Agenda 02/28/2023 Item #16F 7 (Change Order #3 and Change Order #4 to Contract #19-7650 Goldena Gate Folf Courst Redevelopment Project)Proposed Agenda Changes Board of County Commissioners Meeting February 28, 2023 Move Item 16175 to Item 11D: *** This Item continued from the December 10, 2022 BCC Meeting.*** Recommendation to approve an increase of authorized expenditures through an exemption from the Competitive Process to JW Marriott Marco Island for tourism promotional expenses up to $85,000 per fiscal year for a five-year period and to make a finding that this expenditure promotes tourism, and that the exemption waiver is the best interest of the County. (Via separate requests of Commissioners Saunders, LoCastro, and McDaniel) Move Item 16F7 to Item 11E: Recommendation to approve Change Order No. 3 and Change Order No. 4 under Agreement No. 19-7650, Golden Gate Golf Course Redevelopment Project, providing for a time extension of 730 days and a realigning of task funding with a zero -dollar change and to approve payment of invoices for work associated with Change Orders No. 3 & No. 4, which was verbally staff directed prior to approval of those change orders. (Project No. 80412) (Via separate requests of Commissioners Saunders and LoCastro) Move Item 16176 to Item 11F: *** This Item continued from the December 10, 2022 BCC Meeting. *** Recommendation to approve an increase of authorized expenditures through an Exemption from the Competitive Process to Visit Florida for membership fees and destination marketing programs up to $150,000 per fiscal year for a five-year period, to allow purchasing card use when the use of purchase order is not possible or practical, to make a finding that these expenditures promote tourism, and that the exemption waiver is in the best interest of the County. (Via separate requests of Commissioners McDaniel and LoCastro) Notes: Item 10D references 241h Avenue NW. That road is now known as Autumn Oaks Lane. TIME CERTAIN ITEMS: Items 10A to be heard at 9:30 AM: Discuss the request by Quiet Florida to reduce the noise pollution from illegal vehicle modifications. (Sponsored by Commissioner Saunders) Item 10B to be heard following 15B Staff Project Updates: Recommendation to review a draft Escrow Agreement from the Florida Department of Veterans' Affairs (FDVA) and Department of Financial Services (DFS) for the County to appropriate $30 million for the "State Veterans' Nursing Home" project using Infrastructure Sales Surtax Funding (Fund No. 318), convey property interest in the project site, and to approve and authorize the Chairman to execute the final version of the Escrow Agreement once received from the State. (Sponsored by Commissioner Saunders) 2/28/2023 11:53 AM 16.F.7 02/28/2023 EXECUTIVE SUMMARY Recommendation to approve Change Order No. 3 and Change Order No. 4 under Agreement No. 19-7650, Golden Gate Golf Course Redevelopment Project, providing for a time extension of 730 days and a realigning of task funding with a zero -dollar change and to approve payment of invoices for work associated with Change Orders No. 3 & No. 4, which was verbally staff directed prior to approval of those change orders. (Project No. 80412) OBJECTIVE: To approve Change Order Numbers 3 and 4 adding time and realigning existing task funding for zero dollars and approve the payment of invoices associated with same. CONSIDERATIONS: On June 25, 2019, (9275) the Board approved the acquisition of the Golden Gate Golf Course located at 4100 Golden Gate Blvd. (Agenda Item 1 LQ On December 10, 2019, (10932) the Board approved Agreement No. 19-7650 "Collier County Golden Gate Golf Course Redevelopment" with Davidson Engineering in a time and materials amount not to exceed $684,666.50, for all professional services (Agenda Item 16.17.11). The agreement included conceptual planning, community outreach, environmental consulting, golf course site rezoning, and transportation analysis. On September 24, 2020, Change Order No. 1 to Agreement No. 19-7650 was administratively approved. The change order utilized $38,826 of the 10% allowance to provide funding for Phase I, Task 7 surveying tasks necessary for completing lease agreements. This was a zero -dollar net contract change. On May 25, 2021, the Board approved a Long -Term Lease and Operating Agreement with CC BSG Naples, LLC ("BigShots") to operate and manage a twelve -hole public golf course on the former Golden Gate Golf Course property, to lease land for the construction and operation of a BigShots golf/entertainment facility to benefit the residents of Collier County and support the overall redevelopment plan for the property (Agenda Item I LK). On May 26, 2021, Amendment No. 1 to Agreement No. 19-7650 was administratively approved. The amendment replaced Schedule F, Key Personnel for zero dollars to reflect staffing changes at Davidson Engineering. On July 13, 2021, the Board approved Change Order No. 2 to Agreement No. 19-7650 in a time and material amount of $178,273.40 to include services for updating the rezone/GMP amendment, providing for partial ERP permitting, updating the boundary survey and groundwater/environmental tasks. (Agenda Item 16.C.21). On July 27, 2021, the Board approved the Second Amendment to Agreement No. 19-7650 (ratified on September 14, 2021) primarily in a time and material amount of $1,179,786.20. The amendment provided for Phase II (Site Design and Permitting) and Phase III (services during construction). The work provided for the development of the BigShots facility, golf course redevelopment, and further site development. (Agenda Item 16.C.5/16.F.3) On April 26, 2022, the Board approved the rezone of the Golden Gate Golf Course to the MPUD zoning district providing for Golf Course uses, a residential tract, a public use tract and a government facility tract. On November 23, 2022, the Procurement Services Division administratively approved Change Order No. 3 for zero net dollars. Change Order No. 3 realigns $86,682.50 from Site Design and Permitting Phase 2, Task 5, 1.5 Architectural Design Maintenance and Cart Storage to Phase 2, Task 3 Site Development Plan to support obtaining SFWMD ERP and FDEP 404 Permitting. The realignment is required to support work necessitated by unforeseen site conditions and regulatory requirements. This is a zero -dollar net contract change. Change Order No. 4: A time extension is needed to complete the project. Phase 2, Site Design & Permitting tasks have been complicated by the following factors: (1) the Conceptual Environmental Resource Permitting ("ERP") as originally included in the contract encompassed the entire County owned property. This approach was modified to Packet Pg. 1256 16.F.7 02/28/2023 separate the Golf Course from the Big Shots area to expedite the ERP, FDEP and Collier County Site Development Plan permitting; (2) during the permitting process, it was determined that an acoustic survey for Bonneted Bats was required; (3) soil contamination testing was significantly intensified because of more contamination than anticipated; and (4) the SFWMD determined that a FDEP 404 permit (pertaining to wetlands and surface waters) would be needed requiring additional testing and evaluation. The above factors have affected the length of contract time as well as increasing hours necessary to complete required contract tasks. Accordingly, staff recommends approval of the attached Change Order No. 4 providing for a time extension of seven hundred and thirty (730) days and realignment of contract task budgets to provide funding required to support additional permitting and environmental work. Increase Phase 1 Task 5 Concept ERP in the amount of $45,055.00, deduct ($7,425.00) from Phase 1 Task 1 Concept Plan and deduct ($37,630.00) from Phase 1 Task 4 Transportation Rezone GMPA. This is a zero -dollar net contract change. Change Orders No. 3 and No. 4 reflect direction provided verbally prior to the preparation and approval of change orders. This allowed time and material work to exceed task amounts without prior authorization. Staff requests approval for payment of invoices considered "after the fact" (i.e., after the Board's approval of those Change Orders) up to $131,737.50, the task funding realigned by Change Orders No. 3 and No. 4, for otherwise properly documented work under Agreement 19-7650. This issue arises because the consultant was directed to proceed with a revised project approach and proceed with additional work necessitated by unforeseen conditions but the project manager overseeing the project resigned from employment without initiating and finalizing the necessary change orders. FISCAL IMPACT: The current total contract amount under Agreement No. 17-7650 is $2,042,726.10. Task funding realigned by Change Order No. 4 is $45,055.00 for a zero -dollar net contract change. The additional time has no additional net contract fiscal Impact. Funding for Agreement No. 19-7650 is provided in Capital Project Fund (301) under Project No. 80142 (Golden Gate Golf Course Redevelopment). GROWTH MANAGEMENT IMPACT: There is no impact to the current Growth Management Plan standards to ensure the adequacy and availability of viable public facilities. LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for Board approval.-SRT RECOMMENDATION: To approve Change Order No. 3 and Change Order No 4 under Agreement No. 19- 7650, "Golden Gate Golf Course Redevelopment," providing for a time extension of 730 days and a realignment of task funding with a zero -dollar change, approve the payment of invoices for Change Orders No. 3 and 4 as indicated above, and authorize the Chairman to sign the attached Change Orders. Prepared by: Gary McAlpin, Project Manager III ATTACHMENT(S) 1. Change Order No. 3 020923 (PDF) 2. Change Order No. 4 020923 (PDF) Packet Pg. 1257 16.F.7 02/28/2023 COLLIER COUNTY Board of County Commissioners Item Number: 16.17.7 Doc ID: 24630 Item Summary: Recommendation to approve Change Order No. 3 and Change Order No. 4 under Agreement No. 19-7650, Golden Gate Golf Course Redevelopment Project, providing for a time extension of 730 days and a realigning of task funding with a zero -dollar change and to approve payment of invoices for work associated with Change Orders No. 3 & No. 4, which was verbally staff directed prior to approval of those change orders. (Project No. 80412) Meeting Date: 02/28/2023 Prepared by: Title: — Facilities Management Name: Paula Brethauer 02/20/2023 6:28 PM Submitted by: Title: Director - Facilities Maangement — County Manager's Office Name: Ed Finn 02/20/2023 6:28 PM Approved By: Review: County Manager's Office Geoffrey Willig Additional Reviewer Zoning Geoffrey Willig Additional Reviewer Procurement Services Ana Reynoso Level 1 Purchasing Gatekeeper Procurement Services Priscilla Doria Additional Reviewer Procurement Services Sandra Herrera Additional Reviewer Procurement Services Sue Zimmerman Additional Reviewer County Attorney's Office Scott Teach Level 2 Attorney Review County Manager's Office Ed Finn Additional Reviewer Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Office of Management and Budget Susan Usher Additional Reviewer County Manager's Office Geoffrey Willig Level 4 County Manager Review Board of County Commissioners Geoffrey Willig Meeting Pending Completed 02/20/2023 6:36 PM Skipped 02/22/2023 9:32 AM Completed 02/22/2023 9:44 AM Completed 02/22/2023 10:22 AM Completed 02/22/2023 11:45 AM Completed 02/22/2023 11:49 AM Completed 02/22/2023 11:59 AM Completed 02/22/2023 2:53 PM Completed 02/22/2023 2:55 PM Completed 02/22/2023 2:55 PM Completed 02/22/2023 3:16 PM Completed 02/22/2023 4:32 PM 02/28/2023 9:00 AM Packet Pg. 1258 cry 16.F.7.a Procurement Services Change Order Form ® Contract Modification ❑ Work Order Modification Contract M 19-7650 Change #: 3 Purchase Order #: 4500202044 Project #: 80412.3 Contractor/Firm Name: Davidson Engineering Contract/Project: CC Golden Gate Golf Course Redevelopment Project Manager Name: Gary McAlpin/Geoff Willig Division Name: County Managers Office Original Contract/Work Order Amount $ 684,666.50 12/10/16 16F11 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 2,042,726.1 t} 7/31121 16C21 Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 2,042,726.10 2/23/2023 SAP Contract Expiration Date (Master) Dollar Amount of this Change $ 0.00 198.35% Total Change from Original Amount! Revised ContractlWork Order Total $ 2,042,726.101 0.00% Change from Current BCC Approved Amount Cumulative Changes 1 $ 1,358,059.601 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Notice to Proceed 2-24-2020 1 Original 2-23 2023 Last Approved 2I2312023 Revised Date 2123l2023 Date Completion Date Date (includes this change) # of Days Added Select Tasks ❑ Add new task(s) ❑ Delete task(s) ❑ Change task(s) ® Other Provide a response to the following: 1.) detailed and specific explanationlrationale of the requested change(s) to the task(s) and I or the additional days added (if requested); 2.) why this change was not Included in the original contract; and, 3.) describe the impact if this change is not processed. Attach additional information from the Design Professional andlor Contractor if needed. Change Order #3 realigns Phase 2 task funding to provide for required services relative to Phase 2, Task 3, Site Development Plan. This a zero dollar change order. Realign $86,682.50 from Site Design and Permitting Phase 2, Task 5, 1.5 Architectural Design Maintenance and Cart Storage to Phase 2, Task 3 Site Development Plan to obtain the SFWMD ERP and FDEP 404 Permitting authorizations to accommodate the golf course project. 2. These services are necessary to complete Phase 2, Site Design and Permitting but due to unforeseen conditions the quantity of needed services necessary to complete the Phaseitask is greater than anticipated. 3. If this change order is not approved permitting for the redevelopment of the Golden Gate Golf Course cannot be accomplished and the project will not proceed. Digitally signed by WilligGeoHrey 4 Date: 2022.11.1810:46:25-05°oa' 11l18J2022 Prepared by: Date: (Geoff Willig, CMO) Acceptance of this Change Order shall constitute a modification to contract / work order identified above and will be subject to all the same terms and conditions as contained in the contract 1 work order indicated above, as fully as if the same were stated in this acceptance. The adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor I Vendor 1 Consultant 1 Design Professional arising out of or related to the change set forth herein, including claims for impact and delay costs. Accepted by: (Contractor 1 Vendor 1 Consultant / Design Professional and Name of Firm, if project applicable) m�Aft Daw Accepted by: ema7�en� avaw�e ... ku ,-US 'oon5- M062B 2022.11.18 (Design Professional and Name of Firm, if project applicable) McCormickJohn Digitally signed byMrGormlckJohn Approved by: Date: 2022.11.1810:56:16-05'00' (Division Director or Designee) ZimmermanSue oigitaIysigned byzimmermanSue Approved by: Date: 2022.11.23 09:14:55-05'00' (Procurement Professional) Date: Date: Date: Date: M N a) 0 N 0 M Revised: 01/14/2021 (Divisions who may require additional signatures may include on separate sheet.) PROCUREMENT USE ONLY Admin BCC BC ES Rnt Packet Pg. 1259 1 6.F.7.a ATTEST: Crystal K. Kinzel, Cleric of Courts & Comptroller Dated: (SEAL) Approved as to form. and legality: By: Scott R, Teach Deputy County Attorney BOARD OF COUNTY CONMSSIONERS COLLIER COUNTY, FLORIDA MO. Rick LoCastro, Chairman M N O N O M Packet Pg. 1260 16.F.7.a Change Order/Amendment Summary COST TIME CO# AMD# Description Justification Days New Additive (�} Deductive (-) Added Amount Increase Phase 1- Golf Course 1 Redevelopment (task 7-Survey 0 0 0 Provide necessary surveying Design) utilizing related to property leases allowance for zero dollar chan e 1 Replace Schedule F, Key Personnel 0 0 0 Update Ke p y personnel schedule Add additional funding and 2 reallocate existing funding for Phase 178,273.40 0 0 Provide necessary Golf Course 1-Golf Course Redevelopment tasks Redevelopment tasks Add tasks 11 & 12 ( to Phase 1 Golf Course Redevelopment), add Phase 2 tasks Provide for necessary Golf Course 2 1.1 thru 1.9 (Site 1,179,786.20 0 0 Redevelopment, Site Design and Design/Permitting), permitting and Services during add Phase 3 tasks Construction tasks 1 thru 3 (Services During Construction)I Reallocate existing funding from Provide for neccesary Site Design Phase 2 (Site and Permitting as required to 3 Design and 0 0 0 accommodate unforeseen Permitting) task 5, conditions impacting permitting 1.5, to Phase 2 tasks. task 3 Revised: 01/14/2021 (Divisions who may require additional signatures may include on separate sheet.) PROCUREMENT USE ONLY Admin BCC Packet Pg. 1261 1 6.F.7.a From: FirinEd To: SchneebergerSara Subject: email Date: Thursday, November 17, 2022 3:58:39 PM Attachments: image001.pri From:Tocia Hamlin<Tocia(@davidsonengineering.com> Sent: Tuesday, November 15, 2022 2:52 PM To: FinnEd <Ed.FinnPcolliercountyfl.gov> Cc: Jeff Davidson <Jefff@davidsonewineerine.com> Subject: CO #3 - Golden Gate Golf Course EXTERNAL EMAI i This email is from an external source. Confirm this is a trusted sender and use extreme caution when opening attachments or clicking links. Ed, CO#3 is needed to realign the existing budget to obtain the SFWMD ERP and FDEP 404 Permitting authorizations to accommodate the golf course project. Please reallocate $86,682.50 from Phase 2, Task 5, 1.5 —Architectural Design Maintenance and Cart Storage to Phase 2, Task 3 - Collier County Site Development Plan N M N O Thank you, CM M O Tocia Hamlin -Rosa Z Senior Project Coordinator a_ DE DAVIDSON I. N" I P! F F R I h! ('. ESTABLISHED Main: 239.434.6060 tociaCdavidsonengineering, ohm Avw. davi dsonengiiltrefl00-com Under Florida Law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by telephone or in writing. Packet Pg. 1262 Cou� 730 16.F.7.b Procurement Services Change Order Form ® Contract Modification ❑ Work Order Modification Contract #: 19-7650 Change 9: 4 Purchase Order #: 4500202044 Project #: 80412.3 ContractorlFirm Name: Davidson Engineering ContractlProject: CC Golden Gate Golf Course Redevelopment Project Manager Name: Gary McAlpinlGeoff Willig Division Name: I County Managers Office Original Contract/Work Order Amount $ 684,666.50 12/10/16 16F11 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 2,042,726.10 7/31121 16C21 Last BCC Approval Date; Agenda item # Current Contract/Work Order Amount $ 2,042,726.10 2/23/2023 SAP Contract Expiration Date (Master) Dollar Amount of this Change $ 0.00 198.35% Total Change from Original Amount Revised Contract/Work Order Total 1 $ 2,042,726.101 0.00% Change from Current BCC Approved Amount Cumulative Changes 1 $ 1,358,059.601 an a from Current Amount 1 Completion Date, Description of the Task(s) Change, and Rationale for the Change Notice to Proceed 2-24-2020 1 Original 2-23-2023 Last Approved 2l2312023 Revised Date 2/22/2025 Date Completion Date Date (Includes this changi - # of Days Added 730 Select Tastes ❑ Add new task(s) ❑ Delete task(s) ❑ Change task(s) ® Other Provide a response to the following. 1.) detailed and specific explanationlrationale of the requested change(s) to the task(s) and 1 or the additional days added (if requested); 2.) why this change was not included In the original contract; and, 3.) describe the impact if this change is not processed. Attach additional information from the Design Professional and/or Contractor if needed. 1. Change Order #4 provides an additional 730 days. The Golf Course schedule was affected by unforeseen site, regulatory and permitting requirements. More specifically, (1) revising the Environmental Resource Permitting (ERP) approach to allow for phased permitting, (2) unanticipated environmental surveying for Bonneted Bats, (3) intensified soil testing and development of a soil management plan required by permitting agencies. Change Order #4 also realigns ($7,425.00) from Phase I Task I — Charettes, Concepts, Design, Coordination and ($37,630.00) from Phase I Task 4 Transportation -Rezone GMPA, Access Review to increase Phase 1 Task 5 SFWMD Conceptual ERP Permitting in the amount of $45,055.00. The realignment is necessary to fund , unanticipated additional work, environmental studies, inspections, archaeological work, amended ERP approach, and SFWWDI FDEP 404 permitting. 2. The additional time and funding realignment reflects the impact of unforeseen conditions and permitting requirements not anticipated in the original contract. 3. If this change Order is not approved sufficient time and funding for project completion will not be provided. Prepared by: WgMny signed by WifgGaBRray Dale: 2023.02.011I M00 Wool (Project Manager Name and Date: 217123 Acceptance of this Change Order shall constitute a modification to contract ! work order identified above and will be subject to all the same terms and conditions as contained in the contract 1 work order indicated above, as fully as if the same were stated in this acceptance. The adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor ! Vendor ! Consultant 1 Design Professional arising out of or related to the change set forth herein, including claims for impact and delay costs. Accepted by: Date: (Contractor 1 Vendor 1 Consultant 1 Design Professional and Name of Firm, if project applicable) .A1nitPQN .�.'. Y�M'O '•aU5 Accepted by: �n"�°'°"T"�'"° Date: (Design Professional and Name of Firm, if project applicable) Approved by: F i n n E dDigitally signed by FnnEd Date; 2023 02 07 11! 57:48 Date: (Division Director or Designee) Di0mily signed by PeriaPrisdifa DoriaPriSCiiia Dare: 2023.02.071314:03 Approved by:-05'00' Date: (Procurement Professional) M N am 0 N 0 le Revised: 01/14/2021 (Divisions who may require additional signatures may include on separate sheet.) PROCUREMENT USE ONLY Admin BCC BCC ES Packet Pg. 1263 16.F.7.b ATTEST: Crystal K. Kinzel, Clerk of Courts & Comptroller Dated: (SEAL) Approved as to form and legality: By: Scott R. Teach Deputy County Attorney BOARD OF COUNTY COMMISSIONERS COLLIER COUNTY, FLORIDA Rick LoCastro, Chairman eM N CD O N O le Packet Pg. 1264 16.F.7.b Change Order/Amendment Summary COST TIME CO# AMD# Description Days New Justification Additive {+) Deductive {-) Added Amount Increase Phase 1-Golf Course Redevelopment Provide necessary surveying 1 (task 7-Survey Design) 0 0 0 related to property leases utilizing allowance for zero dollar change 1 Replace Schedule F, Key 0 0 0 Update Key personnel Personnel schedule Add additional funding and reallocate existing Provide necessary Golf Course 2 funding for Phase 1-Golf 178,273.40 0 0 Redevelopment tasks Course Redevelopment tasks Add tasks 11 & 12 (to Phase 1 Golf Course Provide for necessary Golf Redevelopment), add Course Redevelopment, Site 2 Phase 2 tasks 1.1 thru 1.9 1 179 786.20 0 0 Design and permitting and (Site Design/Permitting), Services during Construction add Phase 3 tasks 1 thru 3 tasks (Services During Construction)[ Provide for neceesary Site funding Reallocate existing g Design and Permitting as 3 from Phase 2 (Site Design 0 0 0 required to accommodate and Permitting) task 5, 1.5, unforeseen conditions to Phase 2 task 3 impacting permitting tasks. Provide additional contract time to accommodate adjustment to Add additional days for Y approach, unforeseen impact of unforeseen site, conditions, permitting regulatory and permitting requirements and services requirements and realign during construction. Funding 4 task budget from Phase 1 0 0 730 1,825 reallocation required to Task I and from Phase I accommodate additional work Task 4 to increase Phase associated with unforeseen 1 Task 5 SFWMD conditions and revisions to Conceptual ERP project approach. Permitting. M N rn 0 N 0 le 6 z a� O d aM c ns U c d E t v M r r Q Revised: 01/14/2021 (Divisions who may require additional signatures may include on separate sheet.) PROCUREMENT USE ONLY Admin ECC I fall ES Packet Pg. 1265 O M O N CM N O) O N O qq O Z L 4) L 0 IM C w �t V C Cd G t 0 cc y.+ Q Revised: 01/14/2021 (Divisions who may require additional signatures may include on separate sheet.) PROCUREMENT USE ONLY Admin Packet Pg. 1266 16.F.7.b J DAVIDSON Civil Engineering • Planning • Permitting E N G I N E E R I N G ESTABLISHED I Oesigning;:Xceilerrce Revised: February 6, 2023 December 16, 2022 Collier County Facilities Management Division Attn: Ed Finn, Gary McAlpin 3335 Tamiami Trail East, Suite 101 Naples, FL 34112-5356 Email: Ed.finn@colliercountvfl.gov Ga ry.McAI in colliercount fl. ov Re: Professional Services for the Collier County Golden Gate Golf Course Contract No. 19-7650 Davidson Change Order #4 Dear Ed and Gary, Please accept this request to reallocate funds within the existing contract as outlined below. 1. Reallocate $7,425 from Existing Phase 1 Task 1- Charrettes, Concepts, Design, Coordination, to Phase 1 Task 5 - SFWMD ERP 2. Reallocate $37,630 from Phase 1 Task 4 —Transportation — Rezone GMPA— Access Review to Phase 1 Task 5 — SFWMD ERP Please refer to the below scope of work for details. SCOPE OF WORK: Increase Existing Phase 1- SFWMD Conceptual ERP Permitting Task S • As outlined above, this task will increase by reallocating $45,055from existing Phase 1 Tasks 1 and 4. During the Environmental Resource Permitting process, it was determined that additional environmental studies and sewer viewer inspections, not included in the original scope of work/contract, were needed to complete the overall water management design. This extra work scope included contracting with Archaeological and Historical Conservancy Inc. to conduct work needed for the FDEP 404 permitting work. • Additionally, the original contract included a `Conceptual' Environmental Resource Permit for the entire County owned property. It was determined by CC that the driving range should be treated separately to expedite the ERP & 404 FDEP Permitting for the driving range area. The `Construct to Operate' ERP Permit for the driving range area has been approved. This scope change includes SFWMD/FDEP 404 permitting needed to obtain the construction and operation Environmental Resource Permit. Fee: Increase Existing Phase 1 Task 5 Fee by $45,055 4365 Radio Road • Suite 201 • Naples, FL 34104 • P: 239.434.6060 • www.davidsonengineering.com Packet Pg. 1267 16.F.7.b General Notes I Deliverables L Schedule; 1. Deliverables will match the existing contract. 2. This work will be completed within the existing NTP timeline. The time and material charges (noted as Estimate) will be billed monthly in accordance with the attached standard rate schedule. Work can commence immediately upon receipt of your written acceptance of this contract. Sincerely, J # Davidson, P.E. President Page 2 of 2 Packet Pg. 1268 16.F.7.b DAVIDSON E N G I N E ER I N G ESTABLISHED ; REVISED: February 6, 2023 December 13, 2022 Collier County Facilities Management Division Attn: Ed Finn, Gary McAlpin 3335 Tamiami Trail East, Suite 101 Naples, FL 34112-5356 Email: Ed.finnCo)coiliercountyfl.gov Ga .McAI in colliercount fl. ov Civil Engineering • Planning • Permitting DesigningExcellence Re: Professional Services for the Collier County Golden Gate Golf Course Contract No. 19-7650 Davidson Change Order #4 — Time Extension Request Dear Ed and Gary, Please accept this request to add 730-days to the existing contract due to expire on February 23, 2023. This will extend the contract through February 22, 2025. A time extension is needed to complete the golf course portion of the project. The overall Collier County Golf Course project schedule was affected by three major scope changes listed below. I. The Conceptual Environmental Resource Permitting (ERP) as originally included in the contract encompassed the entire County owned property including the driving range area. It was determined by CC that the driving range should be treated separately to expedite the ERP, FDEP and CC Site Development Plan permitting for that portion of the property. 2. During the permitting process through the state agencies, it was determined that an acoustic survey for bonneted bats was required. This was not in the original scope. 3. The original soil contaminate testing scope was intensified because preliminary testing indicated that there is more soil contamination than originally anticipated due to past golf course use and maintenance area use. It was determined by SFWMD that a FDEP 404 would be needed therefore a higher level of new soil testing was required. Please contact me directly at 239.434.6060 should you have any questions or concerns. Sinter r1 Je D s n . . resident 4365 Radio Road • Suite 201 9 Naptes, FL 34104 • P: 239.434.6060 0 www.davidsonengineering.com Packet Pg. 1269