TFAC— L ACCEPTED BY: DATE FCT-3 1 EXHIBIT I FEDERAL CONTRACT PROVISIONS 910 OPPORTUNITY LIST FOR COMMODITIES,CONTRACTUAL SERVICES OR PROFESSIONAL CONSULTANT SERVICES leas too OfA&C,6,4C,04,C0,12}thord: e611rtay44b„s,•4a4escr4n=7101,y,orWri asdr!'es(Is tea aatr4,1feao•agP#5-4s +s CeR)rat. F$araaa Stars.m ff53,must hors o•,c ar r ,tv to:al.toots o,,,roonntraar:w=arr*so •c<on'brsto r root rss:to'es Pr-re Cortraeleo Pnme Cos«u tan ��/W/ t. /'! �, �'YIP� � AddrN.s ants Pisore fs.mbe• o: / Proc eernent Pswn+ber'Attko t€vrert IiWttber: I ....57,-. Tht.:St eitOse ss ar+teneted to"fie a=atcg of frTa that are,s#att!•nitar;to part c pate on ant Project nywc'*erea a>4.x Tgix:-:a r444t nc'udethef<,Ca btt4:a•gcoenEassea** atateasavtrs anti ax4ero erse aasr;toro<areSatar Proaaacaruactorsa^,9cons,tsk srrrrst Pro=' ;•+o••rate,for hyrnoers1.2, 3 a-t4,ar#,sit,.ea^o,ceaep,ofor•rason they Cic,e for N rrbers5 6 T a44E Tns,to*<r,r, st oe sex^nItee«:tr the b e aacwate /feiCn"ten elyivi ' i`!" 1. Neva.Tax it)ha r r 6 8 OSE S ann.a.G=oss Bete was m 3. Fort tyax tram-Del o:::nen 5 1 rni ao," 3. Pnone fti rnber: Setwten 5 1•S ra on kctkre:s fotterm 5 5.10 rfl on 7. aea„t at�a• fetween 5 1045 re 1 on .> - More a'"ar S'15mason 5 i"es"',net Etta9a#a ltot 1. fete,*Tar iDfa,.mbe* 69 CEE 5 Ann.4'4ms:Rece pee 2. Ems'?rre; '.. - 53E. ��.es env,51m:6k . 3. Pnore liasr+ber Wet«test S 1.5 an„on «. Attlee: .^5et«xxn S 3 3d rxl on ?E S4otontractar S'et«een 3$ m1i Subeen.,,:ant '.tare tsar 57.1.5 r .on 5 Yea-f r-r f:tao erect I. federai Tel 40t,,tt7aer 6 CS! -_a'v•a:sSleca;:*: 2. ',ter hero %:)--D3f. Wes tsar 51 m o, 3 Ph,pne hs.mtat ^tee-soon 5 1.5 m:,,on +r..Afiere53 5etween55 0rt.Won Sa beaurattor ...r echeeen 5 10-1S rn• for S,,bcomsultart More to as $15 ri1 an __.... 5. Year fen‘Estao:t-e: 1. fcderai Ta.dD 1+;,r'.arr 6 8 CEE 5 „he ,,Graz:get.pre —.... Z, Pm"home. ',t-•DEE Let;enar 5 1 AI,°or 5. Prone Per Setxeen 5 1.5 m»an », Actress `Sety een 5 5-16 rr,k°on S:.C40.4r3 41•9- Setsres�s 5 10-�15 rr-fi*,sr S b a•s_ - �++.fore man S 15 rno on S.Year tern Estad4 tree FCP-32 EXHIBIT I FEDERAL CONTRACT PROVISIONS COLLIER COUNTY Certification f Lobbying avzeff The undersigned gore, ' / Jj �Y�IC a l � (Vendor/ Contractor) certifies, to the best of his or her knowledge a belief,that: (1)No Federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or attempting to influence an officer or employee of an agency, a Member of Congress,an officer or employee of Congress,or an employee of a Member of Congress in connection with the awarding of any Federal contract,the making of any Federal grant,the making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any Federal contract, grant, loan, or cooperative agreement. (2) If any funds other than Federal appropriated funds have been paid or will be paid to any person for making lobbying contacts to an officer or employee of any agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with this Federal contract, grant, loan, or cooperative agreement, the undersigned shall complete and submit Standard Form--LLL, "Disclosure Form to Report Lobbying," in accordance with its instructions [as amended by "Government wide Guidance for New Restrictions on Lobbying," 61 Fed. Reg. 1413 (1/19/96). Note: Language in paragraph (2) herein has been modified in accordance with Section 10 of the Lobbying Disclosure Act of 1995(P.L. 104-65,to be codified at 2 U.S.C. 1601, et seq.)] (This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by 31, U.S.G.§1352(as amended by the Lobbying Disclosure Act of 1995). Any person who fails to file the required certification shall be subject to a civil penalty of not less than $10,000 and not more than$100,000 for each such failure. The prospective participant also agrees by submitting his or her proposal that he or she shall require that the language of this certification be included in all lower tier subcontracts,which exceed$100,000 and that all such subrecipients shall certify and disclose accordingly. The Vendor/Contractor, , certifies or affirms the truthfulness and accuracy of each statement of its certification and disclosure, if any. In addition, the Contractor understands and agrees that the provisions of 31 U.S.C.A 3801, et seq., apply to this certification and disclosure, if any. Name of Authorized Official �'�.. Tale (� Signature of Vendor/Contractor's Authorized Official r/ /7 Date FCP-33 EXHIBIT I FEDERAL CONTRACT PROVISIONS COLLIER COUNTY Acknowledgement of Religious Organization Requirements 24 CFR 570.200(j) In accordance with the First Amendment of the United States Constitution "church/state principles," Community Development Block Grant CDBG/NSP assistance may not, as a general rule, be provided to primarily religious entities for any secular or religious activities. Therefore, the following restrictions and limitations apply to any provider which represents that it is, or may be deemed to be, a religious or denominational institution or an organization operated for religious purposes which is supervised or controlled by or operates in connection with a religious or denominational institution or organization. A religious entity that applies for and is awarded CDBG/NSP funds for public service activities must agree to the following: 1. It will not discriminate against any employee or applicant for employment on the basis of religion and will not limit employment or give preference to persons on the basis of religion. 2. It will not discriminate against any person applying for such public services on the basis of religion and will not limit such services or give preference to persons on the basis of religion. 3. It will provide no religious instruction or counseling,conduct no religious worship or services, engage in no religious proselytizing,and exert no other religious influence in the provision of such public services. 4. The portion of a facility used to provide public services assisted in whole or in part under this agreement shall contain no sectarian or religious symbols or decorations;and 5. The funds received under this agreement shall be use to construct, rehabilitate or restore any facility, which is owned by the provider and in which the public services are to be provided. However, minor repairs may be made if such repairs are directly related to the public services located in a structure used exclusively for non-religious purposes and constitute in dollar terms, only a minor portion of the CDBG/NSP expenditure for the public services. I hereby acknowledge that I have read the specific requirements contained in this attachment and that eligibility of my organization's project depends upon compliance with the requirements contained in this agreement. m any) , ! 7 94/7„, ignature) (Date) (Print ame) FCP-34 EXHIBIT I FEDERAL CONTRACT PROVISIONS COLLIER COUNTY Certification of Payments to Influence Federal Transactions HUD COMMUNITY DEVELOPMENT BLOCK GRANT(CDBG) PROGRAM The undersigned certifies,to the best of his or her knowledge and belief,that: (1) No Federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or attempting to influence an officer or employee of an agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with the awarding of any Federal contract,the making of any Federal grant,the making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any Federal contract, grant, loan, or cooperative agreement. (2) If any funds other than Federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of an agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with this Federal contract,grant,loan,or cooperative agreement,the undersigned shall complete and submit Standard Form- LLL, Disclosure Form to Report Lobbying, in accordance with its instructions. (3)The undersigned shall require that the language of this certification be included in the award documents for all subawards at all tiers (including subcontracts, subgrants, and contracts under grants, loans, and cooperative agreements)and that all sub recipients shall certify and disclose accordingly. This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by Section 1352, Title 31, U.S. Code. Any person who fails to file the required certification shall be subject to a civil penalty of not less than$10,000 and not more than$100,000 for each such failure. I hereby certify that all the information stated herein, as well as any information provided in the accompaniment herewith, is true and accurate. Warning: HUD will prosecute false claims and statements. Conviction may result in criminal and/or civil penalties.(18 U.S.C. 1001, 1010, 1012; 31 U.S.C.3729,3802) 6-atene4 /77-e-OAL71- Name of Authorized icial Title /16:0,/i;112-5.1 ign ure Date FCP-35 EXHIBIT I FEDERAL CONTRACT PROVISIONS COLLIER COUNTY Acknowledgement of Terms, Conditions and Grant Clauses Flow Down of Terms and Conditions from the Grant Agreement Subcontracts: If the vendor subcontracts any of the work required under this Agreement, a copy of the signed subcontract must be available to the Department for review and approval. The vendor agrees to include in the subcontract that (1) the subcontractor is bound by the terms of this Agreement, (ii) the subcontractor is bound by all applicable state and federal laws and regulations, and (iii) the subcontractor shall hold the Department and Recipient harmless against all claims of whatever nature arising out of the subcontractor's performance of work under this Agreement, to the extent allowed and required by law. The recipient shall document in the quarterly report the subcontractor's progress in performing its work under this agreement. For each subcontract, the Recipient shall provide a written statement to the Department as to whether the subcontractor is a minority vendor as defined in Section 288.703, Fla. Stat. Certification On behalf of my firm, I acknowledge, and agree to perform all of the specifications and grant requirements identified in this solicitation document(s). Vendor/Contractor Name ee, ; 477/19 f , Date Authorized Signature Address / ,.1 / Lr -! Solicitation/Contract# 02/15 R3 FCP-36 AFFIDAVIT REGARDING LABOR AND SERVICES Effective July 1, 2024, pursuant to§ 787.06(13), Florida Statutes,when a contract is executed, renewed, or extended between a nongovernmental entity and a governmental entity, the nongovernmental entity must provide the governmental entity with an affidavit signed by an officer or a representative of the nongovernmental entity under penalty of perjury attesting that the nongovernmental entity does not use coercion for labor or services. Nongovernmental Entity's Name: // ,U, � ;Ye 077/-1...4C ... -. �Address: lip1 Jt e- .� Phone Number: , : /"" . .qti / z� /'- 5-i3V7r.. Authorized Representative's Name: 9...-r' A ^� � jt/�Authorized Representative's Title: t,�fiyte — n�,yam) Email Address: j i t/41W---e--yte1-'T.1-- :Pt(:- 7 G AFFIDAVIT I, ;Tv-n(41- , At(1,-, (Name of Authorized Representative), as authorized representative attest thata /4ee-m&,�/'?GJ L. (Name of Nongovernmental Entity)does not use coercion for labor or services a(defined in §787.06, Florida Statutes. Undernal of , I declare that I have read the foregoing Affidavit and that the facts stated in it are true. --.=- 5/5/ZZ5 (Signature of authorized representative) Date STATE OF trJQ di j k - COUNTY OF H)f If kku(61.) Sworn to(or affirmed)and subscribed before me, by means of L�physical presence or D online n arization this S day of /ram ,20 lc, by 6eellI Jk CVT 5 (Name of Affiant),who produced their t °CO C b— as identification or are personally known to me. ‘/-i zaddlelys M.Gorizzi 9 No Public u • `r Notary Public ` State of Florida (,/,i/s 9 2 uL 3 t„ Dorm*HH47:':17 r I; • Expires 1/9/2028 Commission Expires Personally Known 0 OR Produced Identification Er- Type of Identification Produced: J/rrvw tree , '-Q- CONTRACT,RENEWAL,OR EXTENSION REOUEST FORM Version:2025.1 0