Backup Documents 03/12/2024 Item #11C PresentationPrepared By:
Claudia Roncoroni, Project Manager
Facilities Management Division
March 12, 2024
Agenda Item 11.C
Recommendation to accept a project update on the Collier County
Behavioral Health Center and proceed with the design for 87 total beds (45
CSU, 30 CSU Medicare/Acute and 12 ESAC) with an estimated construction
cost of $49.9 million.
Infrastructure Surtax Fund (318), Project #50239
(District 3)
1Facilities Management Division
2Facilities Management Division
Healthcare Consultant
Maurizio Maso, AIA
Hernan Rivera, AIA
Alex Jordan, AIA
Scott Burgess, CEO
Nancy Dauphinais, COO
Mary Ann Guerra, CCO
Andy Stevens, Director of
Facilities & Safety Officer
Prime Consultant
Ryan S. Richards, AIA,
LEED AP
Javier Salazar, AIA
Construction Manager
Reggie Morgan,
COO, Principal
Eric Brackin, CHC
Project Executive
John Hagan,
Chief Estimator Healthcare
John McCormick, PE
Director Facilities Management
Claudia Roncoroni,
Project Manager
3Facilities Management Division
•We are here to provide a project update to the Board and to recommend moving forward with the value-
engineered design providing 87 total beds (45 CSU, 30 CSU Medicare/Acute and 12 ESAC) with an estimated
construction cost of $49.9 million.
•On June 27, 2023, County staff presented a project update and the Board provided direction to move forward
with a design meeting current and future community needs: 87 beds, 60,000 SF with an estimated
construction cost of $43.9 million based on the Schematic Design.
•In December 2023, the Design Development package (60% design) was received. This stage of design more
specifically develops the elements of the project; site design, building structure, main building systems,
architectural elements and finishes, allowing more complete and specific cost estimates to be developed.
•The December cost estimate developed by the Construction Manager (CM) was $53.1 million.
•Following a substantial value engineering effort the estimate was reduced by $3.2 million to a construction
cost estimate of $49.9 million.
4Facilities Management Division
5Facilities Management Division
TARGET YES NO
•Is 6/27/23 Project Update
Budget met?√
•Is 6/27/23 Project Update
Program met?√
•Is Value Engineering
included?√
•Are Current Community
needs met?√
•Are Future Community
needs met?√
•Design: Change Order for
Time & Money?√
6Facilities Management Division
6/27/23 Project Update
Schematic Design
WITH Value Engineering
3/12/24 Project Update
Design Development
WITH Value Engineering
45 adult CSU 45 adult CSU
15 Acute 15 Acute
15 Medicare Inpatient 15 Medicare Inpatient
12 ESAC 12 ESAC
60,000 SF 60,000 SF
$732/SF $832/SF
87 beds 87 beds
$43.9M $49.9M
CSU = Adult Crisis Stabilization Unit
ESAC= Emergency Services Assessment Center
Includes $3.2M VE Cost Savings
Main Value Engineering Items
•Tiltwall in lieu of CMU
•Door/Frame/ Hardware substitutions
•Changes to interior wall types
•Low Voltage - Nurse Call reduction
•Alternate Kitchen equipment package
•Alternate light fixture package
•Medical Air elimination
•Architectural decorative elements removal
•Loading dock and main entry canopy coverage
reduction
•Chain link fence at Generator in lieu of cast in
place wall
7Facilities Management Division
March 15, 2022
NTP was issued to
RG Architects
November 09, 2021
CMAR Solicitation
Ranking was
approved by
the Board
March 14, 2023
CMAR
Preconstruction
Services Contract
was approved by
the Board
June 27, 2023
BCC Approved 87
Beds and a $43.9
million estimated
construction cost
Q4 2024 – Tentative:
GMP approval
including Site &
Building
March 12, 2024
Project update: proceed
with design for 87 beds
with a revised estimated
construction cost of $49.9M
March 14,2024
Surtax Committee
Update
8Facilities Management Division
Recommendation to accept a project update on the Collier County
Behavioral Health Center and proceed with the design for 87 total beds (45
CSU, 30 CSU Medicare/Acute and 12 ESAC) with an estimated construction
cost of $49.9 million.
9Facilities Management Division
10Facilities Management Division
•The Collier County Behavioral Health Center is an important Community Priority Project endorsed by the
voters in 2018 and identified as the number one priority of the Collier County Mental Health and
Addiction Ad Hoc Advisory Committee (now under the auspices of the Collier Coalition of Healthy Minds).
This project is funded by Infrastructure Sale Surtax Funding.
•This project’s name, originally Collier County Mental Health Facility and often labeled by the Public or by
the Media as Mental Health Facility, Central Receiving Facility or David Lawrence Centers Expansion, has
been formally changed to Collier County Behavioral Health Center.
•The Facility will function as the Central Receiving Facility for those receiving services under both the
Baker and the Marchman Acts and will greatly increase mental health crisis support in Collier County.
•The proposed new Facility will serve the mental health needs of Collier County's expanding population
and will reduce demands currently placed on the Collier County Sheriff’s Office.
11Facilities Management Division
Project Programming and Master Planning Factors – Behavioral Health Center (Adult Beds):
•The average number of adults under the Marchman Act at Collier County Sheriff’s Office jail
facility is 10 beds per month.
•The average number of adults within the existing David Lawrence Centers (DLC) facility is
approximately 29 beds per day.
•The peak number of occupied beds experienced by DLC is 42 beds per day. There has been an
increase of two beds since the June 27, 2023, project update.
•The existing programmatic need for beds based on today’s demand is between 39 and 52
inpatient beds per day.
• 12 Emergency Services Assessment Center (ESAC) beds are required.
•Recent University of South Florida Baker Act reporting indicates that approximately 439
Collier residents per year travel outside of Collier County for Baker Act services due to lack of
capacity within Collier County.
12Facilities Management Division
13Facilities Management Division
MAIN ITEMS
DESCRIPTION
SCHEMATIC
DESIGN
VALUE
DESIGN
DEVELOPMENT
VALUE
VARIANCE PERCENTAGE
•ELECTRICAL $3,983,000 $6,037,000 $2.05M 51%
•INDIRECT COST $5,715,000 $6,774,000 $1.06M 19%
•LOW VOLTAGE $785,000 $1,808,000 $1.02M 130%
•FINISHES $1,566,000 $2,435,000 $869K 55%
•ESCALATION $1,658,000 2,453,000 $796K 48%
•DRYWALL / FRAMING / STUCCO $3,226,000 $4,012,000 $786K 24%
•HVAC $3,400,000 $3,991,000 $591K 17%
•CONCRETE $1,506,000 $2,031,000 $525K 34%
•SITE WORK $1,875,000 $2,339,000 $464K 24%
•SAFETY & SECURITY SYSTEMS $425,000 $819,000 $394K 92%
•FLOORING $598,000 $959,000 $361K 60%
•DOORS / FRAMES / HARDWARE $1,660,000 $1,981,000 $321K 19%
•OWNER CONTINGENCY $1,098,000 $1,328,000 $230K 20%
•CANOPIES $274,000 $494,000 $220K 80%
•KITCHEN EQUIPMENT $595,000 $728,000 $133K 22%
•FIRE PROTECTION $255.000 $320,000 $65K 25%
•SAFETY PADDING $174,000 $219,000 $45K 25%
14Facilities Management Division
Program
reduction:
15 beds.
1 Medicare
Pod is
shelled
50%
Reduction
in Medicare
Services
TARGET YES NO
•Is 6/27/23 Project Update
Budget met?√
•Is 6/27/23 Project Update
Program met?√
•Is Value Engineering
included?√
•Are Current Community
needs met?√
•Are Future Community
needs met?√ *√ *
•Design: Change Order for
Time & Money?√
* This condition is partially met – Option2
provides only 8 inpatient beds more
than today’s demand.
Future needs will be fully met only when
Tenant Built Out, adding 15 more inpatient
beds, is implemented.
15Facilities Management Division
Program reduction: 30 beds.
2 CSU Pods are shelled.
TARGET YES NO
•Is 6/27/23 Project Update
Budget met?√
•Is 6/27/23 Project Update
Program met?√
•Is Value Engineering
included?√
•Are Current Community
needs met?√*√*
•Are Future Community
needs met?√** √**
•Design: Change Order for
Time & Money?√
•* Current inpatient beds demands fluctuates
between 39 and 52; peak demand is
not met.
** Future needs will be fully met only when
Tenant Built Out, adding 30 inpatient beds,
is implemented.
16Facilities Management Division
Permanent Program reduction:
30 beds.
2 CSU Pods are not built.
TARGET YES NO
•Is 6/27/23 Project Update
Budget met?√
•Is 6/27/23 Project Update
Program met?√
•Is Value Engineering
included?√
•Are Current Community
needs met?√*√*
•Are Future Community
needs met?√
•Design: Change Order for
Time & Money?√
•*Current inpatient beds demands fluctuates
between 39 and 52; peak demand is
not met.
6/27/2023
Project Update
•Value Engineering
Schematic Design
Estimate
3/12/2024 BCC
Option 1
•No Changes to Program
•Changes to Budget
•Value Engineering
Design Development
(Recommended)
3/12/2024 BCC
Option 2
•Changes to Program
•Changes to Budget
•Value Engineering
•1 Pod: Shelled
Design Development
3/12/2024 BCC
Option 3
•Changes to Program
•Changes to Budget
•Value Engineering
•2 Pods: Shelled
Design Development
3/12/2024 BCC
Option 4
•Changes to Program
•No Changes to Budget
•Value Engineering
•2 Pods: Eliminated
Design Development
45 adult CSU 45 adult CSU 45 adult CSU 15 adult CSU 15 adult CSU
15 Acute Medicare 15 Acute Medicare 15 Acute Medicare 15 Acute Medicare 15 Acute Medicare
15 Medicare Inpatient 15 Medicare
Inpatient
0 Medicare
Inpatient
15 Medicare
Inpatient
15 Medicare
Inpatient
12 ESAC 12 ESAC 12 ESAC 12 ESAC 12 ESAC
60,000 SF 60,000 SF 60,000 SF 60,000 SF 47,574 SF
$732/SF $832/SF $785/SF $746/SF $911/SF
87 Beds 87 Beds 72 Beds 57 Beds 57 Beds
$43.9M $49.9M $47.1M $44.8M $43.3M
$6.0M
Funding Gap
$3.2M
Funding Gap
$850K
Funding Gap
($600K)
Funding Gap
CSU = Adult Crisis Stabilization Unit
ESAC= Emergency Services Assessment Center
17Facilities Management Division
18Facilities Management Division
6/27/23 Project Update
Schematic Design (30%)
WITH Value Engineering
3/12/24 Project Update
Design Development
WITHOUT Value Evaluation
3/12/24 Project Update
Design Development
WITH Value Engineering
45 adult CSU 45 adult CSU 45 adult CSU
15 Acute 15 Acute 15 Acute
15 Medicare Inpatient 15 Medicare Inpatient 15 Medicare Inpatient
12 ESAC 12 ESAC 12 ESAC
60,000 SF 60,000 SF 60,000 SF
$732/SF $885/SF $832/SF
87 beds 87 beds 87 beds
$43.9M $53.1M $49.9M
CSU = Adult Crisis Stabilization Unit
ESAC= Emergency Services Assessment Center
$3.2M VE Cost Savings
Main Value Engineering Items
•Tiltwall in lieu of CMU
•Door/Frame/ Hardware substitutions
•Changes to interior wall types
•Low Voltage - Nurse Call reduction
•Alternate Kitchen equipment package
•Alternate light fixture package
•Medical Air elimination
•Architectural decorative elements
removal
•Loading dock and main entry canopy
coverage reduction
•Chain link fence at Generator in lieu of
cast in place wall
The Collier County Mental Health Facility is a Community Priority project funded by Infrastructure
Surtax. In accordance with Exhibit A of Ordinance 2018-21 the project had a program budget
of $25M, increased to $43.9M last year.
The project is currently at the end of the Design Development Phase. Four design/construction
options have been identified as provided in the table on slide 15. Estimated construction budgets
for the four options range from $49.9M to $43.3M – the $43.3M option permanently eliminates
part of the 6/27/2023 project update program, and does not meet current adult beds peak
demand nor future community beds need.
19Facilities Management Division
20Facilities Management Division
The project construction cost estimates discussed in the previous slide do not provide for:
•Estimated $4.4M requirement for furniture, fixtures, and equipment nor estimated net annual
operating costs of $4M (after considering program revenue and grant sources).
•As presented at the 06/27/23 meeting, staff in coordination with David Lawrence Center
leadership met with key community stakeholders to address these unfunded aspects of the
program.
•DLC has launched a naming rights initiative that will provide for additional funding.
21Facilities Management Division
•Because of the timing of achieving the $490M combined County/Municipality aggregate Surtax
collection threshold collections continued through December 31, 2023.
•A portion of additional Surtax collections can be made available for the Mental Health Facility.
•County Staff will go before Surtax Committee seeking additional Funds.
22Facilities Management Division
23Facilities Management Division
6/27/23 Project Update
Schematic Design
WITH Value Engineering
3/12/24 Project Update
Design Development
WITHOUT Value Evaluation
3/12/24 Project Update
Design Development
WITH Value Engineering
45 adult CSU 45 adult CSU 45 adult CSU
15 Acute 15 Acute 15 Acute
15 Medicare Inpatient 15 Medicare Inpatient 15 Medicare Inpatient
12 ESAC 12 ESAC 12 ESAC
60,000 SF 60,000 SF 60,000 SF
$732/SF $885/SF $832/SF
87 beds 87 beds 87 beds
$43,927,875 $53,100,357 $49,927,295
CSU = Adult Crisis Stabilization Unit
ESAC= Emergency Services Assessment Center
$3,173, 062 VE
Cost Savings
Main Value Engineering Items
•Tiltwall in lieu of CMU
•Door/Frame/ Hardware substitutions
•Changes to interior wall types
•Low Voltage - Nurse Call reduction
•Alternate Kitchen equipment package
•Alternate light fixture package
•Medical Air elimination
•Elimination of Architectural decorative
elements
•Reduction of loading dock canopy
•Chain link fence at Generator in lieu of
cast in place wall
24Facilities Management Division
6/27/2023
Project Update
•Value Engineering
Schematic Design
Estimate
3/12/2024 BCC
Option 1
•No Changes to Program
•Changes to Budget
•Value Engineering
Design Development
Estimate
(Recommended)
3/12/2024 BCC
Option 2
•Changes to Program
•Changes to Budget
•Value Engineering
•1 Pod: Shelled
Design Development
Estimate
3/12/2024 BCC
Option 3
•Changes to Program
•Changes to Budget
•Value Engineering
•2 Pods: Shelled
Design Development
Estimate
3/12/2024 BCC
Option 4
•Changes to Program
•No Changes to Budget
•Value Engineering
•2 Pods: Eliminated
Design Development
Estimate
45 adult CSU 45 adult CSU 45 adult CSU 15 adult CSU 15 adult CSU
15 Acute Medicare 15 Acute Medicare 15 Acute Medicare 15 Acute Medicare 15 Acute Medicare
15 Medicare Inpatient 15 Medicare
Inpatient
0 Medicare
Inpatient
15 Medicare
Inpatient
15 Medicare
Inpatient
12 ESAC 12 ESAC 12 ESAC 12 ESAC 12 ESAC
60,000 SF 60,000 SF 60,000 SF 60,000 SF 47,574 SF
$732/SF $832/SF $785/SF $746/SF $911/SF
87 Beds 87 Beds 72 Beds 57 Beds 57 Beds
$43,927,875 $49,927,295 $47,107,035 $44,777,823 $43,328,383
$5,999,420
Funding Gap
$3,179,160
Funding Gap
$849,948
Funding Gap
($599,492)
Funding Gap
CSU = Adult Crisis Stabilization Unit
ESAC= Emergency Services Assessment Center