Agenda 10/25/2022 Item #11B (Construction, Engineering, and Inspection Services for the integrated Wastewater Basin 101 Project specific for 105th and 106th Avenue North)10/25/2022
EXECUTIVE SUMMARY
Recommendation to approve a $1,146,154.00 purchase order to Stantec Consulting Services, Inc., under
Professional Services Agreement Number 14-6345, for Construction, Engineering, and Inspection Services
for the Public Utility Renewal Project for 105th and 106th Avenues North. (Companion to item 11A)
OBJECTIVE: To obtain professional Construction, Engineering, and Inspection (“CEI”) services during
construction of the integrated Wastewater Basin 101 Project specific for 105th and 106th Avenues North. The
companion executive summary requests Board approval for the construction contract for the project.
CONSIDERATIONS: On July 7, 2015 (Agenda Item 16.C.6), the County awarded Agreement Number 14 -6345
for CEI Services for the Wastewater Basin Programs to three different firms for each of the designated wastewater
basins projects. Agreement Number 14-6345 encompassed CEI services pertaining to wastewater collection, water
distribution, and stormwater system construction projects within each basin. The County selected Stantec
Consultant Services, Inc. (“Stantec”), for Basin 101 construction projects, which at the time of solicitation and
award contemplated and encompassed an integrated water, wastewater and stormwater construction project . This
Executive Summary is a companion item to the 105th and 106th Avenues North construction agreement services
Executive Summary for Douglas N. Higgins Inc.
The proposed scope of work under Project Number 60139, “Naples Park Stormwater Improvements,” i s consistent
with the Stormwater Five-year Work Program of the 2021 Stormwater Management Annual Update Inventory
Review (AUIR) / CIE approved by the Board on November 9, 2021, and with the goals, objectives and policies of
the Conservation and Coastal Management Element and the Stormwater Management Sub-Element of the Growth
Management Plan. The proposed scope of work under Project Number 70120, “Naples Park Area Basin
Optimization,” is consistent with the FY2022 Budget approved by the Board on September 23, 2021.
On September 12, 2022, Stantec provided a cost proposal in the amount of $1,146,154.00 to provide CEI services
for construction of the 105th and 106th Avenues North Public Utility Renewal Project. Staff found this time and
materials proposal acceptable based on prior negotiation history for similar contracts in Naples Park. The scope of
services proposal includes construction observation and documentation services. The project scope includes
replacing and rehabilitating water, wastewater, and stormwater assets in one coordinated project designed to
minimize cost and neighborhood impact as opposed to multiple separate mobilizations.
After this project is completed, eight Naples Park streets will have been rehabilitated in this comprehensive man ner:
107th, 110th, 95th, 96th, 108th, 109th, 105th and 106th Avenues North. Prior to that, in 2013 and 2014, water mains
were replaced on 91st, 92nd, 93rd and 94th Avenues North. The next two streets planned for water, wastewater and
stormwater construction are 98th and 99th Avenues North.
11.B
Packet Pg. 155
10/25/2022
FISCAL IMPACT: Funding is consistent with the Fiscal Year 2022 Budget approved by the Board on September
23, 2021. A budget amendment is necessary to transfer funding within Stormwater Bond Fund (327) from Reserves
to project 60139. The budget amendment is included with the award of the construction project. The sources of
funding are the Stormwater Bond Fund (327), Water Capital Fund (412) and Wastewater Capital Fund (414), as
allocated below.
FUNDING SOURCE AMOUNT BID %
Stormwater Capital Fund (327) $447,000.06 39%
Water Capital Fund (412) $229,230.80 20%
Wastewater Capital Fund (414) $469,923.14 41%
Total $1,146,154.00 100%
LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for
Board approval.-SRT
GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan standards to
ensure the adequacy and availability of viable public facilities.
RECOMMENDATION: That the Board approves a $1,146,154.00 Purchase Order to Stantec Consulting
Services, Inc., under Professional Services Agreement Number 14-6345 for Construction, Engineering, and
Inspection Services for the Public Utility Renewal Project for 105th and 106th Avenues North. (Project Numbers
60139 and 70120)
Prepared by: Ray G Girgis, PE, Senior Project Manager, Engineering and Project Management Division
ATTACHMENT(S)
1. let_girgis_105th_106th_Ave_CEI_Proposal_2022-09-12_SignedStantec (PDF)
2. 105th and 106th Avenues Presentation-9.27.22 (PDF)
3. 14-6345Stantec_Contract_20210311022721.183 (PDF)
11.B
Packet Pg. 156
10/25/2022
COLLIER COUNTY
Board of County Commissioners
Item Number: 11.B
Doc ID: 23504
Item Summary: *** This Item continued from the September 27, 2022 BCC Meeting. *** Recommendation to
approve a $1,146,154.00 purchase order to Stantec Consulting Services, Inc., under Professional Services
Agreement Number 14-6345, for Construction, Engineering, and Inspection Services for the Public Utility Renewal
Project for 105th and 106th Avenues North. (Project Numbers 60139 and 701 20) (Companion to item 11A)
(Matthew McLean, Director, Engineering and Project Management Division)
Meeting Date: 10/25/2022
Prepared by:
Title: Project Manager – Public Utilities Planning and Project Management
Name: Diana Dueri
10/03/2022 10:37 AM
Submitted by:
Title: Director – Public Utilities Planning and Project Management
Name: Matthew McLean
10/03/2022 10:37 AM
Approved By:
Review:
Public Utilities Planning and Project Management Drew Cody Additional Reviewer Skipped
10/03/2022 10:32 AM
Procurement Services Drew Cody Additional Reviewer Skipped 10/03/2022 10:32 AM
Procurement Services Drew Cody Additional Reviewer Skipped 10/03/2022 10:32 AM
Public Utilities Operations Support Drew Cody Additional Reviewer Skipped 10/03/2022 10:32 AM
Growth Management Department Drew Cody Additional Reviewer Skipped 10/03/2022 10:32 AM
Capital Project Planning, Impact Fees, and Program Management Drew Cody Additional Reviewer Skipped
10/03/2022 10:32 AM
Growth Management Operations Support Drew Cody Additional Reviewer Skipped
10/03/2022 10:32 AM
Public Utilities Department Drew Cody Level 1 Division Reviewer Skipped 10/03/2022 10:32 AM
Procurement Services Drew Cody Level 1 Purchasing Gatekeeper Skipped 10/03/2022 10:32 AM
County Attorney's Office Drew Cody Level 2 Attorney Review Skipped 10/03/2022 10:32 AM
Public Utilities Department Drew Cody Level 2 Division Administrator Review Skipped 10/03/2022 10:32 AM
Growth Management Department Drew Cody Additional Reviewer Skipped 10/03/2022 10:32 AM
County Attorney's Office Drew Cody Level 3 County Attorney's Office Review Skipped 10/03/2022 10:32 AM
Office of Management and Budget Drew Cody Additional Reviewer Skipped 10/03/2022 10:32 AM
Office of Management and Budget Drew Cody Level 3 OMB Gatekeeper Review Skipped 10/03/2022 10:32 AM
County Manager's Office Dan Rodriguez Level 4 County Manager Review Completed 10/18/2022 8:40 AM
Board of County Commissioners Geoffrey Willig Meeting Pending 10/25/2022 9:00 AM
11.B
Packet Pg. 157
Stantec Consulting Services, Inc.
5801 Pelican Bay Boulevard, Suite 300, Naples, FL 34108
12 September 2022
Attention: Mr. Ray G. Girgis, PE
Collier County Public Utilities Engineering and Project Management Department
3339 Tamiami Trail E., Suite 303
Naples, FL 34112
Dear Mr. Girgis,
Reference: CEI Services for Wastewater Basing Program Contract #14-6345,
105th and 106th Avenue North Public Utilities Renewal
Please find enclosed the Scope of Services for the above referenced project for your review and approval.
We thank you for the opportunity to provide Construction, Engineering, and Inspection (CEI) services for this
project. We look forward to working with Collier County on this and upcoming utility infrastructure projects.
We’re prepared to begin work on this assignment as soon as you direct us to proceed.
Should you have any questions or need additional information please do not hesitate to contact Marc Lean
at (239) 910-2757 or marc.lean@stantec.com.
Regards,
Stantec Consulting Services, Inc.
Marc Lean, PE
Principal
Phone: 239-910-2757
marc.lean@stantec.com
Attachments: 105th and 106th Avenue CEI Scope and Fee Sheet
c. Kyle Goodwin, PE, Stantec
lm \\us0226-ppfss01\workgroup\1773\business_development\collier county\14-6345 cei services for the wastewater basin programs\work assignment
development\14-6345_105th_106th_aves\let_girgis_105th_106th_ave_cei_proposal_2022-09-12.docx
11.B.1
Packet Pg. 158 Attachment: let_girgis_105th_106th_Ave_CEI_Proposal_2022-09-12_SignedStantec (23504 : 105th and 106th Avenues Public Utilities Renewal*pDigitally signed by Marc
Lean
Reason: I am the author of
this document
Date: 2022.09.12
13:14:48-04'00'
asdsadasdwd
ml \\us0226-ppfss01\workgroup\1773\business_development\collier county\14-6345 cei services for the wastewater basin programs\work
assignment development\14-6345_105th_106th_aves\scp_105th_106th_ave_ceisvcs_2022-09-12.docx 1
SCHEDULE A – SCOPE OF SERVICES
Collier County Contract 14-6345
Construction Engineering & Inspection (CEI) Services
105th and 106th Avenues North Public Utilities Renewal Project
Prepared 2022-09-12
I. BACKGROUND
105th and 106th AVENUES NORTH – PUBLIC UTILITIES RENEWAL PROJECT
EPMD has selected Stantec Consulting Services Inc. (Stantec) to provide construction and engineering
and inspection services throughout the duration of the preconstruction, construction, and commissioning of
the utilities renewal projects within Basin 101 / Naples Park area. The 105th and 106th Avenues North
Public Utilities Renewal project consists of the repair and replacement of water, wastewater, and
stormwater systems along 105th and 106th Avenues North, between Tamiami Trail and Vanderbilt Drive.
As part of the improvements project, the Contractor will be replacing water and sewer service lines. Each
clay sewer pipe lateral from the property will be replaced with new PVC pipe. The service line work may
need to take place on private property and permission from the owner will be necessary. Stormwater
collection and treatment system rehabilitation work will take place within the right-of-way. This project will
improve the ability to send wastewater flows from Basin 101 to NCWRF and is necessary to ensure a
continued high level of utility service for the community.
II. PURPOSE
The purpose of the 105th and 106th Avenues North Public Utilities Renewal project is to repair and replace
aging water, wastewater, and stormwater infrastructure. This document describes Stantec’s CEI services
scope of work for the 105th and 106th Avenues North Public Utilities Renewal project.
III. SCOPE OF SERVICES
Tasks 1.0 & 2.0 CEI Consultant / Project Oversight and Documentation
All CEI Consulting/Project Oversight and Documentation Services will be completed under a single task
per each avenue and will generally consist of the following as presented below.
Task 1.0 will be designated for 105th Avenue North.
Task 2.0 will be designated for 106th Avenue North.
Services to be provided as part of this task will include the following:
1.1 General Management and Oversight – Stantec will provide support services customarily related to
the construction observation and documentation of similar projects including, but not limited to the following:
a. Upon request by the Project Manager, participate in other meetings as described or implied herein.
b. Review and verify accuracy of the construction Contractor’s monthly applications for payment and
11.B.1
Packet Pg. 159 Attachment: let_girgis_105th_106th_Ave_CEI_Proposal_2022-09-12_SignedStantec (23504 : 105th and 106th Avenues Public Utilities Renewal
asdsadasdwd
ml \\us0226-ppfss01\workgroup\1773\business_development\collier county\14-6345 cei services for the wastewater basin programs\work
assignment development\14-6345_105th_106th_aves\scp_105th_106th_ave_ceisvcs_2022-09-12.docx 2
accompanying data and provide Engineer of Record (EOR) confirmation that quantities shown on
the application for payment accurately reflect the progress of the Work completed in conformance
with the Contract Documents.
c. Coordination correspondence with County Project Manager, Engineer of Record and CEI Field staff
as necessary for Construction of the Work to be in reasonable conformance with the Contract
Documents, and as amended by the Engineer of Record.
Deliverables: None.
1.2 General Construction/Testing Observation – Stantec will conduct on-site observations and
inspections of construction/testing activities on the Project on a full-time basis, up to ten (10) hours per
construction day, unless directed otherwise by the County’s Project Manager, to assess whether the Work
is completed in general conformance with the Contract Documents approved submittals, RFI responses,
Change Orders, and Work Directives issued by the Engineer of Record and/or County Project Manager.
Stantec will notify the Contractor of any issues related to non-conformance of the Work with the
aforementioned documents and document these notifications on the DWR. Stantec will provide
interpretation of plans and specifications and will assist the Contractor by developing solutions to field
issues and conflicts at the project field level. If the issue or conflict cannot be resolved at the project field
level; Stantec will coordinate, document, and prepare a Request For Clarification (RFC). RFCs prepared
by Stantec will be submitted to the Engineer of Record for their response, which in turn, will be reviewed
and approved by the County prior to submitting a response to the Contractor.
Stantec shall not be responsible for preparing, implementing, or supervising the Contractor’s Health and
Safety or Maintenance of Traffic Plans, nor has Supervisor Control of the Contractor or the authority to stop
the Contractor from working. Issues of concern related to either plan will be discussed with the Contractor
at the field level and reported to the County’s Project Manager. If the concern continues to persist following
discussion at the field level, then the issue will be elevated to Contractor’s and County’s Project Managers
for resolution.
1.3 Daily Work Report (DWR) and Construction Documentation – Stantec will prepare a DWR with
pictures recording activities and details related to the work on a form approved by the County’s Project
Manager in advance of the work. Information will be recorded in the DWR when at the Project Site. The
DWR will record relevant aspects of the construction observed while on site including, but not limited to:
construction crew (labor) details, equipment used, materials used, compliance testing and inspection
performed (by Others), site conditions, trench conditions, backfill material used, dewatering methods,
compaction methods, location of the work, and other details related to the Work. The DWRs will reference
the digital photographs and or video taken with appropriate photo captions. Additionally, the DWR will
contain information related to: time and hours on the job site, weather conditions, list of visiting officials and
representatives of manufacturers, fabricators, suppliers and distributors, observations in general and
specific observations in more detail, such as in observing test procedures, conformance observation of
materials and fittings, name plate data for equipment and material installed, customer service field log, and
other information requested by the County’s Project Manager. DWRs including photographs with captions
and other construction documentation will be provided to the County’s Project Manager by Stantec on a
daily basis in an electronic file via E-mail. All other construction documentation produced by Stantec will be
provided upon request. Stantec’s field representatives will also assist the Contractor in completing the AC
Pipe Removal Checklist. Stantec will assist the County with updating project progress on the project
website.
Deliverables: Daily Work Reports, Project Specific Progress Reporting for the weekly PUR website, and
AC Pipe Removal Checklist.
1.4 As-Constructed Field Drawings – Stantec will maintain red pencil “mark-up” notations and sketches
on full size construction plans that reflect the actual details of constructed facilities. These As-Constructed
Field Drawings will be used by Stantec to validate the “As-Built” documentation provided by the construction
11.B.1
Packet Pg. 160 Attachment: let_girgis_105th_106th_Ave_CEI_Proposal_2022-09-12_SignedStantec (23504 : 105th and 106th Avenues Public Utilities Renewal
asdsadasdwd
ml \\us0226-ppfss01\workgroup\1773\business_development\collier county\14-6345 cei services for the wastewater basin programs\work
assignment development\14-6345_105th_106th_aves\scp_105th_106th_ave_ceisvcs_2022-09-12.docx 3
Contractor.
Deliverables: Stantec’s As-Constructed Field Drawings in Digital Format
1.5 Substantial Completion Walk-Through – Stantec’s CEI representative will attend Substantial
Completion Walk-Through when requested by County Project Manager. This service will be limited to 1
walk-through per block, each up to 2 hours in duration. There are four (4) blocks along each avenue,
therefore a total of 4 walk-throughs (maximum of 8-hours) are anticipated for each avenue.
Deliverables: None.
1.6 Final Completion Walk-Through – Stantec’s CEI representative will attend Final Completion Walk-
Through when requested by County Project Manager. This service will be limited to one walk-through per
avenue up to 8 hours in duration per each walk-through.
Deliverables: None.
1.7 Re-commissioning Support – Stantec will provide general coordination and will assist the County’s
Project Manager, the EOR and the construction Contractor during re-commissioning of the water main in
each applicable phase.
1.8 Reimbursable Expenses – $500 in expenses for each avenue has been assumed for reimbursable
expense purposes.
Stantec shall be reimbursed for all expenses in connection with the performance of the above services, as
allowed for in Contract #14-6345.
Project related reimbursable expenses include the printing of notifications, letters, maps, drawings, and
specifications. The cost for all materials and postage will be invoiced under this task with supporting cost
information.
ASSUMPTIONS
• Review of Contractor’s Application for Payment will be by Others.
• Review of Contractor’s Progress Schedule will be by Others.
• Review of Construction Submittals or preparation of Submittal Responses will be by Others.
• Coordination of Submittals for review by the Engineer of Record or County, assistance with
distribution of Submittal Responses, preparation and maintenance of Submittal Logs will be
completed by the Engineer of Record.
• Submittal review and submittal log preparation will be by Others.
• Preparation and Maintenance of Request for Clarification and/or Request for Information Logs,
which will be provided by the Engineer of Record.
• Preparation and maintenance of Work Directive and Change Order tracking logs, which will be
provided by the Engineer of Record or County Project Manager.
• Distribution of Project Records including but not limited to progress schedules and testing reports
prepared or submitted by the Contractor will be by Others.
11.B.1
Packet Pg. 161 Attachment: let_girgis_105th_106th_Ave_CEI_Proposal_2022-09-12_SignedStantec (23504 : 105th and 106th Avenues Public Utilities Renewal
asdsadasdwd
ml \\us0226-ppfss01\workgroup\1773\business_development\collier county\14-6345 cei services for the wastewater basin programs\work
assignment development\14-6345_105th_106th_aves\scp_105th_106th_ave_ceisvcs_2022-09-12.docx 4
• Assisting the County Project Manager with Construction Contract administration items including,
but not limited to: Preparation of Change Orders, Work Directives, and Requests for Proposals;
Review of Change Order Proposals or Change Order back-up/supporting documentation;
Coordination with other utility owners; engineering design coordination with others for restoration
of driveways, swales, and irrigation beyond the information shown on the plans will be by Others.
The County Project Manager or Engineer of Record shall provide Stantec all applicable
aforementioned information to certify the Work is in reasonable conformance with the Contract
Documents and as amended by the Engineer of Record.
• Preparation or maintenance of Substantial and Final Completion Punch Lists will be completed by
the Engineer of Record.
• Preparation of Progress Meeting Agenda’s, Minutes, Notes, or Summaries will be completed by
Others.
• Participation in or assistance with closing out of the Contractor’s Right-of-Way Permit will be by
Others.
• Any services related to dealing with third party administrative hearings is an additional service
that can be provided through a separate work assignment or change order to this work
assignment.
• Distribution of door hangers, providing or delivering chairs or tables, furnishing meeting venues,
not setting up or breaking down meeting venues will be by Others.
• Services not specifically identified in this scope of work are considered additional services that can
be provided through a separate work assignment or change order to this work assignment.
IV. FEE PROPOSAL
All work will be charged on an hourly basis in accordance with the Project Budget Form, to the best of our
ability. Changes in staffing and staff classifications shown in the Project Budget Form may be necessary
depending on actual project needs and staff availability. Therefore, staff classifications not currently shown
on the Project Budget Form, but identified in Stantec’s Construction Engineering and Inspection (CEI)
Service for the Wastewater Basin Programs (MPS 101 Basin) 14-6345), may be utilized as necessary.
Many facets that control the length of the project and necessary effort are outside the control of Stantec.
Hours shown in this work assignment are only estimates. Any additional work that may be required will be
performed under a separate Work Assignment, or as an amendment to this one.
Task Estimated
Fee
Fee
Type
Task 1.0 – 105th Ave CEI Consultant / Project Oversight and Documentation $573,077 T&M
Task 2.0 – 106th Ave CEI Consultant / Project Oversight and Documentation $573,077 T&M
Total Fee $1,146,154 T&M
V. SCHEDULE
Stantec will provide services throughout the duration of the project, which is anticipated to be 64 weeks at
the time of preparing this scope of services, as directed by the County in accordance with the Project
Schedule as defined by Contract #14-6345 “Construction Engineering and Inspection (CEI) Services for
the Wastewater Basin Programs (MPS 101 Basin)” and its amendments.
11.B.1
Packet Pg. 162 Attachment: let_girgis_105th_106th_Ave_CEI_Proposal_2022-09-12_SignedStantec (23504 : 105th and 106th Avenues Public Utilities Renewal
Sr. Project Manager Project Manager Part-Time Sr. Inspector Full-Time Sr. Inspector Clerical/Administrative Full-Time Sr. Inspector Reimbursible Expenses Project Summary Hours Labour Expense Subs Total
Project Billing Rate $168.00 $157.00 $118.00 $118.00 $70.00 $118.00 $1.00 Fixed Fee 0 $0.00 $0.00 $0.00 $0.00
Total Units (T&M) 264 1306 1160 3180 120 3180 1000 Time & Material 9210 $1,145,154.00 $1,000.00 $0.00 $1,146,154.00
Fee (T&M) $44,352.00 $205,042.00 $136,880.00 $375,240.00 $8,400.00 $375,240.00 $1,000.00 Total 9210 $1,145,154.00 $1,000.00 $0.00 $1,146,154.00
Task
Number Task Name Start Date End Date Task Type Hours Labour Expense Subs Total
1
Task 1.0 - 105th Avenue CEI Consultant, Project Oversight
and Documentation 2022-12-01 2024-02-24 132 653 580 3180 60 0 500 Time & Material 4605 $572,577.00 $500.00 $0.00 $573,077.00
2
Task 2.0 - 106th Avenue CEI Consultant, Project Oversight
and Documentation 2022-12-01 2024-02-24 132 653 580 0 60 3180 500 Time & Material 4605 $572,577.00 $500.00 $0.00 $573,077.00
Units
FEE ESTIMATE -105th and 106th Ave Public Utility Renewal Project Avenue, CEI Services
Prepared 2022-09-12
11.B.1
Packet Pg. 163 Attachment: let_girgis_105th_106th_Ave_CEI_Proposal_2022-09-12_SignedStantec (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
105th and 106th Avenues
Public Utilities Renewal
Public Utilities Department
Transportation Management Services
September 27, 2022
Collier County | Florida
11.B.2
Packet Pg. 164 Attachment: 105th and 106th Avenues Presentation-9.27.22 (23504 : 105th and 106th Avenues Public
Companion Items
Two companion executive summaries for the 105th and
106th Avenues Public Utilities Renewal Project are
seeking Board approval:
1.Construction of the water, wastewater and
stormwater infrastructure. The contractor is Douglas
N. Higgins, Inc. with extensive experience in similar
projects, specifically in Naples Park.
2.Construction, Engineering and Inspection (CEI)
Services for Stantec Consulting Services, Inc.,
previously Board-approved for the Naples Park area.
Public Utilities Department
Engineering and Project Management Division 2
11.B.2
Packet Pg. 165 Attachment: 105th and 106th Avenues Presentation-9.27.22 (23504 : 105th and 106th Avenues Public
Objective
•Provide reliable, sustainable, and
regulatory compliant services to the
customers along 105th and 106th
Avenues North in the Naples Park
neighborhood by replacing the water,
wastewater and stormwater
infrastructure.
Public Utilities Department
Engineering and Project Management Division 3
11.B.2
Packet Pg. 166 Attachment: 105th and 106th Avenues Presentation-9.27.22 (23504 : 105th and 106th Avenues Public
Project Location
Public Utilities Department
Engineering and Project Management Division 4
US 41
Va nderbilt
Drive
105th Av e North 106th Av e North
11.B.2
Packet Pg. 167 Attachment: 105th and 106th Avenues Presentation-9.27.22 (23504 : 105th and 106th Avenues Public
Considerations -Water & Stormwater
•Installed in the late 1960s.
•Removes and disposes of existing asbestos-cement
water main.
•Installs approximately 11,000 linear feet of new
polyvinyl chloride (PVC) water main.
•Installs new fire hydrants, gate valves, water
services, water meters, and back flow preventers.
•Removes and replaces approximately 10,000 linear
feet of aging corrugated metal culvert pipes with
new perforated high-performance pipe.
•Replaces old drainage structures with catch basins
and sumps to ensure proper drainage.
Public Utilities Department
Engineering and Project Management Division 5
11.B.2
Packet Pg. 168 Attachment: 105th and 106th Avenues Presentation-9.27.22 (23504 : 105th and 106th Avenues Public
Considerations -Wastewater
Public Utilities Department
Engineering and Project Management Division 6
Wastewater infrastructure
•Installed in the early 1970s.
•Re moves and replaces approximately 10,000
linear feet of existing vitrified clay gravity sewer
pipe, laterals and cleanouts with PVC pipe.
•Re places concrete manholes with polymer
concrete manholes which require less
maintenance.
11.B.2
Packet Pg. 169 Attachment: 105th and 106th Avenues Presentation-9.27.22 (23504 : 105th and 106th Avenues Public
Considerations
Public Utilities Department
Engineering and Project Management Division 8
On March 31, 2022 Procurement Service
Division posted ITB No. 22-7982, 105th
Av e. North and 106th Ave. North Public
Utilities Renewal. On May 10, 2022, the
County received two bids as summarized
below.
Company Name City County ST Bid Amount Responsive/
Responsible
Douglas N. Higgins, Inc. Naples Collier FL $16,806,410.00 Yes/Yes
Haskins, Inc.Bonita Springs Lee FL $20,602,975.00 No/Yes
11.B.2
Packet Pg. 170 Attachment: 105th and 106th Avenues Presentation-9.27.22 (23504 : 105th and 106th Avenues Public
Neighborhood Coordination
Public Utilities Department
Engineering and Project Management Division 7
•Detail information letter with Right of Entry form
will be sent to all homeowners on 105th and 106th
Av enues.
•A Neighborhood Information Meeting (NIM) will be
scheduled before construction starts.
•Project phone line: 239-451-0280.
•Project e-mail: NaplesParkPUR@CollierCountyFL.gov
•Project updates and notices: www.CollierPUR.com
•Public information services provided by Stantec, the
CEI consultant.
11.B.2
Packet Pg. 171 Attachment: 105th and 106th Avenues Presentation-9.27.22 (23504 : 105th and 106th Avenues Public
Recommendations
u To award Invitation to Bid (“ITB”) No. 22-7982, “105th Avenue
North and 106th Avenue North Public Utilities Renewal”, (project
numbers 60139 and 70120) to Douglas N. Higgins Inc., in the
amount of $16,806,410.00, and authorize the Chairman to sign
the attached Agreement and authorize the necessary budget
amendment.
u That the Board of County Commissioners approves a
$1,146,154.00 Purchase Order to Stantec Consulting Services,
Inc.
Public Utilities Department
Engineering and Project Management Division 8
11.B.2
Packet Pg. 172 Attachment: 105th and 106th Avenues Presentation-9.27.22 (23504 : 105th and 106th Avenues Public
Extra Slides
11.B.2
Packet Pg. 173 Attachment: 105th and 106th Avenues Presentation-9.27.22 (23504 : 105th and 106th Avenues Public
Construction Sequence:
Public Utilities Department
Engineering and Project Management Division
•Re place water main simultaneously on 105th and
106th Avenues to avoid damaging fragile asbestos
cement water mains throughout the remainder of
the project.
•Wa stewater and stormwater construction and
restoration will follow, occurring one block at a time
also simultaneously on both avenues.
•Minimizes neighborhood disruption and accelerates
restoration.
•This process was proven effective during
construction of 95th, 96th, 108th and 109th Av enues.
11.B.2
Packet Pg. 174 Attachment: 105th and 106th Avenues Presentation-9.27.22 (23504 : 105th and 106th Avenues Public
Naples Park Summary
u 91st & 92nd Ave. N. Water main replacement completed in 2014.
u 93rd & 94th Ave. N.: Water main replacement completed in 2015.
u 97th Ave. N. (700 Block): Water and sewer main replacement
completed in 2015.
u 107th Ave. N. Public Utility Renewal (PUR): Water and sewer
replacement and wastewater force main installation with
stormwater improvements from Vanderbilt Drive to 8th Street.
Completed in 2018.
u 110th Ave. N. PUR: Water and sewer replacement with stormwater
improvements from Vanderbilt Dr. to US 41. in 2018.
u 95th Ave. N. PUR: Water and sewer replacement combined with
stormwater improvements from Vanderbilt Dr. to US 4 Completed
in 2020.
u 96th Ave. N. PUR: Water and sewer replacement with stormwater
improvements from Vanderbilt Dr. to US 41 completed in 2021.
u 108th and 109th Ave. N. PUR: Water and sewer replacement with
stormwater improvements from Vanderbilt Dr. to US 41 are
scheduled to be completed 09/2022.
11.B.2
Packet Pg. 175 Attachment: 105th and 106th Avenues Presentation-9.27.22 (23504 : 105th and 106th Avenues Public
Naples Park
Summary
11.B.2
Packet Pg. 176 Attachment: 105th and 106th Avenues Presentation-9.27.22 (23504 : 105th and 106th Avenues Public
Existing Conditions
11.B.2
Packet Pg. 177 Attachment: 105th and 106th Avenues Presentation-9.27.22 (23504 : 105th and 106th Avenues Public
During Construction
11.B.2
Packet Pg. 178 Attachment: 105th and 106th Avenues Presentation-9.27.22 (23504 : 105th and 106th Avenues Public
Post-Construction Conditions
11.B.2
Packet Pg. 179 Attachment: 105th and 106th Avenues Presentation-9.27.22 (23504 : 105th and 106th Avenues Public
11.B.3
Packet Pg. 180 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 181 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 182 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 183 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 184 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 185 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 186 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 187 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 188 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 189 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 190 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 191 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 192 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 193 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 194 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 195 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 196 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 197 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 198 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 199 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 200 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 201 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 202 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 203 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 204 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 205 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 206 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 207 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 208 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 209 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 210 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 211 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 212 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 213 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 214 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 215 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 216 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 217 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 218 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 219 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 220 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 221 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 222 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)
11.B.3
Packet Pg. 223 Attachment: 14-6345Stantec_Contract_20210311022721.183 (23504 : 105th and 106th Avenues Public Utilities Renewal Project - CEI)