Loading...
Agenda 07/09/2024 Item #16B 2 (Approve Change Order No. 1 to Agreement No. 23-8079 - Treeline Drive & Logan Blvd., North Immokalee Road Intersection Improvements to Thomas Marine Construction, Inc.)07/09/2024 EXECUTIVE SUMMARY Recommendation to approve Change Order No. 1 to Agreement No. 23-8079, Treetine Drive & Logan Blvd., North of Immokalee Road Intersection Improvements to Thomas Marine Construction, Inc., adding seventeen days to the agreement and utilizing $41,882.00 for unforeseen additional items from the Owner's Allowance, and authorize the Chairman to sign the attached Change Order. (Project No. 60245) OBJECTIVE: To obtain approval of Change Order No. 1 to utilize the Owner's Allowance to pay for additional existing and new pay item quantities and approve adding seventeen days to Agreement No. 23-8079, for the construction contract for the Treeline Drive & Logan Blvd., North of Immokalee Rd Intersection Improvements (the "Project"). CONSIDERATIONS: On April 11, 2023, the Board approved Agreement No. 23-8079 in the amount of $1,249,275.10 (the "Agreement"), providing for the construction contract for the Project to Thomas Marine Construction, Inc. Change Order No.1 requests utilizing a total of $41,882.00 from the Owner's Allowance for unforeseen and additional pay item quantities, including $9,865.20 for after-hours flagging and pedestrian escort operations. This change is needed to mitigate the impact of the construction project occurring after workers complete work for the day and to safely accommodate heavy pedestrian traffic from local developments. Traffic congestion due to the project became so severe that it was impacting other arterial roads and became a risk to the traveling public. This process occurred from February 20, 2024, until March 29, 2024, the presumed end of season. Additionally, $32,016.80 of the Change Order is utilized to pay for overruns on-line items (shown on Exhibit "A") needed to complete the construction of the Project. The attached Change Order No. 1 seeks to add seventeen additional days to the Agreement, which would adjust the Substantial and Final Completion dates accordingly. Extending the time of the Agreement is necessary because of unforeseen existing underground private utility conflicts in the right of way at the intersection of Treeline Drive and Logan Boulevard. This item is consistent with the Collier County strategic plan objective to design and maintain an effective transportation system to reduce traffic congestion and improve the mobility of the County's residents and visitors. FISCAL IMPACT: Requested use of Owner's Allowance in the amount of $41,882.00 are part of the contract award and are encumbered within Transportation & CDES Capital Fund (3081), Project 60245 under Purchase Order 4500224353 and will be used to pay for the unforeseen work. GROWTH MANAGEMENT IMPACT: This recommendation is consistent with the Long -Range Transportation Plan and Objective I of the Transportation Element of the Collier County Growth Management Plan to maintain the major roadway system at an acceptable Level of Service LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for Board approval. -SRT RIF,COMMENDATION: To approve Change Order No. 1, under Agreement No. 23-8079, Treeline Drive & Logan Blvd. North of Immokalee Road, Intersection Improvements project, adding seventeen days to the agreement and $41,882.00 for unforeseen additional items from the Owner's Allowance, and authorize the Chairman to sign the attached Change Order. Prepared by: Shannon Bassett, PMP, Field Inspector 11, Transportation Engineering Division ATTACHMENT(S) 1. [Linked] 23-8079 Contract —Thomas Marine (PDF) I Packet Pg. 343 07/09/2024 2. Change Order #1 (PDF) Packet Pg. 344 07/09/2024 COLLIER COUNTY Board of County Commissioners Item Number: 16.13.2 Doe ID: 29041 Item Summary: Recommendation to approve Change Order No. I to Agreement No. 23-8079, Treeline Drive & Logan Blvd. North of Immokalee Rd. Intersection Improvements to Thomas Marine Construction, Inc., adding seventeen days to the agreement and utilizing $41,882.00 for unforeseen additional items from the Owner's Allowance, and authorize the Chairman to sign the attached Change Order. (Project No. 60245) Meeting Date: 07/09/2024 Prepared by: Title: — Transportation Engineering Name: Kimberly Brandes 05/29/2024 9:54 AM Submitted by: Title: Division Director - Transportation Eng — Transportation Engineering Name: Jay Ahmad 05/29/2024 9:54 AM Approved By: Review: Transportation Management Services Department Jeanne Marcella Department Transportation Engineering Lisa Taylor Other Reviewer Transportation Engineering Anthony Khawaja Other Reviewer Transportation Engineering Matthew Thomas Other Reviewer Transportation Management Operations Support Tara Castillo Procurement Services Sandra Srnka Level 1 Purchasing Gatekeeper Procurement Services Sandra Srnka Procurement Director Review Transportation Management Services Department Trinity Scott County Attorney's Office Office of Management and Budget Community & Human Services County Attorney's Office County Manager's Office Board of County Commissioners Scott Teach Level 2 Attorney Review Debra Windsor Level 3 OMB Gatekeeper Review Maggie Lopez OMB Reviewer Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Geoffrey Willig Level 4 County Manager Review Geoffrey Willig Meeting Pending Transportation Management Services Completed 05/29/2024 10:32 AM Completed 05/29/2024 10:59 AM Completed 05/29/2024 12:57 PM Completed 05/29/2024 1:23 PM Other Reviewer Completed 05/29/2024 1:59 PM Completed 05/30/2024 8:17 AM Completed 05/30/2024 8:18 AM Transportation Completed 06/04/2024 9:59 AM Completed 06/10/2024 9:17 AM Completed 06/10/2024 9:52 AM Completed 06/10/2024 1:47 PM Completed 06/14/2024 12:05 PM Completed 07/02/2024 10:58 AM 07/09/2024 9:00 AM I Packet Pg. 345 1 Co ftcouwy Procurement Services Change Order Form contract# 23-8079 CO# 1 PO# 4600224353 Project#; 60245 Project Name: Treeline Dr Logan Blvd North of CR846 Intersection Improvements Contractor/Consultant Name: Thomas Marine Construction Inc. Select One: El Contract Modification (Construction or Project Specific) El Work Order Modification Project Manager Name] Shannon Bassett Division Name: I Transportation Engineering Services] Original Contract[Work Order Amount $1.249,275,10 4-11-23,16AI6 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $112401M.10 4-1i-23.1GA10 Last 8CC Approval Date; Agenda Item # Current Contract/Work Order Amount $1.249,275,10 MO-24 SAP Contract Expiration Date (MASTER) Dollar Amount of this Change 0.00% Total % Change from Original Amount Revised Contract/Work Order Total $i,249,276A0 1 0,000/0 % Change from Current BCC Approved Amount Fe Changes $0.00 1 o,00% % Change from Current Amount Notice to Proceed Original NTP Original Final Last Final Date # of Days Completion Date Approved Date # of Days Added Revised Final Date Current Substantial Completion Date 5-20-24 = (Includes this change) (if applicable) I Provide responses after each question In box below (Responses should be br-f4L6d:4vocIfI6), Attach additional information andlor documentation from the Design Professlonal and/or Contractor, if needed, with your submission of this Change Order and complete summary on next page. Chock all that apply to this Change Order request: [a Add Time; D Add funds: 2) Use of Allowance; El Modify/Delete existing Task(s); El Add new Task(s); El Reallocate funds-, E) Other (must be explained in detail below) 1. TO utilize the Owner's Allowance to pay for additional existing and new line item quantities and approve seventeen (17) days to Agreement No. 23-8079, for the construction contract for the Treeline Drive & Logan Blvd, North of Immokalee Rd, Intersection Improvements, A. To utilize the Allowance (CC-1000) In the amount of $9,865.20 to compensate for the flagging operation at the intersection of Treeline Dr. and Logan Blvd, during the week from the hours of 4:00pm-6:00pm and incorporate into the contract a new pay Item 102-25-100, This is needed to mitigate the impact of the construction project on the traffic flow on the roadways near the construction site and to safely accommodate heavy pedestrian traffic from local developments during peak rush hour traffic. This operation occured from February 20, 2024, until March 29, 2024, the presumed end of season. B. To utilize the Allowance (CC-1000) in the amount of $32,016.80 (shown on Exhibit "A") to pay for additional line item quantities. C. Seventeen (17) additional days are being requested due to unforeseen private utility conflicts in the right of way on Treeline Dr & Logan Blvd. which prevented the contractor from continuing the construction of the traffic circle at the Intersection, The utilities in conflict were within the roadway of the new traffic circle. 2. Work stop Issued on May 1, 2024, 49 days remain, 3. The change being requested was not included in the original contract because the contract quantities are an estimate and the field conditions required additional materials, the traffic and utility issues were not known at the time of contract. .4. If the changes being request are not approved the project could not be completed on time and according to the current construction standards. Page I of 4 Change Order Form (2023—ver,l) i3 It 04 Q W Packet Pg. 346 001 te� C014nty Procurement Services Change Order Form Contract# 23-8079 CO# I Po# 4500224353 Project#: 60245 Project Name: Treeline Dr & Logan Blvd North of CR846 Intersection Improvements Contractor/Consultant Name: Thomas Marine Construction Inc. . ...... . ...... Change Order/Amendment Summary (if additional spaces needed, attached a separate Summary page to this amendment request) CO# AMD# Description COST TI E Justification Additive Deductive Days Added Total New Time To add additional quantities to existing line Items, add a now line Item for the safety of traveling public and time lost due to delays caused by existing utilities in conflict with construction 41,882.00 17 197 To complete the project per plan, to allow the contractor time to construct the project and mitigate the impact of the construction project on the traffic flow and pedestrian traffic. El Check here If additional summary page/s are attached to this Change Order CN Q W E 0 E Page 2 of 4 Change Order Form (2023—ver.1) -- I Packet Pg. 347 Co ley COHtiv ProCUrement Services Change Order Form contract# 23-8079 CO# 1 PO# 4500224353 Project M 60245 Project Name: Treeline Dr & Logan Blvd North of CR846 Intersection Improvements Contractor/Consultant Name: Thomas Marine Construction Inc. Acceptance of this Change Ordorshall constitute a modification to contract I work order Identified above and will be subject to all the same terms and conditions as contained In the contract / work order Indicated above, as fully as If the same were stated in this acceptance, The adjustment, If any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractorl Vendor / Consultant / DesIgn Professional arising out of or related to the change set foHh herein, Including claims for Impact and delay costs. ContractorlConsultantloesign Professional signature below must be from an authorized personlofficerldirector of the Company of listed as the qualified licensed Professional "Project Coordinator" or DesignIEnglneer Professional under the agreement. Signature authority of person signing will be verified through the contract OR through the Florida Department of State, Division of Corporations (Sunbiz) website ht(ps.�Ildos.n?vflorida,coMIsut2 IzIsearchl), If the person signing Is not listed, we will require signature authority by one of the listed officersIdirectors of the company giving that person signature authority, Shannon Bassett Digitally signed by Shannon Bassell Prepared by: Dale: 2024,04,26 11: 18:4 4 -04'00' Date: Signature-Divislon Project Manager Shannon Bassett PMP, Field Inspector 11 Printed Name Accepted by: Date: Slgnallure� Dosign/Engineor Professional (if applicable) N/A Printed Nomefrille/Company Name JD4 . 1'�t kJVAD.Y4t.4 Accepted by: Mark D. Mabee ClWhA b PAU11"a' 1��" Vq� W14 04 20 IV44 24 06W Signature- ContractorlConsultanWondor Mark Mabee, Vice President, Thomas Marine Construction, Inc. Printed Name/Titlel Company Name Approved lby� _ ThomasMatthew Signature-DIvIslon Manager or Designee (Optional) Matthew Thomas, P.E�, Supervisor of Project Management, Tran8portallon Engineering Printed Name Date: 4/26/24 Datc Anthony Khawaja P.E. Digitally signed by Anthony Khawala P. E. Approved by: Date: 2024,04.26 13:a8;07 �04'00' Date: Signature -Division Director or Designee (Opflonal) Anthony Khawala, Chief Englneer-Tfaffle Operations, Transportation Engineering Printed Name V911SKY Signed by dD_1 ScottTrInity 8DIall'all;T21101121141,05 01 Approved by: 10:20:60 -040�' Date: Signature-Divislon Administrator or Designee (Optional) Trinity Scott, Department Head, Transportation Management Services Depeftment Printed Name Page 3 of 4 Change Order Form (2023—Ver.4) i3 It 04 Q to Packet Pg. 348 Co ft, cotinv Procurement Services Change Order Form Contract# 23-8079 CO# 1 P0# 4500224353 ProjecM. 60245 Project Name. Treellne Dr & Logan Blvd North of CR846 Intersection Improvements Contractor/Consultant Name: Thomas Marine Construction Inc, I FOR PROCURMENT USE ONLY I Fy24 CHORequest#1382 ZimmermanBecca Digitally signed by ZimmermanBecca Approved by: Date: 2024.05.20 10:05:26 -04'00' Signature- Procurement Professional Signature/Date Approved by: Sig nature -Procurement ManagerlDi rector (OPTIONAL) A_PPROVA TYPE: El Administrative 0 Administrative-113CC Report E: BCC Stand -Alone ES (BCC Approval Required) ATTEST: Crystal K. Kinzel, Clerk of the Circuit Court and Comptroller By: Dated: (SEAL) IBCC APPROVAL BOARD OF COUNTY COMMISSIONERS COLLIER COUNTY, FLORIDA By: Date: Agenda # Chris Hall, Chairman Approved as to Form and Legality: Deputy County Attorney Print Name Page 4 of 4 Change Order Form (2023—ver.1) 04 Q w Q a) E 0 E 0 C14p)-,4 A (I� Packet Pg. 349 'ILI i3 It 04 Q (D Q a) pl� Packet Pg. 350 w% r"0116 EXTRA WORK SHEET '%-go Thomas Marine construction, Inc, Number: (411H ""Irarjotros look (Issised by) Name: 8999 High Cotton Lane Added Raggers Project: Logan Blvd and Tfeellne Drive Roundabout Cont. No, Fort Myers, FL 33905 Date: 2/2012024 TMC Projt )24 (Address) ITO Cotlier Courax 0 Material or Subcontractor 0 Owner Force Account Work JAddiess) all Extra Work ChKk one C3 Equipment Lease or Vendor Invoice 0 Unforeseen Condition ATTW Shannon Bassett, PMP I Field Inspector 0 Cost Savings initiative Proposal Description of Work: Description: To provide to 2 certified flaggefs at the intefsectlon of Treetiae OrIve and Logan Boulevard, Monday to Friday during the hours of 4pni to 6pm after normal llag,in, will occur until he late of M .. 111, 1114, Ile plelumld end of season, TMC is r"Wred to have a competent employee onsite also during ,worIffi, flagglng operations. Therefore the daily rate includes 1 TMC employee and 2 certified flogger%, Purpose of Work DlrectNe Change*. To mitigate the impact of the construction project on the traffic flow and pedeitrfan traffic during the t1sted Ilmes and hours, Prime Contractor Hours My Rate Detalt of Equipment, Materials and Labor or or Equipment Material Labor Total Quantity Unit price Cost Cost Cost Asnount Pf oJW Maqag�r (Mark Mabee) $ 105.OD $ $ ProfossiGnai Engineer lKevin Shimp) $ 225.00 $ TMC Labor (see attached sheet) 2.00 s 35V8 71.76 $ 71.. $ 71.76 See attached shoot for breakdown 1.00 ;ee attached sheet for breakdown Sub T*tsl Dfrecus k 1 .76 J 71.761. SUBCONTRACTOR 3ee attached Met foe breakdown 238,W Sub Total Subcontractors: zX00 Total Labor - 71.76 X 10100% 7,18 total Materlats - $ X 10.00% Total Equipment - $ X 10.00% Total Subcontract $ 238.00 X 5,00% 1 f.90 Sub Total: Extra Work 5he4t SUB TOTAL: 1 $ 328,84 JTotal Liability FA Bond X 1 Extra Work Sheet OVERAL TOTALi Approved for Owner, Malodat or Sub�Contractor Approved for Company 15-- By By Pogo i of I Packet Pg. C4 CD 0 E a 0 0 0 E E 4- 0 z M 0 0 -J V- Iq CD CD 04 0 W E Subcontractor Cost Description Unit Qty Unit Price Total 2 PERSON CERTIFIED FLAGGING CREW HR 4 59.50 $ 238.00 Total 238.00 i3 It 04 Q (D GAO) Packet Pg. 0 ............... i3 It 04 Q (D Q a) pl� Packet Pg. �53 w Co 0 E a 0 0 0 Q (D 0 0 0 r,� o 0 0 o C�C)Ooo d66-6 C; C; C; C; 10 V op 0 Ln N 9 Nr Ln UL to to 0 090 00 to U') 00 00 r-- V) I N 0 0 0 CD 8 tn LO to (f) r- >4 1, (/) 0 N , oi t6 4 IN C14 r:: Lo q E = - 0 0 0: V) 0 06 E C 0 b (D 4) IV 21) s W 10 is -5 (n 0 (0 i3 It 04 Q to E 0 C 0'� A Packet Pg. 354 to- 001"as so Sri 0 tz-,C00strucAlo" i3 ("MIStrisn'tol'os '811wo 19W February 20, 2024 Shannon Bassett Field Inspector 11 Collier County - Transportation Engineering 2885 South Horseshoe Drive Naples, FL 34104 Stiannon,Bassett@colliercountyE._qov RE: Added Flagging Operation Verbal Quote County: Collier Project Description: Logan Blvd and Treeline Drive Roundabout SENT Via: Email TMC was contacted on 2119/24 to provide additional flagging operations from 4pm to 6prn starting 2120/24 and to occur Monday through Friday each week until Easter weekend. TMC contacted several companies on Monday 2/19/24 and was only able to get one company to commit to providing flaggers on such short notice as TMC didn't have the resources to provide requested service. Below is the verbal quote from Labor Finders to provide 2 certified flaggers for a minimum of 4 hrs per day. LABOR FINDERS VERBAL QUOTE FROM MICHAEL ON 2/19/24 1) Certified Flaggers 4 HR MIN (2 ea.) - $55 1 HR X 4 HIRS MIN = $220.00 2) Transportation FEE - $18/day X I DAY = $18.00 MIN DAILY RATE FOR 2EA CERTIFIED FLAGGERS - $2W00 Cc: Job File 8999 111gh Cottoll Lane, Fort Myers, Norida.33905 / Voice; Z39-337-00013 / Faxi 239-337-0099 Packet Pg. 355 VAMN quOl-Itfon ?40� P-113-42 I'(6pued f1m Cuslomof Nol Allontion: Title: Addross: P1101101far w NIAUL. 19, Mall Conon tano rilly0ts, Ft 3YM R )137.0001 V-111d Ui II: MAY 2 3, 2024 By; Otto; Quoted 6: TWO! fmallt F . asitio . n 0111 Rate i &nerM Labot Flagging Clean Up Etc, 1`1386�fift 1 527.75 13W Finilefs w0les wnploywt wrultmont i�n,l (MidlOnt Labor FhIffetj PMACtwo flik ffianaptn(it 1hu, (111010 000 Dal 11101f(lt other eiponse$ jtjCIt 3 by 11"t%Q11 Of JnY 00-t-140t (01144ct, any stxh pi TIIJ"% 01i IN the 4PPortunity to plovido this quoi 40"40 $ ;Ve Welcome 11-10 OPPO(tu 1V to woik wO v sign and folorn D4 41S- 0 1r':-UA-R VS D - 7-- IR,-Ie S QUOTATION 1,1 Stalfulv'spr%ices, 111C. Mlpl�-s M(chaelA,poief Assistant hionngef 330 payshora njiyo Na 0 les, F L 34 111 1135) 7934500 1 (239) 7,)j. � Jo5 n a plg %vols,urt zor"pQ')Wtsjjn imuranW, R4110ral hJW1 Y llt"'Artto, Of"WOVA10M WAus 3nd wAI'110111018. 3(fFn'rn%t1oVon al M pspot Not mokes safety Qj cnif 0$qR4 1�ly One. WAOnd, employniqnj physic31%, �tC, Should JAY 111cle ltvlm be requIrcd theiq vxpqjjsos wtsl bo alfdod ja�;qijf ltvulm H�glu 16 w IM04 wap law, mmoct tiOltivr's (000( (111(lVding �inv overtime vlork), it L.)bp( Rndon S031 IS to pta�jd 0 Youf COAWA � th lilt W $t P00610 SOMWIC0 OAd 10 IWIP imProve y6or produo(vily Ehiough il toonpanyanit look lcumod to pot uluil 111j, W vil' u 10 be Vaut business pot wei. Ohm pt OR, corn'W u$ 41019) 19M500 If Wo him any citiostions. 4-1 0 SIONATURG 111 & TITLE rk blaboo Supar -1 � -q-4- DATE I eA C'6/ I . 14114818 A -% d, * �7 *'% A D.) ZA -m4w )� A egivin Siahln?, A in ".6111 11 1zWDA1 THANK YOU ron c 43 OUR 5ERVICES1 ror 010to lnfarm�ltan about ou tuld skrylm ploaso villt ut A �Ad 04 C) (D T— Iq C) a) E 0 I (",1()) 11 Packet Pg. 356