Agenda 01/10/2023 Item #16A 9 (To have BCC approve recording the amended final plat of Maple Ridge at Ave Maria Phase 7B Replat)16.A.9
01 / 10/2023
EXECUTIVE SUMMARY
This item requires that ex parte disclosure be provided by Commission members. Should a hearing be held
on this item, all participants are required to be sworn in. Recommendation to approve for recording the
amended final plat of Maple Ridge at Ave Maria Phase 713 Replat, (Application Number PL20220003332)
approval of the standard form Construction and Maintenance Agreement, and approval of the performance
security in the total amount of $249,615.49.
OBJECTIVE: To have the Board of County Commissioners ("Board") approve recording the amended final plat
of Maple Ridge at Ave Maria Phase 7B Replat, a subdivision of lands located in Section 4, Township 48 South,
Range 29 East, Collier County, Florida, in accordance with the LDC Section 10.02.04.B.4. This procedure allows
for the Board to approve the plat and associated construction documents for construction purposes and recording
purposes concurrently.
CONSIDERATIONS: The Development Review Division of the Growth Management Department has completed
the review of the construction drawings, specifications, and amended final plat, Maple Ridge, at Ave Maria Phase
7B Replat. These documents are in compliance with the County Land Development Code and Chapter 177, Florida
Statutes. This project is within the Ave Maria SRA. All fees have been paid.
Security in the amount of 10% of the total cost of the required improvements associated with this amended final
plat, and 100% of the cost of any remaining improvements, together with a Construction and Maintenance
Agreement for Subdivision Improvements, shall be provided and accepted by the County Manager or his designee
and the County Attorney's office prior to the recording of the final plat. This procedure is in conformance with
Section 10.02.04 F.2 of the Land Development Code.
The Development Review Division recommends that the amended final plat of Maple Ridge at Ave Maria Phase
7B Replat be approved for recording.
FISCAL IMPACT: The project cost associated with this final plat is $226,923.17 (estimated) to be borne by the
developer.
The cost breakdown for the amended final plat is as follows:
a) Water & Sewer $ 53,464.30
b) Drainage, Paving, Grading $173,458.87
The Security amount, equal to 110% of the project revision cost is $249,615.49.
The County will realize revenues as follows:
Fund: Growth Management Fund 131
Agency: County Manager
Cost Center: 138327 -Land Development Services Revenue generated by this project:
Total: $6,203.77
Packet Pg. 611
16.A.9
01/10/2023
The Review Fees are based on a construction estimate of $173,458.87 (does not include Ave Maria Utilities) and
were paid in May 2022.
The breakdown is as follows:
a) Plat Review Fee ($1,000.00 + $5./ac) $ 1,000.00
b) Construction Drawing Review Fee
Water & Sewer (.75% const. est.) N/A
c) Drainage, Paving, Grading
(.75% const. est.) $ 1,300.94
d) Construction Inspection Fee
Water & Sewer (2.25% const. est.) N/A
e) Drainage, Paving, Grading
(2.25% const. est.) $ 3,902.82
GROWTH MANAGEMENT IMPACT: The developer must receive a Certificate of Adequate Public Facilities
(COA) prior to the issuance of the construction plan final approval letter and plat recordation, except when the
applicant elects to delay obtaining a COA for non-residential developments that are required to obtain approval of a
site development plan prior to the issuance of a building permit.
LEGAL CONSIDERATIONS: The applicant is requesting approval of the final subdivision plat and construction
and maintenance agreement. The Board shall consider the County Manager or designee's recommendation and
shall take evidence and testimony regarding the final subdivision plat requirements identified in LDC sections
10.02.04 B, 10.02.04 C, and other provisions of the LDC, as well as Chapter 177, Florida Statutes. If the Board
denies or places conditions on the final subdivision plat, it shall state reasons for such denial or conditions.
In accordance with the LDC, the applicant is required to submit the final subdivision plat to the County Manager or
designee for recording within 18 months of the date of approval of the final subdivision plat by the Board.
However, following approval by the Board, but prior to recordation, the County Manager or designee may approve
minor insubstantial changes to the subdivision plat, and the Board may approve any changes that are not minor and
insubstantial.
This item has been approved as to form and legality and requires a majority vote for Board approval. - DDP
RECOMMENDATION: To endorse staff s recommendation to approve the amended final plat of Maple Ridge at
Ave Maria Phase 7B Replat (Application Number PL20220003332) for recording with the following stipulations:
1. Approve the amount of $249,615.49 as the performance security for the required improvements associated
with this amended plat, or a lesser amount based on work completed, and as is approved by the Growth
Management Department.
2. Approve the standard form Construction and Maintenance Agreement and direct the County Manager or
his designee:
a. To withhold Certificates of Occupancy until the required improvements have received preliminary
acceptance.
b. To delay recording of the amended plat until suitable security and an appropriate Construction and
Maintenance Agreement are approved and accepted by the County Attorney's office and the Board
of County Commissioners or the County Manager or his designee on behalf of the Board pursuant
to Section 10.02.04 F.2 of the Land Development Code.
Prepared by: Lucia S. Martin, Project Manager I, Development Review Division
ATTACHMENT(S)
1. Location Map (PDF)
Packet Pg. 612
16.A.9
01 / 10/2023
2. Plat Map (PDF)
3.Opinion of Probable Cost - AMUC (PDF)
4. Opinion of Probable Cost - Collier County (PDF)
Packet Pg. 613
16.A.9
01/10/2023
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.A.9
Doc ID: 24003
Item Summary: This item requires that ex parte disclosure be provided by Commission members. Should a
hearing be held on this item, all participants are required to be sworn in. Recommendation to approve for recording
the amended final plat of Maple Ridge at Ave Maria Phase 7B Replat, (Application Number PL20220003332)
approval of the standard form Construction and Maintenance Agreement, and approval of the performance security
in the total amount of $249,615.49.
Meeting Date: 01/10/2023
Prepared by:
Title: Technician — Growth Management Development Review
Name: Lucia Martin
11/28/2022 10:49 AM
Submitted by:
Title: Environmental Specialist — Growth Management Department
Name: Jaime Cook
11/28/2022 10:49 AM
Approved By:
Review:
Growth Management Operations & Regulatory Management Kenneth Kovensky
Growth Management Development Review Brett Rosenblum
Growth Management Department
Engineering & Natural Resources
Growth Management Department
Growth Management Department
County Attorney's Office
Office of Management and Budget
County Attorney's Office
Office of Management and Budget
County Manager's Office
Board of County Commissioners
Diane Lynch
Growth Management Department
Jack McKenna
Additional Reviewer
Jaime Cook
Division Director
James C French
Growth Management
Derek D. Perry
Level 2 Attorney Review
Debra Windsor
Level 3 OMB Gatekeeper Review
Jeffrey A. Klatzkow Level 3 County Attorney's Office Review
Laura Zautcke
Additional Reviewer
Amy Patterson
Level 4 County Manager Review
Geoffrey Willig
Meeting Pending
Additional Reviewer Completed
11/28/2022 2:53 PM
Additional Reviewer Completed
12/05/2022 4:39 PM
Completed 12/08/2022 3:08 PM
Completed 12/08/2022 4:01 PM
Completed 12/09/2022 8:17 AM
Completed 12/09/2022 7:17 PM
Completed 12/27/2022 12:22 PM
Completed 12/27/2022 12:30 PM
Completed 12/28/2022 9:03 AM
Completed 12/28/2022 10:12 AM
Completed 01/03/2023 4:54 PM
01/10/2023 9:00 AM
Packet Pg. 614
16.A.9.a
MAPLE RIDGE AT AVE MARIA
PHASE 713 REPLAT
MAPLE
ie E 7B
SITE
LOCATION
ATIDNAL GOLF & .�
COUNTRY CLUB
LOCATION MAP
a
Packet Pg. 615
wd� fZ JD
LLJO wZ LL WF- Q a Z p QNw 0Z
0�
w W0 z w w
wm0
Ce)�OZ z U� ZQ LL OQ
LUa �~w w
O ��i)0
0
Q=°�=> Q
U) w aV
p Z � ~ pp W O Cn w w
> ZF O U o m Z p
O z Q m U_ Z a W 00 Q Z
MQ w ::) W � (� w 0 0
W ~ O Z o w w aLLI ~ Q J
T �Z �QZ� � - WLLI �U 0-z
_ Q w Z = — J
co� CnLL�w �� QU)w dui
r n = O w p z Y 0 U
v, ww p z= Q Q Q O Z
Q Zw w�O0 �= ozw LZ
w z
O 2 C) <>- _~ QOf
QO avQ
O w w 0 0~ U ~ 0 - w J
U >> � J w Z W> a J w 0
H 2w <wmm Ow fnp= JDz
Q J Z w Q Q Z Cn W U U w~ } Q Z
i a_ _� Lu LU -w aaw awo
Q J w 0 d w w 0 W U m Q
2 2 w H a a 0 w U O: w
LJ.I oQ QQ00 U) �:E �Qa-
wozg Qui >: }"O
LU w J U�LU ��~0 w� zww JZO
WD ���U Q� Oc�nLu
U =2U
w O m J w Q � w U w 2 a LU 5
0 Q w D m W w W> a w
Z w w Qw �co :E (/) nQw w
O2 Q J= W Z Q D w Q J w U W Z
Qw } U =W HWZQwww UUco� Q�O
�O z J I10~�rzc�c� O JU) O�z
Q� Q H H O
p U w Q 00 W w m Q W z W X W a H
U wO Q wQ Q�a�w(Ujw' Qw= QQQ
0 w0 � Q E Z w U U w U Z Q 0 U 00 V Q
wZ > OQ W0 � JJ WZ w>cn
W Q 5 O Q w� o Q Q 0 Q p Q z
Q m OU Y U � m a m U D N Q Cl) a
a
Q
m�;
z
0
0
m
Q
1 16.A.9.c
PENINSULA
ENGINEERING
Project:
Task:
Prepared By:
Checked By:
Maple Ridge Phase 7B PPL - Ternberry
Engineer's OPC for AMUC Fee Calculations (ReV00)
ASJ Date: 4/15/2022
DJH
Date: 4/15/2022
Calculation Summary SUB -TOTAL TOTAL
POTABLE WATER $ 31,033.60 $ 31,033.60
IRRIGATION
TOTAL
70
53,464.30
NOTES:
1) This Opinion of Probable Cost shall be used for Fee Calculation Purposes Only.
22, 430.70
53, 464.30
2) All costs provided in this OPC are based on recent contract prices, or the Engineers' latest known unit costs. These costs cannot be guaranteed at this time
due to unpredictable and uncontrollable increases in the cost of concrete, petroleum, or the availability of materials and labor.
IIII11111111///
�• H(/ '
Digitally signed by David 1 Hurst
Reason: This item has been
digitally signed and sealed by
`* No. 60727 '•: *
David J. Hurst on the date
= adjacent to the seal. Printed
_ *
= copies of this document are not
•% STATE OF ;'�`
'
considered signed and sealed
,/-�c,��
�',���: ••. < 0 R 1D. P.
and the signature must be
''oss/ONALE�o`�
verified on any electronic copies.
Date: 2022.09.2008:59:36-04'00'
/ll11111111110
David Hurst, P.E.
FL Registration #60727
Peninsula Engineering
Certificate of Authorization #28275
U
a
0
U
Iv
ca
0
L
4-
0
I_
0
.Q
0
r
E
ci
r
a
P:\Active_Projects\P-AMD-040\001_TernberryRd-PPLA\Budgets\Cost_Estimates\OPC\FeeCalc\MR7B-Ternberry_OPC-AMUC.xlsx Packet Pg. 618
2 16.A.9.c
Project: Maple Ridge Phase 7B PPL - Ternberry
Task: Engineer's OPC for AMUC Fee Calculations (ReV00)
Prepared By: ASJ Date: 4/15/2022
Checked By: DJH Date: 4/15/2022
POTABLE WATER
ID
DESCRIPTION
QTY
UNIT TYPE
UNIT PRICE
TOTAL PRICE
WAT-1
8" PVC WATER MAIN C900, DR18
426
LF
$ 45.10
$ 19,212.60
WAT-2
FIRE HYDRANT ASSEMBLY COMPLETE
1
EA
$ 6,286.00
$ 6,286.00
WAT-3
TESTING
1
LS
$ 500.00
$ 500.00
WAT-4
REMOVE EX BLOW -OFF AND CONNECT TO EX.WATER
MAIN
1
EA
$ 1,975.00
$ 1,975.00
WAT-5
TEMPORARY BLOWOFF W/TBSP (INCLUDES GATE
VALVE)
1
EA
$ 3,060.00
$ 3,060.00
SUB -TOTAL POTABLE WATER = $ 31,033.60
P:\Active_Projects\P-AMD-040\001_TernberryRd-PPLA\Budgets\Cost_Estimates\OPC\FeeCalc\MR7B-Ternberry_OPC-AMUC.xlsx Packet Pg. 619
3 16.A.9.c
Project: Maple Ridge Phase 7B PPL - Ternberry
Task: Engineer's OPC for AMUC Fee Calculations (ReV00)
Prepared By: ASJ
Checked By: DJH
IRRIGATION
Date: 4/15/2022
Date: 4/15/2022
ID
DESCRIPTION
QTY
UNIT TYPE
UNIT PRICE
TOTAL PRICE
IRR-1
6" PVC IRRIGATION MAIN C900,DR18
470
LF
$ 30.21
$ 14,198.70
IRR-2
2" SINGLE IRRIGATION SERVICE (SHORT SIDE)
(COMPLETE)
1
EA
$ 2,147.00
$ 2,147.00
IRR-3
TEMPORARY BLOW -OFF (INLCUDES GATE VALVE)
1
EA
$ 2,803.00
$ 2,803.00
IRR-4
REMOVE EX. BLOW -OFF AND CONNECT TO EX.
IRRIGATION MAIN
1
EA
$ 2,782.00
$ 2,782.00
IRR-5
TESTING
1
LS
$ 500.00
$ 500.00
SUB -TOTAL IRRIGATION = $ 22,430.70
P:\Active_Projects\P-AMD-040\001_TernberryRd-PPLA\Budgets\Cost_Estimates\OPC\FeeCalc\MR7B-Ternberry_OPC-AMUC.xlsx Packet Pg. 620
1 16.A.9.d
PENINSULA
ENGINEERING
Project:
Task:
Prepared By:
Checked By:
Maple Ridge Phase 7B PPL - Ternberry
Engineer's OPC for County PPL Fee Calculations (Rev01)
AJS Date: 9/20/2022
DJH Date: 9/20/2022
Calculation Summary SUB -TOTAL TOTAL
EARTHWORK $ 16,335.00 $ 16,335.00
PAVING
1101:7_11►/_[e11
89,532.67
47,491.20
89, 532.67
47,491.20
LANDSCAPE AND LIGHTING $ 20,100.00 $ 20,100.00
TOTAL $ 173,458.87 $ 173,458.87
NOTES:
1) This Opinion of Probable Cost shall be used for Budgeting Purposes Only.
2) All costs provided in this OPC are based on recent contract prices, or the Engineers' latest known unit costs. These costs cannot be guaranteed at this time
due to unpredictable and uncontrollable increases in the cost of concrete, petroleum, or the availability of materials and labor.
Digitally signed by David J Hurst
.�`�\Op:•���•E•NS f , Reason: This item has been
digitally signed and sealed by
* N0. 60727 * = David J. Hurst on the date
* = adjacent to the seal. Printed
copies of this document are not
.p°., STATE OF •;°� \ considered signed and sealed
'•.• ,r p ; cc, and the signature must be
0
'r�t` •<QR�*' rjj verified on any electronic copies.
",nit, EN Date: 2022.09.20 08:59:00 -04'00'
III,
David Hurst, P.E.
FL Registration #60727
Peninsula Engineering
Certificate of Authorization #28275
P:\Active_Projects\P-AMD-040\001_TernberryRd-PPLA\Budgets\Cost_Estimates\OPC\FeeCalc\MR7B-Ternberry_OPC-CC_REV01.xlsx Packet Pg. 621
2 16.A.9.d
Project:
Maple Ridge Phase 7B PPL - Ternberry
Task:
Engineer's OPC for County PPL Fee Calculations (Rev01)
Prepared By:
AJS Date: 9/20/2022
Checked By:
DJH Date: 9/20/2022
EARTHWORK
ID
DESCRIPTION
QTY
UNIT TYPE
UNIT PRICE
TOTAL PRICE
EW-1
EROSION CONTROL (TURBIDITY BARRIER, INLET
PROTECTION, SILT FENCE)
1
LS
$ 13,910.00
$ 13,910.00
EW-2
NDPES MAINTENANCE
1
MONTH
$ 600.00
$ 600.00
EW-3
FILL & COMPACT TEMPORARY CONVEYANCE SWALE
1
1 LS
I $ 1,825.00
$ 1,825.00
SUB -TOTAL EARTHWORK = $ 16,335.00
P:\Active_Projects\P-AMD-040\001_TernberryRd-PPLA\Budgets\Cost_Estimates\OPC\FeeCalc\MR7B-Ternberry_OPC-CC_REV01.xlsx Packet Pg. 622
3 16.A.9.d
Project:
Maple Ridge Phase 7B PPL - Ternberry
Task:
Engineer's OPC for County PPL Fee Calculations (Rev01)
Prepared By:
AJS Date: 9/20/2022
Checked By:
DJH Date: 9/20/2022
PAVING
ID
DESCRIPTION
QTY
UNIT TYPE
UNIT PRICE
TOTAL PRICE
PAV-1
3/4" ASPHALTIC CONCRETE TYPE S-III FIRST LIFT)
1
LS
$ 11,462.25
$ 11,462.25
PAV-2
3/4" ASPHALTIC CONCRETE TYPE S-III SECOND LIFT
1
LS
$ 11,462.25
$ 11,462.25
PAV-3
8" LIMEROCK BASE
1
LS
$ 15,224.00
$ 15,224.00
PAV-4
12" STABILIZED SUBGRADE
1
LS
$ 3,041.10
$ 3,041.10
PAV-5
2' VALLEY GUTTER
1
LS
$ 8,271.00
$ 8,271.00
PAV-6
TYPE W CURB
1
LS
$ 3,984.00
$ 3,984.00
PAV-7
4' SIDEWALK VALLEY CROSSING
1
LS
$ 851.00
$ 851.00
PAV-8
T VALLEY GUTTER CROSSING
1
LS
$ 1,650.00
$ 1,650.00
PAV-9
CONCRETE SIDEWALK (4" THICK)
1
LS
$ 16,592.90
$ 16,592.90
PAV-10
ADA DETECTABLE MAT
1
LS
$ 850.00
$ 850.00
PAV-11
CURB RAMPS
1
LS
$ 900.00
$ 900.00
PAV-12
SODDING
1
LS
$ 13,656.67
$ 13,656.67
PAV-13
SIGNAGE & ROADWAY STRIPING
1
LS
$ 600.00
$ 600.00
PAV-14
TEMPORARY CONSTRUCTION ACCESS
1
LS
$ 500.00
$ 500.00
PAV-15
REMOVAL OF EXISTING 2' VALLEY GUTTER
1
LS
$ 112.50
$ 112.50
PAV-16
REMOVAL OF EXISTING S CONCRETE SIDEWALK
1
LS
$ 375.00
$ 375.00
SUB -TOTAL PAVING = $ 89,532.67
P:\Active_Projects\P-AMD-040\001_TernberryRd-PPLA\Budgets\Cost_Estimates\OPC\FeeCalc\MR7B-Ternberry_OPC-CC_REV01.xlsx Packet Pg. 623
4 16.A.9.d
Project:
Maple Ridge Phase 7B PPL - Ternberry
Task:
Engineer's OPC for County PPL Fee Calculations (Rev01)
Prepared By:
AJS Date: 9/20/2022
Checked By:
DJH Date: 9/20/2022
DRAINAGE
ID
DESCRIPTION
QTY
UNIT TYPE
UNIT PRICE
TOTAL PRICE
DRA-1
15" RCP STORM SEWER
1
LS
$ 6,897.60
$ 6,897.60
DRA-2
18" RCP STORM SEWER
1
LS
$ 7,381.00
$ 7,381.00
DRA-3
24" RCP STORM SEWER
1
LS
$ 4,569.60
$ 4,569.60
DRA-4
VALLEY GUTTER INLET DOUBLE
1
LS
$ 18,820.00
$ 18,820.00
DRA-5
JUNCTION BOX ROUND
1
LS
$ 8,698.00
$ 8,698.00
DRA-6
REMOVE EXISTING STRUCTURE AND CONNECT TO
PROPOSED DRAINAGE STRUCTURE
1
LS
$ 1,125.00
$ 1,125.00
SUB -TOTAL DRAINAGE = $ 47,491.20
P:\Active_Projects\P-AMD-040\001_TernberryRd-PPLA\Budgets\Cost_Estimates\OPC\FeeCalc\MR7B-Ternberry_OPC-CC_REV01.xlsx Packet Pg. 624
5 16.A.9.d
Project:
Maple Ridge Phase 7B PPL - Ternberry
Task:
Engineer's OPC for County PPL Fee Calculations (Rev01)
Prepared By:
AJS Date: 9/20/2022
Checked By:
DJH Date: 9/20/2022
LANDSCAPE AND LIGHTING
ID
DESCRIPTION
QTY
UNIT TYPE
UNIT PRICE
TOTAL PRICE
LL-1
STREET LIGHTING
1
LS
$ 13,500.00
$ 13,500.00
LL-2
LANDSCAPE (COMMON AREA TREES AND CODE MIN.)
1
LS
$ 6,600.00
$ 6,600.00
$ -
$
SUB -TOTAL LANDSCAPE AND LIGHTING = $ 20,100.00
P:\Active_Projects\P-AMD-040\001_TernberryRd-PPLA\Budgets\Cost_Estimates\OPC\FeeCalc\MR7B-Ternberry_OPC-CC_REV01.xlsx Packet Pg. 625