Agenda 2/14/2023 Item #16A 1 (Approve Change order No. 3 to design the relocation of an exsisting non-profit water main and associated utility apputenances for the Vanderbilt Beach Road Widening Goodlette-Frank Project)16.A.1
02/ 14/2023
EXECUTIVE SUMMARY
Recommendation to approve administrative Change Order No. 3 to Agreement Number 19-7494, "Design
and Related Services for Vanderbilt Beach Road Widening from east of U.S. 41 to east of Goodlette-Frank
Road," with Jacobs Engineering Group Inc., to design the relocation of existing utilities, and increase the
budget in the amount of $96,412. (Project Number 60199)
OBJECTIVE: To approve Change Order No. 3 to design the relocation of an existing non -potable water main and
associated utility appurtenances for the "Vanderbilt Beach Road Widening from east of U.S. 41 to east of
Goodlette-Frank Road," Project 60199 (the "Project").
CONSIDERATIONS: On February 25, 2020, the Board approved Agreement Number 19-7494 (Agenda Item
1 LQ with Jacobs Engineering Group Inc., to provide Professional Design Services for the Project in the amount of
$1,058,378. In November of 2022, the Project achieved the 90% design phase.
Change Order No. 3 addresses specific utility design items that are typically completed by the Collier County
Public Utilities Division; however, the roadway improvement schedule will be significantly delayed if the utility
work is not contemporaneously incorporated into the Project. The necessary utility design items have been added to
the roadway design scope to expedite the design while maintaining the grant -funded construction schedules.
The County's Procurement Services Division administratively approved the Change Order form, as authorized by
the Board in accordance with its Procurement Ordinance, Section Nineteen, Contract Administration, Subsection
3b.
FISCAL IMPACT: This change order will be funded through the following source:
Project Number I Department I Fund I Amount I Source of Funds
70240.6 I PUD 1 414 I $96,412.00 I Wastewater Capital
GROWTH MANAGEMENT IMPACT: This project is in accordance with the goals and objectives of the
Transportation Element of the Growth Management Plan.
LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for
Board approval.-SRT
RECOMMENDATION: To approve Change Order No. 3 to Agreement Number 19-7494, "Design and Related
Services for Vanderbilt Beach Road Widening from east of U.S. 41 to east of Goodlette- Frank Road," with Jacobs
Engineering Group Inc. to design the relocation of existing utilities, increase the budget in the amount of $96,412,
and authorize the Chairman to sign the attached change order. (Project Number 60199)
Prepared by Dennis F. McCoy, P.E., Sr. Project Manager, Transportation Engineering Division, Growth
Management Department
ATTACHMENT(S)
1. [Linked] 19-7494 JacobsEngineering_Contract- (PDF)
2. CO #3 Jacobs 010423 (PDF)
Packet Pg. 549
16.A.1
02/ 14/2023
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.A.1
Doc ID: 24114
Item Summary: Recommendation to approve administrative Change Order No. 3 to Agreement Number 19-7494,
"Design and Related Services for Vanderbilt Beach Road Widening from east of U.S. 41 to east of Goodlette-Frank
Road," with Jacobs Engineering Group Inc., to design the relocation of existing utilities, and increase the budget in
the amount of $96,412. (Project Number 60199)
Meeting Date: 02/14/2023
Prepared by:
Title: Project Manager — Transportation Engineering
Name: Dennis McCoy
01/05/2023 8:54 AM
Submitted by:
Title: Division Director - Transportation Eng — Transportation Engineering
Name: Jay Ahmad
01/05/2023 8:54 AM
Approved By:
Review:
Transportation Engineering
Marlene Messam
Additional Reviewer
Completed
01/05/2023 9:15 AM
Transportation Engineering
Jay Ahmad
Additional Reviewer
Completed
01/05/2023 9:43 AM
Procurement Services
Ana Reynoso
Level 1 Purchasing Gatekeeper
Completed
01/05/2023 11:04 AM
Procurement Services
Sandra Herrera
Additional Reviewer
Completed
01/06/2023 9:40 AM
Growth Management Department
Lisa Taylor
Additional Reviewer
Completed
01/06/2023 1:47 PM
Growth Management Department
Jeanne Marcella
Transportation Management Services Department
Completed
01/09/2023 3:44 PM
Growth Management Operations Support
Tara Castillo
Additional Reviewer Completed
01/10/2023 3:25 PM
Growth Management Department
Gene Shue
Additional Reviewer
Completed 01/10/2023 6:51 PM
Procurement Services
Sara Schneeberger Additional Reviewer
Completed 01/17/2023 2:24 PM
Public Utilities Planning and Project Management
Matthew McLean
Additional Reviewer Completed
01/20/2023 7:53 AM
Procurement Services
Sue Zimmerman
Additional Reviewer
Completed 01/25/2023 5:54 PM
County Attorney's Office
Scott Teach
Level 2 Attorney Review
Completed 01/26/2023 8:23 AM
Growth Management Department
Trinity Scott
Transportation
Completed 01/27/2023 1:19 PM
County Attorney's Office
Jeffrey A. Klatzkow Level 3 County Attorney's Office Review
Completed 01/27/2023 3:47 PM
Office of Management and Budget
Debra Windsor
Level 3 OMB Gatekeeper Review
Completed 01/30/2023 9:28 AM
Office of Management and Budget
Susan Usher
Additional Reviewer
Completed 02/02/2023 2:10 PM
County Manager's Office
Ed Finn
CMO Completed
02/02/2023 2:16 PM
Packet Pg. 550
16.A.1
02/ 14/2023
County Manager's Office
Board of County Commissioners
Amy Patterson Level 4 County Manager Review
Geoffrey Willig Meeting Pending
Completed 02/06/2023 11:22 AM
02/14/2023 9:00 AM
Packet Pg. 551
16.A.1.b
Procurement Services
t} ; l�T" County Change Order Form
N Contract Modification ❑ Work Order Modification
Contract #: 19-7494 Change M 3 Purchase Order #:) 45002023255 —� Project #: 601gg
Contractoffirm Name: Jacobs Engineering Group - -- I Contract/Project: Vanderbilt Beach Road 6-Lane Widening
Project Manager dame: Uonnis F. McCoy _.-- ^� Division Name: rranspartation Engineering Division -
Original Contract/Work Order Amount
_ $
1,058,378.00
2/25/2020,11C
iOriginal BCC Approval date; Agenda Item #
Current BCC Approved Amount
_—$-
1,444,630.00
8l?3/2022116E1
,Last BCC Approval Date; Agenda Item #
Current Contract/Work Order Amount
$
1,444,630,00
8/4/2024
'SAP Contract Expiration Date (Master)
Dollar Amount of this Change
$ 96,412.00
45,60%
'Total Change from Original Amount
Devised Contract/Work Carder Total
$
1,541,042.00
6,67%
.Change from Current BCC Approved Amount
Cumulative Changes _
$
482,664.00
6.67%
Change from Current Amount '
Cpiiiipletiori Date, Descrlptian of the Task(s) Change, and Rationale for the Change
Notice to Proceed 311812020 "'Original -9l9l2023 Last APp rov 814/2024 Revised Date 8/4/2024
Date - Completion Date -.. Date �--__] (Includes this change) - —�
# of Clays Added = Select Tasks ® Add new task(s) ❑ Delete task(s) Z Change task(s) ❑ Other
Provide a response to the following-1.) detailed and specific explanationlrationale of the requested change(s) to the task(s) and ! or
the additional days added (if requested); 2.) why this change was not included in the original contract, and, 3.) describe the impact
if this change is not processed. Attach additional information from the Design Professional and/or Contractor if needed.
1. As the project design is refined, the location of the proposed signal mast arm foundation and an existing non -potable water main are
in conflict. -the proposed mast arm foundation cannot be relocated; therefore, the water main and all the associated appurtenances
must be moved, including Air Release Valves (ARVs), These changes will result in modifications to the design and post -design
services being performed. The total budget is $96,412.00.See Attachment A (Scope of Services) for specific tasks.
2. 'The Public Utilities Division (PUD) owns 5 the watermain facilities and agreed that the redesign could be included in the roadway
improvements for the project to remain on schedule. The i=DOT is providing a $4.2M grant towards the project's construction phase,
and these funds must be encumbered in the timeframe set in their work program. Therefore, this change order is necessary to rneet
the grant funding deadline.
3. Not processing this Change Order will require an RPS solicitation process to relocate the utilities and significantly delay the project.
The utilities rrrust be designed and relocated before the roadway improvements can commence.
Prepared by:
m c of g n n Digitally sign22.1 . by M:02:19 -05'0
�% pate: 2022.12.21 13:Q2:19-05'00'
(Dennis k. McCoy, P.E- , Senior Project Manager, Transportation Engineering Division)
Date:
Acceptance of this Change Order shall constitute a modification to contract ! work order identified above and will be subject to all the same
terms and conditions as contained in the contract / work order indicated above-, as fully as if tho same were stated in this acceptance. The
adjustment, if any, to the Contract shall constitute a full and final settlement of any and all clairns of the Contractor / Vendor / Consultant!
Design Professional arising out of or related to the changqe set forth herein, including claims for impact and delay costs.
Digital ly signer/ by Kenneth Michael
Kenneth Michael Wooten woolen
Accepted by:
Date: 2D22.12.21 11:W37-05'00' --- ._._.-.�______. Date:
-.--_-..
(Ken Wooten, P.E., Jacobs EngineWring Group)
Approved by:
Digitally signed by AhmadJay
Date: 2022.12.21 14:27:37-05'00'
(Jay Ahmad, P.E., Director, Transportation Engineering Division)
Date:
Revised: 01/141202-t (Divisions who may require a0ditional signatLrres may include on separate sheet.) _ PROCUREMENT use otar.v
Admin pf ;} (3CC FS--
Packet Pg. 552
Ii
f
Lt pproved by:
Approved by:
111gilally signed by
ScottTrinity
ScotffrinityDate: 2022.12.22
13:07:12 -05'00'
Date:
(Trinity Scott, Department Head, Growth Management Department)
SchneebergerSara Digitally signed by SchneebergerSara
Date: 2022.12.28 11:52:46 -05'00' Date:
(Sara Schneeberger,Procurement Strategist)
. ............ - -----
Change Order/Amendment Summary
COST
TIME
CO#
AMD#
Description
Justification
Days
New
Additive
DedLICUVe
Added
Amount
Added upsized stormwater
1
Stormwater Improvements were
crossing, additonal
.
included in this project so new
1
permitting requirements
$256,296
90
1360
roadway would not be
and supplemental field
reconstructed later, Permitting
testing for asphalt design
essential to project.
Added dual turn lane north
Best design options to relieve
2
to East and extended right
$129,956
240
'1600
current and future traffic
turn lane east bound at
congestion.
intersection
Design and Post -Design
Best design option to complete
3
for relocation of ARV's and
$96,412,
0
1600
services and not delay
non- potable water line.
construction process
Revised: 0 Ill 4/2021 (Divisions who may mquire additional sigmatures, may indude on separate sheet,)
PROtVRF-1 P �NT N L
AdminPCs
t3CC ES
ce)
cm
I*
Q
V—
Q
to
m
0
0
W
n
0
L)
E
O
Packet Pg. 553
16.A.1.b
ATTEST:
Crystal K. Kinzel, Clerk of Courts
& Comptroller
Dated:
(SEAL)
Approved as to form and legality:
By:
Scott R. Teach
Deputy County Attorney
BOARD OF COUNTY COMMISSIONERS
COLLIER COUNTY, FLORIDA
Rick LoCastro, Chairman
Packet Pg. 554
16.A.1.b
Jacobs Engineering Groin, Ina
5811 Pelican Say Bouiemd
Suite 305 Naples, FL 34188
,.Jacobs Telephone: 239-51 0-1 % 15
ATTAC3Ii1J ENT A
SCOPE OF SERVICES
For
C UANGE ORDER NO.3 -- UTILITY DESIGN SERVICES
TO
CONSULTING ENGINEERING SERVICES AGREEMENT
For
Vanderbilt Beach Road 6 Lane Widening Project (Contract 19-7494)
(East of US 41 to :Gast of Goodlette Frank Road)
County ProjectNo. 60199
Purchase Order: 4500202 325
December 21, 2022
PART 1: OVLRVIEW
Jacobs Engineering lnc. (CONSULTANT) has been requested and retained to provide utility
engineering services associated with Collier Comity 1'ro,ject No. 60199, Vanderbilt Beach Road
6-Lane Widening 'Project (East of CIS 41 to East of Goodlette Frank Road) (PROJECT).
These services were requested by the Collier County Gro'�%,#h Management Depaa-tnaent -
`t'ransportation Engineering Division, per the request of the Public Utilities Department -
Engineering and Proiect Manageraaent Division, The required services will be incorporated
into the 1.00% Plans Submittal.
The attached Scope of Services addresses the following:
*aF Task 4.1: Data Analysis -,in(] Route Alternative(s) for Impacted 20 Inch Nora -Potable
Water Main (NPW — IQ)
Task 4.2: Design Plants/Modifications for Impacted 20 .Inch .Non -Potable Water Main
(NPW-IQ)
y.* 'I`ask 4.3: Air Release Valve (ARV) Evaluation and Design Services
,C- Task 5J: fast Design Services for ARV Removals/Relocations
mot* Task 5.2: Services .During Construction (S.DC) for ARV Design
This Change Order provides for the CONSUL`I"ANT'S services to be n.iodified per the
(`oll(.)wing Scope of Services to Collier COL111ty Project No. 60199.
The reclucste;d scr•vices are; being pe;rforrned under Contract 19-7494 and services are
subject to theTernos and Conditions of that Agreement.
Services regfrired include the fallowing:
Packet Pg. 555
16.A.1.b
PART 2: SCOPE OF W0Rt{
Task 4 —
Task 4.1: Data Analvsis and Route Alterjtativcs for lire reacted 20 heir Non -
Mail] (N1?'Vk'-r01.
CONSi.II.TANT shall analyze existing date and field conditions, evaluate proposed roadway
and signalization improvements o.nd determine the; route alternatives for the impacted existing
20-inch non -potable (NI'W-lQ) line.
Services required include the following:
l . l xistin;� Data Ataalysis -- C'ONSCJL'I'r�N'l' shall analyse the existitaf; 20-inch NI'W- IQ line,
locution and determine impacts of the' proposed Roadway and Signaliz,ation improvernents.
2. Route Altcrraatives%Design MotliCcati(11 s CONSUL"I"AN"T' shall determine alternative
route and deflections ofthe 20-inch non -potable IQ line and/or modifications to proposed
road waylsignalization infrastructure.;
'fast 4.2. Desi n Plansi.Modilicati ms fo : Jr 20 Inch Non -Potable Watermai11 NPW-1
In� ,enacts/Avoidance
CON SUI.!FANT shall prepare design plans -.,and/or rnodity design plans to reflect the needed
design changes to the existing/proposed roadway, signalization and utility infrastrUdUre.
Services required include the f011OWing:
1, Design Plans, Details, t;?Ualltiti
details, quantities and associated
Note: Plans shall he incorporated into
Road Widening Project.
.-.- Prepare new plans/plan modifications,
estimates.
Bid flans and Documents for the Vanderbilt Beach
0 `)UDS"I'Tace UU11ty 1',RCaVat101r t,'.9tJ1-J:
CONSULTANT will perform field review and SUE services, which includes up to two
(2) ten (10) hour days of SUE services within the project limits, to identify existing
Utilities to be avoided by the proposed roadway, signalization and. utilities infrastructure
modifications. If required, "Tie-ir" locations for 20-inch IQ line relocations/deflection
will he identified.
Task 4.3: Air Release Valve (Air
CONSULTANT shall provide engineering:, services to evaluate the existing wastewater system,
located within the median cif Vanderbilt Beach Road, and the associated 14 (fourteen) ARVs for
above -ground relocation, elimination. or r,placernent within the project limits.
Services required include the following;
CON SUI..TANT shall meet with Collier County staf f in person or via video conference to identify
and prioritize AM to be assessed.
Packet Pg. 556
16.A.1.b
CONSULTANT shall review the (
provided by the Collier County and/c
CONSCJ1_ TANT shall visit each AM
above -ground relocation, elimination
CONS UI..,'.l'AN I-' shall prepare a tech€
u ARV location neap and descriptio
o Recommendations :for the replace
* Alternatives for those ARVs to N
Force main diameter
a Photographs of the existing condi
o Sketches of'any proposed relocati
CONSULTANT will prepare design
withilt the project limits.
'>F"ASK 5 -- Bicldhw, Service011ost D
1'ask
Biddinf,y Assistance
CON'SUl. TAN'T' shall assist COUN- Y in
CONSULTANT shall provide a summary
construction and permitting issues, and be
bidders. CONSUL,"l"ANT shall respond to
the COUNTY in preparation of any neces:
apparent lore hid for consistency and respt
necessary to award the: contract..
Task 5.2: S
CUNT UI. TANT will provide the followi
ARV relocations:
• Provide contract document interpre;tatl
OU'D and unforeseen conditions whe€',
• Periodic, meeting attendance (assumes
visits (as required to respond to R171's'
• Assist the C:ONSU1..,TAN`l, with shop''
• Review and assist in field changes wh
CONSUI..:'T'ANT.
• Attend one (1) substantial completion
PART 3: EXCLUSIONYASSUMPTIONS:
The following task's are not inCluded in th
1) Services other than those specifically
2) I %.isting 20-Inch Water Main (.NPW-
3) Directional Brill of20-Inch Watcrni
ollier County available record drawings and information
(JIS files,
site;, inventory the existing conditions, and evaluate each for
or replacement.
cal €memo which will include, but not limited to:
with GIS lD number
.-ient, relocation, or elimination of each ARV (14)
relocated in highly exposed locations (ARV protection)
ns
an,, for removal or relocation of up to 1.4 (fourteen) ARV's
reparing for and attend one pre -bid conference.
f'the final ARV design including design,
vailable to answer questions Erom the prospective
aۥions questions that arise during bidding; and assist
pry addenda. CONSUL,"I"AN'T'shall review the
€siveness and provide input to the CONSULTANT as
sDC;) for ARV Design
li€nited services during constrt€ction ill support of the
on and assistance in addressing requests for in6ormation
requested by the CONSUI..'FANI`.
two (2) meetings per month during construction) and field
and review construction progress).
,ving review(s).
include minor redesign as requested by the
walk through meeting in the field.
Scope of Work for this Change Order:
isted above.
'Q) "Upsizing" is not anticipated/included
i (Nl'W-I/Q) is not anticipated/included
M
N
I*
0
0
W
m
O
0
O
O
U
E
s
a
Packet Pg. 557
16.A.1.b
4) Complete 20-Inch NPW-IQ replacement under VBRA.j'oodlette Intersection is itot
anticipated/indLldcd
5) Geotechnical Services not anticipated/included
G) Utility Permits and/or Permit lees not anticipated/included
7) Collier County ROWPermitting
PART 4: PIZO.IECT SCIIEDIJLE-
Modification to Project SClaedrrle
6 :Project Schedule shall be increased by a total of[} Caler}d:rr Da .s
PART S: COMPENS A`.I ION:
An estimated budget to be utilised for the above; tasks has been established and is shown as
Attachment A — Manhom- and Cost Ii stiinate Surnmait y. A man-hour estimate for the: above;
Scope of Services has been prepared for the sole purpose of establishing the maximum upset
limit for this Task Work Order not to exceed $96,412.00
a The COUNTY will corripensate the CONSULTANT a lee ol'$82,.128.00 for TASK(S)
4.1., 4.2, & 4.3 "Design" and "Expenses" on as LUMP SIJM Basis
• The COUNTY will compensate the CO.NSIJLTANT a fete o.f $I4,2i14.00 'rASK(S) 5.1,
& f+.2 "Post -Design Services" on a'I'I1V1.1: AND MATERIALS Basis
The hourly- labor rates shown for staff reflect the Rate :schedule agreed upon and match
those recently approved under Conti —act 0-7494.
Utilities llivision Budgct $9C,417,00 ("I'aaslc 13i,etikcdo.�vn included i►i F(,
Le Skacet
•3 `l'ransi)ortvtion Division Budget — $0.00 (bask BreakdLown included in sec Sheet
Packet Pg. 558
A
--- ---
-- ---
II
nl
A
C4
Ce)
CM
q*
CD
T-
CD
0
0
w
Ce)
0
CD
E
m
0
m
po-,
Packet Pg. 559
16.A.1.b
SiNcE 1946
ENGINEERING
December 21, 2022
Mr. Bi11 Grunter, P.1 ., A1CP
Jacobs Engineering Group
5801 Pelican Bay Boulevard Suite 505
Naples Florida, 34 1. 08
Re: Change Order No. 3 tnr- Vanderbilt Beach Road 6 l.,ane Widening Air Release Valve (ARV)
Design Services and S€rbsurface Utility Excavation (SUE) in supporfi of Horizontal Directional
Drill Design Services
Dear Mr. Grainer.
Please accept this letter as our Change Order No. 3 proposal to provide Jacobs Engineering Group
(CONSULT —ANT) Air Release Valve (ARV) design services and Subsurface Utility Excavation (SUE) in
support of horizontal directional drill design for tine above reference project. 'Phis proposal includes two (2)
tern (10) Dour clays of SUE services. The overall pr`c�lect limits are defined as Vanderbilt Beach Road (C.R.
862) from U,S. 41 to Airport -Pulling Road within existing Collier County maintained right-of-way.
OVERVIEW
JOHNSON ENGINEERING (SUB -CONSULTANT) CHANGE ORDER NO. 3 SCOPE OF
SERVICES:
Task 4.2 - Additional SUE Services in Support 14 Horizontal Directional Drill Design
SUB -CONSULTANT will perform field review and SUE services, which includes up to two (2) ten (10)
hour days of SUE services within the project limit;;, to identify existing utilities to be avoided by proposed
horizontal direction drill design for Collier County, ro-use main.
Task 4.2 nee: $8,500,00 (LUMP SUM}
Task 4.3 — Air Release Valve (ARV) Evaluatioo And Design Services
SUB -CONSULTANT will provide engineering services to assist CONSULTANT with fire evaluation and
analysis of the wastewater system for up to 14 (fourteen) AR.Vs for above -ground relocation, elimination,
or replacement within the project limits.
• SUB-CONSUTA'ANI"' will meet with Collier County staff in person or via video conference to
identity and prioritize AR -Vs to be assessed.
• The SUB -CONSULTANT will review, the Collier County available record drawings and
information provided by the Collier County anchor Cjls files.
• SUB -CONSULTANT will visit each ARV site, inventory the existing conditions, and evaluate
each for above -ground relocation. elimin€i io►n, or replacement.
• SUB -CONSULTANT will prepare a technical memo which will include, but not limited to:
• ARV location map and description with GTS 1D number,
• recommendations for tine replacementg relocation or elimination of each ARV,
• alternatives for those ARVs to be relocated in highly exposed locations (ARV protection),
• force main diameter,
2350 Stanford Court Naples, Florida 34112
(239) 434-0333 ■ Fax (239) 434-9320 GAO
Packet Pg. 560
16.A.1.b
Vanderbilt Beach Road G Lane; Widening
December 21. 2022
I'age 2
photographs of the existing conditio€
s sketches of any proposed relocation.
b SUB-CONSULTAN1, will prepare; deli
ARV's within the project limits,
Task 5.I --- AJZV Bidding .Assistance
SUB-CONSIA.TANT shall Bassist CONSULTAN'
SUB-CONSULTANTshall provide a ,summary of
permitting issues, and he available to answer questi
shall respond to various questions that arise durin
necessary addenda. SUi13-CONSULTANT shall
responsiveness and provide input to the CONSUL`
Task 5.2 — Services During Cmistr•uction (SDC)
SUB-CONSUI ]"ANI° will provide the CONSUL
in support of the ARV design:
plans for removal or relocation of up to 14 (fourteen)
Task 4.3 Fee: $44,628.00 (LUMP SUM)
I' in preparing for and attend one pre -laid conference.
he final ARV clesign including design, construction and
ins from the prospective bidders. SUB-CONS(A..,TANT
bidding and assist the: COI..JNI'Y in preparation of any
review the apparent loin bid for consistency and
'ANTas necessary to € ward the Contract.
Task 5.1 Fee; $3,760.00 (NTE)
for ARV Design
NT tlrc Li3lioiwing lirnited services during construction
e Provide contract document interpretation and assistance in addressing, requests for information
(R.1"I) and unforeseen conditions when recit[ested by the CONS U1.. NS'T'ANI
o Periodic €necting at€endanco (assu€Ties two: (2) €neetings per month during construction) and field
visits (as required to respond to RPI's and review co€tstruction progress).
• Assist the CONSULTANTwith shop draw;ing review(s).
• Review and assist in field changes tivhieh include minor redesign as requested by the
CONSULTANT.
Attend one (1) substantial completion walk through meeting in the field.
The following tasks are not included in the Scope 617 Work for this Change Order Proposal:
• Construction administration services
5e]'wiCeS clueing co€Istrr.€ction other than t
in Task 4.
* Collier County Right -of -Way Permitting
listen above or requiring more effort than that listed
'rask 5,2 Fee: $10,524.00 (NTE)
Packet Pg. 561
16.A.1.b
Vanderbilt Beach Road 6 Lane Widening
Deccmbor 21, 2022
Page 3
I11f F SUMMARY `TABLE
Task
i3esc> iI>Elort,—.......m-
1+ee Type u _
l{ee Amount
4.2
Add.itional SUE Services in Support of Horizontal
I„u177P Sun)
$8,500.00
I)trection,al l.)rdl f.) ign—
},3
r1ir Release V�dve (ARV) Evalimtion wid Design
1.,u1n}a Sure
$14,t28.0{)
Services
7.1
ARV
NTE
S3,700,00
5.2
SeFV1C£S I.)ul-ing COI strueiion (SDQ for ARV Des'
NTF
$10,524.00
Thy€nk you for the opportunity to pi-ovide professional services for this projoct, We sincerely appreciate this
opportunity and look forward to Nvorlking with you.
Sincerely,
,IOHNSON ENGINEERING, INC:.
.losl7ua J. l-lildebrmid, RE'.. I)TOL'