EXECUTIVE SUMMARY
Recommendation to approve a second Transportation Commitment Extension Request for the ROCKEDGE
Residential Planned Unit Development (RPUD) to provide more time to fulffil the Transit Bus Stop
Improvement Commitment.
OBJECTIVE: To obtain needed bus stop improvements for the transit system impacted by development.
CONSIDERATIONS: ROCKEDGE is a Residential Planned Unit Development (RPUD) allowing the
development of 266 dwelling units on property located near the Northeast comer of Sabal Palm Road and Collier
Boulevard. There are several development commitments contained in the development agreement, including the
requirement to make improvements to benefit the impacts on the Transit system. Specifically, the Developer is
required to install Collier Area Transit bus stop improvements with shelter and associated access pathways at a
location to be determined during the site development plan review process. All improvements are to be completed
prior to the first Certificate of Occupancy issuance.
The proposed location of the bus stop is adjacent to a canal and requires coordination with multiple agencies,
including the South Florida Water Management District (SFWMD). Additional time is being requested to fulfill
this commitment due to the coordination required. The Board issued an initial extension to meet this commitment
no later than eight (8) months after the issuance of the first Certification of Completion or by November 30, 2022,
whichever is sooner. The Developer has made a good faith effort to comply with this date, but additional time is
needed to obtain a permit and the cost of constructing the improvements is more than anticipated.
The Developer is requesting an extension that provides for the issuance of Certificate of Completions (COs) for up
to 50% of the approved units. Staff is recommending that the extension be granted up to June 30, 2023. Should the
commitment not be satisfied by this time period, the issuance of any further COs will be suspended until the
commitment is satisfied.
The Developer has committed to meeting this modified timeframe and has signed the attached letter to show that
commitment. Staff is at this time requesting the Board's approval of the extension through June 30, 2023.
FISCAL IMPACT: The Developer will be responsible for making the improvement at no cost to the County,
therefore there is no fiscal impact associated with this Executive Summary.
GROWTH MANAGEMENT IMPACT: This Item furthers the Growth Management Plan Objective 12 to
encourage the efficient use of transit services now and in the future.
LEGAL CONSIDERATIONS: This item has been reviewed by the County Attorney, is approved as to form and
legality and requires majority vote for approval. JAK
RECOMMENDATION: To approve the Transportation Commitment Extension Request for the ROCKEDGE
Residential Planned Unit Development (RPUD) to provide more time to fulfill the Transit Bus Stop Improvement
Commitment.
PREPARED BY: Michelle Arnold, PTNE Division Director
ATTACHMENT(S)
1. Transit Development Commitment Extension letter #2 - 50% (PDF)
Packet Pg. 576
11/08/2022
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.A.8
Doe ID: 23544
Item Summary: Recommendation to approve a second Transportation Commitment Extension Request for the
ROCKEDGE Residential Planned Unit Development (RPUD) to provide more time to fulfill the Transit Bus Stop
Improvement Commitment.
Meeting Date: 11/08/2022
Prepared by:
Title: Division Director - Pub Tran & Nbrhd Enh — Public Transit & Neighborhood Enhancement
Name: Michelle Arnold
10/05/2022 4:54 PM
Submitted by:
Title: Division Director - Pub Tran & Nbrhd Enh — Public Transit & Neighborhood Enhancement
Name: Michelle Arnold
10/05/2022 4:54 PM
Approved By:
Review:
Public Transit & Neighborhood Enhancement Michelle Arnold
Growth Management Department Jeanne Marcella Growth Management Department
Growth Management Development Review Laurie Beard
Public Transit & Neighborhood Enhancement Omar Deleon
Growth Management Department
Growth Management Department
Office of Management and Budget
County Attorney's Office
Office of Management and Budget
County Manager's Office
Board of County Commissioners
Michelle Arnold Growth Management
Trinity Scott Transportation
Debra Windsor Level 3 OMB Gatekeeper Review
Jeffrey A. Klatzkow Level 3 County Attorney's Office Review
Christopher Johnson Additional Reviewer
Amy Patterson Level 4 County Manager Review
Geoffrey Willig Meeting Pending
Director Review Completed
10/05/2022 4:55 PM
Completed 10/06/2022 9:25 AM
Additional Reviewer Completed
10/06/2022 9:32 AM
Additional Reviewer Completed
10/06/2022 9:53 AM
Skipped 10/05/2022 4:53 PM
Completed 10/06/2022 11:03 AM
Completed 10/06/2022 2:43 PM
Completed 10/07/2022 10:56 AM
Completed 10/13/2022 2:03 PM
Completed 11/02/2022 11:22 AM
11 /08/2022 9: 00 AM
I Packet Pg. 577 1
September 21, 2022
RWA, Inc.
6610 Willow Park Drive, Suite 200
Naples, Florida 34109
Subject: Transportation Commitment "A" Extension Request for Rockedge Residential
Planned Unit Development (RPUD)
AKA: Tamarindo
Project Number: PL20190002554
Dear Mr. Pappas:
Thank you for your continued coordination with the Public Transit & Neighborhood Enhancement (PTNE)
Division regarding the Transportation Commitment requiring the installation of bus stop improvements
with shelter within the vicinity of the intersection of Sabal Palm Road and Collier Boulevard.
Based on your good faith effort towards meeting this commitment the County is amenable to granting an
additional extension providing for the issuance of Certification of Completion (CO) for the Tamarindo
development up to 50% of the approved units. The bus shelter and associated improvements must be
installed and accepted by the County on or before the issuance of COs for 50% of the approved units.
Should the commitment not be satisfied by this time period, the issuance of any further COs will be
suspended until the commitment is satisfied.
Please obtain the property owner's signature below as acceptance of this extension. After receipt of the
signed letter, we will place the extension on a future Board of County Commissioner's agenda for their
approval.
Sincerely,
Michelle Arnold, Director
Public Transit & Neighborhood Enhancement
,4, , Iz? /--
PropAty Owner
Rockedge Residential Planned Unit Development (RPUD)
I Packet Pg. 578 1