Agenda 12/13/2022 Item #16A26.C (Procurement Services Division for change orders)09/13/2022 EXECUTIVE SUMMARY Recommendation to approve the administrative reports prepared by the Procurement Services Division for change orders and other contractual modifications requiring Board approval. OBJECTIVE: To promote accountability and provide transpar ency to the public and gain the Board’s approval/ratification for various procurement -related transactions. CONSIDERATIONS: In accordance with the Board’s Procurement Ordinance 2017-08 and the Procurement Manual, the Procurement Services Division produces a regular administrative report which provides for Board approval of the following transactions: • Change Orders that do not exceed ten (10%) of the current Board approved aggregate amount, and/or require change in schedule (number of days); • Amendments to contracts; • After the fact memos from various County Divisions, as requested by the Clerk’s Finance staff for the timely process of invoices. • Other items as determined by the County Manager or designee that require Board approval. This administrative report includes the following: • Two (2) change orders that in aggregate modify contracts by $62,373.85 and add 93 calendar days to completion periods, see attached summary and backup for details; and • Zero (0) amendments this period with a fiscal impact of $0.00; and • Four (4) after the fact memo with a fiscal impact of $54,299.70 for additional services FISCAL IMPACT: The net total for the six (6) items is $116,673.55. LEGAL CONSIDERATIONS: This item is approved for form and legality and requires a majority vote for Board action. -JAK GROWTH MANAGEMENT IMPACT: There is no Growth Management Impact associated with this action. RECOMMENDATION: To ratify/approve change orders and/or contract amendments and other items as determined by the County Manager or designee in accordance with Procurement Ordinance 2017-08. Prepared By: Sara Schneeberger, Procurement Strategist, Procurement Services ATTACHMENT(S) 1. 0913 After the Fact Report - FY22 (PDF) 2. 0913 After the Fact Backup - FY22 (PDF) 3. 0913 Change Order Report Revised - FY22 (PDF) 4. 0913 Change Order Backup Revised - FY22 (PDF) 16.E.10 Packet Pg. 2850 16.A.26.c Packet Pg. 1087 Attachment: CO #2_Item 16E10d_Agenda - Tuesday, September 13, 2022 (23959 : Mastec Change Order and request to waive LDs) 09/13/2022 COLLIER COUNTY Board of County Commissioners Item Number: 16.E.10 Doc ID: 23161 Item Summary: Recommendation to approve the administrative reports prepared by the Procurement Services Division for change orders and other contractual modifications requiring Board approval. Meeting Date: 09/13/2022 Prepared by: Title: Business Technology Analyst, Senior – Procurement Services Name: Sara Schneeberger 08/25/2022 9:24 AM Submitted by: Title: Manager - Procurement – Procurement Services Name: Sandra Herrera 08/25/2022 9:24 AM Approved By: Review: Procurement Services Ana Reynoso Level 1 Purchasing Gatekeeper Completed 08/25/2022 9:33 AM Procurement Services Catherine Bigelow Additional Reviewer Completed 08/26/2022 6:44 AM Procurement Services Sandra Herrera Additional Reviewer Completed 08/31/2022 12:46 PM Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 08/31/2022 12:51 PM Office of Management and Budget Susan Usher Additional Reviewer Completed 08/31/2022 1:48 PM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 09/01/2022 9:04 AM County Manager's Office Dan Rodriguez Level 4 County Manager Review Completed 09/06/2022 5:22 PM Board of County Commissioners Geoffrey Willig Meeting Pending 09/13/2022 9:00 AM 16.E.10 Packet Pg. 2851 16.A.26.c Packet Pg. 1088 Attachment: CO #2_Item 16E10d_Agenda - Tuesday, September 13, 2022 (23959 : Mastec Change Order and request to waive LDs) Item page #Contract/ Grant No.Change #DateProject Name Vendor Name Division - Project Manager Original Contract Amount Current Contract Amount Current Change Order Amount Revised Contract Amount % Over Board Approved Amount Contract Length Change in length (Days) Updated contract length Change in length (%) 1 1 20-7791 2 8/19/2022 Vanderbilt Drive Underground Utility Conversion MasTec North America, Inc. PTNE - Harry Sells $1,765,869.40 $1,890,788.90 $0.00 $1,890,788.90 0.00% 472 93 565 19.70% 2 5 21-7864 7 8/22/2022 ENCP Welcome Center Curran Young Construction Facilities Management - Dave Closas $2,965,622.28 $3,082,747.86 $62,373.85 $3,145,121.71 2.02% 491 0 491 0.00% Meeting Date Total number of Change Orders Total Dollar Change Total Change in Days 9/13/2022 2 $62,373.85 93 16.E.10.c Packet Pg. 2862 Attachment: 0913 Change Order Report Revised - FY22 (23161 : Procurement Services administrative16.A.26.c Packet Pg. 1089 Attachment: CO #2_Item 16E10d_Agenda - Tuesday, September 13, 2022 (23959 : Mastec Change Order Revised: 01/14/2021 (Divisions who may require additional signatures may include on separate sheet.) PROCUREMENT USE ONLY Admin BCC Rpt BCC ES Contract Modification Work Order Modification Contract #: Change #: Purchase Order #: Project #: Contractor/Firm Name: Contract/Project: Project Manager Name: r: Division Name: Original Contract/Work Order Amount $ 1,765,869.40 2/23/21 11J Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 1,890,788.90 4/26/22 16A14 Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 1,890,788.90 9/1/2022 SAP Contract Expiration Date (Master) Dollar Amount of this Change $ 0.00 7.07% Total Change from Original Amount Revised Contract/Work Order Total $ 1,890,788.90 0.00% Change from Current BCC Approved Amount Cumulative Changes $ 124,919.50 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Notice to Proceed Original Last Approved Revised Date Date Completion Date Date (Includes this change) # of Days Added Select Tasks Add new task(s) Delete task(s) Change task(s) Other Provide a response to the following: 1.) detailed and specific explanation/rationale of the requested change(s) to the task(s) and / or the additional days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the impact if this change is not processed. Attach additional information from the Design Professional and/or Contractor if needed. Prepared by: ___________________________________________________________________________ Date: ________________ (Project Manage, Harry Sells, PTNE) Acceptance of this Change Order shall constitute a modification to contract / work order identified above and will be subject to all the same terms and conditions as contained in the contract / work order indicated above, as fully as if the same were stated in this acceptance. The adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor / Vendor / Consultant / Design Professional arising out of or related to the change set forth herein, including claims for impact and delay costs. Accepted by: ___________________________________________________________________________ Date: ________________ (Michael Acosta, MasTec North America), Approved by: ___________________________________________________________________________ Date:________________ (Michelle Arnold, PTNE Director) Approved by: ___________________________________________________________________________ Date: ________________ (Trinity Scott, Department Head, Transportation Management Services) Procurement Services Change Order Form NA MasTec North America, Inc. 4500210804 20-7791 2 Vanderbilt Drive Underground Utility conversion PTNE Harry Sells 12/3/2022 9/1/2022 5/17/2022 93 05/17/2021 1. Time added due to unexpected circumstances including FPL placing the project on hold for five months due to internal FPL issues; Comcast delaying work through internal company issues; and Prime Contracdtor delaying bridge conduit design and installation. 2. The project time and cost was based on assumptions that contemplated the general complexity of the project and could not have anticipated the coordingtion issues and unexpected occurrences that transpired. 3. If this Change Order is not approved, the work order will expire and the project cannot be proceed to completion. Appro BCC Rpt 1116.E.10.d Packet Pg. 2863 Attachment: 0913 Change Order Backup Revised - FY22 (23161 : Procurement Services administrative reports)16.A.26.c Packet Pg. 1090 Attachment: CO #2_Item 16E10d_Agenda - Tuesday, September 13, 2022 (23959 : Mastec Change Order and request to waive LDs) Revised: 01/14/2021 (Divisions who may require additional signatures may include on separate sheet.) PROCUREMENT USE ONLY Admin BCC Rpt BCC ES Approved by: ___________________________________________________________________________ Date: ________________ (Procurement Professional) BCC Rpt 2 16.E.10.d Packet Pg. 2864 Attachment: 0913 Change Order Backup Revised - FY22 (23161 : Procurement Services administrative reports)16.A.26.c Packet Pg. 1091 Attachment: CO #2_Item 16E10d_Agenda - Tuesday, September 13, 2022 (23959 : Mastec Change Order and request to waive LDs) Revised: 01/14/2021 (Divisions who may require additional signatures may include on separate sheet.) PROCUREMENT USE ONLY Admin BCC Rpt BCC ES Change Order/Amendment Summary CO# AMD# Description COST TIME Justification Additive (+) Deductive (-) Days Added New Amount 1 Add days and modify costs $124,919.50 10 Required changes discovered in construction. 2 Add Days 93 56 Conflicts with various utilities and sub contractor delayed conversion of low voltage network Rpt BCC 3 16.E.10.d Packet Pg. 2865 Attachment: 0913 Change Order Backup Revised - FY22 (23161 : Procurement Services administrative reports)16.A.26.c Packet Pg. 1092 Attachment: CO #2_Item 16E10d_Agenda - Tuesday, September 13, 2022 (23959 : Mastec Change Order and request to waive LDs) 1 SotoCaroline From:SellsHarry Sent:Thursday, August 04, 2022 11:52 AM To:SotoCaroline Subject:FW: CHANGE ORDER WR#5686943 Mastec Change order request. Harry From:Eric Adkins <Eric.Adkins@mastec.com> Sent:Tuesday, July 26, 2022 10:26 AM To:SellsHarry <Harry.Sells@colliercountyfl.gov> Cc:Joelle Hammesfahr <Joelle.Hammesfahr@mastec.com>; Charles Robinson <Charles.Robinson@mastec.com>; Nicholas Sheckler <Nicholas.Sheckler@mastec.com> Subject:CHANGE ORDER WR#5686943 EXTERNAL EMAIL:This email is from an external source. Confirm this is a trusted sender and use extreme caution when opening attachments or clicking links. Good Morning, Harry Due to the delays in attaching conduit to the Cocohatchee Bridge and completion of the low voltage, we need to extend the length of our contract to prevent it from expiring. As we discussed the January date appears appropriate. Regards, Eric Adkins Supervisor 239 689 9911 Under Florida Law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by telephone or in writing. 4 16.E.10.d Packet Pg. 2866 Attachment: 0913 Change Order Backup Revised - FY22 (23161 : Procurement Services administrative reports)16.A.26.c Packet Pg. 1093 Attachment: CO #2_Item 16E10d_Agenda - Tuesday, September 13, 2022 (23959 : Mastec Change Order and request to waive LDs)