Backup Documents 09/10/2024 Item #16B 6 ORIGINAL DOCUMENTS CHECKLIST & ROUTING SLIP 6 B 6
TO ACCOMPANY ALL ORIGINAL DOCUMENTS SENT TO
THE BOARD OF COUNTY COMMISSIONERS OFFICE FOR SIGNATURE
Print on pink paper. Attach to original document. The completed routing slip and original documents are to be forwarded to the County Attorney Office
at the time the item is placed on the agenda. All completed routing slips and original documents must be received in the County Attorney Office no later
than Monday preceding the Board meeting.
**NEW** ROUTING SLIP
Complete routing lines#1 through#2 as appropriate for additional signatures,dates,and/or information needed. If the document is already complete with the
exception of the Chairman's signature,draw a line through routing lines#1 through#2,complete the checklist,and forward to the County Attorney Office.
Route to Addressee(s) (List in routing order) Office Initials Date
1.
2.
3. County Attorney Office County Attorney Office /11)1499
4. BCC Office Board of County /
Commissioners ¶/(o fr y
5. Minutes and Records Clerk of Court's Office 1'� lll111121
PRIMARY CONTACT INFORMATION
Normally the primary contact is the person who created/prepared the Executive Summary. Primary contact information is needed in the event one of the addressees
above,may need to contact staff for additional or missing information.
Name of Primary Staff Pawel Brzeski—TMSD—Capital Phone Number 239.252.2927
Contact/Department Project Planning,Impact Fees,and
Program Management
Agenda Date Item was Agenda Item Number 16.B.6
Approved by the BCC
Type of Document Change Order No.1, Quality Number of Original Documents 1
Attached Enterprises USA, Inc., Carson Rd. Attached
Stormwater Treatment Area
Improvement(Project#60143.2.4)
PO number or account Pawel.Brzeski@colliercountyfl.gov
number if document is to CC
be recorded Nadine.Dunham@colliercountyfl.gov
INSTRUCTIONS & CHECKLIST
Initial the Yes column or mark"N/A"in the Not Applicable column,whichever is Yes N/A(Not
appropriate. (Initial) Applicable)
1. Does the document require the chairman's original signature PB
2. Does the document need to be sent to another agency for additional signatures? If yes, N/A
provide the Contact Information(Name;Agency;Address;Phone)on an attached sheet.
3. Original document has been signed/initialed for legal sufficiency. (All documents to be PB
signed by the Chairman,with the exception of most letters,must be reviewed and signed
by the Office of the County Attorney.
4. All handwritten strike-through and revisions have been initialed by the County Attorney's N/A
Office and all other parties except the BCC Chairman and the Clerk to the Board
5. The Chairman's signature line date has been entered as the date of BCC approval of the
document or the final negotiated contract date whichever is applicable.
6. "Sign here"tabs are placed on the appropriate pages indicating where the Chairman's PB
signature and initials are required.
7. In most cases(some contracts are an exception),the original document and this routing slip N/A
should be provided to the County Attorney Office at the time the item is input into SIRE.
Some documents are time sensitive and require forwarding to Tallahassee within a certain
time frame or the BCC's actions are nullified. Be aware of your deadlines!
8. The document was approved by the BCC on 09/10/2024 and all changes made during PB N/A is not
the meeting have been incorporated in the attached document. The County an option for
Attorney's Office has reviewed the changes,if applicable. this line.
9. Initials of attorney verifying that the attached document is the version approved by the PB N/A is not
BCC,all changes directed by the BCC have been made,and the document is ready for the an option for
Chairman's signature. this line.
I:Forms/County Forms/BCC Forms/Original Documents Routing Slip WWS Original 9.03.04,Revised 1.26.05,Revised 2.24.05;Revised 11/30/12
CO[I er County
Procurement Services Change Order Form
Contract# 23-8114 CO# 1 PO# 4500225866 Project#: 60143.2.4
Project Name: Carson Road Stormwater Treatment Area Improvement
Contractor/Consultant Name: Quality Enterprises USA, Inc.
Select One:Q Contract Modification(Construction or Project Specific) ❑Work Order Modification
Project Manager Name: Pawel Brzeski Division Name: CPP Stormwater Management
Original Contract/Work Order Amount $5,865.783.20 08/08/2023#11A Original BCC Approval Date;Agenda Item#
Current BCC Approved Amount S5.865,783.20 08/08/2023#11A Last BCC Approval Date;Agenda Item#
Current Contract/Work Order Amount S5,865,783.20 11/1512024 SAP Contract Expiration Date(MASTER)
Dollar Amount of this Change o.00 i Total% Change from Original Amount
Revised Contract/Work Order Total S5,865,783.20 o.00i % Change from Current BCC Approved Amount
Total Cumulative Changes So.00 o.00% % Change from Current Amount
Notice to Proceed Original NTP Original Final Last Final 11/15/2024
Date 10/17/2023 #of Days 395 Completion Date 11/15/2024 Approved Date
#of Days Added 0 Revised Final Date 11/15/2024 Current Substantial Completion Date 10116/2024
(includes this change) (if applicable)
Provide responses after each question in box below (Responses should be brief and specific). Attach additional information and/or
documentation from the Design Professional and/or Contractor, if needed, with your submission of this Change Order and complete
summary on next page. Check all that apply to this Change Order request: ❑Add Time; ❑Add funds; ❑s Use of Allowance;
❑Modify/Delete existing Task(s); ❑Add new Task(s); ❑ Reallocate funds; ❑� Other(must be explained in detail below)
1.) Detail of change/s to be made through this Change Order.
This change order is to add 107 LF 48 inch ADS pipe and reduce 107 LF 42 inch RCP pipe Item#57 on the SOV. The
size of the culvert from proposed Lake CR-1 B to Lake CR-2A was required to be increased from 42 inch to 48 inches to
accept the anticipated flow into the Carson Road STA from the future drainage improvements from the Lake Trafford
Road Right-of-Way. This change will add 9,798.30 to the cost of the pipe. Funds will come from the Owner's Allowance.
2.) If this Change Order is currently under a Stop Work, please identify the date issued and number of days remaining or
"N/A" if not applicable.
N/A The project is currently on-going.
3.) Explain why this change was not included in the original contract/Work Order.
Up-sizing the pipe was not considered in the original contract because the design and permitting process for the upstream
Lake Trafford Road Right-of-Way (ROW)was still ongoing and comments from the South Florida Water Management
District(SFWMD)were received only after the project was bid. The Carson Road Stormwater Treatment Area (STA) is
intended to accept flow from the existing stormwater system within the Immokalee Drive ROW and from a series of areas
in which Collier County plans to install future stormwater improvements. At the time the Carson Road STA was advertised
for construction bids, the design and permitting process for the upstream Lake Trafford Road ROW was still in progress,
but subsequent comments received from SFWMD during the design and permitting of the drainage improvements within
the Lake Trafford Road ROW, required the size of the culvert from Lake CR-1 B to Lake CR-2A be increased from 42
inches to 48 inches diameter to accept the anticipated flow into the Carson Road STA from the future drainage
improvements of the Lake Trafford Road Right-of-Way.
4.) Describe the impact if this change is not processed.
If this modification is not processed, Quality Enterprises USA , Inc. will not be able to proceed with the construction in
accordance with the updated construction documents and the project will not be in compliance with the permit issued by
SFWMD.
Page 1 of 4
Change Order Form(2023_ver.1)
Co :ter County
Procurement Services Change Order Form
Contract# 23-8114 CO# 1 PO# 4500225866 Project#: 60143.2.4
Project Name: Carson Road Stormwater Treatment Area Improvement
Contractor/Consultant Name: Quality Enterprises USA, Inc.
Change Order/Amendment Summary
(If additional spaces needed,attached a separate Summary page to this amendment request)
COST TIME
CO# AMD# Description Additive Deductive Days Total New Justification
(+) (-) Added Time
Use funds of$9,798.30 Following permitting comments from
from the Owner's SFWMD the Lake CR-1B to CR-2A
1 Allowance for a change in interconnecting pipe needs to be
the pipe on the job increased from 42"to 48"diameter
❑Check here if additional summary page/s are attached to this Change Order
Page 2 of 4
Change Order Form(2023_ver.1)
16B6
Co [..K.-r county
Procurement Services Change Order Form
Contract# 23-8114 CO# 1 PO# 4500225866 Project#: 60143.2.4
Project Name: Carson Road Stormwater Treatment Area Improvement
Contractor/Consultant Name: Quality Enterprises USA, Inc.
Acceptance of this Change Order shall constitute a modification to contract/work order identified above and will be
subject to all the same terms and conditions as contained in the contract/work order indicated above, as fully as if
the same were stated in this acceptance. The adjustment, if any, to the Contract shall constitute a full and final
settlement of any and all claims of the Contractor/Vendor/Consultant/Design Professional arising out of or related
to the change set forth herein, including claims for impact and delay costs.
Contractor/Consultant/Design Professional signature below must be from an authorized person/officer/director of
the Company or listed as the qualified licensed Professional "Project Coordinator"or Design/Engineer Professional
under the agreement. Signature authority of person signing will be verified through the contract OR through the
Florida Department of State, Division of Corporations (Sunbiz) website (https://dos.mvflorida.com%sunbiz/search/).
If the person signing is not listed, we will require signature authority by one of the listed officers/directors of the
company giving that person signature authority.
?W=•4+�Nb:u..:aw a„..p.0 o,�nPM�ur..
BrzeskiPawel �.....o,x, P., .�..M.,_...
Prepared by: Date:
Signature-Division Project Manager
Pawel Brzeski, Project Manager II
Printed Name
Accepted by Date:
Signature-Design/Engineer Professional (if applicable)
N/A
Printed Name/Title/Company Name
Lou Gaudio Digitally signed by Lou Gaudio
Accepted by: Date:2024.06.27 14:28:25-04'00' Date:
Signature-Contractor/Consultant/Vendor
Louis J Gaudio,Vice President, Quality Enterprises USA, Inc.
Printed Name/Title/Company Name
Approved by. OvaresEriC o5 .. . ......... .•.. ,. ,.,�.�"wao �•u• Date:
Signature-Stormwater Reviewer Designee(Optional)
Eric Ovares, Project Manager II
Printed Name
OvaresRaquel Digitally signed by OvaresRaquel
Approved by: Date:2024.06.27 13:20:3I -04'00' Date:
Signature-Division Director or Designee (Optional)
Beth Johnssen,Director,Capital Project Planning,Impact Fees&Program Management
Printed Name
T.C.7/1/24
ScottTrinity Digitally signed by ScottTrinity
Approved by: Date:2024.07.09 10:38:24-04'00' Date:
Signature-Division Administrator or Designee (Optional)
Trinity Scott, Department Head, Transportation Management Services
Printed Name
Page 3 of 4
Change Order Form(2023_ver.1)
16B6
Crier County
Procurement Services Change Order Form
Contract# 23-8114 CO# 1 PO# 4500225866 Project#: 60143.2.4
Project Name: Carson Road Stormwater Treatment Area Improvement
Contractor/Consultant Name: Quality Enterprises USA, Inc.
FOR PROCURMENT USE ONLY
I
i
FY 24 CHO Request# 451
ZimmermanBec Digitaellysignedby
ZimmermanBecca
Date:2024.08.01 13:31:40
Approved by: ca -04'00'
Signature-Procurement Professional Signature/Date
Approved by:
Signature-Procurement Manager/Director(OPTIONAL)
APPROVAL TYPE:
❑ Administrative ❑ Administrative-BCC Report C BCC Stand-Alone ES (BCC Approval Required)
BCC APPROVAL
ATTEST:
Crystal K. Kinzel, Glerk of the Circuit Court BOARD OF COUNTY COMMISSIONERS
and Comptrollef COLLIER CO TY, FLORIDA
By; _. L.%r�1 By:
Y '
Chris I jail, Chaim an
Dated: D 9 i .
e-,'. : ,,;,a Date:
//.67 V
(SEAL) Agenda# 16 , (3 , 6
Ap oved as t F rm d eg ity: L
Deputy County Attorne
Print ame
Page 4 of 4
Change Order Form(2023_ver.1)
1636
Collier County Capital Project Planning, Impact Fees & Program
Management Division
WORK DIRECTIVE CHANGE
CONTRACT#/PROJECT NAME: #23-8114 PURCHASE ORDER#4500225866
Carson Road Stormwater Treatment Area
Work Directive#: 1 CHANGE: # I
DATE OF ISSUANCE: December 12, 2023 EFFECTIVE DATE: December 12, 2023
OWNER: Collier County Board of Commissioners PROJECT#: 60143.2.4
CONTRACTOR: Quality Enterprises USA,Inc. ENGINEER/DESIGN PROFESSIONAL: GHD,Inc.
You are directed to proceed promptly with the following change(s):
Description: The Carson Road STA is intended to accept flow from the existing stormwater system within the Immokalee
Drive Right-of-Way and from a series of areas in which Collier County plans to install future stormwater improvements. At the
time the Carson Road STA was advertised for construction bids,the design and permitting process for the upstream Lake
Trafford Road Right-of-Way was ongoing. Based on comments received from SFWMD during the design and permitting of the
drainage improvements within the Lake Trafford Road Right-of-Way,the size of the culvert from proposed Lake CR-1 B to
Lake CR-2A was required to be increased from 42 inch to 48 inches to accept the anticipated flow into the Carson Road STA
from the future drainage improvements from the Lake Trafford Road Right-of-Way.
Purpose of Work Directive Change: To resolve unforeseen pipe size change after the project was bid.
Reason/Justification: By providing the upsized storm pipe,Quality Enterprises will he able to proceed with the construction
in accordance with the updated construction drawings.
If a claim is made that the above change(s)have affected Contract Price or Contract Times any claim for a
Change Order based thereon will involve one or more of the following methods of determining the effect of the
changes(s).
Method of determining change in Contract Price: Method of determining change in Contract Times:
❑ Unit Prices ❑ Contractor's records
❑ Lump Sum ® Engineer's record
® Time&Material ❑ Other
❑ Other
Estimated increase(decrease) in Contract Price Estimated change in Contract Time:
$9,798.30 Increase or decrease by calendar days.
RECOMMENDED: AUTHORIZED:
Dgitally signed by Michael A Studney ,ore-m<•�roe«.�•w..°mR.
Michael A StudneyGewirtzStorm ,:w'.°���' °�°°"Sc=' -
y: Ova CO
Date:2023.12.21 15:0331-OS'00' �6+a����„� •^w^•r•<.a�•�o
Engineer Owner's Representative
1666
3494 SHEARWATER STREET
PROPOSAL NAPLES,FL 34117
(239)435-720
QUALITY FAX(239)435-72022
ENTERPRISES
Collier County June 18, 2024
CO-001
PROPOSAL SUBMITTED TO: DATE PROPOSAL#
Carson Road Matthew Murphy
STREET SALES REPRESENTATIVE
Immokalee, Florida 34142 Carson Road Stormwater Treatment Area
CITY, STATE, ZIP JOB NAME
Pawel Brzeski Immokalee, FL
ATTN.: JOB LOCATION
WE PROPOSE hereby to furnish all labor,materials,equipment and services necessa{r to complete the following:
Carson Road Construction Plans Rev06 dated 10/19/23
1. Revised pipe size on control structure CS CRIB/CR2A to 48-inch RCP (see sheets C-111, C-121, and
C-122)
Estimated Total: $9,798.30
O•itaN Waned by arzatkPawel Lou Digitally signed
DN
P+Pawel.kiPew�rtlLarrsam Prcje
Brzeski Pawel CN-$rmdiPawel,OU GapilalPrgetl by Lou Gaudio
Planning Utara,OU=CM e;:r.,
P,4 CCPua,�,,.DU-Cpetlrpnipna„d Date: 2024.06.27
DC
-bcc.D 6-aili7 GM4O°.0=nel Gaudio
14:28:48-04'00'
Date 204 212wrov.
CUSTOMER—SIGNATURE&DATE QUALITY ENTERPRISES USA,INC.—SIGNATURE&DATE
Page 1
16B6
Change Order ff 1
EXHIBIT"A"
Deductions from allowance
Carson Rd.SW Treatment Area
BID PROPOSAL
Original Contract Previous Change Orders This Change Revised Contract
Increase/De
Unit Of Increase/Deere Original Unit Of Total Revised
Original Qty crease Cost per Unit Total Revised Item Cost
Measure ase Quantity Quantity Measure Item Quantity
ITEM B Description Quantity
57 42"RCP pipe 930 LF 930 -107.00 LF $ 252.25 823 $ (26,990.75)
ADD 96 48"ADS pipe 0 LF 0 107.00 LF $ 343.82 107 $ 36,789.05
CHANGE ORDER SUM $ 9,798.30
Owner Allowance-Roadway $ 490,000.00
Previous CO Increases/(Decreases) $Total Increase/(Decrease)This Change $ 9,798.30
Total Revised-Roadway Allowance $ 480,201.70
1 6 B 6
QUALITY ENTERPRISES USA,INC. Job# 14623-12
Emergency Repair Work for Rates-Carson Rd SW Treatment Area Date 06/18/24
Collier County-Board of County Commissioners
Under Contract#20-7800
ST HOURLY OT HOURLY ST OT ST OT
UNIT RATE RATE HOURS HOURS TOTAL TOTAL TOTAL
personnel
Corporate Officer HR $150.00 $195.00 $0.00 $0.00 $0.00
Project Manager HR $125.00 $162.50 $0.00 $0.00 $0.00
Superintendent HR $85.00 $110.50 16 $1,360.00 $0.00 $1,360.00
Foreman HR $85.00 $110.50 16 4 $1,360.00 S442.00 $1,802.00
Mechanic,Equipment 8 Truck Operator HR $75.00 $97.50 32 8 $2,400.00 $780.00 $3,180.00
Laborer HR $55.00 $71.50 48 12 $2,640.00 5858.00 $3.498.00
Administrative HR $75.00 $97.50 $0.00 $0.00 $0.00
Eauioment
Excavator>Cat 349 HR $250.00 $0.00 $0.00 $0.00
Excavator>Cat 320 HR $200.00 16 $3,200.00 $0.00 $3,200.00
Excavator<Cat 320 HR $150.00 $0.00 $0.00 $0.00
Excavator w/hammer/Epiroc HR $350.00 $0.00 $0.00 $0.00
Excavator w/side grip vibratory hammer HR 5350.00 $0.00 $0.00 $0.00
Wheel Loader>Cat 962 HR 5225.00 $0.00 $0.00 $0.00
Wheel Loader>Cat 938 HR $175.00 16 $2,800.00 $0.00 $2,800.00
Wheel Loader<Cat 938 HR $150.00 $0.00 $0.00 $0.00
Bull Dozer HR $175.00 $0.00 $0.00 $0.00
Motor Grader HR $175.00 $0.00 $0.00 $0.00
Soil/Stone Roller HR $125.00 50.00 $0.00 $0.00
Telehandler HR $125.00 $0.00 $0.00 $0,00
Marlin HR S125,00 $0.00 $0.00 $0.00
Forklift HR S100.00 S0.00 $0.00 $0.00
Broom Tractor HR $95.00 $0.00 $0.00 $0.00
Milling Machine HR 5685.00 $0.00 $0.00 $0.00
Skid steer with milling head(bump grinder) HR SI 50.00 $0.00 $0.00 $0.00
1 Asphall/Mat.Shuttle Buggy HR $375,00 $0,00 $0.00 $0.00
Asphalt Paver Weiler 385 HR $375.00 $0.00 $0.00 $0.00
Asphalt Paver Cat 1055 HR $575.00 $0.00 $0.00 $0.00
Asphalt Roller HR $125.00 $0.00 $0.00 $0.00
Off Road Dump HR $250.00 $0.00 $0.00 $0.00
Crane>130 ton HR $1,500.00 $0.00 $0.00 $0.00
Crane>30 ton HR $500.00 $0.00 $0.00 $0.00
Crane<30 ton HR $250.00 $0.00 $0.00 $0.00
Vibratory Hammer HR $400.00 $0.00 $0.00 $0.00
Concrete Crusher HR $685.00 $0.00 $0.00 $0.00
Screener HR $375.00 $0.00 $0.00 $0.00
Push Boat HR $275.00 $0.00 $0.00 $0.00
Sectional/HopperBarge HR $175.00 $0.00 $0.00 $0.00
Drone Lidar Photogrammetry HR $350.00 $0.00 $0.00 $0.00
Directional Drill JT 100 HR $2,000.00 $0.00 $0.00 $0.00
Directional Drill AA 440 HR $4,000.00 $0.00 $0.00 $0.00
Lowboy/Tractor HR $175.00 $0.00 $0.00 $0.00
Dump Truck/Roll Off HR $95.00 $0.00 $0.00 $0.00
Water Truck/Trailer HR $125.00 $0.00 $0.00 $0.00
Tack/Prime Truck/Trailer HR $150.00 $0.00 $0.00 $0.00
Lube/Mechanics Truck HR $125.00 $0.00 $0.00 $0.00
Truck with Hand Tools HR $95.00 16 $1,520.00 $0.00 $1,520,00
Pickup HR $4n.00 16 $640.00 $0.00 $640.00
Camera Truck HR $400.00 $0.00 $0.00 $0.00
Vacuum Truck HR S475.00 $0.00 $0.00 $0.00
small Eauioment $0.00
Air Compressor with Hammer HR $60.00 $0.00 $0.00 $0.00
Concrete Saw HR $60.00 $0.00 $0.00 $0.00
Plate Compactor HR $60.00 16 $960.00 $0.00 $960.00
Trench Box 16'x 10' HR $50.00 $0.00 $0.00 $0.00
Stone Box HR $50.00 16 $800.00 $0.00 S800.00
Steel(Road)Plate HR $50.00 $0.00 $0.00 $0.00
Wellpoint System HR $250.00 $0.00 $0.00 $0.00
3'Trash/Submersible Pump HR $50.00 16 $800.00 $0.00 $800.00
6"Hydraulic Pump HR $150.00 $0.00 $0.00 $0.00
12"Hydraulic Pump HR 5200.00 $0.00 $0.00 $0.00
Cut Off Saw HR $20.00 $0.00 $0.00 $0.00
Light Set HR $50.0U $0.00 $0.00 $0.00
Generator/Welder HR $50.00 $0.00 $0.00 $0.00
Generator 70kw HR 5125.00 $0.00 $0.00 $0.00
Generator 125kw HR $150.00 $0.00 $0.00 $0.00
MOT HR $150.00 $0.00 $0.00 $0.00
Fusing Machine 2-16" HR $150,00 $0.00 $0.00 $0.00
Fusing Machine 18"-42' HR $300.00 $0.00 $0.00 $0.00
Tap Machine-small(3/4"-3") each tap EA S750.00 $0.00 $0.00 $0.00
Tap Machine-large(4'-12") each tap EA $1,000.00 $0.00 $0.00 $0.00
Pipe Trenchtess Piercing tool HR $250.00 $0.00 $0.00 $0.00
Pipe Ramming HR $625.00 $0.00 SO.00 $0.00
Material
Disposal Fee(concrete,asphalt,debris,etc) PER LOAD $500.00 $0.00 $0.00 $0.00
Ferguson Water Works-48x20 HP w/10%mark up LF $151.6734 107 $16,229.05 $0.00 $16,229.05
Grand Total: 536,789.05
10%MARK UP ON MATERIAL
15%MARK UP ON SUBCONTRACTORS
If work is performed other than Monday through Friday,7:00am-4:00 pm.excluding holidays,0T Rates will be used for Personnel.These rates also apply for travel time necessary to
mobilize and demobitiZe to and from work.
REV.3/172021
FERGUSONFEL-NAPLES WATERWORKS#136 Deliver To: ROBERT
3801 PROSPECT AVE From: Grant Kutzke
WATERWORKS NAPLES,FL 34104 Comments:
Phone:239-643-4970
Fax:239-643-4945
08:27:20 DEC 11 2023 Page 1 of 1
FEL-NAPLES WATERWORKS#136
Price Quotation
Phone:239-643-4970
Fax: 239-643-4945
Bid No: B316463 Cust Phone: 239-435-7200
Bid Date: 10/23/23 Terms: NET 10TH PROX
Quoted By: TAE
Customer: QUALITY ENTERPRISES USA INC Ship To: QUALITY ENTERPRISES USA INC
3494 SHEAR WATER STREET 3494 SHEAR WATER STREET
CARSON RD STORMWATER CARSON RD STORMWATER
NAPLES, FL 34117 NAPLES, FL 34117
Cust PO#: 48"ADS HP Job Name: CARSON RD STORMWATER
Item Description Quantity Net Price UM Total
A486500201BPL 48X20 HP N12 DW STORM SLD PL PIP 107 130.3500 FT 13947.45
Net Total: $13947.45
Tax: $886.85
Freight: $0.00
Total: $14834.30
Quoted prices are based upon receipt of the total quantity for immediate shipment(48 hours). SHIPMENTS BEYOND 48 HOURS SHALL BE
AT THE PRICE IN EFFECT AT TIME OF SHIPMENT UNLESS NOTED OTHERWISE.QUOTES FOR PRODUCTS SHIPPED FOR RESALE
ARE NOT FIRM UNLESS NOTED OTHERWISE.
CONTRACTOR CUSTOMERS:IF YOU HAVE DBE/MBE/WBE//VBE/SDVBE/SBE GOOD FAITH EFFORTS DIVERSITY GOALS/REQUIREMENTS ON A
FEDERAL STATE,LOCAL GOVERNMENT,PRIVATE SECTOR PROJECT,PLEASE CONTACT YOUR BRANCH SALES REPRESENATIVE
IMMEDIATELY PRIOR TO RECEIVING A QUOTE/ORDER.
Seller not responsible for delays,lack of product or increase of pricing due to causes beyond our control,and/or based upon
Local,State and Federal laws governing type of products that can be sold or put into commerce. This Quote is offered contingent upon the
Buyer's acceptance of Seller's terms and conditions,which are incorporated by reference and found either following this document,or
on the web at https://www.ferguson.com/contenUwebsite-info/terms-of-sale
Govt Buyers: All items are open market unless noted otherwise.
LEAD LAW WARNING:It is illegal to install products that are not"lead free"in accordance with US Federal or other applicable law in potable water
systems anticipated for human consumption.Products with'NP in the description are NOT lead free and can only be installed in non-potable
applications.Buyer is solely responsible for product selection.
HOW ARE WE DOING? WE WANT YOUR FEEDBACK!
E 4L i0 Scan the QR code or use the link below to
complete a survey about your bids:
l]w https://survey.medallia.com/?bidsorder&fc=136&on=48166
6B6
Carson Road Stormwater Treatment Area pipe size increase 42" to 48" diameter.
Required change following SFWMD permitting comments between lake CR-1 B and CR-2A a length of
107' total at this location that was bid under Item #57 at$252.2500 per linear foot installed of pipe
Fergusson supplied material 48" in 20' lengths at$130.3500 per foot based on 10.23.2023 bid price and
supplied before 12.31.2023 which was subject to taxes at 7%on the first$5,000.00 and at 6%on the
balance, but Collier County only reimburses for actual length of pipe installed.
107' $130.35/ft $13,947.45
10%markup $ 1,394.75 no tax on markup amount
7%Tax $ 5,000.00 $ 350.00 the extra penny tax on first$5k expired 12.31.2023
6%Tax $ 8,947.45 $ 536.85
Total Tax $ 886.85 on base amount only exclusive of mark up
Cost 107'with tax $14,834.30
Cost 107' with Tax and m/up $16,229.05* equivalent to$151.6734/ft UNIT RATE MATERIAL
Unit rate entered into Item #96
Fergusson Water Works—48x20 HP wI 10%mark up LF $151.6734 107 $16,229.05
Bid Item #57 unit rate for 42"pipe at $252.2500 installed per LF
Remove 107 LF g 252.2500=$26,990.75 credited to Item #96
Additional construction costs=$20,560.00 plus additional pipe cost* = $36,789.05**
Less credit for 107'of 42"pipe not installed $26,990.75 - $26,990.75
Utilizing Item #97 Owners Allowance $ 9,798.30
** The unit rate for installation of 48"diameter pipe is$343.8229 per LF