Agenda 05/09/2023 Item #16A12 (Golden Gate & Gordon River Stormwater Improvemnets Projects)05/09/2023 EXECUTIVE SUMMARY Recommendation to authorize the necessary budget amendment to reallocate funds from Stormwater Bond Fund 327 reserves to Golden Gate and Gordon River Stormwater Improvement projects in the total amount of $4,000,000. OBJECTIVE: To meet critical project needs and stormwater management objectives within the Collier County Stormwater Management System and authorize the necessary budget amendment. CONSIDERATIONS: These funds will be used by Collier County Stormwater Management Division for Construction services for the below stormwater capital improvement projects: Golden Gate Area Stormwater Improvements: A multi -year initiative consisting of replacing aged stormwater infrastructure within the Golden Gate City limits. Over 147 outfalls and associated conveyance systems are nearing their end -of -life asset cycle and are being rehabilitated or replaced. Toucan Alley Stormwater Improvements - this flood control project re-establishes stormwater conveyance from Golden Gate Parkway and Toucan Alley for eventual discharge into the Golden Gate canal system. The design is complete, and a budget amendment is needed to issue a purchase order using the Underground Contractor Services under contract 20-7800. Golden Gate Parkway Stormwater Improvements - this project will re-establish stormwater conveyance from Golden Gate Parkway and 55t' St SW for eventual discharge into the Golden Gate canal system. The design is complete, and a budget amendment is needed to issue a purchase order using the Underground Contractor Services under contract 20-7800. 25t' Ave Stormwater Improvements - this project will replace the pipe and outfalls between 25t' Place SW and 25t' Ave SW within Golden Gate City. The design is complete, and a budget amendment is needed to issue a purchase order using the Underground Contractor Services under contract 20-7800. Upper Gordon River Stormwater Improvements: These projects are identified within the Gordon River Improvements Master Plan. Upper Gordon River Pump Station North - This pump station provides controlled discharge into the Gordon River drainage system, allowing for retention and flood control when necessary. The design is complete, and a budget amendment is needed to issue a purchase order using the Underground Contractor Services under contract 20-7800. Upper Gordon River Pump Station South - This pump station, discharging into the Solana Road stormwater ditch system, provides for water quality improvements via retention and flood protection when necessary. The design is complete, and a budget amendment is needed to issue a purchase order using the Underground Contractor Services under contract 20-7800. Burning Tree Drive Stormwater Conveyance Improvements - This project upsizes existing aging infrastructure and provides improved flood protection. The design is complete, and a budget amendment is needed to issue a purchase order using the Underground Contractor Services under contract 20-7800. Packet Pg. 366 16.A.12 05/09/2023 FISCAL IMPACT: A budget amendment in the amount of $4,000,000 is required to transfer funds from Stormwater Bond Fund (327) Reserves to the following listed projects: Project No. Project Name Amount 51029 Toucan Alley Stormwater Improvements $875,000 51029 Golden Gate Parkway Stormwater Improvements $875,000 51029 25' Ave SW Stormwater Improvements $450,000 60102 Upper Gordon River Pump Station North $475,000 60102 Upper Gordon River Pump Station South $475,000 60102 Burning Tree Stormwater Conveyance Improvements $850,000 Total $4,000,000 GROWTH MANAGEMENT IMPACT: This action is consistent with the Stormwater Management Sub - Element of the Collier County Growth Management Plan. LEGAL CONSIDERATIONS: This item has been reviewed by the County Attorney, raises no legal issues, and requires majority vote for approval. -JAK RECOMMENDATION: To authorize the necessary budget amendment to reallocate funds from Stormwater Bond Fund 327 reserves to Golden Gate and Gordon River Stormwater Improvement projects in the total amount of $4,000,000. Prepared by: Daniel Roman, PE, Project Management Supervisor, Capital Project Planning, Impact Fees, and Program Management Packet Pg. 367 16.A.12 05/09/2023 COLLIER COUNTY Board of County Commissioners Item Number: 16.A.12 Doe ID: 25277 Item Summary: Recommendation to authorize the necessary budget amendments to reallocate funds from Stormwater Bond Fund 327 reserves to Golden Gate and Gordon River Stormwater Improvements projects in the total amount of $4,000,000 Meeting Date: 05/09/2023 Prepared by: Title: — Capital Project Planning, Impact Fees, and Program Management Name: Brittany Lazo 04/18/2023 1:39 PM Submitted by: Title: Division Director - Capital Proj Plan, Impact Fees — Capital Project Planning, Impact Fees, and Program Management Name: Beth Johnssen 04/18/2023 1:39 PM Approved By: Review: Capital Project Planning, Impact Fees, and Program Management Jessica Arencibia Capital Project Planning, Impact Fees, and Program Management Daniel Roman Capital Project Planning, Impact Fees, and Program Management Beth Johnssen Growth Management and Community Development Department Jeanne Marcella Department Transportation Management Services Department Trinity Scott Office of Management and Budget Community & Human Services County Attorney's Office County Manager's Office Board of County Commissioners Debra Windsor Level 3 OMB Gatekeeper Review Maggie Lopez Additional Reviewer Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Geoffrey Willig Level 4 County Manager Review Geoffrey Willig Meeting Pending Additional Reviewer Completed 04/18/2023 3:00 PM Additional Reviewer Completed 04/19/2023 2:26 PM Additional Reviewer Completed 04/19/2023 5:13 PM Transportation Management Services Completed 04/21/2023 3:11 PM Transportation Completed 04/21/2023 3:25 PM Completed 04/24/2023 8:45 AM Completed 04/24/2023 10:28 AM Completed 04/28/2023 9:57 AM Completed 05/01/2023 11:28 AM 05/09/2023 9:00 AM Packet Pg. 368