Agenda 03/28/2023 Item #16C4 (Change order No. 15 to Collier County Sport Complex)03/28/2023 EXECUTIVE SUMMARY Recommendation to approve Change Order No. 15 to Collier County Sport Complex Phase 2.1 and 2.2A under the Sixth Amendment to Agreement No. 17-7198 with Manhattan Construction (Florida), Inc., resulting in a net reduction in the amount of $142,028.01. OBJECTIVE: To approve Change Order No. 15 providing for needed projects elements and removing low priority features for a net reduction of $142,028.01 to the approved Guaranteed Maximum Price. CONSIDERATION: On February 13, 2018 (Agenda Item 16.D.21) the Board awarded Agreement No. 17-7198 (the “Agreement”) with Manhattan Construction (Florida), Inc. (“Manhattan”) for Construction Manager at Risk services for all preconstruction phases for the Paradise Coast Sports Complex. On December 8, 2020 (Agenda Item 11.B), the Board awarded the Sixth Amendment to the Agreement with Manhattan for work for Phase 2.1 and 2.2A. Change Order No. 15 requests the following: a) Authorization Request: 7675.021R1 - Cove parking lot expansion Addendum #10 was issued to update signage, stripping, stormwater, landscaping, and irrigation that was not shown on the bid plans used to develop the Guaranteed Maximum Price. The missing elements are required by code and were identified at the time of permitting. Increase to the project of $246,884.37. b) Authorization Request: 7675.028 - Electrical conduits - Fortune Electric Addendum #13 was issued to modify the design and layout of electrical conduits necessary for operation of the Sports Complex. These conduits were not included in the bid plans used to develop the Guaranteed Maximum Price. Increase to the project $147,989.69. c) Authorization Request: 7675.029 - RFI #22- breakers - Fortune Electric The electrical engineer revised the existing breaker size to accommodate new Musco lights to be funded from Owner Contingency in the amount of $6,367.44. The breaker being upsized was installed in Phase 1 but is of insufficient capacity to supply the lighting installed as part of Phase 2. d) Authorization Request: 7675.038 - Descope of RV Park Per Collier County’s request, the RV park is removed from the CM scope for a deductive change in the amount of $705,163.54. e) Authorization Request: 7675.041 - Field 5-8 Curb change and fence - SCG Fields Per Collier County’s request, modifications to the field curb and fence are needed to operate the new fields for an increase to the project in the amount of $128,807.69. The curb and fencing are necessary elements to properly separate the sports fields. As such, the Phase 1 fields include these elements and are needed for the Phase 2 fields. This work is authorized under attached Work Directive #9. The bid plans used to develop the Guaranteed Maximum Price failed to include these necessary project elements. f) Authorization Request: 7675.049 - additional fencing Modify the temporary chain-link fence to separate phase 2.1 from future phase 3 as outlined in addendum #21 for an increase to the project in the amount of $39,453.78. The fencing is necessary to allow the public to safety utilize the four fields constructed under phase 2.1 during construction of field 9 under phase 3. This work is authorized under attached Work Directive #13. FISCAL IMPACT: This change order results in a net contract reduction of $142,028.01. Funding for Sports Complex Project No. 50156 is provided in Sports Complex Capital Improvement Fund (370). Funding for the project is provided by bond proceeds, TDC funds and the General Fund. 16.C.4 Packet Pg. 1278 03/28/2023 GROWTH MANAGEMENT IMPACT: There is no impact to the Growth Management Plan related to this action. LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for Board approval. -SRT RECOMMENDATION: Recommendation to approve Change Order No. 15 to Collier County Sport Complex Phase 2.1 and 2.2A under the Sixth Amendment to Agreement No. 17-7198 with Manhattan Construction (Florida), Inc., resulting in a net reduction in the amount of $142,028.01. (Project 50156) Prepared by: Ayoub R. Al-Bahou, PE, Principal Project Manager, Facilities Management Division ATTACHMENT(S) 1. sport complex2.1 change order #15 backup (PDF) 2. Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (PDF) 16.C.4 Packet Pg. 1279 03/28/2023 COLLIER COUNTY Board of County Commissioners Item Number: 16.C.4 Doc ID: 24927 Item Summary: Recommendation to approve Change Order No. 15 to Collier County Sport Complex Phase 2.1 and 2.2A under the Sixth Amendment to Agreement No. 17-7198 with Manhattan Construction (Florida), Inc., resulting in a net reduction in the amount of $142,028.01. Meeting Date: 03/28/2023 Prepared by: Title: Principal Project Manager – Facilities Management Name: Ayoub Al-bahou 03/09/2023 12:52 PM Submitted by: Title: – Facilities Management Name: John McCormick 03/09/2023 12:52 PM Approved By: Review: Facilities Management Ayoub Al-bahou Additional Reviewer Completed 03/09/2023 12:53 PM Facilities Management John McCormick Director - Facilities Completed 03/09/2023 12:54 PM Procurement Services Ana Reynoso Level 1 Purchasing Gatekeeper Completed 03/09/2023 4:03 PM Procurement Services Priscilla Doria Additional Reviewer Completed 03/10/2023 1:24 PM Procurement Services Sue Zimmerman Additional Reviewer Completed 03/14/2023 11:01 AM Public Utilities Department Drew Cody Level 1 Division Reviewer Completed 03/17/2023 8:37 AM Public Utilities Department George Yilmaz Level 2 Division Administrator Review Completed 03/17/2023 11:02 AM Procurement Services Sandra Herrera Additional Reviewer Completed 03/17/2023 3:44 PM County Attorney's Office Scott Teach Additional Reviewer Completed 03/20/2023 8:43 AM Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 03/20/2023 8:56 AM Corporate Compliance and Continuous Improvement Megan Gaillard Additional Reviewer Completed 03/20/2023 9:06 AM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 03/20/2023 10:23 AM Office of Management and Budget Christopher Johnson Additional Reviewer Completed 03/21/2023 3:56 PM Office of Management and Budget Susan Usher Additional Reviewer Completed 03/21/2023 4:20 PM County Manager's Office Ed Finn Level 4 County Manager Review Completed 03/22/2023 1:17 PM Board of County Commissioners Geoffrey Willig Meeting Pending 03/28/2023 9:00 AM 16.C.4 Packet Pg. 1280 16.C.4.a Packet Pg. 1281 Attachment: sport complex2.1 change order #15 backup (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.a Packet Pg. 1282 Attachment: sport complex2.1 change order #15 backup (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.a Packet Pg. 1283 Attachment: sport complex2.1 change order #15 backup (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.a Packet Pg. 1284 Attachment: sport complex2.1 change order #15 backup (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.a Packet Pg. 1285 Attachment: sport complex2.1 change order #15 backup (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.a Packet Pg. 1286 Attachment: sport complex2.1 change order #15 backup (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.a Packet Pg. 1287 Attachment: sport complex2.1 change order #15 backup (24927 : Sport Complex Phase 2.1- CO#15) 2600 Golden Gate Parkway, Naples, Florida, 34105 Office 239.403.6700 Fax 239.261.1797 Fla Engineer CA 28275 Fla Landscape CA LC26000632 Page | 1 November 8, 2022 Collier County Board of Commissioners 3301 Tamiami Trail East Naples, FL 34112 Re: Collier County Sports Complex and Events Center Phase 2.1 – AR Review AR 7675.021-R4 – ADDENDUM 10 To Whom It May Concern, We have received and reviewed the documents referenced above from Manhattan Construction Company. Regarding pricing, we find this work to be competitive and reasonable for the current market standards. Thank you, Josh Fruth PENINSULA ENGINEERING Vice President 16.C.4.b Packet Pg. 1288 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 2410 Palm Ridge Road - Sanibel Island, FL 33957 239.478.2220 - CoastalVistaDesign@gmail.com Page 1 LANDSCAPE ARCHITECTURE | DESIGN | CONSULTATION | CONSTRUCTION OBSERVATION Date: November 10, 2022 Collier County Board of Commissioners 3301 Tamiami Trail East Naples, FL 34112 Re: Collier County Sports Complex and Events Center Addendum #10 - AR Review Cove Parking Lot Landscaping Collier County Sports Complex Addendum #10 – AR Review To Whom It May Concern, We have received and reviewed the documents referenced above from Manhattan Construction Company with regard to the landscape scope of work provided by Brightview Landscape Development, Inc. Regarding pricing, we find this work to be competitive and reasonable for the current market standards. Thank you, Leigh A. Gevelinger, PLA, ASLA, LEED AP Owner, Coastal Vista Design, Inc. Florida Registered LA #6667171 16.C.4.b Packet Pg. 1289 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase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b Packet Pg. 1290 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) $XWKRUL]DWLRQ5HTXHVW 'HWDLOHG)RUP*URXSHGE\1XPEHU ZLWK&(%UHDNGRZQ    2ZQHU&KDQJH &KDQJH&RQGLWLRQ 'HVFULSWLRQ $''(1'80&RYH3DUNLQJ([SDQVLRQ 3HUPLW 3HQLQVXOD(QJLQHHULQJDFTXLULQJSHUPLWIRU&RYH3DUNLQJH[WHQVLRQ $GGHQGXP 6HH6HSWHPEHU0(025$1'80 7DE3KDVH)RXU±3DUNLQJ/RW([SDQVLRQ $GGHQGXPWR7DE±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±6U3URMHFW0DQDJHU $SSURYHG%\ $XWKRUL]DWLRQ5HTXHVW 3URORJ0DQDJHU 3URMHFW&ROOLHU&RXQW\6SRUWV (YHQWV&RPSOH[ 16.C.4.b Packet Pg. 1291 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1292 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)Supporting Documents 16.C.4.b Packet Pg. 1293 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)CE 016 - Item 001 Excavation - Earth Moved 16.C.4.b Packet Pg. 1294 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1295 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)CE 016 - Item 002 Landscape 16.C.4.b Packet Pg. 1296 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1297 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) BrightView Landscape Development, Inc. TAMPA 2022 All work performed as time and material work in accordance with this sheet shall be payable in full within 30 days of invoice date, without retention. 5326 CR 579, Seffner, FL 33584 813.628.8116 EQUIPMENT RENTAL - LABOR RATE SHEET Equipment Maintained - Moving Time, Operator, and Delivery at Extra Cost ITEM #DESCRIPTION RATE EQUIPMENT (E) DAILY RATE LABOR (L) HOURLY RATE OT Rate L.1 HardscapeForeman 62.00 83.00 L.2 HardscapeLeadman/Operator 54.00 72.00 L.3 HardscapeCraftsman/Finisher 49.00 66.00 L.4 HardscapeLaborer 45.00 61.00 L.5 LandscapeForeman 52.00 70.00 L.6 LandscapeLeadman/Operator 41.00 56.00 L.7 LandscapeLaborer 37.00 50.00 L.8 IrrigationForeman 50.00 67.00 L.9 IrrigationLeadman/Operator 43.00 58.00 L.10 Irrigation Laborer 37.00 50.00 L.11 Survey Crew 195.00 266.00 L.12 Superintendent 99.00 99.00 L.13 Project Manager 99.00 99.00 Equipment rates include fuel, maintenance, tax, and markup. Labor rates are standard time and include burden and markup. One day minimum charge on all equipment, plus delivery and pickup charge of $220. NOTE: If directed, all night work (7 p.m. - 6 a.m.) required will be surcharged at 10% on the above listed items. THIS LIST SUPERSEDES ALL PREVIOUS LISTS AND PRICES BECOME EFFECTIVE JANUARY 1, 2022 1/11/2022 E.1 Concrete Buggy Wheeled 150.00 E.2 Concrete Buggy Tracked 265.00 E.3 Golf Cart 170.00 E.4 Telehandler w/ Attachments 10k #920.00 E.5 Telehandler w/ Attachments 12k #1055.00 E.6 Telehandler w/ Attachments 15k #1475.00 E.7 Mini Excavator 7500#410.00 E.8 Mini Excavator 11000#525.00 E.9 Skid Steer mini 500# MT55 275.00 E.10 Skid Steer 3700# JD333 680.00 E.11 Wheel Loader w/Attachments 1 CY JD244 625.00 E.12 Wheel Loader w/Attachments 2 CY JD344 685.00 E.13 Wheel Loader w/Attachments 3 CY JD544 780.00 E.14 Wheel Loader w/Attachments 4 CY JD644 970.00 E.15 Dozer 70hp 815.00 E.16 Trencher Ride On 280.00 E.17 Water Truck 2000g (owner furnished water)510.00 E.18 Water Buffalo 500g (owner furnished water)155.00 E.19 Truck ¾Ton 235.00 E.20 Light Tower 4000W 160.00 E.21 Pressure Washer 3500 psi 135.00 E.22 Cut Off Saw and Blade 150.00 E.23 Air Compressor 185cfm 225.00 E.24 Breaker (air) w/ Bits 105.00 E.25 Breaker (electric) w/ Bits 115.00 E.26 Double Drum Roller 36”305.00 E.27 Plate compactor 300#120.00 E.28 Plate Compactor 1000#300.00 E.29 Mortar Mixer 6cf 95.00 E.30 Generator 5 kw 105.00 E.31 Sod Cutter 130.00 E.32 Solar Generator for irrigation controller 100.00 E.33 Ride On Deck Mower 225.00 E.34 Trash Pump and hoses 115.00 E.35 Floor Saw (control joints)120.00 E.36 Backhoe 80Hp 435.00 E.37 Pickup and Delivery of Equipment 220.00 16.C.4.b Packet Pg. 1298 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) Collier County Sports Complex Addendum #10 Date : 1/07/22 Lower Tier Subs (A x B) (A x D) (A x F) A BCDEFG H Total C + E + G + H Item Description Qty Unit Labor Unit Price Labor Total Material Unit Price Material Total Equipment Unit Price Equip Total Subcontractor Total Material + Labor + Equipment + Subcontractor Quote Comments 0.00 $ - 0.00 $ - 0.00 $ - $ - Irrigation Valves 1.5" ICV-G full kit with boxes 8 ea $ - 200.00 $ 1,600.00 0.00 $ - $ 1,600.00 Valves 2" ICV-G full kit with boxes 1 ea $ - 250.00 $ 250.00 0.00 $ - $ 250.00 Decoders ICD-100 9 ea $ - 125.00 $ 1,125.00 0.00 $ - $ 1,125.00 Grounding 1 LS $ - 125.00 $ 125.00 0.00 $ - $ 125.00 PROS-12 Spray with nozzles 142 ea $ - 20.50 $ 2,911.00 0.00 $ - $ 2,911.00 Fittings, swing joints grounding 1 ea $ - 790.20 $ 790.20 0.00 $ - $ 790.20 PCB-10 Bubblers 90 ea $ - 4.00 $ 360.00 0.00 $ - $ 360.00 MP3000 PROS-12-PRS40-cv-f Rotator 72 ea $ - 6.05 $ 435.60 0.00 $ - $ 435.60 Laterals - PVC Class 200 SDR 21 2"40 lf $ - 1.81 $ 72.40 0.00 $ - $ 72.40 1.5"20 lf $ - 1.31 $ 26.20 0.00 $ - $ 26.20 1.25"712 lf $ - 1.06 $ 754.72 0.00 $ - $ 754.72 1.0"4430 lf $ - 0.66 $ 2,923.80 0.00 $ - $ 2,923.80 .75"634 lf $ - 0.50 $ 317.00 0.00 $ - $ 317.00 Fittings 1 ls $ - 1,280.00 $ 1,280.00 0.00 $ - $ 1,280.00 Mainline - PVC Sch 40 2"847 lf $ - 3.63 $ 3,074.61 0.00 $ - $ 3,074.61 1.5"142 lf $ - 2.68 $ 380.56 0.00 $ - $ 380.56 Fittings 1 ls $ - 660.00 $ 660.00 0.00 $ - $ 660.00 Sleeves - PVC Sch 40 4"236 lf $ - 7.86 $ 1,854.96 0.00 $ - $ 1,854.96 3"329 lf $ - 7.56 $ 2,487.24 0.00 $ - $ 2,487.24 2"1055 lf $ - 3.64 $ 3,840.20 0.00 $ - $ 3,840.20 Nibco T-113-K at POC 1 ea $ - 303.00 $ 303.00 0.00 $ - $ 303.00 POC Labor $897.00 includes ex. controller tie in programming Wire - 2-wire 1000 lf $ - 0.72 $ 720.00 0.00 $ - $ 720.00 misc irrigation materails 1 ls $ - 1,145.00 $ 1,145.00 0.00 $ - $ 1,145.00 exclude backflow (none shown) $ - 0.00 $ - 0.00 $ - $ - Equipment (Trencher) 15 dy 265.00 $ 3,975.00 Misc delivery & fuel fees 1 ls $ - 1,275.00 $ 1,275.00 Irrigation Foreman 120 hr 49.00 $ 5,880.00 Irrigation Leadman 120 hr 42.00 $ 5,040.00 Irrigation Labor 120 hr 36.00 $ 4,320.00 Irrigation Labor 120 hr 36.00 $ 4,320.00 TAX 7.0%1,696.19$ 7.0%278.25$ 29,411$ check Subtotal 19,560.00$ 29,132.68$ 5,528.25$ -$ 54,221$ Subtotal Overhead & Profit - Materials 10%1,956.00$ 2,743.65$ 4,699.65$ Overhead & Profit - Equipment 10%397.50$ 397.50$ Overhead & Profit - Subs 10%-$ -$ Subtotal 21,516.00$ 31,876.33$ 5,925.75$ -$ 59,318$ Subtotal Bond 0%-$ -$ -$ -$ -$ Total 21,516.00$ 31,876.33$ 5,925.75$ -$ 59,318.08$ Total * On OCIP Projects the labor Rates and Lower Tier Subcontractor values used above are adjusted for OCIP. No future credit for OCIP is pending related to this estimate. Labor Material Equipment 1 of 1 16.C.4.b Packet Pg. 1299 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex 16.C.4.b Packet Pg. 1300 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)CE 016 - Item 003 Storm Drainage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b Packet Pg. 1301 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1302 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)CE 016 - Item 004 Fence 16.C.4.b Packet Pg. 1303 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1304 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 2600 Golden Gate Parkway, Naples, Florida, 34105 Office 239.403.6700 Fax 239.261.1797 Fla Engineer CA 28275 Fla Landscape CA LC26000632 Page | 1 November 9, 2022 Collier County Board of Commissioners 3301 Tamiami Trail East Naples, FL 34112 Re: Collier County Sports Complex and Events Center Phase 2.1 – AR Review AR 7675.028 To Whom It May Concern, We have received and reviewed the documents referenced above from Manhattan Construction Company. Regarding pricing, we find this work to be competitive and reasonable for the current market standards. Thank you, Josh Fruth PENINSULA ENGINEERING Vice President 16.C.4.b Packet Pg. 1305 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase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b Packet Pg. 1306 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase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±6U3URMHFW0DQDJHU $SSURYHG%\ $XWKRUL]DWLRQ5HTXHVW 3URORJ0DQDJHU 3URMHFW&ROOLHU&RXQW\6SRUWV (YHQWV&RPSOH[ 16.C.4.b Packet Pg. 1307 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1308 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)Supporting Documents 16.C.4.b Packet Pg. 1309 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)CE 033 - Item 1 16.C.4.b Packet Pg. 1310 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)Manhattan Note: Rates are within set rates in the Agreement 16.C.4.b Packet Pg. 1311 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1312 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1313 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1314 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1315 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1316 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)Addendum # 13 Page | 1 MEMORANDUM Date: December 1, 2021 To: Manhattan Construction Company From: Peninsula Engineering Regarding: Addendum #13 – Phase 2.1 Please refer to following information as an Addendum to the CD’s provided by Davidson Engineering/Peninsula Engineering for the following WORK: PHASE 2.1 – COLLIER COUNTY SPORTS COMPLEX AND EVENTS CENTER PHASE TWO includes the following Tab as previously described within the Bid Memo dated June 19, 2020, and re-issued to the contractor on May 6, 2021 (no changes, simply re-issued all the documents): Tab 5-7 - Collier County Sports Complex and Events Center – Phase Two Tabs 5-7 - This addendum provides clarity on location of FPL Conduit and Vaults as it pertains to this portion of the development and future connections. 1. Refer to updates within the FOLLOWING ATTACHMENT from the Collier County Sports Complex and Events Center – Phase Two Plan Set: o C-20.51 – Color coded conduit bank layouts for all public utility uses (overall high-level exhibit with proposed conduit banks) ƒ i.e. Comcast, FPL, County Fiber, Etc. ƒ Upon pricing completion and coordination with County, PE will coordinate with FPL for “dry” / future conduit and vault placement All updates are attached for reference. Attachments: x Collier County Sports Complex and Events Center – Phase Two o C–20.51 16.C.4.b Packet Pg. 1317 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) MEMORANDUM TO:Peninsula Engineering PROJECT:CCSC Ph 2.1 FROM:Brett L Sands, PE RE: AR 7675.029 – RFI #22 – Breaker Revisions for Musco Lighting DATE:September 26, 2022 In response to the above referenced authorization request, we have the following comments: Scope and cost increase appears reasonable as indicated. 16.C.4.b Packet Pg. 1318 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase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b Packet Pg. 1319 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase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±6U3URMHFW0DQDJHU $SSURYHG%\ $XWKRUL]DWLRQ5HTXHVW 3URORJ0DQDJHU 3URMHFW&ROOLHU&RXQW\6SRUWV (YHQWV&RPSOH[ 16.C.4.b Packet Pg. 1320 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1321 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)Supporting Documents 16.C.4.b Packet Pg. 1322 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)Sub-Contractor Change Order 16.C.4.b Packet Pg. 1323 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1324 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1325 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1326 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)Phase 1 and Phase 2 Drawings 16.C.4.b Packet Pg. 1327 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1328 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1329 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)RFI 22 16.C.4.b Packet Pg. 1330 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1331 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1332 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1333 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1334 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1335 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1336 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1337 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1338 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1339 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1340 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1341 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1342 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1343 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1344 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1345 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1346 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1347 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1348 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1349 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1350 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1351 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1352 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1353 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1354 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) RFI 054 Docking Station Panel RFI 110 RFI 103 16.C.4.b Packet Pg. 1355 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1356 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 2600 Golden Gate Parkway, Naples, Florida, 34105 Office 239.403.6700 Fax 239.261.1797 Fla Engineer CA 28275 Fla Landscape CA LC26000632 Page | 1 January 27, 2023 Collier County Board of Commissioners 3301 Tamiami Trail East Naples, FL 34112 Re: Collier County Sports Complex and Events Center Phase 2.1 – AR Review AR 7675.038 To Whom It May Concern, We have received and reviewed the documents referenced above from Manhattan Construction Company. Regarding pricing and considering this is a full deduct (100% refund) per the descoping of the project, we find this to be acceptable. Thank you, Josh Fruth PENINSULA ENGINEERING Vice President 16.C.4.b Packet Pg. 1357 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase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b Packet Pg. 1358 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 'HWDLOHG)RUP*URXSHGE\1XPEHU ZLWK&(%UHDNGRZQ $XWKRUL]DWLRQ5HTXHVW ,QRUGHUWRPLWLJDWHSRVVLEOHGHOD\VDQGH[SHGLWHWKHDSSURYDOIRUWKHGLUHFWFRVWRIZRUNUHODWHGWRWKLVFKDQJHXQOHVVVSHFLILFDOO\QRWHGDERYHZH DUHVXEPLWWLQJWKLVFKDQJHUHTXHVWZLWKRXWVFKHGXOHWLPHFRVWLPSDFW:HUHVHUYHWKHULJKWWRVXEPLWIRUFRVWWLPHLPSDFWVUHODWHGWRWKLVFKDQJH XQGHUVHSDUDWHFRYHUZKHQWKDWLQIRUPDWLRQLVDYDLODEOH &RQWUDFWRUGRHVQRWUHOHDVHLPSDFWVWKDWDULVHRXWRI$FWVRI1DWXUH LQFOXGLQJILUHIORRGHDUWKTXDNHVWRUPKXUULFDQHRURWKHUQDWXUDOGLVDVWHU  ZDULQYDVLRQDFWRISXEOLFHQHPLHVKRVWLOLWLHV ZKHWKHUZDULVGHFODUHGRUQRW FLYLOZDUUHEHOOLRQUHYROXWLRQLQVXUUHFWLRQPLOLWDU\RUXVXUSHG SRZHURUFRQILVFDWLRQWHUURULVWDFWLYLWLHVULRWQDWLRQDOL]DWLRQJRYHUQPHQWDFWLRQVWDULIIVEORFNDJHHPEDUJRWUDQVSRUWDWLRQGHOD\VQRWUHDVRQDEO\ IRUHVHHDEOHODERUGLVSXWHVWULNHORFNRXWGLVHDVHRXWEUHDNHSLGHPLFVSDQGHPLFVTXDUDQWLQHUHVWULFWLRQVRULQWHUUXSWLRQRUIDLOXUHRISRZHU VRXUFHV7RWKHH[WHQWWKHVHFRQGLWLRQVPD\RFFXUDQGLPSDFWWKH3URMHFWWKHUHVKDOOEHDQHTXLWDEOHDGMXVWPHQWWRWKH&RQWUDFW 6,*1$785( '$7($\RXE $OEDKRX±6U3URMHFW0DQDJHU $SSURYHG%\ $XWKRUL]DWLRQ5HTXHVW 3URORJ0DQDJHU 3URMHFW&ROOLHU&RXQW\6SRUWV (YHQWV&RPSOH[ 16.C.4.b Packet Pg. 1359 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1360 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)Supporting Documents  &KHULVVH7UDYLV )URP&KHULVVH7UDYLV 6HQW0RQGD\$SULO30 7R0HJDQ3KLOOLSV 6XEMHFW):5(6&(&3+$6($''(1'8059&$5(7$.(5   7KDQN\RX  &KHULVVH$7UDYLV 6U3URMHFW0DQDJHU    0DQKDWWDQ&RQVWUXFWLRQ&RPSDQ\ :HVWYLHZ'ULYH 1DSOHV)/ ϮϯϵͲϰϬϰͲϵϲϱϯĐĞůů ĐƚƌĂǀŝƐΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵ  ZZZPDQKDWWDQFRQVWUXFWLRQFRP )ROORZ8V/LQNHG,Q_)DFHERRN_*RRJOH_7ZLWWHU  &ƌŽŵ͗ůͲďĂŚŽƵLJŽƵďфLJŽƵď͘ůͲďĂŚŽƵΛĐŽůůŝĞƌĐŽƵŶƚLJĨů͘ŐŽǀх ^ĞŶƚ͗&ƌŝĚĂLJ͕&ĞďƌƵĂƌLJϭϴ͕ϮϬϮϮϭϬ͗ϯϵD dŽ͗ŝůů͘^njĐnjĞƉŬŽǁƐŬŝΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵ͖ƌĞƚƚsĂŶƚŽůфsĂŶƚŽůΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵх͖ŚĞƌŝƐƐĞ dƌĂǀŝƐфdƌĂǀŝƐΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵх͖:ĂŵĞƐ͘,ĂůůΛĐŽůůŝĞƌĐŽƵŶƚLJĨů͘ŐŽǀ͖:ĞĨĨΛĚĂǀŝĚƐŽŶĞŶŐŝŶĞĞƌŝŶŐ͘ĐŽŵ͖ ũĨƌƵƚŚΛƉĞŶͲĞŶŐ͘ĐŽŵ͖DĂƌŝƐƐĂ͘ĂŬĞƌΛĐŽůůŝĞƌĐŽƵŶƚLJĨů͘ŐŽǀ͖DĞŐĂŶWŚŝůůŝƉƐфDWŚŝůůŝƉƐΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵх͖ ZŝĐŚĂƌĚ͘WĂƋƵĞƚƚĞΛĐŽůůŝĞƌĐŽƵŶƚLJĨů͘ŐŽǀ͖^ƵƐĂŶ^ƚƵƌŐŝůůф^ƵƐĂŶ͘^ƚƵƌŐŝůůΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵх͖ ƵƌŝŵĂ͘>ƵĨĨΛĐŽůůŝĞƌĐŽƵŶƚLJĨů͘ŐŽǀ ^ƵďũĞĐƚ͗Z͗^W,^Ϯ͘ϭͲEhDϭϱͲZsͬZd<Z  dŽĨŽůůŽǁƵƉŽŶŽƵƌĐŽŶǀĞƌƐĂƚŝŽŶƌĞŐĂƌĚŝŶŐƚŚĞZsƉĂƌŬŝŶŐ  ŽůůŝĞƌĐŽƵŶƚLJǁŝůůŶŽƚŵŽǀĞĨŽƌǁĂƌĚǁŝƚŚĂŶLJĐŽŶƐƚƌƵĐƚŝŽŶǁŝƚŚŝŶƚŚĞZsƉĂƌŬŝŶŐĂƌĞĂ͘ tĞŶĞĞĚƚŽĞůŝŵŝŶĂƚĞƚŚĞĞŶƚŝƌĞƐĐŽƉĞĞdžĐĞƉƚĨŽƌ  ϭ͘tĂƚĞƌƐLJƐƚĞŵ^ƚƵďͲŽƵƚĂƚƚŚĞZsƉĂƌŬŝŶŐĂƌĞĂůŝŵŝƚĨŽƌĨƵƚƵƌĞĚĞǀĞůŽƉŵĞŶƚŽĨƚŚŝƐĂƌĞĂ Ϯ͘^ĂŶŝƚĂƌLJƐĞǁĞƌƐLJƐƚĞŵƐƚƵďͲŽƵƚĂƚƚŚĞZsƉĂƌŬŝŶŐĂƌĞĂůŝŵŝƚĨŽƌĨƵƚƵƌĞĚĞǀĞůŽƉŵĞŶƚŽĨƚŚŝƐĂƌĞĂ ϯ͘DŝŶŝŵƵŵĂŵŽƵŶƚŽĨƐƚŽƌŵǁĂƚĞƌƐLJƐƚĞŵƚŽĂůůŽǁƚŚŝƐĂƌĞĂƚŽĚƌĂŝŶĂďĚĂůŽƉƌŽǀŝĚĞƐƚƵďͲŽƵƚƚŽĂůůŽǁĨŽƌĨƵƚƵƌĞ ĚĞǀĞůŽƉŵĞŶƚŽĨƚŚŝƐĂƌĞĂ ϰ͘tĞĂƌĞĞůŝŵŝŶĂƚŝŶŐƚŚĞĐĂƌĞƚĂŬĞƌĐŽŵƉůĞƚĞůLJ  >ĞƚŵĞŬŶŽǁŝĨLJŽƵŚĂǀĞĂŶLJĨƵƌƚŚĞƌƋƵĞƐƚŝŽŶƐ  dŚĂŶŬLJŽƵ   16.C.4.b Packet Pg. 1361 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)   ZĞƐƉĞĐƚĨƵůůLJ͕  LJŽƵď  Ayoub R. Al-Bahou, PE, LEEDΠ GA WƌŝŶĐŝƉĂůWƌŽũĞĐƚDĂŶĂŐĞƌ &ĂĐŝůŝƚŝĞƐDĂŶĂŐĞŵĞŶƚŝǀŝƐŝŽŶ ϯϯϯϱdĂŵŝĂŵŝdƌĂŝůĂƐƚ EĂƉůĞƐ͕&ůŽƌŝĚĂϯϰϭϭϮ LJŽƵď͘ĂůͲďĂŚŽƵΛĐŽůůŝĞƌĐŽƵŶƚLJĨů͘ŐŽǀ ϮϯϵͲϮϱϮͲϳϳϬϰ;ŽͿ ϮϯϵͲϳϳϴͲϰϱϱϵ;ĐͿ   &ƌŽŵ͗ŚĞƌŝƐƐĞdƌĂǀŝƐфdƌĂǀŝƐΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵх ^ĞŶƚ͗dƵĞƐĚĂLJ͕&ĞďƌƵĂƌLJϭϱ͕ϮϬϮϮϵ͗ϯϳD dŽ͗:ŽƐŚƵĂ&ƌƵƚŚфũĨƌƵƚŚΛƉĞŶͲĞŶŐ͘ĐŽŵх͖ůͲďĂŚŽƵLJŽƵďфLJŽƵď͘ůͲďĂŚŽƵΛĐŽůůŝĞƌĐŽƵŶƚLJĨů͘ŐŽǀх͖>ƵĨĨƵƌŝŵĂ фƵƌŝŵĂ͘>ƵĨĨΛĐŽůůŝĞƌĐŽƵŶƚLJĨů͘ŐŽǀх Đ͗:ŽŚŶĞŐĂŶŝф:ĞŐĂŶŝΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵх͖ŝůů^njĐnjĞƉŬŽǁƐŬŝ фŝůů͘^njĐnjĞƉŬŽǁƐŬŝΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵх͖DĞŐĂŶWŚŝůůŝƉƐфDWŚŝůůŝƉƐΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵх ^ƵďũĞĐƚ͗Z͗^W,^Ϯ͘ϭͲEhDϭϱͲZsͬZd<Z  ydZE>D/>͗dŚŝƐĞŵĂŝůŝƐĨƌŽŵĂŶĞdžƚĞƌŶĂůƐŽƵƌĐĞ͘ŽŶĨŝƌŵƚŚŝƐŝƐĂƚƌƵƐƚĞĚƐĞŶĚĞƌĂŶĚƵƐĞĞdžƚƌĞŵĞĐĂƵƚŝŽŶǁŚĞŶ ŽƉĞŶŝŶŐĂƚƚĂĐŚŵĞŶƚƐŽƌĐůŝĐŬŝŶŐůŝŶŬƐ͘ LJŽƵď͕  DĚŝĚŶŽƚƌĞĐŽŵŵĞŶĚŽƌĂĚǀŝƐĞƚŚĞZsͬĂƌĞƚĂŬĞƌďĞƌĞŵŽǀĞĚĨƌŽŵƚŚĞ'DW͕ƚŚĞƌĞĨŽƌĞƚŚĞĚĚĞŶĚƵŵǁĂƐŶŽƚ ŝƐƐƵĞĚĨŽƌŽƵƌƐŽůĞƉƵƌƉŽƐĞƐ͘/ĨŽůůŝĞƌŽƵŶƚLJŝƐƌĞƋƵĞƐƚŝŶŐĂĐƌĞĚŝƚĨŽƌƐĐŽƉĞŽĨǁŽƌŬŶŽƚƌĞůĂƚĞĚƚŽĂŶĂůůŽǁĂŶĐĞĂŶ^/ ŽƌĚĚĞŶĚƵŵƐƵƉƉŽƌƚŝŶŐƚŚĞƌĞƋƵĞƐƚĞĚĐƌĞĚŝƚƐŚŽƵůĚďĞƉƌŽǀŝĚĞĚ͘dŚŝƐŝƐƚƌĂĚŝƚŝŽŶĂůƉƌĂĐƚŝĐĞ͘  /ĨƚŚĞĐƌĞĚŝƚLJŽƵĂƌĞŽďƚĂŝŶŝŶŐŝƐŶŽƚǁŚĂƚLJŽƵĂƌĞĞdžƉĞĐƚŝŶŐLJŽƵĂƌĞŐŽŝŶŐƚŽĞdžƉĞĐƚĂĐůĞĂƌĞdžƉůĂŶĂƚŝŽŶ͘  7KDQN\RX  &KHULVVH$7UDYLV 6U3URMHFW0DQDJHU    0DQKDWWDQ&RQVWUXFWLRQ&RPSDQ\ :HVWYLHZ'ULYH 1DSOHV)/ ϮϯϵͲϰϬϰͲϵϲϱϯĐĞůů ĐƚƌĂǀŝƐΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵ 16.C.4.b Packet Pg. 1362 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)   ZZZPDQKDWWDQFRQVWUXFWLRQFRP )ROORZ8V/LQNHG,Q_)DFHERRN_*RRJOH_7ZLWWHU  &ƌŽŵ͗:ŽƐŚƵĂ&ƌƵƚŚфũĨƌƵƚŚΛƉĞŶͲĞŶŐ͘ĐŽŵх ^ĞŶƚ͗&ƌŝĚĂLJ͕&ĞďƌƵĂƌLJϭϭ͕ϮϬϮϮϳ͗ϰϵD dŽ͗ŚĞƌŝƐƐĞdƌĂǀŝƐфdƌĂǀŝƐΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵх͖ůͲďĂŚŽƵLJŽƵďфLJŽƵď͘ůͲďĂŚŽƵΛĐŽůůŝĞƌĐŽƵŶƚLJĨů͘ŐŽǀх͖ >ƵĨĨƵƌŝŵĂфƵƌŝŵĂ͘>ƵĨĨΛĐŽůůŝĞƌĐŽƵŶƚLJĨů͘ŐŽǀх Đ͗:ŽŚŶĞŐĂŶŝф:ĞŐĂŶŝΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵх͖ŝůů^njĐnjĞƉŬŽǁƐŬŝ фŝůů͘^njĐnjĞƉŬŽǁƐŬŝΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵх͖DĞŐĂŶWŚŝůůŝƉƐфDWŚŝůůŝƉƐΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵх ^ƵďũĞĐƚ͗Z͗^W,^Ϯ͘ϭͲEhDϭϱͲZsͬZd<Z  dŚĞŚŝŐŚůŝŐŚƚĞĚĂĚĚĞŶĚƵŵǁĂƐƚŽĂƐƐŝƐƚǁŝƚŚLJŽƵĂŶĚ:ĞŶƐĞŶ;ƚŽĐůĞĂƌůLJƐŚŽǁǁŚĂƚƵƚŝůŝƚŝĞƐĂƌĞďĞŝŶŐƌĞŵŽǀĞĚĨƌŽŵƚŚĞ ŝƐ'DWĂƐŝƚƌĞůĂƚĞƐƚŽƚŚĞZsĂƌĞĂͿ͘^ŝŶĐĞƚŚĞůŝĞŶƚƌĞƋƵĞƐƚĞĚϭϬϬйŝŶĨƌĂƐƚƌƵĐƚƵƌĞƌĞůĂƚĞĚƚŽǁĂƚĞƌĂŶĚƐĞǁĞƌ ƌĞŵŽǀĞĚ͕ƚŚĂƚĂůƐŽŝŶĐůƵĚĞƐƌĞŵŽǀŝŶŐĂůůŽƚŚĞƌŝƚĞŵƐƉƌŽƉŽƐĞĚĨƌŽŵƚŚĞ'DW͘dŚĞZsĂƌĞĂǁŝůůďĞĂƐƚĂŶĚͲĂůŽŶĞƉŚĂƐĞ ŝŶƚŚĞĨƵƚƵƌĞďĞĐĂƵƐĞŝƚĐĂŶŶŽƚďĞĐŽŶƐƚƌƵĐƚĞĚƉƌŽƉĞƌůLJǁŝƚŚŽƵƚǁĂƚĞƌĂŶĚƐĞǁĞƌ͘  dŚĂŶŬLJŽƵ͕  WWE/E^h>E'/EZ/E' :ŽƐŚ&ƌƵƚŚ sŝĐĞWƌĞƐŝĚĞŶƚŽĨŶŐŝŶĞĞƌŝŶŐ  ϮϲϬϬ'ŽůĚĞŶ'ĂƚĞWĂƌŬǁĂLJ EĂƉůĞƐ͕&ůŽƌŝĚĂϯϰϭϬϱ WŚŽŶĞ͗Ϯϯϵ͘ϰϬϯ͘ϲϳϬϬ ŝƌĞĐƚ͗Ϯϯϵ͘ϰϬϯ͘ϲϳϯϵ ũĨƌƵƚŚΛƉĞŶͲĞŶŐ͘ĐŽŵ  KŶůLJĐƵƌƌĞŶƚ͕ƐŝŐŶĞĚ͕ĂŶĚƐĞĂůĞĚƉůĂŶƐƐŚĂůůďĞĐŽŶƐŝĚĞƌĞĚǀĂůŝĚĐŽŶƐƚƌƵĐƚŝŽŶĚŽĐƵŵĞŶƚƐ͘ĞĐĂƵƐĞŽĨƚŚĞĐŽŶƐƚĂŶƚůLJĐŚĂŶŐŝŶŐŶĂƚƵƌĞŽĨĐŽŶƐƚƌƵĐƚŝŽŶĚŽĐƵŵĞŶƚƐ͕ŝƚŝƐ ƚŚĞƌĞĐŝƉŝĞŶƚ͛ƐƌĞƐƉŽŶƐŝďŝůŝƚLJƚŽƌĞƋƵĞƐƚƚŚĞůĂƚĞƐƚĚŽĐƵŵĞŶƚƐĨƌŽŵWĞŶŝŶƐƵůĂŶŐŝŶĞĞƌŝŶŐĨŽƌƚŚĞŝƌƉĂƌƚŝĐƵůĂƌƚĂƐŬ͘    &ƌŽŵ͗ŚĞƌŝƐƐĞdƌĂǀŝƐфdƌĂǀŝƐΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵх ^ĞŶƚ͗dŚƵƌƐĚĂLJ͕&ĞďƌƵĂƌLJϭϬ͕ϮϬϮϮϭϬ͗ϭϮWD dŽ͗:ŽƐŚƵĂ&ƌƵƚŚфũĨƌƵƚŚΛƉĞŶͲĞŶŐ͘ĐŽŵх͖ůͲďĂŚŽƵLJŽƵďфLJŽƵď͘ůͲďĂŚŽƵΛĐŽůůŝĞƌĐŽƵŶƚLJĨů͘ŐŽǀх͖>ƵĨĨƵƌŝŵĂ фƵƌŝŵĂ͘>ƵĨĨΛĐŽůůŝĞƌĐŽƵŶƚLJĨů͘ŐŽǀх Đ͗:ŽŚŶĞŐĂŶŝф:ĞŐĂŶŝΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵх͖ŝůů^njĐnjĞƉŬŽǁƐŬŝ фŝůů͘^njĐnjĞƉŬŽǁƐŬŝΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵх͖DĞŐĂŶWŚŝůůŝƉƐфDWŚŝůůŝƉƐΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵх ^ƵďũĞĐƚ͗&t͗^W,^Ϯ͘ϭͲEhDϭϱͲZsͬZd<Z  :ŽƐŚ͕  dŽĐůĂƌŝĨLJͬĐŽŶĨŝƌŵĂůůƐĐŽƉĞǁŝƚŚŝŶƚŚĞ'DWƌĞůĂƚĞĚƚŽƚŚĞZsWĂƌŬ;ƉĂǀŝŶŐ͕ƐƚƌŝƉŝŶŐ͕ůĂŶĚƐĐĂƉŝŶŐ͕ĞůĞĐƚƌŝĐĂůͿŝƐƚŽƌĞŵĂŝŶ ĂŶĚǁĞĂƌĞKE>zƌĞŵŽǀŝŶŐƚŚĞǁĂƚĞƌĂŶĚƐĂŶŝƚĂƌLJ͘  /ĂŵĂƐŬŝŶŐďĞĐĂƵƐĞǁĞƐƉĞĐŝĨŝĐĂůůLJďƌŽŬĞŽƵƚƚŚĞZsĂƌĞĂǁŝƚŚŝŶŽƵƌŽƌŝŐŝŶĂů'DWĞƐƚŝŵĂƚĞĨŽƌƚŚĞƐĞƐĐŽƉĞƐĂŶĚƚŚĞ ǀĂůƵĞŽĨƚŚĞǁĂƚĞƌĂŶĚƐĂŶŝƚĂƌLJƐĞǁĞƌƌĞŵŽǀĂůŝƐƐŝŐŶŝĨŝĐĂŶƚůLJůĞƐƐƚŚĂŶƚŚĞƐĐŽƉĞŽĨƚŚĞZsƉĂƌŬ͘LJŽƵďŝƐĞdžƉĞĐƚŝŶŐ ΨΨΨΨΨΨƌĞƚƵƌŶĞĚ͘  7KDQN\RX  16.C.4.b Packet Pg. 1363 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)  &KHULVVH$7UDYLV 6U3URMHFW0DQDJHU    0DQKDWWDQ&RQVWUXFWLRQ&RPSDQ\ :HVWYLHZ'ULYH 1DSOHV)/ ϮϯϵͲϰϬϰͲϵϲϱϯĐĞůů ĐƚƌĂǀŝƐΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵ  ZZZPDQKDWWDQFRQVWUXFWLRQFRP )ROORZ8V/LQNHG,Q_)DFHERRN_*RRJOH_7ZLWWHU  &ƌŽŵ͗:ŽƐŚƵĂ&ƌƵƚŚфũĨƌƵƚŚΛƉĞŶͲĞŶŐ͘ĐŽŵх ^ĞŶƚ͗&ƌŝĚĂLJ͕:ĂŶƵĂƌLJϳ͕ϮϬϮϮϱ͗ϮϮWD dŽ͗ďŝůů͘ƐnjĐnjĞƉŬŽǁƐŬŝΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵ͖dƌĂǀŝƐΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵ͖ sĂŶƚŽůΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵ͖ŵƉŚŝůůŝƉƐΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵ͖ <^ĂŶƚŝĂŐŽΛŵĂŶŚĂƚƚĂŶĐŽŶƐƚƌƵĐƚŝŽŶ͘ĐŽŵ Đ͗ĂLJŽƵď͘ĂůͲďĂŚŽƵΛĐŽůůŝĞƌĐŽƵŶƚLJĨů͘ŐŽǀ ^ƵďũĞĐƚ͗^W,^Ϯ͘ϭͲEhDϭϱͲZsͬZd<Z  ůů͕  WĞƌŽƵƌƉƌŽĚƵĐƚŝŽŶŵĞĞƚŝŶŐLJĞƐƚĞƌĚĂLJ͕ĂƚƚĂĐŚĞĚŝƐĚĚĞŶĚƵŵϭϱĨŽƌWŚĂƐĞϮ͘ϭ;ƌĞŵŽǀĂůŽĨZsĂƌĞĂƵƚŝůŝƚŝĞƐ͕ ĂƌĞƚĂŬĞƌͿ͘WůĞĂƐĞƌĞǀŝĞǁĂŶĚůĞƚŵĞŬŶŽǁŝĨLJŽƵŚĂǀĞĂŶLJƋƵĞƐƚŝŽŶƐ͘  dŚĂŶŬLJŽƵ͕  WWE/E^h>E'/EZ/E' :ŽƐŚ&ƌƵƚŚ sŝĐĞWƌĞƐŝĚĞŶƚŽĨŶŐŝŶĞĞƌŝŶŐ  ϮϲϬϬ'ŽůĚĞŶ'ĂƚĞWĂƌŬǁĂLJ EĂƉůĞƐ͕&ůŽƌŝĚĂϯϰϭϬϱ WŚŽŶĞ͗Ϯϯϵ͘ϰϬϯ͘ϲϳϬϬ ŝƌĞĐƚ͗Ϯϯϵ͘ϰϬϯ͘ϲϳϯϵ ũĨƌƵƚŚΛƉĞŶͲĞŶŐ͘ĐŽŵ  ΀ydZE>D/>΁KEKd>/<ůŝŶŬƐŽƌĂƚƚĂĐŚŵĞŶƚƐƵŶůĞƐƐLJŽƵƌĞĐŽŐŶŝnjĞƚŚĞƐĞŶĚĞƌĂŶĚŬŶŽǁƚŚĞĐŽŶƚĞŶƚŝƐƐĂĨĞ͘ 8QGHU)ORULGD/DZHPDLODGGUHVVHVDUHSXEOLFUHFRUGV,I\RXGRQRWZDQW\RXUHPDLODGGUHVVUHOHDVHGLQUHVSRQVHWRD SXEOLFUHFRUGVUHTXHVWGRQRWVHQGHOHFWURQLFPDLOWRWKLVHQWLW\,QVWHDGFRQWDFWWKLVRIILFHE\WHOHSKRQHRULQZULWLQJ 16.C.4.b Packet Pg. 1364 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1365 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)CE 042 - Item 001 Excavation 16.C.4.b Packet Pg. 1366 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1367 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)CE 042 - Item 002 Storm Drainage 16.C.4.b Packet Pg. 1368 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1369 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1370 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)CE 042 - Item 003 Electrical 16.C.4.b Packet Pg. 1371 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex 16.C.4.b Packet Pg. 1372 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport ComplexRV Park Total $51,000 2600 Golden Gate Parkway, Naples, Florida, 34105 Office 239.403.6700 Fax 239.261.1797 Fla Engineer CA 28275 Fla Landscape CA LC26000632 Page | 1 November 8, 2022 Collier County Board of Commissioners 3301 Tamiami Trail East Naples, FL 34112 Re: Collier County Sports Complex and Events Center Phase 2.1 – AR Review AR 7675.041 To Whom It May Concern, We have received and reviewed the documents referenced above from Manhattan Construction Company. Regarding pricing, we find this work to be competitive and reasonable for the current market standards. Thank you, Josh Fruth PENINSULA ENGINEERING Vice President 16.C.4.b Packet Pg. 1373 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) G:\!01-PROJECTS-ACTIVE\Sports Complex - Phase 2.1\06-Construction\08-Change order\Work Directive\09-CUrb and Fencing\20220623-CC Sports & Events Complex 2-WDC009-sport fields curb and fencing.docx Division/Department Name WORK DIRECTIVE CHANGE CONTRACT #17-7198 Sixth Amendment /PROJECT NAME: CC Sports and Special Events Complex CHANGE # 09 DATE OF ISSUANCE: 6/24/2022 EFFECTIVE DATE: 4/8/2022 OWNER: Collier County Board of Commissioners PROJECT#: 50156 CONTRACTOR: Manhattan Construction Florida, Inc. ENGINEER/DESIGN PROFESSIONAL: Davidson Engineering You are directed to proceed promptly with the following change(s): Description: The Contract is being modified to include the additional scope as outlined in addendum #17 for the construction of the cove sport fields and more specifically outlined below: Funding: Funds for this work directive shall come from Project 50156. Purpose of Work Directive Change: To direct the Contractor to supply any necessary materials and labor to install or complete the following: x Increase the size of curbs from 6” to 12” to accommodate the additional field fencing. x Additional of approximately 1,470 linear feet of 4’ high black vinyl coated chain link fence along the south side of fields 5 and 6 and along the north and south sides of fields #7 & 8 as outlined in addendum #17 in the amount not to exceed $145,000 (from project fund 50156). Final cost and back-up documents shall be provided at time of issuing the required change order. Attachments: Authorization request #7675.041, dated 6/22/2022. If a claim is made that the above change(s) have affected Contract Price or Contract Times any claim for a Change Order based thereon will involve one or more of the following methods of determining the effect of the changes(s). Method of determining change in Contract Price: Method of determining change in Contract Times: Unit Prices Contractor’s records Lump Sum Engineer’s record Other Other Estimated increase (decrease) in Contract Price Estimated change in Contract Time: $145,000.00 Increase or decrease by 0 calendar days. RECOMMENDED: AUTHORIZED: By: By: Consultant 5(&200(1'(' By: &RQVXOWDQW Principal Project Manager ACCEPTED: AUTHORIZED: By: By: Contractor Division Director 16.C.4.b Packet Pg. 1374 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase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±6U3URMHFW0DQDJHU $SSURYHG%\ $XWKRUL]DWLRQ5HTXHVW 3URORJ0DQDJHU 3URMHFW&ROOLHU&RXQW\6SRUWV (YHQWV&RPSOH[ 16.C.4.b Packet Pg. 1375 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1376 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1377 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1378 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1379 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1380 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 2600 Golden Gate Parkway, Naples, Florida, 34105 Office 239.403.6700 Fax 239.261.1797 Fla Engineer CA 28275 Fla Landscape CA LC26000632 Page | 1 February 8, 2023 Collier County Board of Commissioners 3301 Tamiami Trail East Naples, FL 34112 Re: Collier County Sports Complex and Events Center Phase 2.1 – AR Review AR 7675.049 To Whom It May Concern, We have received and reviewed the documents referenced above from Manhattan Construction Company. Regarding pricing, we find this work to be competitive and reasonable for the current market standards. Thank you, Josh Fruth PENINSULA ENGINEERING Vice President 16.C.4.b Packet Pg. 1381 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) G:\!01-PROJECTS-ACTIVE\Sports Complex - Phase 2.1\06-Construction\08-Change order\Work Directive\13-additional fencing addendum 21 Division/Department Name WORK DIRECTIVE CHANGE CONTRACT #17-7198 Sixth Amendment /PROJECT NAME: CC Sports and Special Events Complex CHANGE # 13 DATE OF ISSUANCE: 2/8/2023 EFFECTIVE DATE: 2/8/2023 OWNER: Collier County Board of Commissioners PROJECT#: 50156 CONTRACTOR: Manhattan Construction Florida, Inc. ENGINEER/DESIGN PROFESSIONAL: Davidson Engineering You are directed to proceed promptly with the following change(s): Description: The Contract is being modified to include the additional scope as outlined in AR#7675.049; more specifically outlined below: Funding: Funds for this work directive shall come from Project 50156. Purpose of Work Directive Change: To direct the Contractor to supply any necessary materials and labor to install or complete the following: x AR#7675.049 – modify the temporary chain-link fence to separate phase 2.1 from future phase 3 as outlined in addendum #21 in the amount not to exceed $50,000. Final cost and back-up documents shall be provided at time of issuing the required change order. Attachments: Authorization request #7675.049, dated 1/25/2023. If a claim is made that the above change(s) have affected Contract Price or Contract Times any claim for a Change Order based thereon will involve one or more of the following methods of determining the effect of the changes(s). Method of determining change in Contract Price: Method of determining change in Contract Times: Unit Prices Contractor’s records Lump Sum Engineer’s record Other Other Estimated increase (decrease) in Contract Price Estimated change in Contract Time: $50,000 Increase or decrease by 0 calendar days. RECOMMENDED: AUTHORIZED: By: By: Consultant AUTHORIZED: By: &RQVXOWDQW $&&(37(' Principal Project Manager ACCEPTED: AUTHORIZED: By: By: Contractor Division Director 16.C.4.b Packet Pg. 1382 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase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±6U3URMHFW0DQDJHU $SSURYHG%\ $XWKRUL]DWLRQ5HTXHVW 3URORJ0DQDJHU 3URMHFW&ROOLHU&RXQW\6SRUWV (YHQWV&RPSOH[ 16.C.4.b Packet Pg. 1383 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1384 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 16.C.4.b Packet Pg. 1385 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) COLLIER COUNTY ON-SITE PRESERVE (4.37 ACRES) COLLIER COUNTY OFF-SITE PRESERVE PER PUD ORD. 20-13 (9.28 ACRES) COLLIER COUNTYTYCOLLIER COUNTYY 1" = 150'COLLIER COUNTY SPORTS COMPLEX AND EVENTS CENTER MAY 2021 REVISIONS: No: Revision: Date: OWNER/CLIENT/CONSULTANT: PROFESSIONAL SEALS: File Number: Project Number: Vertical Scale: Horizontal Scale: Date: Drawn by: Designed by: City B 1 1 E D C A County:[Save Date: 8/12/2022 8:49:37 AM] [Saved By: SCarlisle] [Plot Date: 8/12/2022 10:02:08 AM] [Plotted By: Shawn Carlisle] [Original Size: 24x36] [Drawing Path: Z:\ActiveProjects\CC SPORTS COMPLEX\DWG\Sheetfiles - PHASE 2\EX02 PAVILION GMD UPDATED.dwg]2 2 3 3 4 4 5 5 6 6 PROFESSIONAL ENGINEER: FLORIDA LICENSE NUMBER: SEC: RGE:TWP: NAPLES COLLIER TITLE: PROJECT: JENNA A. WOODWARD 84212 CIVIL ENGINEERING · LANDSCAPE ARCHITECTURE · ENVIRONMENTAL CONSULTING · LAND PLANNING · SITE PLANNING · CONSTRUCTION MANAGEMENT · OWNER REPRESENTATIVE 2600 Golden Gate Parkway Naples, FL. 34105 Phone: 239.403.6700 Fax: 239.261.1797 Email: info@pen-eng.com Website: www.pen-eng.com Florida Certificate of Authorization # 28275 JAW DJS --- --- 35 49 26 COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS 3335 TAMIAMI TRAIL EAST, SUITE 101 NAPLES, FL 34112 MASTER PHASING PLAN SHEET C-19.00 PHASE 1 PHASE PLAN x x x x x x x x x x x x PHASE 2 PHASE PLAN xx x x x xx x x xx x xx xx xx x x x x x x x x x x xx xx x x xx x 1:150 1 PHASE 4 PHASE PLAN PHASE 3 PHASE PLAN x xx x 16.C.4.b Packet Pg. 1386 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport ComplexADD FENCING (GREEN AREA FROM EXISTING TO GATE 3 AND THEN TO LAKE) GATE 2 GATE 3 EXISTING FENCING LIMITS TO REMAIN 3-9-BUTTON SIGNS FOR CLOSED ACCESS GATE 1 6'-0" TYP.6'-0" TYP.2'-6"2'-6" MIDFIELD LINE 12'-0"12'-0"12'-0"12'-0"L24'-0"6'-0"2'-0"2'-0"6'-0"12'-0"6'-0"4'-0"10'-0"5'-0"5'-0"SHEET TITLE: PROJECT: REVISIONS: CLIENT: DATEREV.DESCRIPTION COLLIER COUNTY SPORTS COMPLEX AND EVENTS CENTER SITE LOCATION MAP COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS 3335 TAMIAMI TRAIL EAST, SUITE 101 NAPLES, FL 34112 PROJECT NO.: 18-0097 18-0098 18-0099 SHEET NO: NOTES: SCALE: A B D C E F H G8/10/2022 10:36 AM4365 Radio Road, Suite 201 Naples, Florida 34104 P: 239.434.6060 Company Cert. of Authorization No. 00009496 2600 GOLDEN GATE PARKWAY NAPLES, FLORIDA 34105 PHONE: 239.403.6700 FLORIDA ENGINEERING CERTIFICATE OF AUTHORIZATION: #28275 JEFF L. DAVIDSON, P.E NO. 47161 ANDREW E. RATH, P.E. NO. 73996 CARL M. THRUSHMAN P.E. NO. 86499 RYAN A. WHITE, P.E. NO. 67400 JENNA A. WOODWARD, P.E. NO. 84212 0 SCALE: 1" = 20'-0" 4010 20 1" = 20' AREA B SITE LAYOUT & MATERIALS PLAN SD1.02 LANDSCAPE AREA RE: LANDSCAPE PLANS CONSTRUCT STANDARD DUTY GRAY CONCRETE PAVEMENT RE: CIVIL PLANS FOR PROFILE LEGEND COL FENCE CORNER COLUMN RE: K/SD4.01 LA CONSTRUCT HEAVY DUTY STANDARD GRAY CONCRETE PAVEMENT RE: CIVIL PLANS FOR PROFILE HD L# / C#SITE LAYOUT GUIDELINE RE: SD1.00 BV SAWCUT JOINT WITH 45° BEVELED EDGE RE: E/SD4.01 PHASE 2A LIMIT LINE SD SERIES PLANS LIMIT OF SCOPE 6' HT TEMPORARY CHAIN-LINK CONSTRUCTION FENCING LAMATCHLINE - SD1.01MATCHLINE - SD1.03 MATCHLINE - SD1.03MATCHLINE - SD1.011 BVBVBV DG LIMIT OF SCOPE - SD SERIES PLANS MULTI-PURPOSE FIELD 6 RE: PF SERIES PLANS INSTALL 6' HT. VINYL COATED CHAIN-LINK FENCE COLOR: BLACK RE: SD1.01 FOR LENGTH & CONTINUATION RE: J/SD4.01 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT EDGE OF PARKING LOT PAVEMENT RE: CIVIL PLANS RE: CIVIL PLANS LA LA MULTI-PURPOSE FIELD 5 RE: PF SERIES PLANS LIMIT OF SCOPE - SD SERIES PLANS LIMIT OF SCOPE - SD SERIES PLANS6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT LAKE RE: CIVIL PLANSA/SD4.01 A/SD4.01 1 07/24/2020 ADDENDUM 1-2.1 1 RE: CIVIL PLANS LIMITS OF PHASE 2.11 03/18/2022 CONFORMED SET 2 08/12/2022 ADDENDUM 21 2 INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 1' FROM AND TO PARALLEL PLAYING FIELD CURB INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING SURROUNDING PLAYING FIELD LIGHT POLE INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 3' FROM AND TO PARALLEL PLAYING FIELD CURB INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING AT EDGE OF STORMWATER BASIN TO PARKING LOT 2 SD1.03SSDD000033SSDD11..0033 SD1.03SD103SD103 SD1.00SD1.01SD1.011100001111DDSSSD1.01 A/AA//SD444SSDD44 A///SD4SSDD44 //SD4.0SD4 0 K/SD4. E/SD4 16.C.4.b Packet Pg. 1387 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTIONAIN-LINK CONSTRU FENCING AT EDGE OF STORMWATER BASIN TO PARKING LOTG AT EDGE OF STO INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCINGK CONSTRUCTION F SURROUNDING PLAYING FIELD LIGHT POLESURR INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTIONAIN-LINK CONSTRU FENCING 1' FROM AND TO PARALLEL PLAYING FIELD CURBNG 1' FROM AND T INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTIONAIN-LINK CONSTRU FENCING 3' FROM AND TO PARALLEL PLAYING FIELD CURBG 3' FROM AND T 2'-6"6'-0" TYP.EQ.EQ.20'-0"6'-0" TYP.L2L32'-6"2'-6"2'-6"4'-0"6'-0" TYP.6'-0" TYP.6'-0" TYP.20'-0"12'-0"2'-0"2'-0" 2'-6"2'-6" R1 5 ' - 0 "R15'-0"6'-0" TYP.L3 R 1 5 ' - 0 " -9" SHEET TITLE: PROJECT: REVISIONS: CLIENT: DATEREV.DESCRIPTION COLLIER COUNTY SPORTS COMPLEX AND EVENTS CENTER SITE LOCATION MAP COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS 3335 TAMIAMI TRAIL EAST, SUITE 101 NAPLES, FL 34112 PROJECT NO.: 18-0097 18-0098 18-0099 SHEET NO: NOTES: SCALE: A B D C E F H G8/10/2022 10:36 AM4365 Radio Road, Suite 201 Naples, Florida 34104 P: 239.434.6060 Company Cert. of Authorization No. 00009496 2600 GOLDEN GATE PARKWAY NAPLES, FLORIDA 34105 PHONE: 239.403.6700 FLORIDA ENGINEERING CERTIFICATE OF AUTHORIZATION: #28275 JEFF L. DAVIDSON, P.E NO. 47161 ANDREW E. RATH, P.E. NO. 73996 CARL M. THRUSHMAN P.E. NO. 86499 RYAN A. WHITE, P.E. NO. 67400 JENNA A. WOODWARD, P.E. NO. 84212 0 SCALE: 1" = 20'-0" 4010 20 1" = 20' AREA C SITE LAYOUT & MATERIALS PLAN SD1.03 LANDSCAPE AREA RE: LANDSCAPE PLANS CONSTRUCT STANDARD DUTY GRAY CONCRETE PAVEMENT RE: CIVIL PLANS FOR PROFILE LEGEND COL FENCE CORNER COLUMN RE: K/SD4.01 LA CONSTRUCT HEAVY DUTY STANDARD GRAY CONCRETE PAVEMENT RE: CIVIL PLANS FOR PROFILE HD L# / C#SITE LAYOUT GUIDELINE RE: SD1.00 BV SAWCUT JOINT WITH 45° BEVELED EDGE RE: E/SD4.01 PHASE 2A LIMIT LINE SD SERIES PLANS LIMIT OF SCOPE 6' HT TEMPORARY CHAIN-LINK CONSTRUCTION FENCING MULTI-PURPOSE FIELD 5 RE: PF SERIES PLANSMATCHLINE - SD1.04MATCHLINE - SD1.06 MATCHLINE - SD1.06MATCHLINE - SD1.04MATCHLINE - SD1.02 MATCHLINE - SD1.02 HD 1 1 07/24/2020 ADDENDUM 1-2.1 MULTI-PURPOSE FIELD 6 RE: PF SERIES PLANS LIMIT OF SCOPE - SD SERIES PLANS6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT 12" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT BV BV BVBVBVBVBVBV BV LA LA LIMIT OF SCOPE - SD SERIES PLANSLAKE RE: CIVIL PLANS LAKE RE: CIVIL PLANS A/SD4.01 A/SD4.01 1 1 LA LA LA LIMITS OF P H ASE 2.1 2 2 01/28/2022 ADDENDUM 14R2-2.1 2 2 03/18/2022 CONFORMED SET 3 INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 3' FROM AND TO PARALLEL PLAYING FIELD CURB RE: SD1.03 FOR LENGTH AND CONTINUATION INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 1' FROM AND TO PARALLEL PLAYING FIELD CURB INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING SURROUNDING PLAYING FIELD LIGHT POLE INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 1' FROM AND TO PARALLEL PLAYING FIELD CURB INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING SURROUNDING PLAYING FIELD LIGHT POLE INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 3' FROM AND TO PARALLEL PLAYING FIELD CURB INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 4' FROM AND TO PARALLEL PLAYING FIELD CURB INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 1' FROM AND TO PARALLEL PLAYING FIELD CURB INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 1' FROM EDGE OF SIDEWALK 3 08/12/2022 ADDENDUM 21 3 SD1.06SSDD110066S1.06DD1.06 SD1.06SD1.04444400001111DDDDSSSSSD1.04444400000000DDSSSSSD1.02000022SSDDDD110022 SD1.02SD1.002SD2 SD1.00 A/AA////SD4SSDD4444SSDDDD44 A///AA//SD4SSDD44SSDDDD44 K/SD4. E/SD4 16.C.4.b Packet Pg. 1388 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCINGK CONSTRUCTION F SURROUNDING PLAYING FIELD LIGHT POLESURR INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTIONAIN-LINK CONSTRU FENCING 1' FROM AND TO PARALLEL PLAYING FIELD CURBG 1' FROM AND T INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTIONCONSTRUC FENCING 3' FROM AND TO PARALLEL PLAYING FIELD CURBTO PARALL RE:RE SD1.03 FOR LENGTH AND CONTINUATION INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTIONAIN-LINK CONSTRU FENCING 1' FROM AND TO PARALLEL PLAYING FIELD CURBG 1' FROM AND T INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCINGK CONSTRUCTION F SURROUNDING PLAYING FIELD LIGHT POLESURR INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTIONAIN-LINK CONSTRU FENCING 3' FROM AND TO PARALLEL PLAYING FIELD CURBNG 3' FROM AND T INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 1' FROM EDGE OF SIDEWALK INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTIONAIN-LINK CONSTRU FENCING 4' FROM AND TO PARALLEL PLAYING FIELD CURBG 4' FROM AND T INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTIONAIN-LINK CONSTRU FENCING 1' FROM AND TO PARALLEL PLAYING FIELD CURBG 1' FROM AND T 6' 0" TYP 2'-6" 12'-0" TYP. 6'-0"6'-0"20'-0"2'-6"2'-6"10'-0"10'-0"R15'-0"SHEET TITLE: PROJECT: REVISIONS: CLIENT: DATEREV.DESCRIPTION COLLIER COUNTY SPORTS COMPLEX AND EVENTS CENTER SITE LOCATION MAP COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS 3335 TAMIAMI TRAIL EAST, SUITE 101 NAPLES, FL 34112 PROJECT NO.: 18-0097 18-0098 18-0099 SHEET NO: NOTES: SCALE: A B D C E F H G8/10/2022 10:37 AM4365 Radio Road, Suite 201 Naples, Florida 34104 P: 239.434.6060 Company Cert. of Authorization No. 00009496 2600 GOLDEN GATE PARKWAY NAPLES, FLORIDA 34105 PHONE: 239.403.6700 FLORIDA ENGINEERING CERTIFICATE OF AUTHORIZATION: #28275 JEFF L. DAVIDSON, P.E NO. 47161 ANDREW E. RATH, P.E. NO. 73996 CARL M. THRUSHMAN P.E. NO. 86499 RYAN A. WHITE, P.E. NO. 67400 JENNA A. WOODWARD, P.E. NO. 84212 0 SCALE: 1" = 20'-0" 4010 20 1" = 20' AREA F SITE LAYOUT & MATERIALS PLAN SD1.06 LANDSCAPE AREA RE: LANDSCAPE PLANS CONSTRUCT STANDARD DUTY GRAY CONCRETE PAVEMENT RE: CIVIL PLANS FOR PROFILE LEGEND COL FENCE CORNER COLUMN RE: K/SD4.01 LA CONSTRUCT HEAVY DUTY STANDARD GRAY CONCRETE PAVEMENT RE: CIVIL PLANS FOR PROFILE HD L# / C#SITE LAYOUT GUIDELINE RE: SD1.00 BV SAWCUT JOINT WITH 45° BEVELED EDGE RE: E/SD4.01 PHASE 2A LIMIT LINE SD SERIES PLANS LIMIT OF SCOPE 6' HT TEMPORARY CHAIN-LINK CONSTRUCTION FENCINGMATCHLINE - SD1.05MATCHLINE - SD1.07 MATCHLINE - SD1.07MATCHLINE - SD1.05MATCHLINE - SD1.03 MATCHLINE - SD1.03 1 INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 3' FROM AND TO PARALLEL PLAYING FIELD CURB 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT HD BV BV LIMITS OF SCOPE - SD SERIES PLANSMULTI-PURPOSE FIELD 8 RE: PF SERIES PLANS BV BV HD LAKE RE: CIVIL PLANS LAKE RE: CIVIL PLANS 1 07/24/2020 ADDENDUM 1-2.1 1 LIMITS OF PHASE 2.1LIM ITS OF PHASE 2 .1 2 2 01/28/2022 ADDENDUM 14R2-2.1 2 03/18/2022 CONFORMED SET INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 1' FROM AND TO PARALLEL PLAYING FIELD CURB INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 1' FROM AND PARALLEL TO EDGE OF SIDEWALK INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING SURROUNDING PLAYING FIELD LIGHT POLE 3 3 08/12/2022 ADDENDUM 21 3 SD1.07 SD1.07SD1.055555550000DDDDSSSS0SD1.05SD1.03SSDD110033SSDDDD0000331100 SD1.03 SD1.00 K/SD4. E/SD4 16.C.4.b Packet Pg. 1389 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTIONAIN-LINK CONSTRU FENCING 1' FROM AND TO PARALLEL PLAYING FIELD CURBG 1' FROM AND T INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTIONAIN-LINK CONSTRU FENCING 3' FROM AND TO PARALLEL PLAYING FIELD CURBG 3' FROM AND T INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCINGK CONSTRUCTION F SURROUNDING PLAYING FIELD LIGHT POLESURR INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 1' FROM AND PARALLEL TO EDGE OF SIDEWALK L46'-0" TYP. 2'-0"2'-0"12'-0"6'-0" TYP.6'-0" TYP.MIDFIELD LINE 4'-0"6'-0" TYP.6'-0" TYP.2'-6"2'-6"6'-0" TYP.6'-0" TYP. 6 2'-6"2'-6"20'-0"EQ.EQ.6'-0" TYP.R15'-0"R 1 5 ' - 0 " SHEET TITLE: PROJECT: REVISIONS: CLIENT: DATEREV.DESCRIPTION COLLIER COUNTY SPORTS COMPLEX AND EVENTS CENTER SITE LOCATION MAP COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS 3335 TAMIAMI TRAIL EAST, SUITE 101 NAPLES, FL 34112 PROJECT NO.: 18-0097 18-0098 18-0099 SHEET NO: NOTES: SCALE: A B D C E F H G8/10/2022 10:37 AM4365 Radio Road, Suite 201 Naples, Florida 34104 P: 239.434.6060 Company Cert. of Authorization No. 00009496 2600 GOLDEN GATE PARKWAY NAPLES, FLORIDA 34105 PHONE: 239.403.6700 FLORIDA ENGINEERING CERTIFICATE OF AUTHORIZATION: #28275 JEFF L. DAVIDSON, P.E NO. 47161 ANDREW E. RATH, P.E. NO. 73996 CARL M. THRUSHMAN P.E. NO. 86499 RYAN A. WHITE, P.E. NO. 67400 JENNA A. WOODWARD, P.E. NO. 84212 0 SCALE: 1" = 20'-0" 4010 20 1" = 20' AREA E SITE LAYOUT & MATERIALS PLAN SD1.05 LANDSCAPE AREA RE: LANDSCAPE PLANS CONSTRUCT STANDARD DUTY GRAY CONCRETE PAVEMENT RE: CIVIL PLANS FOR PROFILE LEGEND COL FENCE CORNER COLUMN RE: K/SD4.01 LA CONSTRUCT HEAVY DUTY STANDARD GRAY CONCRETE PAVEMENT RE: CIVIL PLANS FOR PROFILE HD L# / C#SITE LAYOUT GUIDELINE RE: SD1.00 BV SAWCUT JOINT WITH 45° BEVELED EDGE RE: E/SD4.01 PHASE 2A LIMIT LINE SD SERIES PLANS LIMIT OF SCOPE 6' HT TEMPORARY CHAIN-LINK CONSTRUCTION FENCING HD MATCHLINE - SD1.06MATCHLINE - SD1.08 MATCHLINE - SD1.08 MATCHLINE - SD1.06MATCHLINE - SD1.04 MATCHLINE - SD1.04 1 LIMIT OF SCOPE - SD SERIES PLANSSITE CENTERLINESITE CENTERLINELIMITS OF PHASE 2.1PHASE 1A MULTI-PURPOSE FIELD 7 RE: PF SERIES PLANS EXISTING PHASE 1A ORNAMENTAL FENCE 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT BV BV BV BV BV BV BVBVHD LA LA LA BVBVMULTI-PURPOSE FIELD 8 RE: PF SERIES PLANSLIMITS OF PHASE 2.1PHASE 1A PHASE 1A LIMITS OF PHASE 2.1A/SD4.01 A/SD4.01 1 07/24/2020 ADDENDUM 1-2.1 1 2 2 01/28/2022 ADDENDUM 14R2-2.1 03/18/2022 CONFORMED SET INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 1' FROM AND PARALLEL TO EDGE OF SIDEWALK INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 1' FROM AND PARALLEL TO EDGE OF SIDEWALK 3 3 08/12/2022 ADDENDUM 21 3 SD1.08SD1.08 SD1.08 SD1.0666660000DDSSSS0SD1.06SD1.04 SD1.04SSDDDD000044SSDD110044 SD1.00 A/AA////SD4SSDDDD44SSDD44 A/AA//AA SD4SSDDDD44SSDD4444 K/SD4. E/SD4 16.C.4.b Packet Pg. 1390 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 1' FROM AND PARALLEL TO EDGE OF SIDEWALK INSTALL 6' HT. TEMPORARY CHAIN-LINK CONSTRUCTION FENCING 1' FROM AND PARALLEL TO EDGE OF SIDEWALK 16.C.4.b Packet Pg. 1391 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) Item 002 Black Vinyl Coated Fence and Gate Sheet1 Date: July 28, 2021 Project:Manahattan 6' Black Vinyl Collier Sports Complex / Phase II QTY DESC SIZE COST TOTAL QTY DESC SIZE COST TOTAL 8 B. Band 3" 0.71 5.71 948 Fabric 6' #6 ga 9.64 9,141.43 4 B. Band 2-1/2" 0.64 2.57 95 LinePost 2-1/2" x 9' 80.50 7,647.50 20 T. Band 3" 0.71 14.29 4 TermPost 3" x 9' 120.00 480.00 8Rail End1-5/8" 1.79 14.29 966 TopRail 1-5/8" 5.19 5,009.40 4 T. Tightener 1.43 5.71 4 TenBar 1002 8.57 34.29 46 Sleeve 1-5/8" 1.79 82.14 1 TenWire 178.57 178.57 100 Loop Cap 2-1/2" 2.50 250.00 4 TrussRod 14.29 57.14 4Dome Cap 3" 4.29 17.14 50 Bolts 0.17 8.57 Equipement 150 TieWire 0.29 42.86 450 expenses 2.86 1,285.71 8 Quikrete 142.86 1,142.86 1,586.14 Subcontract 23,834.04 948 6' w/ BTW 4.29 4,062.86 4 Bars / Brace 7.14 28.57 - MATERIAL 25,420.19 TAX 1,779.41 LABOR 4,091.43 TOTAL 31,291.03 948' 33.01$ Page 1 16.C.4.b Packet Pg. 1392 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) Date: July 28, 2021 Project: Manahattan 6' Ornamental Gate Collier Sports Complex / Phase II QTY DESC SIZE COST TOTAL QTY DESC SIZE COST TOTAL 4 B. Band 3" 0.71 2.86 2 TermPost 3" x 9' 120.00 240.00 10 T. Band 3" 0.71 7.14 2 TenBar 1002 8.57 17.14 2Rail End1-5/8" 1.79 3.57 2 TrussRod 14.29 28.57 2 Dome Cap 3" 4.29 8.57 1 Gate 6'h x 16'w DD 754.29 754.29 20 Bolts 0.17 3.43 0.5 Quikrete 142.86 71.43 Subcontract 1,040.00 97.00 1 Gate Installation 150.00 150.00 MATERIAL 1,137.00 TAX 79.59 LABOR 150.00 TOTAL 1,366.59 16.C.4.b Packet Pg. 1393 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 6'-0" TYP.6'-0" TYP.2'-6"2'-6" MIDFIELD LINE 12'-0"12'-0"12'-0"12'-0"L24'-0"6'-0"2'-0"2'-0"6'-0"12'-0"6'-0" 10'-0" 10'-0"10'-0"10'-0" 10'-0"10'-0"4'-0"10'-0"5'-0"5'-0"10'-0"EQ.EQ.0+001+002+00BP: 0+00.00 PC: 0+10.00 PR C : 0 + 4 0 . 5 0 PRC: 0+77.99L12C14C15 C166'-0" 6'-0" SHEET TITLE: PROJECT: REVISIONS: CLIENT: DATEREV.DESCRIPTION COLLIER COUNTY SPORTS COMPLEX AND EVENTS CENTER SITE LOCATION MAP COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS 3335 TAMIAMI TRAIL EAST, SUITE 101 NAPLES, FL 34112 PROJECT NO.: 18-0097 18-0098 18-0099 SHEET NO: NOTES: SCALE: A B D C E F H G3/4/2022 12:19 PM4365 Radio Road, Suite 201 Naples, Florida 34104 P: 239.434.6060 Company Cert. of Authorization No. 00009496 2600 GOLDEN GATE PARKWAY NAPLES, FLORIDA 34105 PHONE: 239.403.6700 FLORIDA ENGINEERING CERTIFICATE OF AUTHORIZATION: #28275 JEFF L. DAVIDSON, P.E NO. 47161 ANDREW E. RATH, P.E. NO. 73996 CARL M. THRUSHMAN P.E. NO. 86499 RYAN A. WHITE, P.E. NO. 67400 JENNA A. WOODWARD, P.E. NO. 84212 0 SCALE: 1" = 20'-0" 4010 20 1" = 20' AREA B SITE LAYOUT & MATERIALS PLAN SD1.02 LANDSCAPE AREA RE: LANDSCAPE PLANS CONSTRUCT STANDARD DUTY GRAY CONCRETE PAVEMENT RE: CIVIL PLANS FOR PROFILE LEGEND COL FENCE CORNER COLUMN RE: K/SD4.01 LA CONSTRUCT HEAVY DUTY STANDARD GRAY CONCRETE PAVEMENT RE: CIVIL PLANS FOR PROFILE HD L# / C#SITE LAYOUT GUIDELINE RE: SD1.00 BV SAWCUT JOINT WITH 45° BEVELED EDGE RE: E/SD4.01 PHASE 2A LIMIT LINE SD SERIES PLANS LIMIT OF SCOPE LAMATCHLINE - SD1.01MATCHLINE - SD1.03 MATCHLINE - SD1.03MATCHLINE - SD1.011 BVBVBV LIMIT OF SCOPE - SD SERIES PLANS DG LIMIT OF SCOPE - SD SERIES PLANS MULTI-PURPOSE FIELD 6 RE: PF SERIES PLANS INSTALL 6' HT. VINYL COATED CHAIN-LINK FENCE COLOR: BLACK RE: SD1.01 FOR LENGTH & CONTINUATION RE: J/SD4.01 INSTALL 398 L.F. 6' HT. VINYL COATED CHAIN-LINK FENCE FENCE TO PARALLEL PLAYING FIELD CURB COLOR: BLACK RE: SD1.03 FOR CONTINUATION RE: J/SD4.01 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT EDGE OF PARKING LOT PAVEMENT RE: CIVIL PLANS RE: CIVIL PLANS LA LA LA CONSTRUCT 10' W. ASPHALT TRAIL RE: SD1.00 FOR CENTERLINE ALIGNMENT MULTI-PURPOSE FIELD 5 RE: PF SERIES PLANS LIMIT OF SCOPE - SD SERIES PLANS LIMIT OF SCOPE - SD SERIES PLANS6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT LAKE RE: CIVIL PLANSA/SD4.01 A/SD4.01 LA 1 07/24/2020 ADDENDUM 1-2.1 1 RE: CIVIL PLANS LIMITS OF PHASE 2.11 03/18/2022 CONFORMED SET A/AA//SD444SSDD44DD A///SD4SSDD44SS //SD4.0SD4 0 /SD4.0 K/SD4. E/SD4 SD1.03SSDD000033SSDD11..0033 SD1.03SD103SD103 SD1.03 SD1.00D1.00 SD1.00SD1.01SD1.011100001111DDSSSD1.01 16.C.4.b Packet Pg. 1394 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 2'-6"6'-0" TYP.EQ.EQ.20'-0"6'-0" TYP.L2L32'-6"2'-6"2'-6"4'-0"6'-0" TYP.6'-0" TYP.6'-0" TYP. 10'-0"20'-0"12'-0"2'-0"2'-0" 2'-6"2'-6"7'-6"8'-8"7'-6"8'-8"6'-0"21'-3"25'-9"6'-0" R1 5 ' - 0 "R15'-0"10'-0"10'-0"10'-0"10'-0"10'-0"10'-0"10'-0"10'-0" 6'-0" TYP.L3 R 1 5 ' - 0 "3+004+005+00 6+007+00PCC: 4+35.37 PCC: 4+75.07PRC: 5+32.87PRC: 6+07.60 C17C18 C19C20-9"R15'-0"R15'-0"2'-6"2'-6"2'-6"R 1 5 ' - 0 " R 1 5 ' - 0 "3'-0"SHEET TITLE: PROJECT: REVISIONS: CLIENT: DATEREV.DESCRIPTION COLLIER COUNTY SPORTS COMPLEX AND EVENTS CENTER SITE LOCATION MAP COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS 3335 TAMIAMI TRAIL EAST, SUITE 101 NAPLES, FL 34112 PROJECT NO.: 18-0097 18-0098 18-0099 SHEET NO: NOTES: SCALE: A B D C E F H G3/4/2022 12:19 PM4365 Radio Road, Suite 201 Naples, Florida 34104 P: 239.434.6060 Company Cert. of Authorization No. 00009496 2600 GOLDEN GATE PARKWAY NAPLES, FLORIDA 34105 PHONE: 239.403.6700 FLORIDA ENGINEERING CERTIFICATE OF AUTHORIZATION: #28275 JEFF L. DAVIDSON, P.E NO. 47161 ANDREW E. RATH, P.E. NO. 73996 CARL M. THRUSHMAN P.E. NO. 86499 RYAN A. WHITE, P.E. NO. 67400 JENNA A. WOODWARD, P.E. NO. 84212 0 SCALE: 1" = 20'-0" 4010 20 1" = 20' AREA C SITE LAYOUT & MATERIALS PLAN SD1.03 LANDSCAPE AREA RE: LANDSCAPE PLANS CONSTRUCT STANDARD DUTY GRAY CONCRETE PAVEMENT RE: CIVIL PLANS FOR PROFILE LEGEND COL FENCE CORNER COLUMN RE: K/SD4.01 LA CONSTRUCT HEAVY DUTY STANDARD GRAY CONCRETE PAVEMENT RE: CIVIL PLANS FOR PROFILE HD L# / C#SITE LAYOUT GUIDELINE RE: SD1.00 BV SAWCUT JOINT WITH 45° BEVELED EDGE RE: E/SD4.01 PHASE 2A LIMIT LINE SD SERIES PLANS LIMIT OF SCOPE MULTI-PURPOSE FIELD 5 RE: PF SERIES PLANSMATCHLINE - SD1.04MATCHLINE - SD1.06 MATCHLINE - SD1.06MATCHLINE - SD1.04MATCHLINE - SD1.02 MATCHLINE - SD1.02 HD 1 1 07/24/2020 ADDENDUM 1-2.1 MULTI-PURPOSE FIELD 6 RE: PF SERIES PLANS MULTI-PURPOSE FIELD 8 RE: PF SERIES PLANS LIMIT OF SCOPE - SD SERIES PLANSRESTROOMS INSTALL 421 L.F. 6' HT. VINYL COATED CHAIN-LINK FENCE FENCE TO PARALLEL PLAYING FIELD CURB COLOR: BLACK RE: SD1.06 FOR CONTINUATION RE: J/SD4.01 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT INSTALL 6' HT. VINYL COATED CHAIN-LINK FENCE FENCE TO PARALLEL PLAYING FIELD CURB COLOR: BLACK RE: SD1.02 FOR LENGTH AND CONTINUATION RE: J/SD4.01 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT INSTALL 123 L.F. 6' HT. VINYL COATED CHAIN-LINK FENCE FENCE TO PARALLEL PLAYING FIELD CURB COLOR: BLACK RE: J/SD4.01 12" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT HD 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT BV BV BVBVBVBVBVBV BV LA LA LIMIT OF SCOPE - SD SERIES PLANSLAKE RE: CIVIL PLANS LAKE RE: CIVIL PLANS A/SD4.01 A/SD4.01 CONSTRUCT 10' W. ASPHALT TRAIL RE: SD1.00 FOR CENTERLINE ALIGNMENT CONSTRUCT 10' W. ASPHALT TRAIL RE: SD1.00 FOR CENTERLINE ALIGNMENT 1 1 LA LA LA LA LA LA LA LA LA LIMITS OF P H ASE 2.1 2 2 01/28/2022 ADDENDUM 14R2-2.1 2 2 03/18/2022 CONFORMED SET A/AA////D44444DD44DDDSDSSSSDDDD A///AA//SD4DD44SSDDDD44SSS /SD4.0 /SD4.0 /SD4.0 K/SD4. E/SD4 SD1.06 SDSSDD1.06110066S1.06DD1.06 SD1.06SD1.04444400001111DDDDSSSSSD1.04444400000000DDSSSSSD1.02000022SSDDDD110022 SD1.02SD1.002SD2 SD1.0202 SD1.00D1.00 SD1.00D1.00 SD1.00 16.C.4.b Packet Pg. 1395 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15) 6' 0" TYP 2'-6" 12'-0" TYP. 6'-0"6'-0"20'-0"2'-6"2'-6"10'-0"10'-0"10'-0"10'-0"10'-0" 10'-0"10'-0"10'-0" CENTER OF COLUMN N: 666437.83 E: 436690.03 CENTER OF COLUMN N: 666459.83 E: 436689.73R15'-0"8+009+0010+0011+0012+00PRC: 9+79.70 PRC: 10+60.62C20C21-9"R15'-0"R 1 5 ' - 0 " 41'-10"CENTER OF FOOTING N: 666381.55 E: 436581.90 CENTER OF FOOTING COOOG CENTER OF FOOTING N: 666382.64 E: 436661.89 8'-0"8'-0"6'-0"39'-0"SHEET TITLE: PROJECT: REVISIONS: CLIENT: DATEREV.DESCRIPTION COLLIER COUNTY SPORTS COMPLEX AND EVENTS CENTER SITE LOCATION MAP COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS 3335 TAMIAMI TRAIL EAST, SUITE 101 NAPLES, FL 34112 PROJECT NO.: 18-0097 18-0098 18-0099 SHEET NO: NOTES: SCALE: A B D C E F H G3/4/2022 12:20 PM4365 Radio Road, Suite 201 Naples, Florida 34104 P: 239.434.6060 Company Cert. of Authorization No. 00009496 2600 GOLDEN GATE PARKWAY NAPLES, FLORIDA 34105 PHONE: 239.403.6700 FLORIDA ENGINEERING CERTIFICATE OF AUTHORIZATION: #28275 JEFF L. DAVIDSON, P.E NO. 47161 ANDREW E. RATH, P.E. NO. 73996 CARL M. THRUSHMAN P.E. NO. 86499 RYAN A. WHITE, P.E. NO. 67400 JENNA A. WOODWARD, P.E. NO. 84212 0 SCALE: 1" = 20'-0" 4010 20 1" = 20' AREA F SITE LAYOUT & MATERIALS PLAN SD1.06 LANDSCAPE AREA RE: LANDSCAPE PLANS CONSTRUCT STANDARD DUTY GRAY CONCRETE PAVEMENT RE: CIVIL PLANS FOR PROFILE LEGEND COL FENCE CORNER COLUMN RE: K/SD4.01 LA CONSTRUCT HEAVY DUTY STANDARD GRAY CONCRETE PAVEMENT RE: CIVIL PLANS FOR PROFILE HD L# / C#SITE LAYOUT GUIDELINE RE: SD1.00 BV SAWCUT JOINT WITH 45° BEVELED EDGE RE: E/SD4.01 PHASE 2A LIMIT LINE SD SERIES PLANS LIMIT OF SCOPEMATCHLINE - SD1.05MATCHLINE - SD1.07 MATCHLINE - SD1.07MATCHLINE - SD1.05MATCHLINE - SD1.03 MATCHLINE - SD1.03 1 INSTALL 6' HT. VINYL COATED CHAIN-LINK FENCE FENCE TO PARALLEL PLAYING FIELD CURB COLOR: BLACK RE: SD1.03 FOR LENGTH AND CONTINUATION RE: J/SD4.01 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT COL COL INSTALL 16' W. X 6' HT. DOUBLE SWING GATE WITH CANE BOLTS AND LOCKING LATCHING MECHANISM (2) 8' W. GATE LEAFS RE: G/SD4.02 HD BV BV LIMITS OF SCOPE - SD SERIES PLANSMULTI-PURPOSE FIELD 8 RE: PF SERIES PLANS BV BV HD MULTI-PURPOSE FIELD 9 RE: PF SERIES PLANS INSTALL 420 L.F. 6' HT. VINYL COATED CHAIN-LINK FENCE PARALLEL TO PLAYING FIELD CURB COLOR: BLACK RE: SD1.07 FOR CONTINUATION RE: J/SD4.01 6" W. PLAYING FIELD ATTACHMENT CURB RE: PF SERIES PLANS FOR LAYOUT LAKE RE: CIVIL PLANS LAKE RE: CIVIL PLANSLIMITS OF SCOPE - SD SERIES PLANSCONSTRUCT 10' W. ASPHALT TRAIL RE: SD1.00 FOR CENTERLINE ALIGNMENT CONSTRUCT 10' W. ASPHALT TRAIL RE: SD1.00 FOR CENTERLINE ALIGNMENT 1 07/24/2020 ADDENDUM 1-2.1 1 1 LIMITS OF PHASE 2.1LIM ITS OF PHASE 2 .1 PEMB FOOTINGS BELOW PEMB FOOTINGS BELOW PRE-ENGINEERED METAL BUILDING (ABOVE) 2 2 01/28/2022 ADDENDUM 14R2-2.1 PRE-ENGINEERED METAL BUILDING RE: ARCHITECTURAL 2 03/18/2022 CONFORMED SET K/SD4. E/SD4 J/SD4 J/SD4 G/G/SD4SD4 SD1.07SD SD1.07SSDD110077 SD1.07SD1.00000DDDDSSSS55555550SD1.055555000000DDDDSSSS1.03110033000033SDSSDDSSDDDD101100 SD1.03 SD1.0303 SD1.00D1.00 SD1.00D1.00 SD1.00 16.C.4.b Packet Pg. 1396 Attachment: Sports Complex 2 - Change Order#15-ARs-20230227-back up doc (24927 : Sport Complex Phase 2.1- CO#15)