Agenda 01/10/2023 Item #16C 3 (To obtain an amended design for the New Chiller Plant Building K)16.C.3
01 / 10/2023
EXECUTIVE SUMMARY
Recommendation to approve administrative Change Order No. 1 for time extension and utilization of
$125,659.20 of the Design Contingency under the Professional Services Agreement 21-7884 with Matern
Professional Engineering, Inc., for the New Chiller Plant Building K. (Project No. 50214.1)
OBJECTIVE: To obtain an amended design for the New Chiller Plant Building K, by utilizing the design
contingency, and adding additional time to the agreement.
CONSIDERATIONS: The Board awarded Professional Services Agreement No. 21-7884 (the "Agreement") to
Matern Professional Engineering, Inc. ("Matern") to provide design services for the new Chiller Plant Building K,
Jail Generator and Platform at its January 25, 2022, Board meeting (Agenda Item 16.C.5.). Upon obtaining
construction cost estimates at the 60% design phase of the new Chiller Plant in conjunction with the fmal design of
the Underground Chilled Water mains project, it was determined that the original direction of design would result
in a construction project that exceeded the available budget by $8-$9 Million. Staff discussed an amended design
of the New Chiller Plant and reduction of scope to the Underground Chilled Water Mains whereby Matern and its
subconsultants will produce a 90% set of documents for the New Chiller Plant utilizing the amended design
direction. The amended design of the New Chiller Plant and reduction of scope of the Underground Chilled Water
Mains project is expected to bring the project more in line with available funding.
This Change Order No. 1 proposes to add 120 days to the design completion date and will also utilize existing
funds available in the purchase order for the additional design work necessary to complete the amended direction of
design. This change does not increase the value of the existing Agreement.
If not approved the contract will not have the necessary time and funding to complete the amended design.
The County's Procurement Services Division administratively previously approved Change Order No. 1 as
authorized by the Board in accordance with its Procurement Ordinance, Section Nineteen, Contract Administration,
subsection 3.b.
FISCAL IMPACT: The combined Infrastructure Surtax funded Government Campus Chiller and Chilled Water
lines project budget is $15,500,000. This change order utilizes $125,659.20 of contract contingency but does not
increase the contract total.
GROWTH MANAGEMENT IMPACT: There is no impact to the current Growth Management Plan standards
to ensure the adequacy and availability of viable public facilities.
LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for
Board approval.-SRT
RECOMMENDATION: That the Board approves administrative Change Order No. 1 for time extension and
utilization of $125,659.20 of the Design Contingency under Professional Services Agreement 21-7884 with Matern
Professional Engineering, Inc., for the New Chiller Plant Building K (Project No. 50214.1)
Prepared by: John McCormick, PE, Interim Director, Facilities Management Division
ATTACHMENT(S)
1. Matern Professional Engineering Proposal (PDF)
2. Matern CO#1 122122 (PDF)
Packet Pg. 763
16.C.3
01/10/2023
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.C.3
Doe ID: 23987
Item Summary: Recommendation to approve administrative Change Order No. 1 for time extension and
utilization of $125,659.20 of the Design Contingency under the Professional Services Agreement 21-7884 with
Matern Professional Engineering, Inc., for the New Chiller Plant Building K. (Project No. 50214.1)
Meeting Date: 01/10/2023
Prepared by:
Title: Operations Analyst, Senior — Facilities Management
Name: Bendisa Marku
11/21/2022 3:18 PM
Submitted by:
Title: — Facilities Management
Name: John McCormick
11/21/2022 3:18 PM
Approved By:
Review:
Procurement Services
Ana Reynoso
Level 1 Purchasing Gatekeeper
Facilities Management
Jennifer Belpedio
Manager - Real Property
Procurement Services
Sandra Herrera
Additional Reviewer
Facilities Management
Tim Rygiel
Additional Reviewer
Procurement Services
Sue Zimmerman
Additional Reviewer
Facilities Management
John McCormick
Director - Facilities
Public Utilities Operations Support
AmiaMarie Curry
PUD Department Review
Procurement Services
Sara Schneeberger
Additional Reviewer
Public Utilities Department
Drew Cody
Level 1 Division Reviewer
Public Utilities Department
George Yilmaz
Level 2 Division Administrator Review
County Attorney's Office
Scott Teach
Level 2 Attorney Review
Office of Management and Budget
Debra Windsor
Level 3 OMB Gatekeeper Review
Office of Management and Budget
Susan Usher
Additional Reviewer
County Attorney's Office
Jeffrey A. Klatzkow Level 3 County Attorney's Office Review
County Manager's Office
Ed Finn
CMO Completed
County Manager's Office
Dan Rodriguez
Level 4 County Manager Review
Board of County Commissioners
Geoffrey Willig
Meeting Pending
Completed
11/22/2022 4:25 PM
Completed
11/28/2022 10:51 AM
Completed
12/11/2022 4:58 PM
Completed
12/12/2022 10:15 AM
Completed
12/13/2022 9:54 PM
Completed
12/20/2022 9:42 AM
Completed
12/20/2022 4:26 PM
Completed
12/22/2022 8:19 AM
Completed
12/27/2022 9:33 AM
Completed
12/27/2022 9:52 AM
Completed
12/27/2022 2:53 PM
Completed
12/27/2022 3:07 PM
Completed
12/27/2022 3:34 PM
Completed
12/28/2022 8:57 AM
01/02/2023 3:54 PM
Completed
01/04/2023 2:15 PM
01/10/2023 9:00 AM
Packet Pg. 764
16.C.3.a
2
MATOR N
ENGINEERING BUILDING SYSTEMS THAT WORK FOR YOU
Mechanical • Electrical • Plumbing • Fire Protection
Technology • Energy • Commissioning Engineers
ADDITIONAL SERVICES PROPOSAL #1
DATE: October 27, 2022
CLIENT: Mr. John McCormick
Principal Facilities Engineer
Facilities Management Division
Collier County Government
John.McCormick(a)colliercountyfl.gov
Mr. Tim Rygiel
Project Manager
Facilities Management Division
Collier County Government
Timothy Rygiel(q_)colliercountyfl.gov
3335 Tamiami Trail East
Naples, FL. 34112
RE: Collier County Government Center — Chiller Plant
MPE Project No.: 2022-021
Dear Gentlemen,
We submit herewith our fee proposal for additional services on the above project. We
appreciate the opportunity to provide you with this proposal.
Scope of Additional Services Requested:
1. TASK 9 - Construction Documents Redesign Directive
1.1. Based on the mutually agreed upon redesign directive consultant shall prepare,
for approval by the Owner, design documents consisting of drawings and other
documents illustrating the scale and relationship of Project components.
1.2. The redesign directive involves utilizing the existing structure of building K for
support of the four air cooled chillers, the addition of a new pump room to be
located east of the existing building K where the existing ice tanks are currently
located, and utilization of the existing ice tank farm located north of building K for
a new backup generator.
Fee (lump sum/time and materials)
Page 1 of 2
Corporate Office: 130 Candace Drive, Maitland, Florida 32751.3331 Phone: 407.740.5020
Orlando • Fort Myers • Tampa
FL CA #5096 • Federal CAGE# OSCD3 I GSA Small Business Contract #470SHA19DO026 • www,matern.net
Registered: ALABAMA • FLORIDA • GEORGIA • NORTH CAROLINA • PENNSYLVANIA • SOUTH CAROLINA - TENNESSEE • TEXAS • VIRGINIA
R
Packet Pg. 765
16.C.3.a
John McCormick and Tim Rygiel
October 27, 2022
Basic Services
Lump Sum
Time &
Materials
Subconsultant's
Markup 5%
Subtotal
Task 9 Design
Redirective
Matern Engineering
$25,380.00
$25,380.00
RG Architects
$29,052.00
$1,452.60
$30,504.60
TRC
$25,035.00
$1,251.75
$26,286.75
Stantec
$29,170.00
$1,458.50
$30,628.50
Task 9.1
AIM (Sue Level B)
$2,697.00
$134.85
$2,831.85
Velocity
$9,550.00
$477.50
$10,027.50
Total
$12.5,659.20
2.1. TOTAL
$ 125,659.20
All assumptions, clarifications, etc. remain the same as in our prime contract on this project. If
you approve of this additional service please advise us. If you so desire, your acceptance of
this proposal for contract will be witnessed by your signature below. Please call if you have any
questions in regards to this proposal.
Sincerely,
MATERN PROFESSIONAL ENGINEERING, INC.
K. Todd Griffith, PE
Sr VP — Director of SWFL Division
Page 2 of 2
Corporate Office:130 Candace Drive, Maitland, Florida 32751-3331 Phone: 407.740.5020
Orlando • Fort Myers • Tampa Q
FL CA #5096 • Federal CAGE# OSCD3 I GSA Small Business Contract #470SHA19DO026 • www.matern.net
Registered: ALABAMA • FLORIDA • GEORGIA • NORTH CAROLINA • PENNSYLVANIA • SOUTH CAROLINA • TENNESSEE • TEXAS • VIRGINIA
Packet Pg. 766
�
)
�
K
B
S.
2)
0
0
a
�
�
c
w
�
0
JT
2
a
§
k
�
k
E
t
a
2
9
Pack !Pg 767
I 16.C.3.a I
al
Packet Pg. 768
Procurement Services
�lercmftty
Change Order Form
® Contract Modification ❑ Work Order Modification
Contract #: 21-7 Change #: 01 Purchase Order #: 4500216578 Project #: 50214.1
ContractorJFirm Name: Matem Professional Engineering, Inc. Contract/P►oject: FNew
Chiller Plant Building K
Project Manager Name: John McCormick, PE Division Name: I
Facilities Management
Original Contract/Work Order Amount $ 1,406,974.00 1/25122 16.C.5 Original BCC Approval Date; Agenda Item #
Current BCC Approved Amount $ 1,406,974.00' 1125122,16.C.5 Last BCC Approval Date; Agenda Item #
Current Contract[Work Order Amount $ 1,406,974.00 2/1/2024 SAP Contract Expiration Date (Master)
Dollar Amount of this Change $ 0.00 0.00% Total Change from Original Amount
Revised Contract/Work Order Total $ 1,406,974.00 0.00% Change from Current BCC Approved Amount
Cumulative Changes $ 0 nni 0.00% Chan a from Current Amount
Completion Date, Description of the Task(s) Change, and Rationale for the Change 71
Notice to Proceed 211112022 Original 2101I2024 Last Approved 2l0112024 Revised Date 5131J2024
Date Completion Date Date (includes this change)
# of Days Added 120 Select Tasks ❑dd new task(s) ❑ Delete task(s) ® Change task(s) ❑ Other
Provide a response to the following: 1.) detailed and specific explanationfrationale of the requested change(s) to the task(s) and / or
the additional days added (if requested); 2.) why this change was not included In the original contract; and, 3.) describe the Impact
If this change is not processed. Attach additional information from the Design Professional and/or Contractor if needed.
1. This change order will utilize $125,659.20 of the approved Owner's Design Contingency, leaving a balance of $1203.60 to amend
the design direction, and add 120 days to the contract time. Upon obtaining construction cost estimates at the 60% design phase, it
was determined that the original direction of design given to Matern would result in a construction project that would substantially
exceed the available budget for this project. An amended design was discussed and agreed upon. Matern and their subconsultants
will produce a 90% set of documents utilizing the amended design direction in order to reduce estimated construction costs. An
additional 120 days has been added to the contract time to account for the additional work necessary.
2. The potential for this change was included in the original contract and accounted for with the design contingency as part of our cost
estimating and value engineering process.
3. If this change order is not processed, the design for this project will not be completed. It is estimated that the use of the design
contingency will result in a $1.5 million reduction of the 60% construction cost estimate.
RygieiTimothy Digitally signed by RygielTimathy N
Date: 2022.11.04 10:49:08-04'00' `
Prepared by: Date: E
(Tim Rygiel, CFM, Project Manager, Facilities Management Division) Q
Acceptance of this Change Order shall constitute a modification to contract J work order identified above and will be subject to all the same
terms and conditions as contained in the contract / work order indicated above, as fully as if the same were stated in this acceptance. The rn
adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor J Vendor J Consultant J N
Design Professional arising out of or related to the change set forth herein, including claims for impact and delay costs.
N
Digftallysigned by K. Todd Grifllih, PE N
K• Todd Griffith, PE ON: email.r9 dGtitfth,einai, ca mProfessional Engineering,fnc,
ou,emall=[ nrBrhsamatemnel,c=US N
04
Accepted by: 04le:2022.1 0809:13a0-05'W Date:
(K.Todd Griffith, PE, SVP-Director of SWFL Division, Matern Professional Engineering, Inc.)
O
Digitally signed by McCormickJohn
M cCo rm i ckJ o h n v
Approved by: Date: 2022.11.10 04:28.24-05'00'
Date:
(John McCormick, PE, interim Director, Facilities Management Division) f°
SChneebGrgerSara Digitally signed by SchneebergerSara
Date: 2022.11.17 09:14:42 -05'00'
Approved by: Date: E
(Procurement Professional)
Revised: 01/14/2021 (Divisions who may require additional signatures may include on separate sheet.)
Reviewed 10/27/22 CD
PROCUREMENT USE ONLY
Admin�
8CC ES
Packet Pg. 769
16.C.3.b
ATTEST:
Crystal K. Kinzel, Clerk of Courts
& Comptroller
M.
Dated:
(SEAL)
Approved as to form and legality:
By:
Scott R. Teach
Deputy County Attorney
BOARD OF COUNTY COMMISSIONERS
COLLIER COUNTY, FLORIDA
Rick LoCastro, Chairman
N
N
V-
N
N
O
V
C
L
rt+
C
Y
- (41)
Packet Pg. 770
16.C.3.b
Change Order/Amendment Summary
CO#
AMD#
Description
COST
TIME
Justification
Additive (+)
Deductive (-)
Days
Added
New
Amount
1
This change order
will utilize
$125,659.20 of the
approved Owners
Design
Contingency,
leaving a balance
of $1203.80 to
amend the design
direction, and add
120 days to the
contract time
120
040
Estimated construction costs
dictated amended design direction.