Backup Documents 02/06/2024 Item # 2B 1 (Current Strategic Program Budget Alignment)Strategic Plan
COLLIER COUNTY
STRATEGIC PLAN
PRIORITY PROJECTS
February 6, 2024
Workshop
Updated 2.5.2024
Strategic Plan
Annual
Strategic
Review
Strategic Plan
PRIORITY PROJECT INDEX
AFFORDABLE & WORKFORCE HOUSING SLIDE #
AFFORDABLE HOUSING 5
WORKFORCE HOUSING LAND TRUST FUND 6
HURRICANE AND MULTI-HAZARD PREPAREDNESS SLIDE#
HURRICANE AND MULTI-HAZARD PREPAREDNESS 8
HURRICANE IAN PERMANENT REPAIRS 9
DUNE RESTORATION PLANTING 10
PARKS, RECREATION, MARINAS & BEACHES SLIDE #
AQUATICS CAPITAL PROGRAM (NEW PRIORITY)12
IMMOKALEE SPORTS COMPLEX (NEW PRIORITY)13
BEACH PARKING ADDITIONS 14
BEACH RENOURISHMENT 2024 (UPDATED)15
BIG CORKSCREW ISLAND REGIONAL PARK - PHASE 2A & 2B 16
BOAT RAMP ADDITIONS 17
CAXAMBAS SEAWALL REPLACEMENT (NEW PRIORITY)18
CAXAMBAS NEW FUEL SYSTEM (NEW PRIORITY)19
EMERGENCY BERM TRUCK HAUL & CONSTRUCTION REACHES A & B 20
GOLDEN GATE 9-12 HOLE GOLF COURSE 21
PLANNING & COUNTY OPERATIONS SLIDE #
CYBERSECURITY INITIATIVES 23
DAS ANIMAL SERVICES RENOVATION (SURTAX) 24
HR RECRUITMENT & RETENTION 25
STRATEGIC REAL ESTATE ACQUISITIONS 26
STRATEGIC PLAN BUDGET INTEGRATION 27
HUSSEY PROPERTY SITE PREP - MASTER PLANNING (NEW PRIORITY)28
CAMP KEAIS/ROCK SRINGS MASTER PLANNING/ENVIRONMENTAL TESTING (NEW PRIORITY)29
PUBLIC HEALTH & SAFETY SLIDE #
CCSO FORENSICS BUILDING (SURTAX)31
COLLIER COUNTY MENTAL HEALTH FACILITY (SURTAX)32
STATE VETERANS’ NURSING HOME (SURTAX)33
EMS STATION 74 (SURTAX) (NEW PRIORITY)34
800 MHz RADIO HARDENING -PROJECT ANALYSIS FOR FULL UPGRADE (UPDATED)35
800 MHz RADIO HARDENING - CARNESTOWN RADIO SITE 36
TRANSPORTATION SLIDE #
VANDERBILT BEACH ROAD EXTENSION 38
VANDERBILT BEACH ROAD EXTENSION - PHASE III (NEW PRIORITY)39
PINE RIDGE ROAD IMPROVEMENTS 40
ROADWAY RESURFACING PROGRAM 2024 41
UNDERGROUND STROMWATER CLEAN, VIEW & REPAIR PROGRAM 2024 (NEW PRIORITY)42
ROADSIDE SWALE PROGRAM 2024 43
TIGER GRANT - IMMOKALEE IMPROVEMENTS (NEW PRIORITY)44
GOODLETTE-FRANK ROAD WIDENING (NEW PRIORITY)45
COLLIER BOULEVARD WIDENING PHASE III (NEW PRIORITY)46
GOLDEN GATE CITY WATER RESOURCE PROTECTION/RESTORATION MASTER PLAN 47
IMMOKALEE ROAD I-75 INTERCHANGE IMPROVEMENTS (NEW PRIORITY)48
WATER RESOURCES SLIDE #
GOLDEN GATE CITY INFRASTRUCTURE & ECONOMIC DEVELOPMENT MASTER PLAN 50
GOLDEN GATE CITY TRANSMISSION WATER MAIN IMPROVEMENTS 51
NE REGIONAL UTILITY PROGRAM - PHASE I 52
NE REGIONAL UTILITY PROGRAM - PHASE II 53
NE REGIONAL UTILITY PROGRAM - TANKS, PUMP STATIONS 54
NE REGIONAL UTILITY PROGRAM - NE UTILITY FACILITIES 55
NORTH COLLIER WATER RECLAMATION FACILITY 56
SEPTIC TO SEWER CONVERSION - PALM RIVER AREA 4 RENEWAL PROGRAM 57
UTILITY MASTER PLANNING - MASTER PLAN LIBRARY 58
STORMWATER/UTILITY PARNERSHIP PROJECTS SLIDE #
STORMWATER UTILITY PARTNERSHIP - PALM RIVER AREAS 1 & 2 RENEWAL PROGRAM 60
STORMWATER UTILITY PARTNERSHIP - NAPLES PARK - 98TH & 99TH AVENUES RENEWAL PROGRAM 61
STORMWATER UTILITY PARTNERSHIP - NAPLES PARK - 105TH & 106TH AVENUES RENEWAL
PROGRAM 62
STORMWATER UTILITY PARTNERSHIP - OLD LELY - PHASES 7, 8, & 9 RENEWAL PROGRAM 63
WEST GOODLETTE-FRANK JOINT STORMWATER - SEWER PHASE 2 64
ASSET MANAGEMENT PLANS SLIDE #
PUBLIC UTILITIES 66
TRANSPORTATION MANAGEMENT 67
FACILITIES MANAGEMENT 68
PUBLIC SERVICES 69
Strategic Plan
PROJECT NAME DEPARTMENT/DIVISION SLIDE #
AFFORDABLE HOUSING ECONOMIC DEVELOPMENT 5
WORKFORCE HOUSING LAND TRUST FUND REAL PROPERTY / ECONOMIC DEVELOPMENT & HOUSING 6
AFFORDABLE & WORKFORCE HOUSING
Strategic Plan
AFFORDABLE HOUSING POLICY
Next Steps/Current Challenges 01/09/24
•Overcoming NIMBY issues related to traffic, density, and “low-income” households.
•Codification and standardization of Board policies.
•Integrate “Live Local Act” incentives with County GMP/LDC.
Progress:
•In calendar year 2023 a total of 1,208 new affordable housing units were approved by the Board of County
Commissioners.
•The Housing Policy & Economic Development Division continues to form Public/ Private partnerships with the
development community to enact the Board’s policy to increase the supply of housing that is affordable.
•All these units carry an affordability restriction of at least 30-years, promoting the long-term affordability of Collier’s
housing stock.
•Since FY2018 these actions have resulted in the approval of over 4,000 new affordable housing units.
•The vast majority of these units have been created at no cost to the taxpayers of Collier County by using land use policies
as incentives.
District #All Districts
Project #TBD
Project Manager Cormac Giblin, Director, Economic Development &
Housing
Project Sponsor Housing Policy & Economic Development
Scope:
•Purchase land that can be reserved for housing that is affordable
through extended County ownership. (Done through Land Trust)
•Acquire land for housing that is affordable (Done through Land Trust)
•Long term affordability of Collier’s housing stock
•Promote economic development by increasing affordable housing
options for the area's workforce
Total Budget TBD
5
Strategic Plan
WORKFORCE HOUSING LAND TRUST FUND
Next Steps/Current Challenges Updated: 01/11/2024
•Staff is currently accepting and reviewing applications for properties for acquisition.
•Two application requests totaling $5,734,500 are scheduled to be brought to the Board of County
Commissioners for review/approval in early 2024.
•End of dedicated funding source with expiration of Workforce Housing Land Acquisition Surtax Funding on
December 31,2023
Progress First acquisition validated by the Surtax Infrastructure Committee on January 11, 2024.
•On March 28, 2023, Agenda Item 11.F., the Board of County Commissioners adopted a policy for the use of the Workforce
Housing Land Acquisition portion of the voter-approved Local Government Infrastructure One-Cent Sales Surtax.
•The Policy evaluation criteria includes Management Summary, Property and Business Plan, Financing & Cost of Services to
the County, Experience and Capacity of the Firm, Specialized Expertise of Team Members, Certified Minority Business
Enterprise, and Local Vendor Preference.
•On January 9, 2024, Agenda Item 16.A.16., the Board adopted AHAC recommended enhancements to the application and
review policy to streamline the process.
•5 Workforce Housing Land Acquisition applications have been received thus far exceed the total available funding.
.
Stage % Complete
Procurement 0%
Design 0%
Construction 0%
Closeout 0%
District #3 3
Project #50267
Project Manager Cormac Giblin, Director Economic Development &
Housing
Project Sponsor Real Property
GMCD – Housing Policy & Economic Development
Division
Scope:
•Purchase land that can be reserved for housing that is affordable
through extended County ownership.
•Acquire land for housing that is affordable
•Long term affordability of Collier’s housing stock
•Promote economic development by increasing affordable housing
options for the area's workforce
Design Budget N/A
Const Budget N/A
Total Budget $20,000,000.00
Arch/Eng:N/A
General Cont N/A
Owner Rep (CEI)N/A
NTP Design N/A
NTP Const N/A
Sub Completion N/A
Final Completion N/A
6
Strategic Plan
PROJECT NAME DEPARTMENT/DIVISION SLIDE #
HURRICANE AND MULTI-HAZARD PREPAREDNESS EMERGENCY SERVICES 8
HURRICANE IAN PERMANENT REPAIRS FACILITIES MANAGEMENT 9
DUNE RESTORATION PLANTING TRANSPORTATION MANAGEMENT 10
HURRICANE AND MULTI-HAZARD
PREPAREDNESS
Strategic Plan
HURRICANE & MULTI-HAZARD
PREPAREDNESS
Next Steps/Current Challenges Updated 1.22.2024
•Continue public education and awareness opportunities.
•Promote Alert Collier for emergency notifications
•Leverage funding to expand evacuation shelter resources
•Expand supporting contracts for disaster logistical support, shelter support, exercises, and recovery planning.
•Leverage social media opportunities for disaster preparedness education.
•Expand the scope, services, and resources of volunteer agencies in mid and long-term recovery.
•Continue planning efforts to respond to fast-breaking mass casualty or mass violence situations.
•Support continuity planning for cyberterrorism concerns.
•Replacement of EOC video wall and peripheral equipment.
Progress
•Support the formation of the local Volunteer Agencies in Disaster Recovery initiative.
•Continue efforts to support local and regional multi-hazard incident management training.
•Refinements to incident management software applications.
•Subscribe to the FROC initiative to improve FEMA/State reimbursement processes.
Stage % Complete
Procurement-EOC Video Wall 0%
Design 100%
Construction 0%
Closeout 0%
District #ALL
Project/Cost Center #144210
Project Manager Dan Summers, Director
Project Sponsor Bureau of Emergency Services- Emergency
Management
Scope: Continuation of Collier County’s commitment to a disaster-resilient
community by addressing natural, technological, and man-made
hazards. Continue to find opportunities for breaking the damage repair cycle
caused by Tropical Storms and assisting individuals, families and businesses
with disaster readiness strategies in an all-hazards environment
Design Budget Within Existing Operating
Total Budget TBD
Final Completion On-going efforts with periodic review.
8
Strategic Plan
DUNE RESTORATION PLANTING
Next Steps/Current Challenges Updated 2.2.2024
•Bid package assembled and ready for solicitation for construction Feb. 2024.
•Award of contract will begin a 3 to 4 month growing period, followed by plantings in May / June ‘24.
Progress
•Held multiple stakeholder meetings with a good turnout and consensus for planting strategy.
•Bid package complete and routed to Fiscal and Grants for approval to send to Procurement.
Stage % Complete
Procurement 95%
Design 100%
Construction 0%
Closeout 0%
District #1, 2 & 4
Project #50280
Project Manager Andy Miller, Manager Coastal Management Program
Project Sponsor Transportation Management Services
Scope: Planting of newly constructed berm / dune along Gulf facing County
beaches due to the destruction of the dunes and vegetation by Hurricane Ian.
Design Budget $89,787
Const Budget $2,000,000
Total Budget $2,100,000
Engineer Taylor Engineering, Inc.
General Contractor TBD
Owner Rep (CEI)In-house
NTP Design June 15, 2023
NTP Const *Growing March 1, 2024; Planting May 30, 2024
Sub Completion *July 30, 2024
Final Completion *September 1, 2024 (* Estimated)
(*Estimated date contingent on construction
solicitation and negotiations)
9
Strategic Plan
Name of damage/facility Status Approx. Cost
Marco CCSO Building Design $ 4,137,000
Barefoot Beach Preserve Design $ 4,000,000
Clam Pass Park Design $ 3,000,000
Caxambas Park & Marina Construction $ 3,000,000
Marco Tax Collector Design $ 2,230,000
Vanderbilt Beach Permitting $ 2,000,000
Small Damage Repair Projects Ongoing $ 2,000,000
Naples Depot Museum Bidding $ 1,250,000
CCSO Special Operations Closeout $ 750,000
HURRICANE IAN PERMANENT REPAIRS
Next Steps/Current Challenges Updated: 1/19/2024
•Continuing design work for all major projects
•100% bid docs will be ready on a rolling basis over the next 4 months and each project will be put out to bid
•Developing all small repair locations scope development for a consolidated solicitation in preparation – 3/15/2024
•As individual estimates for projects are developed, budget increases via budget amendments by OMB will be coordinated
•Construction contracting for small projects over 50k is challenged by being unable to utilize contract 19-7525, Annual
Agreement for General Contractors
Progress
•Secured design teams for all major project locations
•Post-storm emergency assessment and repair reopened all public facilities but 4 within 90 days
Stage % Complete
Procurement 50%
Design 50%
Construction 15%
Closeout 0%
District #All
Project #50280
Project Manager Tony Barone, PMP
Project Sponsor Office of Management and Budget
Scope:
The assessment and repair of all damages to facilities from Hurricane Ian.
Includes coordination with Rick/Insurance and FEMA to seek maximum
reimbursement of costs and post-project closeout with agencies.
Design Budget $2,500,000
Const Budget $20,000,000 EST
Total Budget $11,274,011.38 available
Arch/Eng:Harvard Jolly Architects, PK Studios, RG
Architects, Studio+, Taylor Engineering
General Cont TBD – Varies by project
Owner Rep (CEI)WSP, Jacobs Engineering
NTP Design Varies by project
NTP Const Varies by project
Sub Completion Q4 2026
Final Completion Q4 2026
10
Strategic Plan
PARKS & MARINAS & BEACHES
PROJECT NAME DEPARTMENT/DIVISION SLIDE #
AQUATICS CAPITAL PROGRAM (NEW PRIORITY)FACILITIES MANAGEMENT CIP 12
IMMOKALEE SPORTS COMPLEX (NEW PRIORITY)FACILITIES MANAGEMENT CIP 13
BEACH PARKING ADDITIONS PARKS & RECREATION 14
BEACH RENOURISHMENT 2024 TRANSPORTATION MANAGEMENT 15
BIG CORKSCREW ISLAND REGIONAL PARK - PHASE 2A & 2B FACILITIES MANAGEMENT CIP 16
BOAT RAMP ADDITIONS PARKS & RECREATION 17
CAXAMBAS SEAWALL REPLACEMENT (NEW PRIORITY)FACILITIES MANAGEMENT CIP 18
CAXAMBAS NEW FUEL SYSTEM (NEW PRIORITY)FACILITIES MANAGEMENT CIP 19
EMERGENCY BERM TRUCK HAUL & CONSTRUCTION REACHES A & B TRANSPORTATION MANAGEMENT 20
GOLDEN GATE 9-12 HOLE GOLF COURSE FACILITIES MANAGEMENT CIP 21
Strategic Plan
AQUATICS CAPITAL PROGRAM (NEW PRIORITY)
Next Steps/Current Challenges Updated: 1/23/2024
District #2, 3 and 5
Project #80421, 80384, 80275, 80406 and 80429
Project Manager Dayne Atkinson, Project Manager
Project Sponsor Parks and Recreation
Scope:
To restore the operational status of Sun-N-Fun, Golden Gate, and Immokalee
aquatics facilities.
Design Budget $370,000 Est
Const Budget $9,320,000 Est
Total Budget $9,690,000 Est
Arch/Eng:Various
General Cont Various
Project Stage Final Completion
SNF – Lazy River Main Drains Design Procurement Q2 2025
SNF – Ventilation Of Pumphouse #1 Design Procurement Q2 2025
SNF – Interactive Water Feature Basin Design Procurement Q3 2025
SNF – Slide Pool Basin Construction Procurement May 2024
SNF – Slide Tower And Stairs Design Procurement Q4 2025
SNF – Geothermal System Repair Construction Procurement May 2024
SNF – Pump Repair And Replacement Construction Procurement Dec 2024
GG – Aquatics Facilities Renovation Design Procurement Q4 2026
GG – Geothermal System Repair Construction Procurement Jun 2024
GG – Aquatics Men’s Locker Room Renovation Design Procurement Q2 2025
ISC – New Pool Design Procurement Q2 2027 12
Strategic Plan
IMMOKALEE SPORTS COMPLEX (NEW PRIORITY)
Next Steps/Current Challenges Updated: 1/23/2024
•Proposal from Stantec for redesign – 1/19/24
•WO submitted to Procurement – 1/29/24
•NTP issued to Stantec – 2/19/24
Progress
•Met with Stantec on 12/6 to discuss stormwater for site that may affect pool construction
•Direct select submitted to Procurement – 11/9/23
•Submit Project approval form – 11/7/23
•Met with Stantec and WTI – 11/1/23
•GMD confirmed that only a SDPI is required if pool stays within the existing footprint – 10/30/23
Stage % Complete
Procurement A: 20%; S: 20%
Design A: 0%; S 0%
Construction A: 0%; S 0%
Closeout A: 0%; S 0%
District #5
Project #80429
Project Manager Dayne Atkinson
Project Sponsor Parks and Recreation
Scope:
Aquatics: Construction of a new pool, renovation of the pump house,
replacement of the concrete deck, installation of a new slide, consolidating
the lap pool with the kiddie pool and installation of shade structures.
Stormwater: Upgrading the stormwater system to achieve compliance and
building a new restroom facility adjacent to the fields.
Design Budget $200,000 Est
Const Budget $3,900,000 Est
Total Budget $4,100,000 Est
Arch/Eng:Stantec
General Cont TBD
Owner Rep (CEI)TBD
NTP Design 2/18/2024 Est
NTP Const Aquatics: Q1 2026; Stormwater: Q1 2026
Sub Completion Aquatics: Q2 2027; Stormwater: Q4 2026
Final Completion Aquatics: Q2 2027; Stormwater: Q5 2026
13
Strategic Plan
BEACH PARKING ADDITIONS
Updated: 1.11.2024
Next Steps/Current Challenges
•Continue research into available properties for acquisition
•Identify available funding sources for acquisition and property development
•Garner public support for identified project(s)
Additional Options for Consideration
•Viability of expanding Beach Trolley Circulator
•Investigate off-site parking option properties (i.e. The Excursion, Pewter Mug, etc.)
•Look at current beach parking permitting process for expanded accessibility
District # 4
Project #TBD
Project Manager Tanya Williams, Department Head
Project Sponsor Public Services Dept – Parks & Recreation
Scope: Research, plan, and determine approach to acquiring additional beach
parking spaces.
Design Budget TBD
Const Budget TBD
Total Budget TBD
Arch/Eng:TBD
General Cont TBD
Owner Rep (CEI)TBD
NTP Design TBD
NTP Const TBD
Sub Completion TBD
Final Completion TBD
14
Strategic Plan
BEACH RENOURISHMENT
Next Steps/Current Challenges Updated 2.3.2024
•Begin annual monitoring (surveying) of County beaches and inlets in January 2024 to determine scope of required
renourishment (if any).
•Present monitoring results and recommendations of consultant to CMO for approval of any necessary renourishment
project.
•Renourishment typically occurs outside of sea turtle nesting season which is from May through October each year.
Progress
•NTP issued to Humiston & Moore December 27, 2023, for annual monitoring of beaches and inlets.
Stage % Complete
Design 0%
Construction Procurement 0%
Construction 0%
Closeout 0%
District #1, 2 & 4
Project #90068, 90066, 90067, 90071
Project Manager Andy Miller, Manager, Coastal Management
Program
Project Sponsor Transportation Management Services
Scope: Renourishment of Collier’s engineered beaches at Vanderbilt, Pelican
Bay, Park Shore, Naples, and South Marco beaches.
Design Budget $200,000
Const Budget $8,000,000 (TBD)
Total Budget $10,000,000 (TBD)
Arch/Eng.:TBD
General Contractor TBD
Owner Rep (CEI)In-House
NTP Design * May 1, 2024
NTP Const * November 1, 2024
Sub Completion * December 15, 2024
Final Completion * January 15, 2025
* Estimated date – Will be contingent on the
survey recommendations
15
Strategic Plan
BIG CORKSCREW ISLAND REGIONAL PARK
PHASE 2A AND 2B
Next Steps/Current Challenges Updated: 1/23/2024
•Phase 2A
•Actively coordinating with adjacent developers
•Intersection design 90% – bid docs due – 1/15/2024
•QE to revise schedule – 1/19/2024
•Phase 2B
•FM meeting with Parks to finalize scope/phasing – 1/10/2024
•Provide design team notes from meeting – 1/12/2024
Progress
•Phase 2A
•PO Issued. NTP to be issued for – 1/22/2024
•CEI contract amendment approved – 11/14/2024
•Phase 2B
•Engineer Design Phase 2B 100% draft completed – 12/7/2023
•90% plans reviewed and modifications discussed with Parks – 12/5/2023
Stage % Complete
Procurement 2A 80%, 2B 50%
Design 2A 100%, 2B 90%
Construction 2A 0%, 2B 0%
Closeout 2A 0%, 2B 0%
District #5
Project #80039
Project Manager James K. Morton, PE
Project Sponsor Facilities Management
Scope: The Big Corkscrew Island Regional Park (BCIRP) Phase 2 includes four
sub-phases 2A, 2B, 2C, and 2D. Project scope for 2A is Oil Well/Big Corkscrew
drive access road, traffic signal at Oil Well Rd/Big Corkscrew Dr and PUD
utilities/wells #4 and #5. Phase 2B includes Site Civil/Drainage, Jogging/Biking
Paths, Landscape Features, Nance Drive, Dog Park, Bollt Canal Crossing, Bollt
Canal Weir at Golden Gate Canal and remainder of NESA utility corridor.
Design Budget $770,470 (Includes all phases)
Const Budget $7.8MM Est
Total Budget $7.9MM Est
Arch/Eng:Q Grady Minor/Victor Latavish
General Cont Quality Enterprises (Low Bid $9,028,810)
Owner Rep (CEI)WSP Environmental and Infrastructure
NTP Design 2A: 3/1/2017; 2B: 3/1/2017
NTP Const 2A: 1/22/2024; 2B: Q4 2024 Est
Sub Completion 2A: 8/19/2024 Est; 2B: Q2 2026 Est
Final Completion 2A: 10/30/2024 Est; 2B: Q3 2026 Est
Phase 2A Phase 2B
16
Strategic Plan
BOAT RAMP ADDITIONS
Progress Updated: 1.11.2024
•Cocohatchee Bay Planned Unit Development Amendment to Settlement Agreement, BCC Approved 10/10/2023
(Exhibit A) – Parking for boat launch.
Next Steps/Current Challenges
•Continue research into available properties for acquisition
•Identify available funding sources for acquisition and property development (TDC, FY 2025, Bond/Long-term
financing, etc.)
•Garner public support for identified project(s)
Additional Options for Consideration
•Purchase of additional and/or utilization of existing properties on Danford Street (Bayview Park/Ramp Access)
•Maximize public boat ramp capacity by phasing out or relocating commercial use to single location
District #ALL
Project #TBD
Project Manager Tanya Williams, Department Head
Project Sponsor Public Services Dept – Parks & Recreation
Scope: Research, plan, and determine approach to acquiring additional boat
launch ramps and required parking.
Design Budget TBD
Const Budget TBD
Total Budget TBD
Arch/Eng:TBD
General Cont TBD
Owner Rep (CEI)TBD
NTP Design TBD
NTP Const TBD
Sub Completion TBD
Final Completion TBD
Additional Parking for
Cocohatchee River Park &
Marina
Tract 10, Wiggins Bay Phase 1
Subdivision (includes 1.61 acres to
be conveyed to County for parking)
17
Strategic Plan
Stage % Complete
Procurement 85%
Design 100%
Construction 0%
Closeout 0%
Next Steps/Current Challenges Updated: 1/10/2024
•NORA and DELORA under way – 1/19 /24
•City issuance of Marco Island construction permits to be coordinated with planning, zoning, commercial vendors permits,
and parking changes
•Pending action on new lease agreement for City of Marco Police boat lift
•Additional funding requested from (1813) to fully fund construction and follow-on projects
Progress
•Bids opening – 1/3/22
•Permits, submitted 7/22/22 – FDEP received on 3/10/2023, and USACE received 4/28/23
•The City will allow Batter Piles, and 0.2 ft rise in seawall cap
•Coordinated with emergency seawall repairs & petroleum infrastructure reconstruction
District #1
Project #80423.2
Project Manager James K. Morton, PE
Project Sponsor Facilities Management
Scope: Replace bulkhead, dock, boat ramp and because of Hurricane Ian assess
additional damage and design repair. A separate project includes removal of fuel
system and installation of a new fuel tank and system.
Design Budget $114,928
Const Budget $1,968,815 Est
Total Budget $805,708 available (1813)
$1,753,751 requested (1813)
Arch/Eng:Aptim Environmental & Infrastructure, LLC -
PO#4500217875
Contractor TBD
Owner Rep (CEI)WSP Engineering Team
NTP Design 5/23/2022
NTP Const 3/15/2024 Est
Sub Completion 10/18/2024 Est
Final Completion 11/18/2024 Est
CAXAMBAS SEAWALL REPLACEMENT
(NEW PRIORITY)
18
Strategic Plan
Stage % Complete
Procurement 50%
Design 10%
Construction 0%
Closeout 0%
District #1
Project #TBD
Project Manager Camden Smith, PMP, MPA
Project Sponsor Facilities Management
Scope: To design and build a new fuel system for Caxambas and to
determine if above ground or underground fuel tank is best during the
programming phase.
Design Budget $75,000 Est
Const Budget $350,000 (Est to remove old, install above ground)
$650,00 (Est to remove old, install underground)
Total Budget $725,000 Est
Arch/Eng:Agnoli Barber & Brundage
General Const TBD
Owner Rep (CEI)TBD
NTP Design 12/8/2023
NTP Const 7/30/2024 Est
Sub Completion 11/17/2024 Est
Final Completion 12/17/2024 Est Next Steps/Current Challenges Updated: 1/9/2024
•Provide feedback to designer on fuel tank recommendation – 1/12/24
•30% design plans – 2/16/24
Progress
•Designer issued fuel tank recommendation – 12/14/23
•Design NTP issued – 12/4/23
•Design Kick-Off meeting held – 12/4/23
CAXAMBAS NEW FUEL SYSTEM
(NEW PRIORITY)
19
Strategic Plan
EMERGENCY BERM TRUCK HAUL & CONSTRUCTION
REACHES A & B
Next Steps/Current Challenges Updated: 2.1.2024
•*Due to the incomplete easement acquisitions on Port Royal’s private beach and heavy sea turtle nesting activities, staff
opted to forego construction in South Naples until the necessary easements had been acquired and sea turtle nesting
ends. Due to the delay in construction and according to section 10.4 of agreement 23-81111 with Phillips and Jordan,
Inc, the contract was terminated for convenience and BCC approved on 12/12/23.
• Hurricane Idalia passed offshore of Collier beaches on August 30, 2023, the lack of berm in South Naples allowed a
storm surge of 2-4 feet to encroach into landward properties.
• *Change Order No.1 with Aptim Environmental and Infrastructure, LLC was processed to have the
engineering consultant provide a re-survey, re-design, bidding assistance, and post-design services for the remaining South
Naples emergency berm due to impacts of Hurricane Idalia.
Progress
• *Staff will wait for the engineering consultant to complete the re-survey and re-design prior to soliciting South Naples
berm construction.
• Reach B was successfully completed.
Stage % Complete
Procurement 100%
Design 100%
Construction 90%*
Closeout 90%*
District #1, 2 & 4
Project #50280
Project Manager Andy Miller, Project Manager
Project Sponsor Transportation Management Services
Scope: Construction of an elevated emergency berm/dune along all
developed Gulf facing County beaches due to the destruction of the dunes
by Hurricane Ian
Design Budget $241,772.75
Const Budget $20,000,000
Total Budget $24,000,000 (BCC Approved)
Arch/Eng.:Aptim Environmental and Infrastructure, LLC
General Contractor A- Phillips & Jordan, Inc
B- Earth Tech Enterprises
Owner Rep (CEI)In-House
NTP Design December 28, 2022
NTP Const A- April 3, 2023, B- April 12, 2023
Sub Completion A- June 12, 2023, B- June 21, 2023
Final Completion A- July 12, 2023*, B- July 21, 2023
20
Strategic Plan
GOLDEN GATE 9-12 HOLE
PUBLIC GOLF COURSE
Next Steps/Current Challenges Updated: 1/23/2024
•Updated stormwater model for 0.04 cfs/acre discharge rate – 1/15/24
•Notify Davidson Engineering to develop construction/solicitation package for the construction of swale west of
Residential tract – 1/12/24
•ITN 24-8223 - Golf and Entertainment Complex at the Former Golden Gate Golf Course proposal due – 1/8/24
Progress
•Environmental testing CO approved by BCC – 12/12/23
•Met with Grady Minor on rezone scope – 11/17/23
Stage % Complete
Procurement 30%
Design 20%
Construction 0%
Closeout 0%
District #3
Project #80412
Project Manager Brian DeLony, PE
Project Sponsor Facilities Management
Scope: Revise and enhance the golf course facilities, while also considering
modifications to zoning regulations and infrastructure to accommodate
diverse purposes, including but not limited to affordable housing and the
establishment of a State Veterans’ Nursing Home.
Design Budget $2,250,000 Est
Const Budget TBD
Total Budget $7,000,000 Est
Arch/Eng:Davidson Engineering
General Cont TBD
Owner Rep (CEI)TBD
NTP Design 2/24/2020
NTP Const TBD
Sub Completion TBD
Final Completion TBD
21
Strategic Plan
PROJECT NAME DEPARTMENT/DIVISION SLIDE #
CYBERSECURITY INITIATIVES INFORMATION TECHNOLOGY 23
DAS ANIMAL SERVICES RENOVATION (SURTAX)FACILITIES MANAGEMENT CIP 24
HR RECRUITMENT & RETENTION HUMAN RESOURCES 25
STRATEGIC REAL ESTATE ACQUISITIONS REAL PROPERTY 26
STRATEGIC PLAN BUDGET INTEGRATION COUNTY MANAGER'S OFFICE 27
HUSSEY PROPERTY SITE PREP – MASTER PLANNING (NEW PRIORITY)FACILITIES MANAGEMENT CIP 28
CAMP KEAIS/ROCK SPRINGS – MASTER PLANNING/ENVIRONMENTAL
TESTING (NEW PRIORITY)FACILITIES MANAGEMENT CIP 29
PLANNING & COUNTY OPERATIONS
Strategic Plan
CYBERSECURITY INITIATIVES
Next Steps/Current Challenges
•Need to finish Security Operation Center on F6
•Other CS Initiatives
Progress
•Installed upgraded backup software to allow for immutable backups
•Upgraded SAN/NAS software that will not allow horizontal attacks
•Added more back up capacity to allow for 6 months of backups
•Added monitoring software to monitor vulnerabilities within the agency for both hardware and software and
allows for mitigation
•Added Incident Recovery capabilities
•MFA across County
•Upgraded Edge Routers
•Instituted and implemented Cybersecurity Training Program throughout the Agency.
•Implemented over $300K/annually software upgrades from State Grant Program (FLDS)
Stage % Complete
Procurement 100%
Design 100%
Construction 0%
Closeout 0%
District #1-5
Project #N/A
Project Manager Mark Gillis, Division Director, Information
Technology
William Bouza, Cybersecurity Manager
Project Sponsor Information Technology
Scope: As cybersecurity threats become more sophisticated, ways to combat
the threat of malware, ransomware, and viruses must also keep up to date. This
project entails adding layers to our security apparatus to combat potential
threats. This includes mitigation and prevention.
Design Budget $300,000 from State Grant
$555,000 SAN/NAS Upgrades
$1,800,000 in backup Upgrades
Const Budget NA
Total Budget $2,655,000
Final Completion 12/31/2024 and Ongoing
23
Strategic Plan
DOMESTIC ANIMAL SERVICES RENOVATION (SURTAX)
Next Steps/Current Challenges Updated: 1/23/2024
•Building envelope improvements are under way by Service Contracting Solutions (SCS) – 3/1
•Solicitation to Procurement – 3/1
•Exterior electrical work continuing expected completion – 2/23
•Livestock fence solicitation – Draft underway – 2/2
•100% plan revisions for building design under way – 1/19
o TECO Gas confirmed they will handle gas drawings
•Midmark Quote for Kennel Cages ($285,000); review of design with DAS Director – ¼
Progress
•SDPI application approved – 11/6
Stage % Complete
Procurement 50%
Design 95%
Construction 0%
Closeout 0%
District #1
Project #50145.4
Project Manager Camden Smith, PMP MPA
Project Sponsor Surtax
Scope: To renovate five buildings on the DAS site Renovation includes
improving comfort for stray and adoptable pets by adding HVAC to all
buildings, redesigning an expanded pet holding area for the high bay building,
and constructing built-in storage. Scope includes pet care improvements with
a new veterinary clinic X-Ray room and medical-grade floor/ceiling for the pet
surgical suite. Expanded stray cat holding within the existing footprint and
new pet wash areas are also included.
Design Budget $398,785
Const Budget $4,000,000 Est
Total Budget $4.4MM Est
Arch/Eng:Studio Plus
General Cont TBD
Owner Rep (CEI)Studio Plus
NTP Design 5/6/2023
NTP Const Q3 2024 Est
Sub Completion Q4 2025 Est
Final Completion Q1 2026 Est
24
Strategic Plan
HR RECRUITMENT & RETENTION
Next Steps/Current Challenges Updated: 1.12.2024
•Temporary deferral of recruitment for certain General Fund vacancies.
•Collaboration between Communications, Government & Public Affairs and Human Resources to coordinate filming of
engaging, short videos with County employees across the organization to use in future recruitment advertising. The
clips will highlight the reasons individuals appreciate working for the organization and County benefits they value
most.
Progress
•Advertisement of openings through web outlets (GovernmentJobs.com, Indeed) and social media (County Facebook
sites, LinkedIn, myCollier Community newsletter).
•Successful implementation of pay adjustments to employees at the start of FY24.
•Assessment of the effectiveness of using retractable, table-top, digital, and mesh banners placed strategically both
inside and outside County buildings to advertise open positions. Trackable QR codes allow the organization to better
identify the source where candidates learned of a vacancy.
•Preparation to launch re-designed Performance Evaluation Tool in January 2024 County-wide. This will capture a six-
month performance period and will provide data necessary to evaluate options for a future merit pay program
recommendation.
District #All
Project #N/A
Project Manager Amy Lyberg, Director
Project Sponsor County Manager
Scope: Position Collier County to be successful in recruiting and retaining
quality talent for the organization who will deliver high-quality, best-value
public services to meet the needs of our residents and visitors.
25
Strategic Plan
STRATEGIC REAL ESTATE ACQUISITION
Next Steps/Current Challenges: Updated: 1.11.2024
On going monitoring and evaluation of properties for acquisition such as:
•Williams Reserve Farms/Williams Reserve Lake Trafford
•CCSO Acquisitions:
•Substations
•Training
•Hodges University
•Property Investment Opportunities
District #All Districts
Project #TBD
Project Manager Jennifer A. Belpedio, Manager
Project Sponsor Real Property
Scope: The purchase of properties that align with the County’s objectives while
considering economic trends, demographics and growth.
26
Williams Reserve
$23,000,000
CCSO Acquisitions
$13,000,000 +
Strategic Plan
STRATEGIC PLAN BUDGET INTEGRATION
Next Steps/Current Challenges Updated: 1.11.2024
•Contract Development and Procurement of Resource X.
•Program Data Collection
•Alignment of Programs with Organizational Strategic Goals
•Development of Performance and Activity Measures
•Prioritization of Programs utilizing Resource X Software
Progress
•Board direction to move forward with ResourceX
•Working on Procurement of ResourceX via Cooperative Agreement with Omnia Partners
•Initiated Programming Updates to GovMax
•Incorporation of Strategic Goals and Aligned Objectives
•Modified Budget Document to Display Strategic Goals and Objectives
•Incorporate Priority Field into Account Detail
Stage % Complete
Procurement 75%
Design 15%
Test 0%
Go Live 0%
District #All Districts
Project #50001
Project Manager Christopher Johnson, OMB Director
Project Sponsor Corporate Financial and Management Services
Scope: Alignment of financial resources with strategic goals to enhance
organizational performance utilizing a priority-based budgeting approach
(PBB).
Total Estimated Budget $420,000
Vendors ResourceX, GovMax
Owner Rep (CEI)N/A
Purchase Orders Govmax PO: 4500228593
Resource X PO: TBD
Final Completion Estimated April 2024
27
Strategic Plan
CAMP KEAIS/ROCK SPRINGS – MASTER PLANNING/ENVIRONMENTAL TESTING
(NEW PRIORITY)
Next Steps/Current Challenges: Updated: 1/10/2024
•Secondary soil testing underway – 2/23/2024
•Utilities investigation and coordination underway – 6/3/2024
•Key stakeholder meetings/requirements development scheduled for late February
•Property sale negotiations ongoing – 6/3/2024
Progress
•Kickoff/Planning meeting held – 1/25/2024
•Planning project schedule delivered – 1/19/2024
•PO and NTP received and forwarded to WSP – 1/10/2024
•Phase 2 environmental study received – 12/8/2023
•Work Order for WSP on Master planning submitted – 9/26/2023
Stage % Complete
Procurement 10%
Design 0%
Closeout 0%
District #3
Project #50224
Project Manager Brian Mondgock, Project Manager
Project Sponsor Facilities Management
Scope: Sample/Test areas of concern from Phase 1 using more concentrated
testing patterns to determine the total area of remediation Determine scope
of remediation and monitoring for each area of concern.
Professional planning services related to the master planning, PUD
development, state and federal permitting, zoning, surveying and other
consulting services of the Camp Keais property for future development.
Design Budget $350,000 (pending BA)
Total Budget $850,000
Arch/Eng:Davidson / WSP
NTP Design 9/11/2023 (Davidson)
1/16/2024(Master planning)
Sub Completion TBD
Final Completion TBD
28
Strategic Plan
HUSSEY PROPERTY SITE PREP
MASTER PLANNING (NEW PRIORITY)
Next Steps/Current Challenges Updated: 1/23/2024
•WSP to provide corrected proposal and subcontractor backups – 2/2/2024
•WSP to provide summary schedule – 3/4/2024
Progress
•Received proposal from WSP for master planning and Phase I environmental – 12/7/2024
•Received Phase II environmental study to proposal from WSP – 12/18/2024
•
Stage % Complete
Procurement 50%
Design 0%
Construction 0%
Closeout 0%
District #5
Project #50205
Project Manager Brian Mondgock, Project Manager
Project Sponsor Facilities Management
Scope: Site master planning for approximately 1,000 acres. Stormwater
planning, Wetland mitigation planning, Zoning/Land use Transportation
coordination/planning, Environmental studies and Environmental testing.
Design Budget $350,000 Est
Total Budget $850,000 Est
Arch/Eng:WSP
NTP Design 3/4/2024 Est
29
Strategic Plan
PROJECT NAME DEPARTMENT/DIVISION SLIDE #
CCSO FORENSICS BUILDING (SURTAX)FACILITIES MANAGEMENT CIP 31
COLLIER COUNTY MENTAL HEALTH FACILITY (SURTAX)FACILITIES MANAGEMENT CIP 32
STATE VETERANS’ NURSING HOME (SURTAX)FACILITIES MANAGEMENT CIP 33
EMS STATION 74 (SURTAX) (NEW PRIORITY)FACILITIES MANGEMENT CIP 34
800 MHz RADIO HARDENING – PROJECT ANALYSIS FOR FULL UPGRADE
(UPDATED)EMERGENCY SERVICES – TELECOMMUNICATIONS 35
800 MHz RADIO HARDENING - CARNESTOWN RADIO SITE EMERGENCY SERVICES - TELECOMMUNICATIONS 36
PUBLIC HEALTH & SAFETY
Strategic Plan
CCSO FORENSICS BUILDING
(SURTAX)
Next Steps / Current Challenges Updated: 1/23/2024
•Questions & Answer due date: 01/19/2024 at 5:00 p.m.
•Bid Opening scheduled for 01/30/2024 at 3:00 p.m.
•Obtaining all pending permits
Progress
•Change Order #5, to Stantec, was approved during the 12/12/2023 BCC Meeting
•Vehicle Storage Permit Comments: received / Design Team is addressing them.
•All Permits have been submitted – November 2023 update as indicated below - the items underlined and in italic are
estimated timeframes based on past experiences:
1.Environmental Resource Permit (ERP) was submitted to FDEP on 10/10/23. 30-day review period expired on
11/13/23. RAI 1 response 12/18/23 with permit approval/waiting period (45 days) by 1/31/23
2.SDPA (Collier County Growth) 10/19/23 (permit deemed complete). Review period ended on 11/19/23. RAI 1
response 12/20/23, Approval 1/26/24
3.FDEP Water Permit, TBD (form submitted to Collier County for review and signature, once returned will submitted to
FDEP). 30-day review approval/window (site work can begin without this permit).
4.FDEP Wastewater Permit, TBD (form submitted to Collier County for review and signature, once returned will
submitted to FDEP). 30-day review approval/window (site work can begin without this permit).
5.ACOE permit previously issued and extension requested by County. Stantec was informed that extension was applied
for and awaiting approval. County staff and Stantec met with Collier County Growth Management staff and discussed
permit status and GM stated they would not hold up SDPA permitting based on ACOE permit tension request.
Stage % Complete
Procurement 60%
Design 100%
Construction 0%
Closeout 0%
District #5
Project #70167
Project Manager Olivier Sureau, Project Manager
Project Sponsor Surtax
Scope: This facility will house crime scene, evidence and technical services
bureau and include storage for evidence, vehicles as well as large
equipment.
Design Budget $5,773,613
Const Budget $61,000,000 - Anticipated Construction Cost
Total Budget $33,000,000
Arch/Eng:Stantec
General Cont Pre-construction: Manhattan
Construction: TBD – Plan/Spec Hard-Bid
Owner Rep (CEI)Facilities Management Division
NTP Design 7/26/2019
NTP Const Summer 2024 - Tentative
Sub Completion Summer 2026 - Tentative
Final Completion Summer 2026 - Tentative
31
Strategic Plan
COLLIER COUNTY MENTAL HEALTH FACILITY
(SURTAX)
Next Steps / Current Challenges Updated: 1/23/2024
•Biweekly meetings with all stakeholders and the Design Team have resumed and are ongoing
•Maintain the allocated budget
•60% construction cost is due on 12/5/2023
Progress
•60% design documents delivered on 10/25/2023
•BCC approved budget of $43.9 Million for 87 Beds, and approximately 60,000 SF facilities on 06/27/2023
•Second Amendment to Vacant Land Contract extending by one year the time to obtain site development plans was
approved by BCC – 05/09/2022
•Rezoning pertinent selected site was approved by BCC – 02/14/2022
•30% construction documents & cost analysis are completed
•60% documents are under review
Stage % Complete
Procurement 50%
Design 60%
Construction 0%
Closeout 0%
District #3
Project #50239
Project Manager Claudia Roncoroni, Project Manager
Project Sponsor Surtax
Scope: The Collier County Mental Health Facility project will be located on a
parcel along Golden Gate Parkway, not far from the David Lawrence Center
Complex. This new structure will increase crisis support and will function as
the Central Receiving Center (CRC) for those receiving services under both
the Baker and the Marchman Acts.
Design Budget $2,589,309
Const Budget $43.9 Million
Total Budget $25 million
Arch/Eng:R.G. Architects
General Cont DeAngelis Diamond
Owner Rep (CEI)Facilities Management
NTP Design 3/15/2022
NTP Const Pre-Construction: 4/7/2023
Construction: TBD
Sub Completion Fall 2026 (anticipated)
Final Completion Fall 2026 (anticipated)
32
Strategic Plan
STATE VETERANS’ NURSING HOME
(SURTAX)
Next Steps/Current Challenges Updated: 1/23/2024
•Preliminary design – 2/19/2024
Progress
•NTP for preliminary design services – 1/5/2024
•$30 million in Collier County surtax funding approved by voters as the State match for federal construction
matching grant funds
•13.5 acres at NW corner of Golden Gate Golf Course committed via MOA with the State
•$500,000 appropriated by the State Legislature for preliminary design
•$10 million in surplus surtax funding committed by BCC for Adult Day Health Care and Outpatient Therapy
facilities (not matched by the federal government in the grant program)
•Updated MOA with the State moving facility site to 20 acres along SR 951
•Preliminary design being created by State contractor for inclusion with the Federal Construction Grant
Application which is due by April 15, 2024
Stage % Complete
Procurement N/A
Design 0%
Construction 0%
Closeout 0%
District #3
Project Sponsor Florida Department of Veterans’ Affairs
Scope: Offer assistance and financial backing to the Florida Department of
Veterans’ Affairs in the design, permitting and construction of a State Veterans’
nursing home, adult day health care, and outpatient services.
Arch/Eng:Williamson Design (Preliminary Design for Federal
Application)
General Cont.TBD
Owner Rep (CEI)TBD
NTP Design TBD
NTP Const TBD
Sub Completion TBD
Final Completion 2028 Est
33
Strategic Plan
EMS STATION 74 (SURTAX)
(NEW PRIORITY)
Next Steps/Current Challenges Updated: 1/5/2024
•Award of construction agreement by BCC - 1/9 /2024
•Surtax committee meeting to validate usage of funds - 1/11/2024
Progress
•Received document package including construction agreement signed by Rycon from Procurement
Stage % Complete
Procurement 90%
Design 100%
Construction 0%
Closeout 0%
District #5
Project #55212
Project Manager Clint Perryman, PMP, CGC
Project Sponsor Surtax
Scope:
Design and construct a new facility to support EMS and Fire District
operations in the Golden Gate Estates area to lower response times.
Design Budget $454,769
Const Budget $9,464,456
Total Budget $10,766,159
Arch/Eng:Schenkel Shultz Architecture
General Cont Rycon
NTP Design 5/4/2021
NTP Const TBD
Sub Completion TBD
Final Completion TBD
34
Strategic Plan
800 MHz RADIO HARDENING PROGRAM
PROJECT ANALYSIS FOR FULL UPGRADE (UPDATED)
Next Steps/Current Challenges. Updated: 2.2.2024
•Finalize a needs analysis for the 800Mhz P25 radio program.
•Task Team meetings: Continue meetings with customers to determine full scope of needs.
•Meeting with financing to determine potential funding sources and options.
•Meeting with procurement to secure a method of potential purchase options.
•Internal needs assessments are being completed with due diligence.
Progress
•We are continuing our efforts to reassess our Public Safety 800Mhz radio system to examine the most
technologically advanced and supported options with respect to the specific needs of CCSO, Fire and EMS.
•The Hardening Program will be limited to mission critical requirements pending a decision to pursue a full system
upgrade.
Stage % Complete
Procurement 0%
Design 80%
Construction 0%
Closeout 0%
District #ALL
Project #TBD
Project Manager Nathaniel Hinkle, Telecommunications Manager
Project Sponsor County Manager’s Operations
SCOPE: The existing 800Mhz L3Harris P25 radio system was purchased in 2015 and
has experienced several critical failures related to system design issues, lack of radio
site hardening and resiliency measures. In examining the needs of our First
Responders we are in the process of looking into a complete upgrade to the latest
technologies with features that support our critical life safety communications needs.
Design Budget TBD
Const Budget TBD
Total Budget TBD
Funds Remaining
General Cont TBD
Owner Rep (CEI)TBD
NTP Design TBD
NTP Const TBD
Sub Completion TBD
Final Completion TBD
Public Safety Radio System Analysis
35
Strategic Plan
800 MHz RADIO HARDENING PROGRAM
CARNESTOWN RADIO SITE RELOCATION
Next Steps/Current Challenges Updated: 1.11.2024
•A Conditional Use Permit from the County is required. If permit is not approved, another candidate location would
need to be jointly decided on by Collier County and State of Florida DMS, adding risk to maintaining adequate
coverage of the County and the State radio systems.
Progress
•Ochopee Fire station 66 has been selected as a suitable candidate and will provide similar coverage to the existing
site
•CU application from Davidson Engineering waiting on State DMS information 1/3/2024.
Stage % Complete
Procurement 0%
Design 80%
Construction 0%
Closeout 0%
District #5
Project #50104.14
Project Manager Nathaniel Hinkle, Telecommunications Manager
Project Sponsor County Manager’s Operations
SCOPE: We are being required by Big Cypress National Parks and the tower owner,
along with several other government and commercial tenants, to vacate an existing
tower site at US 41 and SR 29 in 2024. We have identified a candidate site location
that will be a new tower build on County-owned property. We are collaborating
with the State of Florida who also wishes to use the same location.
Design Budget TBD
Const Budget TBD
Total Budget $1,500,000
General Cont State of Florida DMS/ Hardware TBD
Owner Rep (CEI)TBD
NTP Design TBD
NTP Const TBD
Sub Completion TBD
Final Completion TBD
Carnestown Radio Site Forced Relocation
36
Strategic Plan
PROJECT NAME DEPARTMENT/DIVISION SLIDE #
VANDERBILT BEACH ROAD EXTENSION TRANSPORTATION ENGINEERING 38
VANDERBILT BEACH ROAD EXTENSION - PHASE II (NEW PRIORITY)TRANSPORTATION ENGINEERING 39
PINE RIDGE ROAD IMPROVEMENTS TRANSPORTATION ENGINEERING 40
ROADWAY RESURFACING PROGRAM 2024 ROAD, BRIDGE & STORMWATER MAINTENANCE 41
UNDERGROUND STORMWATER INFRASTRUCTURE CLEAN, VIEW & REPAIR
PROGRAM ROAD, BRIDGE & STORMWATER MAINTENANCE 42
ROADSIDE SWALE PROGRAM ROAD, BRIDGE &STORMWATER MAINTENANCE 43
TIGER GRANT - IMMOKALEE IMPROVEMENTS TRANSPORTATION ENGINEERING 44
GOODLETTE-FRANK ROAD WIDENING (NEW PRIORITY)TRANSPORTATION ENGINEERING 45
COLLIER BOULEVARD WIDENING PHASE III (NEW PRIORITY)TRANSPORTATION ENGINEERING 46
GOLDEN GATE CITY WATER RESOURCE PROTECTION/RESTORATION MASTER
PLAN TRANSPORTATION/CPP & PUBLIC UTILTIES EPMD 47
IMMOKALEE ROAD I-75 INTERCHANGE IMPROVEMENTS (NEW PRIORITY)TRANSPORTATION ENGINEERING 48
TRANSPORTATION MANAGEMENT SERVICES
Strategic Plan
VANDERBILT BEACH ROAD EXTENSION
Current Status : Updated:
1.11.2024
•Excavating Cypress Canal, ponds, processing material and placing roadway embankment at various locations
within project limits.
•Installing drainage between Orange Tree Canal and Curry Canal.
•Driving 18” concrete piles at Curry Canal & placing rip rap rubble at Corkscrew Canal.
•Fusing 30” HDPE NPW Main at Wilson Blvd.
4-week Look Ahead:
•Continue driving concrete piles at Curry Canal.
•Continue excavating ponds, processing materials, and placing roadway embankment.
•Continue storm drain installation and pipe video.
•Tie in 18” HDPE NPW Main at Curry Canal.
Stage % Complete
Procurement 100%
Design 100%
Construction Work Complete 32%
Construction Time Complete 41%
District #5
Project #60168
Project Manager Felipe Baez, PM II
Project Sponsor Transportation Engineering
Scope: A 7-mile extension of Vanderbilt Beach Road; 6-lane urban roadway
from east of Collier Blvd to Wilson Blvd., followed by two lanes up to 16th
St. NE. New intersections and traffic signals on Wilson Blvd., 8th St. NE and
16th St. NE. Canal relocation to south of the roadway from 29th Street N.W.
to 15th Street N.W. Improvements to existing intersecting streets including
Weber Boulevard, Massey Street and Douglas Street.
Const Budget $153M ($74M Surtax)
Arch/Eng:Jacobs Engineering
General Contractor Sacyr Construction USA
Owner Rep (CEI)In-house staff with support from Johnson
Engineering
NTP Const 9/12/2022
Final Completion 9/26/2025
38
Strategic Plan
VANDERBILT BEACH ROAD EXTENSION PHASE II
(NEW PRIORITY)
Current Status Updated 1.11.2024
•Previous plans were completed up to the 60% design stage in 2008.
•Consultant is working on analyzing and updating these plans.
•Once current 60% design plans are available, right-of-way acquisition can commence.
Stage % Complete
Design Procurement 100%
Design 10%
Construction 0%
District #5
Project #60249
Project Manager Bee Thao, P.E, Project Manager III
Project Sponsor Transportation Engineering
Scope: A continuation of Vanderbilt Beach Rd. Extension, this 2-mile project
consists of two travel lanes from 16th St. NE to Everglades Blvd.
The footprint of this project will allow for a future 6-lane expansion as traffic
demand increases. A new signalized intersection is planned at the corner of
Everglades Blvd, while one new bridge will be constructed within the limits
of this project.
Design Budget $1.79M
Const Budget $20M
CEI Budget $2.5M
Total Budget $24.29M
Arch/Eng:Kimley-Horn
Owner Rep (CEI)TBD
NTP Design 11/2023
Design Completion 7/2025 Everglades Blvd Nend of Vanderbilt
Beach Rd
Extension 16th Str NE39
Strategic Plan
PINE RIDGE ROAD IMPROVEMENTS
Current Status Updated: 1.11.2024
•Re-evaluated intersection improvements for Livingston Road;
•Design change to jughandle intersection approved by BCC on 11/14/23;
•In Nov 2023, FDOT opted to remove the Interchange improvements from the County's project and will be completing
as a separate project funded with Moving Florida Forward;
•Contract amendment for Jacobs to be negotiated.
Stage % Complete
Procurement for Design 100%
Design 20%
Construction 0%
District #2, 4
Project #60201
Project Manager Dennis McCoy, P.E., Sr. Project Manager
Project Sponsor Transportation Engineering
Scope: Design, permit, and construct improvements at the intersection of
Livingston Road and Pine Ridge Road (jughandle intersection) and at the
intersection of Whippoorwill Lane and Pine Ridge Road (standard). The I-75
interchange on Pine Ridge Road (diverging diamond intersection) is now to
be completed by FDOT.
Design Budget $2.6M
Const Budget $35.9M ($23M Surtax)
CEI Budget $3.5M
Total Budget $42M
Arch/Eng:Jacobs Engineering
Owner Rep (CEI)To be outsourced
NTP Design 10/2022
Design Completion 9/2025
FDOT Project
Jughandle
40
Strategic Plan
ROADWAY RESURFACING PROGRAM
Next Steps/Current Challenges Updated 1.11.2024
•As of 01/04/2024, work has started on Rattlesnake Hammock Rd, from Collier Blvd to Grand Lely Dr, and Collier Blvd,
from Rattlesnake Hammock Rd to Triangle Blvd. Work is estimated to be complete by 03/15/2024.
•We plan to resurface the southern section of Collier Ave in Everglades City after Collier Blvd and Rattlesnake Hammock
Rd is finished. This will complete the resurfacing of the main road of Everglades City.
•Contract under All Hazard Preparedness, Planning, Consulting, and Recovery Services is approved, and Roadway Asset
Services was chosen to perform the PCI rescoring. Estimated to begin in Feb. 2024
Progress
•Our current list of resurfaced roadways include:
Stage % Complete
Procurement 100%
Design 100%
Construction 30%
Closeout 0%
District #All Districts
Project #60131
Project Manager Christopher Covert, PE
Project Sponsor Road Maintenance
Scope: The 2024 Roadway Resurfacing Program is for the maintenance of
roadways throughout Collier County due to degradation, surface level
damage, or structural imperfections. Additional roads will be added in cases
of emergency maintenance and Program will be adjusted accordingly.
Design Budget In house
Const Budget $10,000,000
Total Budget $10,000,000
Arch/Eng:N/A
General Contractor Preferred Materials, Inc.
Owner Rep (CEI)In-House
NTP Design N/A
NTP Const October 1st, 2023
Sub Completion April 31st, 2024
Final Completion September 30th, 2024
•Donna St
•Kathy Ave
•Bonnie St
•Lorraine Ave
•Burton Rd
•Esther St
•3rd Ave SW
•5th Ave SW
•7th Ave SW Radio Rd 41
Strategic Plan
UNDERGROUND STORMWATER INFRASTRUCTURE CLEAN, VIEW,
AND REPAIR PROGRAM
Next Steps/Current Challenges Updated: 1.11.2024
•Previous clean and view records identified 22 deficiencies. Currently creating a scope of work to determine repair
methods, work orders will be issued to contractors to start repairing deficient infrastructure in phases.
Progress
•As of 01/04/2024, we have cleaned and videoed approx. 12,600 LF of pipe. We are currently cleaning pipes along
Vanderbilt Dr, from Vanderbilt Beach Rd to Bonita Beach Rd, moving away from coastal areas as we progress through
the year.
•Assessing 2025 planned sites and checking aging infrastructure with high-volume calls due to issues reported during
recent storm events and re-prioritizing planned work accordingly.
Stage % Complete
Procurement 100%
Design 100%
Construction 0%
Closeout 0%
District #All Districts
Project #Cost Center 172929
Project Manager Erik Montalvo, Project Manager II
Project Sponsor Road, Bridge, and Stormwater Maintenance
Scope: The Clean, View, and Repair Program is for the maintenance and
repair of aging underground stormwater infrastructure throughout Collier
County. It ensures the proper functionality of our underground stormwater
system by cleaning blockages and repairing deficiencies.
Design Budget In house
Const Budget $1,500,000
Total Budget $1,500,000
Arch/Eng:N/A
General Contractor Shenandoah General Construction, LLC
Owner Rep (CEI)In-House
NTP Design N/A
NTP Const October 1st, 2024
Sub Completion June 30th, 2024
Final Completion September 30th, 2024
Clean and View Approx. Length To
Be Cleaned
Vanderbilt Beach Rd PH1 8,800 LF
Bluebill Ave/111th Ave N 3,848 LF
Vanderbilt Dr 21,048 LF
Goodlette Frank PH2 29,917 LF
Pine Ridge PH1 17,752 LF
Golden Gate Pkwy PH2 28,547 LF
Logan Blvd/Santa Barbara 44,674 LF
Collier Blvd 25,178 LF
Deficiencies Found Since 2023 22
42
Strategic Plan
ROADSIDE SWALE PROGRAM 2024
Next Steps/Current Challenge Updated: 1.11.2024
•Post and hire the Field Supervisor 2 (FS2), FS2 will train under current Supervisors and be introduced to their area
of assignment within the Estates. The FS2 will then commence the assessment of assigned areas and create a list of
tasks to relay to subsequent employees as they are hired when vehicles and equipment become available.
Progress
Heavy Equipment and Vehicles have been specified to the needs of the program and ordered with Fleet
•Five Pickup Trucks – F-250 pickup truck has arrived, and the exterior fuel tank is on order. F-150 (3) and Maverick
(1) pickup trucks estimated arrival is 6 to 8 months.
•Four (4) 22-Yard Dump Trucks – Estimated arrival is 1 year.
•Two (2) John Deere 85 Excavators with attachments – Estimated arrival is 6 to 8 months.
•Two (2) Mower Max Gen 3 boom Mowers – Estimated arrival is 8 months to 1 year.
•Two (2) Freightliner M2106 Crew Cabs – Estimated arrival is 6 to 8 months.
Stage % Complete
Procurement 100%
Design 0%
Construction 0%
Closeout 0%
District #5
Project #TBD
Project Manager Marshal Miller
Project Sponsor Road Maintenance
Scope: The Roadside Swale Maintenance Program is intended to repair and
maintain swales throughout the Estates portion of Collier County. The plan is
to bring swale conditions to a grade level which will facilitate better flow to the
outfall areas during significant rain events. Degradation and new construction
have created imperfections that hinder the function of the swales, which will
benefit from crews that exclusively focus on Maintenance of the 655.93 miles
of swales in the Estates area.
Design Budget N/A
Const Budget N/A
Total Budget $2,823,800.00
Arch/Eng:N/A
General Contractor N/A
Owner Rep (CEI)In-House
NTP Design N/A
NTP Const N/A
Sub Completion N/A
Final Completion Ongoing
43
Strategic Plan
TIGER GRANT – IMMOKALEE IMPROVEMENTS
Current Status Updated: 1.11.2024
•Area 1-Contractor QE, Is finishing Area 1 - School DR asphalt SUP complete.
•Area 2A- Adding Sod, completing asphalt driveways & roadway transitions, & replacing brick paver driveways.
•Area 3- 3A SW construction complete, CEI generated punch list. 3B & C S&S plans distributed.
•Area 4- is still in design.
•Area 5-is still in design and contractor is moving forward with 60% plans on N side along Seminole Reservation,
pending SFWMD permitting review.
•CAT Building : QE has County approval for SPDA, earthwork & grading for slab on grade (SOG), retention area,
parking lot, & entrance nearing completion. Installation of stormwater systems to begin.
Stage % Complete
Procurement 100%
Design 80%
Project Work Complete 29%
Project Time Complete 63%
District #5
Project #33563
Project Manager Jamie Khawaja, PM II
Project Sponsor Transportation Engineering
Scope: This Design-Build project will construct complete streets
improvements in Immokalee, including approximately 20 miles of new
sidewalks, a bike boulevard network, a shared-use path, street lighting, bus
shelters, a new transit center, landscaping, drainage improvements, and
intersection and traffic calming retreats.
Design – Build Budget $22.869M ($13M FHA Grant)
CEI Budget $ 1.946M
Total Budget $24.815M
Arch/Eng:QE USA
Owner Rep (CEI)KCA
NTP Design-Build 3/2022
Final Completion 1/2025 (pending approval of time extension)
44
Strategic Plan
GOODLETTE-FRANK ROAD WIDENING
(NEW PRIORITY)
Current Status Updated: 1.4.2024
•Worked with Pelican Marsh on bridge ownership and landscaping maintenance agreement issues.
•2 firms responded to the Design Solicitation. Top ranked firm was selected.
•Negotiation on scope and fee is in progress.
•Design can start once BCC approves negotiated agreement.
Stage % Complete
Procurement for Design 50%
Design 0%
Construction 0%
District #2
Project #60259
Project Manager Ray G. Girgis, P.E, Project Manager III
Project Sponsor Transportation Engineering
Scope: Goodlette-Frank Road from Vanderbilt Beach Road to Immokalee Rd.
widening from 2 to 4 lanes to match the roadway to the south of this segment.
Design Budget $2.1M
Const Budget $21.2M
CEI Budget $3.18M
Total Budget $26.48M
Arch/Eng:TBD
Owner Rep (CEI)TBD
NTP Design 5/2024
Design Completion 5/2028
45
Strategic Plan
COLLIER BLVD WIDENING PHASE III
(NEW PRIORITY)
Current Status Updated: 1.11.2024
•New bridge is going to be on 27th Ave SW.
•60% design plans submitted by Consultant for staff review.
Stage % Complete
Procurement Design 100%
Design 60%
Construction 0%
District #3
Project #68056
Project Manager Bee Thao, P.E, Project Manager III
Project Sponsor Transportation Engineering
Scope: Widening of Collier Boulevard from 4 to 6 lanes between Green
Boulevard and City Gate Drive N. One lane will be added in each direction along
with a road alignment shift and the following: traffic signal revision, new traffic
signals, new bridges, bridge removal, on-street bike lanes, and pedestrian
upgrades. The contract with Jacobs was re-instated to pick up at the 60% design
stage.
Design Budget $1.86M
Const Budget $42M
CEI Budget $5.88M
Total Budget $49.74M
Arch/Eng:Jacobs Engineering
Owner Rep (CEI)TBD
NTP Design 2/13/2023
Design Completion 7/2024
46
Strategic Plan
GOLDEN GATE CITY WATER RESOURCE PROTECTION/RESTORATION
MASTER PLAN
Current Status:
•Coordination regarding approval of the Agreement with DEP.
•Continued coordination with county departments and divisions.
•4-week look ahead: Vendor selected and received BCC approval to negotiate on 10/10/23. Will continue with
negotiations and prepare contract draft to go to BCC in the Spring.
Stage % Complete
Procurement 95%
Design 0%
Construction 0%
Closeout 0%
District #3
Project #33842
Project Manager Lorraine Lantz, Transportation Planning Manager
Project Sponsor Transportation – CPP & Public Utilities - EPMD
Scope: This Study will use State Appropriation funds to look at the
conversion of the septic systems to central sewer and the private wells to
municipal water as a priority for protecting and restoring local water
resources within Golden Gate City. The project will develop a master plan
that will detail water quality and flood protection issues and evaluate the
feasibility of providing stormwater improvements, septic system
conversions to central sewer, private well conversions to municipal water,
and roadway improvements.
Study Budget $1,000,000
Const Budget TBD
Total Budget TBD
Study Consultant:Pending Board Approval
General Cont TBD
Owner Rep (CEI)TBD
NTP Design TBD
NTP Const TBD
Sub Completion TBD
Final Completion TBD
47
Strategic Plan
IMMOKALEE ROAD I-75
INTERCHANGE IMPROVEMENTS (NEW PRIORITY)
Current Status 01/2024:
•On January 23, 2024, the BCC discussed that improvements to the I-75
interchange on Immokalee Road should be advanced with funding from the
County.
•The team is working with FDOT for timing and funding requirements.
Stage % Complete
Design Procurement 0%
Design 0%
Construction 0%
District #2,3
Project #TBD
Project Manager Marlene Messam/FDOT
Project Sponsor Transportation Engineering
Scope: Improve traffic conditions on Immokalee Rd by implementing a diverging
diamond design at the I-75 interchange.
Design Budget $ 6M
Const Budget $30M
CEI Budget $ 4M
Total Budget $40M
Arch/Eng:TBD
Owner Rep (CEI)TBD
NTP Design TBD
Design Completion TBD
48
Strategic Plan
PROJECT NAME DEPARTMENT/DIVISION SLIDE #
GOLDEN GATE CITY INFRASTRUCTURE & ECONOMIC DEVELOPMENT MASTER PLAN PUBLIC UTILITIES - SUBREGIONAL UTILITIES 50
GOLDEN GATE CITY TRANSMISSION WATER MAIN IMPROVEMENTS PUBLIC UTILITIES - EPMD 51
NE REGIONAL UTILITY PROGRAM - PHASE I PUBLIC UTILITIES - SUBREGIONAL UTILITIES 52
NE REGIONAL UTILITY PROGRAM - PHASE II PUBLIC UTILITIES - SUBREGIONAL UTILITIES 53
NE REGIONAL UTILITY PROGRAM - TANKS, PUMP STATIONS PUBLIC UTILITIES - SUBREGIONAL UTILITIES 54
NE REGIONAL UTILITY PROGRAM - NE UTILITY FACILITIES PUBLIC UTILITIES - SUBREGIONAL UTILITIES 55
NORTH COLLIER WATER RECLAMATION FACILITY PUBLIC UTILITIES - EPMD 56
SEPTIC TO SEWER CONVERSION - PALM RIVER AREA 4 - RENEWAL PROGRAM PUBLIC UTILITIES - EPMD 57
UTILITY MASTER PLANNING - MASTER PLAN LIBRARY PUBLIC UTILITIES DEPARTMENT 58
WATER RESOURCES
Strategic Plan
NORTHEAST REGIONAL UTILITY PROGRAM
NESA SOUTH WELLFIELD – PHASE I
Next Steps/Current Challenges Updated: 1.11.2024
•Project to install the proposed raw water mains to be constructed in two phases in conjunction with BCIRP
infrastructure development.
Progress
•Phase 1A (southern portion) proposed raw water main included with Facilities Management team’s access road bid.
Bids received on August 7, 2023. Awarded to Quality Enterprises on 11/14/2023.
•Phase 1B (northern portion) proposed raw water main design complete, to be bid with Facilities Management team’s
access road project. Project is anticipated to be bid in early 2024.
•Design of the proposed well sites is at 95% complete. Project is anticipated to be bid in mid/late 2024.
Stage % Complete
Procurement 100%
Design 95%
Construction 0%
Closeout 0%
District #5
Project #70194.8.1.1
Project Manager Craig Pajer, PE; Alicia Abbott, PMP
Project Sponsor Public Utilities Department – Subregional Utilities
Scope: Design and construction of a raw water wellfield consisting of piping,
power, fiber communication, ductbanks, water supply wells, electrical control
buildings and related site improvement.
Design Budget $1,758,436
Const Budget Phase 1: Pipes $12,000,00 Est. + Wells $7,500,000
Total Budget $21,258,436 Est.
Arch/Eng:CDM Smith, Inc.
General Cont Phase 1: Quality Enterprises (pipelines)
Owner Rep (CEI)TBD
NTP Design October 26, 2020
NTP Const Phase 1A: $4,371,556.00
Phase 1B: 2024 Est TBD
Wells: 2025 EST
Sub Completion TBD
Final Completion TBD
Phase 1A – Yellow lines
Phase 1B - Orange line
50
Strategic Plan
GOLDEN GATE CITY INFRASTRUCTURE & ECONOMIC DEV. MASTERPLAN
GOLDEN GATE CITY WWTP 4 MGD EXPANSION
Next Steps/Current Challenges Updated: 1.11.2024
•Finalize SDP
•Submit FDEP permit for construction
Financing
•Collier County is requesting State appropriations for $35,000,000.
Progress
•A deposit of $151,090,000 was made in the District’s bond fund 419 which included $70M for this project.
•Conditional Use approved by Hearing Examiner 10 March 2023.
Stage % Complete
Procurement 0%
Design 95%
Construction 0%
Closeout 0%
District #3
Project #70243
Project Manager Corinne Trtan, PMP
Project Sponsor Public Utilities Department – Subregional Utilities
Scope: Construct 4 MGD capacity at the Golden Gate City WWTP.
Design Budget $2,143,000
Const Budget $140,000,000 Est
Total Budget $142,143,000 Est
Arch/Eng:TetraTech, Inc.
General Cont TBD
Owner Rep (CEI)TBD
NTP Design May 18, 2020
NTP Const Q3 2024 Est
Sub Completion TBD
Final Completion TBD
51
Strategic Plan
WELL TO POTABLE WATER CONVERSION
GOLDEN GATE CITY TRANSMISSION WATER MAIN IMPROVEMENTS
Next Steps/Current Challenges Updated: 2.2.2024
•County Staff held a public meeting for each phase with the Golden Gate City residents to discuss the construction phase
of the Transmission Water Main Improvement projects.
Progress
•Phase 1A – Nearly complete installing WM, FM & IQ mains within golf course.
•Phase 1B – Completed FM installation on Coronado Parkway.
•Phase 2 – Completed several WM directional drills and currently installing WM on 48th Street SW.
•CEI Services for the entire project was awarded by the BCC on March 28, 2023.
Stage % Complete
Procurement 100%
Design 100%
Construction Phase 1A
Construction Phase 1B
Construction Phase 2
68%
9%
31%
District #3
Project #70253
Project Manager Liz Gosselin, E.I.
Project Sponsor Public Utilities Department - EPMD
Scope: Construct new transmission water mains around Golden Gate City and
connect these mains to the regional water system.
Design Budget $1,393,105
Const Budget $27,813,615
Total Budget $29,206,720
Arch/Eng:Johnson Engineering, Inc
General Cont Accurate Drilling Systems, Inc. - Phase 1A
Metro Equipment Service, Inc. - Phase 1B
DBE Utility Services - Phase 2
Owner Rep (CEI)AIM Engineering & Surveying
NTP Design October 12, 2020
NTP Const August 7, 2023 - Phase 1A, October 30, 2023 -
Phase 1B, June 26, 2023 - Phase 2
Sub Completion March 6, 2024 - Phase 1A, May 8, 2025 - Phase 1B,
December 23, 2024 - Phase 2
Final Completion April 5, 2024 - Phase 1A, July 7, 2025 - Phase 1B,
January 22, 2025 - Phase 2
52
Strategic Plan
NORTHEAST REGIONAL UTILITY PROGRAM
NESA PERIMETER WELLFIELD – PHASE II
Current Status: Updated: 1.11.2024
•The BCC approved at the October 24, 2023, meeting the increase of Purchase Order No. 4500207573 to start
designing the next phase of the new NESA wellfields.
Progress:
Design contract was approved by the BCC on September 11, 2020, but required the BCC to approve an increase to the
Purchase Order to begin this new NESA wellfield phase.
Stage % Complete
Procurement 0%
Design 0%
Construction 0%
Closeout 0%
District #5
Project #70194.1
Project Manager Craig Pajer, PE; Alicia Abbott, PMP
Project Sponsor Public Utilities Department – Subregional Utilities
Scope: Design and construction of a raw water wellfield consisting of sixteen
well sites which can include both freshwater and brackish water wells. The
design will include piping, power, fiber communication, ductbanks, water
supply wells, electrical controls and related site improvement. This project is
being executed in conjunction with the proposed regional NECWTP.
Design Budget $2,620,804
Const Budget $55,200,000 Est
Total Budget $57,820,804 Est
Arch/Eng:CDM Smith, Inc.
General Cont TBD
Owner Rep (CEI)TBD
NTP Design January 2024
NTP Const Q3: 2026 EST
Sub Completion TBD
Final Completion TBD
53
Strategic Plan
NORTHEAST REGIONAL UTILITY PROGRAM
NESA INTERIM WWTP, TANKS, PUMP STATIONS & PIPELINES
Next Steps/Current Challenges Updated: 2.2.2024
•Meeting with future developments’ engineers and planners.
•Delay occurred due to treatment plant material availability; however, commitments to developers are not in
jeopardy.
Progress
•Direct Material Purchase Sales Tax Savings: $638,829 on $9+M material purchases
•Planning future well sites for IQ and potable water.
•Finalizing last Brightshore pipe procurement to POC.
•Completed Phases: 1, 2, 4
•Current Construction Phases: 5A, 5B
•Current Startup Phase: 3
Stage % Complete
Procurement 90%
Design 90%
Construction 90%
Closeout 0%
District #5
Project #70194.7
Project Manager Craig Pajer, P.E.
Project Sponsor Public Utilities Department – Subregional Utilities
Scope: Design and construct potable water storage tank and pump station, interim
wastewater treatment plant, Irrigation Quality (IQ) storage tank and IQ pump
station, and potable water, IQ water and wastewater transmission mains.
Neighborhood Information is provided through CollierNESA.com.
Design/Construction
Budget
$78,203,700
Total Budget $78,203,700
Arch/Eng:Johnson Engineering, Inc.
General Cont Mitchell & Stark Construction Co. Inc.
Owner Rep (CEI)CCWSD QA/QC team
NTP Design April 1, 2019
NTP Const April 1, 2019
Sub Completion Q2, 2024 Est
Final Completion Q2, 2024 Est
54
Strategic Plan
NORTHEAST REGIONAL UTILITY PROGRAM
NORTHEAST UTILITY FACILITIES
Next Steps/Current Challenges Updated: 1.11.2024
•NECWTP design update is pending upcoming BCC approval.
•Timing and capacity may be adjusted with AUIR updates.
Progress
•Design updates funded from District’s 2021 bond.
•NECWRF design update kicked-off in 2022.
•DIWs bids received on 12/15/2023. Working with Procurement to finalize contract for BCC approval.
Stage % Complete
Procurement - Design 100%
Design 70%
Construction 0%
Closeout 0%
District #5
Project #70194.2
Project Manager Craig Pajer, P.E.
Project Sponsor Public Utilities Department – Subregional Utilities
Scope: Update 2010 designs for technology. Coordinating design with perimeter
wellfield design update.
Design Budget WRF $ 4,819,950
WTP $ 5,626,190 Est.
DIW $ 1,637,264
Const Budget DIW $ 31,789,000
WRF+WTP: $200,000,000 Est
Total Budget $243,872,404 Est
Arch/Eng:Carollo Engineers
General Cont TBD
Owner Rep (CEI)TBD
NTP Design DIW 9/2020
WRF 1/14/2022
WTP TBD
NTP Const TBD
Sub Completion TBD
Final Completion TBD
55
Strategic Plan
NORTH COUNTY WATER RECLAMATION FACILITY PROJECT
Next Steps/Current Challenges Updated: 1.11.2024
•Stone Columns (Aggregate Pier Soil Reinforcement): Encountered Obstructions during installation. Efforts to
remove obstructions impacted project schedule and will result in change order
•Begin Yard Piping and Foundations
•Challenges include timely manufacture and delivery of long lead procurement items.
Progress
•Site clearing
•Relocated 20” IQ Water Main
•Resolved Stone Column Obstruction issue and completed Ground Stabilization for Headworks Buildings
Project Phase Schedule
Design NTP August 17, 2022
Design 100%
Construction NTP August 28, 2023
Construction Duration 2.5 years
Construction Time Complete 12%
Construction Work Billed/Complete 7%
District #2
Project #70149
Project Manager Wayne Karlovich, P.E.
Project Sponsor Public Utilities Department - EPMD
Scope: Installation of a new pretreatment facility at the North County
Water Reclamation Facility (NCWRF).
Design Budget $14,105,963
Const Budget $55,660,000
Total Budget $69,765,963
Arch/Eng:AECOM
General Cont Poole and Kent
Owner Rep (CEI)CCWSD QA/QC team
CEI Cost NA
Sub Completion January 8, 2026
Final Completion March 9, 2026
56
Strategic Plan
SEPTIC TO SEWER CONVERSION
PALM RIVER AREA 4 PUBLIC UTILITY RENEWAL
Next Steps/Current Challenges Updated: 1.11.2024
•Neighborhood coordination is critical. Meeting was held on December 12, 2023, with property owners to discuss project.
Progress
•Engineer of Record submitted final construction plans and bid documents on December 21, 2023.
•Received grant award and processing a FDEP grant agreement in the amount of $3,000,000 for the septic to sewer
conversion in this area.
•Construction budget based on the engineer’s opinion of probable cost and will change based on the final construction bids.
Stage % Complete
Procurement 90%
Design 100%
Construction 0%
Closeout 0%
District #2
Project #70257
Project Manager Diana Dueri, PMP
Project Sponsor Public Utilities Department - EPMD
Scope: Replace and rehabilitate 50-year-old water system and convert existing
septic tanks to low pressure sewer system for 24 connections, into one
combined project.
Design Budget $369,572
Const Budget $3,605,126 Est
Total Budget $3,974,698 Est
Arch/Eng:Q. Grady Minor
General Cont TBD
Owner Rep (CEI)Stantec Consulting Services Inc.
NTP Design August 2, 2021
NTP Const Est July 2024
Sub Completion Est June 2025
Final Completion Est July 2025
57
Strategic Plan
UTILITY MASTER PLANNING
UTILITY MASTER PLAN LIBRARY
Next Steps/Current Challenges Updated: 1.11.2024
•The Master Plan was last revised in April 2023. Annually, the team evaluates the Collier County Public Utility System – Facilities
Work Plan Library to evaluate the need for updates to existing work plans or new work plans.
Progress
•NCRWTP – Facility work plan scope development initiated.
•SCRWTP – Negotiating contract with consultant.
•NCWRF – Facility work plan scope development initiated.
•SCWRF – Facility work plan scope development initiated.
•Wellfield Plan – Wells are being evaluated in conjunction with the permit renewal process. (CDM Smith, Inc.)
•Water Distribution – Active work order to assist with development of the yearly CIP. (Corollo Engineers, Inc.)
•Wastewater Collection – Active work order to assist with development of the yearly CIP. (Corollo Engineers, Inc.)
Stage % Complete
Procurement TBD
Design TBD
Construction TBD
Closeout TBD
District #All Districts
Project #Various
Project Manager Anthony Stolts, PE
Project Sponsor Public Utilities Department
Scope: Utility Planning
•Raw Water System – Four work plans identified
•Potable Water System – Six work plans identified
•Wastewater System – Four work plans identified
•Irrigation Quality Water System – Three work plans identified
•Supervisory Control and Data Acquisition System
•Supplemental Studies
Total Budget Varies by individual plan/analysis
Arch/Eng:Various (see progress notes)
Final Completion Ongoing
58
Strategic Plan
STORMWATER/UTILITY - PARTNERSHIP PROGRAM
PROJECT NAME DEPARTMENT/DIVISION SLIDE #
STORMWATER UTILITY PARTNERSHIP - PALM RIVER AREAS 1 & 2 RENEWAL PROGRAM
PUBLIC UTILITIES – EPMD &
TRANSPORTATION – CPP 60
STORMWATER UTILITY PARTNERSHIP - NAPLES PARK - 98TH & 99TH AVENUES RENEWAL
PROGRAM
PUBLIC UTILITIES – EPMD &
TRANSPORTATION - CPP 61
STORMWATER UTILITY PARTNERSHIP - NAPLES PARK - 105TH & 106TH AVENUES
RENEWAL PROGRAM
PUBLIC UTILITIES – EPMD &
TRANSPORTATION - CPP 62
STORMWATER UTILITY PARTNERSHIP - OLD LELY - PHASES 7, 8, & 9 RENEWAL PROGRAM
PUBLIC UTILITIES – EPMD &
TRANSPORTATION - CPP 63
WEST GOODLETTE-FRANK JOINT STORMWATER– SEWER PHASE 2 TRANSPORTATION - CPP 64
Strategic Plan
STORMWATER UTILITY PARTNERSHIP PROJECTS
PALM RIVER AREAS 1 & 2 PUBLIC UTILITY RENEWAL PROGRAM
Next Steps/Current Challenges Updated: 1.11.2024
•Neighborhood coordination is critical. Meeting was held on January 25, 2023, with property owners to discuss
project prior to construction commencing.
Progress
•Contractor has completed the installation of the proposed water main & wastewater mains in Area 1.
•Contractor has completed the installation of the proposed storm drainage system on Cypress Way E and Palm River
Blvd in Area 1. Contractor is finishing the installation of the storm drainage system on Golfview Drive.
•Contractor is working on the roadway and right of way restoration in Area 1.
•Contractor has completed the installation of the proposed water main in Area 2.
Stage % Complete
Procurement 100%
Design 100%
Construction 52%
Closeout 0%
District #2
Project #70257
Project Manager Diana Dueri, PMP
Project Sponsor Public Utilities Department – EPMD & Transportation -
CPP
Scope: Replace and rehabilitate 50-year-old water, wastewater and stormwater
infrastructure into one combined project.
Design Budget $1,544,305
Const Budget $15,579,339
Total Budget $17,123,645
Arch/Eng:Q. Grady Minor
General Cont Haskins, Inc.
Owner Rep (CEI)Stantec Consulting Services Inc.
NTP Design August 2, 2021
NTP Const March 13, 2023
Sub Completion June 12, 2024
Final Completion July 12, 2024
60
Strategic Plan
STORMWATER UTILITY PARTNERSHIP PROJECTS
NAPLES PARK 98TH & 99TH AVENUES PUBLIC UTILITY RENEWAL PROGRAM
Next Steps/Current Challenges Updated: 2.2.2024
•Neighborhood coordination is critical. Meeting was held on September 28, 2023, with property owners to discuss
project prior to construction commencing.
Progress
•Contractor commenced construction of this project in January 2024. Contractor is planning to first construct all the
proposed water main improvements and then start the wastewater/stormwater improvements one each block after
completing the water main improvements.
Stage % Complete
Procurement 100%
Design 100%
Construction 0%
Closeout 0%
District #2
Project #70120
Project Manager Diana Dueri, PMP
Project Sponsor Public Utilities Department – EPMD & Transportation -
CPP
Scope: Replace and rehabilitate 50-year-old water, wastewater and stormwater
infrastructure into one combined project.
Design Budget $702,830.00
Const Budget $17,862,085
Total Budget $18,564,915
Arch/Eng:Q. Grady Minor
General Cont Douglas N Higgins, Inc.
Owner Rep (CEI)Stantec Consulting Services Inc.
NTP Design July 27, 2021
NTP Const December 12, 2023
Sub Completion May 17, 2025
Final Completion July 16, 2025
61
Strategic Plan
STORMWATER UTILITY PARTNERSHIP PROJECTS
NAPLES PARK 105TH & 106TH AVENUES PUBLIC UTILITY RENEWAL PROGRAM
Next Steps/Current Challenges Updated: 1.11.2024
•Neighborhood coordination is critical. Meeting was held on November 16, 2022, with property owners to discuss
project prior to construction commencing.
Progress
•The Contractor has completed all the proposed water main improvements on both avenues.
•The Contractor has completed the proposed wastewater and storm drainage improvements on the 500, 600, and 700
blocks of both avenues.
•The Contractor is currently working on the wastewater and storm drainage improvements on the 800 block of both
avenues.
Stage % Complete
Procurement 100%
Design 100%
Construction 73%
Closeout 0%
District #2
Project #70120
Project Manager Diana Dueri, PMP
Project Sponsor Public Utilities Department – EPMD &
Transportation - CPP
Scope: Replace and rehabilitate 50-year-old water, wastewater and
stormwater infrastructure into one combined project.
Design Budget $702,830
Const Budget $16,806,410
Total Budget $17,509,240
Arch/Eng:Q. Grady Minor
General Cont Douglas N Higgins, Inc.
Owner Rep (CEI)Stantec Consulting Services Inc.
NTP Design July 27, 2021
NTP Const January 2, 2023
Sub Completion March 11, 2024
Final Completion April 10, 2024
62
Strategic Plan
STORMWATER UTILITY PARTNERSHIP PROJECTS
OLD LELY – PHASES 7, 8, & 9 PUBLIC UTILITY RENEWAL PROGRAM
Next Steps/Current Challenges Updated: 1.11.2024
•Neighborhood coordination is critical.
Progress
•The Consultant has completed Task 1, Preliminary Engineering which included the Final Preliminary Engineering Report
and the 30% construction plans for the entire project.
•BCC approved at their 8/8/2023 meeting to increase Consultant’s PO to complete the design services for Phases 7, 8,
and 9.
•Consultant currently working on preparing the 60% construction plans for Phases 7, 8, and 9.
Stage % Complete
Procurement 100%
Design 30%
Construction 0%
Closeout 0%
District #1
Project #60224
Project Manager Lis Carrasquel, PE
Project Sponsor Public Utilities Department – EPMD &
Transportation - CPP
Scope: Replace and rehabilitate 60-year-old water, wastewater and
stormwater infrastructure into one combined project.
Design Budget $6,424,266
Const Budget TBD
Total Budget TBD
Arch/Eng:Johnson Engineering
General Cont TBD
Owner Rep (CEI)TBD
NTP Design October 16, 2023
NTP Const TBD
Sub Completion TBD
Final Completion TBD
63
Strategic Plan
WEST GOODLETTE-FRANK
JOINT STORMWATER– SEWER PHASE 2
Next Steps/Current Challenges
•The City of Naples has received $500K for this fiscal year and a $10M State grant
•Stormwater met with the City of Naples for coordination purposes, at this time it is the City’s intent to issue one
solicitation, with a phased approach to construction.
•Costs continue to escalate, with the stormwater portion estimated to be $31M, a funding source is required.
Progress
•Stormwater continues to remain in communication with the City of Naples to determine solicitation schedule
(FY2025) and anticipated construction start date (late 2025)
Stage % Complete
Procurement 100%
Design PI 60%, P2 60%, P3 10%
Construction 0%
Closeout 0%
District #4
Project #60142.6
Project Manager Mark Zordan
Project Sponsor Transportation Management Services
Scope: Scope: A joint project with the City of Naples to replace septic systems
with sanitary sewer within the City’s Unsewered Areas 1, 2, 3 and 6 and correct
street and yard flooding issues between US-41 and Goodlette-Frank Road from
Pine Ridge Road to Cypress Woods Drive plus Creech Road.
Project #1: $26,199,000 (Stormwater: $9,679,167)
Project #2: $29,953,000 (Stormwater: $10,969,670)
Project #3: $27,304,000 (Stormwater: $10,327,500)
Design Budget $1.30M
Const Budget $31M
Total Budget $TBD
Arch/Eng:$83.4M
General Cont Grady Minor/Johnson Engineering
Owner Rep (CEI)TBD
NTP Design April 2021
NTP Const FY2025
Sub Completion TBD
Final Completion TBD
64
Strategic Plan
ASSET MANAGEMENT PROGRAMS
DEPARTMENT/DIVISION SLIDE #
PUBLIC UTILITIES DEPARTMENT 66
TRANSPORTATION MANAGEMENT SERVICES DEPARTMENT 67
FACILITIES MANAGEMENT DIVISON 68
PUBLIC SERVICES DEPARTMENT 69
Strategic Plan
WATER & SEWER DISTRICT
ASSET MANAGEMENT PROGRAM
Next Steps/Current Challenges Updated: 1.11.2024
•Phase 1-4 Continued quarterly maintenance of GIS based asset rating system:
•Red: Level 3 - RISKED COMPLIANCE – There is a high risk of non-compliance with consent orders being issued. The
reliability of the utility system and the level of service is in danger of being compromised with full-scale migration
toward costly break-down maintenance, resulting in customer service outages, service interruptions, SSOs (spills),
back-ups and property damage.
•Yellow: Level 2 - MANAGED COMPLIANCE – There is a risk of potential non-compliance with enforcement letters
being issued. The level of service is sustained through deferred planned maintenance, asset management and
mitigation measures based on the resources available.
•Green: Level 1 - SUSTAINED COMPLIANCE – There is little risk of non-compliance. Generally, maintenance is routine
and planned. The County is providing reliable and full service to customers that is sustained quality-compliant
wastewater , water, and solid/hazardous waste services 24/7/365, with no consent orders, no back-ups, no SSOs
(spills), no off-site odor emissions, and no off-site noise emissions.
•Phase 5 - Finalization and Implementation of Enterprise System– Future Forecasting/Budgeting
Project Phase Schedule
Phase 1-4 Complete
Phase 5 Target FY26
Perpetual Improvement Process On-Going
District #All Districts
Project #Fund 4008
Project Manager Patrick Thir, Manager
Project Sponsor Public Utilities Department
Vision:Geographic Information System (GIS)-centric Integrated
Asset Management System including a computerized
maintenance management system (Cityworks) with
graphical user interface capable of collecting data
automatically through existing SCADA systems, with the last
phase being financial integration into enterprise systems
including SAP.
Mission:Repair/maintain assets just in time through a GIS-based
system having full operational visibility.
Establish risked-based and managed preventative
maintenance programs with full visibility of assets for
resource optimization.
Provide short and long term Capital Improvement Plans
(CIP) integrated into the master plan and the AUIR based on
level of risk and service levels.
Guiding
Principles:
Sustained safe and reliable delivery of Public Utilities
Division Services; Revenue-centric, cost-contained approach
to operations and CIPs; Full asset visibility and preservation;
Sustainable logistic support functions; Follow discipline-
specific taxonomy
66
Strategic Plan
TRANSPORTATION MANAGEMENT SERVICES
ASSET MANAGEMENT PROGRAM
Next Steps/Opportunities
•Dedicated and centralized data quality program primarily focused on TMSD assets and infrastructure
•Refining asset collection and work management platform to better align with the current TMSD objectives
•TMSD Performance Management Scorecard
•Refining land and land rights GIS dataset
Project Phase Schedule
Pavement Rating (OCI) Update Target FY25
System Maintenance & Updates On-Going
District #All Districts
Project #60037
Project Manager Darren Hutton
Project Sponsor Operations & Performance Management Division
Vision:Utilize Cartegraph OMS software with ArcGIS
(Geographic Information System) to map assets with
spatial analysis and update in real time; build maps and
visual representations of data; track asset condition,
work history, and cost data; create assignments and
complete tasks to extend the life of assets; and leverage
powerful analytic tools to guide overall decision-making
and budget spend.
Mission:-Manage and maintain assets with full operational
visibility.
-Establish preventative maintenance programs for
resource optimization.
-Provide short and long-term Capital Improvement
Plans (CIP) integrated into the master plan and the
AUIR
Guiding Principles:-Full asset visibility and preservation
-Proper allocation of funds to create, maintain, and
extend the life of the assets
-Quality assurance and quality control of data
-Development of division SMEs (subject matter
experts)
67
Strategic Plan
Next Steps/Current Challenges Updated: 1/8/2024
•Completion of PM/Inspection program – FY24
•Asset data collection and cataloging through the completion of the Master Space Plan and Utilization for County
Facilities initiative
•Physical Evaluations of Exteriors and Sites – FY25
•Structural, Internal, & MEP – FY26
Progress
•System Live, Phase 1 – 11/1/2022
•Catalog asset data and forecast replacement costs/schedule – 14,000+ Assets
•Work order management – 26,000 Yearly WOs
•Develop framework for preventative maintenance(PM)/inspection program – 700+ PMs
•ArcGIS and 311 integration
•Inventory Management – 55,000+ inventoried items
•Reporting module
Stage % Complete
Phase 1 – Go Live 100%
Phase 2 – Closeout 40%
District #All
Project #N/A
Project Manager Olga Grie, Senior Analyst
James Williams, Assistant Division Director
Project Sponsor Facilities Management
Scope: Adopt an Asset Management System (Cartegraph) with user capability to:
•Catalog asset data and forecast replacement costs/schedule
•Manage maintenance work orders through mobile application
•Develop preventative maintenance(PM)/inspection program
•ArcGIS and 311 integration
•Inventory Management
•Reporting module
Total Budget $93,388 Yearly
Owner Rep (CEI)N/A
Implementation
Completion
November 1, 2022 – Asset Management, Work Order
Management, PM/Inspections Tracking, ArcGIS,
Inventory Management, Reporting
Final Completion FY24 – Completion of PM/Inspection program
FY26 – Final Asset Management data collection and
cataloging contingent on completion of Master Space
Plan
FACILITIES MANAGEMENT
ASSET MANAGEMENT PROGRAM
68
Strategic Plan
PUBLIC SERVICES DEPARTMENT
ASSET MANAGEMENT PROGRAM
Next Steps/Current Challenges Updated: 1/25/2024
•Parks & Recreation currently using CityWorks for park specific asset management.
•Cartograph is utilized by Facilities Management for vertical structure assest management and Transportation for its
asset management requirements.
•All Divisions annually perform the Clerk’s Annual Inventory Report identifying assets as New, Good, or Poor.
•Stand-up PSD Team to catalog data and forecast replacement costs/schedule for remaining PSD Divisions: Library,
Museum, Domestic Animal Services, University Extension, Community & Human Services, Health Dept.
•Evaluate remaining on CityWorks, or transition to the Cartograph platform to align software platforms with
Facilities Management and Transportation.
Project Phase Schedule
Parks & Recreation Complete
Library, Museum, Domestic Animal Services,
University Ext., Community & Human Services,
Health Dept.
TBD
District #All Districts
Project #N/A
Project Manager PSD Division Directors
Project Sponsor Public Services Department
Scope:
•Parks & Recreation completed migration to PUD CityWorks system in
2017 allowing them to:
•Manage maintenance work orders through mobile application
•Develop preventative maintenance (PM)/inspection program
•Total Inventory Management
•Access real-time reporting module
•Expand asset management program to other PSD Divisions
Total Budget $75,000 Yearly (Parks ONLY-Cost Share w/ PUD)
Owner Rep (CEI)N/A
Implementation
Completion
PARKS: 2017– Asset management migration to
CityWorks platform
All other PSD Divisions: TBD
Final Completion TBD
69