Agenda 05/09/2023 Item #16C 2 (Change Order #1 for time extension of 150 days for Contract #19-7622 pump station 302.25)16.C.2 05/09/2023 EXECUTIVE SUMMARY Recommendation to ratify and approve Change Order No. 1, providing for a 150-day time extension and $9,887.37 draw on owner's allowance under Request for Quotation No. 19-7622-302.25 with U.S. Water Services Corporation under Agreement No. 19-7622, for the Pump Station 302.25 Rehabilitation project, and authorize the Chairman to sign the attached Change Order. (Project No. 70145) OBJECTIVE: To approve Change Order No. 1, providing for a 150-day time extension and allowance draw under Request for Quotation No. 19-7622-302.25 with U.S. Water Services Corporation under Agreement No. 19-7622, for the Pump Station 302.25 Rehabilitation project, to maintain the reliability and sustainability of the wastewater collections system. CONSIDERATIONS: The proposed scope of work under Project No. 70145, "Pump Station 302.25 Rehabilitation," is consistent with funding in the Board's FY2021 Capital Improvement Project Budget approved on September 17, 2020 (the "Project"). On July 13, 2021 (Agenda Item No. 16.C.8), the Board awarded Request for Quotation No. 19-7622-302.25 US Water Services Corporation, for the Pump Station 302.25 Rehabilitation. The Project consists of civil site work, underground utility work, electrical components, and mechanical process piping work. The work includes the installation of all piping, valves, wet well coating and other material or component necessary to place the pump station into service. The confined space valve vault will be eliminated by moving piping and appurtenances above grade. In accordance with Collier County utility standards, this project provides connectivity at Pump Station 302.25 for a standby diesel generator for operational power resiliency. Material supply chain issues have impacted the manufacturer and resultant delivery schedule of the generator. Attached proposed Change Order No. 1 (See Attachment 1) provides for a 150-day time extension and draw on the owner's allowance under Request for Quotation No. 19-7622-302.25 to account for the delay in generator acquisition. Approval of this Change Order will extend the current Substantial and Final Completion dates accordingly. FISCAL IMPACT: There is no fiscal impact associated with this executive summary as the owner's allowance is included in the original work order and the allowance draw for Change Order No. 1 is part of the allowance. GROWTH MANAGEMENT IMPACT: There is no impact to the current Growth Management Plan standards to ensure the adequacy and availability of viable public facilities. LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for Board approval. -SRT RECOMMENDATION: That the Board approve Change Order No. 1, providing for a 150-day time extension and a $9,887.37 draw on the owner's allowance draw under Request for Quotation No. 19-7622-302.25 with U.S. Water Services Corporation under Agreement No. 19-7622, for the Pump Station 302.25 Rehabilitation project, and authorize the Chairman to sign the attached Change Order. (Project No. 70145). Prepared by: Corinne Trtan, Project Manager 11, Subregional Utilities Division ATTACHMENT(S) 1. CO#1 (PDF) Packet Pg. 690 16.C.2 05/09/2023 COLLIER COUNTY Board of County Commissioners Item Number: 16.C.2 Doe ID: 25342 Item Summary: Recommendation to ratify and approve Change Order No. 1, providing for a 150-day time extension and $9,887.37 draw on owner's allowance under Request for Quotation No. 19-7622-302.25 with US Water Services Corporation under agreement 19-7622, for the Pump Station 302.25 Rehabilitation project, and authorize the Chairman to sign the attached Change Order. (Project No. 70145) Meeting Date: 05/09/2023 Prepared by: Title: Project Manager, Senior — Engineering and Project Management Name: Wayne Karlovich 04/20/2023 3:11 PM Submitted by: Title: Subregional Utilities Director — Engineering and Project Management Name: Craig Pajer 04/20/2023 3:11 PM Approved By: Review: Procurement Services Ana Reynoso Level 1 Purchasing Gatekeeper Procurement Services Priscilla Doria Additional Reviewer Procurement Services Sue Zimmerman Additional Reviewer Engineering and Project Management Corinne Trtan Additional Reviewer Engineering and Project Management Matthew McLean Additional Reviewer Corporate Compliance and Continuous Improvement Megan Gaillard Engineering and Project Management Craig Pajer Additional Reviewer Public Utilities Department Drew Cody Level 1 Division Reviewer Public Utilities Department Drew Cody Level 2 Division Administrator Review Procurement Services Sandra Herrera Procurement Director Review County Attorney's Office Scott Teach Level 2 Attorney Review Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Community & Human Services Maggie Lopez Additional Reviewer Corporate Compliance and Continuous Improvement Megan Gaillard County Manager's Office Dan Rodriguez Level 4 County Manager Review Board of County Commissioners Geoffrey Willig Meeting Pending Completed 04/20/2023 3:17 PM Completed 04/21/2023 1:39 PM Completed 04/24/2023 9:22 AM Completed 04/25/2023 4:05 PM Completed 04/27/2023 2:31 PM Additional Reviewer Completed 04/27/2023 8:23 PM Completed 04/28/2023 9:56 AM Completed 04/28/2023 12:49 PM Skipped 04/28/2023 12:49 PM Completed 05/01/2023 8:39 AM Completed 05/01/2023 10:07 AM Completed 05/01/2023 10:09 AM Completed 05/01/2023 11:24 AM Completed 05/01/2023 1:31 PM Additional Reviewer Completed 05/01/2023 1:51 PM Completed 05/01/2023 2:37 PM 05/09/2023 9:00 AM Packet Pg. 691 16.C.2.a . I 0 Procurement Services Change Order Form ® Contract Modification ❑ Work Order Modification 19-7622- �� 450021257d p #: 70145.3.1 Contract M 302.25 hange #: 1 Purchase Order #: t Pump Station 302.25 Rehabilitation Contractor/Firm Name: US Water Services Corporation Contraict/Project: Project Manager Name: Corinne Trtan Division Name: Public Utilities Sub -regional Utilities Original Contract/Work Order Amount $ 435,105.01 7/13/2021;16C8 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 435,105.01 7/13/2021;16C8 Last BCC Approval Date; Agenda Item # Current ContracVWork Order Amount $ 435,105.01 4/27/2024 SAP Contract Epiration Date (Master) Dollar Amount of this Change $ 0.00 0.00% Total Change from Original Amount Revised Contract/Work Order Total S 435,105.01 0.00% Change from Current BCC Approved Amount Cumulative Changes S 0.0D 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Notice to Proceed 4/13/2022 Original 10/10l2022 Last Approved 10/10/2022 Revised Date Date Completion Date Date {Includes this Change) # of Days Added 150 Select Tasks ❑ Add new task(s) ❑ Delete task(s) ❑ Change task(s) ® Other Provide a response to the following: 1.) detailed and specific explanationlrationale of the requested change(s) to the task(s) and / or the additional days added (if requested); 2.) why this change was not Included in the original contract; and, 3.) describe the impact If this change Is not processed. Attach additional information from the Design Professional and/or Contractor if needed. This contract is currently on a stop work order with 38 days remaining (8 days prior to substantial completion}. Days added (time extensions) for this project, and all future time added to this project, move the substantial completion along with the final completion. This change order is adding an additional 150 days to the substantial and final contract time for the procurement and delivery of the pump station generator. Currently, generators are backordered and the estimate is 1.5 years for delivery. Our generator was ordered in February 2022. The current delivery date estimate is April 2023. WDA This work directive is an allowance draw. The contractor was required to order and install an additional wet well riser ring due to unforeseen conditions discovered during the demolition of the existing wet well top in preparation for the new top slab. When the Contractor began to excavate and remove the existing top slab it was discovered that the existing top portion of the wet well had been constructed using bricks and mortar. It was determined that the designed wet well riser would not allow the top slab of the station to meet the 100 year flood elevation requirement. In order to meet the 100 year flood elevation per the County and FDEP requirements an additional 9-inch riser is required. If this change is not processed, the pump station will not meet the County and FDEP requirement for the top slab elevation to be at the 100 year flood elevation. This Change is to use $6,295.00. This Change DOES NOT increase the contract amount. A?", Revised: 01J14r2021 (Divisions who may require additional signatures may inciude on separate sheet.) 03022023 PROCUrWMNT USE ONLY Adain BCC Es Packet Pg. 692 16. C.2.a WD#2 1. This work directive is an allowance draw. The purpose of this work directive is to direct the contractor to install a new 4-inch plug valve on the existing 4-inch force main due to the existing 4-inch plug valve determined to being inoperable. 2. When the contractor began rehabilitation efforts on the pump station it was proposed that a new 6-inch force main would tie into the existing 4-inch force main and ultimately tie into the existing 30-inch force main within the county ROW. The existing 4-inch plug valve was believed to be operable during design, but was deterimined during construction to be inoperable. in order to provide flexibility in isolating 11", 302.25 and/or flow in the County's wastewater collection system, the inoperable existing 4-inch plug valve needs to be replaced. 3. If this change is not processed, the County's Wastewater Collection Division will not be able to isolate PS 302.25 and/or the flow in the County's wastewater collections system. This Change is to use $3.595.37 from the project allowance. This Change DOES NOT increase the contract amount. Beginning General Allowance $ 20,000.00 Allowance Draw WD# I $ (6,295.00) Allowance Draw WD#2 $ (3,595.37) Remaining General Allowance $ 10,109.63 A Pmpaared by: (Project Manager Nar Caun.nc 74zrA.*v Division) rit,-Cll �diz"Wr Date: 61i/ Acceptance of this Change Order shall constitute a modification to contract i work order identified above and will be subject to all the same terms and conditions as contained in the contract i work order indicated above, as fully as if the same were stated in this acceptance. The adjustment, if any, to the Contract shall constitut a full and final settlement of any and all claims of the Contractor / Vendor' Consultant I Design ProfessislFOM brising out of or ►ated t o change set forth herein, including claims for impact and delay costs. Accepted by: Accepted Approved by: USWC, Edward Mitchell, VP Date: _ 3/Rl2Q2_-_ I Design Professional and Name of Firm, if project applicable) Alexander Dunko, P.E. - Project Manager Date: 3/3/2023._...__. (0esign Professional and Name of Firm, if project applicable) Pa j e rC ra i g Digitally signed by PajerCraig Date: 2023.04.05 1 101.-04'00' Date: 9 (Division Director or Designee) Do ri a P ri se i I I a Digitally signed by DoriaPriscilla Date: 2023.04.05 12:30:47-04'00' Approved by: -- — (Procurement Professional) Revised: ov1412021 (bivislans who may require additional signatures may include on separate sheet.) Date: 03022023 yPROCUR USE ONLY -- AGM► sCC BCC ES RM Packet Pg. 693 16.C.2.a ATTEST: Crystal K. Kinzel, Clerk of Courts & Comptroller M. Dated: (SEAL) Approve as to form and legality: By: Scott R. Teach Deputy County Attorney BOARD OF COUNTY COMMISSIONERS COLLIER COUNTY, FLORIDA Rick LoCastro, Chairman Packet Pg. 694 16.C.2.a Change Order/Amendment Summary COO AMDO Description COST TIME dtistiftcation - Additive N Deductive (-? Days Added New Amount 1 Allowance draw ; time addition 150 330 County and FDEP Code compliance; collections system operations Revised: 01/1412021 (Divisions who may require additional signatures may include on separate sheet.) 03022023 USE ONLY ApROCUREMM ecc ecc V Packet Pg. 695 16.C.2.a Collier County Engineering & Proiect Management Division WORK DIRECTIVE CHANGE CONTRACT # /PROJECT NAME: # 19-7622-302 25 Pump Station 302.25 Rehabilitation PURCHASE ORDER #: 4500212570 OWNER: Collier Count% Board of Commissioners CONTRACTOR: U.S. Water Services Corporation WORK DIRECTIVE # 1 DATE OF ISSUANCE: May 2, 2022 PROJECT#: 70145.3.1 ENGINEER/DESIGN PROFESSIONAL: Q. Grady Minor & Associates. P.A. You are directed to proceed promptly with the following change(s): Detailed and specific explanation/rationale of the requested change(s) to the task(s) and / or the additional dal added (iif'requested): The Change is requested to alloy% the Contractor to install an additional wet well riser ring due to unforeseen conditions discovered during the demolition of the existing wet well top in preparation for the new top slab. Whv this change was not included in the original contract: When the Contractor began to excavate and remo%e the existing top slab it was discovered that the existing top portion of the wet well had been constructed using bricks and mortar. It was determined that the designed wet well riser would not allow the top slab of the station to meet the 100 year flood elevation requirement. In order to meet the 100 year flood elevation per the County and FDEP requirements an additional 9-inch riser is required. Describe the impact if this change is not processed: If this change is not processed. the pump station will not meet the County and FDEP requirement for the top slab elevation to be at the 100 year flood elevation. Attachments: PS 302.25 IFT Riser Proposal.pdf If a claim is made that the above changc(s) ha%e affected Contract/Allowance Price or Contract Times am claim for a Change Order based thereon will involve one or more of the following methods of determining the effect of the changes(s). Method of determining change in Contract/Allowance Price: ❑ Unit Prices ® Lump Sum ❑ Time & Material ❑ Other (see attached Bid Schedule) Estimated decrease in Allowance: $ 6.283.00 REC E DF.D: B}: Alexander Dunko. PE Project Manager Method of determining change in Contract Times: ❑ Contractor's records ❑ Engineer's record ❑ Other Estimated change in Contract Time: Increase or decrease by 0 calendar days. AUJH Rl7ED: By: Corinne Trtan Owner's Representative Ct a^ P► O Packet Pg. 696 Draft Invoice S165962 16.C.2.a U.S. water January 31, 2023 External Document No. 4500212570 Page 1 / 1 Collier County BOCC 3299 Tamiami Trail East, Suite 700 Attn: Accounts Payable Naples, FL 34112-5749 U.S. WATER SERVICES CORPORATION 4939 CROSS BAYOU BOULEVARD NEW PORT RICHEY, FL 34652 O Your Reference Payment Terms Shipment Method U Net 30 days o :r Job Number: J01269 WA: 19-7622-302.25 = c� Job Description: Collier County BOCC Change Order #1 LO N N O M Unit Price Line Amount Excl. Date Description Task No. Qty Unit Excl. Tax Tax .r rn 09/13/22 IET Lid (with 15% mark-up) 0002 1 EA 5,175.00 5,175.00 09/13/22 Maintenance Technician 0002 16 EA 70.00 1,120.00 a N CF M LO Subtotal 6,295.00 v Total Tax 0.00 O Total $ Incl. Tax 6,295.00 v c m E s m r Q Toll Free Phone No. Email (866) 753-8292 Ext. 219 (727) 848-8292 Ext. 219 ar@uswatercorp.net Packet Pg. 697 16.C.2.a Paints & Coatings, Inc. 17660 East Street North Fort Myers, FL 33917 US (239) 997-6645 carl@paintsandcoatings.net www.paintsandcoatings.net BILL TO U.S. Water Services Corporation 5605 2nd St. W. Lehigh Acres, FL 33971 PROJECT NAME Collier PS 302.25 C�ova.ti'ng �� � fThi Finst in 11'.�,trwuter $Ini:turr Krhubilililion"� / rJ liLL4ivt Applicrtun Of Irr CONFINED Provide Certified Confined Space Permit 100.00 SPACE PERMIT RH-IET-Coating Lift Station 61D Approx. 1 VVF Blast & coat with IET 8,478.00 RH-Invert Structural rebuild invert/channel 1,500.00 RH-Water Leaks Inspect, Repair water leaks & supply material to fix leaks 1,300.00 RH-IET-Crete Form & pour 1' riser with IET-Crete 4,500.00 Crane Services Set lid with crane on lift station We appreciate your business and look forward to helping you SUBTOTAL 15,878.00 again soon. TAX 0.00 Please, make checks payable to: Paints & Coatings, Inc. TOTAL 15,878.00 Item in Red Box is in relation to Work Directive #1 52005 15,878.00 J012690002 M3 CC 5/13 10% late charge on balances outstanding more than 30 days from date of invoice. This company complies with any and or all lien laws per Florida Statutes. This contract is entered into in Lee County and all disputes arising from this contract will be litigated in Lee County. Buyer agrees to pay outside agency/attorney's fees if this contract is referred for collection/litigation. O U _ 0 Z s a� N N N 0 M _ .2 a E a N M N r O c.� d E t a J P%j Packet Pg. 698 16.C.2.a Collier County Engineering & Project Management Division WORK DIRECTIVE CHANGE CONTRACT # /PROJECT NAME: WORK DIRECTIVE # 2 #19-7622-302.25 Pump Station 302.25 Rehabilitation PURCHASE ORDER #: 4500212570 DATE OF ISSUANCE: May 2, 2022 OWNER: Collier County Board of Commissioners PROJECT#: 70145.3.1 CONTRACTOR: U.S. Water Services Corporation ENGINEER/DESIGN PROFESSIONAL: Q. Grady Minor & Associates, P.A. You are directed to proceed promptly with the following change(s): Detailed and specific explanation/rationale of the requested change(s) to the task(s) and , or the additional days added (if requested): The Change is requested to allow the Contractor to install a new 4-inch plug valve on the existing 4-inch force main due to the existing 4-inch plug valve determined to being inoperable. Why this change was not included in the original contract: When the Contractor began rehabilitation efforts on the pump station it was proposed that a new 6-inch force main would tie into the existing 4-inch force main and ultimately tie into the existing 30-inch fierce main within the County ROW. The existing 4-inch plug valve was believed to be operable during design. but was determined during construction to be inoperable. In order to provide Flexibility in isolating PS 302?5 and/or flow in the County's wastewater collection system. the inoperable existing 4-inch plug valve needs to he replaced. Describe the impact if this change is not processed: If this change is not processed. the County's Wastewater Collection Division w ill not be able to isolate PS 302.25 and/or the flow in the Countv's wastewater collection system. Attachments: Contractor's proposal tier 4-inch plus: valve installation If a claim is made that the above change(s) have affected Contract/Allowance Price or Contract Times am claim for a Change Order based thereon will involve one or more of the following methods of determining the effect of the changes(s). Method of determining change in Contract/Allowance Price: ❑ Unit Prices ❑ Lump Sum ® Time & Material ❑ Other (see attached Bid Schedule) Estimated decrease in Allowance: $ TBD RECOMMENDED: By: Alex Dunko. PE Project Manager Method of determining change in Contract "Limes: ❑ Contractor's records ❑ Engineer's record ❑ Other Estimated chance in Contract Time: Increase or decrease by 0 calendar days. T OYILED: By: Corinne Trtan Owner's Representative Q 0 Packet Pg. 699 Draft Invoice S165170 16.C.2.a U.S��Wate January 12, 2023 External Document No. 4500212570 Page 1 / 1 Collier County BOCC 3299 Tamiami Trail East, Suite 700 Attn: Accounts Payable Naples, FL 34112-5749 U.S. WATER SERVICES CORPORATION 4939 CROSS BAYOU BOULEVARD NEW PORT RICHEY, FL 34652 r O Your Reference Payment Terms Shipment Method U Net 30 days o Job Number: J01269 WA: 19-7622-302.25 = Job Description: Collier County BOCC Change Order #2 (N N O M Unit Price Line Amount Excl. _ O Date Description Task No. Qty Unit Excl. Tax Tax ' P U) 09/13/22 4" PV & MJ fittings (with 15% mark-up + 0002 1 EA 2,551.57 2,551.57 E tax) a 09/13/22 Project Manager 0002 1 EA 123.80 123.80 M u7 09/13/22 Maintenance Supervisor 0002 4 EA 90.00 360.00 V 09/13/22 Maintenance Technician 0002 8 EA 70.00 560.00 r O 0 C) c Subtotal 3,595.37 E Total Tax 0.00 Total $ Incl. Tax 3,595.37 a Toll Free Phone No. Email (866) 753-8292 Ext. 219 (727) 848-8292 Ext. 219 ar@uswatercorp.net Packet Pg. 700 16. C.2.a FORTUNE � SALES ORDER ACKNOWLEDGEMENT 11/18/22 WATERWORKS 5889314 10:48:29 REMIT TO: • 009 PAYMENT: FORTILINE FORT MYERS FORTILINE FORT MYERS PO BOX 744053 4810 LAREDO AVE ATLANTA, GA 30384-4053 FORT MYERS, FL 33905 phone k 239 332 0112 • • • SHIP TO:INSTRUCTIONS: US WATER S=RVICES CCF.FDRATIDN US WATER SERVICFS CORPORATION 5605 2ND STREET W 5605 2ND STREET W LEHIGH ACRES, FL 33971 LEHIGH ACRES, FL 33971 CUSTOMER•• JOBNAME JOB # CSR SLS ORDER DATE SHIPPING METHOD ORIG ORDER # 0 GET SHOP2 SHOP2 NES PSP 11/18/22 OUR TRUCK 0000000 V DESCRIPTIONLINE ITEMj • •'• • UNIT PRICE DISCOUNTO r r 001 4MPV 4" MJ PLUG VLV EA 1 1 0 1295.0000 1295.00 011980 Y14 s d 002 64MRP401 6"X4" MJ REDUCER P401 C153 EA 1 1 0 426.7500 426.75 272694 04 N W06 002 001 Cj 0 003 461SLLD 461S SCREW VB DOM LESS LID EA 1 1 0 145.0000 145.00 C) 308404 r- Y04 O :r 004 VBLICSD 5-1/4 VB LID M/SEWER DOMESTIC EA 1 1 0 37.3300 37.33 O U) 011817 Q Y04 E 005 44000P 4" SG PVC REST W/ACC 4000P EA 2 2 0 70.4000 140.80 d 395057 W03 002 001 / W03 002 003 N F/C900 4.80 OD M 006 43000P 4" STAR GRIP DIP W/ACC 3000P EA 1 1 0 63.8500 63.85 N 242209 v W03 002 002 / W02 002 005 O U c a> E t v i R +r r Q .------------- -------- -- -- Am eh—em er desereoa"cies —mica W s utder most be mooned within 2�. he:. 2,108.73 126.53 .00 2,235.26 ------------------- Packet Pg. 701