Agenda 09/27/2022 Item #16C 7 (Project update on the Collier County Sports Complex being built under agreement No.17-7198)09/27/2022
EXECUTIVE SUMMARY
Recommendation to accept a project update on the Collier County Sport Complex being built
under Agreement No. 17-7198, with Manhattan Construction (Florida), Inc., (Project 50156).
OBJECTIVE: To keep the Board informed on this major capital improvement project.
CONSIDERATION: On July 7, 2022, the Board approved Change Order No. 10 to Agreement 17-7198
with Manhattan Construction (Florida), Inc. The change order provided a time extension of 145 days to
complete Phase 2.1 and 2.2A of the Collier County Sports Complex. Substantial completion under this
extension is November 30, 2022, and final completion is December 30, 2022.
Phase 1 update: Phase 1 construction is completed with buildings and improvements open to the public
under temporary Certificates of Occupancy originally issued in July 2020 for the Welcome Center and
December 2020 for the Stadium. Manhattan has been pursuing final certificates of occupancy that require
completion of required inspections and other work. There are pending Phase 1 issues including: final
Certificate of Occupancy, punch list items, outstanding change orders, other potential contractor claims,
and liquidated damages. Notwithstanding the foregoing, the improvements in this phase are in use by the
County.
Phase 2 update: The excavation of water management areas and other related site construction elements
are largely completed. The extension of City Gate Boulevard North, the addition of four sports fields,
internal roadways, and parking lots are approximately 70% complete.
With a priority placed on delivering four fields in advance of the December FBU National Football
Championship substantial completion was programmed to be November 2022 and final completion
December 2022.
On September 9, 2022, the supplier of aggregate for the four fields under construction, (Conrad
Yelvington) advised SCG Fields (field subcontractor) that a significant supply disruption has impacted its
ability to deliver materials as planned. As of September 21, 2022, Manhattan Construction is diligently
working to mitigate the supply disruption. They are in direct communication with other suppliers as far
north as Georgia to secure the necessary material. At this time, the supply disruption has negatively
impacted the completion schedule by at least 3 weeks. While it is presently impossible to estimate total
lost time it is likely that completion will not be achieved before the final completion date of December 30,
2022. Staff will monitor the situation and advise Sports Facili ties Companies and FBU management on
availability of the four fields under construction as soon as possible.
Phase 3 update: Phase 3 will include field No. 9 and its associated prefabricated metal building
structure, the south parking lot and potentially a bathroom structure (Bldg. 18) originally value engineered
out of Phase 2. Staff will construct this phase through a new contract mechanism separate from the
current Manhattan contract. Potential start of construction is Spring 2023 with an approximat e
construction timeline of nine to twelve months.
Phase 4 update: This phase consists of eleven multipurpose fields (five fields will be softball, mini
soccer, and little league, six fields will be baseball and soccer) as well as ancillary buildings. Building
selection and design will be determined through the design process.
Phase 4 design and construction management services are estimated to be $1.4M with estimated
construction costs between $25M and $30M. Financing will be required. Staff will prese nt a design
contract and a plan of finance to the Board late spring 2023.
FISCAL IMPACT: This project update does not have a fiscal impact. Funding for Sports Complex
Project No. 50156 is provided in Sports Complex Capital Improvement Fund (370). Funding for the
project is provided by bond proceeds, TDC funds and the General Fund.
16.C.7
Packet Pg. 1027
09/27/2022
GROWTH MANAGEMENT IMPACT: There is no impact to the Growth Management Plan related to
this action.
LEGAL CONSIDERATIONS: This item has been reviewed by the County Attorney, raises no legal
issues and requires majority vote for any Board action. -JAK
RECOMMENDATION: To accept a project update for the Collier County Sports Complex.
Prepared by: Ed Finn, Interim Deputy County Manager
ATTACHMENT(S)
1. Material Status Letter- SCG -09-09-22 (PDF)
2. 7675-CC19_Full Schedule (PDF)
3. Mexico Halts Vulcan Operation - Rock Products Magazine (PDF)
4. Aerial North (JPG)
5. Aerial North 2 (JPG)
16.C.7
Packet Pg. 1028
09/27/2022
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.C.7
Doc ID: 23459
Item Summary: Recommendation to accept a project update on the Collier County Sport
Complex being built under Agreement No. 17-7198, with Manhattan Construction (Florida), Inc.,
(Project 50156).
Meeting Date: 09/27/2022
Prepared by:
Title: Sr. Operations Analyst – County Manager's Office
Name: Geoffrey Willig
09/21/2022 3:36 PM
Submitted by:
Title: – Facilities Management
Name: John McCormick
09/21/2022 3:36 PM
Approved By:
Review:
Facilities Management John McCormick Director - Facilities Completed 09/21/2022 4:25 PM
County Manager's Office Ed Finn Additional Reviewer Completed 09/21/2022 4:26 PM
Office of Management and Budget Susan Usher Additional Reviewer Completed 09/21/2022 4:32 PM
County Attorney's Office Ed Finn Level 3 County Attorney's Office Review Skipped 09/21/2022 4:31 PM
County Manager's Office Dan Rodriguez Level 4 County Manager Review Completed 09/21/2022 4:43 PM
Board of County Commissioners Geoffrey Willig Meeting Pending 09/27/2022 9:00 AM
16.C.7
Packet Pg. 1029
2328 BELLEVUE AVENUE * DAYTONA BEACH, FLORIDA 32114 * (386) 257-5504 * www.cydi.com
09-09-22
SCG Fields,
To follow up in writing our conversations over the last two weeks, to explain the supply issues on
all aggregates in Florida that was not present when we quoted this project
Back in Feb 2022. We did have a reserve of 20k of 57 in stock and based on availability with a job start
eta of Mar 2022 we could have supplied this project if it had not been delayed. Then the project was
pushed back to July and material was not pulled until late August.
Here are some details as to why there is a supply issue we are facing.
1) Since the project got pushed back to July but did not start until late Aug there has
been a major shift the aggregate market, due to unforeseen circumstances of one of
the largest limestone vendors losing access to their quarry in Mexico removing aprx
200k+ tons per month out of Florida that came in via ship. Every state and local
government office is aware of this since as it is causing shortages of aggregate for all
FDOT major projects and county projects in the state and has put constraints on
every aggregate supplier in Florida that is trying to make up for almost 200k of
aggregate a month taken out of the supply chain due to high demand, no avaibility
or allocation shifts that has limited even our own availability to get product to our
internal concrete and asphalt plants.
I have attached the web address for the news event that lead up to this supply issue below.
See item 3
2) We are looking into our production and breakdowns to see what if any we will be
able to supply at this time and as soon as I have that information I will pass it onto
you and SCG.
3) https://rockproducts.com/2022/05/10/mexico-halts-vulcan-operation/
We know that our business is built on servicing our customer and fulfilling the commitments we make
but at times such as this that is just not possible.
Thanks Brenda Purvis
16.C.7.a
Packet Pg. 1030 Attachment: Material Status Letter- SCG -09-09-22 (23459 : Sports Complex update)
2328 BELLEVUE AVENUE * DAYTONA BEACH, FLORIDA 32114 * (386) 257-5504 * www.cydi.com
16.C.7.a
Packet Pg. 1031 Attachment: Material Status Letter- SCG -09-09-22 (23459 : Sports Complex update)
IDDescriptionOrigDurRemDurStartFinishCollier County Sports Park - Phase 2.1A, 2.1B, & 2.2Project Notes & MilestonesNTP02Notice To Proceed - Phase 2.10003/09/21ACONDURNTP to Substantial Completion (HAMMOCK - Calendar Days) 6329203/09/21A11/30/22OCT21FUNDRelease remainder of the Phase 2.1 work 0011/24/21ASUBST COMPSubstantial Completion0011/30/22FINAL COMPFinal Completion0012/30/22Schedule Delays / ImpactsCE#01 - Partial GMP ReleaseDEL.01-100Owner Issue Partial NTP1003/09/21A03/09/21ADEL.01-150Owner Issue Full GMP Funding183003/10/21A11/24/21ADEL.01-200Re-Bid & Review 15011/29/21A12/17/21ADEL.01-250Owner Review & Approve Bid (BCC Approval)26012/20/21A01/25/22ADEL.01-300CC Issue DMP PO1001/25/22A01/25/22ADEL.01-400MCC Receive Submittals From Subs34001/26/22A03/14/22ADEL.01-350Issue SCG Fields Subcontracts36001/26/22A03/16/22ADEL.01-450MCC Review & Submit SCG Fields Submittals1003/15/22A03/15/22ADEL.01-500AE Review & Approve SCG Fields Submittals22003/16/22A04/14/22ADEL.01-550PO, Fabrication & Delivery Of Early Materials (1st Delivery)15004/18/22A05/06/22ADEL.01-600PO, Fabrication & Delivery Of Early Materials (2nd Delivery)30004/18/22A05/27/22ADEL.01-650Delivery Turf Material (Fields 5 & 6)73004/18/22A07/29/22ADEL.01-700Delivery Turf Material (Fields 7 & 8)84004/18/22A08/15/22ADEL.01-750Subcontractor Mobilization5005/27/22A06/03/22AFPL Lighting & Distribution DrawingsDEL.02-100Receive FPL Phasing Agreement Exhibit140003/09/21A09/23/21ADEL.02-150Receive Lighting Agreement ROS #5 & #658009/24/21A12/16/21ADEL.02-200Receive Lighting Agreement ROS #759009/24/21A12/17/21ADEL.02-250Receive Lighting Agreement ROS #8133009/24/21A04/01/22ADEL.02-300Receive FPL Lighting Drawings (ROS #8)133009/24/21A04/01/22ADEL.02-350Receive FPL Lighting Drawings (ROS #5, #6 & #7)56012/20/21A03/08/22ADEL.02-400Receive FPL Lighting Material (ROS #5, #6 & #7)54012/22/21A03/08/22ADEL.02-450Receive FPL Lighting Material (ROS #8)36004/04/22A06/01/22ADEL.02-550Install FPL Lighting @ City Gate Blvd. North20006/02/22A06/29/22ADEL.02-600Install FPL Lighting @ City Gate Blvd. South7006/30/22A07/11/22APre-ConstructionDesign and PermittingD&P-50Construction Documents: Architect & Engineer Design42001/01/20A06/18/20AD&P-100Addendum #1: Architect & Engineer Design23006/19/20A09/09/20AD&P-150Permit Drawings: Architect & Engineer Design64009/10/20A01/21/21AGMP Phase 2.1A & B-Phase 2.2GMP-2.1&2.2-50MCC GMP Pricing and Review 68009/10/20A12/08/20AGMP-2.1&2.2-100Board Agenda Submission & Approval37012/09/20A12/14/20AGMP-2.1&2.2-125Collier County Limited Notice to Proceed (LNTP)1012/15/20A01/25/21AGMP-2.1&2.2-150Collier County Processing NTP #2.11001/15/21A03/09/21AGMP-2.1&2.2-200MCC Re wright of NTP #02 SOV and Phases, L.O.I.s Sent out for Sub-Contractor Submittals25003/10/21A04/20/21AGMP-2.1&2.2-225MCC Aggregating Bid Tabs & Delivery to Collier County1004/21/21A06/30/21A20202021202220232024D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J FM A M J J A S O N D JProject StartProject FinishData DateNotice To Proceed - Phase 2.1NTP to Substantial Completion (HAMMOCK - Calendar Days) Release remainder of the Phase 2.1 work Substantial CompletionFinal CompletionOwner Issue Partial NTPOwner Issue Full GMP FundingRe-Bid & Review Owner Review & Approve Bid (BCC Approval)CC Issue DMP POMCC Receive Submittals From SubsIssue SCG Fields SubcontractsMCC Review & Submit SCG Fields SubmittalsAE Review & Approve SCG Fields SubmittalsPO, Fabrication & Delivery Of Early Materials (1st Delivery)PO, Fabrication & Delivery Of Early Materials (2nd Delivery)Delivery Turf Material (Fields 5 & 6)Delivery Turf Material (Fields 7 & 8)Subcontractor MobilizationReceive FPL Phasing Agreement ExhibitReceive Lighting Agreement ROS #5 & #6Receive Lighting Agreement ROS #7Receive Lighting Agreement ROS #8Receive FPL Lighting Drawings (ROS #8)Receive FPL Lighting Drawings (ROS #5, #6 & #7)Receive FPL Lighting Material (ROS #5, #6 & #7)Receive FPL Lighting Material (ROS #8)Install FPL Lighting @ City Gate Blvd. NorthInstall FPL Lighting @ City Gate Blvd. SouthConstruction Documents: Architect & Engineer DesignAddendum #1: Architect & Engineer DesignPermit Drawings: Architect & Engineer DesignMCC GMP Pricing and Review Board Agenda Submission & ApprovalCollier County Limited Notice to Proceed (LNTP)Collier County Processing NTP #2.1MCC Re wright of NTP #02 SOV and Phases, L.O.I.s Sent out for Sub-Contractor SubmittalsMCC Aggregating Bid Tabs & Delivery to Collier CountyStart Date: 12/31/19Finish Date: 12/30/22Data Date: 08/31/22Run Date: 09/07/227675-CC19.ppxCOLLIER COUNTY SPORTS COMPLEX - PHASE 2.1NAPLES, FLORIDAMCC Project #7675Page 1A16.C.7.bPacket Pg. 1032Attachment: 7675-CC19_Full Schedule (23459 : Sports Complex update)
IDDescriptionOrigDurRemDurStartFinishCOVID-19 Time Line2003/19/21A04/29/21ASubmittal / Review / Material ProcurementShop Drawings / Submittals / Procurment / DeliverySubmittal ApprovalMCCRD-50Fire Main Shop Drawings - MCC Receive1004/22/21A04/22/21AMCCRD-100Storm Pre-Cast Submittals - MCC Receive1004/22/21A04/22/21AMCCRD-150Sanitary Piping - MCC Receive1004/22/21A04/22/21AMCCRD-200Sanitary Pre-Cast - MCC Receive1004/22/21A04/22/21AMCCRD-250Water Main - MCC Receive1004/22/21A04/22/21AMCCR-50Fire Main - Shop Drawings - Manhattan Review3004/23/21A04/27/21AMCCR-100Storm Pre-Cast - MCC Review/Submit3004/23/21A04/27/21AMCCR-150Sanitary PVC Piping - MCC Review3004/23/21A04/27/21AMCCR-200Sanitary Pre-cast - MCC Review/Submit3004/23/21A04/27/21AMCCR-250Water Main - MCC Review/Submit3004/23/21A04/27/21APECR-50Fire Main - Shop Drawings - Design Review/Approve10004/28/21A05/06/21APECR-150Sanitary Piping - Design Review10004/28/21A05/06/21APECR-200Sanitary Pre-Cast - Design Review/Approve10004/28/21A05/06/21APECR-250Water Main - Design Review/Approve10004/28/21A05/06/21APECR-100Storm Pre-Cast - Design Review/Approve10004/28/21A05/11/21AMCCRD-850Storm Pre-Cast Resubmit - MCC Receive1005/12/21A05/12/21AMCCR-850Storm Pre-Cast - MCC Review/Resubmit3005/13/21A05/14/21APECR-850Storm Pre-Cast - Design Review/Re-approve10005/17/21A05/19/21AMCCRD-700Sports Lighting - MCC Receive1005/24/21A05/24/21AMCCR-700Sports Lighting - MCC Review/Submit3005/25/21A05/27/21APECR-700Sports Lighting - Design Review/Approve10005/28/21A06/17/21AMCCRD-550Scoreboards - MCC Receive1012/13/21A12/13/21AMCCR-550Scoreboards - MCC Review/Submit3012/14/21A12/14/21APECR-550Scoreboards - Design Review/Approve10012/15/21A01/11/22AMCCRD-450Shade Structures - MCC Receive1002/23/22A02/24/22AMCCR-450Shade Structures - MCC Review/Submit3002/24/22A03/24/22APECR-450Shade Structures - Design Review/Approve10002/25/22A03/30/22AMCCR-650Fencing - MCC Review/Submit3003/01/22A03/01/22AMCCRD-650Fencing - MCC Receive1003/01/22A03/01/22APECR-650Fencing - Design Review/Approve10003/02/22A05/24/22AMCCR-750Concrete Data - MCC Review/Submit3003/11/22A03/11/22AMCCRD-350Turf Samples and Shop Drawings - MCC Receive1003/14/22A03/14/22APECR-750Concrete Data - Design Review/Approve10003/14/22A03/30/22AMCCR-350Turf Samples and Shop Drawings - MCC Review & Submit3003/15/22A03/15/22APECR-350Turf Samples and Shop Drawings - Design Review/Approve10003/16/22A04/05/22AMCCR-600Irrigation Data - MCC Review/Submit3004/14/22A04/18/22APECR-600Irrigation Data - Design Review/Approve10004/19/22A04/20/22AMCCRD-400Field Drainage Storm Piping - MCC Receive1004/22/22A04/22/22AMCCR-400Field Drainage Storm Piping - MCC Review/Submit3004/25/22A04/27/22APECR-400Field Drainage Storm Piping - Design Review/Approve10004/28/22A05/06/22AMCCRD-300Field Drainage Shops - MCC Receive1004/29/22A04/29/22AMCCRD-750Concrete Data - MCC Receive1004/29/22A04/29/22AMCCR-300Field Drainage Shops - MCC Review & Submit3005/02/22A05/04/22APECR-300Field Drainage Shops - Design Review/Approve10005/05/22A05/17/22AMCCRD-600Irrigation Data - MCC Receive1005/09/22A05/09/22AMCCRD-800Sports Netting - MCC Receive1005/31/22A05/31/22AMCCR-800Sports Netting - MCC Review/Submit3006/01/22A06/03/22APECR-800Sports Netting - Design Review/Approve10006/06/22A06/17/22A20202021202220232024D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J FM A M J J A S O N D JProject StartProject FinishData DateFire Main Shop Drawings - MCC ReceiveStorm Pre-Cast Submittals - MCC ReceiveSanitary Piping - MCC ReceiveSanitary Pre-Cast - MCC ReceiveWater Main - MCC ReceiveFire Main - Shop Drawings - Manhattan ReviewStorm Pre-Cast - MCC Review/SubmitSanitary PVC Piping - MCC ReviewSanitary Pre-cast - MCC Review/SubmitWater Main - MCC Review/SubmitFire Main - Shop Drawings - Design Review/ApproveSanitary Piping - Design ReviewSanitary Pre-Cast - Design Review/ApproveWater Main - Design Review/ApproveStorm Pre-Cast - Design Review/ApproveStorm Pre-Cast Resubmit - MCC ReceiveStorm Pre-Cast - MCC Review/ResubmitStorm Pre-Cast - Design Review/Re-approveSports Lighting - MCC ReceiveSports Lighting - MCC Review/SubmitSports Lighting - Design Review/ApproveScoreboards - MCC ReceiveScoreboards - MCC Review/SubmitScoreboards - Design Review/ApproveShade Structures - MCC ReceiveShade Structures - MCC Review/SubmitShade Structures - Design Review/ApproveFencing - MCC Review/SubmitFencing - MCC ReceiveFencing - Design Review/ApproveConcrete Data - MCC Review/SubmitTurf Samples and Shop Drawings - MCC ReceiveConcrete Data - Design Review/ApproveTurf Samples and Shop Drawings - MCC Review & SubmitTurf Samples and Shop Drawings - Design Review/ApproveIrrigation Data - MCC Review/SubmitIrrigation Data - Design Review/ApproveField Drainage Storm Piping - MCC ReceiveField Drainage Storm Piping - MCC Review/SubmitField Drainage Storm Piping - Design Review/ApproveField Drainage Shops - MCC ReceiveConcrete Data - MCC ReceiveField Drainage Shops - MCC Review & SubmitField Drainage Shops - Design Review/ApproveIrrigation Data - MCC ReceiveSports Netting - MCC ReceiveSports Netting - MCC Review/SubmitSports Netting - Design Review/ApproveStart Date: 12/31/19Finish Date: 12/30/22Data Date: 08/31/22Run Date: 09/07/227675-CC19.ppxCOLLIER COUNTY SPORTS COMPLEX - PHASE 2.1NAPLES, FLORIDAMCC Project #7675Page 2A16.C.7.bPacket Pg. 1033Attachment: 7675-CC19_Full Schedule (23459 : Sports Complex update)
IDDescriptionOrigDurRemDurStartFinishProcurement and DeliveryJUFD-50Fire Main/Hydrants - Fabrication15005/06/21A05/27/21AJUFD-100Storm Pre-Cast - Fabrication42005/17/21A10/08/21AFRTNFD-50Sports Lighting - Fabrication60006/21/21A01/10/22AJUFD-200Sanitary Pre-Cast - Fabrication42009/27/21A11/30/21AJUFD-400Storm Piping - Fabrication6011/02/21A11/10/21AJUFD-150Sanitary Piping - Fabrication7011/23/21A11/30/21AJUFD-250Water Main - Fabrication8012/07/21A12/17/21ADAKFD-50Scoreboards - Fabrication50001/14/22A07/15/22AUSAFD-50Shade Structures - Fabrication60004/01/22A06/20/22ASPRTFD-100Turf Samples and Shop Drawings - Fabrication40004/06/22A07/15/22AIRRFD-50Irrigation - Delivery10004/21/22A04/29/22ASPRTFD-50Field Drainage - Fabrication7005/18/22A05/27/22ASMTHFD-50Fencing - Fabrication48105/25/22A08/31/22PROC-4110Sports Netting - Fabrication48006/20/22A08/25/22AConstructionPhase 2.1A - 951 Sign, Cove Rd Parking and Ramp, Asphalt WalkwayMobilization & Temporary ProtectionP2.1A-MOB-100Mobilization: Phase 2.1A5012/29/21A12/31/21ASite work P2.1A-SW-50Lake 1 Blasting (North Lake)21004/30/21A05/28/21AP2.1A-SW-100Lake 1 Excavation (North Lake)40005/10/21A06/29/21AP2.1A-SW-150Processing Spoils190005/14/21A04/29/22AP2.1A-SW-200Lake 2 Blasting (Middle Lake)6006/01/21A06/09/21AP2.1A-SW-250Lake 3 Blasting (SW)22006/10/21A06/18/21AP2.1A-SW-300Lake 4 Blasting (SE)6006/21/21A06/24/21AP2.1A-SW-350Lake 2 Excavation (North Lake)16006/30/21A07/16/21AP2.1A-SW-400Lake 3 Excavation (SW)25007/20/21A09/28/21AP2.1A-SW-450Lake 4 Excavation (SE)17009/29/21A10/07/21ACove Parking Lot ExpansionP2.1A-PLE-50Install Silt Fence1001/03/22A01/04/22AP2.1A-PLE-100Clear & Grub (2 Acres)5001/06/22A01/29/22AP2.1A-PLE-150Install Site Utilities, Irrigation Sleeves & Drainage15004/25/22A07/08/22AP2.1A-PLE-250Onsite Fill and Stabilize Sub grade10007/11/22A07/20/22AP2.1A-PLE-200Install Underground Electrical5007/21/22A07/27/22AP2.1A-PLE-350Install Irrigation3007/21/22A07/27/22AP2.1A-PLE-300Install Curbs, Factory Ramp, and Sidewalks5007/28/22A08/11/22AP2.1A-PLE-400Install Base & Pave 1st Lift15008/12/22A08/19/22AP2.1A-PLE-450Install FPL Light Poles and Pull Wires5508/31/2209/07/22P2.1A-PLE-500Install Landscaping5509/08/2209/14/22P2.1A-PLE-550Pave 2nd Lift1709/15/2209/23/22P2.1A-PLE-600Striping & Signage1109/26/2209/26/22Phase 1A Asphalt Path ExtensionP2.0-APE-75Install New Drainage8004/01/22A04/11/22AP2.0-APE-50Stabilize Sub grade3006/20/22A06/22/22AP2.0-APE-100Install Base & Pave5007/11/22A08/15/22AP2.0-APE-125Repair and Install Irrigation and Landscaping3308/31/2209/02/22P2.0-APE-150Stripe and Signage1109/27/2209/27/22Phase 2.1B - Lakes, Site work, Utilities, Drainage & Turf FieldsMobilization & Temporary ProtectionP2.1B-MOB-50Mobilization: Phase 2.1B5004/27/21A04/29/21A20202021202220232024D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J FM A M J J A S O N D JProject StartProject FinishData DateFire Main/Hydrants - FabricationStorm Pre-Cast - FabricationSports Lighting - FabricationSanitary Pre-Cast - FabricationStorm Piping - FabricationSanitary Piping - FabricationWater Main - FabricationScoreboards - FabricationShade Structures - FabricationTurf Samples and Shop Drawings - FabricationIrrigation - DeliveryField Drainage - FabricationFencing - FabricationSports Netting - FabricationMobilization: Phase 2.1ALake 1 Blasting (North Lake)Lake 1 Excavation (North Lake)Processing SpoilsLake 2 Blasting (Middle Lake)Lake 3 Blasting (SW)Lake 4 Blasting (SE)Lake 2 Excavation (North Lake)Lake 3 Excavation (SW)Lake 4 Excavation (SE)Install Silt FenceClear & Grub (2 Acres)Install Site Utilities, Irrigation Sleeves & DrainageOnsite Fill and Stabilize Sub gradeInstall Underground ElectricalInstall IrrigationInstall Curbs, Factory Ramp, and SidewalksInstall Base & Pave 1st LiftInstall FPL Light Poles and Pull WiresInstall LandscapingPave 2nd LiftStriping & SignageInstall New DrainageStabilize Sub gradeInstall Base & PaveRepair and Install Irrigation and LandscapingStripe and SignageMobilization: Phase 2.1BStart Date: 12/31/19Finish Date: 12/30/22Data Date: 08/31/22Run Date: 09/07/227675-CC19.ppxCOLLIER COUNTY SPORTS COMPLEX - PHASE 2.1NAPLES, FLORIDAMCC Project #7675Page 3A16.C.7.bPacket Pg. 1034Attachment: 7675-CC19_Full Schedule (23459 : Sports Complex update)
IDDescriptionOrigDurRemDurStartFinishResource Recovery Business Park InterconnectP2.1B-RRBPI-100Install Drainage, Water and Force Main - North6011/15/21A01/04/22AP2.1B-RRBPI-50Install Drainage, Water and Force Main - East -West5011/22/21A01/27/22AP2.1B-RRBPI-150Sub grade and Stabilize Sub grade - East -West10001/31/22A02/07/22AP2.1B-RRBPI-200Sub grade and Stabilize Sub grade - North10001/31/22A02/07/22AP2.1B-RRBPI-300Install Curbs - North3002/08/22A02/10/22AP2.1B-RRBPI-250Install Curbs - East - West and Island3002/09/22A02/10/22AP2.1B-RRBPI-350Install Base & Pave 1st lift - East - West10002/15/22A02/28/22AP2.1B-RRBPI-400Install Base & Pave 1st Lift - North10002/16/22A02/25/22AP2.1B-RRBPI-450Install Irrigation10007/26/22A08/08/22AP2.1B-RRBPI-550Pave 2nd Lift Asphalt1008/15/22A08/15/22AP2.1B-RRBPI-500Install Landscaping101008/31/2209/14/22P2.1B-RRBPI-600Striping & Signage3309/28/2209/30/22City Gate Boulevard North ExtensionCGBNE 00+00 - 18+00P2.1B CGBNE-1 10Demucking and Wetland Mitigation20011/01/21A11/19/21AP2.1B CGBNE-1 20Install Storm Drainage15002/10/22A03/29/22AP2.1B CGBNE-1 50Stabilize Sub grade30005/11/22A05/20/22AP2.1B CGBNE-1 30Install FPL Conduit20005/23/22A06/29/22AP2.1B CGBNE-1 60Install Curbs20006/06/22A06/17/22AP2.1B CGBNE-1 70Install Base & Pave 1st Lift20006/20/22A07/22/22AP2.1B CGBNE-1 80Irrigation and Landscaping55007/18/22A08/19/22AP2.1B CGBNE-1 90Pave 2nd Lift5008/22/22A08/26/22AP2.1B CGBNE-1 40Install FPL Light Poles and Pull Wires101009/26/2210/07/22P2.1B CGBNE-1 100Striping & Signage4410/03/2210/06/22CGBNE 18+00 - 36+61P2.1B CGBNE-2 10Demucking and Wetland Mitigation20011/22/21A12/17/21AP2.1B CGBNE-2 20Install Storm Drainage15002/21/22A05/05/22AP2.1B CGBNE-2 50Stabilize Sub grade20005/23/22A07/19/22AP2.1B CGBNE-2 60Install Curbs20007/20/22A08/16/22AP2.1B CGBNE-2 70Install Base & Pave 1st Lift201508/17/22A09/21/22P2.1B CGBNE-2 30Install FPL Backbone202208/17/22A09/30/22P2.1B CGBNE-2 90Pave 2nd Lift5509/22/2209/28/22P2.1B CGBNE-2 100Striping & Signage4410/07/2210/12/22P2.1B CGBNE-2 40Install FPL Light Poles and Pull Wire101010/10/2210/21/22City Gate Boulvard South ExtensionCGBSE 00+00 - 12+00P2.1B CGBSE-1 10Install Storm Drainage15004/11/22A06/06/22AP2.1B CGBSE-1 30Install FPL Underground Electrical Conduit15006/20/22A07/11/22AP2.1B CGBSE-1 50FPL Install Roadway Light poles and Pull Wire20007/12/22A08/08/22AP2.1B CGBSE-1 60Stabilize Sub grade20008/03/22A08/26/22AP2.1B CGBSE-1 20Install Curbs10808/29/22A09/12/22P2.1B CGBSE-1 40Install Base & Pave 1st Lift10808/29/22A09/20/22P2.1B CGBSE-1 80Pave 2nd Lift5509/21/2209/27/22P2.1B CGBSE-1 90Striping & Signage4410/13/2210/18/22CGBSE 12+00 - 24+47P2.1B CGBSE-2 50Install Storm Drainage15003/21/22A06/06/22AP2.1B CGBSE-2 300Stabilize Sub grade20007/20/22A07/28/22AP2.1B CGBSE-2 100Install Curbs10007/29/22A08/11/22AP2.1B CGBSE-2 150Install FPL Underground Electrical Conduit15008/01/22A08/19/22AP2.1B CGBSE-2 200Install Base & Pave 1st Lift102208/12/22A09/30/22P2.1B CGBSE-2 400Pave 2nd Lift5510/03/2210/07/22P2.1B CGBSE-2 250FPL Install Roadway Light poles and Pull Wire202010/10/2211/04/2220202021202220232024D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J FM A M J J A S O N D JProject StartProject FinishData DateInstall Drainage, Water and Force Main - NorthInstall Drainage, Water and Force Main - East -WestSub grade and Stabilize Sub grade - East -WestSub grade and Stabilize Sub grade - NorthInstall Curbs - NorthInstall Curbs - East - West and IslandInstall Base & Pave 1st lift - East - WestInstall Base & Pave 1st Lift - NorthInstall IrrigationPave 2nd Lift AsphaltInstall LandscapingStriping & SignageDemucking and Wetland MitigationInstall Storm DrainageStabilize Sub gradeInstall FPL ConduitInstall CurbsInstall Base & Pave 1st LiftIrrigation and LandscapingPave 2nd LiftInstall FPL Light Poles and Pull WiresStriping & SignageDemucking and Wetland MitigationInstall Storm DrainageStabilize Sub gradeInstall CurbsInstall Base & Pave 1st LiftInstall FPL BackbonePave 2nd LiftStriping & SignageInstall FPL Light Poles and Pull WireInstall Storm DrainageInstall FPL Underground Electrical ConduitFPL Install Roadway Light poles and Pull WireStabilize Sub gradeInstall CurbsInstall Base & Pave 1st LiftPave 2nd LiftStriping & SignageInstall Storm DrainageStabilize Sub gradeInstall CurbsInstall FPL Underground Electrical ConduitInstall Base & Pave 1st LiftPave 2nd LiftFPL Install Roadway Light poles and Pull WireStart Date: 12/31/19Finish Date: 12/30/22Data Date: 08/31/22Run Date: 09/07/227675-CC19.ppxCOLLIER COUNTY SPORTS COMPLEX - PHASE 2.1NAPLES, FLORIDAMCC Project #7675Page 4A16.C.7.bPacket Pg. 1035Attachment: 7675-CC19_Full Schedule (23459 : Sports Complex update)
IDDescriptionOrigDurRemDurStartFinishP2.1B CGBSE-2 450Striping & Signage4410/19/2210/24/22North and West Parking LotsP2.1B N&WPL-10Install Storm Drainage10012/15/21A02/03/22AP2.1B N&WPL-20Install FPL Underground Conduit10001/31/22A02/04/22AP2.1B N&WPL-30Stabilize Sub grade10007/11/22A07/22/22AP2.1B N&WPL-40Install F Curbs and Gutters5007/25/22A08/04/22AP2.1B N&WPL-50Install Base & Pave 1st Lift101208/05/22A09/16/22P2.1B N&WPL-60Install D Curbs3309/19/2209/21/22P2.1B N&WPL-80Install Irrigation, Sod and Landscaping151509/22/2210/12/22P2.1B N&WPL-90Pave 2nd Lift1110/13/2210/13/22P2.1B N&WPL-100Striping & Signage2210/25/2210/26/22P2.1B N&WPL-70Install FPL Light Poles and Pull Wires5510/31/2211/04/22Playing Field #5P2.1B PF5-10Install Underground Electrical - 5/610001/03/22A01/14/22AP2.1B PF5-30FRP Footings for Shade Structures Fields 5 15005/23/22A05/27/22AP2.1B PF5-20Install Musco Bases and Lighting Poles5005/23/22A06/08/22AP2.1B PF5-40Perimeter Concrete Curb5006/15/22A07/15/22AP2.1B PF5-60Install Stone Base10007/29/22A08/11/22AP2.1B PF5-70Install Field Drainage10008/05/22A08/25/22AP2.1B PF5-100Install PF5 Scoreboard3008/26/22A08/30/22AP2.1B PF5-80Install Leveling Stone101008/31/2209/14/22P2.1B PF5-90Install Turf & Infill101009/15/2209/28/22P2.1B PF5-50Install Shade Structures Fields 5 101009/29/2210/12/22P2.1B PF5-110Install Fencing & Backstops101009/29/2210/12/22Playing Field #6P2.1B PF5-200FRP Footings for Shade Structures Fields 615005/23/22A05/27/22AP2.1B PF6-10Install Musco Bases and Lighting Poles5005/23/22A06/08/22AP2.1B PF6-20Perimeter Concrete Curb5006/15/22A07/15/22AP2.1B PF6-30Install Stone Base10007/29/22A08/11/22AP2.1B PF6-40Install Field Drainage10008/12/22A08/25/22AP2.1B PF6-70Install PF6 Scoreboard3008/26/22A08/30/22AP2.1B PF6-50Install Leveling Stone101008/31/2209/14/22P2.1B PF6-60Install Turf & Infill101009/15/2209/28/22P2.1B PF5-150Install Shade Structures Fields 6101009/29/2210/12/22P2.1B PF6-80Install Fencing & Backstops101009/29/2210/12/22P2.1B PF6-90Irrigation and Landscaping Fields 5 & 65510/13/2210/19/22P2.1B PF6-100Install Signage Fields 5&64410/20/2210/25/22Fields 5 and 6 sidewalksP2.1B PF5&6SW-15Install FPL Backbone Conduit and Pull Boxes10001/31/22A05/02/22AP2.1B PF5&6SW-20FPL Install Walkway Light poles and Pull Wire - 5/610005/03/22A05/16/22AP2.1B PF5&6SW-10Layout - 5/6 Sidewalks3007/05/22A07/06/22AP2.1B PF5&6SW-30Stabilize SidewalksSubgrade - 5/622007/07/22A07/15/22AP2.1B PF5&6SW-40Form & Reinforce & Pour Sidewalks & Aprons - 5/6201107/18/22A09/15/22P2.1B PF5&6SW-50Install Sod and Landscaping51109/16/2209/30/22Playing Field #7P2.1B PF7-10Install Underground Electrical - 7/810001/17/22A01/21/22AP2.1B PF5-250FRP Footings for Shade Structures Fields 715005/23/22A05/27/22AP2.1B PF7-20Install MUSCO Bases and Lighting Poles5005/23/22A06/08/22AP2.1B PF7-30Perimeter Concrete Curb5007/18/22A07/22/22AP2.1B PF7-80Install PF7 Scoreboard3008/26/22A08/30/22AP2.1B PF7-40Install Stone Base101008/31/2209/14/22P2.1B PF7-50Install Field Drainage101009/07/2209/20/22P2.1B PF7-60Install Leveling Stone101009/21/2210/04/2220202021202220232024D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J FM A M J J A S O N D JProject StartProject FinishData DateStriping & SignageInstall Storm DrainageInstall FPL Underground ConduitStabilize Sub gradeInstall F Curbs and GuttersInstall Base & Pave 1st LiftInstall D CurbsInstall Irrigation, Sod and LandscapingPave 2nd LiftStriping & SignageInstall FPL Light Poles and Pull WiresInstall Underground Electrical - 5/6FRP Footings for Shade Structures Fields 5 Install Musco Bases and Lighting PolesPerimeter Concrete CurbInstall Stone BaseInstall Field DrainageInstall PF5 ScoreboardInstall Leveling StoneInstall Turf & InfillInstall Shade Structures Fields 5 Install Fencing & BackstopsFRP Footings for Shade Structures Fields 6Install Musco Bases and Lighting PolesPerimeter Concrete CurbInstall Stone BaseInstall Field DrainageInstall PF6 ScoreboardInstall Leveling StoneInstall Turf & InfillInstall Shade Structures Fields 6Install Fencing & BackstopsIrrigation and Landscaping Fields 5 & 6Install Signage Fields 5&6Install FPL Backbone Conduit and Pull BoxesFPL Install Walkway Light poles and Pull Wire - 5/6Layout - 5/6 SidewalksStabilize SidewalksSubgrade - 5/6Form & Reinforce & Pour Sidewalks & Aprons - 5/6Install Sod and LandscapingInstall Underground Electrical - 7/8FRP Footings for Shade Structures Fields 7Install MUSCO Bases and Lighting PolesPerimeter Concrete CurbInstall PF7 ScoreboardInstall Stone BaseInstall Field DrainageInstall Leveling StoneStart Date: 12/31/19Finish Date: 12/30/22Data Date: 08/31/22Run Date: 09/07/227675-CC19.ppxCOLLIER COUNTY SPORTS COMPLEX - PHASE 2.1NAPLES, FLORIDAMCC Project #7675Page 5A16.C.7.bPacket Pg. 1036Attachment: 7675-CC19_Full Schedule (23459 : Sports Complex update)
IDDescriptionOrigDurRemDurStartFinishP2.1B PF7-90Install Fencing & Backstops101009/21/2210/04/22P2.1B PF5-300Install Shade Structures Fields 7101009/29/2210/12/22P2.1B PF7-70Install Turf & Infill101010/05/2210/18/22Playing Field #8P2.1B PF5-350FRP Footings for Shade Structures Fields 815005/23/22A05/27/22AP2.1B PF8-10Install Musco Lighting Bases and Poles5005/23/22A06/08/22AP2.1B PF8-20Perimeter Concrete Curb5007/18/22A07/22/22AP2.1B PF8-70Install PF8 Scoreboard3008/26/22A08/30/22AP2.1B PF8-30Install Stone Base101008/31/2209/14/22P2.1B PF8-40Install Field Drainage101009/07/2209/20/22P2.1B PF8-50Install Leveling Stone101009/21/2210/04/22P2.1B PF5-400Install Shade Structures Fields 8101009/29/2210/12/22P2.1B PF8-60Install Turf & Infill101010/05/2210/18/22P2.1B PF8-80Install Fencing & Backstops101010/19/2211/01/22P2.1B PF8-90Irrigation and Landscaping - Fields 7&85511/02/2211/08/22P2.1B PF8-100Install Signage Fields 7&84411/09/2211/14/22Fields 7 and 8 SidewalksP2.1B PF7,8,9SW-10Layout - 7/8 Sidewalks3007/05/22A07/06/22AP2.1B PF7,8,9SW-70Stabilize Sub grade - 7/822007/07/22A07/15/22AP2.1B PF7,8,9SW-80Form & Reinforce & Pour Sidewalks & Aprons - 7/8203007/18/22A10/12/22P2.1B PF7,8,9SW-40FPL Install Walkway Light poles and Pull Wires - 7/8101010/13/2210/26/22P2.1B PF7,8,9SW-45Irrigation3310/27/2210/31/22P2.1B PF7,8,9SW-100Install Sod and Landscaping5511/01/2211/07/22Playing Field #9P2.1B PF9-10Install Underground Electrical - 910001/10/22A01/14/22AP2.1B PF9-20Install Musco Bases and Lighting Poles5005/23/22A06/08/22ACounty InsectionsP2.1-I-100Final Site Inspections3311/15/2211/17/22Close-OutPhase 2.1A - 951 Sign, Cove Rd Parking and Ramp, Asphalt WalkwayPH2.1A-CO-50MCC Punch list101009/27/2210/10/22PH2.1A-CO-100Project Closeout152112/01/2212/30/22Phase 2.1B - Lakes, Site work, Utilities, Drainage & Turf FieldsPH2.2-CO-50MCC Punch List and TCO Inspection Fields 5 thru 8 & City Gate Extensions101011/15/2211/30/22PH2.2-CO-100Project Close Out152112/01/2212/30/2220202021202220232024D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J FM A M J J A S O N D JProject StartProject FinishData DateInstall Fencing & BackstopsInstall Shade Structures Fields 7Install Turf & InfillFRP Footings for Shade Structures Fields 8Install Musco Lighting Bases and PolesPerimeter Concrete CurbInstall PF8 ScoreboardInstall Stone BaseInstall Field DrainageInstall Leveling StoneInstall Shade Structures Fields 8Install Turf & InfillInstall Fencing & BackstopsIrrigation and Landscaping - Fields 7&8Install Signage Fields 7&8Layout - 7/8 SidewalksStabilize Sub grade - 7/8Form & Reinforce & Pour Sidewalks & Aprons - 7/8FPL Install Walkway Light poles and Pull Wires - 7/8IrrigationInstall Sod and LandscapingInstall Underground Electrical - 9Install Musco Bases and Lighting PolesFinal Site InspectionsMCC Punch listProject CloseoutMCC Punch List and TCO Inspection Fields 5 thru 8 & City Gate ExtensionsProject Close OutStart Date: 12/31/19Finish Date: 12/30/22Data Date: 08/31/22Run Date: 09/07/227675-CC19.ppxCOLLIER COUNTY SPORTS COMPLEX - PHASE 2.1NAPLES, FLORIDAMCC Project #7675Page 6A16.C.7.bPacket Pg. 1037Attachment: 7675-CC19_Full Schedule (23459 : Sports Complex update)
16.C.7.c
Packet Pg. 1038 Attachment: Mexico Halts Vulcan Operation - Rock Products Magazine (23459 : Sports Complex update)
16.C.7.c
Packet Pg. 1039 Attachment: Mexico Halts Vulcan Operation - Rock Products Magazine (23459 : Sports Complex update)
16.C.7.c
Packet Pg. 1040 Attachment: Mexico Halts Vulcan Operation - Rock Products Magazine (23459 : Sports Complex update)
16.C.7.c
Packet Pg. 1041 Attachment: Mexico Halts Vulcan Operation - Rock Products Magazine (23459 : Sports Complex update)
16.C.7.d
Packet Pg. 1042 Attachment: Aerial North (23459 : Sports Complex update)
16.C.7.e
Packet Pg. 1043 Attachment: Aerial North 2 (23459 : Sports Complex update)