Agenda 2/14/2023 Item #16C 7 (Phases of Sports Complex and approve Change Order No. 14 for extention of time neccessary to accommodate unforeseen delays)16.C.7 02/ 14/2023 EXECUTIVE SUMMARY Recommendation to accept a project update on the Collier County Sports Complex and approve administrative Change Order No. 14 to Collier County Sport Complex Phase 2.1 and 2.2A Agreement No. 17-7198 with Manhattan Construction (Florida), Inc., for a time extension of 45 days (Project 50156) OBJECTIVE: To provide the Board with an update on the current and future phases of the Sports Complex and approve Change Order No. 14 for extension of time necessary to accommodate unforeseen delays as discussed below. CONSIDERATION: Phase 1 update: Phase 1 construction is completed with buildings and improvements open to the public. All punch list items have been completed, there are a few permits that Manhattan Construction is working on with the Growth Management Division to close out. Notwithstanding the foregoing, the improvements in this phase are in use by the County. Phase 2 update: The excavation of water management areas and other related site construction elements are largely completed. The extension of City Gate Boulevard North is approximately 98% complete, internal roadways, and parking lots are approximately 95% complete. The addition of four sports fields is approximately 95% complete (fields 5, & 6 are 100%, fields 7 & 8 are 90%). The current contract substantial completion date is January 30, 2023, with a final completion date of February 28, 2023. While the contractor is making substantial progress toward completion, because of FPL material delays staff estimates actual substantial completion will be 45 days beyond the January 30, 2023, contractual substantial completion date. Change Order #14 to Collier County Sport Complex Phase 2.1 and 2.2A, the Sixth Amendment to Agreement No. 17-7198, provides for a time extension of 45 days to complete Phase 2.1 and 2.2A. This Change Order is for additional time only adding forty-five (45) days to Contract time because Florida Power & Light's ("FPL") design was missing material for four lighting locations on the project. FPL was made aware of the issue and requested that the required material be provided for installation by the Construction Manager's electrician. After numerous repeated requests by Davidson Engineering and Manhattan, the material was not provided until January 25, 2023, which has a preliminary schedule impact of 45 days. Phase 1 & Phase 2 of the Agreement has several matters pending between the parties that need to be addressed and resolved, which include change orders, damages resulting from delays, material price increase claims, and other matters that need to be resolved to close out Phase I to move to open the Phase 2 facilities. The contractor and staff are working cooperatively to resolve those issues and are meeting regularly to work towards settling the outstanding Phase I and Phase 2 issues. Phase 3 update: Phase 3 includes field No. 9 and its associated prefabricated metal building structure (Bldg. 21), the south parking lot and potentially a bathroom structure (Bldg. 18) originally value engineered out of Phase 2. Staff has received the plans and provided comments back to the design team. Bidding for a new contract mechanism separate from the current Manhattan contract is expected to commence in March 2023. Potential start of construction is summer 2023 with an approximate construction timeline of nine to twelve months. Unsolicited Offer for Long -Term Lease or Purchase Update: On November 7, 2022, the County received a letter of interest from 3Step Sports to initiate a dialogue on a possible purchase or long-term lease of the Paradise Coast Sports Complex. Through December staff has had multiple discussions with 3Step Sports. In mid January 3Step advised that changes in leadership will necessitate additional time to generate the promised offer letter. Staff remains engaged. Packet Pg. 979 16.C.7 02/ 14/2023 Phase 4 update: The concept for this phase consists of eleven multipurpose fields (five fields will be softball, mini soccer, and little league, six fields will be baseball and soccer) as well as ancillary buildings. Building selection and design will be determined through the design process. Phase 4 design and construction management services are estimated to be $1.4M with estimated construction costs between $25M and $30M. Financing will be required. Staff will present a design contract and a plan of finance to the Board late summer 2023. The County's Procurement Services Division administratively approved this Change Order No. 14, as authorized by the Board in accordance with its Procurement Ordinance, Section Nineteen, Contract Administration, Section 19, subsection 3.b. FISCAL IMPACT: This project update does not have a fiscal impact. Change Order No 14 is a net zero dollar change. Funding for Sports Complex Project No. 50156 is provided in Sports Complex Capital Improvement Fund (370). Funding for the project is provided by bond proceeds, TDC funds and the General Fund. GROWTH MANAGEMENT IMPACT: There is no impact to the Growth Management Plan related to this action. LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for Board approval.-SRT RECOMMENDATION: To accept a project update on the Collier County Sports Complex and approve administrative Change Order No. 14 to Collier County Sport Complex Phase 2.1 and 2.2A Agreement No. 17-7198 with Manhattan Construction (Florida), Inc., for a time extension of 45 days. (Project 50156) Prepared by: Ayoub R. Al-Bahou, PE, LEED ® GA, ADAC, Principal Project Manager, Facilities Management ATTACHMENT(S) 1. Change Order #14 020223 (PDF) Packet Pg. 980 16.C.7 02/14/2023 COLLIER COUNTY Board of County Commissioners Item Number: 16.C.7 Doe ID: 24586 Item Summary: Recommendation to accept a project update on the Collier County Sports Complex and approve administrative Change Order No. 14 to Collier County Sport Complex Phase 2.1 and 2.2A Agreement No. 17-7198 with Manhattan Construction (Florida), Inc., for a time extension of 45 days (Project 50156) Meeting Date: 02/14/2023 Prepared by: Title: Principal Project Manager — Facilities Management Name: Ayoub Al-bahou 02/06/2023 12:48 PM Submitted by: Title: — Facilities Management Name: John McCormick 02/06/2023 12:48 PM Approved By: Review: Facilities Management Paula Brethauer Director - Facilities Procurement Services Ana Reynoso Level 1 Purchasing Gatekeeper Procurement Services Sue Zimmerman Additional Reviewer Procurement Services Sandra Herrera Additional Reviewer County Manager's Office Ed Finn CMO Completed County Attorney's Office Scott Teach Level 2 Attorney Review Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Office of Management and Budget Susan Usher Additional Reviewer County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review County Manager's Office Amy Patterson Level 4 County Manager Review Board of County Commissioners Geoffrey Willig Meeting Pending Skipped 02/08/2023 9:48 AM Completed 02/08/2023 9:58 AM Completed 02/08/2023 10:17 AM Completed 02/08/2023 12:44 PM 02/08/2023 2:37 PM Completed 02/08/2023 3:20 PM Completed 02/08/2023 3:20 PM Completed 02/08/2023 3:22 PM Completed 02/08/2023 3:34 PM Completed 02/08/2023 3:50 PM 02/14/2023 9:00 AM Packet Pg. 981 16.C.7.a ❑ this exhibit is not applicable EXHIBIT F CHANGE ORDER ® Contract Modification ❑ Work Order Modification Contract #: 17-7198 Change #: 14 Purchase Order #: 4500209838 Project #: 50156 Contra ctorlf=lrm Name: Manhattan Construction Florida Inc. Project Name: Phase 2.1 Collier County Sports Complex Project Manager Name: Ayoub AI-bahou, P.E.,ADAC,LEED GA department: Facilities Management Original Contract/Work Order Amount $ 32,998,449.0 11.13 1218/20 Original 13CC Approval mate; Agenda Item # Current BCC Approved Amount $ 29,688,852.4 11.13 12/8/20 j Last BCC Approval Date; Agenda Item # i Current Contract/Work Order Amount $ 29,688,852.43 2/28/2023 ASAP Contract Expiration Date (Master) Dollar Amount of this Change $ 0.00 -10.03% Total Change from Original Amount j Revised ContractlWork Order Total 1 $ 29,688,852.43 0.00% IChange from Current BCC Approved Amount Cumulative Changes 1 $ (3,309,596.57)11 0.00% CChange from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Notice to Proceed Original Last Approved Revised Date Date Completion Date 61e122 Date 2128123 Includes this change) 4l14123 # of Days Added 45 Select Tasks ❑ Add new task(s) ❑ Delete task(s) ❑ Change task(s) ® Other (see below) Provide a response to the following: 1.) detailed and specific explanationlrationale of the requested change(s) to the task(s) and l or the additional days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the impact of this change Is not processed. Attach additional information from the Design Professional and Contractor if needed. 1) This change order requests the following: This Change Order is for additional time only adding forty-five (45) days to Contract time due to FPL's design was missing material for 4 lighting locations on the project. FPL was made aware of the issue and requested that the required material be provided for installation by Construction Manager's electrician. After numerous repeated requests by Davidson Engineering and Manhattan, the material was not provided until January 2V11 Which has preliminary schedule impact of 45 days in Manhattan request in its Notice of Claim. 2) The changes were not included in the original contract because F.P.& L. is direct vendor of Collier County and Construction Manager does not have any control over their performance, 3) If the Change Order is not processed the contractor will not be credited for additional project time needed because of factors outside of the contractor's control. AI-bahouAyoub Digitally signed by Al-bahouAyoub Prepared by: Date: 2023.01.27 10:21:06-05'00' Date: _ (Ayoub Al-bahou, P.E.,ADAC, LEED GA, Principal Project Manager, Facilities Management Division) Acceptance of this Change Order shall constitute a modification to the contract/work order identified above and will be subject to all the same terms and conditions as contained in the contract 1 work order indicated above, as fully as if the same were slated in this acceptance. The adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor 1 Vendor I Consultant 1 Design Professional arising out of or related to the change set forth herein, including claims for impact and delay costs. Packet Pg. 982 16.C.7.a C�jllglly slpnad by Craig pryaM C �� I Bryant C C=US, ECam an ,OUm Vice reside t.GN com, Bry anhatlnn �1 - Cai61mc8on Campany,OU-�co PresSdenl, CN=Cralp Bryant Accepted by: oaibzoza.ot.antzzast-asop Dale: (Manhattan Construclion Florida, Inc.) —.10 UaMson. a=UaYdwn FE,gia�ty u9ned byJosh F.0 En�fn—Ing,—Englrwerhg. �� o0. c=us, e�fr,tlhgpen-eag.wm, o vioso nmai=Jenr�6nVlIs ergtnnanrg, PENINSULA i&i-a do:da En2u.p.ClpJosh zo7a.otsnoiae;tz-0s'pn FNGN�Iff_RINGeio.mxnoi.vrt:xs_aaasnrc Approved 6y: � .r. Date: (Davidson Engineering) Approved by: Approved 6y: McCormickJohn Digitally signed byMcCormickJohn t� Date: 2023.01.30 14:45:13-05'00' Date: �n McCorrmick rim Division Director) Date: (Procurement roTessional) Q H Packet Pg. 983 16.C.7.a ATTEST: Crystal K. Kinzel, Clerk of Courts & Comptroller Dated: (SEAL) Approved as to form and legality: By: Scott R. Teach Deputy County Attorney BOARD OF COUNTY COMMISSIONERS COLLIER COUNTY, FLORIDA Rick LoCastro, Chairman - rS Packet Pg. 984 16.C.7.a Change Order/Amendment Summary COST TIME C0ft AMD# Description Justification s Da Additive (*) Deductive (-) Added New Amount To deduct builders' risk The use of the owner's 1 insurance and (;1 E303,tiU) allowance and deduction for the approve the use builder's risk insurance would of owners survey not be recognized. allowance. To approve the The use of the subcontractor's 2 use of the allowance would not be subcontractors recognized allowance. To approve the The use of the owner's 3 use of owners allowance would not be testing allowance. recognized. To deduct and 4 approve Direct ($753,3t35.80) To take advantage of sales tax Material savings. Purchases. To approve the The use of the owner's use of Owner contingency would not be 5 Contingency for ($1,627,901.54) recognized. To take advantage price escalation. of sales tax savings. DMP Turf 6 reallocate SDI to To reconcllelreallocate SDI the proper line To deduct and approve Direct To lake advantage of sales tax 7 Material ($189,635.66) Purchases. Core savings. & Main To deduct and approve Direct Material 8 Purchases. ($1,095,177.51) To take advantage of sales tax Conrad savings. Yeivington and Sportsfield Specialties Project time will be lost due to 9 To extend the 60 516 both material shortages and time by 60 days shipping delays, ripple effects of the COVID-19 pandemic Deduct allowances that Deductive change and Project are not being increase amounts would not be Extended utilized. Extended recognized, Project time will be 10 GCs and GIRS (3,088.63) 145 661 lost due to both material Increase to the shortages and shipping delays, project due to ripple effects of the COVID-19 materials delays pandemic And to extend the time by 145 days Packet Pg. 985 16.C.7.a Change Order/Amendment Summary CO# AMD# Description COST TIME Justification Additive {+) Deductive (-} ass Added New Amount 11 To approve the use of Owner Contingency for changes to the project 0 661 The use of the owner's contingency would not be recognized. 12 Reversed of DMPoriginally approved on CO #8 $506 395.57 0 661 Local supplier cannot provide the required material 13 Hurricane Ian Impact 0 0 60 721 Adding 60 days due to Impact of Hurricane Ian to the site 14 FP&L schedule impact 0 0 45 766 Adding 45 days due to lack of FP& L material a) E i= r. Packet Pg. 986 16.C.7.a Manhattan Construction Group 239.643.6000 (office) 3705-1 Westview Drive 239.643.0090 (facsimile) Naples, FL 34104 www.manhattanconstructiongroup.com Manhattan Building excellence. January 25, 2023 Facilities Management Division Ayoub AI-Bahou Principal Project Manager 3335 Tamiami Trail East Naples, FL 34112 RE: Notice of Claim for Delay and Impacts, FPL 43 Collier County Sports Complex Dear Mr. Al-Bahou, As we have discussed previously, Florida Power & Light continues to impact our ability to complete the project. As a direct vendor to Collier County, MCC has no control over their performance and they have, on multiple occasions, failed to deliver necessary materials to the project so that our contract work to install the material can be completed. This is the 3'd of such delays by FPL and our contract has been previously extended for these events. On November 41, while reviewing the as-builts for the FPL conduit, Davidson Engineering discovered that FPL's design was missing material for 4 lighting locations on the project. MCC and Davidson Engineering immediately made FPL aware of the issue and requested that the material be provided for installation by our electrician. After numerous repeated requests by Davidson Engineering and Manhattan, the material was not provided until today, January 25`t'. We will also need approximately 5 days to install the material, 10 days to as -built and 5 days to revise and record easements. Furthermore, FPL has subsequent work to complete after MCC completes the installation of the conduit. This includes of street lighting, parking lot lighting and pathway lighting. All of this work will be required to be finished by FPL in order for MCC to pass final inspections on the site and achieve Substantial Completion. While there are concerns for FPL's ability to furnish material and labor to complete their work, the full impact to MCC's ability to achieve Substantial Completion is not currently known due to FPL's inability to provide a schedule, It's due to these conditions that MCC respectfully requests an extension of time of 45 days now and further reserves its rights to additional time as additional delays occur. Regards, Craig Bryant Vice President Manhattan Construction Company kU?rr CAC Packet Pg. 987