Agenda 04/11/2023 Item #16C11 (Change Order No. 1 to obtain additional funding for engineering and design services for two Collier County Emergency Medical Services Stations)04/11/2023
EXECUTIVE SUMMARY
Recommendation to approve administrative Change Order No. 1 to Purchase Order 4500217564 for an
additional $9,320 to investigate an alternative site under Agreement No. 20-7753 with Schenkel & Shultz,
Inc., for Design Services for North Naples EMS Station (Project No. 55213.1).
OBJECTIVE: To obtain additional funding for engineering and design services for two new Collier County
Emergency Medical Services ("EMS") Stations as part of the Emergency Medical Services expansion program
outlined in the Annual Inventory Report ("AIUR").
CONSIDERATIONS: Golden Gate Estates EMS Station 74 and Old 41/North Naples EMS Station 412 are
included in Emergency Medical Services AUIR growth plan. The AUIR identified the need for new stations at
these locations to address growth and development within each of the coverage areas. Generally, for every 16,900
increase in population, EMS adds a station in order to maintain the adopted level of service for the County of 8
minutes or less in the urban area and 12 minutes or less in the rural area 90% of the time. Collier County EMS and
the Facilities Management Division intend to collaborate with the local Fire Districts to explore partnership and co -
location agreements for both future stations, which may include a cost sharing component for their construction.
Proposed Change Order No. I will add $9,320 to Agreement No. 20-7753 (the "Agreement") for additional services
required to investigate alternative sites and a shared agency building configuration as requested by the project
sponsors (EMS & the North Collier Fire Control and Rescue District). The change being requested was not
included in the Agreement because the possible availability of alternate sites and the opportunity for a shared
agency building were not known to the project sponsors at the time the Board awarded the Agreement.
The County's Procurement Services Division administratively approved the Change Order on March 7, 2023, as
authorized by Collier County Procurement Ordinance No. 2013-69, as amended, at Section Nineteen, Contract
Administration, subsection 3.b.
FISCAL IMPACT: Funding in the amount of $9,320 for the EMS North Naples Project is available in the
Infrastructure Sales Tax Fund (318), Project (55213).
GROWTH MANAGEMENT IMPACT: There is no impact to the current Growth Management Plan standards
to ensure the adequacy and availability of viable public facilities.
LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for
Board approval. -SRT
RECOMMENDATION: That the Board approve administrative Change Order No.1 to Purchase Order
4500217564 for an additional $9,320 under Agreement No. 20-7753 with Schenkel & Shultz, Inc., for Design
Services for North Naples EMS Station.
Prepared by: Olivier Sureau, Project Manager, Facilities Management Division
ATTACHMENT(S)
1. 4500217564—CO#1—Schenkel&Schultz (North Naples EMS Station) [Approved] (PDF)
I Packet Pg. 1012
04/11/2023
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.C. I I
Doe ID: 24744
Item Summary: Recommendation to approve administrative Change Order No. I to Purchase Order 4500217564
for an additional $9,320 to investigate an alternative site under Agreement No. 20-7753 with Schenkel & Shultz,
Inc., for Design Services for North Naples EMS Station (Project No. 55213. 1).
Meeting Date: 04/11/2023
Prepared by:
Title: Operations Analyst, Senior — Facilities Management
Name: Bendisa Marku
03/08/2023 4:27 PM
Submitted by:
Title: — Facilities Management
Name: John McCormick
03/08/2023 4:27 PM
Approved By:
Review:
Facilities Management
John McCormick
Director - Facilities
Procurement Services
Ana Reynoso
Level 1 Purchasing Gatekeeper
Facilities Management
Jennifer Belpedio
Manager - Real Property
Facilities Management
Olivier Sureau
Additional Reviewer
Procurement Services
Priscilla Doria
Additional Reviewer
Procurement Services
Sue Zimmerman
Additional Reviewer
Public Utilities Department
Drew Cody
Level 1 Division Reviewer
County Attorney's Office
Scott Teach
Level 2 Attorney Review
Procurement Services
Sandra Herrera
Additional Reviewer
Public Utilities Department
George Yilmaz
Level 2 Division Administrator Review
Office of Management and Budget
Debra Windsor
Level 3 OMB Gatekeeper Review
County Attorney's Office
Jeffrey A. Klatzkow Level 3 County Attorney's Office Review
Community & Human Services
Maggie Lopez
Additional Reviewer
Office of Management and Budget
Susan Usher
Additional Reviewer
County Manager's Office
Amy Patterson
Level 4 County Manager Review
Board of County Commissioners
Geoffrey Willig
Meeting Pending
Completed
03/08/2023 4:37 PM
Completed
03/08/2023 5:59 PM
Completed
03/09/2023 11:14 AM
Completed
03/09/2023 3:14 PM
Completed
03/23/2023 9:45 AM
Completed
03/23/2023 10:19 AM
Completed
03/27/2023 10:26 AM
Completed
03/27/2023 11:41 AM
Completed
03/29/2023 8:47 AM
Completed
03/30/2023 10:37 AM
Completed
03/30/2023 10:41 AM
Completed
03/30/2023 4:27 PM
Completed
04/03/2023 8:48 AM
Completed
04/03/2023 3:32 PM
Completed
04/05/2023 4:13 PM
04/11/2023 9:00 AM
I Packet Pg. 1013 1
Corley County
Procurement Services
Change Order Form
0 Contract Modification n Work Order Modification
Contract #: 20-7753 Change #:[1 urchase Order#: 1 4500217564 Project #: 1 55213.1
1 .......... 1.
Contractor/Firm Name: FS CHENKEL & SHULTZ INC Contract/Project: Design Services for CC EMS Stations (Nort S)
Olivier Sureau Facilities Management
Project Manager Name] Bivislon Nan, . __ I
Original Contract/Work Order Amount
$
258,911.00
03/23/21; 16C7
Original BCC Approval Date; Agenda Item #
Current BCC Approved Amount
$
258,911.0
03/23/2 1; 16C7
Last BCC Approval Date; Agenda Item #
Current Contract/Work Order Amount
$
258,911.00
5/7/2024
SAP Contract Expiration Date (Master).
Dollar Amount of this Change
$
9,320.00
3.60%
Total Change from Original Amount
Revised Contract/Work Order Total
$
268,231.0011
3.60%
Change from Current BCC Approved Amount
Cumulative Chanaes
$
9.320 001
1 3.61
Chanoe from Current Amount
Completion Date, Description of the Task(s) Change, and Rationale for the Change
Notice to Proceed Original Last Approve Revised Date
Date Completion Date Date (Includes this chang
# of Days Added Select Tasks E] Add new task(s) EJ Delete task(s) [I Change task(s) E Other
Provide a response to the following: 1.) detailed and specific explanationlrationale of the requested change(s) to the task(s) and I or
the additional days added (if requested); 2.) why this change was not included In the original contract; and, 3.) describe the Impact
If this chanue is not processed. Attach additional information from the Design Professional and/or Contractor if needed.
1) This change order will add $9,320 to task 8. 1 for additional level of effort required to Investigate an alternative site and a shared
agency building configuration requested by the project sponsors (EMS & North Collier Fire District)
2) The change being requested was not included in the original contract because the availability of the alternate site and the opportunity
for a shared agency building were not known to the project sponsors at the time the original contract was awarded
3) If this modification is not processed, the design professional will not be able to advise the best site and building configuration to
progress
NOTE: EMS Chief has renumbered station from 412 to 410
W
Prepared by: Sure a u 0 1 ivier =5 W' Date:
Olivier Sureau, Senior Project Manager, Facilities Management
Acceptance of this Change Order shall constitute a modification to contract / work order identified above and will be subject to all the same
terms and conditions as contained in the contract /work order indicated above, as fully as If the same were stated in this acceptance. The
adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor / Vendor / Consultant
Design Professional TfAing out of or^Ja4eq to the change set forth herein, including claims for impact and delay costs.
Accepted by:
, Scherkel & Shultz Inc.
Accepted by:
Approved by: McColmickJohn
John McCormick, Interim Director, Facilities Management
Digitally signed by DoriaPriscilla
Approved by:DoriaPriscilla Date: 2023.03.07 11:17:45 -05'00'
Procurement Professional
Revised: 0 1/1412021 (Divisions who may require additional signatures may include on separate sheet.)
Reviewed CD 1/30/23
Date:
Date� -712-3
Date:
Date:
PROCUREMENT U317ONLY
AdmIn
1 4c'D
I OCC ES
, I
,$-.,%0
Packet Pg. 1014
ATTEST:
Crystal K. Kinzel, Clerk of Courts
& Comptroller
By:_
Dated:
(SEAL)
Approve as to forin and legality:
By:
County Attorney
BOARD OF COUNTY COMMISSIONERS
COLLIER COUNTY, FLORIDA
Bv:
Rick LoCastro, Chairman
Revised: 01/14/2021 (Divisions who may require additional signatures may Include on separate sheet.)
Reviewed CD 1/30123
PROCUREMENT USE ONLY
Admin
I
Fpacket Pg. 1015
Change Order/Amendment Summary
CO#
AMD#
Description
COST
Additive Deductive
TIME
- - ---- I..--- N - ew
Added Amount
Justification
Task 8.1 additional
effort
9,320
Alternative site & shared agency
building investigation
. . . . ...................... . .. . ..... . . ..... .. . .... . . .......... . . .
Revised: 01/14/2021 (Divisions who may require additional signatures may include on separate sheet.)
Reviewed CD 1/30/23
PROCUREMENT USE ONLY-7
Adm1n
�C
I �.0
�.CC ES
Packet Pg. 1016
SCHENKELSHULTZ
0 0 0 A R C H J T E C T 0 R E 9 1 f I
Proposal for Additional Design Services
k'
January 25, 2023
Mr. Olivier Sureay
Senior Project Manager
Collier County Public Utilities Department
Facilities Management Division
3335 Tarniami Trail E., Suite 10 1
Naples, Fl, 34112
RE: Additional Services #01
Alternate Site
Collier County EMS Station #410
COMMISSION NO.: 2021807
Dear Olivier:
SCHENKELSHULTZ is pleased to submit the follokving proposal for Additional Professional Design
Services:
Scope Description:
Provide preliminary site designs and due diligence investigation for the above referenced
EMS facility regarding an alternate site to the original property planned on Performance
Way located at the Kaela Bay Development, Naples, FL. Preliminary analysis included
consideration of Litilizing the Station 474 building design on the alternate site, as well as
a new two-story structure on the Performance Way site that would accommodate
multiple agencies in consideration of the North Collier Fire District sharing the facility.
The Current professional services design contract is based upon utilizing the County
EMS prototype facility occupied only by the EMS on the Performance Way site.
Due diligence included investigation of site constraints and county and state agency
permitting requirements relative to the development of the alternate site, as well as
coordination of correspondence with the Kaela Bay property developer regarding
financial responsibilities and obligations for development of the parcel and ofrsite
improvements.
1111. Design Disciplines included:
A. Consulting services for the project include the following disciplines:
1. Architectural
2. Civil Engineering
Ill. Compensation for Professional Services:
Fees will be billed on a lump -sum basis as follows;
A. Architectural: $5,500.00
B. Civil: $3,820.00
TOTAL $9,320.00
200 E. ROBINSON ST SUITE 300 ORLANDO. I'L 32801 PH- 407-872-3322 FAX 407-872-3303
Packet Pg. 1017
Should there be any qUestions regarding this reqUeSt, please contact me directly.
Sincerely,
SCHENKELSFrULTZ
-�Gary F. rueger, AIA
3 ry Feg e r
Partner
CC: Dan Laggan/SchenkelSliultz
Iris Zayas/SchenkelShultz
200 E ROBINSON ST SUITE 300 ORLANDO, FL 32801
ACCEP'rED BY:
NAME AND TITLE:
DATE:
PH: 407-872-3322