Agenda 01/24/2023 Item #16A12 (To help recoup FEMA reimbursement for the construction of emergency sand berms following Hurricane Irma)01/24/2023
EXECUTIVE SUMMARY
Recommendation to authorize the County Attorney to retain outside counsel to work with the County
Attorney, staff and outside consultants, to commence a FEMA arbitration panel with respect to the
Hurricane Irma Federal Emergency Management Agency (“FEMA”) First Appeal Denial of Grants
Manager Project 48791/Project Worksheet 5856.
OBJECTIVE: To help recoup FEMA reimbursement for the construction of emergency sand berms following
Hurricane Irma.
CONSIDERATIONS: Hurricane Irma skirted the Collier County coast and damaged Collier County beaches. An
emergency declaration issued by the President and Collier County proceeded to assess damage and develop a
documented funding request through FEMA. Working with a FEMA hurricane specialist Collier County submitted
a funding request for $1,340,321, in damages to the beach berms.
In November 2022, Collier County received notification that the funding request was denied. The issue on appeal
is whether Collier County complied with applicable Environmental and Historic Preservation requirements
(“EHP”). Collier County was required to make every effort to afford FEMA the opportunity to perform an EHP
assessment prior to construction. Performance of the beach and dune restoration did not procee d until November
2021, and unfortunately, FEMA had not completed its EHP analysis, some four years post Hurricane Irma.
County staff contends that the denial letter references natural beaches, of which the beaches in question are not.
Engineered beaches are not addressed in the denial letter. An EHP evaluation is not necessary because this is
addressed and permitted in the existing engineered beach renourishment permits. The emergency berm was
constructed in the same footprint as the pre-existing facility, which contained the necessary EHP reviews.
If the County wishes to pursue either a second appeal or seek arbitration pursuant to Section 423 of the Stafford
Act, as amended by Section 1219 of the Disaster Recovery Act, notification must be sent within 60 days of the
denial, which is the end of January 2023. (See attached November 30, 2022, Denial Letter) Staff has researched
second appeals over the last two years and have discovered that few, if any, have been granted by FEMA.
However, arbitration during the same time frame has resulted in an approximately 50% success rate. Staff
anticipates defense for an appeal or arbitration to be approximately $30,000, based on the review of this legal issue
on briefs; but could go higher if a formal hearing is held. Based on this research, staff is recommending the County
proceed with arbitration in this matter.
Staff and the County Attorney’s Office has also conferred with its existing FEMA outside counsel who concurs that
the FEMA arbitration process brings the greater likelihood of success, costs approximately the same as a standard
appeal, and usually results in much quicker decisions. The arbitration process involves the appointment of three
FEMA knowledgeable attorneys who review the issue on appeal and render a decision. The County has long
engaged Ernest B. Abbott, who previously served as General Counsel to the Federal Emergency Management
Agency as its general counsel. Mr. Abbott is presently with the law firm of Baker, Donelson, Bearman, Caldw ell
& Berkowitz, P.C. with whom the County already has a retainer agreement in place and can quickly proceed to
issue a purchase order for this service.
FISCAL IMPACT: The County Attorney recommends that the cost of hiring outside counsel and experts be
capped at $30,000, with any additional funding requiring Board approval. Funding for this request is available
within the Stormwater CIP Fund (325), Hurricane Irma Project (50154).
GROWTH MANAGEMENT IMPACT: None.
LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for
Board approval.-SRT
16.A.12
Packet Pg. 550
01/24/2023
RECOMMENDATION: That the Board authorize the County Attorney to retain outside counsel to work with the
County Attorney, staff and outside consultants, with respect to the Hurricane Irma Federal Emergency Management
Agency (“FEMA”) First Appeal Denial of Grants Manager Project 48791/Project Worksheet 5856.
Prepared by: Gary McAlpin, Project Manager III, Transportation Management Services Department
ATTACHMENT(S)
1. 20221130 4337-FL Collier Co GMP 48791 FAR (002) (PDF)
16.A.12
Packet Pg. 551
01/24/2023
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.A.12
Doc ID: 24427
Item Summary: Recommendation to authorize the County Attorney to retain outside counsel to work with the
County Attorney, staff and outside consultants, to commence a FEMA arbitration panel with respect to the
Hurricane Irma Federal Emergency Management Agency (“FEMA”) First Appeal Denial of Grants Manager
Project 48791/Project Worksheet 5856.
Meeting Date: 01/24/2023
Prepared by:
Title: Deputy Department Head – Growth Management Department
Name: Trinity Scott
01/18/2023 9:52 AM
Submitted by:
Title: Deputy Department Head – Growth Management Department
Name: Trinity Scott
01/18/2023 9:52 AM
Approved By:
Review:
Growth Management Department Jeanne Marcella Transportation Management Services Department Completed
01/18/2023 9:54 AM
Growth Management Operations Support Tara Castillo Additional Reviewer Completed
01/18/2023 10:03 AM
Growth Management Department Trinity Scott Transportation Completed 01/18/2023 10:03 AM
Grants Erica Robinson Level 2 Grants Review Completed 01/18/2023 10:04 AM
County Attorney's Office Scott Teach Level 2 Attorney Review Completed 01/18/2023 10:11 AM
County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 01/18/2023 10:15 AM
Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 01/18/2023 10:15 AM
Grants Therese Stanley Additional Reviewer Completed 01/18/2023 10:35 AM
Office of Management and Budget Susan Usher Additional Reviewer Completed 01/18/2023 10:37 AM
County Manager's Office Ed Finn CMO Completed 01/18/2023 3:34 PM
County Manager's Office Ed Finn Level 4 County Manager Review Completed 01/18/2023 4:54 PM
Board of County Commissioners Geoffrey Willig Meeting Pending 01/24/2023 9:00 AM
16.A.12
Packet Pg. 552
U. S. Department of Homeland Security
Region 4
3005 Chamblee Tucker Road
Atlanta, Georgia 30341
www.fema.gov
Kevin Guthrie Therese Stanley
Director Grants Compliance Manager
Florida Division of Emergency Management Collier County
2555 Shumard Oak Boulevard 3299 Tamiami Trail East, Suite 201
Tallahassee, Florida 32399-2100 Naples, Florida 34112
Reference: FEMA-4337-DR-FL
Collier County
PA ID: 021-99021-00
First Appeal, Grants Manager Project 48791/Project Worksheet 5856
Dear Director Guthrie and Therese Stanley:
This is in response to a letter from the Florida Division of Emergency Management (Recipient)
dated June 7, 2022, which transmitted the referenced first appeal on behalf of Collier County
(Applicant). The Applicant is appealing the U.S. Department of Homeland Security’s Federal
Emergency Management Agency’s (FEMA) denial of funding in the amount of $1,340,321.00
on Grants Manager Project (GMP) 48791 for the construction of emergency sand berms on
beaches impacted by Hurricane Irma. The appeal is denied as explained below and in the
enclosed analysis.
The Applicant began construction on the natural beach prior to receiving FEMA approval and
without affording FEMA the opportunity to conduct the necessary environmental and historic
preservation (EHP) compliance reviews. Thus, FEMA cannot ensure that the Applicant
complied with applicable EHP requirements. This letter constitutes the official notification of
this determination to the Applicant.
Under the Robert T. Stafford Disaster Relief and Emergency Assistance (Stafford) Act and
applicable regulations, the Applicant is entitled to appeal this decision.1 If the Applicant elects
to submit a second appeal, it must: 1) contain documented justification supporting the
Applicant’s position; 2) specify the monetary figure in dispute; and 3) cite the provisions in
federal law, regulation, or policy with which the Applicant believes the initial action was
inconsistent. The Applicant may submit the appeal electronically via the FEMA Grants Manager
Portal (GM).
The Applicant must submit the second appeal to the Recipient within 60 days of receipt of this
letter. The Recipient’s transmittal of that appeal, with recommendation, is required to be
submitted to my office within 60 days of receipt of the Applicant’s appeal. My office will
transmit the second appeal to FEMA Headquarters.
1 See Robert T. Stafford Disaster Relief and Emergency Assistance Act, as amended, § 423, 42 U.S.C. § 5189a
(2021); Title 44 Code of Federal Regulations § 206.206 (2021).
November 30, 2022
16.A.12.a
Packet Pg. 553 Attachment: 20221130 4337-FL Collier Co GMP 48791 FAR (002) (24427 : Recommendation to authorize the County Attorney to retain outside
2
If the appeal is submitted electronically in GM, the Applicant should select all relevant
supporting documentation associated with this Project, Damage Inventory, or Applicant Profile
and upload any additional supporting documentation not already in GM. If the Applicant
chooses not to submit its appeal through GM, it must submit all relevant supporting information
with its appeal. For reference, a current index of documents relevant to this determination is
enclosed.
Alternatively, the Applicant may seek arbitration pursuant to Section 423 of the Stafford Act, as
amended by Section 1219 of the Disaster Recovery Reform Act. To determine eligibility for
arbitration, see Title 44 Code of Federal Regulations (44 C.F.R.) § 206.206, Appeals. The
Applicant must submit its request for arbitration simultaneously to the Recipient, the FEMA
Regional Administrator, and the Civilian Board of Contract Appeals (CBCA). Requests for
arbitration cannot be submitted through GM. The CBCA’s rules of procedure for Section 423
arbitrations can be found at 48 C.F.R. Part 6106 and on the CBCA’s website at www.cbca.gov.
If you have questions about FEMA’s arbitration process, please contact Paul Wilson, Acting
Region 4 Public Assistance Branch Chief.
If the Applicant elects not to submit a second appeal request or request for arbitration within 60
days from the issuance of the first appeal decision, this is the final agency determination on the
matter, and the Applicant will no longer be able to appeal or arbitrate the decision.
If you have questions or need additional information, please contact Saidat O. Thomas, Director,
Recovery Division, at (770) 220-5300.
Sincerely,
Gracia B. Szczech
Regional Administrator
Enclosures:
Appeal Analysis: FEMA-4337-DR-FL, Collier County, GMP 48791/PW 5856
Administrative Record Index
16.A.12.a
Packet Pg. 554 Attachment: 20221130 4337-FL Collier Co GMP 48791 FAR (002) (24427 : Recommendation to authorize the County Attorney to retain outside
1
FIRST APPEAL ANALYSIS
FEMA-4337-DR-FL
Collier County, PA ID: 021-99021-00
Grants Manager Project 48791/Project Worksheet 5856
EHP and Other Compliance
Background
Hurricane Irma made landfall in the Florida Keys on September 10, 2017, and tracked up and
across Florida’s peninsula, severely damaging communities along both the west and east coasts
with strong winds, heavy rain, and storm surge. The President declared the event a major
disaster (FEMA-4337-DR-FL) on September 10, 2017, with an incident period extending from
September 4 to October 18, 2017.
As a result of the disaster, Collier County (Applicant) sustained natural beach and dune erosion
that occurred from monument markers R-22+300 to R-79, which includes four beach reaches:
Vanderbilt Beach, Pelican Bay Beach, Park Shore Beach, and Naples Beach.1 Following
Hurricane Irma, FEMA prepared Grants Manager Project (GMP) 48791 to provide funding in the
amount of $1,340,321.00 to bring the dune system to a height that would protect the area against
the threat of damage from a five-year flood event.
In a Determination Memorandum (DM) dated February 21, 2020,2 FEMA denied funding for
GMP 48791 because federal regulations and FEMA policies mandate that Public Assistance
(PA) projects are completed within specific deadlines, subject to approved extensions, to receive
funding for eligible work. FEMA noted that the Applicant had not requested a deadline
extension, nor had it provided sufficient justification to substantiate the delay in construction.3
Moreover, FEMA found that the Applicant had not taken action to construct the emergency
berms to eliminate or lessen the threat of future damage for more than three years after the major
disaster declaration.
On April 1, 2020, the Applicant submitted a first appeal of GMP 48791 to the Florida Division
of Emergency Management (Recipient)4 asserting that the delay in construction of the sand
berms was predicated on several factors: 1) turtle nesting season; 2) complications with upland
sand re-nourishment operations; 3) timeliness associated with bidding and awarding the contract;
and 4) negotiations with FEMA.5 The Recipient forwarded the Applicant’s first appeal to FEMA
with a letter of recommendation on May 26, 2020.6 On August 16, 2021, FEMA issued a first
appeal response approving the Applicant’s appeal with the following statement and conditions:
1 Determination Memorandum from Public Assistance (PA) Management, Region 4, FEMA, to Collier County (Feb.
21, 2020).
2 Id.
3 Id.
4 First Appeal Letter from Applicant Agent, Collier County, to Executive Director, Florida Division of Emergency
Management (FDEM) (Apr. 1, 2020).
5 Id., at 3.
6 Recipient Letter from Executive Director, FDEM, to Regional Administrator, Region 4, FEMA (May 26, 2020).
16.A.12.a
Packet Pg. 555 Attachment: 20221130 4337-FL Collier Co GMP 48791 FAR (002) (24427 : Recommendation to authorize the County Attorney to retain outside
2
The Subrecipient exceeded the regulatory deadline for completion
of the work. As a result, FEMA properly issued a [DM] denying
GMP 48791. Further, the Subrecipient’s delays obviated the
expedited EHP and permitting procedures available for the
construction of emergency beach berms. As a result of the project
denial, the full EHP review and permitting process, already in
process, was suspended. However, based on the extenuating
circumstances outlined by the Applicant in its appeal, FEMA
conditionally grants the Subrecipient’s appeal and provides a time
extension through April 30, 2022. However, it should be noted
that almost four years has elapsed from the damage sustained
during Hurricane Irma. The current state of the beach’s profile is
unclear; therefore, this appeal is conditionally granted based on the
premise that costs may only be reimbursed on GMP 48791 upon
the Subrecipient’s compliance with the following conditions:
1) All beach nourishment work relative to dune restoration from
Hurricane Irma must be completed in conjunction with any
additional beach renourishment projects between R-22+300 to R-
79 to reduce environmental impacts; and
2) All conditions outlined in FEMA’s Finding of No Significant
Impact (FONSI) for the finalized Supplemental Environmental
Assessment (SEA) must be followed.
The Subrecipient must justify any future time extensions in
accordance with the requirements of Title 44 Code of Federal
Regulations (44 C.F.R.) § 206.204(d) and such time extension
requests must be based upon extenuating circumstances or unusual
project requirements beyond the control of the Subrecipient.7
FEMA contacted the Applicant’s engineer on November 3, 2021, to schedule a conference call to
discuss the status of outstanding Environmental and Historic Preservation (EHP) requirements.8
During the conference call, the Applicant stated that it had started construction on November 1,
2021, with an anticipated completion date of January 15, 2022.9 FEMA EHP notified the
Applicant that the project was not in compliance with the National Environmental Policy Act
(NEPA), as consultation with interested Tribes under Section 106 of the National Historic
Preservation Act (NHPA) and the public comment period for NEPA and Executive Order (EO)
11988 must be complete prior to work completion. FEMA EHP initially gave the Applicant the
option to cease work until after the SEA was finalized, published, and the public comment period
had ended; however, the Applicant found that it was not feasible to halt the entire project.10
7 First Appeal Response, FEMA-4337-DR-FL, Collier County, Grants Manager Project (GMP) 48791, at 5-6 (Aug.
16, 2021)
8 Email from Project Specialist, FEMA, to Applicant Agent, Collier County (Nov. 3, 2021, 1148 EST).
9 Email from Environmental Specialist, FEMA, to Project Specialist, FEMA (Nov. 9, 2021, 1405 EST).
10 Email from Project Specialist, FEMA, to Applicant Agent, Collier County (Nov. 12, 2021, 1022 EST).
16.A.12.a
Packet Pg. 556 Attachment: 20221130 4337-FL Collier Co GMP 48791 FAR (002) (24427 : Recommendation to authorize the County Attorney to retain outside
3
In a subsequent DM dated February 24, 2022,11 FEMA denied GMP 48791, as the Applicant
failed to adhere to EHP regulations requiring completion of the SEA prior to commencing
construction. Accordingly, FEMA removed a total of $1,340,321.00 in PA funding for a second
time.
First Appeal
On April 12, 2022, the Applicant submitted a subsequent first appeal of GMP 48791 to the
Recipient requesting PA reimbursement in the amount of $1,340,321.00.12 On appeal, the
Applicant contends that Condition 2 in the first appeal response implied that a FONSI was
already in place and that the SEA had been finalized; therefore, it proceeded in advancing toward
construction to start at the end of sea turtle nesting season on November 1, 2021. Additionally,
the Applicant attributes the delay in obtaining a first appeal response from FEMA and the
relating subsequent delay in resuming and completing the EHP review, as factors resulting in its
loss of eligibility for reimbursement. Lastly, the Applicant questions the necessity of a full EHP
review and SEA procedure, as similar work has been performed under existing United States
Army Corps of Engineers (USACE) and Florida Department of Environmental Protection
(FDEP) permits since 1996.
The Recipient transmitted the Applicant’s appeal to FEMA with a letter recommending approval
on June 7, 2022.13
Discussion
Environmental and Historic Preservation Compliance
Several statutes, EOs, and regulations establish requirements to protect the environment and
preserve the Nation’s historic and archaeological resources, and FEMA must ensure compliance
with them prior to funding work. As part of FEMA’s EHP review, Section 106 of the NHPA
outlines a process that requires federal agencies to identify and assess the effects their actions
may have on historic properties.14 The Section 106 process seeks to balance historic
preservation concerns with the needs of federal undertakings through consultation with the
agency official and other parties with an interest in the effects of the undertaking on historic
properties, commencing at the early stages of project planning.15 The goal of consultation is to
identify historic properties potentially affected by the undertaking, assess its effects, and seek
ways to avoid, minimize, or mitigate any adverse effects on historic properties.16
11 Determination Memorandum from PA Management, Region 4, FEMA, to Collier County (Feb. 24, 2022).
12 Applicant First Appeal Letter from Applicant Agent, Collier County, to Executive Director, FDEM (Apr. 12,
2022) [hereinafter Applicant’s First Appeal Letter].
13 Recipient First Appeal Letter from Executive Director, FDEM, to Regional Administrator, FEMA Region 4 (June
7, 2022).
14 The National Historic Preservation Act of 1966, Pub. L. No. 89-665, § 106 (codified as amended at 54 U.S.C. §
306108) (2014).
15 See generally Title 36 Code of Federal Regulations (36 C.F.R.) § 800.3 (2020).
16 36 C.F.R. § 800.1(a).
16.A.12.a
Packet Pg. 557 Attachment: 20221130 4337-FL Collier Co GMP 48791 FAR (002) (24427 : Recommendation to authorize the County Attorney to retain outside
4
The Public Assistance Program and Policy Guide states that for all permanent work,17 especially
work that alters the predisaster design of a facility, applicants need to make every effort to afford
FEMA the opportunity to perform EHP reviews prior to the start of construction.18 A project’s
Scope of Work (SOW) may potentially impact EHP resources; therefore, FEMA EHP staff must
review the SOW to determine if modifications could reduce potential impacts. If an applicant
begins permanent construction before FEMA completes its EHP review, the applicant will
jeopardize funding for that project.19 FEMA generally cannot conduct consultation with resource
agencies after an applicant initiates work on a project because those agencies lose the ability to
consider alternatives that would avoid, minimize, or mitigate adverse effects to the environment
or historic properties.20
In this case, an SEA is necessary, as USACE and FDEP permits do not equate to a review under
NEPA, which serves as an umbrella law with numerous EHP laws and EOs necessitating
individual review. For example, it is the federal agency’s responsibility under the NHPA to
consult with interested parties, including Tribes, on projects that may have potential to affect
historic properties. A USACE permit, especially one from 1996, would not cover these
consultation requirements; however, it would help satisfy Clean Water Act requirements.
Likewise, the FDEP permit would only help satisfy Coastal Zone Management Act requirements.
It is important to note that the Applicant had bi-weekly phone calls with FEMA regarding the
SEA process prior to the initial denial on February 21, 2020, and suspension of the SEA
process.21 The Applicant actively participated in the EHP compliance process and was aware of
the importance of completing EHP requirements prior to construction.
Further, FEMA’s first appeal response conditioned the approval to include that the FONSI
conditions in the finalized SEA must be followed. This statement indicates that there would be
subsequent conditions to the project as outlined in the FONSI, implying that the Applicant would
need to obtain a copy of the finalized FONSI to ensure compliance with conditions. The
Applicant had no follow-up with FEMA regarding a finalized FONSI and instead carried through
with construction planning and advertising for bids after receiving notification of FEMA’s first
appeal response and project conditions on August 16, 2021.22 It is the Applicant’s responsibility
to comply with all conditions of the grant, including EHP requirements.
Lastly, FEMA provided an option for the Applicant to cease construction until after consultation
under Section 106 of the NHPA could take place, and after the public comment periods and SEA
were finalized. However, the Applicant declined this option for the following reasons: the
17 Although GMP 48791 was written as a Category B, Emergency Protective Measure, for EHP compliance
purposes, this project is considered permanent work, as dune restoration is an extended effort that significantly alters
the surrounding landscape and ecosystem. Additionally, the area subject to this project was purposefully excluded
during a planned renourishment (i.e., ‘permanent work’) that occurred in 2019, compounding the Applicant’s
inability to claim this project as ‘emergency work’ (see Email from Environmental Specialist, FEMA, to
Infrastructure Branch Director, FEMA (Oct. 3, 2019, 1054 EST)).
18 Public Assistance Program and Policy Guide, FP 104-009-2, at 85 (Apr. 2018).
19 Id; See also FEMA Second Appeal Analysis, Town of Killington, FEMA-4022-DR-VT (Oct. 22, 2019).
20 Robert T. Stafford Disaster Relief and Emergency Assistance Act, as amended, § 316, 41 U.S.C. § 5159; 44
C.F.R. Part 10, Environmental Considerations. See also 36 C.F.R. § 800.9(b).
21 EHP meeting notes (Jan. 9, 2020).
22 First Appeal Response Transmittal Email from Public Assistance Appeals, FEMA, to Applicant Agent, Collier
County (Aug. 16, 2021, 1609 EST); Applicant’s First Appeal Letter.
16.A.12.a
Packet Pg. 558 Attachment: 20221130 4337-FL Collier Co GMP 48791 FAR (002) (24427 : Recommendation to authorize the County Attorney to retain outside
5
likelihood of contractor claims due to work stoppage; delays and remobilization; the sand mine
would have to stop production; hired staff would have been idle or temporarily laid off without
pay; and truck hauls would have been intrusive to beachgoers during peak tourist demand.23
Therefore, the Applicant’s actions foreclosed on the opportunity for any meaningful consultation
among interested parties, including public involvement, to mitigate potential negative impacts to
the surrounding environment, thereby leaving FEMA in a position of noncompliance with
NEPA, EO 11988, and the NHPA, if it were to fund the endeavor.24
Conclusion
FEMA must ensure compliance with federal environmental laws, regulations, and EOs prior to
funding work. The Applicant completed sand dune construction prior to receiving FEMA
approval and without affording FEMA the opportunity to conduct the necessary EHP compliance
reviews. Therefore, the Applicant’s appeal is denied.
23 Applicant’s First Appeal Letter.
24 36 C.F.R. § 800.14(f).
16.A.12.a
Packet Pg. 559 Attachment: 20221130 4337-FL Collier Co GMP 48791 FAR (002) (24427 : Recommendation to authorize the County Attorney to retain outside
1
ADMINISTRATIVE RECORD INDEX
FEMA-4337-DR-FL
Collier County, PA ID: 021-99021-00
Grants Manager Project 48791/Project Worksheet 5856
Doc
#
No.
of
Pages
Project Document
Date
Document
Type From To
Document
Description/
Subject
1 2 48791 5/26/20 Letter Recipient FEMA 1st Appeal
Transmittal
2 3 48791 4/1/20 Letter Applicant Recipient 1st Appeal Letter
3 9 48791 2/21/20 Letter FEMA Applicant Determination
Memorandum
4 2 48791 6/7/22 Letter Recipient FEMA Second 1st Appeal
Transmittal
5 72 48791 4/12/22 Letter Applicant Recipient
Second 1st Appeal
Letter and
Attachments
6 10 48791 2/28/22 Letter Applicant FEMA
Second
Determination
Memorandum
7 2 48791 8/16/21 Email FEMA Applicant
First Appeal
Response
Transmittal
8 2 48791 11/3/21 Email FEMA Applicant
GM Attachment:
EHP Meeting
Request
9 2 48791 11/9/21 Email FEMA FEMA GM Attachment:
EHP Follow Up
10 2 48791 11/12/21 Email FEMA FEMA/Ap
plicant
GM Attachment:
EHP Compliance
Concerns
11 2 48791 10/3/19 Email FEMA FEMA
Appeal Folder:
EHP notification to
PA
End of Record
16.A.12.a
Packet Pg. 560 Attachment: 20221130 4337-FL Collier Co GMP 48791 FAR (002) (24427 : Recommendation to authorize the County Attorney to retain outside