Agenda 12/12/2023 Item #16B18 (Accept December 2023 Project Update for Post-Ian Inland Waterway Debris Removal)12/12/2023 EXECUTIVE SUMMARY Recommendation to accept the December 2023 Project Update for Post -Ian Inland Waterway Debris Removal. (Project 33852) OBJECTIVE: To keep the Board informed on major capital improvement projects. CONSIDERATIONS: On April 11, 2023, the Board of County Commissioners provided an after-the-fact approval for the submittal of a Watershed Protection Program grant application to the United States Department of Agriculture, Natural Resources Conservation Service (NRCS). The purpose of this grant-funded project is to remove storm-related debris deposited after Hurricane Ian within inland waterways, maintain an appropriate stormwater conveyance system and provide an adequate flood protection level of service. A summary of the estimated expenses are shown below: Estimated Debris Removal Expenses** Estimated Match** Estimated Local Funds** Estimated Total** Construction $7,142,400.00 $2,380,800.00 $9,523,200.00 Technical Assistance $761,856.00 $33,877.95 $795,733.95 Total $10,318,933.95 **Estimates based on vendor proposal. Actual amounts will be determined as work is completed. Construction activities are being conducted by CrowderGulf Joint Venture, Inc (Contract 15 -6365), and the technical services are being provided by Tetra Tech, Inc (Contract 17-7116). Approved areas for debris removal were determined to be: • Gordon River • Henderson Creek and tributary • Rock Creek • Coco Palm Horse • Haldeman Kelly Work has begun and as of Nov. 17th approximately 60% of the targeted debris has been removed from the Gordon River, 14% from Rock Creek and 45% from Henderson Creek. The total cubic yards collected to date are 6,235. FISCAL IMPACT: The total estimated project cost is $10,318,934. Funding has been previously appropriated and is available within Growth Management Grant Fund (1841) and Growth Management Grant Match Fund (1842), Project 33852. A small portion in the amount of $33,878 is not covered by the NRCS grant program due to exhaustion of the technical assistance allowance and is funded through Disaster Fund (1813), Project 50280 as this cost may become eligible for reimbursement under the Federal Emergency Management Agency (FEMA) Public Assistance Program. GROWTH MANAGEMENT IMPACT: The project is in conformance with the goals and objectives of the Growth Management Plan and is consistent with the objectives of the strategic plan to maintain and provide infrastructure and asset management. LEGAL CONSIDERATIONS: This item has been reviewed by the County Attorney, is approved as to form and legality, and requires majority vote for Board approval. -JAK RECOMMENDATION: Recommendation to accept the December 2023 Project Update for Post -Ian Inland Waterway Debris Removal. (Project 33852) 16.B.18 Packet Pg. 1638 12/12/2023 Prepared by: Daniel Roman, P.E., Project Manager Supervisor, Capital Project Planning, Impact Fees and Transportation Management Division ATTACHMENT(S) 1. 33852 Post-Ian Inland Waterway (PPTX) 16.B.18 Packet Pg. 1639 12/12/2023 COLLIER COUNTY Board of County Commissioners Item Number: 16.B.18 Doc ID: 27317 Item Summary: Recommendation to accept the December 2023 Project Update for Post Ian Inland Waterway Debris Removal. (Project 33852) (Daniel Roman, Supervisor Project Management) Meeting Date: 12/12/2023 Prepared by: Title: – Capital Project Planning, Impact Fees, and Program Management Name: Raquel Ovares 11/21/2023 4:02 PM Submitted by: Title: Division Director - Capital Proj Plan, Impact Fees – Capital Project Planning, Impact Fees, and Program Management Name: Beth Johnssen 11/21/2023 4:02 PM Approved By: Review: Transportation Management Services Department Jeanne Marcella Transportation Management Services Department Completed 11/29/2023 3:25 PM Transportation Management Operations Support Michelle DAndrea Additional Reviewer Completed 11/29/2023 3:40 PM Capital Project Planning, Impact Fees, and Program Management Beth Johnssen Additional Reviewer Completed 11/29/2023 3:48 PM Road Maintenance Ellen Sheffey Additional Reviewer Completed 11/29/2023 3:58 PM Transportation Management Operations Support Brandy Otero Additional Reviewer Completed 11/29/2023 4:30 PM Growth Management Community Development Department Lisa Taylor Additional Reviewer Completed 11/30/2023 6:27 AM County Attorney's Office Scott Teach Level 2 Attorney Review Completed 11/30/2023 8:54 AM Transportation Management Services Department Trinity Scott Transportation Completed 12/04/2023 4:50 PM Grants Erica Robinson Level 2 Grants Review Completed 12/04/2023 4:53 PM Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 12/05/2023 8:36 AM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 12/05/2023 8:50 AM Grants Therese Stanley Additional Reviewer Completed 12/06/2023 9:05 AM Community & Human Services Maggie Lopez Additional Reviewer Completed 12/06/2023 10:57 AM County Manager's Office Amy Patterson Level 4 County Manager Review Completed 12/06/2023 12:26 PM Board of County Commissioners Geoffrey Willig Meeting Pending 12/12/2023 9:00 AM 16.B.18 Packet Pg. 1640 Project Manager:Pawel Brzeski Project Description:This project will address the existence of storm related debris in Collier County waterways due to Hurricane Ian and to maintain an appropriate conveyance system for an adequate flood protection level of service. Current Phase: Construction Construction Contractor: Crowder Gulf Joint Venture, Inc. Construction: $12.1 million CEI: Te tra Tech, Inc. Revised: 12/05/2023 1 33852 Post-Ian Inland Waterway Debris Removal Project Phase Anticipated Schedule Construction Start 10/18/2023 Construction Duration 150 Final Completion 03/16/2024 Wo rk Complete 24% Current Status 12/04/2023: 4-week look ahead: •Finish Gordon River and Henderson Creek in early December •Finish Rock Creek mid-December •Start debris removal on Haldeman Creek and Cocohatchee River in late December for January completion Location Quantity (CY) Gordon River (5,000 CY)3,021.30 Rock Creek (10,500 CY)1,474.20 Henderson Creek (2,000 CY)1,739.15 Palm River/ Cocohatchee (4,500 CY) 0 Haldeman Creek (3,600 CY)0 Total 6,234.65 Rock Creek area Gordon River area Henderson Creek area Haldeman Creek area Palm River/ Cocohatchee area 16.B.18.a Packet Pg. 1641 Attachment: 33852 Post-Ian Inland Waterway (27317 : Recommendation to accept the December 23 33852 Post-Ian Inland Waterway Debris Removal 12/6/2023 2 16.B.18.a Packet Pg. 1642 Attachment: 33852 Post-Ian Inland Waterway (27317 : Recommendation to accept the December 23 33852 Post-Ian Inland Waterway Debris Removal 12/6/2023 3 16.B.18.a Packet Pg. 1643 Attachment: 33852 Post-Ian Inland Waterway (27317 : Recommendation to accept the December 23 33852 Post-Ian Inland Waterway Debris Removal Debris Removal 12/6/2023 4 Gordon River –Near Naples Zoo 16.B.18.a Packet Pg. 1644 Attachment: 33852 Post-Ian Inland Waterway (27317 : Recommendation to accept the December 23 33852 Post-Ian Inland Waterway Debris Removal 12/6/2023 5 Debris Removal 16.B.18.a Packet Pg. 1645 Attachment: 33852 Post-Ian Inland Waterway (27317 : Recommendation to accept the December 23 33852 Post-Ian Inland Waterway Debris Removal 12/6/2023 6 Pre-Wo rk Assessment Post-Wo rk Assessment Gordon River 16.B.18.a Packet Pg. 1646 Attachment: 33852 Post-Ian Inland Waterway (27317 : Recommendation to accept the December 23 33852 Post-Ian Inland Waterway Debris Removal 12/6/2023 7 Pre-Wo rk Assessment Post-Wo rk Assessment Gordon River 16.B.18.a Packet Pg. 1647 Attachment: 33852 Post-Ian Inland Waterway (27317 : Recommendation to accept the December 23 33852 Post-Ian Inland Waterway Debris Removal 12/6/2023 8 16.B.18.a Packet Pg. 1648 Attachment: 33852 Post-Ian Inland Waterway (27317 : Recommendation to accept the December 23 The Po st Ian Debris Clearing project has removed over 6,000 cubic yards from our secondary canal system, enough to fill approx imately 2 Olympic-sized swimming pools. By the completion of this project,it is expected to remove over 24,600 CY of debris,enough to fill 7.5 Olympic-sized swimming pools. 16.B.18.a Packet Pg. 1649 Attachment: 33852 Post-Ian Inland Waterway (27317 : Recommendation to accept the December 23