Agenda 08/27/2024 Item #16F 3 (Change Order #13 under Agreement No. 17-7199, “Design Services for Collier County Sports Complex)08/27/2024 EXECUTIVE SUMMARY Recommendation to approve Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier County Sports Complex,” by adding a time extension of 365 days, and additional funds in the amount of $48,500, consisting of new Task 13-PUDA for $40,000, new Task 14-General Consulting and Coordination for $6,000, and increasing Task-6 Reimbursables by $2,500 under Phase 3 of the project. (Project No. 50156) OBJECTIVE: To obtain approval of Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier County Sports Complex,” by adding a time extension of 365 days, and additional funds in the amount of $48,500 consisting of new Task 13-PUDA for $40,000, new Task 14-General Consulting and Coordination for $6,000, and increasing Task-6 Reimbursables by $2,500 under Phase 3 of the project. CONSIDERATIONS: On June 12, 2018 (Agenda Item 11. C), the Board approved Agreement No. 17-7199 (the “Agreement”) in the amount of $4,854,383 to Davidson Engineering, Inc. for the Collier County Sports Complex Design Services. On May 28, 2024, the Board gave direction to amend the Paradise Coast Sports Complex (the “Complex”) PUD to lessen the restrictions on the allowable direction for amplified sound. Approval of Change Order No.13 will add 365 days and $48,500 to the agreement. Task 13 is being provided as a lump sum since the PUD Amendment will be performed by a subconsultant to Davidson Engineering Inc. These changes are required to include a zoning amendment to the existing City Gate Commerce Park PUD Ordinance No. 2021-15 to lessen the restrictions on the allowable direction for amplified sound. If Change Order 13 is not approved and the PUD amendment does not move forward, the current restrictions on amplified sound direction will remain, limiting the ability to host concerts and other entertainment events, thereby reducing the versatility and attractiveness of the complex's facilities. Additionally, the Complex would continue to rely on special event permits that conflict with the current PUD, requiring Board approval for each event, which is inefficient and could cause delays. Furthermore, the Complex's strategic vision of becoming a national tourism destination for sports and entertainment could be hindered, limiting its growth and development potential due to the inability to meet the needs of major event organizers. This item is consistent with the Infrastructure and Asset Management, and Quality of Place elements of the Collier County Strategic Plan. The County’s Procurement Services Division administratively approved Change Order No. 13 as authorized under the Procurement Ordinance, Section Nineteen, Contract Administration, Section 19, subsection 3.b. To date, there have been twelve change orders consisting of adding cost and time. (See attached Change Order No. 13 Amendment Summary). FISCAL IMPACT: Funds in the amount of $48,500 are available within the Sports Complex Capital Fund (3007) Project No. (50156). LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for Board approval. -SRT GROWTH MANAGEMENT IMPACT: This action has no impact on the Growth Management Plan. RECOMMENDATION: To approve Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier County Sports Complex,” by adding a time extension of 365 days, additional funds in the amount of $48,500, consisting of new Task 13-PUDA for $40,000, new Task 14-General Consulting and Coordination for $6,000, increasing Task-6 Reimbursables by $2,500 under Phase 3 of the project, and authorizing the Chairman to sign the attached change order. (Project No. 50156) 16.F.3 Packet Pg. 1544 08/27/2024 Prepared by: Brian DeLony, Supervisor- Project Management (Licensed), Facilities Management Division ATTACHMENT(S) 1. Change Order # 13_PO 4500187994_Davidson Engineering (PDF) 2. 17-7199 DavidsonEngineering_Contract (PDF) 16.F.3 Packet Pg. 1545 08/27/2024 COLLIER COUNTY Board of County Commissioners Item Number: 16.F.3 Doc ID: 29583 Item Summary: Recommendation to approve Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier County Sports Complex,” by adding a time extension of 365 days, and additional funds in the amount of $48,500, consisting of new Task 13-PUDA for $40,000, new Task 14-General Consulting and Coordination for $6,000, and increasing Task-6 Reimbursables by $2,500 under Phase 3 of the project. (Project No. 50156) Meeting Date: 08/27/2024 Prepared by: Title: Operations Analyst, Senior – Facilities Management Name: Bendisa Marku 08/06/2024 2:51 PM Submitted by: Title: – Facilities Management Name: John McCormick 08/06/2024 2:51 PM Approved By: Review: Facilities Management John McCormick Director - Facilities Completed 08/06/2024 2:59 PM Facilities Management Brian DeLony Other Reviewer Completed 08/06/2024 4:40 PM Procurement Services Vanessa Miguel Level 1 Purchasing Gatekeeper Completed 08/07/2024 8:27 AM Facilities Management Jennifer Belpedio Manager - Real Property Completed 08/07/2024 9:50 AM Procurement Services Sandra Srnka Procurement Director Review Completed 08/14/2024 7:49 PM County Attorney's Office Scott Teach Level 2 Attorney Review Completed 08/15/2024 2:35 PM Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 08/15/2024 2:37 PM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 08/16/2024 9:19 AM Community & Human Services Maggie Lopez OMB Reviewer Completed 08/19/2024 10:44 AM County Manager's Office Amy Patterson Level 4 County Manager Review Completed 08/20/2024 11:54 AM Board of County Commissioners Geoffrey Willig Meeting Pending 08/27/2024 9:00 AM 16.F.3 Packet Pg. 1546 16.F.3.a Packet Pg. 1547 Attachment: Change Order # 13_PO 4500187994_Davidson Engineering (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design 16.F.3.a Packet Pg. 1548 Attachment: Change Order # 13_PO 4500187994_Davidson Engineering (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design 16.F.3.a Packet Pg. 1549 Attachment: Change Order # 13_PO 4500187994_Davidson Engineering (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design 16.F.3.a Packet Pg. 1550 Attachment: Change Order # 13_PO 4500187994_Davidson Engineering (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design 16.F.3.a Packet Pg. 1551 Attachment: Change Order # 13_PO 4500187994_Davidson Engineering (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design 16.F.3.a Packet Pg. 1552 Attachment: Change Order # 13_PO 4500187994_Davidson Engineering (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design 16.F.3.a Packet Pg. 1553 Attachment: Change Order # 13_PO 4500187994_Davidson Engineering (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design 16.F.3.a Packet Pg. 1554 Attachment: Change Order # 13_PO 4500187994_Davidson Engineering (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design 16.F.3.bPacket Pg. 1555Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1556Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1557Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1558Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1559Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1560Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1561Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1562Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1563Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1564Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1565Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1566Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1567Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1568Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1569Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1570Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1571Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1572Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1573Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1574Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1575Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1576Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1577Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1578Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1579Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1580Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1581Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1582Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1583Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1584Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1585Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1586Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1587Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1588Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1589Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1590Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1591Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1592Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1593Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier 16.F.3.bPacket Pg. 1594Attachment: 17-7199 DavidsonEngineering_Contract (29583 : Change Order No. 13 under Agreement No. 17-7199, “Design Services for Collier