Loading...
Agenda 08/27/2024 Item #15B 1 (Construction update on NCWRF Pretreatment Facility Project No. 70149)08/27/2024 EXECUTIVE SUMMARY *** Continued from July 23, 2024 BCC Meeting. *** Recommendation to accept a project update to NCWRF Pretreatment Facility Project No. 70149 currently under construction with Poole & Kent Company of Florida under Agreement No. 23-8116. OBJECTIVE: To keep the Board informed of the construction progress on NCWRF Pretreatment Facility Project No. 70149 (the “Project”). CONSIDERATIONS: This project includes the design, competitive procurement, and construction of a new Pretreatment Facility (the “Headworks”) at the North County Water Reclamation Facility (“NCWRF”). The Project will upgrade the plant’s operational needs and allow the NCWRF to remain in compliance while meeting demand throughout the service area. On July 12, 2022, the Board certified the existence of a valid public emergency necessary to expedite a re-design of the project and approved Agreement No. 20-7722-NS to AECOM Technical Services, Inc. (“AECOM”) for NCWRF Headworks Engineering Services. Staff issued a Notice to Proceed to AECOM on August 18, 2022, initiating the redesign effort for the Pretreatment Facility. The design effort was completed on February 28, 2023, with the solicitation for the construction contract issued for bid on March 6, 2023. At the July 11, 2023, Board meeting, the Board awarded the construction contract to Poole & Kent Company of Florida and authorized execution of Agreement No. 23-8116. The Notice to Proceed for construction was issued on August 28, 2023. The current construction contract progress summary as of July 3, 2024, includes continued installation of reinforcing steel, concrete formwork, sequenced concrete pours, extension of 42”, 36”, 24” yard piping, and electrical building conduit installation under slab and foundations. The contract summary is included in the table below: County Contract # 23-8116 County Project Number / PO Number WBS 70149.1 / PO 4500225567 Notice To Proceed Date August 28, 2023 Substantial Completion Date January 8, 2026 Final Completion Date March 9, 2026 Original Contract Time 924 days (final completion) Revised Substantial Completion Date n/a Revised Final Completion Date n/a Revised Contract Time n/a Days to Date 310 Days Remaining to Substantial Completion 554 Days Remaining to Final Completion 614 Time % Complete 34% Original Contract Amount $55,660,000 Revised Contract Amount n/a Billed to Date $10,948,117.41 Billed to Date: 20% AECOM is under contract to provide construction administration services throughout the construction of the project. In-house staff is providing quality assurance/quality control construction inspection services. 15.B.1 Packet Pg. 113 08/27/2024 FISCAL IMPACT: The source of funding for this project is Wastewater User Fee Capital Fund (4014), Project 70149, and the Water/WW Bond/Loan Fund (4020), Project 70149. The project update itself does not carry a fiscal impact. GROWTH MANAGEMENT IMPACT: There is no Growth Management impact associated with this item. LEGAL CONSIDERATIONS: This item has been reviewed by the County Attorney’s Office and does not present a legal issue required for acceptance of staff’s Project update. -SRT RECOMMENDATION: To accept a project update for the NCWRF Pretreatment Facility Project No. 70149. Prepared by: Wayne Karlovich, Supervisor - Project Management, Public Utilities Engineering and Project Management Division ATTACHMENT(S) 1. BCC Update - Headworks - Karlovich 07.23.24 final (PPTX) 15.B.1 Packet Pg. 114 08/27/2024 COLLIER COUNTY Board of County Commissioners Item Number: 15.B.1 Doc ID: 29553 Item Summary: *** Continued from July 23, 2024 BCC Meeting. *** Recommendation to accept a project update to NCWRF Pretreatment Facility Project No. 70149 currently under construction with Poole & Kent Company of Florida under Agreement No. 23-8116. Meeting Date: 08/27/2024 Prepared by: Title: Management Analyst II – County Manager's Office Name: Geoffrey Willig 07/31/2024 4:46 PM Submitted by: Title: Director – Engineering and Project Management Name: Matthew McLean 07/31/2024 4:46 PM Approved By: Review: Engineering and Project Management Geoffrey Willig PUD Reviewer Skipped 07/31/2024 4:46 PM Public Utilities Operations Support Geoffrey Willig PUD Reviewer Skipped 07/31/2024 4:46 PM Wastewater Geoffrey Willig PUD Reviewer Skipped 07/31/2024 4:46 PM County Attorney's Office Geoffrey Willig Level 2 Attorney Review Skipped 07/31/2024 4:46 PM Corporate Compliance and Continuous Improvement Geoffrey Willig Additionall Reviewer Skipped 07/31/2024 4:46 PM County Attorney's Office Geoffrey Willig Level 3 County Attorney's Office Review Skipped 07/31/2024 4:46 PM Office of Management and Budget Geoffrey Willig Level 3 OMB Gatekeeper Review Skipped 07/31/2024 4:46 PM Public Utilities Department George Yilmaz Level 2 Division Administrator Review Completed 08/07/2024 4:28 PM Community & Human Services Maggie Lopez OMB Reviewer Completed 08/19/2024 11:01 AM County Manager's Office Ed Finn Level 4 County Manager Review Completed 08/14/2024 5:44 PM Board of County Commissioners Geoffrey Willig Meeting Pending 08/27/2024 9:00 AM 15.B.1 Packet Pg. 115 Strategic Plan Next Steps/Current Challenges Updated: 07/03/24 •Installation of reinforcing steel, concrete formwork and sequenced concrete pours. •Extending 42”, 36” and 24” yard piping from main structure to west fence line. •Electrical building under slab conduit and foundations. •Challenges to date: •Unforeseen underground soil conditions impacting Aggregate Pier Soil Reinforcement columns and building pad foundation (Resolved –finalization of change order in process) •Unforeseen abandoned 30” underground pipe conflict (Work Directive issued -change order process underway) Progress •Headworks structure concrete foundations have been poured; concrete wall pours underway. •All 24”, 36” and 42” piping has been installed under building footprint and encased in concrete. •Electricians have completed all electrical conduits and duct bank under building footprint. •Resolved stone column obstruction issue and completed ground stabilization for Headworks buildings. ScheduleProject Phase August 17, 2022Design NTP 100%Design August 28, 2023Construction NTP 2.5 yearsConstruction Duration 34%Construction Time Complete 20% Construction Work Billed/Complete 2District # 70149Project # Wayne Karlovich, P.E.Project Manager Public Utilities Department -EPMDProject Sponsor Scope: Installation of a new pretreatment facility at the North County Water Reclamation Facility (NCWRF). $14,105,963Design Budget $55,660,000Const Budget $69,765,963Total Budget AECOMArch/Eng: Poole and KentGeneral Cont CCWSD QA/QC teamOwner Rep (CEI) In-house InspectionsCEI Cost January 8, 2026Sub Completion March 9, 2026Final Completion NORTH COUNTY WATER RECLAMATION FACILITY PREAT MENT FACILITY PROJECT 15.B.1.a Packet Pg. 116 Attachment: BCC Update - Headworks - Karlovich 07.23.24 final (29553 : NCWRF Pretreatment Facility Strategic Plan Rebar & Forms Installation for Wa ll Pour 6 NORTH COUNTY WATER RECLAMATION FACILITY PREAT MENT FACILITY PROJECT 15.B.1.a Packet Pg. 117 Attachment: BCC Update - Headworks - Karlovich 07.23.24 final (29553 : NCWRF Pretreatment Facility Strategic Plan Wall Pour 6 NORTH COUNTY WATER RECLAMATION FACILITY PREAT MENT FACILITY PROJECT 15.B.1.a Packet Pg. 118 Attachment: BCC Update - Headworks - Karlovich 07.23.24 final (29553 : NCWRF Pretreatment Facility Strategic Plan Extending 42”, 36”, and 24” Yard Piping to West Fence Line. NORTH COUNTY WATER RECLAMATION FACILITY PREAT MENT FACILITY PROJECT 15.B.1.a Packet Pg. 119 Attachment: BCC Update - Headworks - Karlovich 07.23.24 final (29553 : NCWRF Pretreatment Facility Strategic Plan Electrical Building Underground Conduit Installation NORTH COUNTY WATER RECLAMATION FACILITY PREAT MENT FACILITY PROJECT 15.B.1.a Packet Pg. 120 Attachment: BCC Update - Headworks - Karlovich 07.23.24 final (29553 : NCWRF Pretreatment Facility Strategic Plan Electrical Building Underground Conduit Backfilling, Pour and Clean Up NORTH COUNTY WATER RECLAMATION FACILITY PREAT MENT FACILITY PROJECT 15.B.1.a Packet Pg. 121 Attachment: BCC Update - Headworks - Karlovich 07.23.24 final (29553 : NCWRF Pretreatment Facility Strategic Plan Thank you! 15.B.1.a Packet Pg. 122 Attachment: BCC Update - Headworks - Karlovich 07.23.24 final (29553 : NCWRF Pretreatment Facility