Agenda 07/11/2023 Item #16F8 (Change Order No. 1 by adding 58 days to the Main Campus Chiller Plant Upgrades)16.F.8 07/ 11 /2023 EXECUTIVE SUMMARY Recommendation to approve Change Order No. 1 adding fifty-eight (58) days to Agreement No. 21-7883-ST (CMAR), Main Campus Chiller Plant Upgrades, with O-A-K/Florida, Inc. d/b/a Owen -Ames -Kimball Company and authorize the Chairman to sign the attached change order. (Projects 50214 and 50189) OBJECTIVE: To provide a fifty-eight (58) day time extension relative to pre -construction services for the Main Campus Chiller Plant project under a Construction Manager at Risk (CMAR) agreement with O-A-K/Florida, Inc. d/b/a Owen -Ames -Kimball Company. CONSIDERATIONS: On May 10, 2022, the Board awarded Agreement No. 21-7883-ST (the "Agreement") to the top -ranked firm, O-A-K/Florida, Inc. d/b/a Owen -Ames -Kimball Company ("O-A-K"), for a CMAR agreement for the Main Campus Upgrades (Agenda Item No. 16.C.4). A CMAR is a project delivery method that entails a commitment by the Construction Manager to deliver a project within a Guaranteed Maximum Price ("GMP"), which is based on the construction documents and specifications at the time the GMP is determined, plus any inferred items or tasks. On May 24, 2022, the County issued a Notice to Proceed to O-A-K/Florida, Inc, and a final completion date for the pre -construction services by March 18, 2023. On November 15, 2022, a stop work letter was issued for this project. On March 16, 2023, the project was reactivated leaving 123 days remaining on contract and ultimately extending the final completion date to July 17, 2023. On September 28, 2022, Hurricane Ian made landfall near Fort Myers, Florida. This event caused a delay of the change order that was in process to add additional time to amend the design for the New Chiller Plant Building K project, the main component of the Main Campus Upgrades. On November 17, 2022, staff issued the change order for the New Chiller Plant, Building K project. The by-product of that change order required an extension of the time needed for pre -construction services. A change order to the Agreement with O-A-K is necessary to add additional time for pre -construction services to accommodate for the development of the GMP for construction services. FISCAL IMPACT: There is no new fiscal impact associated with this Executive Summary. Funding is available in the Infrastructure Sales Tax, Fund (3018), Projects 50214 and 50189. GROWTH MANAGEMENT IMPACT: There is no impact to the Growth Management Plan associated with this Executive Summary. LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for Board approval. -SRT RECOMMENDATION: To approve Change Order No.l, adding fifty-eight (58) days for Agreement No. 21- 7883-ST, Main Campus Chiller Plant Upgrades, with O-A-K/Florida, Inc. d/b/a Owen -Ames -Kimball Company, and authorize the Chairman to sign the attached change order. (Projects 50214 and 50189) Prepared by: Tim Rygiel, PMP, CFM., Project Manager II, Facilities Management Division ATTACHMENT(S) 1. Agreement No. 21-7883-ST with O-A-KFlorida, Inc (PDF) 2. Change Order 1(PDF) Packet Pg. 1231 16.F.8 07/11/2023 COLLIER COUNTY Board of County Commissioners Item Number: 16.17.8 Doe ID: 25839 Item Summary: Recommendation to approve Change Order No. 1 adding fifty-eight (58) days to Agreement No. 21-7883-ST (CMAR), Main Campus Chiller Plant Upgrades, with O-A-K/Florida, Inc. d/b/a Owen -Ames -Kimball Company and authorize the Chairman to sign the attached change order. (Projects 50214 and 50189) Meeting Date: 07/11/2023 Prepared by: Title: Operations Analyst, Senior — Facilities Management Name: Bendisa Marku 06/12/2023 3:34 PM Submitted by: Title: — Facilities Management Name: John McCormick 06/12/2023 3:34 PM Approved By: Review: Facilities Management John McCormick Director - Facilities Facilities Management Tim Rygiel Additional Reviewer Procurement Services Ana Reynoso Level 1 Purchasing Gatekeeper Facilities Management Jennifer Belpedio Manager - Real Property Procurement Services Sue Zimmerman Additional Reviewer Procurement Services Heather Yilmaz Additional Reviewer Procurement Services Sandra Herrera Procurement Director Review County Attorney's Office Scott Teach Level 2 Attorney Review Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Community & Human Services Maggie Lopez Additional Reviewer County Manager's Office Ed Finn Level 4 County Manager Review Board of County Commissioners Geoffrey Willig Meeting Pending Completed 06/12/2023 3:46 PM Completed 06/12/2023 3:47 PM Completed 06/13/2023 10:21 AM Completed 06/13/2023 10:39 AM Completed 06/16/2023 3:55 PM Completed 06/19/2023 9:10 AM Completed 06/20/2023 8:39 AM Completed 06/22/2023 3:38 PM Completed 06/23/2023 8:33 AM Completed 06/23/2023 9:08 AM Completed 06/27/2023 8:18 AM Completed 07/05/2023 4:50 PM 07/11/2023 9:00 AM Packet Pg. 1232 1 6.F.8.b Col -r County Procurement Services Change Order Form ® Contract Modification F-1 Work order Modification Contract #: 21-7883-5T Change M = Purchase Order #: 4500217988 ^ � Project #: 50214.1 COntractorlFlrm Name: O-A-KIFlorida, Inc. Contract/Project:l swain Campus Upgrades (MCU) Project Manager Name: Tim Rygiei-PMP, CFM, Projecl Division Name, Manager ll Facilities Management Original Contract/Work Order Amount $ 70,595,00 5/10/22 16C4 Original BCC Approval Date; Agenda Item 4 Current BCC Approved Amount $ 70,595.00 5110/22 1GC4 Last BCC Approval Date; Agenda Item 4 Current Contract/Work Order Amount �$ 70,595.00 7/17/2021 SAP Contract Expiration Date (Master) Dollar Amount of this Change $ 0.00 0.00% Total Change front Original Amount Revised Contract/Work Order Total $ 70,595.00 0.00% Change from Current BCC Approved Amount Cumulaiiva Chan es $ 0.00 0,00% Chan e from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Notice to Proceed 5124/2022 Original 311 BI2023 Fast Approved 7117I2023 Revised Date 9/13/2023 Date Completion Date Date (Includes this change) # of Days Added '8 select Tasks ❑ Add new task(s) ❑ Delete task(s) ❑ Change task(s) ® Other Provide a response to the following: 1,) detalled and specific explanatlonlratlonale of the requested changes) to the task(s) and 1 or the additional days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the Impact If this change is not processed. Attach additional infonnalion from the Design Professional andlor Contractor if needed. 1,) This chango order will add 58 days to the contract time in order to accommodate the extra time needed to develop [fie GMP. 2.) The additional time is needed to align with the design schedule which experienced delays due to Hurricane Ian. 3.) If this change order Is not processed, the vendor will he unable to fulfill their contract obligations for delivery of a GMP Ry i8lTi mothy Digitally signed by Rygieffinlothy Prepared by, Bate; 2023.05.31 09:58:06-04'00' Date: Tim Rygiei-PMP, CFM, Project Manager il, Facilities Management Acceptance of this Change Order shall constitute a modification to contract 1 work order identified above and will be subject to all the same terms and conditions as contained in the contract 1 work order Indicated above, as fully as If the same were stated In this acceptance, The adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor / Vendor / Consultant l Design Professional arising out of or related to the change set forth herein, including claims for impact and delay costs, Accepted lorida, Inc. McCormiekJohn Digitally signed by McCormickJohn Approved by; Date: 2023.06,05 13:42:12-04'00' John McCormick, Interim Director, Facilities Management YiimazHeather Digitally signed by YilmazHeather Aby. Date; 2023.06.08 12:36:25-04'00' pproved (Procurement Professional) Revised: 01114021 (Divisions who may require additional sign -alums may Include on separate sheet.) Date; y' Date: Date: PROCI}r{EMENTSJSE ONLY Armin Rp� BCC ES iN Packet Pg. 1233 16.F.8.b ATTEST: Crystal K. Kinzel, Clerk of Courts & Comptroller Im Dated: (SEAL) Approved as to form and legality: Im Scott R. Teach Deputy County Attorney BOARD OF COUNTY COMMISSIONERS COLLIER COUNTY, FLORIDA Im Rick LoCastro, Chairman 0?4 a CXO Packet Pg. 1234 1 6.F.8.b Change Order/Amendment Summary CO# AMn# Description COST TIME - Justification Additive (F) Doducttve (-) Days Added New Amount 1 Adds 58 days 58 356 This change is to accommodate extra time needed for OAK to develop the GMP, Thelr schedule is dependent on the design schedule and the design schedule has been amended. Revised: 01114/2021 (Divisions who may require additional signatures may indUde on separate sheet.) L d L O M .i PROCUREMENT USE 014LY� Admin BCC E8 Rp! Packet Pg. 1235