Agenda 11/14/2023 Item #16C 4 (Change Order #1 for a 45 day extension w/Accurate Drilling Systems, Inc.)11/14/2023 EXECUTIVE SUMMARY Recommendation to approve Change Order No. 1, authorizing the use of the owner’s allowance in the amount of $70,751.75 and providing for a time extension of 45 days under Construction Agreement No. 23 - 8058, with Accurate Drilling Systems, Inc., for the “Golden Gate City Transmission Water Main Improvements - Phase 1A - Golf Course” project, and authorize the Chairman to sign the attached Change Order. (Project No. 70253) OBJECTIVE: To approve Change Order No. 1 authorizing the use of the owner’s allowance in the amount of $70,751.75 and providing for a 45-day extension of time to complete the Golden Gate City Transmission Water Main Improvements - Phase 1A - Golf Course by constructing a new transmission potable water system, and to provide potable water, wastewater, and irrigation quality service connections to the new golf course and future developments within the Golden Gate City Golf Course. CONSIDERATIONS: On March 28, 2023 (Agenda Item No. 11.A), the Board awarded Construction Agreement No. 23-8058 (the “Agreement”) to Accurate Drilling Systems, Inc. (see Attachment 1). This project provides for the construction of a 24-inch transmission water main, 12-inch distribution water main, 6-inch & 8-inch force main, and a 10-inch irrigation quality main traveling through the golf course in Golden Gate City. Change Order No. 1 also authorizes the use of the owner’s allowance in the amount of $70,751.75 to install various force main stops, and provides for a 45-day time extension to the Agreement to account for the delays associated with additional unforeseen work to install force main double line stops to connect the 8-inch new force main being installed through the golf course to the existing 14-inch force main on 44th Street SW and replacing the existing inoperable valves with new valves on the connected force mains. County Staff is recommending that the Board approve the attached Change Order No. 1 (see Attachment 2). FISCAL IMPACT: There is no fiscal impact associated with the Change Order #1. GROWTH MANAGEMENT IMPACT: There is no impact to the current Growth Management Plan standards to ensure the adequacy and availability of viable public facilities. LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for Board approval. -SRT RECOMMENDATION: That the Board approve Change Order No. 1, allowing for the use of the owner’s allowance in the amount of $70,751.75 and providing for a time extension of 45 days under Construction Agreement No. 23-8058, with Accurate Drilling Systems, Inc., for the “Golden Gate City Transmission Water Main Improvements - Phase 1 A - Golf Course” project, and authorize the Chairman to sign the attached change order. Prepared By: Liz Gosselin, Project Manager II, Public Utilities Engineering and Project Management Division ATTACHMENT(S) 1. [Linked] #23-8058 (Accurate Drilling Systems, Inc.) Executed (PDF) 2. CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (PDF) 3. Backup for CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (PDF) 16.C.4 Packet Pg. 829 11/14/2023 COLLIER COUNTY Board of County Commissioners Item Number: 16.C.4 Doc ID: 27084 Item Summary: Recommendation to approve Change Order No. 1, authorizing the use of the owner’s allowance in the amount of $70,751.75 and providing for a time extension under Construction Agreement No. 23-8058, with Accurate Drilling Systems, Inc., for the Golden Gate City Transmission Water Main Improvements – Phase 1A – Golf Course project. (Project No. 70253) Meeting Date: 11/14/2023 Prepared by: Title: Associate Project Manager – Engineering and Project Management Name: Liz Gosselin 10/27/2023 11:40 AM Submitted by: Title: Director – Engineering and Project Management Name: Matthew McLean 10/27/2023 11:40 AM Approved By: Review: Public Services Department Todd Henry Level 1 Department Review Skipped 10/27/2023 11:47 AM Engineering and Project Management Benjamin Bullert Additional Reviewer Completed 10/27/2023 12:50 PM Wastewater Robert Von Holle Additional Reviewer Completed 10/27/2023 2:18 PM Water Howard Brogdon Additional Reviewer Completed 10/27/2023 2:25 PM Engineering and Project Management Craig Pajer Additional Reviewer Completed 10/27/2023 2:41 PM Engineering and Project Management Matthew McLean Additional Reviewer Completed 10/27/2023 4:21 PM Public Utilities Department Mary Linhard Additional Reviewer Completed 10/30/2023 9:26 AM Public Utilities Operations Support Joseph Bellone Additional Reviewer Completed 10/30/2023 12:35 PM Procurement Services Vanessa Miguel Level 1 Purchasing Gatekeeper Completed 10/30/2023 1:01 PM Procurement Services Heather Yilmaz Additional Reviewer Completed 10/30/2023 3:13 PM Procurement Services Sue Zimmerman Additional Reviewer Completed 10/30/2023 11:28 PM Public Utilities Department Joseph Bellone Level 2 Division Administrator Review Completed 10/31/2023 7:22 AM County Attorney's Office Scott Teach Level 2 Attorney Review Completed 10/31/2023 10:14 AM Procurement Services Sandra Herrera Procurement Director Review Completed 10/31/2023 4:06 PM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 11/01/2023 9:18 AM Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 11/01/2023 9:39 AM Corporate Compliance and Continuous Improvement Megan Gaillard Additional Reviewer Completed 11/01/2023 7:27 PM Community & Human Services Maggie Lopez Additional Reviewer Completed 11/03/2023 1:55 PM County Manager's Office Amanda Barnwell Level 4 County Manager Review Completed 11/06/2023 10:43 AM 16.C.4 Packet Pg. 830 11/14/2023 Board of County Commissioners Geoffrey Willig Meeting Pending 11/14/2023 9:00 AM 16.C.4 Packet Pg. 831 16.C.4.b Packet Pg. 832 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 833 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 834 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 835 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 836 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 837 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 838 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 839 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 840 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 841 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 842 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 843 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 844 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 845 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 846 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 847 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 848 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 849 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 850 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 851 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) 16.C.4.b Packet Pg. 852 Attachment: CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (CAO) (27084 : CO#1 GGC Transmission Water Main Ph-1) From: Mario E. Acevedo <ace@accuratedrilling.com> Sent: Friday, October 27, 2023 8:31 AM To: Matthew McLean; Liz Gosselin; 'Mike Dickey'; Benjamin Bullert; Heather Yilmaz Cc: civil.pe.schmidt@gmail.com Subject: Re: Change Order #1 - 14" Force Main Connection - PO4500224424 - Contract #23-8058 EXTERNAL EMAIL: This email is from an external source. Confirm this is a trusted sender and use extreme caution when opening attachments or clicking links. No issues Thank you Get Outlook for iOS From: Matthew McLean <Matthew.McLean@colliercountyfl.gov> Sent: Friday, October 27, 2023 8:15:40 AM To: Liz Gosselin <Liz.Gosselin@colliercountyfl.gov>; Mario E. Acevedo <ace@accuratedrilling.com>; 'Mike Dickey' <MSD@johnsoneng.com>; Benjamin Bullert <Benjamin.Bullert@colliercountyfl.gov>; Heather Yilmaz <Heather.Yilmaz@colliercountyfl.gov> Cc: civil.pe.schmidt@gmail.com <civil.pe.schmidt@gmail.com> Subject: RE: Change Order #1 - 14" Force Main Connection - PO4500224424 - Contract #23-8058 Great Qa/Qc. No issues from my side. Respectfully, Matt McLean, P.E. Division Director Collier County Public Utilities Department Engineering & Project Management Division “Continuous Improvement” Matthew.McLean@colliercountyfl.gov 3339 Tamiami Trail East, Suite 303 Naples, FL 34112 239-252-6213 Office 239-571-2448 Cell “HOW ARE WE DOING?” Please click here for our Customer Service Survey 16.C.4.c Packet Pg. 853 Attachment: Backup for CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (27084 : CO#1 GGC Transmission Water Main Ph-1) From: Liz Gosselin <Liz.Gosselin@colliercountyfl.gov> Sent: Thursday, October 26, 2023 6:18 PM To: 'Mario E. Acevedo' <ace@accuratedrilling.com>; 'Mike Dickey' <MSD@johnsoneng.com>; Benjamin Bullert <Benjamin.Bullert@colliercountyfl.gov>; Matthew McLean <Matthew.McLean@colliercountyfl.gov>; Heather Yilmaz <Heather.Yilmaz@colliercountyfl.gov> Cc: civil.pe.schmidt@gmail.com Subject: Change Order #1 - 14" Force Main Connection - PO4500224424 - Contract #23-8058 All- Minor modifications were done to the change order. Please refer to pages 1 thru 5 of the PFD doc attached. If you have any questions, please let me know. Respectfully, Liz Gosselin Project Manager II Public Utilities Department Engineering and Project Management Division “Continuous Improvement” 3339 Tamiami Trail East | Suite 303 | Naples, FL 34112 Office: (239) 252-1037 Cell: (239) 380-4617 E-mail: Liz.Gosselin@colliercountyfl.gov “HOW ARE WE DOING?” Please click here for our Customer Service Survey Under Florida Law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by telephone or in writing. 16.C.4.c Packet Pg. 854 Attachment: Backup for CO#1 - PO4500224424 - ADS - GGC TWM Ph1A (27084 : CO#1 GGC Transmission Water Main Ph-1)