Agenda 07/12/2022 Item #11M (Collier Boulevard Bridge Location Study)
11.M 07/12/2022 EXECUTIVE SUMMARY Recommendation to approve the Collier Boulevard Bridge Location Study and authorize the County Manager or designee to incorporate the recommended alternative into the Collier Boulevard Widening Project (Project No. 68056). (Lorraine Lantz, Principal Planner, Capital Project Planning) OBJECTIVE: To obtain approval of the Collier Boulevard Bridge Location Study which evaluated a new replacement bridge location along Collier Boulevard, as required by the widening of Collier Boulevard between City Gate Boulevard N and Green Boulevard (Collier III) and incorporate the recommended location into the Collier III project. CONSIDERATIONS: The widening of Collier Boulevard between City Gate Boulevard N to Green Boulevard (Collier III) from four lanes to six lanes is in the design phase under the direction of the Collier County Transportation Engineering Division. The proposed improvements will help relieve congestion, improve safety, and accommodate future traffic demands within the area. The Collier III project is the last segment in a series of five projects to improve 15 miles of Collier Boulevard (CR 951), from US 41 to Immokalee Road, to a six -lane roadway. The Collier III Project impacts the existing bridge at 25th Avenue SW, requiring it to be removed. This bridge connects 39th Street SW to CR 951 over the CR 951 Canal. In 2021, Collier County initiated the Collier Boulevard Bridge Location Study (Study) to evaluate a new replacement bridge location to reconnect Collier Boulevard to 39th Street SW. The proposed locations included 291h Avenue SW, 27th Avenue SW, 25th Avenue SW, and Golden Gate Parkway, Alternatives 1 through 4, respectively. The Study also considered the implications of traffic signals at the various bridge locations and included multimodal accommodations such as a separate pedestrianibicyclist bridge that would provide access from 391h Street SW to Golden Gate Parkway. The CR 951 Canal requires relocation with the Collier Boulevard widening. Canal relocation will be required starting south of the proposed bridge location alternative selected and end midway between 23rd Avenue SW and 2 1 " Avenue SW where it will join the current alignment of the CR 951 Canal. Each alternative for this Study was evaluated for additional canal relocation required beyond the widening project. Preliminary concepts of Alternatives 1 through 4 were developed and evaluated against current design criteria for access management, mobility and safety, and opportunities for signalization, such as spacing requirements, operational impacts, turn lane requirements, and weaving distances. Results of the initial alternatives evaluation indicated that a proposed intersection at 25th Avenue SW and Collier Boulevard (Alternative 3) had multiple limitations and was eliminated as a viable alternative. The initial alternatives evaluation of Alternatives 1, 2, and 4 indicated that these alternatives met most design criteria requirements, as well as the project's purpose and need, and were carried forward as viable alternatives. The No -Build Alternative consisted of removing the existing bridge at 25th Avenue SW and assumed that no replacement bridge was provided. This would require traffic to travel to the 39th Street SW intersections at 171h Avenue SW and Green Packet Pg. 476 11.M 07/12/2022 Boulevard to access Collier Boulevard. The No -Build Alternative does not satisfy the project's purpose and need and, therefore, is not a viable alternative. The No -Build Alternative was carried forward through the Study only as a comparison for all other alternatives. The viable alternatives were presented at the Collier Blvd. Widening Project and Bridge Location Study Public Meeting held on April 6, 2022. A overwhelming comment received during the meeting and consistent in the written comments was that a traffic signal was needed at the chosen bridge location. At the time of the meeting, Alternative 4 was the only alternative to show a traffic signal and was preferred in the survey results. As a result of traffic data analysis, comments received from project stakeholders and the public, Alternative 2 was further refined and evaluated as both a "Non -Signalized" and "Signalized" intersection. These two options are identified as Alternative 2A and Alternative 2B respectively. A preliminary signal warrant analysis was performed for Alternative 2 which indicated the proposed intersection would meet the criteria for a traffic signal. Based on existing and future traffic demand, traffic operational needs, access management requirements, multimodal needs (pedestrian and bicyclist) physical and environmental constraints, and public comment, Alternative 2B: 27th Ave SW (Signalized) is identified as the Recommended Alternative. To improve multimodal accommodations, a pedestrianibicycle signal phase would be included with the signal's timing to connect pedestrians and bicyclists to the dedicated bike lane and shared -use pathway on Collier Boulevard. It is also recommended to include a pedestrian bridge at the intersection of Collier Boulevard and Golden Gate Parkway over the CR 951 Canal, to enhance multimodal access east of 39th Street SW. Public comments indicated a pedestrian bridge at this location would encourage residents living on the east side of Collier Boulevard to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway and Collier Boulevard. Additional recommendations include expanding the planned improvements on 39th Street SW from the existing 9-to-10-foot wide (varies) travel lanes to 11-feet-wide with 2-foot-wide shoulders. A 10-foot-wide shared -use pathway is proposed along the west side of 39th Street SW as part of the Collier III Project. If approved, the recommendations of the Study are intended to be included in the Design, Permitting and Construction phases of the Collier III Project. FISCAL IMPACT: The preliminary planning level estimated costs of the recommended bridge location is $2,811,000. The County's 5-Year Work Program and Capital Improvement Element include the funding for the right-of-way, design and construction of the Collier III Project. GROWTH MANAGEMENT IMPACT: The project is consistent with the Growth Management Plan and the MPO's Long Range Transportation Plan. LEGAL CONSIDERATIONS: This item has been reviewed by the County Attorney, raises no legal issues and requires majority vote for approval. -JAK RECOMMENDATION: That the Board of County Commissioners accept the Collier Boulevard Bridge Location Study and direct the County Manager or designee to: Packet Pg. 477 11.M 07/12/2022 1. Incorporate the recommended bridge location at 27th Ave. SW into the Collier III project; 2. Pursue other recommended improvements to 39th St. SW for enhanced mobility throughout the project corridor; 3. Continue with public engagement with impacted stakeholders through all future phases of Collier III. Prepared by: Lorraine Lantz, AICP, Principal Planner, Capital Project Planning, Impact Fees, and Program Management ATTACHMENT(S) 1. [Linked] Collier Blvd Bridge Location Study (PDF) 2. [Linked] Collier Blvd Bridge Study - Attachments A -I (PDF) Packet Pg. 478 11.M 07/12/2022 COLLIER COUNTY Board of County Commissioners Item Number: I LM Doe ID: 22664 Item Summary: *** This Item continued from the June 28, 2022, BCC Meeting. *** Recommendation to approve the Collier Boulevard Bridge Location Study and authorize the County Manager or designee to incorporate the recommended alternative into the Collier Boulevard Widening Project (Project No. 68056). (Lorraine Lantz, Principal Planner, Capital Project Planning) Meeting Date: 07/12/2022 Prepared by: Title: Sr. Operations Analyst — County Manager's Office Name: Geoffrey Willig 06/29/2022 1:45 PM Submitted by: Title: Division Director - Capital Proj Plan, Impact Fees — Capital Project Planning, Impact Fees, and Program Management Name: Beth Johnssen 06/29/2022 1:45 PM Approved By: Review: Growth Management Department Lisa Taylor Additional Reviewer Transportation Engineering Marlene Messam Additional Reviewer Growth Management Department Jeanne Marcella Growth Management Department Growth Management Department Anthony Khawaja Additional Reviewer Growth Management Operations Support Tara Castillo Transportation Engineering Jay Ahmad Additional Reviewer Capital Project Planning, Impact Fees, and Program Management Jeanne Marcella Growth Management Department James C French Growth Management Growth Management Department Trinity Scott Transportation Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Office of Management and Budget Susan Usher Additional Reviewer County Manager's Office Geoffrey Willig Level 4 County Manager Review Board of County Commissioners Geoffrey Willig Meeting Pending Completed 06/29/2022 2:11 PM Completed 06/29/2022 2:14 PM Completed 06/29/2022 3:24 PM Completed 06/29/2022 3:43 PM Additional Reviewer Completed Completed 06/30/2022 8:19 AM Additional Reviewer Skipped Skipped 06/29/2022 2:40 PM Completed 06/30/2022 11:20 AM Completed 06/30/2022 12:04 PM Completed 06/30/2022 1:36 PM Completed 07/01/2022 12:24 PM Completed 07/05/2022 1:54 PM 07/12/2022 9:00 AM Packet Pg. 479 � fiiM. l MIMI _ O + + �� ,yam •��r�., _3 Kier Bouteva d Br0 0 id a Location Study Memorandum } May 2022 ' 7FFp_, . . . . . . . . . . . . Collier Boulevard Bridge Location Study Memorandum Contents Acronymsand Abbreviations......................................................................................................................................... iv 1. Project Introduction.......................................................................................................................................1-5 1.1 Project Overview.............................................................................................................................................1-5 1.2 Purpose and Need.........................................................................................................................................1-6 1.3 Alternatives Development..........................................................................................................................1-8 2. Existing Conditions........................................................................................................................................2-1 2.1 Roadway Typical Section.............................................................................................................................2-1 2.2 Existing Bridge Typical Section at 25th Avenue SW........................................................................2-1 2.3 Traffic Characteristics...................................................................................................................................2-2 2.4 Roadway/Functional Classification.........................................................................................................2-3 2.5 Existing Land Use...........................................................................................................................................2-3 2.6 Existing Area Transit.....................................................................................................................................2-4 2.7 Existing Drainage...........................................................................................................................................2-4 2.8 Existing Utilities..............................................................................................................................................2-4 2.9 Existing Traffic.................................................................................................................................................2-5 2.10 Existing Intersection Configurations.......................................................................................................2-6 2.10.1 29th Avenue SW Intersection Configuration (Alternative 1).......................................2-6 2.10.2 27th Avenue SW Intersection Existing Configuration (Alternative 2)......................2-6 2.10.3 25th Avenue SW Intersection Existing Configuration (Alternative 3)......................2-7 2.10.4 Golden Gate Parkway Intersection Existing Configuration (Alternative 4).............2-8 2.11 Existing Structures.........................................................................................................................................2-9 3. Future Conditions...........................................................................................................................................3-1 3.1 Collier Boulevard Roadway Improvements..........................................................................................3-1 3.2 Future Land Use..............................................................................................................................................3-1 4. Design Controls and Criteria........................................................................................................................4-1 5. Alternatives Analysis.....................................................................................................................................5-1 5.1 Initial Alternatives Analysis........................................................................................................................5-1 5.2 Viable Alternatives Analysis.......................................................................................................................5-1 5.2.1 Alternative 1: 29th Avenue SW................................................................................................5-2 5.2.2 Alternative 2: 27th Avenue SW................................................................................................5-3 5.2.3 Alternative 4: Golden Gate Parkway......................................................................................5-6 5.2.4 Evaluation Matrix of Viable Alternatives..............................................................................5-8 6. Recommended Alternative and Improvements......................................................................................6-1 6.1 Recommended Bridge Location...............................................................................................................6-1 6.2 39th Street SW Improvements.................................................................................................................6-1 7. Public Involvement........................................................................................................................................7-1 7.1 Project Website...............................................................................................................................................7-1 7.2 Public Input Summary..................................................................................................................................7-1 7.2.1 Public Information Meeting Summary..................................................................................7-2 8. Summary..........................................................................................................................................................8-1 Collier Boulevard Bridge Location Study Memorandum 8.1 Conclusions and Recommendations......................................................................................................8-1 8.2 Next Steps.........................................................................................................................................................8-2 9. References............................................................................................................................................................3 Attachment Attachment A Preliminary Concepts for Viable Alternatives Attachment B Existing Conditions Maps Attachment C Sunshine One Call Tickets Attachment D Photograph Log Attachment E Traffic Counts Attachment F Future Land Use Attachment G Preliminary Signal Warrant Analysis Attachment H Preliminary Synchro Analysis Reports Attachment I Public Involvement Meeting Summary Tables Table 2-1. Existing Traffic Characteristics 2-3 Table 2-2. Existing Roadway Classifications...........................................................................................................2-3 Table 2-3. Utility Agency/Owner Summary ............................................................................................................2-5 Table4-1. Roadway Design Criteria..........................................................................................................................4-1 Table 5-1. Alternative 4 Delay Impacts (2045).....................................................................................................5-8 Table 5-2. Viable Alternatives Comparative Matrix..............................................................................................5-9 Table 7-1. Summary of Public Meeting Notification Techniques and Attendees..........................................7-3 Table 7-2. Summary of Public Meeting Notifications Table 7-3. Summary of Public Comments by Theme Figures 7-3 7-4 Figure1-1. Regional Location Map...........................................................................................................................1-5 Figure 1-2. Study Area for the Collier Boulevard Bridge Location Study........................................................1-6 Figure 1-3. Bicycle User on the Existing 25th Avenue SW Bridge.....................................................................1-7 Figure 1-4. Pedestrian Using the Existing 25th Avenue SW Bridge..................................................................1-7 Figure 1-5. Existing Access from 39th Street Southwest....................................................................................1-8 Figure 2-1. Existing Roadway Typical Section of Study Area (Looking North)..............................................2-1 Figure 2-2. Existing 25th Avenue SW Bridge (looking west)..............................................................................2-2 Figure 2-3. Existing 25th Avenue SW Bridge (looking north)............................................................................2-2 PPS0425221130SWF ii Collier Boulevard Bridge Location Study Memorandum Figure 2-4. Existing Intersection at 29th Avenue SW and 39th Street SW......................................................2-6 Figure 2-5. Existing Intersection at 27th Avenue SW and 39th Street SW......................................................2-7 Figure 2-6. Existing Intersections at 25th Avenue SW with 39th Street SW and Collier Boulevard .........2-8 Figure 2-7. Existing Intersection at Golden Gate Parkway and Collier Boulevard.........................................2-9 Figure 3-1. Proposed/Planned Typical Section for the Collier Boulevard Phase III Widening Project ..... 3-1 Figure 5-1. Alternative 1 Intersection Concept......................................................................................................5-2 Figure 5-2. Alternative 1 Access Management along Collier Boulevard.........................................................5-2 Figure 5-3. Alternative 2A Intersection Concept...................................................................................................5-4 Figure 5-4. Alternative 2A Access Management along Collier Boulevard......................................................5-4 Figure 5-5. Alternative 2B Intersection Concept...................................................................................................5-6 Figure 5-6. Alternative 2B Access Management along Collier Boulevard.......................................................5-6 Figure 5-7. Alternative 4 Intersection Concept......................................................................................................5-7 Figure 5-8. Alternative 4 Access Management along Collier Boulevard.........................................................5-7 Figure 7-1. Public Information Meeting...................................................................................................................7-1 Figure 7-2. Public Involvement Meeting Room Layout.......................................................................................7-2 Figure 7-3. Bridge Location Alternative Selection................................................................................................7-5 Figure 7-4. Bridge Location Alternative with Traffic Signal Adjustment.........................................................7-5 Figure 7-5. Pedestrian Bridge Preference...............................................................................................................7-6 PPSO425221130SWF Collier Boulevard Bridge Location Study Memorandum Acronyms and Abbreviations AM morning AUIR Annual Update and Inventory Report CAT Collier Area Transit FDOT Florida Department of Transportation GGAMP Golden Gate Area Master Plan LDC Land Development Code LOS Level of service LRTP Long Range Transportation Plan PM afternoon ROW right-of-way SFWMD South Florida Water Management District VMS Variable Message Sign vph vehicles) per hour PPS0425221130SWF iv Collier Boulevard Bridge Location Study Memorandum 1. Project Introduction 1.1 Project Overview The Collier County Capital Project Planning, Impact Fees & Program Management Division (hereinafter, "the County") initiated the Collier Boulevard Bridge Location Study (hereinafter, "the Study") to evaluate a new replacement bridge location along Collier Boulevard (CR 951), required as a result of widening Collier Boulevard between City Gate Boulevard N to Green Boulevard. The Study Area is located in western Collier County as shown in the Regional Location Map in Figure 1-1. The widening project impacts the existing bridge at 25th Avenue SW, requiring it to be removed. This bridge connects 39th Street SW to Collier Boulevard over the CR 951 Canal. The widening of this segment of Collier Boulevard from four lanes to six Lanes (hereinafter, "the Collier Boulevard Widening Phase III Project") is in the design phase under the direction of the Collier County Transportation Engineering Division. The proposed widening improvements will help relieve congestion, improve safety, and accommodate future traffic demands within the area. r az—_ N�NaPYCgW1Y --- DDllERWI.NIY —i �L CorksDre In—oaalee Corkscrew Swam city of _ Sa uary Bonita Ecosystem µitershed Blyd Springs -� �,r� Rooke m Swampm n Ave Ys Marla . �Caanv ors tree w 04- LRD Now IMMDNALEE RD RAND eLVD 5 NENDVYLDUNfv NepMe of CDIIIER CGMrr at a CORRIDOR STUDYAREJA — Florida Panther Golden oats National Wildlife Refuge 9J TDa AII.EY City of Naples t $ Picayune is Shand State Forest $ Fakahatcllee Strand J Stab Big cypress 116 11 Park National Preserve — ty of Ten at Marco Thousan lands t Island National so Wildlife Refuge Gulf of bferico Ev. IWN ty N W E Everglades lional Park DGn,Fp DGRnr 6 uuNaoL Wyly Not to Scale Figure 1-1. Regional Location Map The Study involved evaluating various locations for a new bridge to reconnect Collier Boulevard to 39th Street SW. Proposed locations included 29th Avenue SW, 27th Avenue SW, 25th Avenue SW, and Golden Gate Parkway. Figure 1-2 presents the Study Area, which is located east of 1-75. The Study also considered the implications of traffic signals at the various bridge locations; however, a full signal warrant analysis was not within the scope of this Study. To prioritize safety, comfort, and access to destinations along Collier Boulevard and Golden Gate Parkway (within Golden Gate City), the Study included multimodal accommodations such as a separate pedestrian/bicyclist bridge that would provide access from 39th Street SW to Golden Gate Parkway. PPSO425221130SWF 1-5 Collier Boulevard Bridge Location Study Memorandum URBAN GO E GATE ESTATES GREEN BLVD VE SWH Ft;l AVE SW 0 J HUN ER BLVD GOLDEN— i / , i 21STAVE SW = GATE CITY- 23RDAVE SW Q RURAL 0 m CORONAD PKWY GATEIP LU 25THAVE SIN GOLDEN 2 GATE W a a KIM ESTATES z 27TH AVE SW o O a O a y 29TH AVE SW m z ¢ 31STAVE SW O J H m Q Study Area OLDEN GATE MAIN CANAL W CITY GATE BLVD N — Canals yy J J Water Bodies O Major Streetsu Golf Course 0 0.25 0.5 Miles I Figure 1-2. Study Area for the Collier Boulevard Bridge Location Study 1.2 Purpose and Need The purpose of the bridge relocation project is to evaluate alternatives to address replacing the existing 25th Avenue SW bridge that will be removed as a result of widening Collier Boulevard between City Gate Boulevard N to Green Boulevard. The existing bridge does not provide multimodal accommodations, nor does it meet existing design criteria (refer to Figures 1-3 and 1-4). The project needs include: ■ Maintaining access to Collier Boulevard for residents and businesses in Rural Golden Gate Estates ■ Enhancing multimodal mobility and access for bicyclists and pedestrians by providing dedicated bicycle and pedestrian facilities ■ Improving safety by reducing conflicts between motorists, and bicyclists and pedestrians, and ensuring the new replacement bridge meets current design and safety criteria The Recommended Alternative is anticipated to be included with the design and construction of the Collier Boulevard Widening Phase III Project. PPSO425221130SWF 1-6 Collier Boulevard Bridge Location Study Memorandum Figure 1-3. Bicycle User on the Existing 25th Avenue SW Bridge Figure 1-4. Pedestrian Using the Existing 25th Avenue SW Bridge As identified in the Golden Gate Area Master Plan (GGAMP), Rural Golden Gate Estates includes the residential area east of Collier Boulevard and 39th Street SW, between 31st Avenue SW and 11th Avenue SW (refer to Figure 1-5). This area has limited access to Collier Boulevard because of the existing CR 951 Canal system east of Collier Boulevard. The area's access to Collier Boulevard is limited to the existing bridge connections along 39th Street SW crossing the CR 951 Canal at 25th Avenue SW, 17th Avenue SW, and Green Boulevard, as well as an at -grade connection from 39th Street SW to White Boulevard. The traffic signal at Green Boulevard provides full access from 39th Street SW to Collier Boulevard (left - turn, through, and right -turn movements). The other bridge locations as well as the at -grade connection at White Boulevard do not include traffic signals and are limited to right -turn -only movements to/from Collier Boulevard, requiring a U-turn to travel southbound on Collier Boulevard. There is also a southbound left turn movement from Collier Boulevard to the existing 25th Avenue SW bridge. PPSO425221130SWF 1-7 Collier Boulevard Bridge Location Study Memorandum ® PINE RIDGE RD WHITE BLVD J ¢ 11THAVE SW z a a RURAL URBAN GOLDEN 13THAVE SW a OLDS GATE ESTATES GATE STATE " 15TH AVE SW GREEN BLVD c - � 17TH AVE SW U) ~ 19 H AVE SW V x r OLDE M m ;' fir. AVTE 21STAVESW CITY w Q m J O `. 23RD AVE SW Q m � H DEN ATE KWY Z M.UJ 25THAVE SW to J Q Z LEGEND 27rH AVE SW Q v z LU Study Area ® Golden Gate City 29TH AVE SW 0 z ® Rural Golden Gate Estates o — Canals 31STAVE SW ° Water Bodies Major Streetsi� Golf Course GOLDEN GATE CITY GATE BLVD N Miles MALN C Figure 1-5. Existing Access from 39th Street Southwest 1.3 Alternatives Development Alternatives considered as part of this study include the No -Build Alternative and four alternatives. The initial alternatives include four bridge replacement locations that connect 39th Street SW to Collier Boulevard and identified as follows: ■ Alternative 1: 29th Avenue SW ■ Alternative 2: 27th Avenue SW ■ Alternative 3: 25th Avenue SW ■ Alternative 4: Golden Gate Parkway These initial alternatives were evaluated using current design criteria to determine their feasibility. Alternative 3, 25th Avenue SW, was deemed a non -viable alternative early in the study due to its proximity to Golden Gate Parkway and the restrictions associated with that location. The remaining three viable alternatives were further refined based on their ability to meet current design criteria for access management and safety. A qualitative and quantitative analyses was also performed with regards to mobility, opportunities for signalization, and impacts to traffic operations. The alternatives were presented PPSO425221130SWF 1-8 Collier Boulevard Bridge Location Study Memorandum at the Public Information Meeting on April 6, 2022, for public review and comment. The viable alternatives were further refined based on public input and a more detailed analysis of operational impacts, to identify the Recommended Alternative. Attachment A provides preliminary concepts for the viable alternatives. Note: The No -Build Alternative includes the removal of the 25th Avenue SW bridge associated with the widening of Collier Boulevard, with no replacement bridge provided. The No -Build Alternative serves as a baseline for comparison and remained an alternative throughout the Study. However, based on existing and future traffic needs, the No -Build Alternative is not a feasible solution. PPSO425221130SWF 1-9 Collier Boulevard Bridge Location Study Memorandum 2. Existing Conditions 2.1 Roadway Typical Section Figure 2-1 presents the existing roadway typical section within the Study Area, which includes a 200-foot- wide right-of-way (ROW) for Collier Boulevard and the CR 951 Canal, and a 60-foot-wide ROW for 39th Street SW. Within the Study Area, Collier Boulevard is a divided four -lane roadway with a posted speed Limit of 45 miles per hour (mph), and 39th Street SW is an undivided two-lane roadway with a posted speed limit of 30 mph. No bicycle or pedestrian facilities exist along Collier Boulevard or 39th Street SW within the Study Area. COLLIER BOULEVARD CR 951 CANAL 39TH STREET SW Figure 2-1. Existing Roadway Typical Section of Study Area (Looking North) 2.2 Existing Bridge Typical Section at 25th Avenue SW The existing bridge typical section at 25th Avenue SW includes two 12-foot-wide travel lanes. The westbound travel lane is a right -turn -only lane. The existing posted speed limit for 25th Avenue SW is 30 mph. The two -span prestressed concrete slab bridge is 42.8 feet long and approximately 28 feet wide. The existing bridge has bridge -mounted guard rail behind a raised curb along both edges. Figures 2-2 and 2-3 present pictures of the existing bridge. PPSO425221130SWF 2-1 Collier Boulevard Bridge Location Study Memorandum Figure 2-2. Existing 25th Avenue SW Bridge (looking west) Figure 2-3. Existing 25th Avenue SW Bridge (looking north) 2.3 Traffic Characteristics Collier County's 2021 Annual Update and Inventory Report (AUIR) on Public Facilities documents existing and projected deficiencies for major County roadways (Collier County 2021). Within the Study Area, the major roadways currently meet the County's minimum level of service (LOS), which is LOS D for this area (refer to Table 2-1). However, Golden Gate Parkway between Santa Barbara Boulevard and Collier Boulevard is expected to be deficient by 2028. PPS0425221130SWF 2-2 Collier Boulevard Bridge Location Study Memorandum Table 2-1. Existing Traffic Characteristics 2021 Peak Changein Year Hour Peak Directional Expected Directional Volume to be Peak 2021 Volume (from 2020 Deficient Road From To Direction LOS (vph) to 2021) Collier Green Golden Gate Pkwy North C 1420 >20% -- Boulevard Boulevard decrease Collier Golden Golden Gate Main North D 1800 < ±5% 2028 Boulevard Gate Canal change Parkway Golden Santa Collier Boulevard East D 1690 < ±5% 2028 Gate Barbara change Parkway Boulevard vph = vehicles per hour 2.4 Roadway/Functional Classification Table 2-2 lists the Study Area's functional classifications, which are based on Collier County's current Growth Management Plan Transportation Element 3 (amended June 13, 2017). Transportation Element 7 of the County Growth Management Plan also notes that Collier Boulevard and Golden Gate Parkway are County -designated hurricane evacuation routes. Table 2-2. Existing Roadway Classifications Road Classification Additional Characteristics Collier Boulevard Minor Arterial Hurricane Evacuation Route 39th Street SW Local 29th Avenue SW Local 27th Avenue SW Local 25th Avenue SW Local Golden Gate Parkway Minor Arterial Hurricane Evacuation Route Source: Collier County Growth Management Plan Transportation Element 3 and 7 (amended June 13, 2017) 2.5 Existing Land Use Existing land use within the Study Area was evaluated based on Collier County Property Appraiser parcel data and is primarily residential (Collier County 2021). Commercial businesses exist along the west side of Collier Boulevard north of Golden Gate Parkway. Behind the commercial properties are single-family residential land uses associated with Golden Gate City. South of Golden Gate Parkway, land use along the west side of Collier Boulevard is public, associated with a former golf course that is now County -owned property, along with single- and multi -family residential land uses north, south, and west. Land uses along 39th Street SW are primarily low -density residential associated with the Rural Golden Gate Estates area, but include pockets of commercial land uses including a restaurant south of 25th Avenue SW and a church just north of 29th Avenue SW. PPS0425221130SWF 2-3 Collier Boulevard Bridge Location Study Memorandum The Study Area is included in the GGAMP. Within the Study Limits, the west side of Collier Boulevard is included with the GGAMP's Golden Gate City sub -element and the east side is included with the Rural Golden Gate Estates sub -element (identified in Figure 1-2). The residential parcels associated with the Rural Golden Gate Estates within the Study Area are reaching full build -out. Based on aerial imagery from the Collier County Property Appraiser reviewed on December 10, 2021, approximately 90% of the parcels between 31 st Avenue SW and 11th Avenue SW west of the Golden Gate Main Canal are developed. Attachment B includes the Existing Land Use Map. 2.6 Existing Area Transit Three Collier Area Transit (CAT) bus routes serve Collier Boulevard within the Study Area. No CAT routes serve 39th Street SW and no bus stops are located within the Study area. The CAT bus routes that serve Collier Boulevard within the Study Area include: ■ Route 19 — Golden Gate Estates — Immokalee ■ Route 25 — Golden Gate Parkway — Goodlette-Frank ■ Route 28 — Golden Gate Estates — Everglades Blvd — Immokalee Refer to the Transit Map in Attachment B. 2.7 Existing Drainage The Study Area is located within the jurisdiction of South Florida Water Management District (SFWMD). According to the Collier County Stormwater Management Facilities map, the Study Area is within the 951 Canal Central Basin. There is an existing SFWMD weir at the CR 951 Canal just north of 31 st Avenue SW. Stormwater runoff from Collier Boulevard discharges to the CR 951 Canal via reinforced concrete pipe, and runoff from 39th Avenue SW is conveyed by parallel roadside ditches along the east side before ultimately discharging to the CR 951 Canal. 2.8 Existing Utilities The existing Utility Agency/Owners at each alternative location were identified from Sunshine One Call design tickets (total of four) performed February 7, 2022, and summarized in Table 2-3. The Sunshine One Call tickets are included in Attachment C. Major utilities within the Study Area include overhead electric lines that run along the west side of Collier Boulevard and the east side of 39th Street SW and cross over the CR 951 Canal at 29th Avenue SW, 27th Avenue SW, and 25th Avenue SW. According to the Sunshine One Call tickets, additional major utilities in the area include potable water and gas. There is no lighting along Collier Boulevard or 39th Street SW within the Study Area. An existing City of Naples main runs along the west side of 39th Street and includes an aerial crossing (east -west) over the CR 951 Canal at Golden Gate Parkway. According to the SFWMD's Right of Way Criteria Manual, an aerial crossing cannot be located within 100 feet of a bridge or pile -supported utility crossing (SFWMD 2013). The existing aerial crossing at Golden Gate Parkway falls under this criterion, however it is to be relocated as part of the Collier Boulevard Widening Phase III Project. PPS0425221130SWF 2-4 Collier Boulevard Bridge Location Study Memorandum A Golden Gate City Transmission Water Main project is proposed for construction in 2022 at Collier Boulevard and 29th Avenue SW (Golden Gate City Transmission Water Main Improvements n.d.). The proposed project includes a 24-inch water main crossing under the CR 951 Canal from west of Collier Boulevard to east of 39th Street SW, on the south side of 29th Street SW. Attachment D includes photos of the surroundings near each alternative location including visible utilities and/or utility markers. Table 2-3. Utility Agency/Owner Summary Alternative 1: Alternative 2: Alternative 3: Alternative 4: Utility 29th Avenue 27th Avenue 25th Avenue Golden Gate Utility Agency/Owner Type SW SW SW Parkway Collier County Traffic Electric, ✓ ✓ ✓ ✓ Operations Fiber Collier County Fiber Information ✓ ✓ ✓ ✓ Technology Collier County Board of Irrigation County Commissioners ✓ ✓ ✓ ✓ Road Maintenance CenturyLink Fiber, ✓ ✓ ✓ ✓ Telephone City of Naples — Water Water ✓ ✓ ✓ ✓ Collier County Stake Sewer, ✓ ✓ ✓ ✓ and Locates Water Comcast CATV ✓ ✓ ✓ ✓ Florida Power and Electric ✓ ✓ ✓ ✓ Light - Collier Crown Castle NG Fiber ✓ ✓ ✓ ✓ Summit Broadband Fiber, ✓ ✓ ✓ ✓ Telephone TECO Peoples Gas — Ft. Gas ✓ ✓ ✓ ✓ Myers 2.9 Existing Traffic Traffic data were collected at six locations to evaluate existing traffic patterns and are provided in Attachment E. Traffic data were collected via tube counts between December 14 through December 16, 2021, for morning (AM) and afternoon (PM) peak -hour turning movement counts and 3-day, 24-hour bi- directional traffic counts. The traffic count Locations were taken on 39th Street SW at the following Locations: 1) On 39th Street SW, south of White Boulevard 2) On 39th Street SW, north of Green Boulevard PPSO425221130SWF 2-5 Collier Boulevard Bridge Location Study Memorandum 3) On 39th Street SW, south of Green Boulevard 4) On 39th Street SW, south of 17th Avenue SW 5) On 39th Street SW, north of 25th Avenue SW 6) On 39th Street SW, south of 25th Avenue SW 2.10 Existing Intersection Configurations This section presents the existing layout of each initial alternative to identify potential engineering and environmental conditions and constraints. Refer to the Photograph Log in Attachment D for further details. 2.10.1 29th Avenue SW Intersection Configuration (Alternative 1) As presented on Figure 2-4, the intersection of 39th Street SW and 29th Avenue SW forms a three -leg minor intersection with one lane for each direction. A stop sign on 29th Avenue SW controls the intersection. The intersection is separated from Collier Boulevard by the CR 951 Canal. 44 • Z> i OWN z� W'+��; R '1 Figure 2-4. Existing Intersection at 29th Avenue SW and 39th Street SW 2.10.2 27th Avenue SW Intersection Existing Configuration (Alternative 2) As presented on Figure 2-5, the intersection of 39th Street SW and 27th Avenue SW forms a three -leg minor intersection with one lane for each direction. A stop sign on 27th Avenue SW controls the intersection. The intersection is separated from Collier Boulevard by the CR 951 Canal. PPS0425221130SWF 2-6 Collier Boulevard Bridge Location Study Memorandum x• z ta 1 Figure 2-5. Existing Intersection at 27th Avenue SW and 39th Street SW 2.10.3 25th Avenue SW Intersection Existing Configuration (Alternative 3) As presented on Figure 2-6, the intersection of 39th Street SW and 25th Avenue SW forms a four -leg intersection with one lane in each direction. Stop signs at 39th Street SW northbound and southbound control the intersection. Just west of this intersection is the intersection of Collier Boulevard and 25th Avenue SW, which forms a three -leg intersection with one lane in each direction on 25th Avenue SW and two lanes in each direction along Collier Boulevard. A directional median opening in the median of Collier Boulevard allows left -turn access from southbound Collier Boulevard to 25th Avenue SW. The existing bridge structure on 25th Avenue SW over the CR 951 Canal forms the eastern leg of the intersection. A stop sign on 25th Avenue SW controls the intersection. Westbound traffic on 25th Avenue SW is limited to a right -turn -only movements onto Collier Boulevard. On the west side of Collier Boulevard (opposite the intersection of 25th Avenue SW and Collier Boulevard), a local development driveway intersects with Collier Boulevard and allows only right -turn -in and right - turn -out movements. However, the development driveway access to and from Collier Boulevard is currently closed and will remain closed in the future. PPS0425221130SWF 2-7 Collier Boulevard Bridge Location Study Memorandum + t.• r 1.: s a. h w Collier Blvd 4 39th St SW Figure 2-6. Existing Intersections at 25th Avenue SW with 39th Street SW and Collier Boulevard 2.10.4 Golden Gate Parkway Intersection Existing Configuration (Alternative 4) As presented on Figure 2-7, the intersection of Collier Boulevard and Golden Gate Parkway forms a three - leg major intersection with all movements controlled by a traffic signal. Sidewalk exists along the north and south sides of Golden Gate Parkway, and there is a marked crosswalk on Golden Gate Parkway for the north -south movement. The west leg of the intersection includes two left -turn lanes and one right -turn Lane. The north leg of the intersection includes two through lanes and one right -turn lane, and the south Leg of the intersection includes two through lanes and one left -turn lane. PPSO425221130SWF 2-8 Collier Boulevard Bridge Location Study Memorandum --- in -'0 s y Figure 2-7. Existing Intersection at Golden Gate Parkway and Collier Boulevard 2.11 Existing Structures The existing bridge structure over the CR 951 Canal at 25th Avenue SW is owned by Collier County but maintained by the Florida Department of Transportation (FDOT) as Bridge No. 034012. According to the April 1, 2022, FDOT Florida Bridge Information Report, the bridge was constructed in 1965, and the last bridge inspection was performed March 8, 2022. The report notes the bridge has a Sufficiency Rating of 70 and a Health Index of 93.36. The bridge has an operating rating of 48.6 tons and is not posted for load restrictions. The report also notes an average daily traffic of 1,000 (FDOT 2022a). PPS0425221130SWF 2-9 Collier Boulevard Bridge Location Study Memorandum 3. Future Conditions 3.1 Collier Boulevard Roadway Improvements The Collier Boulevard Widening Phase III Project widens Collier Boulevard from four to six lanes using existing ROW within the median and County -owned property along the west side of Collier Boulevard. The project includes relocating portions of the CR 951 Canal. This project is the last segment in a series of five projects to improve 15 miles of Collier Boulevard, from US 41 to Immokalee Road, to a six -lane roadway. Within the Study Area, the Collier Boulevard Widening Phase III Project includes the Collier Boulevard proposed typical section with three 11-foot-wide travel lanes with a 4-foot-wide dedicated bike lane in each direction. Curb and gutter are proposed to the outside of the dedicated bike lanes and a 10-foot- wide shared -use pathway added on the west side of Collier Boulevard. Guardrail is proposed along the east side of Collier Boulevard as a barrier to the CR 951 Canal (due to proximity). Planned improvements on 39th Street SW include expanding the existing 9-to-10-foot wide (varies) travel Lanes to 11-feet-wide with 2-foot-wide shoulders. A 10-foot-wide shared -use pathway is proposed along the west side of 39th Street SW as part of the Collier Boulevard Widening Phase III Project. Figure 3-1 presents the proposed typical section within the Study Area. A future traffic signal is anticipated at the intersection of Collier Boulevard and City Gate Boulevard N to create a four -leg intersection (considers "future" Noah's Way) and was included in the alternative's evaluation for signal spacing. The CR 951 Canal requires relocation with the Collier Boulevard widening. Canal relocation will be required starting south of the proposed bridge location alternative selected and end midway between 23rd Avenue SW and 21 st Avenue SW where it willjoin the current alignment of the CR 951 Canal. Each alternative for this Study was evaluated for additional canal relocation required beyond the widening project. COLLIER BOULEVARD 39TH STREET SW RELOCATED enFOIAu CR 951 CANAL VATHWAV VARIES VATHWAV VARIES 18' VARIES 4' 11' 11' 11' 2f1'-28' 11' 1111' 4' VARIES 1C' 2' 11' 11' 2' • • • • • • VARIES VARIES PROPOSED RIGHT OF WAY EXISTING 200' RIGHTOF WAY EXISTING EASEMENT Figure 3-1. Proposed/Planned Typical Section for the Collier Boulevard Phase III Widening Project 3.2 Future Land Use Attachment F includes the Future Land Use Map. Land use is not anticipated to change as a result of the proposed project. The existing golf course facility located at the southwest quadrant of the intersection of PPSO425221130SWF 3-1 Collier Boulevard Bridge Location Study Memorandum Collier Boulevard and Golden Gate Parkway was recently purchased by the County to promote economic growth in Golden Gate City. According to the Golden Gate Golf Course Master Planned Unit Development Traffic Impact Statement (revised February 4, 2022), the proposed plans for the former golf course facility is to redevelop into residential workforce housing and a golf/entertainment facility (JMB Transportation Engineering 2022b). According to the golf/entertainment facility Traffic Impact Statement (revised January 19, 2022), the projected traffic volumes associated with the facility are not anticipated to warrant a traffic signal (JMB Transportation Engineering 2022a). The entrance to the golf/entertainment facility is planned to be aligned with 27th Avenue SW, with right -turn -in and right -turn -out access to/from Collier Boulevard. A northbound directional median opening is proposed on Collier Boulevard for left -turn access into the facility, and a downstream south bound -to -northbound U-turn lane/movement is also proposed within the median of Collier Boulevard. PPSO425221130SWF 3-2 Collier Boulevard Bridge Location Study Memorandum 4. Design Controls and Criteria The design criteria and standards are based on design parameters in accordance with the FDOT 2018 Florida Greenbook (FGB) (effective July 20, 2021), Collier County Land Development Code (LDC) (updated September 7, 2021), 2022 FDOT Design Manual (FDM), FDOT Access Management Guidebook (FDOT 2019), Collier County Growth Management Plan, and the Collier County Access Management Policy update, which reflects FDOT guidelines and Florida Administrative Code. Table 4-1 lists the design criteria for Collier Boulevard and 39th Street SW to analyze traffic operations and impacts with a future signal. Table 4-1. Roadway Design Criteria Design Element Collier Boulevard 39th Street SW Source Functional Classification Minor Arterial Urban Collector Collier County Growth Management Plan Transportation Element 3.4, FGB Access Class Proposed as 3 in the update N/A Collier County pending approval* Access Management Policy *Currently listed as Present Class 4 and Future Class 3 (arterial, divided) ar c 0 Design Speed 45 mph 30 mph min. FGB Table 3-1 Posted Speed 45 mph 30 mph Scope and field conditions Access Management N/A FDM Table Minimum Connection 660 feet 201.4.2 Access Spacing Class 3 and Minimum Median FDOT Access Opening Spacing Management Guidebook 2019 Directional 1320 feet Full 2,640 feet Signal Spacing 2,640 feet No. Lanes (Ultimate) 6 (3 per direction) 2 (1 per direction) Based on scope of Collier Boulevard 0 U Widening Project a) tA u Lane Width FGB Table 3-20 .Q F Travel Lane 11 feet min. 11 feet min. Turn Lane 11 feet min. N/A PPSO425221130SWF 4-1 Collier Boulevard Bridge Location Study Memorandum Table 4-1. Roadway Design Criteria Design Element Collier Boulevard 39th Street SW Source Bike Lane Width 4 feet min. 4 feet min. FGB Figure 9-1 Curbed Street without 5 feet min. N/A Collier County Parking Standard 4 feet Roadway with Flush 5 feet min. 5 feet min. Shoulder and Barrier Sidewalk Width 6 feet 6 feet (bridge) LDC 6.06.02, Pathway Width 10 feet 10 feet Collier Boulevard Widening Project Outside Full (Paved) 10 feet Full (5 feet min. Paved) 10 feet Full (5 feet min. FDM Table Paved) 210.4.1 Inside/Median 16 inches N/A FDM Figure Bridge 260.1.3 v Outside Bridge 6 feet 4 inches Culvert —same as roadway FDM Figure 0 N (Includes 5-foot-wide bike lane) 260.1.3 Median Width 22 feet N/A FGB Table 3-23 (19.5 feet min) Undivided Border Width 14 feet Urban General N/A FDM Table 210.7.1 (1) Clear Zone 20 feet 6 feet FGB Table 4- Curbed Facility 4 foot (AADT < 1500) 1(1 b), Table 4-2 ROW Width Varies source Collier Boulevard 60-foot Easement Widening Project PPSO425221130SWF 4-2 Collier Boulevard Bridge Location Study Memorandum Table 4-1. Roadway Design Criteria Design Element Collier Boulevard 39th Street SW Source Min. Stopping Sight Distance 360 feet 200 feet FGB Table 3-4, level roadway Merging Taper Termination 50:1 recommended but not N/A FGB Figure 3-19 Length less than 210 ft. Deceleration, and 180 ft. Acceleration Max. Deflection w/o Curve 1100, 2° 00' FDM 210.8.1 c 0 •� Length of Curve 675 feet 450 feet FDM Table = 210.8.1, FGB (400 feet min.) (400 feet min.) Table 3-8 Max. Curvature (Min. Radius) 8° 15' (694 feet) 20' 00' (286 feet) FDM Table 210.9.2 Max. Superelevation 0.05 0.05 FGB 3.C.4.c.2, Table 3-11 Max. Grade 6% 9% FGB Table 3-16 Max. Change in Grade w/o 0.70% 1.00% FGB Table 3-17 Vertical Curve Base Clearance above BCWE 3 feet from bottom of the 2 feet FDM 210.10.3. roadway base course for 2-lane Roadway (2) 76 Crest Curve K 61 19 FGB Table 3-18 a > Sag Curve K 79 37 FGB Table 3-18 Vertical Clearance Over 2.0 feet min. for debris N/A— bridge culvert FGB C.3.b Water clearance between design SFWMD = 4 Foot flood stage and bridge low member SFWMD Criteria Governs = 4 foot BCWE = Base Clearance Water Elevation PPS0425221130SWF 4-3 Collier Boulevard Bridge Location Study Memorandum 5. Alternatives Analysis 5.1 Initial Alternatives Analysis Preliminary concepts of Alternatives 1 through 4 were developed and evaluated against current design criteria for access management, mobility and safety, and opportunities for signalization, such as spacing requirements, operational impacts, turn lane requirements, and weaving distances. Results of the initial alternatives evaluation indicated that a proposed intersection at 25th Avenue SW and Collier Boulevard (Alternative 3) had multiple limitations including: Proposed directional median opening at this intersection (along Collier Boulevard) for access to 25th Avenue SW would not meet the minimum spacing requirement to the intersection at Golden Gate Parkway and Collier Boulevard ■ Proposed southbound Collier Boulevard left -turn lane for access to 25th Avenue SW would conflict with the proposed dual northbound Collier Boulevard left -turn lanes ■ Location would result in minimal weaving distance for the right -turn movements from 25th Avenue SW to the northbound Collier Boulevard left -turn lanes at Golden Gate Parkway Because of these limitations, Alternative 3 was eliminated as a viable alternative. The initial alternatives evaluation of Alternatives 1, 2, and 4 indicated that these alternatives met most design criteria requirements, as well as the project's purpose and need, and were carried forward as viable alternatives. The No -Build Alternative consists of removing the existing bridge at 25th Avenue SW and Collier Boulevard as a result of the Collier Boulevard widening. This alternative assumes that no replacement bridge is provided and that the traffic at the 25th Avenue SW would travel to the 39th Street SW intersections at 17th Avenue SW and Green Boulevard to access Collier Boulevard. The No -Build Alternative does not satisfy the project's purpose and need and, therefore, is not a viable alternative. However, the No -Build Alternative is carried forward through the Study as a comparison for all other alternatives. 5.2 Viable Alternatives Analysis Concepts of the viable alternatives (Alternatives 1, 2, and 4) were further refined to better evaluate access management needs, multimodal needs, impacts to traffic operations, impacts to utilities, and canal relocation requirements. Attachment A presents the concepts for each viable alternative. Future roadway needs near the Study area were identified in the Collier Metropolitan Planning Organization 2045 Long Range Transportation Plan (LRTP) (Collier MPO 2020). Because the 2045 LRTP only identifies study areas for the future regional network and specific corridors have not been developed, the viable alternatives could not be evaluated against long-term regional benefits and compatibility with the future network. The viable alternatives were only evaluated against benefits to the existing roadway network. Bicycle and pedestrian mobility and safety were evaluated for each viable alternative. Multimodal improvements were evaluated to coincide with the proposed improvements associated with the Collier Boulevard widening. Limitations to bicyclist and pedestrian mobility would exist for Alternatives 1 and 2, as no pedestrian facilities would be present for northbound Collier Boulevard and no crosswalk is proposed to access southbound Collier Boulevard. PPS0425221130SWF 5-1 Collier Boulevard Bridge Location Study Memorandum To accommodate these limitations, a pedestrian bridge over the CR 951 Canal was evaluated to connect residents to dining, shopping, and entertainment at Golden Gate City. The pedestrian bridge is proposed to connect the shared -use pathway along the west side of 39th Street SW to the Collier Boulevard/Golden Gate Parkway intersection (north side) and include a pedestrian phase with the existing traffic signal. The following subsections present the benefits and limitations of each viable alternative. 5.2.1 Alternative 1: 29th Avenue SW Figure 5-1 shows a portion of the concept for Alternative 1. Figure 5-2 shows access changes along Collier Boulevard as a result of Alternative 1 (with no traffic signal proposed). This alternative would provide right -turn -only access from 39th Street SW to Collier Boulevard and would provide left -turn and U-turn movements from southbound Collier Boulevard. The Golden Gate City Transmission Water Main Project that proposes a 24-inch-diameter water main crossing under the CR 951 Canal from Collier Boulevard to 39th Street SW would need to be avoided for this alternative. Figure 5-1. Alternative 1 Intersection Concept Figure 5-2. Alternative 1 Access Management along Collier Boulevard PPSO425221130SWF 5-2 Collier Boulevard Bridge Location Study Memorandum Alternative 1 Benefits ■ Includes a southbound U-turn for Collier Boulevard widening that also serves as southbound left -turn Lane to the 29th Avenue SW bridge ■ Provides northbound left turn at 27th Avenue SW to the future golf/entertainment facility that also serves as a northbound U-turn location to southbound Collier Boulevard ■ Meets minimum directional median opening ■ Provides additional queue length of approximately 40 feet for each lane at 29th Avenue SW (because of roadway offset) ■ Promotes distribution of traffic to other major east -west facilities (rather than attracting more trips to Golden Gate Parkway which is constrained) ■ Reduces impacts to signal operations at Golden Gate Parkway Alternative 1 Limitations ■ Provides farthest access alternative along 39th Street SW for residents between Golden Gate Main Canal and Green Boulevard (may attract less trips than Alternatives 2 and 4 resulting in more cars utilizing Green Boulevard intersection) ■ Requires separate pedestrian/bicycle bridge at Golden Gate Parkway — Does not provide pedestrian access from 39th Street SW to Collier Boulevard, as no facilities are planned on the east side of Collier Boulevard — Does not provide bicycle connectivity from 39th Street SW to the dedicated bike lane on southbound Collier Boulevard ■ Requires longest canal relocation (approximately 2,090 feet) ■ Must avoid Golden Gate City Transmission Water Main Project proposed under CR 951 Canal 5.2.2 Alternative 2: 27th Avenue SW A preliminary signal warrant analysis was performed for Alternative 2 at the 27th Avenue SW and Collier Boulevard intersection under Warrant 2 (Four -Hour Vehicular Volume) to evaluate if a traffic signal is needed for existing and future traffic volumes. The preliminary analysis indicated the proposed intersection would meet the criteria for a traffic signal under Warrant 2. Attachment G provides additional details on this preliminary analysis. During design, a full signal warrant analysis will be prepared. Note: As a result of traffic data analysis and comments received from project stakeholders, Alternative 2 was evaluated as both a "Non -Signalized" and "Signalized" intersection. These two options are identified as Alternative 2A and Alternative 2B respectively. 5.2.2.1 Alternative 2A: 27th Avenue SW - Not Signalized Figure 5-3 shows a portion of the concept for Alternative 2A. Figure 5-4 shows access changes along Collier Boulevard as a result of Alternative 2A. This alternative provides right -turn -only access from 39th Street SW to Collier Boulevard, and would provide left -turn and U-turn movements from southbound Collier Boulevard. This alternative also provides left -turn and U-turn movements from northbound Collier Boulevard to the future golf/entertainment facility. PPSO425221130SWF 5-3 Collier Boulevard Bridge Location Study Memorandum Figure 5-3. Alternative 2A Intersection Concept Figure 5-4. Alternative 2A Access Management along Collier Boulevard Alternative 2A Benefits ■ Provides additional queue length of approximately 40 feet for each lane at 27th Avenue SW (because of roadway offset) ■ Provides better access alternative along 39th Street SW for residents between Golden Gate Main Canal and Green Boulevard (may attract more trips than Alternative 1) ■ Promotes distribution of traffic to other major east -west facilities (rather than attracting more trips to Golden Gate Parkway which is constrained) ■ Reduces impacts to signal operations at Golden Gate Parkway ■ Meets minimum directional median opening spacing standard Alternative 2A Limitations: ■ Requires northbound U-turn lane just south of Golden Gate Parkway intersection to eliminate U-turns at the intersection (if not signalized) PPSO425221130SWF 5-4 Collier Boulevard Bridge Location Study Memorandum ■ Provides approximately 1,700 feet to the Golden Gate Parkway signal versus the signal spacing standard of 2,640 feet ■ Requires separate pedestrian/bicycle bridge at Golden Gate Parkway — Does not provide pedestrian access from 39th Street SW to Collier Boulevard, as no facilities are planned on the east side of Collier Boulevard — Does not provide bicycle connectivity from 39th Street SW to the dedicated bike lane on southbound Collier Boulevard. ■ Requires additional canal relocation (approximately 770 feet) 5.2.2.2 Alternative 2B: 27th Avenue SW - Signalized Figure 5-5 shows a portion of the concept for Alternative 2B. Figure 5-6 shows access changes along Collier Boulevard as a result of Alternative 2B. Alternative 2B Benefits ■ Provides additional queue length of approximately 40 feet for each lane at 27th Avenue SW (because of roadway offset to west within this area) ■ Enhances access to and from future golf/entertainment facility ■ Provides better access alternative along 39th Street SW for residents between Golden Gate Main Canal and Green Boulevard (may attract more trips than Alternative 1) ■ Promotes distribution of traffic to other major east -west facilities (rather than attracting more trips to Golden Gate Parkway which is constrained) ■ Reduces impacts to signal operations at Golden Gate Parkway ■ Meets minimum directional median opening spacing standard ■ Does not require additional southbound U-turn lane/movement on Collier Boulevard (aligned with 29th Avenue SW) Alternative 2B Limitations: ■ Provides approximately 1,700 feet to the Golden Gate Parkway signal versus the signal spacing standard of 2,640 feet ■ Requires separate pedestrian/bicycle bridge at Golden Gate Parkway Does not provide pedestrian access from 39th Street SW to Collier Boulevard, as no facilities are planned on the east side of Collier Boulevard ■ Requires additional canal relocation (approximately 770 feet) PPSO425221130SWF 5-5 Collier Boulevard Bridge Location Study Memorandum f !' ap .1 M Figure 5-5. Alternative 2B Intersection Concept Figure 5-6. Alternative 2B Access Management along Collier Boulevard Alternative 2B does not require a northbound U-turn just south of Golden Gate Parkway intersection. Additionally, it does not require the southbound U-turn on Collier Boulevard at 29th Avenue SW, whereas all other alternatives would require an additional U-turn movement. The proposed signal would provide a crosswalk for bicycle and pedestrian connectivity from 27th Avenue SW to the west side of Collier Boulevard. Based on the additional benefits and reduced limitations of Alternative 2B, the signalized intersection is the recommended concept for 27th Avenue SW— Please see Conclusions section for further details. 5.2.3 Alternative 4: Golden Gate Parkway Figure 5-7 shows a portion of the concept for Alternative 4. Figure 5-8 shows access changes along Collier Boulevard as a result of Alternative 4. This alternative provides full access from 39th Street SW to Collier Boulevard and would provide left -turn and U-turn movements from northbound and southbound Collier Boulevard. PPSO425221130SWF 5-6 Collier Boulevard Bridge Location Study Memorandum s Figure 5-7. Alternative 4 Intersection Concept but" Figure 5-8. Alternative 4 Access Management along Collier Boulevard A preliminary analysis was performed to evaluate impacts to the existing traffic signal operations, as the signal green time would be redistributed to include the additional approach leg. The increase in delay was estimated for both AM peak hour and PM peak hour conditions for future (2045) traffic volumes. The preliminary traffic analysis was performed using Trafficware's Synchro software, which analyzes intersection traffic data per the Highway Capacity Manua( 6th Edition procedures (TRB 2016). This analysis used existing 15-minute count data from Collier County. Turning movement volumes for the existing movements along Collier Boulevard and Golden Gate Parkway were developed from segment counts provided by the County. Turning movement volumes for the new movements using the proposed bridge were developed from turning movement counts collected at the existing 25th Avenue SW bridge. Because the proposed bridge would be included as part of the Collier Boulevard Widening Phase III Project, the traffic model included Collier Boulevard as a six -lane facility with double northbound left -turn Lanes to Golden Gate Parkway. The Alternative 4 scenario as a four -leg intersection was modeled and compared by adding the following movements at the intersection: eastbound through lane, southbound Left -turn lane, dual westbound left -turn lanes, dual westbound through lanes, and westbound right -turn Lane. PPSO425221130SWF 5-7 Collier Boulevard Bridge Location Study Memorandum The analysis indicates that the proposed intersection would experience approximately 16 seconds of additional overall delay in the AM peak hour condition, and approximately 15 seconds in the PM peak hour condition. Table 5-1 summarizes the estimated increases in delay for each scenario. Attachment H includes Synchro reports for this analysis. Table 5-1. Alternative 4 Delay Impacts (2045) Intersection Delay (seconds) AM Peak PM Peak Intersection Scenario No -Build three -leg Alternative intersection 25.3 22.2 with six -lane Collier Boulevard Alternative 4 four -leg intersection 41.5 36.9 with Bridge with six -lane Collier Boulevard Note: Southbound Collier Boulevard U-turns were not included in the No -Build Alternative model. Adding U-turn movements to the No -Build Alternative would increase delay. Alternative 4 Benefits ■ Does not add new signal to roadway network ■ Provides more operational movements (full access) for residents exiting 39th Street SW ■ Provides centrally located access along 39th Street SW for residents between Golden Gate Main Canal and Green Boulevard (may attract more trips than Alternatives 1 and 2) ■ Requires no additional canal relocation ■ No separate pedestrian/bicycle bridge needed Alternative 4 Limitations ■ Increased delays at intersection (because of extra leg added to intersection) ■ Limited available queue length (approximately 40 feet less per lane than Alternatives 1 and 2) ■ May attract more trips on Golden Gate Parkway (policy constrained to four lanes)* *Note that because of the land use surrounding Golden Gate Parkway from Santa Barbara Boulevard to Collier Boulevard, County policy constrains this facility to four lanes. Additionally, the County AUIR notes that this segment of Golden Gate Parkway is expected to be deficient by 2028 (Collier County 2021). Therefore, attracting additional traffic along this corridor is not recommended due to the Limited capacity of the facility. 5.2.4 Evaluation Matrix of Viable Alternatives Table 5-2 compares each of the viable alternatives. The viable alternatives (sans Alternative 26) were presented for public review and comment at the Public Information Meeting on April 6, 2022. The PPSO425221130SWF 5-8 Collier Boulevard Bridge Location Study Memorandum preliminary cost estimates are conceptual and were based on the estimated size of a bridge culvert (based on typical section/number of lanes), length of canal relocation, and signalization requirements. Table 5-2. Viable Alternatives Comparative Matrix Evaluation Criteria Alternative 1 Alternative 2A Alternative 2B Alternative 4 29th Avenue SW 27th Avenue SW 27th Avenue SW Golden Gate Non -Signalized Signalized Parkway Total Parcels Secondary Impacts (No.) 1 residential 0 0 0 visual impact Additional Canal Relocation Required (feet) 2,090 770 770 0 Potential Utility Impacts (No.) 3 2 2 2 No Aligns with residential Bridge Aligns with Cross Street Yes Yes Yes property Includes Pedestrian and Bicycle Facilities Yes Yes Yes Yes Provides Pedestrian and Bicycle Connectivity to southbound Collier Boulevard No No Yes Yes Separate Pedestrian/Bicycle Bridge Crossing Option at Golden Gate Parkway Needed Yes Yes Yes No Provides Pedestrian/Bicycle Access to Golden Gate City Network No No Yes Yes Estimated Preliminary Construction Cost (2022) $2,595,000 $2,232,000 $2,811,000 $2,940,000 Note: Alternatives resulted in no ROW impacts or potential displacements. PPS0425221130SWF 5-9 Collier Boulevard Bridge Location Study Memorandum 6. Recommended Alternative and Improvements 6.1 Recommended Bridge Location Alternative 2B: 27th Avenue SW (Signalized) Based on existing and future traffic demand, traffic operational needs, access management requirements, multimodal needs (pedestrian and bicyclist) physical and environmental constraints, and public comment, Alternative 26: 27th Ave SW (Signalized) is identified as the Recommended Alternative. As previously noted, a preliminary signal warrant analysis was performed for Alternative 2 which indicated the proposed intersection would meet the criteria for a traffic signal. The following provides details why Alternative 2B is identified as the Recommended Alternative and assumes this alternative will include a traffic signal. Purpose and Need: Alternative 213 satisfies the purpose and need of the project by maintaining and enhancing access, reducing conflict points for all roadway users, and enhancing multimodal mobility. Alternative 2B is more centrally located for residents and businesses in Rural Golden Gate Estates which may attract more trips and benefit more motorists than Alternative 1. Public Input: Both written and verbal public comments consisted primarily of a request for a traffic signal to allow left -turn movements from the proposed bridge to Collier Boulevard. Major concerns from the public included driver safety and mobility, with a request to enhance access to Collier Boulevard. A preliminary signal warrant analysis indicated a signal warrant would be satisfied. Access Management: Alternative 213 will maintain access to Collier Boulevard for the residents that live east of 39th Street SW. It provides an added benefit of enhancing access for the proposed golf/entertainment facility on the west side of Collier Boulevard. Note: The golf/entertainment facility entrance would be designed to align with Alternative 2B. Traffic Operations: This alternative promotes distribution of traffic to other major east -west facilities, rather than attracting more trips to Golden Gate Parkway, which is constrained to 4 lanes and is expected to be deficient by 2028 (Collier County 2021). The proposed signal will be coordinated with the existing signal at the Golden Gate Parkway/Collier Boulevard intersection to maintain traffic flow along Collier Boulevard. The geometry of Alternative 213 with the Collier Boulevard Widening Phase III Project provides additional storage length available for each lane on the proposed bridge thus enhancing operations. The additional storage allows more vehicles to queue allowing better traffic flow through the intersection during the signals' green time. To improve multimodal accommodations, a pedestrian/bicycle signal phase would be included with the signal's timing to connect pedestrians and bicyclists to the dedicated bike lane and shared -use pathway on Collier Boulevard. It is also recommended to include a pedestrian bridge at the intersection of Collier Boulevard and Golden Gate Parkway over the CR 951 Canal, to enhance multimodal access east of 39th Street SW. Public comments indicated a pedestrian bridge at this location would encourage residents living on the east side of Collier Boulevard to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway and Collier Boulevard. PPS0425221130SWF 6-1 Collier Boulevard Bridge Location Study Memorandum 6.2 39th Street SW Improvements During the Study, a recommendation was made for improvements to 39th Street SW consisting of wider travel lanes (11-foot-wide) and added shoulders (2-foot-wide). In addition, to further enhance multimodal mobility along 39th Street SW and Collier Boulevard, a recommendation was made for a pedestrian bridge at the southern end of 39th Street SW (by 31 st Ave SW). This facility would provide continuous access for pedestrians and bicyclists along the east side of Collier Boulevard. Required improvements would include: ■ Constructing a wider Golden Gate Main Canal bridge to accommodate pedestrians on the east side ■ Constructing a sidewalk along the east side of Collier Boulevard ■ Relocating portions of CR 951 Canal ■ Constructing Segments of retaining wall along east side of Collier Boulevard ■ Constructing a pedestrian bridge to cross over the CR 951 Canal. These recommendations will be evaluated for inclusion into the Collier Boulevard Widening Phase III Project. PPSO425221130SWF 6-1 Collier Boulevard Bridge Location Study Memorandum 7. Public Involvement Public involvement is an integral part of this Study to provide awareness of community values and concerns and to gain insight into existing constraints and issues that may affect the bridge location. 7.1 Project Website The County included information to the public about the Study under two different webpages: ■ The Planning Projects and Studies webpage, under "Current — Collier Blvd. III — Bridge Location Study", which directs the public to the Transportation Engineer Projects page for more information The Transportation Engineering Projects webpage under "Projects in Design — Collier Boulevard Widening Phase III", which provides information to the public about widening project and bridge Location study, and provides public involvement materials presented as well as the project comment/survey form. Project information was made available at the start of the Study and has been updated throughout its duration. A copy of the Transportation Engineering Projects webpage is included in Attachment I. 7.2 Public Input Summary A Public Information Meeting was held on April 6, 2022, to provide the public with an opportunity to review and comment on the project alternatives (refer to Figure 7-1 and 7-2). Representatives from the County and key project study team members were in attendance to answer questions and discuss the project with meeting attendees. Public comments were collected as hard copies at the meeting and the comment card was available online on the project website after the meeting. In total 71 comment forms were received through the comment period ending April 20, 2022. Comments and questions were also received via email throughout the entire study period by the County Project Managers Lorraine Lantz and Bee Thao. Four project comments or question were received via email. A log of comments received, and responses provided, is included in Attachment I. Additionally, an article on the project and public involvement meeting was included in the County Manager's Newsletter, published April 22, 2022 (refer to Attachment 1). Figure 7-1. Public Information Meeting PPSO425221130SWF 7-1 Collier Boulevard Bridge Location Study Memorandum Figure 7-2. Public Involvement Meeting Room Layout 7.2.1 Public Information Meeting Summary Collier County held a Public Information Meeting for the Collier Boulevard Widening Project 60 Percent Design Plans and Collier Boulevard Bridge Location Study on Wednesday, April 6, 2022, from 5:00 p.m. to 7:00 p.m. at the Golden Gate Community Center Auditorium located at 4701 Golden Gate Parkway, Naples, Florida 34116. The purpose of the meeting was to provide residents, business owners, and other interested persons the opportunity to review project information and comment on the project alternatives. Several options for making comments were available to members of the public, including making oral comments to the project team during the meeting, providing written comments on comment forms, and providing written comments delivered by mail or email. As an alternative to attending the meeting in person, public involvement materials and the comment form were available on the County Transportation Engineering Projects webpage the day of the meeting. The public comment period ended April 20, 2022. Several notification techniques were used for the meeting including a press release, emails, newsletters, and social media posts. A total of 90 people signed in at the public meeting, and 23 members of the project team (including County staff) were available to answer questions. Table 7-1 summarizes the public meeting notifications as well as the number of attendees. On March 22, 2022, a public information meeting notification email, including an attachment of the project newsletter, was emailed to elected/appointed officials, agencies, special -interest groups, and interested parties. The information in the newsletter was provided in English and Spanish, and included a contact for anyone who wished to discuss the project in Creole. Attachment I includes a copy of the notifications. The project newsletter was mailed on March 22, 2022, to property owners located within 500 feet of Collier Boulevard. A map of the property owner database boundary is included in Attachment I, along with the property owner mailing list. The property owner database was provided by the Collier County Property Appraiser. Attachment I includes a copy of the project newsletter. PPS0425221130SWF 7-2 Collier Boulevard Bridge Location Study Memorandum Table 7-1. Summary of Public Meeting Notification Techniques and Attendees Meeting Notification Format Number of Signed in Attendees (excluding Number of County and Number of Invitations Project Comment Project Meeting Invitation Notification Mailed/ Team Forms Team Staff Meeting Format Email Letter Other Emailed Members) Received Attendees Elected/ Open Appointed House with Officials, Project Agencies, Public Display and Social 254/345 Information Alternatives Interested Property Media Returned: Meeting on tables Parties Owners Posts 4a 90 71 23 a44 invitations were returned as undeliverable; however, 40 were identified as vacant or undeveloped with another invitation successfully delivered to the alternative address listed in Collier County Property Appraiser. Collier County also posted notifications on their social media sites, including Facebook, Nextdoor, and Twitter. A press release was distributed by the County on March 31, 2022. Additionally, three variable message signs (VMS) that provided meeting information were placed within the project limits 1 week prior to the public meeting. Two VMS were placed along Collier Boulevard south of Golden Gate Main Canal and south of Green Boulevard, while the other was placed on 25th Avenue SW at the intersection of 39th Street SW. Table 7-2 summarizes the notifications sent out prior to the meeting. A copy of the meeting notifications are included in Attachment I. Table 7-2. Summary of Public Meeting Notifications Meeting Notifications Dates Total Description/Outreach Facebook Post 1:3/30/2022, Post 2: 4/6/2022 2 31,307 people reached, 2,920 engagements, 214 reactions, 201 comments, 107shares Social Media Nextdoor 3/30/2022 1 265 impressions (message sent to 15 neighborhoods) Post 1: 3/30/2022, Twitter Post 2: 4/6/2022 2 999 impressions, 34 engagements, 15 link clicks Public 3/22/2022 8 Elected/Appointed Officials (24 Meeting Notifications 3/22/2022 19 Agencies (via email) 3/22/2022 237 Interested Parties Project Newsletter 3/22/2022 254 Property Owners (via mail) Press Release 3/31 /2022 1 Collier County Website PPS0425221130SWF 7-3 Collier Boulevard Bridge Location Study Memorandum Meeting attendees were given a project comment form and informational handout as they signed in at the welcome table. The project alternatives were displayed during the meeting. Key project team members were available to talk with the public, as needed. Attachment I includes a graphic of the room layout, signage used throughout the meeting space, project displays, a copy of the project informational handout distributed, the comment form, and completed sign -in sheets. As a result of the public meeting or meeting notifications 71 survey responses were received. A total of 52 comments were received at the public meeting, and 19 comments were received via email. Table 7-3 summarizes the public comments received by theme. Attachment I includes a copy of the comments received. Table 7-3. Summary of Public Comments by Theme Theme Number of Comments Natural Environmental Concerns 3 Aesthetic Concerns 4 Multimodal Safety 10 Vehicular Safety 21 Traffic 21 Survey results yielded the following data: ■ 97% live or work within 1 mile of the project ■ 93% use the Study Area daily, 3% weekly, and 4% responded as other Of the three bridge alternatives, 14% of residents prefer Alternative 1, 9% prefer Alternative 2, and 74% prefer Alternative 4 (refer to Figure 7-3) — A review of the written comments received from the public meeting indicated that less than half (44%) would have selected Alternative 4 if a signal was provided at Alternative 1 or 2 (refer to Figure 7-4) ■ Of the 44%, approximately 88% of this group did not indicate a preferred location, while 8% specifically indicated Alternative 1 and 4% specifically indicated Alternative 2 — A few excerpts from comments received include: ■ "The current situation is very dangerous without the assistance of a traffic light..." "Because we Live in a high fire dangerzone it's important that any bridge crossing have a traffic signal." "I would much rather wait at a Light knowing that I will eventually have a turn to go as opposed to waiting ad infinitum..." 60% of residents on the east side of 39th Street SW would be encouraged to use a pedestrian bridge at Golden Gate Parkway from 39th Street SW (refer to Figure 7-5) — 11 % reported they would use the pedestrian bridge daily, 38% weekly, and 47% other ■ 80% do not use CAT, but of the 20% who use or plan to use CAT: PPS0425221130SWF 7-4 Collier Boulevard Bridge Location Study Memorandum — 4% said they would prefer Bus Stop 276 to be relocated to 20th Place SW — 1 % prefer relocating across from 18th Avenue SW — 12% prefer the existing location at 17th Avenue SW If you live on the east side of 39th St SW, after reviewing the bridge location alternatives, which bridge location do you prefer? I do not live on the east side of 39th Street SW 29th Avenue SW 3% 14% 27th Avenue SW 9% � Golden Gate Parkway 74%* Figure 7-3. Bridge Location Alternative Selection *Note: A further analysis into the comments revealed that less than half (44%) would select Alternative 4 if a signal was provided at Alternative 1 or 2 (see Figure 7-4). *Preferred Bridge Location Alternative with Traffic Signal Adjustment 29th Avenue SW 14% 27th Avenue SW 9% Chose Golden Gate Parkway, but would choose Alternative 1 or 2 if they included a traffic signal 31% I do not live on the east side of 39th Street SW 2% Golden Gate Parkway 44% Figure 7-4. Bridge Location Alternative with Traffic Signal Adjustment PPSO425221130SWF 7-5 Collier Boulevard Bridge Location Study Memorandum If there was a pedestrian bridge at Golden Gate Pkwy from 39th St SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Pkwy or Collier Blvd? I do not live along the east side of Collier Boulevard and would not use the No, I wouldn't bridge use a pedestrian 2% bridge 38% Yes, I'd be encouraged to use the pedestrian bridge 60% Figure 7-5. Pedestrian Bridge Preference PPS0425221130SWF 7-6 Collier Boulevard Bridge Location Study Memorandum 8. Summary 8.1 Conclusions and Recommendations Alternative 2B: 27th Avenue SW — Signalized. is the Recommended Alternative. Alternative 2B was chosen based on an analysis of existing and future traffic demand, traffic operational needs, access management requirements, multimodal needs, physical and environmental constraints, public comments, and project cost. When comparing the alternatives, the results of the analysis indicated that Alternative 2B provides the most overall benefits when compared to the other alternatives. The following presents a summary of the primary reasons Alternative 2B was selected. Compared to Alternative 4: • Alternative 2B improves traffic operations and reduces delay at the Golden Gate Parkway intersection, while Alternative 4 will attract more trips to Golden Gate Parkway. (Note: Golden Gate Parkway is policy constrained to four lanes and is expected to be deficient by 2028.) • Alternative 2B provides an additional 40-foot vehicular storage/queue length for each lane, which will improve traffic operations and reduce delay at the intersection, while Alternative 4 has limited vehicular storage/queue length. • Alternative 2B bridge aligns directly with 27th Avenue SW and does not have secondary impacts to the adjacent properties, while Alternative 4 aligns directly with a residential property. • Alternative 2B is estimated to have a lower construction cost (4 percent) than Alternative 4. • Alternative 2B provides signalized access for residential and commercial traffic to 39th Street SW as well as the proposed golf/entertainment facility on the west side of Collier Boulevard, while Alternative 4 does not provide access to the proposed golf/entertainment facility. • Alternative 2B would not require a southbound U-turn aligned with 29th Avenue SW on Collier Boulevard, while Alternative 4 would require that U-turn lane for access management. Compared to Alternative 1: • Alternative 2B is more centrally located for residents and businesses in Rural Golden Gate Estates, so it will capture more trips as compared to Alternative 1, which would increase traffic distribution to the Green Boulevard intersection. • Alternative 2B has less canal relocation required (1,320 feet less), which reduces environmental impacts and cost as compared to Alternative 1. • Alternative 2B provides signalized access for residential and commercial traffic to 39th Street SW as well as the proposed golf/entertainment facility on the west side of Collier Boulevard, while Alternative 1 does not provide signalized access. • Alternative 2B would not require a southbound U-turn aligned with 29th Avenue SW on Collier Boulevard, while Alternative 1 would require that U-turn lane for access management. • Alternative 2B improves multimodal mobility by providing a crosswalk at the proposed signal to access the dedicated bike lanes along Collier Boulevard and shared -use pathways on the west side PPSO425221130SWF 8-1 Collier Boulevard Bridge Location Study Memorandum of Collier Boulevard and west side of 39th Street SW, while Alternative 1 does not provide signal access. Compared to Alternative 2A: • Alternative 2B provides signalized access for residential and commercial traffic to 39th Street SW as well as the proposed golf/entertainment facility on the west side of Collier Boulevard, while Alternative 2A does not provide signalized access. • Alternative 2B improves multimodal mobility by providing a crosswalk at the proposed signal to access the dedicated bike lanes along Collier Boulevard and shared -use pathways on the west side of Collier Boulevard and west side of 39th Street SW, while Alternative 2A does not provide signal access. • Alternative 2B would not require a northbound U-turn on Collier Boulevard just south of Golden Gate Parkway, while Alternative 2A would require that U-turn lane for access management. • Alternative 2B would not require a southbound U-turn aligned with 29th Avenue SW on Collier Boulevard, while Alternative 2A would require that U-turn lane for access management. Additional recommendations of this Study include: ■ A pedestrian bridge at the intersection of Collier Boulevard and Golden Gate Parkway (over the CR 951 Canal) ■ 39th Street SW improvements (evaluated for inclusion, see Section 6.2) o Wider travel lanes (11-foot-wide) and added shoulders (2-foot-wide) o Pedestrian bridge at the southern end of 39th Street SW (by 31 st Avenue SW) 8.2 Next Steps The recommendations of this Study are to be presented to the Board of County Commissioners for approval. If approved, the recommendations would be incorporated into the funding, design, permitting, and construction of the Collier Boulevard Widening Phase III Project. The design phase of the widening project is anticipated to be complete by late 2023 with construction anticipated to begin in early 2024, subject to funding availability. PPSO425221130SWF 8-2 Collier Boulevard Bridge Location Study Memorandum 9. References Collier County 2021.2021 Annual Update and Inventory Report on Public Facilities. October. https://www.colliercountyfL.gov/home/showpubLisheddocument/98467/637723267086830000 Collier County. n.d. Collier County Property Appraiser parcel data. Accessed December 10, 2021. https://www.collierappraiser.com Collier County. n.d. Collier County Stormwater Management Facilities. Accessed April 25, 2022. https://collieramdcm.maps.arcgis.com/apes/webappviewer/index.html?id=8784a4d66eac4f778ca62b9 d006e367f Collier County. n.d. Golden Gate Area Master Plan. Accessed April 25, 2022. https://www.colliercountyfL.gov/government/growth-management/divisions/planning-and-zoning- division/comprehensive-planning-section/growth-management-plan Collier County. n.d. Growth Management Plan. Accessed April 25, 2022. https://www.colliercountyfL.gov/government/growth-management/divisions/planning-and-zoning- division/comprehensive-planning-section/growth-management-plan Collier County. n.d. Land Development Code Section and Amendments. Accessed April 25, 2022. https://www.colliercountyfL.gov/government/growth-management/divisions/planning-and-zoning= division/land-development-code-and-amendments Collier Metropolitan Planning Organization. 2020.2045 Long Range Transportation Plan. December 11. Florida Department of Transportation (FDOT). 2018. Manual of Uniform Minimum Standards for Design, Construction and Maintenance for Streets and Highways. FDOT Office of Design. Topic # 625-000-015. Florida Department of Transportation (FDOT). 2019. Access Management Guidebook. November. Florida Department of Transportation (FDOT). 2022a. Bridge Information. April 1, 2022. https://www.fdot.gov/maintenance/bridgeinfo.shtm Florida Department of Transportation (FDOT). 2022b. FDOT Design Manual. Topic # 625-000-002. January. Golden Gate City Transmission Water Main Improvements. n.d. Accessed April 25, 2022. https://ggcwatertransmission.com JMB Transportation Engineering, Inc. 2022a. Traffic Impact Statement Big Shots Golf of Naples. Published November 16, 2021. Revised January 19. JMB Transportation Engineering, Inc. 2022b. Traffic Impact Statement Golden Gate Golf Course MPUD. Published July 18, 2021. February 4. South Florida Water Management District. 2013. Right of Way Criteria Manual for Use of Works or Lands of the District. August 12. Transportation Research Board. 2016. Highway Capacity Manual Sixth Edition: A Guide for Multimodal Mobility Analysis. July 13. �'IiL�►�.7►�►�i i Ieli���/ � Collier Boulevard Bridge Location Study Memorandum https://jacobsengineering.sharepoint.com/:u:/r/sites/iCWilsonBoulevardCorridorStudyCollierCounty/Shar ed Documents/CollierBlvdBridgeStudy/Utility Tickets/GG Transmission Proi/FW Golden Gate City Transmission WM -- SFWMD ROW -- CR-9S 1 0) 27th Avenue (Golf Course H D D).msg?csf=1 &web=1 &e=zLYk90 9 WITYMORi i FCIIJATTT/ 9 Attachment A Preliminary Concepts for Viable Alternatives 3 F Attachment B Existing Conditions Maps ■■�mm■n■■m mn�.■..■■ �� 1IIIIIIIIII II1 I� III II 1 � I���I. IIIIIIIII IIIIIIIII: I II I I II IIIIIIIII' I 1 11 IIIII: IIIIIIIIIIIIN IIIIIII IIIMOM II IIIIIIIIIII: IIIIIIII II i m r Em [W-A MEMv I'�. Attachment C Sunshine One Call Tickets 2/7/22, 9:58 AM Ticket Ticket : 038201067 Rev:000 Taken: 02/07/22 08:45ET State: FL Cnty: COLLIER GeoPlace: NAPLES CallerPlace: NAPLES Subdivision: Address : Street 39TH ST SW Cross 1 29TH AVE SW Within 1/4 mile: Y Locat: DESIGN REQUEST FOR BOTH SIDES OF COLLIER BLVD FROM WEST SIDE OF COLLIER BLVD TO INTERSECTION OF 29TH AVE SW AND 39TH ST SW Remarks : IN RESPONSE TO RECEIPT OF A DESIGN TICKET, SSOCOF PROVIDES THE ORIGINATOR OF THE DESIGN TICKET WITH A LIST OF SSOCOF MEMBERS IN THE VICINITY OF THE DESIGN PROJECT. SSOCOF DOES NOT NOTIFY SSOCOF MEMBERS OF THE RECEIPT BY SSOCOF OF A DESIGN TICKET. IT IS THE SOLE RESPONSIBILITY OF THE DESIGN ENGINEER TO CONTACT SSOCOF MEMBERS TO REQUEST INFORMATION ABOUT THE LOCATION OF SSOCOF MEMBERS' UNDERGROUND FACILITIES. SUBMISSION OF A DESIGN TICKET WILL NOT SATISFY THE REQUIREMENT OF CHAPTER 556, FLORIDA STATUTES, TO NOTIFY SSOCOF OF AN INTENT TO EXCAVATE OR DEMOLISH. THAT INTENT MUST BE MADE KNOWN SPECIFICALLY TO SSOCOF IN THE MANNER REQUIRED BY LAW. IN AN EFFORT TO SAVE TIME ON FUTURE CALLS, SAVE YOUR DESIGN TICKET NUMBER IF YOU INTEND TO BEGIN EXCAVATION WITHIN 90 DAYS OF YOUR DESIGN REQUEST. THE DESIGN TICKET CAN BE REFERENCED, AND THE INFORMATION ON IT CAN BE USED TO SAVE TIME WHEN YOU CALL IN THE EXCAVATION REQUEST. *** LOOKUP BY MANUAL *** Grids : 261OB8141C 261OB8141D Work date: 02/07/22 Time: 08:44ET Hrs notc: 000 Category: 6 Duration: UNKNOWN Due Date : 02/09/22 Time: 23:59ET Exp Date : 03/09/22 Time: 23:59ET Work type: DESIGN Boring: N White -lined: N Ug/Oh/Both: U Machinery: N Depth: UNK Permits: N N/A Done for : DESIGN Company JACOBS ENGINEERING Type: MEMB Co addr 9010 STRADA STELL CT STE 108 City NAPLES State: FL Zip: 34109 Caller SONAL DODIA Phone: 239-776-8139 Contact SONAL DODIA Email: SONAL.DODIA@JACOBS.COM BestTime: Email : SONAL.DODIA@JACOBS.COM Submitted: 02/07/22 08:45ET Oper: SON Chan: WEB Mbrs : CC1255 CC1650 CC2156 CNTL01 CPW592 FPLCLR L3C900 NN1882 OTC811 PGSSW https://exactix.sunshine8l l.com/tickets/view/2918a446-881 c-11 ec-bed 1-3ecaa6b21 dfe#tab2 1 /2 2/7/22, 9:58 AM Ticket * Responses are current as of 02/07/2022 09:58 AM Ex. Circum Service Area Utility Type(0 Contact No COLLIER COUNTY ELECTRIC, FIBER PAM WILSON TRAFFIC (239) 252-8260 OPERATIONS SECTION CC1255 No COLLIER COUNTY FIBER JOE OLIVER INFORMATION (239) 252-6205 TECHNOLOGY (IT) CC1650 No COLLIER COUNTY IRRIGATION PAMELA LULICH BCC ROAD (239) 252-8924 MAINTENANCE CC2156 Alternate Contact Emergency Qontact Positive Response HARIS DOMOND HARIS DOMOND (239)252-5000 (239)252-5000 HARIS DOMOND HARIS DOMOND (239)252-5000 (239)252-5000 DIANE LYNCH (239)252-8924 x5820 No CENTURYLINK FIBER, TELEPHONE BILL MCCLOUD RYAN EAGAN CABLE PROTECTION CNTL01 (850) 599-1444 (918) 547-0063 CENTER (877) 366-8344 x3 No COLLIER COUNTY SEWER, WATER ERIC FEY COLLIER COUNTY AFTER 5:00 PM / STAKE & LOCATES (239) 252-1037 STAKES & LOCATES ON -CALL LOCATOR CP\Afl (239) 252-5924 (239) 825-1444 No FLORIDA POWER & ELECTRIC JOEL BRAY USIC DISPATCH LIGHT --COLLIER (386) 586-6403 CENTER FPLCLR (800)778-9140 No CENTURYLINK FIBER NETWORK TECH ON DUTY TECH ON DUTY L3C900 RELATIONS (877) 366-8344 x3 (877) 366-8344 x3 (877) 366-8344 x2 No CROWN CASTLE NG FIBER FIBERDIG TEAM CROWN CASTLE NN1882 (888) 632-0931 x2 FIBER NOC (855) 933-4237 x1 No SUMMIT FIBER, TELEPHONE MICHELLE DANIEL SHAWN DONNELLY NETWORK BROADBAND (407) 996-1183 (727) 465-8229 OPERATION CENTER OTC811 (407)996-1188 No TECO PEOPLES GAS GAS JOAN DOMNING SHARON BECK TECO PEOPLES GAS - FT MYERS (813) 275-3783 (813) 853-9337 CUSTOMER PGSSW SERVICE" (877)832-6747 https:Hexactix.sunshine8l l .com/tickets/view/2918a446-881 c-11 ec-bedl-3ecaa6b2l dfe#tab2 2/2 2/7/22, 9:57 AM Ticket Ticket : 038201125 Rev:000 Taken: 02/07/22 08:49ET State: FL Cnty: COLLIER GeoPlace: NAPLES CallerPlace: NAPLES Subdivision: Address : Street 39TH ST SW Cross 1 27TH AVE SW Within 1/4 mile: Y Locat: DESIGN REQUEST FOR BOTH SIDES OF COLLIER BLVD FROM WEST SIDE OF COLLIER BLVD TO INTERSECTION OF 39TH ST SW AND 27TH AVE SW Remarks : IN RESPONSE TO RECEIPT OF A DESIGN TICKET, SSOCOF PROVIDES THE ORIGINATOR OF THE DESIGN TICKET WITH A LIST OF SSOCOF MEMBERS IN THE VICINITY OF THE DESIGN PROJECT. SSOCOF DOES NOT NOTIFY SSOCOF MEMBERS OF THE RECEIPT BY SSOCOF OF A DESIGN TICKET. IT IS THE SOLE RESPONSIBILITY OF THE DESIGN ENGINEER TO CONTACT SSOCOF MEMBERS TO REQUEST INFORMATION ABOUT THE LOCATION OF SSOCOF MEMBERS' UNDERGROUND FACILITIES. SUBMISSION OF A DESIGN TICKET WILL NOT SATISFY THE REQUIREMENT OF CHAPTER 556, FLORIDA STATUTES, TO NOTIFY SSOCOF OF AN INTENT TO EXCAVATE OR DEMOLISH. THAT INTENT MUST BE MADE KNOWN SPECIFICALLY TO SSOCOF IN THE MANNER REQUIRED BY LAW. IN AN EFFORT TO SAVE TIME ON FUTURE CALLS, SAVE YOUR DESIGN TICKET NUMBER IF YOU INTEND TO BEGIN EXCAVATION WITHIN 90 DAYS OF YOUR DESIGN REQUEST. THE DESIGN TICKET CAN BE REFERENCED, AND THE INFORMATION ON IT CAN BE USED TO SAVE TIME WHEN YOU CALL IN THE EXCAVATION REQUEST. *** LOOKUP BY MANUAL *** Grids : 261OA8141C 261OA8141D 261OB8141C 261OB8141D Work date: 02/07/22 Time: 08:47ET Hrs notc: 000 Category: 6 Duration: UNKNOWN Due Date : 02/09/22 Time: 23:59ET Exp Date : 03/09/22 Time: 23:59ET Work type: DESIGN Boring: N White -lined: N Ug/Oh/Both: U Machinery: N Depth: UNK Permits: N N/A Done for : DESIGN Company JACOBS ENGINEERING Type: MEMB Co addr 9010 STRADA STELL CT STE 108 City NAPLES State: FL Zip: 34109 Caller SONAL DODIA Phone: 239-776-8139 Contact SONAL DODIA Email: SONAL.DODIA@JACOBS.COM BestTime: Email : SONAL.DODIA@JACOBS.COM Submitted: 02/07/22 08:49ET Oper: SON Chan: WEB Mbrs CC1255 CC1650 CC2156 CNTL01 CON762 CPW592 CTV413 FPLCLR L3C900 NN1882 Mbrs OTC811 PGSSW https://exactix.sunshine8l l.com/tickets/view/c4a2a45c-881 c-11 ec-aa8a-3ecaa6b21 dfe#tab2 1 /2 2/7/22, 9:57 AM Ticket * Responses are current as of 02/07/2022 09:57 AM Ex. Circum Service Area Utility Types) Contact No COLLIER COUNTY ELECTRIC, FIBER PAM WILSON TRAFFIC (239) 252-8260 OPERATIONS SECTION CC1255 No COLLIER COUNTY FIBER JOE OLIVER INFORMATION (239) 252-6205 TECHNOLOGY (IT) CC1650 No COLLIER COUNTY IRRIGATION PAMELA LULICH BCC ROAD (239) 252-8924 MAINTENANCE CC2156 Alternate Contact Emergency Qontact Positive Response HARIS DOMOND HARIS DOMOND (239)252-5000 (239)252-5000 HARIS DOMOND HARIS DOMOND (239)252-5000 (239)252-5000 DIANE LYNCH (239)252-8924 x5820 No CENTURYLINK FIBER, TELEPHONE BILL MCCLOUD RYAN EAGAN CABLE PROTECTION CNTL01 (850) 599-1444 (918) 547-0063 CENTER (877) 366-8344 x3 No CITY OF NAPLES- WATER ALICIA ACEVEDO ALICIA ACEVEDO SHARDA WILLIAMS WATER (239) 213-4712 (239) 213-4712 (239) 213-4745 CON762 No COLLIER COUNTY SEWER, WATER ERIC FEY COLLIER COUNTY AFTER 5:00 PM / STAKE & LOCATES (239) 252-1037 STAKES & LOCATES ON -CALL LOCATOR CPW592 (239) 252-5924 (239) 825-1444 No COMCAST CATV JOSH DAVIS HFC HELP DESK CTV413 (239)253-7642 (855)962-8525 No FLORIDA POWER & ELECTRIC JOEL BRAY USIC DISPATCH LIGHT --COLLIER (386) 586-6403 CENTER FPLCLR (800)778-9140 No CENTURYLINK FIBER NETWORK TECH ON DUTY TECH ON DUTY L3C900 RELATIONS (877) 366-8344 x3 (877) 366-8344 x3 (877) 366-8344 x2 No CROWN CASTLE NG FIBER FIBERDIG TEAM CROWN CASTLE NN1882 (888) 632-0931 x2 FIBER NOC (855) 933-4237 x1 No SUMMIT FIBER, TELEPHONE MICHELLE DANIEL SHAWN DONNELLY NETWORK BROADBAND (407) 996-1183 (727) 465-8229 OPERATION CENTER OTC811 (407) 996-1188 No TECO PEOPLES GAS GAS JOAN DOMNING SHARON BECK TECO PEOPLES GAS - FT MYERS (813) 275-3783 (813) 853-9337 CUSTOMER PGSSW SERVICE" (877)832-6747 https:Hexactix.sunshine8l l .com/tickets/view/c4a2a45c-881 c-11 ec-aa8a-3ecaa6b2l dfe#tab2 2/2 2/7/22, 9:59 AM Ticket Ticket : 038201010 Rev:000 Taken: 02/07/22 08:41ET State: FL Cnty: COLLIER GeoPlace: GOLDEN GATE CallerPlace: GOLDEN GATE Subdivision: Address : Street COLLIER BLVD Cross 1 25TH AVE SW Within 1/4 mile: Y Locat: DESIGN REQUEST FOR BOTH SIDES OF COLLIER BLVD FROM INTERSECTION WITH 25TH AVE SW TO 39TH ST SW Remarks : IN RESPONSE TO RECEIPT OF A DESIGN TICKET, SSOCOF PROVIDES THE ORIGINATOR OF THE DESIGN TICKET WITH A LIST OF SSOCOF MEMBERS IN THE VICINITY OF THE DESIGN PROJECT. SSOCOF DOES NOT NOTIFY SSOCOF MEMBERS OF THE RECEIPT BY SSOCOF OF A DESIGN TICKET. IT IS THE SOLE RESPONSIBILITY OF THE DESIGN ENGINEER TO CONTACT SSOCOF MEMBERS TO REQUEST INFORMATION ABOUT THE LOCATION OF SSOCOF MEMBERS' UNDERGROUND FACILITIES. SUBMISSION OF A DESIGN TICKET WILL NOT SATISFY THE REQUIREMENT OF CHAPTER 556, FLORIDA STATUTES, TO NOTIFY SSOCOF OF AN INTENT TO EXCAVATE OR DEMOLISH. THAT INTENT MUST BE MADE KNOWN SPECIFICALLY TO SSOCOF IN THE MANNER REQUIRED BY LAW. IN AN EFFORT TO SAVE TIME ON FUTURE CALLS, SAVE YOUR DESIGN TICKET NUMBER IF YOU INTEND TO BEGIN EXCAVATION WITHIN 90 DAYS OF YOUR DESIGN REQUEST. THE DESIGN TICKET CAN BE REFERENCED, AND THE INFORMATION ON IT CAN BE USED TO SAVE TIME WHEN YOU CALL IN THE EXCAVATION REQUEST. *** LOOKUP BY MANUAL *** Grids : 261OA8141C 261OA8141D 2611D8141C 2611D8141D Work date: 02/07/22 Time: 08:40ET Hrs notc: 000 Category: 6 Duration: UNKNOWN Due Date : 02/09/22 Time: 23:59ET Exp Date : 03/09/22 Time: 23:59ET Work type: DESIGN Boring: N White -lined: N Ug/Oh/Both: U Machinery: N Depth: UNK Permits: N N/A Done for : DESIGN Company JACOBS ENGINEERING Type: MEMB Co addr 9010 STRADA STELL CT STE 108 City NAPLES State: FL Zip: 34109 Caller SONAL DODIA Phone: 239-776-8139 Contact SONAL DODIA Email: SONAL.DODIA@JACOBS.COM BestTime: Email : SONAL.DODIA@JACOBS.COM Submitted: 02/07/22 08:41ET Oper: SON Chan: WEB Mbrs CC1255 CC1650 CC2156 CNTL01 CON762 CPW592 CTV413 FPLCLR L3C900 NN1882 Mbrs OTC811 PGSSW https://exactix.sunshine8l l.com/tickets/view/a723367c-881 b-11 ec-b81 d-3ecaa6b21 dfe#tab2 1 /2 2/7/22, 9:59 AM Ticket * Responses are current as of 02/07/2022 09:59 AM Ex. Circum Service Area Utility Type(0 Contact No COLLIER COUNTY ELECTRIC, FIBER PAM WILSON TRAFFIC (239) 252-8260 OPERATIONS SECTION CC1255 No COLLIER COUNTY FIBER JOE OLIVER INFORMATION (239) 252-6205 TECHNOLOGY (IT) CC1650 No COLLIER COUNTY IRRIGATION PAMELA LULICH BCC ROAD (239) 252-8924 MAINTENANCE CC2156 Alternate Contact Emergency Qontact Positive Response HARIS DOMOND HARIS DOMOND (239)252-5000 (239)252-5000 HARIS DOMOND HARIS DOMOND (239)252-5000 (239)252-5000 DIANE LYNCH (239)252-8924 x5820 No CENTURYLINK FIBER, TELEPHONE BILL MCCLOUD RYAN EAGAN CABLE PROTECTION CNTL01 (850) 599-1444 (918) 547-0063 CENTER (877) 366-8344 x3 No CITY OF NAPLES- WATER ALICIA ACEVEDO ALICIA ACEVEDO SHARDA WILLIAMS WATER (239) 213-4712 (239) 213-4712 (239) 213-4745 CON762 No COLLIER COUNTY SEWER, WATER ERIC FEY COLLIER COUNTY AFTER 5:00 PM / STAKE & LOCATES (239) 252-1037 STAKES & LOCATES ON -CALL LOCATOR CPW592 (239) 252-5924 (239) 825-1444 No COMCAST CATV JOSH DAVIS HFC HELP DESK CTV413 (239)253-7642 (855)962-8525 No FLORIDA POWER & ELECTRIC JOEL BRAY USIC DISPATCH LIGHT --COLLIER (386) 586-6403 CENTER FPLCLR (800)778-9140 No CENTURYLINK FIBER NETWORK TECH ON DUTY TECH ON DUTY L3C900 RELATIONS (877) 366-8344 x3 (877) 366-8344 x3 (877) 366-8344 x2 No CROWN CASTLE NG FIBER FIBERDIG TEAM CROWN CASTLE NN1882 (888) 632-0931 x2 FIBER NOC (855) 933-4237 x1 No SUMMIT FIBER, TELEPHONE MICHELLE DANIEL SHAWN DONNELLY NETWORK BROADBAND (407) 996-1183 (727) 465-8229 OPERATION CENTER OTC811 (407) 996-1188 No TECO PEOPLES GAS GAS JOAN DOMNING SHARON BECK TECO PEOPLES GAS - FT MYERS (813) 275-3783 (813) 853-9337 CUSTOMER PGSSW SERVICE" (877)832-6747 https:Hexactix.sunshine8l l .com/tickets/view/a723367c-881 b-11 ec-b81 d-3ecaa6b2l dfe#tab2 2/2 2/7/22, 10:00 AM Ticket Ticket : 038200959 Rev:000 Taken: 02/07/22 08:37ET State: FL Cnty: COLLIER GeoPlace: NAPLES CallerPlace: NAPLES Subdivision: Address : Street COLLIER BLVD Cross 1 GOLDEN GATE PKWY Within 1/4 mile: Y Locat: DESIGN REQUEST FOR BOTH SIDES OF COLLIER BLVD FROM INTERSECTION WITH GOLDEN GATE PKWY TO 39TH ST SW. Remarks : IN RESPONSE TO RECEIPT OF A DESIGN TICKET, SSOCOF PROVIDES THE ORIGINATOR OF THE DESIGN TICKET WITH A LIST OF SSOCOF MEMBERS IN THE VICINITY OF THE DESIGN PROJECT. SSOCOF DOES NOT NOTIFY SSOCOF MEMBERS OF THE RECEIPT BY SSOCOF OF A DESIGN TICKET. IT IS THE SOLE RESPONSIBILITY OF THE DESIGN ENGINEER TO CONTACT SSOCOF MEMBERS TO REQUEST INFORMATION ABOUT THE LOCATION OF SSOCOF MEMBERS' UNDERGROUND FACILITIES. SUBMISSION OF A DESIGN TICKET WILL NOT SATISFY THE REQUIREMENT OF CHAPTER 556, FLORIDA STATUTES, TO NOTIFY SSOCOF OF AN INTENT TO EXCAVATE OR DEMOLISH. THAT INTENT MUST BE MADE KNOWN SPECIFICALLY TO SSOCOF IN THE MANNER REQUIRED BY LAW. IN AN EFFORT TO SAVE TIME ON FUTURE CALLS, SAVE YOUR DESIGN TICKET NUMBER IF YOU INTEND TO BEGIN EXCAVATION WITHIN 90 DAYS OF YOUR DESIGN REQUEST. THE DESIGN TICKET CAN BE REFERENCED, AND THE INFORMATION ON IT CAN BE USED TO SAVE TIME WHEN YOU CALL IN THE EXCAVATION REQUEST. *** LOOKUP BY MANUAL *** Grids : 2611D8141C 2611D8141D Work date: 02/07/22 Time: 08:24ET Hrs notc: 000 Category: 6 Duration: UNKNOWN Due Date : 02/09/22 Time: 23:59ET Exp Date : 03/09/22 Time: 23:59ET Work type: DESIGN Boring: N White -lined: N Ug/Oh/Both: U Machinery: N Depth: UNK Permits: N N/A Done for : DESIGN Company JACOBS ENGINEERING Type: MEMB Co addr 9010 STRADA STELL CT STE 108 City NAPLES State: FL Zip: 34109 Caller SONAL DODIA Phone: 239-776-8139 Contact SONAL DODIA Email: SONAL.DODIA@JACOBS.COM BestTime: Email : SONAL.DODIA@JACOBS.COM Submitted: 02/07/22 08:37ET Oper: SON Chan: WEB Mbrs CC1255 CC1650 CC2156 CNTL01 CON762 CPW592 CTV413 FPLCLR L3C900 NN1882 Mbrs OTC811 PGSSW https://exactix.sunshine8l l.com/tickets/view/l 14db960-881 b-11 ec-bf41-3ecaa6b21 dfe#tab2 1 /2 2/7/22, 10:00 AM Ticket * Responses are current as of 02/07/2022 10:00 AM Ex. Circum Service Area Utility Types) Contact No COLLIER COUNTY ELECTRIC, FIBER PAM WILSON TRAFFIC (239) 252-8260 OPERATIONS SECTION CC1255 No COLLIER COUNTY FIBER JOE OLIVER INFORMATION (239) 252-6205 TECHNOLOGY (IT) CC1650 No COLLIER COUNTY IRRIGATION PAMELA LULICH BCC ROAD (239) 252-8924 MAINTENANCE CC2156 Alternate Contact Emergency Contact Positive Response HARIS DOMOND HARIS DOMOND (239)252-5000 (239)252-5000 HARIS DOMOND HARIS DOMOND (239)252-5000 (239)252-5000 DIANE LYNCH (239)252-8924 x5820 No CENTURYLINK FIBER, TELEPHONE BILL MCCLOUD RYAN EAGAN CABLE PROTECTION CNTL01 (850) 599-1444 (918) 547-0063 CENTER (877) 366-8344 x3 No CITY OF NAPLES- WATER ALICIA ACEVEDO ALICIA ACEVEDO SHARDA WILLIAMS WATER (239) 213-4712 (239) 213-4712 (239) 213-4745 CON762 No COLLIER COUNTY SEWER, WATER ERIC FEY COLLIER COUNTY AFTER 5:00 PM / STAKE & LOCATES (239) 252-1037 STAKES & LOCATES ON -CALL LOCATOR CPW592 (239) 252-5924 (239) 825-1444 No COMCAST CATV JOSH DAVIS HFC HELP DESK CTV413 (239)253-7642 (855)962-8525 No FLORIDA POWER & ELECTRIC JOEL BRAY USIC DISPATCH LIGHT --COLLIER (386) 586-6403 CENTER FPLCLR (800)778-9140 No CENTURYLINK FIBER NETWORK TECH ON DUTY TECH ON DUTY L3C900 RELATIONS (877) 366-8344 x3 (877) 366-8344 x3 (877) 366-8344 x2 No CROWN CASTLE NG FIBER FIBERDIG TEAM CROWN CASTLE NN1882 (888) 632-0931 x2 FIBER NOC (855) 933-4237 x1 No SUMMIT FIBER, TELEPHONE MICHELLE DANIEL SHAWN DONNELLY NETWORK BROADBAND (407) 996-1183 (727) 465-8229 OPERATION CENTER OTC811 (407) 996-1188 No TECO PEOPLES GAS GAS JOAN DOMNING SHARON BECK TECO PEOPLES GAS - FT MYERS (813) 275-3783 (813) 853-9337 CUSTOMER PGSSW SERVICE" (877)832-6747 https:Hexactix.sunshine8l l .com/tickets/view/l l4db960-881 b-11 ec-bf41-3ecaa6b2l dfe#tab2 2/2 Attachment D Photograph Log .;acobs Project Title Collier Boulevard Bridge Location Study Location Wilson Boulevard, Naples, Florida Date November 23, 2021 Photograph Log Photo Log of Potential Bridge Locations Figure 1 presents a map identifying each potential bridge Location evaluated. This photograph log documents existing conditions as of November 23, 2021. ��� �,• _•` Y - C-R.951 CANAL - - Y ' / Q Bridge Location Altemative1. r f�''t�frr➢ (` �.. �syei Figure 1. Bridge Locations Evaluated Attachment D - Photograph Log D-1 Photo Log of Potential Bridge Locations (November 23, 2021) Alternative 1: 29th Avenue Southwest and 39th Street Southwest Intersection Photograph 1-1: 29th Ave. S.W. Intersection — Looking north at intersection (to the right) Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-3: 29th Ave. S.W. Intersection — Looking west Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-5: 29th Ave. S.W. Intersection — Looking east from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-2: 29th Ave. S.W. Intersection — Looking north Taken by.- Felicia Kirby Date taken: 11123121 see Photograph 1-4: 29th Ave. S.W. Intersection — Looking south Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-6: 29th Ave. S.W. Intersection — Looking west from 39th St. SW Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-2 Photo Log of Potential Bridge Locations (November 23, 2021) QT i Photograph 1-7: 29th Ave. S.W. Intersection — Looking north from intersection Taken by.- Felicia Kirby Date taken: 8/201/21 Photograph 1-9: 29th Ave. S.W. Intersection — Looking southeast from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-11: 29th Ave. S.W. Intersection — Looking north from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-8: 29th Ave. S.W. Intersection — Looking south from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-10: 29th Ave. S.W. Intersection — Looking east from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-12: 29th Ave. S.W. Intersection — Looking northeast from intersection Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-3 Photo Log of Potential Bridge Locations (November 23, 2021) Photograph 1-13: 29th Ave. S.W. Intersection - Looking southwest from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-15: 29th Ave. S.W. Intersection - Looking northwest from 29th Ave. SW Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-17: 29th Ave. S.W. Intersection - Looking south from 29th Ave. SW Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-14: 29th Ave. S.W. Intersection - Looking west at intersection, from 29th Ave. SW Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-16: 29th Ave. S.W. Intersection - Looking north from 29th Ave. SW Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-18: 29th Ave. S.W. Intersection - Looking north from 29th Ave. SW at church (Golden Gate Assembly of God) Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-4 Photo Log of Potential Bridge Locations (November 23, 2021) Photograph 1-19: 29th Ave. S.W. Intersection - Looking north from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-21: 29th Ave. S.W. Intersection - Looking south along 951 Canal Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-23: 29th Ave. S.W. Intersection - Looking southeast at intersection Taken by.- Felicia Kirby Date taken: 11123121 TIM Photograph 1-20: 29th Ave. S.W. Intersection - Looking west Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-22: 29th Ave. S.W. Intersection - Looking north along 951 Canal Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-24: 29th Ave. S.W. Intersection - Looking northeast Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-5 Photo Log of Potential Bridge Locations (November 23, 2021) Photograph 1-25: 29th Ave. S.W. Intersection — Inside church parking lot, looking south Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-27: 29th Ave. S.W. Intersection — Inside church parking lot, looking east from entrance Taken by.- Felicia Kirby Date taken: 11123121 k Photograph 1-29: 29th Ave. S.W. Intersection — Inside church parking lot, front of building Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-26: 29th Ave. S.W. Intersection — Inside church parking lot, looking southeast Taken by.- Felicia Kirby Date taken: 11123121 Photograph 1-28: 29th Ave. S.W. Intersection — Inside church parking lot, looking northeast from entrance Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-6 Photo Log of Potential Bridge Locations (November 23, 2021) Alternative 2: 27th Avenue Southwest and 39th Street Southwest Intersection id MOM ! its 7 ... Photograph 2-1: 27th Ave. S.W. Intersection — Looking northwest at utility marker Taken by.- Felicia Kirby Date taken: 11123121 Photograph 2-3: 27th Ave. S.W. Intersection — Looking south Taken by.- Felicia Kirby Date taken: 11123121 Photograph 2-5: 27th Ave. S.W. Intersection — Looking east from intersection Taken by.- Felicia Kirby Date taken: 11 /23/21 Photograph 2-2: 27th Ave. S.W. Intersection — Looking north at intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 2-4: 27th Ave. S.W. Intersection — Looking east from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 2-6: 27th Ave. S.W. Intersection — Looking west from intersection Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-7 Photo Log of Potential Bridge Locations (November 23, 2021) Photograph 2-7: 27th Ave. S.W. Intersection — Looking east from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 2-9: 27th Ave. S.W. Intersection — Looking south from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 2-11: 27th Ave. S.W. Intersection — Looking north from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 2-8: 27th Ave. S.W. Intersection — Looking southeast from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 2-10: 27th Ave. S.W. Intersection — Looking northeast from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 2-12: 27th Ave. S.W. Intersection — Looking northeast from intersection Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-8 Photo Log of Potential Bridge Locations (November 23, 2021) JO Photograph 2-13: 27th Ave. S.W. Intersection — Looking northwest from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 2-15: 27th Ave. S.W. Intersection — Looking west across the 951 Canal Taken by.- Felicia Kirby Date taken: 11123121 Photograph 2-17: 27th Ave. S.W. Intersection — Looking east at intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 2-14: 27th Ave. S.W. Intersection — Looking west from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 2-16: 27th Ave. S.W. Intersection — Looking south along the 951 Canal Taken by.- Felicia Kirby Date taken: 11123121 Photograph 2-18: 27th Ave. S.W. Intersection — Looking north along the 951 Canal Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-9 Photo Log of Potential Bridge Locations (November 23, 2021) Photograph 2-19: 27th Ave. S.W. Intersection - Looking northwest along the 951 Canal at Collier Blvd. Photograph 2-21: 27th Ave. S.W. Intersection - Looking south Taken by.- Felicia Kirby Date taken: 11123121 Photograph 2-20: 27th Ave. S.W. Intersection - Looking north Photograph 2-22: 27th Ave. S.W. Intersection - Looking east Taken by.- Felicia Kirby Date taken: 11123121 Photograph 2-23: 27th Ave. S.W. Intersection - Photograph 2-24: 27th Ave. S.W. Intersection - Looking north at intersection (to the right) Looking northeast at intersection Taken by.- Felicia Kirby Date taken: 11123121 Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-10 Photo Log of Potential Bridge Locations (November 23, 2021) Alternative 3: 25th Avenue Southwest and 39th Street Southwest Intersection Photograph 3-1: 25th Ave. S.W. Intersection — Looking south at existing 25th Ave. SW bridge Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-3: 25th Ave. S.W. Intersection — Looking south at bridge Taken by.- Felicia Kirby Date taken: 11/23/21 Photograph 3-5: 25th Ave. S.W. Intersection — Existing buried fiber optic cable marker Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-2: 25th Ave. S.W. Intersection — Looking west across the 951 Canal Taken by.- Felicia Kirby Date taken: 11123121 r1- 7 y Photograph 3-4: 25th Ave. S.W. Intersection — Looking south at intersection and bridge Taken by.- Felicia Kirby Date taken: 11/23/21 Photograph 3-6: 25th Ave. S.W. Intersection — Looking southwest at bridge Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-11 Photo Log of Potential Bridge Locations (November 23, 2021) Photograph 3-7: 25th Ave. S.W. Intersection — Photograph 3-8: 25th Ave. S.W. Intersection — Looking east, north of 25th Ave. SW Looking southeast at intersection Taken by.- Felicia Kirby Date taken: 11123121 Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-9: 25th Ave. S.W. Intersection — Photograph 3-10: 25th Ave. S.W. Intersection — Looking southwest from 39th St. SW Looking west from intersection Taken by.- Felicia Kirby Date taken: 11123121 Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-11: 25th Ave. S.W. Intersection — Photograph 3-12: 25th Ave. S.W. Intersection — Looking east from bridge Looking southeast from bridge Taken by.- Felicia Kirby Date taken: 11123121 Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-12 Photo Log of Potential Bridge Locations (November 23, 2021) r- Photograph 3-13: 25th Ave. S.W. Intersection - Photograph 3-14: 25th Ave. S.W. Intersection - Looking southwest from intersection Looking west from intersection Taken by.- Felicia Kirby Date taken: 11123121 Taken by.- Felicia Kirby Date taken: 11123121 -1 Photograph 3-15: 25th Ave. S.W. Intersection - Photograph 3-16: 25th Ave. S.W. Intersection - Looking northwest at bridge Looking west at utility along Golden Gate Pkwy. Taken by.- Felicia Date taken: 11123121 Taken by.- Felicia Kirby Date taken: 11123121 Kirby Photograph 3-17: 25th Ave. S.W. Intersection - Looking north at bridge Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-18: 25th Ave. S.W. Intersection - Looking northwest Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-13 Photo Log of Potential Bridge Locations (November 23, 2021) Photograph 3-19: 25th Ave. S.W. Intersection — Looking south along the 951 Canal Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-21: 25th Ave. S.W. Intersection — Looking north from 39th St. SW at the intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-20: 25th Ave. S.W. Intersection — Looking north from 39th St. SW; Existing bollards and utility pedestal Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-22: 25th Ave. S.W. Intersection — Looking south from 39th St. SW Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-23: 25th Ave. S.W. Intersection — Photograph 3-24: 25th Ave. S.W. Intersection — Looking northeast from 39th St. SW at the Looking east from 39th St. SW, south of 25th Ave. intersection SW Taken by.- Felicia Kirby Date taken: 11123121 Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-14 Photo Log of Potential Bridge Locations (November 23, 2021) Photograph 3-25: 25th Ave. S.W. Intersection — Looking southeast from 39th St. SW, south of 25th Ave. SW Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-27: 25th Ave. S.W. Intersection — Existing utilities at east leg of intersection Taken by.- Felicia Kirby Date taken: 11123121 .j Photograph 3-26: 25th Ave. S.W. Intersection — Looking northeast from 39th St. SW, south of 25th Ave. SW Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-28: 25th Ave. S.W. Intersection — Existing utilities at east leg of intersection Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-15 Photo Log of Potential Bridge Locations (November 23, 2021) Photograph 3-29: 25th Ave. S.W. Intersection — Looking east from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-31: 25th Ave. S.W. Intersection — Looking south from 39th St. SW Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-33: 25th Ave. S.W. Intersection — Looking northeast from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-30: 25th Ave. S.W. Intersection — Looking east from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-32: 25th Ave. S.W. Intersection — Looking north from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-34: 25th Ave. S.W. Intersection — Calibration Baseline Survey Marker Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-16 Photo Log of Potential Bridge Locations (November 23, 2021) air Photograph 3-35: 25th Ave. S.W. Intersection — Reference for Calibration Baseline Survey Marker at south leg of intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-36: 25th Ave. S.W. Intersection — Looking north from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-37: 25th Ave. S.W. Intersection — Photograph 3-38: 25th Ave. S.W. Intersection — Looking north from 39th St. SW Looking south from intersection Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-39: 25th Ave. S.W. Intersection — Existing Bridge No. 034012 label on guardrail, Looking north from bridge Taken by.- Felicia Kirby Date taken: 11123121 Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-40: 25th Ave. S.W. Intersection — Looking south from 25th Ave. SW bridge Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-17 Photo Log of Potential Bridge Locations (November 23, 2021) Photograph 3-41: 25th Ave. S.W. Intersection - Looking west from 25th Ave. SW bridge at Collier Blvd. Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-43: 25th Ave. S.W. Intersection - Looking south from 25th Ave. SW bridge Taken by.- Felicia Kirby Date taken: 11123121 Photograph 3-42: 25th Ave. S.W. Intersection - Looking southwest from 25th Ave. SW bridge at Collier Blvd. Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-18 Photo Log of Potential Bridge Locations (November 23, 2021) Alternative 4: Golden Gate Parkway and 39th Street Southwest Photograph 4-1: Golden Gate Pkwy. Intersection — Looking northwest at the Golden Gate Pkwy. and Collier Blvd. intersection (to the left) Taken by.- Felicia Kirby Date taken: 11123121 4 t Y Photograph 4-2: Golden Gate Pkwy. Intersection — Looking northwest at 951 Canal and Golden Gate Pkwy. Taken by.- Felicia Kirby Date taken: 11123121 Or F� _`��y 4��+� � �`•fir � _ r Photograph 4-3: Golden Gate Pkwy. Intersection - Looking north along the 951 Canal Taken by.- Felicia Kirby Date taken: 11123121 Photograph 4-5: Golden Gate Pkwy. Intersection — Looking north from 39th St. SW Taken by.- Felicia Kirby Date taken: 11123121 Photograph 4-4: Golden Gate Pkwy. Intersection — Looking south at existing water main crossing 951 Canal Taken by.- Felicia Kirby Date taken: 11123121 Photograph 4-6: Golden Gate Pkwy. Intersection — Looking west from 39th St. SW Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-19 Photo Log of Potential Bridge Locations (November 23, 2021) Photograph 4-7: Golden Gate Pkwy. Intersection Photograph 4-8: Golden Gate Pkwy. Intersection — Looking south from 39th St. SW — Looking north from 39th St. SW Taken by.- Felicia Kirby Date taken: 11123121 Photograph 4-9: Golden Gate Pkwy. Intersection - Looking southwest at Golden Gate Pkwy. and Collier Blvd. intersection Taken by.- Felicia Kirby Date taken: 11123121 Taken by.- Felicia Kirby Date taken: 11123121 Photograph 4-10: Golden Gate Pkwy. Intersection — Looking south Taken by.- Felicia Kirby Date taken: 11123121 •'�° i.F.,,Pv'M1�.di "WS '.��Nh k �. ....: :. �sZ.1i�G: Photograph 4-11: Golden Gate Pkwy. Intersection Photograph 4-12: Golden Gate Pkwy. Intersection — Looking southwest — Looking east at 39th St. SW Taken by.- Felicia Kirby Date taken: 11123121 Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-20 Photo Log of Potential Bridge Locations (November 23, 2021) Photograph 4-13: Golden Gate Pkwy. Intersection — Looking south Taken by.- Felicia Kirby Date taken: 11123121 Photograph 4-14: Golden Gate Pkwy. Intersection — Looking west at Collier Blvd. Taken by.- Felicia Kirby Date taken: 11123121 Photograph 4-15: Golden Gate Pkwy. Intersection Photograph 4-16: Golden Gate Pkwy. Intersection — Looking southwest at Golden Gate Pkwy. and — Looking west at Golden Gate Pkwy. and Collier Collier Blvd. intersection Blvd. intersection Taken by.- Felicia Kirby Date taken: 11123121 Taken by.- Felicia Kirby Date taken: 11123121 Photograph 4-17: Golden Gate Pkwy. Intersection Photograph 4-18: Golden Gate Pkwy. Intersection — Looking north — Looking northwest Taken by.- Felicia Kirby Date taken: 11123121 Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-21 Photo Log of Potential Bridge Locations (November 23, 2021) Photograph 4-19: Golden Gate Pkwy. Intersection Photograph 4-20: Golden Gate Pkwy. Intersection — Looking northwest from 39th St. SW — Looking south along the 951 Canal Taken by.- Felicia Kirby Date taken: 11123121 Taken by.- Felicia Kirby Date taken: 11123121 Attachment D - Photograph Log D-22 Attachment E Traffic Counts AM AND PM PEAK HOUR TURNING MOVEMENT COUNTS LD Y-i Z LP L.k 00 N� N� 01 o I� M w m n H m a p - Szj a > v 3 a a o 0 0 0 0 0 0 0 O 0 0 0 O m C 01 O `~ ci `-I c-I (7 Z � N � m N M W am -I .-I .'t-I N n ID V W O N w V J ac � y a O O N 0 0 0 .--i O M N N o p ti Ln m ro aC ti m in ti m m io a z o r J z O N O m � V\i c N c-I N W H O 0 0 0 O c N J W V1 00 V1 Ol 00 o cZ G W > O V1 Z y a O O O O O O O O O O 0 o v > O = w W -I �W-Ic�-I c�-I cm < Q W > m c2 G N O N F N N m Oo m r m m m o 0 O O O1 O O m N p G O O O ey O O O O .--i N N o v O H N n lD m Ol Vl V �--� ^ L > N � Z 0 O �O N v m o -6 o m x F- m 01 O w w �o v m m w N m� w c O Z .-IN N N N .-IN .-I w F O N v u (D c O 0j C � � O � O N O U J m N" O O O ri — Q'o Q Z w Z 0 m O m O m O m Q LL xz Z o U W Y (7 m 0 mv, n o m m m 00 v 0o _ O a > w 0 U 2 a � Z w x H Q n w Q Y U D Ou n m O W � Q w 2 s W LD Y-i Z LP L.k 10 ei N O N M m n m O N oR W L > v 3 N a O ti O O O O O N Ln M N N o m c OC o0 00 I, ti ti N O^ oq (7 Z O v O N � m N L M W 7j F V lD V Ol 111 Ol n 00 N al W V N o N N O ti V 111 O io O n H J ac � y a N O O O O O O O O N O � o M V1 M I� l0 L!1 00 O n w ti w 00 c5 N O m � v c-I N c-I N w H O�i 0 0 � O ZW �--I N N Ln N ` -I N M M N OOl > > O V1 Z y O ti o 0 o o o N M N N d o v > O = w > W U) w } � _ W O > m cQ � cG G � � N O N F �o 11 m m r-, n a N o � J O O O O O O1 O m v lU a O O O O .--i O O O ti .--i N o v o Z~ .-ZT -� oo cN-I cLn-I N N rn N^ v O O m F- m O J Vl tD rl N O N V N O m N m O N oo� cD Oz rl r-I o N v u (D c O of C C H H V V V N 00 N 00 V1 n M M N o � 0 O � J O ri a W Q O Z w Z 0 ul O ui O ul O V1 Q LL xz Z o u W � Y � H (7 m 0 v ,�mv, T v v Ln Un Ln Ln � O a > w 0 u 2 a Z w = H Q 0 Q Y u Ou v m O w Q s W LD 1--i L.:.k LL„L Z LP L.k 10 V V N w M Ln O w 1� LA M LnN O 01 N N n a N OO a O O O O O O N N o Ol a' p N n c-I Ln Ln Ln LO N oo M ti Z O N � m N � M W N Ln O N N � O H OC J y a O .--i o O o O O o o Z O r JFz O N O m N L\n c-I N c-I W F .--I e-I N N O O M O O Ol Ln � O N F N Vl � Z O w 0 O H Z y O O O ti o N O O v > O = w > W U z OC O O O O O M N u? 0 } _ D O < W > O m cQ G F- D O F N , O w m M w N n Ln O O O a O O O O ti ti N o p o r, V u? O O N N O N O Z � m O N C 0 m tD w c Oc Q t n N N Ln N ti O ti 02 � N ry J po V1 00 l0 M n N Ln N'r, O O O ? Qi m v V L Z H O Nam' 'O O v w Z 0 mO mO mO mQ w LL Z V w w 0 Z0 Y o .� m r, v, n o m .� m m 00 y 0o _ O a > V 2 a � Z w = H Q p s Q Y V O Ou n m O W Q n s W 10 H N tD In 00 w u1 In w O 00 N m M m lG o0 N Lm paj O M a oo o v a' Q M M M V V V N� o ti Z m � � M w O m .--I . O N m In � O N 0 0 N 0 0 0 M N N O tKI K J y a o o 0 o m o m n v rq o Q� N N M Lnrl Vl M Ln O N N r JFz Z O O N O m � c-I N c-I Ll N 'p l(J N m W oq O N In V M M c-I V1 - n M O 6 ZJ > > O V1 Z y a O O .--i O O N O ti ool t m In O v > O = w > W U z w o o o o o o o o o o q O w w > O m cQ G F- pF m .� m m m - � - �o N � N r, .� m't .� oo � w O V I" M n lA n l0 m N N O -d y a O O O O O O e O N N n o Q cz ti ti O O N O O ti oo ul m cn Z D O m O N C Qz w F m W N N m V m N 7, c L rl 0� J M M GO N V c-I I� V N D M ti � N N O J F- O � Q1 m v u z u Z o u w o Y g H 0 m 0 v .1 v m v v v o Ln .1 Un mv, Ln Ln cl, x O a > w = 0 V s 2 a Z z w v H Q Q Q Q Y V Ou m O w < s w O O Q1 I, N OD N 00 O 01 r, 1, V V1 C1 CO l/1 W W~ tD N IA M � � O v a O O O O O O O O O O o c a CC ti N N v1 M O O O ti ti 0 � N � [0 N L � M W � H l0 •--I .�i Ol N M G 'n oo o O � O N N .... N N O tKI H K J y a O O O O ti 0 0 o N ID M Ol -I QD n Lfl 0 Oo Z cm O r JFz m O N O m N � N rl ti � o moLl N V N oo J I� n 111 M Ln I" Z � O H y a O O O O O O N O O v > O = w > LL W u ti ti ti m m ti oo ko v n O z¢ w < W > O [O cQ cG G N N O F M O n0 lfl N O a o 0 0 N O � OC N O O O O O O O z � m O C Naj ~ K 0� rn m n n n n m m o t N N � OM ON cW-I NO N c^-I `m-I c�-I M N 000oq � a.+ N t ? 0 � Z Q LL Z V w w Z0 Y F m n n o0 00 oo oo O a > V 2 Q F- Z w = H Q 0 Q Y V ou m OO] W Q 0 s a- LD 4 Y-i 1.J..L Z LP L.k 0 000 o`no -e o m N m F - N n a o O "V v a O o 0 0 0 0 0 0 0 0 0 o c > a 0 O N O �--� N M c-I ti 'o N Z O � � N � m N M W F M V O ct w In N M^ W �D � 0 N N tKI F F K J y a N o o o o N o O V N N o N O m lD I� n lD tD m�� Z r J F C O N O m N v�i N c-I w F v �D n m o0 00 c, n m m mc,R o ri Z W --I --I `m -I > > O V1 Z v > O = w > 0 W U z In w In w In tD W oo N oo } _ D O < W > O m cQ cG G N F- Z) O N F M w n t-, iD N w 000 O N O y a O O O O O O O O O O O o o or o ti o 0 o ti ti � v m Z D O m O a, c Qz F m C l0 m N °� ^ V O t .N-i cN-I N o� N m oo `� I� m O N O N n cD N � � 0 � M v 6 V O J F- N— 0 a W 0 w Z O In O In O In O lfl O Q ii YY Z o V w w Z0 Y F (� m T v v v Ln Ln Ln V 'n F O d a > V 2 a F Z w 2 F Q p cc Q Y V Ou n m O W Q 0 ww W 3 DAY 24-HR BI-DIRECTIONAL TRAFFIC COUNTS LOCATION 1 Collier County 39th and White Blvd (South) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/14/2021 Combined Time Southbound Northbound Total 12:00 AM 5 5 10 1:00 7 4 11 2:00 1 1 2 3:00 1 3 4 4:00 5 7 12 5:00 8 19 27 6:00 15 68 83 7:00 40 117 157 8:00 57 92 149 9:00 55 62 117 10:00 55 66 121 11:00 77 71 148 12:00 PM 68 70 138 1:00 65 63 128 2:00 79 69 148 3:00 103 70 173 4:00 111 75 186 5:00 110 72 182 6:00 89 62 151 7:00 55 49 104 8:00 44 37 81 9:00 31 22 53 10:00 21 10 31 11:00 10 6 16 Total 1112 1120 2232 Percent 49.8% 50.2% 100.0% Peak 4:00 7:00 4:00 Volume 111 117 186 Collier County 39th and White Blvd (South) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/15/2021 Combined Time Southbound Northbound Total 12:00 AM 1 0 1 1:00 2 3 5 2:00 1 1 2 3:00 2 1 3 4:00 4 8 12 5:00 9 28 37 6:00 21 72 93 7:00 62 120 182 8:00 48 93 141 9:00 60 53 113 10:00 54 52 106 11:00 66 65 131 12:00 PM 64 74 138 1:00 77 59 136 2:00 71 82 153 3:00 93 73 166 4:00 107 68 175 5:00 143 94 237 6:00 98 65 163 7:00 79 43 122 8:00 53 71 124 9:00 28 32 60 10:00 18 9 27 11:00 10 3 13 Total 1171 1169 2340 Percent 50.0% 50.0% 100.0% Peak 5:00 7:00 5:00 Volume 143 120 237 Collier County 39th and White Blvd (South) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/16/2021 Combined Time Southbound Northbound Total 12:00 AM 4 11 15 1:00 2 8 10 2:00 3 0 3 3:00 0 2 2 4:00 3 6 9 5:00 9 25 34 6:00 19 78 97 7:00 61 115 176 8:00 57 89 146 9:00 48 56 104 10:00 59 56 115 11:00 72 68 140 12:00 PM 53 66 119 1:00 64 54 118 2:00 69 74 143 3:00 104 68 172 4:00 122 89 211 5:00 121 82 203 6:00 90 92 182 7:00 65 54 119 8:00 54 46 100 9:00 46 19 65 10:00 17 12 29 11:00 12 3 15 Total 1154 1173 2327 Percent 49.6% 50.4% 100.0% Volume 122 115 211 Grand Total 3437 3462 6899 Percent 49.8% 50.2% 100.0% LOCATION 2 Collier County 39th and Green Blvd (North) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/14/2021 Combined Time Southbound Northbound Total 12:00 AM 2 4 6 1:00 1 3 4 2:00 0 2 2 3:00 1 3 4 4:00 2 0 2 5:00 10 15 25 6:00 38 28 66 7:00 62 70 132 8:00 49 43 92 9:00 44 40 84 10:00 23 43 66 11:00 41 47 88 12:00 PM 32 55 87 1:00 30 70 100 2:00 36 57 93 3:00 47 93 140 4:00 48 113 161 5:00 63 141 204 6:00 45 79 124 7:00 26 46 72 8:00 15 34 49 9:00 9 27 36 10:00 8 13 21 11:00 4 6 0 Total 636 1032 1668 Percent 38.1 % 61.9% 100.0% Peak 5:00 5:00 5:00 Volume 63 141 204 Collier County 39th and Green Blvd (North) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/15/2021 Combined Time Southbound Northbound Total 12:00 AM 4 4 8 1:00 4 1 5 2:00 0 1 1 3:00 1 0 1 4:00 2 2 4 5:00 10 14 24 6:00 39 32 71 7:00 87 49 136 8:00 70 46 116 9:00 38 39 77 10:00 30 44 74 11:00 48 49 97 12:00 PM 40 59 99 1:00 43 51 94 2:00 33 58 91 3:00 47 94 141 4:00 66 134 200 5:00 70 152 222 6:00 38 69 107 7:00 33 37 70 8:00 14 36 50 9:00 14 23 37 10:00 5 14 19 11:00 3 7 10 Total 739 1015 1754 Percent 42.1 % 57.9% 100.0% Peak 7:00 5:00 5:00 Volume 87 152 222 Collier County 39th and Green Blvd (North) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/16/2021 Combined Time Southbound Northbound Total 12:00 AM 3 5 8 1:00 0 1 1 2:00 1 1 2 3:00 2 0 2 4:00 2 3 5 5:00 9 12 21 6:00 44 31 75 7:00 59 59 118 8:00 50 53 103 9:00 33 38 71 10:00 32 37 69 11:00 47 46 93 12:00 PM 29 45 74 1:00 36 49 85 2:00 32 66 98 3:00 58 102 160 4:00 60 109 169 5:00 60 127 187 6:00 46 88 134 7:00 26 50 76 8:00 15 33 48 9:00 15 34 49 10:00 9 18 27 11:00 6 4 Total 674 1015 1689 Percent 39.9% 60.1 % 100.0% Volume 60 127 187 Grand Total 2049 3062 5111 Percent 40.1 % 59.9% 100.0% LOCATION 3 Collier County 39th and Green Blvd (South) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/14/2021 Combined Time Southbound Northbound Total 12:00 AM 5 5 10 1:00 0 2 2 2:00 0 1 1 3:00 1 2 3 4:00 1 6 7 5:00 8 21 29 6:00 26 77 103 7:00 42 155 197 8:00 49 100 149 9:00 37 53 90 10:00 31 54 85 11:00 38 59 97 12:00 PM 47 61 108 1:00 43 75 118 2:00 50 84 134 3:00 80 90 170 4:00 108 134 242 5:00 89 150 239 6:00 85 80 165 7:00 34 34 68 8:00 28 40 68 9:00 23 22 45 10:00 16 4 20 11:00 6 2 8 Total 847 1311 2158 Percent 39.2% 60.8% 100.0% Peak 4:00 7:00 4:00 Volume 108 155 242 Collier County 39th and Green Blvd (South) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/15/2021 Combined Time Southbound Northbound Total 12:00 AM 4 1 5 1:00 2 3 5 2:00 2 0 2 3:00 1 2 3 4:00 0 4 4 5:00 6 18 24 6:00 31 82 113 7:00 58 121 179 8:00 45 95 140 9:00 42 62 104 10:00 32 69 101 11:00 45 63 108 12:00 PM 50 63 113 1:00 49 65 114 2:00 61 84 145 3:00 87 103 190 4:00 98 98 196 5:00 108 180 288 6:00 77 72 149 7:00 47 30 77 8:00 33 27 60 9:00 18 15 33 10:00 10 8 18 11:00 11 7 18 Total 917 1272 2189 Percent 41.9% 58.1 % 100.0% Peak 5:00 5:00 5:00 Volume 108 180 288 Collier County 39th and Green Blvd (South) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/16/2021 Combined Time Southbound Northbound Total 12:00 AM 6 4 10 1:00 1 0 1 2:00 1 1 2 3:00 2 2 4 4:00 2 3 5 5:00 9 15 24 6:00 28 78 106 7:00 50 144 194 8:00 43 99 142 9:00 25 63 88 10:00 34 48 82 11:00 42 63 105 12:00 PM 39 50 89 1:00 53 61 114 2:00 64 91 155 3:00 79 89 168 4:00 97 130 227 5:00 100 139 239 6:00 71 100 171 7:00 47 48 95 8:00 28 24 52 9:00 21 29 50 10:00 23 17 40 11:00 8 9 17 Total 873 1307 2180 Percent 40.0% 60.0% 100.0% Volume 100 144 239 Grand Total 2637 3890 6527 Percent 40.4% 59.6% 100.0% LOCATION 4 Collier County 39th and 17th Ave SW (South) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/14/2021 Combined Time Southbound Northbound Total 12:00 AM 4 5 9 1:00 2 1 3 2:00 0 1 1 3:00 1 2 3 4:00 1 3 4 5:00 7 18 25 6:00 27 70 97 7:00 52 138 190 8:00 52 93 145 9:00 37 54 91 10:00 30 51 81 11:00 44 55 99 12:00 PM 48 56 104 1:00 47 69 116 2:00 54 88 142 3:00 85 89 174 4:00 119 139 258 5:00 118 166 284 6:00 96 77 173 7:00 36 28 64 8:00 35 39 74 9:00 26 21 47 10:00 17 6 3 11:00 9 2 11 Total 947 1271 2218 Percent 42.7% 57.3% 100.0% Peak 4:00 5:00 5:00 Volume 119 166 284 Collier County 39th and 17th Ave SW (South) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/15/2021 Combined Time Southbound Northbound Total 12:00 AM 5 3 8 1:00 3 2 5 2:00 2 1 3 3:00 1 1 2 4:00 1 1 2 5:00 6 17 23 6:00 34 72 106 7:00 58 124 182 8:00 48 89 137 9:00 35 56 91 10:00 34 51 85 11:00 47 63 110 12:00 PM 49 56 105 1:00 60 65 125 2:00 60 96 156 3:00 94 107 201 4:00 115 105 220 5:00 105 180 285 6:00 79 76 155 7:00 51 29 80 8:00 38 23 61 9:00 23 17 40 10:00 12 8 20 11:00 10 4 14 Total 970 1246 2216 Percent 43.8% 56.2% 100.0% Peak 4:00 5:00 5:00 Volume 115 180 285 Collier County 39th and 17th Ave SW (South) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/16/2021 Combined Time Southbound Northbound Total 12:00 AM 7 3 10 1:00 2 0 2 2:00 1 2 3 3:00 2 2 4 4:00 1 3 4 5:00 11 18 29 6:00 32 74 106 7:00 53 129 182 8:00 49 99 148 9:00 33 61 94 10:00 36 44 80 11:00 53 55 108 12:00 PM 43 43 86 1:00 50 60 110 2:00 69 89 158 3:00 86 79 165 4:00 99 124 223 5:00 103 139 242 6:00 74 90 164 7:00 43 39 82 8:00 40 35 75 9:00 26 17 43 10:00 23 14 37 11:00 8 7 15 Total 944 1226 2170 Percent 43.5% 56.5% 100.0% Volume 103 139 242 Grand Total 2861 3743 6604 Percent 43.3% 56.7% 100.0% LOCATION 5 Collier County 39th and 25th Ave SW (North) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/14/2021 Combined Time Southbound Northbound Total 12:00 AM 0 7 7 1:00 0 3 3 2:00 2 2 4 3:00 0 2 2 4:00 3 2 5 5:00 27 5 32 6:00 53 22 75 7:00 83 60 143 8:00 84 48 132 9:00 63 31 94 10:00 47 25 72 11:00 35 41 76 12:00 PM 47 51 98 1:00 41 48 89 2:00 46 65 111 3:00 64 94 158 4:00 74 167 241 5:00 73 211 284 6:00 77 102 179 7:00 29 46 75 8:00 23 46 69 9:00 19 32 51 10:00 13 10 23 11:00 3 10 13 Total 906 1130 2036 Percent 44.5% 55.5% 100.0% Peak 8:00 5:00 5:00 Volume 84 211 284 Collier County 39th and 25th Ave SW (North) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/15/2021 Combined Time Southbound Northbound Total 12:00 AM 0 4 4 1:00 0 5 5 2:00 0 1 1 3:00 1 0 1 4:00 2 2 4 5:00 20 6 26 6:00 54 19 73 7:00 86 58 144 8:00 66 51 117 9:00 54 26 80 10:00 43 31 74 11:00 42 59 101 12:00 PM 36 48 84 1:00 37 53 90 2:00 53 96 149 3:00 76 88 164 4:00 77 100 177 5:00 70 151 221 6:00 52 83 135 7:00 28 56 84 8:00 30 44 74 9:00 19 32 51 10:00 13 19 32 11:00 6 7 13 Total 865 1039 1904 Percent 45.4% 54.6% 100.0% Peak 7:00 5:00 5:00 Volume 86 151 221 Collier County 39th and 25th Ave SW (North) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/16/2021 Combined Time Southbound Northbound Total 12:00 AM 3 7 10 1:00 0 0 0 2:00 0 3 3 3:00 2 1 3 4:00 4 2 6 5:00 23 7 30 6:00 53 23 76 7:00 97 58 155 8:00 66 38 104 9:00 54 34 88 10:00 51 34 85 11:00 46 34 80 12:00 PM 41 50 91 1:00 45 52 97 2:00 58 57 115 3:00 72 86 158 4:00 64 119 183 5:00 63 145 208 6:00 57 85 142 7:00 38 57 95 8:00 24 59 83 9:00 23 30 53 10:00 17 22 39 11:00 9 8 17 Total 910 1011 1921 Percent 47.4% 52.6% 100.0% Volume 97 145 208 Grand Total 2681 3180 5861 Percent 45.7% 54.3% 100.0% LOCATION 6 Collier County 39th and 25th Ave SW (South) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/14/2021 Combined Time Southbound Northbound Total 12:00 AM 1 3 4 1:00 2 2 4 2:00 0 1 1 3:00 0 3 3 4:00 1 4 5 5:00 8 13 21 6:00 19 31 50 7:00 35 87 122 8:00 55 58 113 9:00 36 34 70 10:00 33 26 59 11:00 28 35 63 12:00 PM 39 43 82 1:00 36 36 72 2:00 47 52 99 3:00 75 91 166 4:00 92 135 227 5:00 88 192 280 6:00 70 73 143 7:00 40 36 76 8:00 18 30 48 9:00 22 8 30 10:00 15 8 23 11:00 13 5 18 Total 773 1006 1779 Percent 43.5% 56.5% 100.0% Peak 4:00 5:00 5:00 Volume 92 192 280 Collier County 39th and 25th Ave SW (South) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/15/2021 Combined Time Southbound Northbound Total 12:00 AM 2 3 5 1:00 1 3 4 2:00 1 0 1 3:00 0 0 0 4:00 0 6 6 5:00 2 10 12 6:00 18 29 47 7:00 57 117 174 8:00 47 94 141 9:00 33 38 71 10:00 25 22 47 11:00 46 47 93 12:00 PM 25 42 67 1:00 48 62 110 2:00 49 86 135 3:00 74 74 148 4:00 105 68 173 5:00 145 87 232 6:00 64 70 134 7:00 38 45 83 8:00 36 26 62 9:00 30 17 47 10:00 23 15 38 11:00 2 11 13 Total 871 972 1843 Percent 47.3% 52.7% 100.0% Peak 5:00 7:00 5:00 Volume 145 117 232 Collier County 39th and 25th Ave SW (South) `r Start Date: 12/14/2021 End Date: 12/16/2021 ENGINEERING 12/16/2021 Combined Time Southbound Northbound Total 12:00 AM 1 9 10 1:00 2 0 2 2:00 0 2 2 3:00 0 5 5 4:00 1 3 4 5:00 3 21 24 6:00 16 44 60 7:00 39 92 131 8:00 40 88 128 9:00 26 57 83 10:00 17 63 80 11:00 12 59 71 12:00 PM 20 77 97 1:00 11 69 80 2:00 28 83 111 3:00 44 119 163 4:00 25 161 186 5:00 52 173 225 6:00 16 113 129 7:00 22 80 102 8:00 5 61 66 9:00 5 46 51 10:00 3 43 46 11:00 0 18 18 Total 388 1486 11174 Percent 20.7% 79.3% 100.0% Volume 52 173 225 Grand Total 2032 3464 5496 Percent 37.0% 63.0% 100.0% Attachment F Future Land Use gm.\�� Attachment G Preliminary Signal Warrant Analysis Collier County Transportation - Bridge Location Study Turning Movement Volumes - AM Peak Hour N/S Roadway: 39th St E/W Roadway: 25th Ave Date Taken: 12/15/21 SF 0.92 S 3 3 2021 Background 8:00am SF Adjustment n129 39th St 67 62 44 18 5 25th Ave 26 N 9 53 242 � 21 W E 81 78 31 S 3 28 25th Ave ir�� E 52 II II 108 160 39th St ZUZ9 BaCK round v:UUam SF AO ustmen 95 39th St 50 A � 45 13 2 25th Ave 18 N 3 21 169 7 W E 17 30 54 29 S � 9 � 25th Ave 43 4 k 87 ` 130 39th St 2u21 Background Count 8:OUam 140 39th St 73 67 48 20 5 25th Ave 79 1 28 E N 10 58 264 23 W E 88 85 34 0 25th Ave 86 29 2 57 117 174 39th St Collier County Transportation - Bridge Location Study Turning Movement Volumes - PM Peak Hour N/S Roadway: 39th St E/W Roadway: 25th Ave Date Taken: 12/15/21 SF 0.92 2021 Background 5:00 m SF Adjustment n140 39th St 52 88 22 22 7 25th Ave 68 q6O N 3 14 226 W E 40 158 S 1 27 25th Ave n 26 1 103 II II 63 166 39th St ZUZ9 BaCKgrouna t1:UUpm SF Aotusi 189 39th St 52 �� 136 26 5 25th Av 75 87 N 9 25 299 30 W E <; 15 63 224 107 S 1 38 25th Av 133 4 k 80 213 39th St 2u21 Background Count 5:U0 m 152 39th St 56 96 24 24 8 25th Ave 65 N 3 15 W 246 20 E 44 172 87 S 1 29 25th Ave 39 n28 1 112 II 68 180 39th St 2021 Background Count 6:00 m n205 39th St 57 148 24 28 5 25th Ave 95 N 0 27 325 33 W E 16 � 68 244 116 S 1 41 25th Ave n 43 3 145 II 87 232 39th St Form 750-020-01 State of Florida Department of Transportation TRAFFIC ENGINEERING TRAFFIC SIGNAL WARRANT SUMMARY October 2020 City: Engineer: RG County: 03 — Collier Date: April 20, 2022 District: One Major Street: Collier Blvd Lanes: 6 Major Approach Speed: 45 Minor Street: 27th Ave Lanes: 1 Minor Approach Speed: 30 MUTCD Electronic Reference to Chapter 4: httr):Hmutcd.fhwa.dot.gov/i)dfs/2009rl r2/part4.pdf Volume Level Criteria 1. Is the posted speed or 85th-percentile of major street > 40 mph? C Yes C No 2. Is the intersection in a built-up area of an isolated community with a population < 10,000? C Yes C No 70W volume level may be used if Question 1 or 2 above is answered "Yes" C MAY C 70% C 100% WARRANT 2 - FOUR-HOUR VEHICULAR VOLUME If all four points lie above the appropriate line, then the warrant is satisfied. Applicable: C Yes C No 100% Volume Level Four Volumes Highest Major Minor Hours Street Street 70% Volume Level Four Highest Hours Volumes Major Minor Street Street 8:00 AM 2020 165 9:00 AM 2020 114 5:00 PM 2020 68 6:00 PM 3015 75 500 x > 400 x FO w = 300 �a ~a n< O 200 z_ 3 O x 100 !7 x Satisfied: C Yes C No Plot four volume combinations on the applicable figure below. FIGURE 4C-1: Criteria for "100%" Volume Level I 2 OR MORE LANES & 2 OR MORE LANES 2 OR MORE LANES & I LANE 11 LANE & LANE 0 1 1 1 1 1 1 1 1 1 1 1 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 MAJOR STREET - TOTAL OF BOTH APPROACHES -VPH Note: 115 ph. applies as the lower threshold volume for a minor street approach with two or more lanes and 80 mph applies as the lower threshold volume threshold for a minor street approach with one lane. FIGURE 4C-2: Criteria for "70%" Volume Level (Community Less than 10,000 population or above 70 km/hr. (40 mph) on Major Street) 400 > 2 OR MORE LANES & 2 OR MOREL ANES F Q 300 WO K K 2 OR MORE LANES & 1 LANE Fa x200 02 z� 2 JO 1 LANE & 1 LANE S. 2too *60 0 200 300 400 500 600 700 800 900 MAJOR STREET - TOTAL OF BOTH APPROACHES -VPH Note: 80 ph. applies as the lower threshold volume for a minor street approach with two or more lanes and 60 ph. applies as the lower threshold volume threshold for a minor street approach with one lane. 1000 WARRANT 2 - FOUR-HOUR VEHICULAR VOLUME Page 1 of 1 Attachment H Preliminary Synchro Analysis Reports Golden Gate Pkwy/Collier Blvd 3-leg Intersection - 2045 AM Lanes, Volumes, Timings } I 04/05/2022 I t Lane Group EBL EBR NBL NBT SBT SBR Lane Configurations r )) ttt ttt r Traffic Volume (vph) 482 482 290 869 2059 571 Future Volume (vph) 482 482 290 869 2059 571 Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900 Lane Util. Factor 0.97 1.00 0.97 0.91 0.91 1.00 Frt 0.850 0.850 Flt Protected 0.950 0.950 Satd. Flow (prot) 3433 1583 3433 5085 5085 1583 Flt Permitted 0.950 0.039 Satd. Flow (perm) 3433 1583 141 5085 5085 1583 Right Turn on Red Yes Yes Satd. Flow (RTOR) 480 337 Link Speed (mph) 45 45 45 Link Distance (ft) 699 503 552 Travel Time (s) 10.6 7.6 8.4 Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 Adj. Flow (vph) 524 524 315 945 2238 621 Shared Lane Traffic (%) Lane Group Flow (vph) 524 524 315 945 2238 621 Enter Blocked Intersection No No No No No No Lane Alignment Left Right Left Left Left Right Median Width(ft) 24 24 24 Link Offset(ft) 0 0 0 Crosswalk Width(ft) 16 16 16 Two way Left Turn Lane Headway Factor 1.00 1.00 1.00 1.00 1.00 1.00 Turning Speed (mph) 15 9 15 9 Turn Type Prot Free pm+pt NA NA Prot Protected Phases 8 1 6 2 2 Permitted Phases Free 6 Detector Phase 8 1 6 2 2 Switch Phase Minimum Initial (s) 5.0 5.0 5.0 5.0 5.0 Minimum Split (s) 31.4 12.1 37.1 37.1 37.1 Total Split (s) 44.0 38.0 116.0 78.0 78.0 Total Split (%) 27.5% 23.8% 72.5% 48.8% 48.8% Maximum Green (s) 37.6 30.9 108.9 70.9 70.9 Yellow Time (s) 4.4 4.8 4.8 4.8 4.8 All -Red Time (s) 2.0 2.3 2.3 2.3 2.3 Lost Time Adjust (s) 0.0 0.0 0.0 0.0 0.0 Total Lost Time (s) 6.4 7.1 7.1 7.1 7.1 Lead/Lag Lead Lag Lag Lead -Lag Optimize? Yes Yes Yes Vehicle Extension (s) 3.0 3.0 3.0 3.0 3.0 Recall Mode None None C-Max C-Max C-Max Walk Time (s) 7.0 7.0 7.0 7.0 Flash Dont Walk (s) 18.0 23.0 23.0 23.0 Pedestrian Calls (#/hr) 4 4 4 4 Act Effct Green (s) 29.7 160.0 116.8 116.8 95.3 95.3 Golden Gate Comparison - AM 2045 Synchro 10 Report RG Page 1 Golden Gate Pkwy/Collier Blvd 3-leg Intersection - 2045 AM Lanes, Volumes, Timings 04/05/2022 Lane Group EBL EBR NBL NBT SBT SBR Actuated g/C Ratio 0.19 1.00 0.73 0.73 0.60 0.60 v/c Ratio 0.82 0.33 0.79 0.25 0.74 0.58 Control Delay 73.8 0.6 56.6 7.7 26.5 11.4 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 73.8 0.6 56.6 7.7 26.5 11.4 LOS E A E A C B Approach Delay 37.2 19.9 23.2 Approach LOS D B C Queue Length 50th (ft) 275 0 116 109 595 167 Queue Length 95th (ft) 328 0 170 149 780 336 Internal Link Dist (ft) 619 423 472 Turn Bay Length (ft) Base Capacity (vph) 806 1583 738 3713 3029 1079 Starvation Cap Reductn 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 Reduced v/c Ratio 0.65 0.33 0.43 0.25 0.74 0.58 Intersection Summa Area Type: Other Cycle Length: 160 Actuated Cycle Length: 160 Offset: 23 (14%), Referenced to phase 2:SBT and 6:NBTL, Start of Green Natural Cycle: 85 Control Type: Actuated -Coordinated Maximum v/c Ratio: 0.82 Intersection Signal Delay: 25.3 Intersection LOS: C Intersection Capacity Utilization 79.0% ICU Level of Service D Analysis Period (min) 15 Splits and Phases: 3: Collier Blvd & Golden Gate Pkwy 01 7 O R t06 rR 08 Golden Gate Comparison - AM 2045 Synchro 10 Report RG Page 2 Golden Gate Pkwy/Collier Blvd 3-leg Intersection - 2045 PM Lanes, Volumes, Timings } I 04/05/2022 I t Lane Group EBL EBR NBL NBT SBT SBR Lane Configurations r )) ttt ttt r Traffic Volume (vph) 644 644 301 903 1367 390 Future Volume (vph) 644 644 301 903 1367 390 Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900 Lane Util. Factor 0.97 1.00 0.97 0.91 0.91 1.00 Frt 0.850 0.850 Flt Protected 0.950 0.950 Satd. Flow (prot) 3433 1583 3433 5085 5085 1583 Flt Permitted 0.950 0.107 Satd. Flow (perm) 3433 1583 387 5085 5085 1583 Right Turn on Red Yes Yes Satd. Flow (RTOR) 512 305 Link Speed (mph) 45 45 45 Link Distance (ft) 699 503 552 Travel Time (s) 10.6 7.6 8.4 Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 Adj. Flow (vph) 700 700 327 982 1486 424 Shared Lane Traffic (%) Lane Group Flow (vph) 700 700 327 982 1486 424 Enter Blocked Intersection No No No No No No Lane Alignment Left Right Left Left Left Right Median Width(ft) 24 24 24 Link Offset(ft) 0 0 0 Crosswalk Width(ft) 16 16 16 Two way Left Turn Lane Headway Factor 1.00 1.00 1.00 1.00 1.00 1.00 Turning Speed (mph) 15 9 15 9 Turn Type Prot Free pm+pt NA NA Prot Protected Phases 8 1 6 2 2 Permitted Phases Free 6 Detector Phase 8 1 6 2 2 Switch Phase Minimum Initial (s) 5.0 5.0 5.0 5.0 5.0 Minimum Split (s) 31.4 12.1 37.1 37.1 37.1 Total Split (s) 52.0 42.0 98.0 56.0 56.0 Total Split (%) 34.7% 28.0% 65.3% 37.3% 37.3% Maximum Green (s) 45.6 34.9 90.9 48.9 48.9 Yellow Time (s) 4.4 4.8 4.8 4.8 4.8 All -Red Time (s) 2.0 2.3 2.3 2.3 2.3 Lost Time Adjust (s) 0.0 0.0 0.0 0.0 0.0 Total Lost Time (s) 6.4 7.1 7.1 7.1 7.1 Lead/Lag Lead Lag Lag Lead -Lag Optimize? Yes Yes Yes Vehicle Extension (s) 3.0 3.0 3.0 3.0 3.0 Recall Mode None None C-Max C-Max C-Max Walk Time (s) 7.0 7.0 7.0 7.0 Flash Dont Walk (s) 18.0 23.0 23.0 23.0 Pedestrian Calls (#/hr) 4 4 4 4 Act Effct Green (s) 36.3 150.0 100.2 100.2 80.0 80.0 Golden Gate Comparison - PM 2045 Synchro 10 Report RG Page 1 Golden Gate Pkwy/Collier Blvd 3-leg Intersection - 2045 PM Lanes, Volumes, Timings 04/05/2022 Lane Group EBL EBR NBL NBT SBT SBR Actuated g/C Ratio 0.24 1.00 0.67 0.67 0.53 0.53 v/c Ratio 0.84 0.44 0.62 0.29 0.55 0.43 Control Delay 63.9 0.9 17.0 11.0 25.3 7.9 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 63.9 0.9 17.0 11.0 25.3 7.9 LOS E A B B C A Approach Delay 32.4 12.5 21.4 Approach LOS C B C Queue Length 50th (ft) 339 0 56 135 338 57 Queue Length 95th (ft) 388 0 101 184 463 163 Internal Link Dist (ft) 619 423 472 Turn Bay Length (ft) Base Capacity (vph) 1043 1583 967 3397 2711 986 Starvation Cap Reductn 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 Reduced v/c Ratio 0.67 0.44 0.34 0.29 0.55 0.43 Intersection Summa Area Type: Other Cycle Length: 150 Actuated Cycle Length: 150 Offset: 55 (37%), Referenced to phase 2:SBT and 6:NBTL, Start of Green Natural Cycle: 85 Control Type: Actuated -Coordinated Maximum v/c Ratio: 0.84 Intersection Signal Delay: 22.2 Intersection LOS: C Intersection Capacity Utilization 70.5% ICU Level of Service C Analysis Period (min) 15 Splits and Phases: 3: 01 • 02. 03 t06 IF Golden Gate Comparison - PM 2045 Synchro 10 Report RG Page 2 Golden Gate Pkwy/Collier Blvd 4-leg Intersection - 2045 AM Lanes, Volumes, Timings -11 --1. 4--- 1I04/05/2022 t Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations + r tt r )) ttt r ) ttt r Traffic Volume (vph) 482 37 482 85 85 85 290 869 37 37 2059 571 Future Volume (vph) 482 37 482 85 85 85 290 869 37 37 2059 571 Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900 Lane Util. Factor 0.97 1.00 1.00 0.97 0.95 1.00 0.97 0.91 1.00 1.00 0.91 1.00 Frt 0.850 0.850 0.850 0.850 Flt Protected 0.950 0.950 0.950 0.950 Satd. Flow (prot) 3433 1863 1583 3433 3539 1583 3433 5085 1583 1770 5085 1583 Flt Permitted 0.950 0.950 0.950 0.950 Satd. Flow (perm) 3433 1863 1583 3433 3539 1583 3433 5085 1583 1770 5085 1583 Right Turn on Red Yes Yes Yes Yes Satd. Flow (RTOR) 483 120 125 319 Link Speed (mph) 45 45 45 45 Link Distance (ft) 631 684 558 544 Travel Time (s) 9.6 10.4 8.5 8.2 Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 Adj. Flow (vph) 524 40 524 92 92 92 315 945 40 40 2238 621 Shared Lane Traffic (%) Lane Group Flow (vph) 524 40 524 92 92 92 315 945 40 40 2238 621 Enter Blocked Intersection No No No No No No No No No No No No Lane Alignment Left Left Right Left Left Right Left Left Right Left Left Right Median Width(ft) 24 24 24 24 Link Offset(ft) 0 0 0 0 Crosswalk Width(ft) 16 16 16 16 Two way Left Turn Lane Headway Factor 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Turning Speed (mph) 15 9 15 9 15 9 15 9 Turn Type Split NA Free Split NA Perm Prot NA Perm Prot NA Perm Protected Phases 8 8 4 4 1 6 5 2 Permitted Phases Free 4 6 2 Detector Phase 8 8 4 4 4 1 6 6 5 2 2 Switch Phase Minimum Initial (s) 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 Minimum Split (s) 25.4 25.4 12.8 12.8 12.8 13.0 37.1 37.1 13.0 37.1 37.1 Total Split (s) 38.0 38.0 16.0 16.0 16.0 33.0 73.0 73.0 33.0 73.0 73.0 Total Split (%) 23.8% 23.8% 10.0% 10.0% 10.0% 20.6% 45.6% 45.6% 20.6% 45.6% 45.6% Maximum Green (s) 31.6 31.6 8.2 8.2 8.2 25.9 65.9 65.9 25.9 65.9 65.9 Yellow Time (s) 4.4 4.4 3.7 3.7 3.7 4.8 4.8 4.8 4.8 4.8 4.8 All -Red Time (s) 2.0 2.0 4.1 4.1 4.1 2.3 2.3 2.3 2.3 2.3 2.3 Lost Time Adjust (s) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Lost Time (s) 6.4 6.4 7.8 7.8 7.8 7.1 7.1 7.1 7.1 7.1 7.1 Lead/Lag Lead Lag Lag Lead Lag Lag Lead -Lag Optimize? Yes Yes Yes Yes Yes Yes Vehicle Extension (s) 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 Recall Mode None None None None None None C-Max C-Max None C-Max C-Max Walk Time (s) 7.0 7.0 7.0 7.0 7.0 7.0 Flash Dont Walk (s) 12.0 12.0 23.0 23.0 23.0 23.0 Pedestrian Calls (#/hr) 0 0 0 0 0 0 Act Effct Green (s) 28.7 28.7 160.0 8.0 8.0 8.0 19.9 88.5 88.5 9.0 75.0 75.0 Golden Gate Comparison - AM 2045 Synchro 10 Report RG Page 1 Golden Gate Pkwy/Collier Blvd 4-leg Intersection - 2045 AM Lanes, Volumes, Timings 04/05/2022 Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Actuated g/C Ratio 0.18 0.18 1.00 0.05 0.05 0.05 0.12 0.55 0.55 0.06 0.47 0.47 v/c Ratio 0.85 0.12 0.33 0.54 0.52 0.48 0.74 0.34 0.04 0.40 0.94 0.68 Control Delay 77.2 54.6 0.6 86.3 85.1 13.1 78.0 21.3 0.1 83.9 49.3 20.4 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 77.2 54.6 0.6 86.3 85.1 13.1 78.0 21.3 0.1 83.9 49.3 20.4 LOS E D A F F B E C A F D C Approach Delay 39.5 61.5 34.4 43.6 Approach LOS D E C D Queue Length 50th (ft) 273 35 0 49 50 0 166 206 0 41 821 257 Queue Length 95th (ft) 340 71 0 81 83 31 214 256 0 82 #1017 443 Internal Link Dist (ft) 551 604 478 464 Turn Bay Length (ft) Base Capacity(vph) 678 367 1583 175 181 194 555 2811 931 286 2384 911 Starvation Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.77 0.11 0.33 0.53 0.51 0.47 0.57 0.34 0.04 0.14 0.94 0.68 Intersection Summa Area Type: Other Cycle Length: 160 Actuated Cycle Length: 160 Offset: 0 (0%), Referenced to phase 2:SBT and 6:NBT, Start of Green Natural Cycle: 110 Control Type: Actuated -Coordinated Maximum v/c Ratio: 0.94 Intersection Signal Delay: 41.5 Intersection LOS: D Intersection Capacity Utilization 85.6% ICU Level of Service E Analysis Period (min) 15 # 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles. Splits and Phases: 7: Collier Blvd & Golden Gate Pkwy 01 • 0?_ 04 8 o5 t06 fR Golden Gate Comparison - AM 2045 Synchro 10 Report RG Page 2 Golden Gate Pkwy/Collier Blvd 4-leg Intersection - 2045 PM Lanes, Volumes, Timings -11 --1. 4--- 1I04/05/2022 t Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations + r tt r )) ttt r ) ttt r Traffic Volume (vph) 644 119 644 40 40 40 301 903 119 119 1367 390 Future Volume (vph) 644 119 644 40 40 40 301 903 119 119 1367 390 Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900 Lane Util. Factor 0.97 1.00 1.00 0.97 0.95 1.00 0.97 0.91 1.00 1.00 0.91 1.00 Frt 0.850 0.850 0.850 0.850 Flt Protected 0.950 0.950 0.950 0.950 Satd. Flow (prot) 3433 1863 1583 3433 3539 1583 3433 5085 1583 1770 5085 1583 Flt Permitted 0.950 0.950 0.950 0.950 Satd. Flow (perm) 3433 1863 1583 3433 3539 1583 3433 5085 1583 1770 5085 1583 Right Turn on Red Yes Yes Yes Yes Satd. Flow (RTOR) 532 128 133 332 Link Speed (mph) 45 45 45 45 Link Distance (ft) 631 684 558 544 Travel Time (s) 9.6 10.4 8.5 8.2 Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 Adj. Flow (vph) 700 129 700 43 43 43 327 982 129 129 1486 424 Shared Lane Traffic (%) Lane Group Flow (vph) 700 129 700 43 43 43 327 982 129 129 1486 424 Enter Blocked Intersection No No No No No No No No No No No No Lane Alignment Left Left Right Left Left Right Left Left Right Left Left Right Median Width(ft) 24 24 24 24 Link Offset(ft) 0 0 0 0 Crosswalk Width(ft) 16 16 16 16 Two way Left Turn Lane Headway Factor 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Turning Speed (mph) 15 9 15 9 15 9 15 9 Turn Type Split NA Free Split NA Perm Prot NA Perm Prot NA Perm Protected Phases 8 8 4 4 1 6 5 2 Permitted Phases Free 4 6 2 Detector Phase 8 8 4 4 4 1 6 6 5 2 2 Switch Phase Minimum Initial (s) 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 Minimum Split (s) 32.9 32.9 12.8 12.8 12.8 13.0 38.0 38.0 13.0 38.0 38.0 Total Split (s) 36.0 36.0 18.0 18.0 18.0 32.0 64.0 64.0 32.0 64.0 64.0 Total Split (%) 24.0% 24.0% 12.0% 12.0% 12.0% 21.3% 42.7% 42.7% 21.3% 42.7% 42.7% Maximum Green (s) 29.6 29.6 10.2 10.2 10.2 24.9 56.9 56.9 24.9 56.9 56.9 Yellow Time (s) 4.4 4.4 3.7 3.7 3.7 4.8 4.8 4.8 4.8 4.8 4.8 All -Red Time (s) 2.0 2.0 4.1 4.1 4.1 2.3 2.3 2.3 2.3 2.3 2.3 Lost Time Adjust (s) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Lost Time (s) 6.4 6.4 7.8 7.8 7.8 7.1 7.1 7.1 7.1 7.1 7.1 Lead/Lag Lead Lag Lag Lead Lag Lag Lead -Lag Optimize? Yes Yes Yes Yes Yes Yes Vehicle Extension (s) 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 Recall Mode None None None None None None C-Max C-Max None C-Max C-Max Walk Time (s) 7.0 7.0 7.0 7.0 7.0 7.0 Flash Dont Walk (s) 18.0 18.0 23.0 23.0 23.0 23.0 Pedestrian Calls (#/hr) 0 0 0 0 0 0 Act Effct Green (s) 33.7 33.7 150.0 7.3 7.3 7.3 19.5 67.1 67.1 16.2 63.8 63.8 Golden Gate Comparison - PM 2045 Synchro 10 Report RG Page 1 Golden Gate Pkwy/Collier Blvd 4-leg Intersection - 2045 PM Lanes, Volumes, Timings 04/05/2022 Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Actuated g/C Ratio 0.22 0.22 1.00 0.05 0.05 0.05 0.13 0.45 0.45 0.11 0.43 0.43 v/c Ratio 0.91 0.31 0.44 0.26 0.25 0.22 0.73 0.43 0.17 0.68 0.69 0.49 Control Delay 73.2 51.9 0.9 72.1 71.8 2.5 72.6 30.0 4.4 81.2 37.9 9.3 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 73.2 51.9 0.9 72.1 71.8 2.5 72.6 30.0 4.4 81.2 37.9 9.3 LOS E D A E E A E C A F D A Approach Delay 38.3 48.8 37.4 34.7 Approach LOS D D D C Queue Length 50th (ft) 351 107 0 21 21 0 161 242 0 124 436 55 Queue Length 95th (ft) #491 175 0 42 43 0 208 305 40 190 521 159 Internal Link Dist (ft) 551 604 478 464 Turn Bay Length (ft) Base Capacity(vph) 770 418 1583 233 240 226 569 2274 781 293 2163 864 Starvation Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.91 0.31 0.44 0.18 0.18 0.19 0.57 0.43 0.17 0.44 0.69 0.49 Intersection Summa Area Type: Other Cycle Length: 150 Actuated Cycle Length: 150 Offset: 55 (37%), Referenced to phase 2:SBT and 6:NBT, Start of Green Natural Cycle: 100 Control Type: Actuated -Coordinated Maximum v/c Ratio: 0.91 Intersection Signal Delay: 36.9 Intersection LOS: D Intersection Capacity Utilization 77.2% ICU Level of Service D Analysis Period (min) 15 # 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles. Splits and Phases: 7: Collier Blvd & Golden Gate Pkwy o5 t05 Golden Gate Comparison - PM 2045 Synchro 10 Report RG Page 2 Attachment Public Involvement Meeting Summary Attachment 1.1 Public Information Meeting Notifications Transportation Engineering Projects Web Page 4/27/22, 4:29 PM Transportation Engineering Projects I Collier County, FL Transportation Engineering Projects DESIGN PROJECT MANAGEMENT ROAD CONSTRUCTION / CEI PROJECTS IN DESIGN PROJECTS IN CONSTRUCTION Vanderbilt Beach Road Extension - Collier Bl to 16th St. NE (Project Manager: Mario Puente, P.E.) The Vanderbilt Beach Road Extension (Collier Boulevard to 16th Street NE) is an approximate 7-mile extension of the existing roadway. Please refer to this page for project details. Vanderbilt Beach Road Widening Project from East of US 41 to East of Goodlette-Frank Road (Project Manager: Dennis McCoy, P.E.) This road widening project will expand Vanderbilt Beach Road from four to six lanes and extend approximately 1.8 miles from just east of US 41 to approximately the intersection of Vanderbilt Beach Road and Fontana Del Sol Way. https://www.colliercountyfl.gov/government/growth-managementldivisions/transportation-engineering-division/transportation-engineering-projects 1/5 4/27/22, 4:29 PM Transportation Engineering Projects I Collier County, FL Much of the lane expansion will occur in the existing median. The project will include: improved roadway intersections at Strada Place and Goodlette- Frank Road; maintaining existing sidewalks and providing bike lanes; improved drainage throughout the project area. Collier County held a public information meeting for the 6o % Design Plal Tuesday, March 30, 2021. Click here for a copy of the public information meeting newsletter, which includes a location map for the meeting, project limits and other important information. The meeting displays are available here: • Project Handout • Typical Section • Exhibit Part 1 (11MB, enlarge for details) • Exhibit Part 2 (19MB, enlarge for details) • Exhibit Part 3 (22MB, enlarge for details) The final design plans are expected to be completed late in early 2022 and construction is slated to begin in 2023. Whippoorwill Lane Extension (Project Manager: Bee Thao, P.E.) This project connects Whippoorwill Lane with Marbella Lakes Drive. There will be 4 roundabouts and a new signal on Livingston Road at Marbella Lakes Drive with lighting at roundabouts and narrower travel lanes (1o'-11') to slow speed. A Design -Build contract in the amount of $4,720,450 was awarded to Quality Enterprises and the 'Notice to Proceed' was issued on July 12th, 2021. https://www.colliercountyfl.gov/government/growth-managementldivisions/transportation-engineering-division/transportation-engineering-projects 2/5 4/27/22, 4:29 PM Transportation Engineering Projects I Collier County, FL 11, The Whippoorwill Lane Extension Design/Build 6o Percent Design Plans Public Information Meeting took place on Nov. 10, 2021. At the Meeting the 6o% Design for Marbella Lakes Drive as well as for Whippoorwill Lane were presented (zoom in on attachments for details). Golden Gate Parkway (CR 886) at Santa Barbara Canal Bridge Replacement Project (Project Manager: Dennis McCoy, P.E.) This four -lane bridge, built in 1971, is nearing the end of its useful life and needs to be replaced. The existing bridge will be replaced with a new structure that will include two, 12400t travel lanes eastbound and two, _ 12400t travel lanes westbound with eight -foot shoulders, and _ 12400t sidewalks on each side. The two adjacent pedestrian bridges that were added in 2oo8 will be removed and stored for potential future use in another location. Design of the new bridge is expected to be completed in summer of 2022. Construction is anticipated to begin shortly after the design is finished and completed late in fall of 2023. During the first part of construction, traffic for both directions of travel will use one side of the existing bridge (one lane in each direction) while the contractor removes the old two-lane section (half of the existing bridge) and constructs https://www.colliercountyfl.gov/government/growth-managementldivisions/transportation-engineering-division/transportation-engineering-projects 3/5 4/27/22, 4:29 PM Transportation Engineering Projects I Collier County, FL the new two-lane section. Once half of the bridge is constructed, traffic will shift to the new structure to allow construction on the second half of the bridge. Throughout construction travel will be maintained for vehicles, bicycles, and pedestrians with limited traffic delays during peak periods. Temporary lane closures may be necessary. The county does not anticipate fully closing the roadway at any time during this work. However, detours will be provided should a temporary, full closure be necessary. Access to businesses and residents near the bridge will be maintained. A Public Information Meeting was held on March 29, 2022 at the 60% design stage. Find here the handout and the Typical Bridge Sections Display. Collier Boulevard Widening Phase III (Project Manager: Bee Thao, P.E.) The project is located along Collier Boulevard between City { Gate Boulevard North and Green Boulevard. The proposed improvements will help relieve congestion, improve safety, and • a accommodate future traffic demands within the area. The _ - project involves widening Collier Boulevard from four- to six -lanes r = — �' _ • ?� K. within the project limits (approximately 2.1 miles). This is the final project, in a series of five projects, to improve 15 miles of Collier Boulevard, from US 41 to Immokalee Road, to a six - lane roadway. This project includes widening within the median and along the west side of Collier Boulevard and realigns portions of the adjacent CR 951 Canal. Multimodal improvements include the addition of bike lanes along Collier Boulevard, as well as two 10-foot-wide shared -use pathways along the west side of Collier Boulevard and along the west side of 39th Street SW. The Collier Boulevard Bridge Location Study is evaluating various locations for a bridge connection (over the CR 951 Canal) between Collier Boulevard and 39th Street SW. The Collier Boulevard Widening Project will remove the existing bridge at 25th Avenue SW to accommodate the proposed https://www.colliercountyfl.gov/government/growth-managementldivisions/transportation-engineering-division/transportation-engineering-projects 4/5 4/27/22, 4:29 PM Transportation Engineering Projects I Collier County, FL improvements. Locations being evaluated for the new replacement bridge include Golden Gate Parkway, 25th Avenue SW, 27th Avenue SW, and 29th Avenue SW. A Public Information Meeting at the 6o% design stage was held on April 6, 2022. The following displays were provided: • Collier Blvd from City Gate Blvd N to Golden Gate Pkwy (enlarge for details) • Collier Blvd from Golden Gate Pkwy to Green Blvd (enlarge for details) • Typical Section • Bridge Locations Alternatives Table A comment form is available. By April 20, 2022 please print, fill out, and either mail or scan/photograph and then email to growth. management @ colliercountyfl. goy. https://www.colliercountyfl.gov/government/growth-managementldivisions/transportation-engineering-division/transportation-engineering-projects 5/5 County Manager's Newsletter 4/27/22, 3:18 PM Project Update Collier Blvd Widening Project Update More than 90 Collier County residents and visitors attended the Collier Boulevard Widening Project 60 Percent Design Plans and Collier Boulevard Bridge Location Study Public Information Meeting held on Wednesday, April 6, 2022, at Golden Gate Community Center Auditorium, 4701 Golden Gate Pkwy, Naples. During the informal, open house -style meeting, attendees were able to review the latest design plans that were overlaid on aerial photographs of the roadway and adjacent land. They were also able to talk one-on-one with design team members that included staff from the Collier County Transportation Engineering Division and from the county's design consultant, Jacobs. The project is located along Collier Boulevard between City Gate Boulevard North and Green Boulevard. The proposed improvements will help relieve congestion, improve safety, and accommodate future traffic demands within the area. The project involves widening Collier Boulevard from four- to six -lanes within the project limits (approximately 2.1 miles). This is the final project, in a series of five projects, to improve 15 miles of Collier Boulevard, from US 41 to Immokalee Road, to a six -lane roadway. This project includes widening within the median and along the west side of Collier Boulevard and realigns portions of the adjacent CR 951 Canal. Multimodal improvements include the addition of bike lanes along Collier Boulevard, as well as two 10-foot-wide shared -use pathways along the west side of Collier Boulevard and along the west side of 39th Street SW. The Collier Boulevard Bridge Location Study is evaluating various locations for a bridge connection (over the CR 951 Canal) between Collier Boulevard and 39th Street SW. The Collier Boulevard Widening Project will remove the existing bridge at 25th Avenue SW to accommodate the proposed improvements. Locations being evaluated for the new replacement bridge include Golden Gate Parkway, 25th Avenue SW, 27th Avenue SW, and 29th Avenue SW. The Collier Boulevard Widening Project design is anticipated to be completed by the end of 2023. Funding for widening Collier Boulevard is anticipated in the projected Collier County 2022 Five-year Work Program for design, right-of-way, and construction between Fiscal Years 2022 and 2026. The Collier Boulevard Bridge Location Study is anticipated to be completed and presented to the Board of County Commissioners by mid-2022 for approval. The proposed bridge would be constructed as part of the Collier Boulevard Widening Project. The meeting displays, handouts and comment forms are posted on the county's website at www.colliercountyl.gov/transportatio pLojects Subscribe https://I p.constantcontactpages.com/cu/rg5Le2n/Coll ierBlvd W iden ing?source_id=9a 140283-77l d-443b-99b9-097e236fl O7b&source type=em&c=8Ee ... 1 /2 Press Release Collier County Government zl� Growth Management Department Contact: Connie Deane Transportation Engineering Division Community Liaison 2885 S. Horseshoe Drive 239-252-8365 Naples, FL 34104 colliercountyfl.2ov twitter.com/CollierPIO facebook.com/CollierGov youtube.com/CollierGov March 31, 2022 FOR IMMEDIATE RELEASE Collier Boulevard Widening Project 60 Percent Design Plans & Bridge Location Study Public Information Meeting Wednesday, April 6, 2022 5 p.m. to 7 p.m. All interested members of the public are invited to attend a public information meeting on the Collier Boulevard Widening Project 60 Percent Design Plans and Collier Boulevard Bridge Location Study from 5 to 7 p.m., Wednesday, April 6 at Golden Gate Community Center Auditorium, 4701 Golden Gate Pkwy, Naples, FL 34116. The meeting will be conducted in an informal, open house setting with no formal presentation. Attendees may attend at any time during the two-hour time frame to review the project displays and talk one-on-one with the project team regarding any questions. (A diagram showing the project location and public meeting location is at the end of this release.) The project is located along Collier Boulevard between City Gate Boulevard North and Green Boulevard. The proposed improvements will help relieve congestion, improve safety, and accommodate future traffic demands within the area. The project involves widening Collier Boulevard from four- to six -lanes within the project limits (approximately 2.1 miles). This is the final project, in a series of five projects, to improve 15 miles of Collier Boulevard, from US 41 to Immokalee Road, to a six -lane roadway. This project includes widening within the median and along the west side of Collier Boulevard and realigns portions of the adjacent CR 951 Canal. Multimodal improvements include the addition of bike lanes along Collier Boulevard, as well as two 10-foot-wide shared -use pathways along the west side of Collier Boulevard and along the west side of 39th Street SW. The Collier Boulevard Bridge Location Study is evaluating various locations for a bridge connection (over the CR 951 Canal) between Collier Boulevard and 39th Street SW. The Collier Boulevard Widening Project will remove the existing bridge at 25th Avenue SW to accommodate the proposed improvements. Locations being evaluated for the new replacement bridge include Golden Gate Parkway, 25th Avenue SW, 27th Avenue SW, and 29th Avenue SW. The Collier Boulevard Widening Project is anticipated to complete design by mid-2023. Funding for widening Collier Boulevard is anticipated in the projected Collier County 2022 Five-year Work Program for design, right-of-way, and construction between Fiscal Years 2022 and 2026. The Collier Boulevard Bridge Location Study is anticipated to be completed and presented to the Board of County Commissioners by mid-2022 for approval. The proposed bridge would be constructed as part of the Collier Boulevard Widening Project. -more- Collier Boulevard Widening Project 60 Percent Design Plans & Bridge Location Study Public Information Meeting News Release/Page 2 of 2 As an alternative to attending the meeting in person, the meeting displays and handouts will be posted on the county's website at www.colliercouniyfl.gov/transportatioLiprojects on April 6, 2022. Public input is very important and we encourage all interested residents, businesses owners and visitors to share their comments. Comment forms will be available at the public information meeting as well as on the county website. The public comment period will end April 20, 2022. Two or more members of the Board of County Commissioners (BCC) may be present and participate at this meeting. The subject matter of this meeting may be an item for discussion and action at a future BCC meeting. Anyone who requires an auxiliary aid or service for effective communication, or other reasonable accommodations to participate in this proceeding, should contact the Collier County Facilities Management Division located at 3335 Tamiami Trail E., Suite 101, Naples, Florida 34112, or 239-252-8380 as soon as possible, but no later than 48 hours before the scheduled event. Such reasonable accommodations will be provided at no cost to the individual. For additional information concerning the Collier Boulevard Widening Project, please contact Senior Project Manager Bee Thao, P.E. at 239-252-8192 or Bee. Thao(ibcolliercountyfl. gov. For additional information concerning the Collier Boulevard Bridge Location Study please contact Principal Planner Lorraine Lantz, AICP at 239-252-5779 or Lorraine.Lantzkcolliercoun . fl.-ov. News media inquiries may be directed to Community Liaison Connie Deane at 239-252-8365 or Connie.Deanegcolliercountyfl. gov. 15TH AVE SW GREEN BLVD co MEETING LOCATION W 17TH AVE SW Wednesday, April 6, 2022 1 5 p.m. to 7 p.m. "' 19TH AVE 5W Golden Gate Community Center 4701 Golden Gate Parkway _ Naples, FL 34116 2,STvEsw PROJECT i AREA 23TH AVE SW I 25TH AVE SW J � m m 27TH AVE SW i w a CO J 29TH AVE SW O 0 I Rik 31STAVESW Q � � U Z _CfTY GATE BLVD N Collier Boulevard Widening Project Notification Emails, Letters and Mailing Lists Elected Officials ELECTED OFFICIALS: BCC: chris.sweet(a)mail.house.gov; rod rigues.ray.web(a)_flsenate.gov; pass idomo.kathleen.web(a)flsenate.gov; lauren.melo(a)myfloridahouse.gov; crustal.kinzel(d_)collierclerk.com; Mike.Sheffield(d_)CollierClerk.com; Rick. LoCastro(d_)colliercountyfl.gov; Aixa.Capizzi(cDcolliercountyfl.gov; Andy. Sol is(d_)colIiercountyfl.gov; Angela. Good ner(d_)colliercountyfl.gov; Burt. Saunders(d_)colliercountyfl.gov; Dave. Lykins(c)_colliercountyfl.gov; Pen ny.Taylor(a)_colIiercountyfl.gov; Sherry.Greco(cDcolliercountyfl.gov; Bill.McDaniel(cDcolliercountyfl.gov; Sue. Filson(a)colliercountyfl.gov; webinfo(cDcollierappraiser.com; SupervisorOfElections(CDCollierCountyfl.Gov; WestbeJo(cDcollierschools.com; lucars(cDcollierschools.com; mitchi3(@collierschools.com; cartee1 .collierschools.com; terryro .collierschools.com; sheriff .colliersheriff.org; Felicia. KirbyZjcDiacobs.com; sonal.dodia(a�iacobs.com; colleen. ross(a)iacobs.com CC: Jay.Ahmad(a)-colliercountyfl.gov; Bee.Thao(d-)colliercountyfl.gov; Trinity.Scott(a)-colliercountyfl.gov; maruio.brock(d_)colliercountyfl.gov; Connie. Dean e(a)_colIiercountyfl.gov; Marlene. Messam(D-colliercountyfl.gov From: LantzLorraine Subject: [EXTERNAL] Collier Boulevard Widening Project 60 Percent Design Plans and Collier Boulevard Bridge Location Study Date: Tuesday, March 22, 2022 3:07:22 PM Attachments: Collier Blvd Widenina - Public Information Meeting Newsletter.Ddf Dear Elected Official: Collier County will hold a public information meeting for the Collier Boulevard Widening Project 60 Percent Design Plans and Collier Boulevard Bridge Location Study. The public meeting will be held on Wednesday, April 6, 2022, from 5 p.m. to 7 p.m. at the Golden Gate Community Center, 4701 Golden Gate Parkway, Naples, FL 34116. The meeting will be conducted in an informal, open house setting with no formal presentation. Attendees may review the project displays and talk one-on-one with the project team regarding any questions. The purpose of this meeting is to provide the public with an opportunity to review and comment on the Collier Boulevard Project 60 Percent Design Plans and the Collier Boulevard Bridge Location Study alternatives. Attached is the public information meeting newsletter, which includes a location map for the meeting, project limits and other important information. This newsletter is being sent to all property owners located within 500 feet of the project limits, as well as other public officials, agencies, and other interested parties. As an alternative to attending the meeting in person, the meeting displays and handouts will be posted on the county's website at www.colliercountyfl.gov/transportationprojects (under "Projects in Design") beginning April 6, 2022. Your input is very important, and we encourage you to share your comments. Comment forms will be available at the public information meeting as well as on the county website. The public comment period will end April 20, 2022. Collier County looks forward to keeping you informed as we progress through this project. If you have any comments or questions, please contact us by phone or email at: Collier Boulevard Widening Project Bee Thao, P.E., Senior Project Manager, Collier County Transportation Engineering Division Phone (239) 252-5844 Bee.Thaoft_colliercountyFL.gov Collier Boulevard Bridge Location Study Project Lorraine Lantz, AICP, Principal Planner, Collier County Transportation Management Services Department Phone (239) 252-5779 Lorraine. Lantzg_colliercountyFL.gov Respectfully, Lorraine M. Lantz, AICP Principal Planner i Co per 4Z;01414ty Collier County Capital Projects, Planning, Impact Fees & Program Management NOTE: Email Address Has Changed 2685 S. Horseshoe Drive, Suite #103 Naples, FL 34104 Phone: (239) 252-5779 Lorraine. Lantz@CollierCountyFL.aov Under Florida Law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by telephone or in writing. NEWSLETTER Coll ieriBoulevard Widening Project 'and Bridge Location Study Collier County is conducting a public information meeting for the Collier Boulevard Widening Project 60 Percent Design Plans and the Collier Boulevard Bridge Location Study. The project is located along Collier Boulevard between City Gate Boulevard North and Green Boulevard. The proposed improvements will help relieve congestion, improve safety, and accommodate future traffic demands within the area. The Collier Boulevard Widening Project involves widening Collier Boulevard from four- to six -lanes within the project limits (approximately 2.1 miles). This is the final project, in a series of five projects, to improve 15 miles of Collier Boulevard, from US 41 to Immokalee Road, to a six -lane roadway. This project includes widening within the median and along the west side of Collier Boulevard, and realigns portions of the adjacent CR 951 Canal. Multimodal improvements include the addition of bike lanes along Collier Boulevard, as well as two 10-foot- wide shared -use pathways along the west side of Collier Boulevard and along the west side of 39th Street SW. The Collier Boulevard Bridge Location Study is evaluating various locations for a bridge connection (over the CR 951 Canal) between Collier Boulevard and 39th Street SW. The Collier Boulevard Widening Project will remove the existing bridge at 25th Avenue SW to accommodate the proposed improvements. Locations being evaluated for the new replacement bridge include Golden Gate Parkway, 25th Avenue SW, 27th Avenue SW, and 29th Avenue SW. D YOU'RE INVITED Collier County invites you to participate in the upcoming public information meeting for the Collier Boulevard Widening Project 60 Percent Design Plans and Collier Boulevard Bridge Location Study. The public meeting will be held on LOCATION Wednesday, April 6, 2022, from Wednesday, April 6, 2022 5 p.m. to 7 p.m. at the Golden 5 p.m. to 7 p.m. Gate Community Center, 4701 Golden Gate Community Center Golden Gate Parkway, Naples, 4701 Golden Gate Parkway FL 34116. The meeting will be Naples, FL 34116 conducted in an informal, open house setting with no formal presentation. Attendees may review the project displays, and >> talk one-on-one with the project m team regarding any questions. a " As an alternative to attending the meeting in person, the meeting m displays and handouts will be is posted on the county's website Z on April 6, 2022. Your input 'is� very important and we encourager you to share your comments. Comment forms will be available at the public information meeting as well as on the county website. The public comment period will end April 20, 2022. PROJECT SCHEDULES The Collier Boulevard Widening Project is anticipated to complete design by mid-2023. Funding for widening Collier Boulevard is anticipated in the projected Collier County 2022 Five-year Work Program for design, right-of-way, and construction between Fiscal Years 2022 and 2026. The Collier Boulevard Bridge Location Study is anticipated to be completed and presented to the Board of County Commissioners by mid-2022 for approval. The proposed bridge would be constructed as part of the Collier Boulevard Widening Project. March 2022 El condado de Collier esta Ilevando a cabo una reunion de informacion publica para el Proyecto de Ampliacion de Collier Boulevard 60 por ciento de planes de diseno y el Estudio de Ubicacion del Puente de Collier Boulevard. El proyecto esta ubicado a to largo de Collier Boulevard entre City Gate Boulevard North y Green Boulevard. Las mejoras propuestas ayudaran a aliviar la congestion, mejorar la seguridad y adaptarse a las futuras demandas de trafico dentro del area. El Proyecto de Ampliacion de Collier Boulevard consiste en ampliar Collier Boulevard de cuatro- a seis-carriles dentro de los limites del proyecto (aproximadamente 2,1 millas). Este es el proyecto final, en una serie de cinco proyectos, para mejorar 15 millas de Collier Boulevard, entre US 41 y Immokalee Road, a una carretera de seis carriles. Este proyecto incluye la ampliacion dentro de la mediana ya to largo del lado oeste de Collier Boulevard, y realinea partes del canal CR 951 adyacente. Las mejoras multimodales incluyen la adicion de carriles para bicicletas a to largo de Collier Boulevard, asi como dos vias de use compartido de 10 pies de ancho a Io largo del lado oeste de Collier Boulevard y a to largo del lado oeste de 39th Street SW. El Estudio de Ubicacion del Puente de Collier Boulevard esta evaluando varias ubicaciones para una conexion de puente (sobre el canal CR 951) entre Collier Boulevard y 39th Street SW. El Proyecto de Ampliacion de Collier Boulevard eliminara el puente existente en 25th Avenue SW para acomodar las mejoras propuestas. Las ubicaciones que se estan evaluando para el nuevo puente de reemplazo incluyen Golden Gate Parkway, 25th Avenue SW, 27th Avenue SW y 29th Avenue SW. ESTAS INVITADO ONE El Condado de Collier to invita a participar en la proxima vista publica para presentar el 60 porciento de los planos de diseno para el Proyecto de Ampliacion de Collier Boulevard y el Estudio de Ubicacion del 15THAVE SW Puente de Collier Boulevard. La GREEN BLVD N vista publica se Ilevara a cabo el 17THAVE SW miercoles 6 de abril de 2022, desde las 5 p.m. hasta las 7 p.m. 19TH AVE SW en el Centro Comunitario Golden Gate, 4701 Golden Gate Parkway, 21STAVE SW Naples, FL 34116. La vista publica PROJECT se Ilevara a cabo en un ambiente AREA IF 23THAVESW informal de puertas abiertas y sin una presentacion formal. Los GOLDEN GATE PKWY 25TH AVE SW asistentes podran revisar las W exhibiciones del proyecto y de tener m 27THAVE SW alguna pregunta podran hablar personalmente con el equipo de a 29THAVE SW trabajo del proyecto. 0 Como alternativa de no poder 31STAVE SW asistir a la reunion en persona, las exhibiciones y los folletos de CITY GATE BLVDN la reunion se publicaran en el sitio web del Condado el 6 de abril de 2022. Su opinion es muy importante y to alentamos a que comparta sus comentarios. Los formularios para comentarios estaran disponibles en la vista publica, asi como en el sitio web del Condado. El periodo para comentarios del publico finalizara el 20 de abril de 2022. CALENDARIO DEL PROYECTO Se preve que el diseno para el proyecto de Ampliacion de Collier Boulevard este terminado a mediados de 2023. SegOn el Programa de Trabajo de Cinco anos del Condado Collier 2022 se anticipa que la financiacion para el diseno, derecho de paso y la construccion del proyecto sea entre los anos fiscales 2022 y 2026. Se preve que el Estudio de Ubicacion del Puente de Collier Boulevard este completado y sea presentado a la Junta de Comisionados del Condado a mediados de 2022 para su aprobacion. El puente propuesto se construira como parte del Proyecto de Ampliacion de Collier Boulevard. Co yer County Principal Planner, Lorraine M. Lantz, AICP Collier County Transportation Management Services 2685 S. Horseshoe Drive, Suite #103 Naples, FL 34104 PUBLIC INVOLVEMENT One of the most important aspects of design and studies is public involvement. It is very important for you to be able to provide your comments related to the proposed improvements. We use a variety of methods for you to stay involved in the process such as public meetings, small group meetings, and the project website. In addition, Collier County mails notifications to all property owners within the study area as well as to agencies and local officials prior to the public meeting. PROJECT CONTAC If you have any questions, comments, or concerns regarding the project, please contact us: PARTICIPACION PUBLICA Uno de los aspectos mas importantes del diseno y los estudios es la participaci6n publica. Es muy importante que ustedes puedan aportar sus comentarios sobre las mejoras propuestas. Se usaran una variedad de met000s para que ustedes sigan participando en el proyecto, tal como vistas publicas, reuniones en grupos pequenos y en un sitio web del proyecto. En adici6n, el Condado de Collier enviara por correo notificaciones a todos los duenos de propiedades dentro del area de estudio y a las agencias y funcionarios locales antes de las reuniones. CONTACTO DEL PROYE Si tiene alguna pregunta, comentario o inquietud con respecto al proyecto, contactenos: Pou 6d an krey6l, tanpri kontakte Diana Francois sou Diana.Francois@jacobs. Collier Boulevard Widening Project Collier Boulevard Bridge Study Project Bee Thao, P.E., Senior Project Manager SCAN ME: Lorraine Lantz, AICP, Principal Planner Collier County Transportation Engineering Nlr '& R1 Collier County Transportation Management Services 2885 S. Horseshoe Drive 2685 S. Horseshoe Drive, Suite # 103 Naples, FL 34104 Naples, FL 34104 Phone (239) 252-5844 { Phone (239) 252-5779 Bee.Thao@CollierCountyFL.gov ,_; Lorraine.Lantz@CollierCountyFL.gov FOR MORE PROJECT INFORMATION GO TO: www.colliercountyfl.gov/transportationprojects Two or more members of the Board of County Commissioners (BCC) may be present and participate at this meeting. The subject matter of this meeting may be an item for discussion and action at a future BCC meeting. Anyone who requires an auxiliary aid or service for effective communication, or other reasonable accommodations to participate in this proceeding, should contact the Collier County Facilities Management Division located at 3335 Tamiami Trail E., Naples, Florida 34112, or 239-252-8380 as soon as possible. Such reasonable accommodations will be provided at no cost to the individual. Dos o mas miembros de la Junta de Comisionados del Condado (BCC, por sus siglas en ingles) pueden estar presentes y participar en esta reuni6n. El tema de esta reuni6n puede ser un tema de discusi6n y acci6n en una futura reunion del BCC. Cualquier persona que requiera ayuda o servicio auxiliar para tener comunicaci6n eficaz, u otras adaptaciones razonables para participar en este procedimiento, debe comunicarse con la Division de Administraci6n de Instalaciones del Condado de Collier ubicada en 3335 Tamiami Trail E., Naples, Florida 34112, 6 239-252-8380 como tan pronto como sea posible. Tales adaptaciones razonables se proporcionaran sin costo alguno para el individuo. Agencies and Appointed Officials AGENCIES/ APPOINTED: BCC: John tupy(o)fws.gov; Portia. Sapp(aVreshfromflorid a.com; AESCares(c�FDACS.gov; barbara.powell(a)deo.myflorida.com; samantha.browne(a)dep.state.fl.us; Kali na.Warren(a)Florida DEP.gov; Jon. lglehart(a-)_FloridaDEP.gov; Megan. Mills(a)FloridaDEP.gov; terry.gilbert(a)_myfwc.com; All ie.McCue(a-)MVFWC.com; John wrublik(a-)_fws.gov; mparrott(a)_sfwmd.gov; briackso(o-)_sfwmd.gov; annemullins(a)semtribe.com; Lauren. Peters(c�dot.state.fl.us; Christopher. Simpron(a)dot.state.fl.us; Victoria. Peters(c)dot.state.fl.us; Richard. Ouievolk(a)dot.state.fl.us; Jonathon. Bennett(a-).dot.state.fl.us; Mark. Isackson(a)colliercountyfl.gov; Amy.Patterson(a)-colliercountyfl.gov; James.French (aj)coIIiercountyfl.gov; trinity.scott .colliercountyfl.gov; Jaime. Cook(alcolliercountyfl.gov; Ken. Kovensky(a-)colliercountyfl.gov; Michael. Bosi(a-i.colliercountyfl.gov; Matthew. Mclean(E�colliercountyfl.gov; Lorraine.Lantz(c�colliercountyfl.gov; Michael.Sawyer(E�colliercountyfl.gov; richard.miller(c�colliercountyfl.gov; michael.studney(a�colliercountyfl.gov; Gene.Shue(o-)colliercountyfl.gov; Gerald. Kurtz(E�colliercountyfl.gov;; Robert. Bosch(a)_colliercountyfl.gov; Steve. Ritter(o-)_colliercountyfl.gov; Anthony. Khawaia(a)colliercountyfl.gov; Pamela.Wilson(d_)colliercountyfl.gov; George.Yilmaz(o-)_Colliercountyfl.gov; Tom. Chmelik(a)_colIiercountyfl.gov; Kari.Hodgson(a)colliercountyfl.gov; Steve. Messner(c)-colliercountyfl.gov; Beth. Johnssen(alcolIiercountyfl.gov; Jack. McKenna(a-)-colIiercountyfl.gov; Cormac.Giblin(a-)colliercountyfl.gov; alicia.humphries(a)-colliercountyfl.gov; brett.rosenblum(a-)colliercountyfl.gov; kirsten.wilkie(a-)colliercountyfl.gov; Dan. Summers(a)colliercountyfl.gov; Tabitha.Butcher(a colliercountyfl.gov; John. Mullins(a-)colliercountyfl.gov; deborah.curry(a colliercountyfl.gov; Connie. Deane(5)colliercountyfl.gov; Heather. Meyer(a)colliercountyfl.gov; Omar. Deleon(c�colliercountyfl.gov; eastmath(c�collierschools.com; oliver(a-)collierschools.com; Daniel. Rodriquez(a�colliercountyfl.gov; Kimberley.Grant(c colliercountyfl.gov; Barry.Williams(c�colliercountyfl.gov; Michelle.Arnold(a-)_colliercountyfl.gov; Twvla.Leigh(a-)colliercountyfl.gov; Karen. Homiak(a-)_colliercountyfl.gov; christopher.vernon(a-)_colliercountyfl.gov; karl.fry(c�colliercountyfl.gov; Edwin Fryer(a)_colliergov.net; robert.klucik(a-)_colliercountyfl.gov; JosephSchmitt(a)_colliergov.net; paul.shea(a)_colliercountyfl.gov; Ray.Bellows(a)colliercountyfl.gov; nsapp(a)gnfire.org; mwuerstle(a-)-swfrpc.org; michael(a)napleschamber.org; Anne.McLaughlinCo�colliercountyfl.gov; Brandy. Otero(a-)colliercountyfl.gov; Thad. Rhodes(a-)colliersheriff.org; Geoffrey.Willig(o-)CollierCountyFI.Gov; DavidAnthony(o colliergov.net; DoraCarrillo(a-)colliergov.net; eric.johnson .colliercountyfl.gov; CristinaPerez(o)colliergov.net; Felicia. KirbyZjcDiacobs.com; sonal.dodia(a�iacobs.com; colleen. ross(aMacobs.com CC: Jay.Ahmad(a)-colliercountyfl.gov; Bee.Thao(c�colliercountyfl.gov; Trinity.Scott(a)-colliercountyfl.gov; maryio.brock(d_)colliercountyfl.gov; Connie. Deane(a)_colliercountyfl.gov; Marlene. Messam(D-colliercountyfl.gov From: LantzLorraine Subject: [EXTERNAL] Collier Boulevard Widening Project 60 Percent Design Plans and Collier Boulevard Bridge Location Study Date: Tuesday, March 22, 2022 3:08:48 PM Attachments: Collier Blvd Widenina - Public Information Meetina Newsletter.odf Dear Government/Agency Partner Collier County will hold a public information meeting for the Collier Boulevard Widening Project 60 Percent Design Plans and Collier Boulevard Bridge Location Study. The public meeting will be held on Wednesday, April 6, 2022, from 5 p.m. to 7 p.m. at the Golden Gate Community Center, 4701 Golden Gate Parkway, Naples, FL 34116. The meeting will be conducted in an informal, open house setting with no formal presentation. Attendees may review the project displays and talk one-on-one with the project team regarding any questions. The purpose of this meeting is to provide the public with an opportunity to review and comment on the Collier Boulevard Project 60 Percent Design Plans and the Collier Boulevard Bridge Location Study alternatives. Attached is the public information meeting newsletter, which includes a location map for the meeting, project limits and other important information. This newsletter is being sent to all property owners located within 500 feet of the project limits, as well as other public officials, agencies, and other interested parties. As an alternative to attending the meeting in person, the meeting displays and handouts will be posted on the county's website at www.colliercountyfl.gov/transportationprojects (under "Projects in Design") beginning April 6, 2022. Your input is very important, and we encourage you to share your comments. Comment forms will be available at the public information meeting as well as on the county website. The public comment period will end April 20, 2022. Collier County looks forward to keeping you informed as we progress through this project. If you have any comments or questions, please contact us by phone or email at: Collier Boulevard Widening Project Bee Thao, P.E., Senior Project Manager, Collier County Transportation Engineering Division Phone (239) 252-5844 Bee.Thaoft_colliercountyFL.gov Collier Boulevard Bridge Location Study Project Lorraine Lantz, AICP, Principal Planner, Collier County Transportation Management Services Department Phone (239) 252-5779 Lorraine. Lantzp_colliercountyFL.gov Respectfully, Lorraine M. Lantz, AICP Principal Planner Lorraine M. Lantz, AICP Principal Planner o -rer C,014ftty Collier County Capital Projects, Planning, Impact Fees & Program Management NOTE: Email Address Has Changed 2685 S. Horseshoe Drive, Suite #103 Naples, FL 34104 Phone: (239) 252-5779 Lorraine.Lantz@CollierCountyFL.gov Under Florida Law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by telephone or in writing. Special Interest Groups and Interested Parties INTERESTED PARTIES: BCC: gimitchellhouse@centurylink.net; PSpenFla(@Daol.com; kaydee(cDtuffnews.com; fesposl957(cDgmail.com; csimone77(@D_gmail.com; zentiltd(@_gmail.com; riefferson(d_)flynaples.com; Dan. Schumacher(@-colIiercountyfl.gov; michael.mcgrath(@psierraclub.org; audubon.southwest.florida(@D_gmail.com; mwolok(d_)audubonwe.org; jwraithmell(d_)audubon.org; fta(@Dfloridatrail.org; hikerdavid(@outlook.com; efleming(@defenders.org; southeastoffice(@-defenders.org; fran.perch ick(@Dtnc.org; florida(@tnc.orq; friends(cD1000fof.org; info(@collierenterprises.com; robm(@conservancy.org; Felicia. Kirbv26�jacobs.com; sonal.dodia(c)jacobs.com; colleen. ross(o-)jacobs.com CC: Jay.Ahmad(a)-colliercountyfl.gov; Bee.Thao(@�colliercountyfl.gov; Trinity.Scott(a-)-colliercountyfl.gov; maryio.brock(d_)colliercountyfl.gov; Connie. Dean e(a)_colIiercountyfl.gov; Marlene. Messam(a)-colliercountyfl.gov From: LantzLorraine Subject: [EXTERNAL] Collier Boulevard Widening Project 60 Percent Design Plans and Collier Boulevard Bridge Location Study Date: Tuesday, March 22, 2022 3:11:33 PM Attachments: Collier Blvd Widenina - Public Information Meetina Newsletter.odf Dear Interested Party Collier County will hold a public information meeting for the Collier Boulevard Widening Project 60 Percent Design Plans and Collier Boulevard Bridge Location Study. The public meeting will be held on Wednesday, April 6, 2022, from 5 p.m. to 7 p.m. at the Golden Gate Community Center, 4701 Golden Gate Parkway, Naples, FL 34116. The meeting will be conducted in an informal, open house setting with no formal presentation. Attendees may review the project displays and talk one-on-one with the project team regarding any questions. The purpose of this meeting is to provide the public with an opportunity to review and comment on the Collier Boulevard Project 60 Percent Design Plans and the Collier Boulevard Bridge Location Study alternatives. Attached is the public information meeting newsletter, which includes a location map for the meeting, project limits and other important information. This newsletter is being sent to all property owners located within 500 feet of the project limits, as well as other public officials, agencies, and other interested parties. As an alternative to attending the meeting in person, the meeting displays and handouts will be posted on the county's website at www.colliercountyfl.gov/transportationprojects (under "Projects in Design") beginning April 6, 2022. Your input is very important, and we encourage you to share your comments. Comment forms will be available at the public information meeting as well as on the county website. The public comment period will end April 20, 2022. Collier County looks forward to keeping you informed as we progress through this project. If you have any comments or questions, please contact us by phone or email at: Collier Boulevard Widening Project Bee Thao, P.E., Senior Project Manager, Collier County Transportation Engineering Division Phone (239) 252-5844 Bee.Thaoft_colliercountyFL.gov Collier Boulevard Bridge Location Study Project Lorraine Lantz, AICP, Principal Planner, Collier County Transportation Management Services Department Phone (239) 252-5779 Lorraine. Lantzp_colliercountyFL.gov Respectfully, Lorraine M. Lantz, AICP Principal Planner Lorraine M. Lantz, AICP Principal Planner o -rer C,014ftty Collier County Capital Projects, Planning, Impact Fees & Program Management NOTE: Email Address Has Changed 2685 S. Horseshoe Drive, Suite #103 Naples, FL 34104 Phone: (239) 252-5779 Lorraine.Lantz@CollierCountyFL.gov Under Florida Law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by telephone or in writing. INTERESTED PARTIES: BCC: btrsweet2(aD_verizon.net; ANBEKE(a)_Vahoo.com; acosta-adriana @-hotmail.com; agrano(a)-bellsouth.net; Tnis76(a_gmail.com; duffya18(d_)gmail.com; alicia34120(aD_Vahoo.com; lockha(@collierschools.com; angeltarpleV(d_)gmail.com; arletys1996(a_yahoo.com; bat pkrfan(ogmail.com; corkeybandit(d_)gmail.com; causerie(d)aol.com; larrybiela15(cDgmail.com; wmenaples(@gmail.com; bill.gramer(@Jacobs.com; billnl353(@aol.com; poteetproperties(cDgmail.com; billq(cDgatorinv.com; nfn23440(cDnaples.net; awp- plastering(aDcomcast.net; bleegruninger(cDcomcast.net; Bcornell(a-audubonWE.org; info.tropicalenvironmentalconsultants.com; lebrooks(a)belIsouth. net; rbanderson(a)napleslaw.com; ccuevasiano(o-)yahoo.com; carmene.cyprien .yahoo.com; chazpot .aol.com; cwilliams7417(cDyahoo.com; csimone77(cDgnail.com; Chris(c�haganeng.com; cindV(c�carrollandcarroll.com; onehundredpercentrealtV(a)gmail.com; 07bettinger(cDgmail.com; codie186a corncast.net; mcurrier(o)govmserv.com; dan.oberski(cDtrinitycre.com; gdanyocean(a_aol.com; Dhartley(c)pen-eng.com; dwhyte(a_gatorinvestments.com; dhunt.winterisle(cDgmail.com; Werra mCcDaol.com; david. engeIhart(cDcomcast. net; dchml(aD_aol.com; deb12753(a-)_aol.com; dkribbs5(d_)aol.com; Pattesvond2(o-)_gmail.com; do3stalzer(cDgmail.com; doteyberg(d_)gmail.com; edwamcel(d)aol.com; eglisi1972(a)icloud.com; egch1105(cDhotmail.com; emrevhs(cDvahoo.com; e2dream homes(cDgmail. com; netiennetcDlutgertinsurance.com; rgordillo(cDoutlook.com; ezdreamhomes(cDgmail.com; felipe.arcila(cDsvn.com; dorongto(cDvahoo.com; beamoon3(cDgmail.com; fred .davidsonengineering.com; fred.kermani(o-)creconsultants.com; glopez1916(cDgmail.com; gfxbeyrent .aol.com; gaylenevasaturo(a)sbcgolbal. net; grape4486(6ahoo.com; dhiranlambert(o-)gmail.com; jrhuttner .gmail.com; cardosoirene(5)yahoo.com; jackkennedy4(jj)gmail.com; roehand0826(a)gmail.com; Jabaio(c comcast.net; wjklugiii(cDyahoo.com; laxpomales(a�comcast.et; pricer(a�aol.com; 'en na(anapleschamber.org; jbreining03(c�msn.com; jericobb(c�iohnvwood.com; Jessica.ayerscrane(a sharecare.com; jesgettel78(aVahoo.com; jessica(c�davidsonengineerinq.com; kazimour13(cDatt.net; beautreeclimber(cDaol.com; colettaJ(cD_Vahoo.com; Jamestduffy(a_comcast.net; Jrgmsu25(a_aol.com; Jopalev(d_)aol.com; WT4018(cDhotmail.com; Jodi.walborn(aD_sharecare.com; Josephgaccetta8102(@comcast.net; Tacojoe1(d_)aol.com; iron Joe3(cDaol.com; jdschmidt(a�sfwmd.gov; lindavap65(d)aol.com; JEnglish(cDbarroncollier.com; macdonaldjohnpatrick(cDgmail.com; a osh(cDdavidsonengineering.com; Joyca(cDbelIsouth. net; yislei.Jd(cDgmail.com; nester. jimanaz.rivero(cDgmail.com; jptd22(cD.hotmail.com; jcarlos2670(cDyahoo.com; uncledave650)yahoo.com; julielunch(a)gmail.com; justinmessierCcDgmail.com; karenbishop(5)pmsnaples.com; drkmthorpeCcDgmail.com; theseekerheheCcDaol.com; lances22CcDgmail.com; swdouble11(cDaol.com; IdeJohn(c�Johnsoneng.com; lenberlinC@comcast.net; lenorawalter(cDvahoo.com; dhark 10172(c�aol.com; LindsaV.Rodriguez(awaldropengineering.com; Ikoehler(a sfwmd.gov; dlizette6a govmserv.com; Ifh1016(a�aol.com; loredanazambon(a�Vahoo.com; luismedinahome(d_)gmail.com; hotrdh(cDhotmail.com; mavibelearrillo9100(aD_gmail.com; marcoe(d_)prodigV.net; dayelin18(aD_Vahoo.com; elietcamejo(a_Vahoo.com; monicaeche73(a_yahoo.com; mariocaro1969(a_gmail.com; trandbel(a_aol.com; matt(aD_pikusproperties.com; cmcmahon(cDgnfire.org; megan.greer(a_sharecare.com; megan.mills(cDdep.states.fl.us; melkaufman3(@gmail.com; mbstefanos(aD-comcast.net; michael(cDnapleschamber.org; michelle(cDnaplespathways.org; cepear(cDlive.com; marouey(cDpga.com; milvduez(cDaol.com; deb.millsap(cDhealthways.com; ruagardener2(d)-outlook.com; mvalle .pbscontractors.com; nancypayton(cDfwfonline.org; nevillewilliams(a)comcast.net; nkouloheras anhabitatcollier.org; nicolejCa.conservancy.org; noel rod rig uez33 .gmai1.com; noralvarez00(5)hotmail.com; nolvislg77 .yahoo.com; orlandolopez1168(cD-gmail.com; gospencer(cDvahoo.com; pos516(cDcomcast.net; patti.gpi(agmail.com; cathyallen19(@comcast.net; stanleydykes(cDgmail.com; echevepa(cilcollierschools.com; pia.naples(a�hotmail.com; prisiladrl804(a)gmail.com; bobmattix(aearthlink.net; Igorrostieta(c Vahoo.com; royalpalmlawn(a)aol.com; rayoriorden(a-)comcast.net; rreaburn(cDgmail.com; Janellegillum(d_)gmail.com; bud(a_budsignshop.com; mightpa60(d_)yahoo.com; Rsinger(cDnaplesgov.com; dam iana99(aD_msn.com; RJefferson(aMlynaples.com; Kribbz42(d)aol.com; ren i nvest(d)comcast. net; reospdwgn42(cDyahoo.com; herewegrowofnaples(cDvahoo.com; trandbec(@aol.com; russelI(cDsocial-impact. com; ruth.rich 127(cDgmail.com; ruthlaube(d)aol.com; rwever(cDree-i.com; scott.hudson(cDtrinitycre.com; sromos1296CUMotmail.com; secretaryCcDgoldengateisgreat.com; seelgen41 gmail.com; 2238 _colliersheriff.org; palace8mama(c)gmail.com; sharrybee _yahoo.com; scbarnett1(cDearthlink.net; stephaniebutlerswfl(c)gmail.com; Leystephen13C@yahoo.com; buckeye(c�aol.com; suebgranny(c�aol.com; pastorgeorgesluckner(c-)yahoo.com; teddyfairfax(a-)comcast. net; dannyterrero(c�gmail.com; tfernandez(�planningdevelopmentinc.com; Tim. Hancock(a)stantec.com; tim.steeves(a�dep.state.fl.us; tinalom(a-)_netscape.com; toddmathes(cD_benderson.com; TL-MAIL(a_gmail.com; b101535941(aDgmail.com; val.hofmann(a_yahoo.com; cvarga(a)naplesgov.com; vsmithco)_naplesgov.com; viviana brnal(cD_hotmail.com; PWhite(a-)_porterwright.com; wmenaples(a-)_yahoo.com; clapton135(a_ch.com; wmfsmith1(aOmail.com; cdsi2010(a�yahoo.com; Yenilee0224CcDgmail.com; mercyt9496(a)gmail.com; garciairina78(a_yahoo.com; zfsmith212gmail.com; zulinar yahoo.com; zullvruizCcDbellsouth.net Felicia. Kirbv26�jacobs.com; sonal.dodia(a)jacobs.com; colleen. ross(o-)jacobs.com CC: Jay.Ahmad(a)colliercountyfl.gov; Bee.Thao(a�colliercountyfl.gov; Trinity.Scott(a)colliercountyfl.gov; maryio.brock(a)colliercountyfl.gov; Connie. Deane(acolliercountyfl.gov; Marlene.Messam(D-colliercountyfl.gov From: LantzLorraine Subject: [EXTERNAL] Collier Boulevard Widening Project 60 Percent Design Plans and Collier Boulevard Bridge Location Study Date: Tuesday, March 22, 2022 3:10:00 PM Attachments: Collier Blvd Widenina - Public Information Meetina Newsletter.odf Dear Interested Party We are contacting you due to your prior involvement with another study in the vicinity of this project. Collier County will hold a public information meeting for the Collier Boulevard Widening Project 60 Percent Design Plans and Collier Boulevard Bridge Location Study. The public meeting will be held on Wednesday, April 6, 2022, from 5 p.m. to 7 p.m. at the Golden Gate Community Center, 4701 Golden Gate Parkway, Naples, FL 34116. The meeting will be conducted in an informal, open house setting with no formal presentation. Attendees may review the project displays and talk one-on-one with the project team regarding any questions. The purpose of this meeting is to provide the public with an opportunity to review and comment on the Collier Boulevard Project 60 Percent Design Plans and the Collier Boulevard Bridge Location Study alternatives. Attached is the public information meeting newsletter, which includes a location map for the meeting, project limits and other important information. This newsletter is being sent to all property owners located within 500 feet of the project limits, as well as other public officials, agencies, and other interested parties. As an alternative to attending the meeting in person, the meeting displays and handouts will be posted on the county's website at www.coIIiercountyf1.gov/transportationprojects (under "Projects in Design") beginning April 6, 2022. Your input is very important, and we encourage you to share your comments. Comment forms will be available at the public information meeting as well as on the county website. The public comment period will end April 20, 2022. Collier County looks forward to keeping you informed as we progress through this project. If you have any comments or questions, please contact us by phone or email at: Collier Boulevard Widening Project Bee Thao, P.E., Senior Project Manager, Collier County Transportation Engineering Division Phone (239) 252-5844 Bee.Thao&colliercountyFL.gov Collier Boulevard Bridge Location Study Project Lorraine Lantz, AICP, Principal Planner, Collier County Transportation Management Services Department Phone (239) 252-5779 Lorraine. Lantzg_colliercountyFL.gov Respectfully, Lorraine M. Lantz, AICP Principal Planner Lorraine M. Lantz, AICP Principal Planner C;Qtle-r C;074ftty Collier County Capital Projects, Planning, Impact Fees & Program Management NOTE: Email Address Has Changed 2685 S. Horseshoe Drive, Suite #103 Naples, FL 34104 Phone: (239) 252-5779 Lorraine.LantzgCollierCountyFL.gov Under Florida Law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by telephone or in writing. Mailing Lists E y y E -6 0 0 E E y E E y E E E E y y E E E E y y E E E E y y E E y E 0 -- 0 o -- -- a a -- -- -- -- -- y . . . . . . . . E E 6 6 E E E E E 6 y y E E E i3 B B E E E E E E IE o ZE E E E E E E E E E g E E E E 0 9 9 o 0 & E E E o o 2 2 2F g E "6 E o .2 .2 .2 0 o 0 o 0 . .. .. . . . . . . 0 -0 -0 -0 0 . . . . . . . . . . 2 E . . . . . . . . . . . . . . . . . . . . E Z Z Z . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . E . E E E E E E E E E E E E E E E E E E E E E E E E E a . E . . . . . . . . . E 5 o 15 o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o A 0 1 o o o E E 0 0 0 E E E E E E o E o E 2 E 2 E 2 E E o E o E E 02 2 2 1 o 2 2 2 2 2 2 2 02 2 2 2 o E o 2 o 12 0 o 2 2 2 02 2 2 I 0 2 2 o 2 E m o 6 Ea E' 0 2 E 0 0 o E� E g g E� E 8 8 1�1 �j �j MR 0 E 50 0 0 o S 8 Z W 2 0 0 2 o o - o 0 0 2 o o 2 2 2 2 .0 o o I-o -0 S t t k V 6 c '? - _0 g 'E E :E 0 0 0 0 m 5 E g 0 E E E E E -0 .E E E 0 "0 o C t t t . t . t . t . t . t . t E o E E E E oE ` I 10 - - - - - - o - - o o - o o 2 2 0. R R R R R 10 o E .2 .2 2 aL 6 6 6 6 -o '6 'o o .0 2 2 C� K C� o I o o o o o 0 E 9 E E E E E E E K E I E E E E E E E E 0 E E E E E E E 0 'o z E 0 E E E E E E E E E E t E 0 0 R E E E E E oE oE oE E E oE oE o E E oE I oE oE I oE oE E o . o o . . o' o' oE oE oE oE E ml o E E a a a K a 0 E E E I EEEE IE ... . . . . 0 lo 0 - - - - 0 E 0 9 E E . . . F 'E 0 o E E 2 o' 2 E 2 0 0 0 0 0 0 0 2 2 2 2 2 o 2 E E E 0 o o o E Z Z Z Z Z m E E E E E E E 2 2 2 8 2 -0 . . . . . . . . . . . . . 8� L9 E E .0 A A A A o A L9, A A A A A A 0 - - - - - - - 0 'o 0 RR2 o 3 3 33 3 3 3 a 8 8 8 8 8 i 8 I I I 1 8 3 3 1 3 3 3 A 3 3 3 3 a a a a a 5 0 sass 2 2 .w 0 t t It 'a �q 4 E 0 o 0 c E E .0 12 2 .2 .2 .2 .2 .2 .2 .2 'o '0 E d 0 o o .0 '32 E , , E E t 0 k o. 0 o .0 .0 .0 . . 2 . . . . 2 . us g aka 10 o El 0 0 10 o c .0 o E 0 o 0 E Z 0 �5 E 0 E E , ig F -0 ij, q ai g A I- A q . I I 5 . n . 9 L . -2 I 0 . . . f f) o ! !!!!Z !>! )))ii 2 2.M ! \�} }}}}} - :_!! rrrrr - 1.1.> ;)\}] . \ \\\\\ \\}\\}}��\ \\\\\ 0. ( }}}}} E! A A A A f ='3 o')) ( /!o \ }}}}} \\\\j\\\\ \ \}\{} ' )))))\\}/\}\!\ ) }}}}\ )}\\ }\\ \ }\}\0 i !!/If !$}); 2J! 0 2 {1 ) f!!/] !2)3! !]! ! !!!f Name A Last Name Sibson AddressFirst Email btrsweet2@verizon.net A. and E. Kennedy ANBEKE@vahoo.com Adriana Acosta acosta-adriana@hotmail.com Al Granovsky agrano@bellsouth.net Alan Laeffer Tnis76@gmail.com Alice Duffy duffyal8@gmail.com Alicea Grucia alicia34120@yahoo.com Amy Taylor Lockhart lockha@collierschools.com Angel Tarpley angeltarplev@gmail.com Arnaldo Gome arletys1996@yahoo.com Barb Anderson balpkrfan@gmail.com Betty Fabian corkeybandit@gmail.com Beverly Maranto causerie@aol.com Larry Biela larrybielal5@gmail.com Bill Arthur wmenaples@gmail.com Bill Gramer bill.gramer@lacobs.com Bill Nlutting billnl353@aol.com Bill Poteet poteetproperties@gmail.com bills@gatorinv.com Bob and Joyc( Curlew nfn23440@naples.net Bob Williams awp-plastering@comcast.net Bobby Lee Davenport bleegruninger@comcast.net Brad Cornell Bcornell@audubonWE.org Brooke Hollander info@tropicalenvironmentalconsultants. com Larry Brooks lebrooks@bellsouth.net Bruce Anderson rbanderson@napleslaw.com Carlos Cuevas ccuevasiano@yahoo.com Carmene Cyprien carmene.cyprien@vahoo.com Charles Potzka chazpot@aol.com Cheryl Williams cwilliams7417@yahoo.com Chris Simone csimone77@gnail.com Christopher Hagan Chris@haganeng.com Cindy Carroll cindv@carrollandcarroll.com Clark Pear onehundredpercentrealtv@gmail.com Connie Bettinger 07bettinger@gmail.com Connie JoDimond codiel8@comcast.net Mike Currier mcurrier@govmserv.com Dan O'berski dan.oberski@trinitycre.com Daniel Garcia gdanvocean@aol.com Daniel Hartley Dhartley@pen-eng.com Daniel Whyte dwhyte@gatorinvestments.com Dave Hunt Hunt dhunt.winterisle@gmail.com Dave Marren Werram@aol.com David Engelhart david.engelhart@comcast.net David Harvey dchml aoLcom Debbie Imorclowanel Idebl2753@aol.com Debra jKribbs Denise H Pattesvond2@gmaiI.com Dennis Stalzar do3stalzer@gmail.com Dorothy Eyberg doteyberg@gmail.com Ed & Nancy McElaney edwamcel@aol.com Eglis Morales eglisil972@icloud.com Elizabeth Guiterrez egchl105@hotmail.com Emilia Reyes emrevhs@vahoo.com Enrique Zabala e2dream homes mail.com Norma Etienne netienne@lutgertinsurance.com Evelyn Gordillo rordillo@outlook.com Evrique Z ezdreamhomes@gmail.com Felipe Arcilla felipe.arcila@svn.com Ron and Fewkes dorongto@yahoo.com Frank Thorpe beamoon3@&mail.com Fred Hood fred@davidsonengineering.com Fred Kermani fred.kermani@creconsultants.com G. Rodreguez glopez1916@gmail.com Garrett Beyrent gfxbeyrent@aol.com Gaylene Vasaturo gaylenevasaturo@sbcgolbal.net Grace Pinedo grape4486@ahoo.com Hiran Lambert dhiranlambert@gmail.com John Huttner jrhuttner@gmail.com Irene and Jose Cardoso cardosoirene@yahoo.com Jack Kennedy jackkennedy4@gmail.com Roehand Jean Jaqus roehand0826@gmail.com James Baio aabaio@comcast.net James Klug wjklugiii@yahoo.com Jax Pomales jaxpomales@comcast.et Jeff and Tammy Price pricer@aol.com Jenna Buzzacco-Foer! jenna@napleschamber.or Jennifer Breining jbreinin03@msn.com Jeri Cobb jericobb@johnvwood.com Jessica Ayerscrane jessica.ayerscrane@sharecare.com Jessica Gettel jesgettel78@yahoo.com Jessica Harrelson Jessica@davidsonengineering.com Jim and Theresa Kazimour kazimourl3@att.net Jim Beauchamp beautreeclimber@aol.com Jim Coletta colettaj@yahoo.com Jim Duffy jamestduffy@comcast.net Jim Goulding Jrgmsu25@aol.com Joanne and Alan Audet jopalev@aol.com Joanne Doran WT4018@hotmail.com Jodi Walborn odi.walborn sharecare.com Joe and Carolyn Gaccetta a osephgaccetta8102@comcast.net Joe Arciere Tacojoel@aol.com Joe Bonness iron'oe3 aol.com Joe Schmidt dschmidt sfwmd. ov John and Linda lindavap65@aol.com John English JEnglish barroncollier.com John Mcdonald macdonaldiohnpatrick@gmail.com Josh Fruth josh@davidsonengineering.com Joyce Abernathy o ca bellsouth.net Juan Dominguez islei.'d mail.com Juan Jimenez nester. iimanaz.rivero@gmail.com Juan Pablo Torrez ptd22@hotmail.com Juan Thamos carlos2670@Vahoo.com Juanetta Collins uncledave65@yahoo.com Julie Lyn G ulielunch@gmail.com Justin Messier ustinmessier@gmail.com Karen Bishop karenbishop@pmsnaples.com Karen M Thorpe drkmthorpe@gmail.com La Sugarman theseekerhehe@aol.com Lance Shearer lances22@gmail.com Larry Lawrence swdoublell@aol.com Laura DeJohn Ide'ohn 'ohnsonen .com Len Berlin lenberlin@comcast.net Lenora Walter lenorawalter@yahoo.com Linda Harkness dhark10172@aol.com Lindsay Rodriguez Lindsa .Rodri uez waIdro en ineerin . Lisa Koehler Ikoehler@sfwmd.gov Donna Lizzette dlizette@govmserv.com Lloyd and Linda Hill Ifh1016@aol.com Loredana Zambon loredanazambon@yahoo.com Luis Medina Iuismedinahome@gmail.com Cynthia MacDonald hotrdh@hotmail.com Manibel Carrillo mavibelearrillo9100@gmail.com Marcoe marcoe@prodily.net Maria Lopez dayelinl8@yahoo.com Maria Luisa Lopez elietcameio@yahoo.com Maria Puintero monicaeche73@yahoo.com Mario Martinez Caro mariocaro1969@gmail.com Marvin Rareir trandbel@aol.com Matt Pikus matt@ pikusproperties.com Chuck McMahon cmcmahon@gnfire.org Megan Greer megan.greer@sharecare.com Megan Mills megan.mills@dep.states.f1.us Mel Kaufman melkaufman3@gmail.com Michael and Stefanos mbstefanos@comcast.net Michael Dalby michael@napleschamber.org Michelle Avola michelle@naplespathways.org Michelle Pearman cepear@live.com Mike Arouey marouey@pga.com Mileycly Dominguez milyduez@aol.com Deb Millsap deb.millsap@healthways.com MJ Cary ruagardener2@outlook.com mvalle@pbscontractors.com Nancy Payton nancypayton@fwfonline.org Neville Williams nevillewilliams@comcast.net Nick Kouloheras nkouloheras@habitatcollier.org Nicole Johnson nicolel@conservancy.org Noel Rodriguez noelrodriguez33@gmaiI.com Nora Alvarez noralvarez00@hotmail.com Norvis Lovaina nolvislg77@yahoo.com Orlando Lopez orlandolopez1168@gmail.com Pat Spencer gospencer@yahoo.com Patrick Posney pos516@comcast.net Patti Muzzonigo patti.gpi@gmail.com Paul and Allen cathyallenl9@comcast.net Paul Dykes stanleydykes@gmail.com Paulo Echeverri echevepa@collierschools.com Pia Carrasco pia.naples@hotmail.com Prisilla Gutierrez prisiladr1804@gmail.com R.C. Mattix bobmattix@earthlink.net Rafael Tvera Igorrostieta@yahoo.com Ray Cleary Jr. royalpalmlawn@aol.com Ray Oriorden rayoriorden@comcast.net Robert Reaburn rreaburn@gmail.com Rick and Janelle Gillum janellegillum@gmail.com Robert Perkins bud@budsignshop.com Robert Stedman mightpa60@vahoo.com Robin Singer Rsinger@naplesgov.com Rolando Marrezo damiana99@msn.com Ron Jefferson Rlefferson@flynaples.com Ron Kribbs Kribbz42@aol.com Ronald DePiro reninvest@comcast.net Ronald Orthib reospdwgn42@yahoo.com Roylan and Reyes herewegrowofnaples@yahoo.com Marvin Rubett trandbec@aol.com Russell Tuff russell@social-impact.com Ruth & Ron Rich ruth.rich127@gmaiI.com Ruth Laube ruthlaube@aol.com rweyer@ree-i.com Scott Hudson scott.hudson@trinitVcre.com Sebastian Romos sromosl296@hotmail.com Secretary secretary@goldengateisgreat.com Clayton Seelgen seelgen4l@gmail.com Sgt. B. Williams 2238@colliersheriff.org Shari Palacious palace8mama@gmail.com Sharry Brewer sharrybee@y2hoo.com Sheri & R.S. Barnett scbarnettl@earthlink.net Stephanie Butler stephaniebutlerswfl@gmail.com Steve Ley Leystephenl3@yahoo.com Steve Neff buckeye@aol.com Susan Thomas suebgranny@aol.com Georges Luckner Sylla pastorgeorgesluckner@yahoo.com Ted Fairfax teddVfairfax@comcast.net Daniel Terrero dannyterrero@gmail.com Terri Fernandez tfernandez@planningdevelopmentinc.co m Tim Hancock Tim. Hancock@stantec.com Tim Steeves tim.steeves@dep.state.fl.us Tina Tober tinalo' netsca e.com Todd Mathes toddmathes@benderson.com Tonya Loreman TL-MAIL@gmail.com tzu chi hsu b101535941@gmail.com Valerie Hofman val.hofmann@yahoo.com Cecilia Varga cvarga@naplesgov.com Vicki Smith vsmithCcDnaplesgov.com Viviana viviana brnal@hotmail.com Patrick G. White PWhite@porterwright.com William Arthur wmenaples@vahoo.com William Combs claptonl35@ch.com William Smith wmfsmithl@gmail.com David A. and Wright cdsi2010@yahoo.com Yenilee Yenilee0224@gmail.com yesenia caballeru mercyt9496@gmail.com Yoela Vega garciairina78@yahoo.com Zachary Smith zfsmith2l2@gmail.com Zulina Riveron zulinar@yahoo.com Zully lRuiz IzullVruiz@bellsouth.net Interested Parties GG Complete Streets Total Emails Sent = 21E Property Owner Database Map VA a!IIo- un r N N Property Owner Mailing List r 0 0 N O M r r M p n E 0 d v` a m m c� Na cormmmm�o�om��or: oR oR n Ro 20 :_e_<or_�cr1�2�2r_ cg`r��1`21` row'2�2<2�`rv`r1��g`r��n<o�co�c2V�2�c��2�2�2�2 ��commm�4 � �No� -low j v v ov a a a M a v v v m v v v v v rn e e e e v v v v v v a a a a a o a a r= a a a voi a uNi a a a a a a a v v v v v coi v v v v m N lh lh lh lh M M M M M M W aJ J J J J J J J J Q J J J J J J J J J J J J J J J J J J O J J J J J a J J J J J J S J J J J J J J J p J J p J J JI� J Q J J J Q J J J a J J J J J J J J J J J F LL LL LL LL LL LL LL LL LL> LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL� LL LL LL LL LL a LL LL LL LL LL LL O LL LL LL LL LL LL LL LL� LL LL [n LL LL LL Q LL a LL LL LL> LL LL LL U LL LL LL LL LL LL LL LL LL LL LL Hl O F (� Z Z Q m Of Ww J W W J Q In <Z wwwwwwww_owwwwawwwwwwww�wwwwawwwwwpwwwwww=wwwwww�w>ww wwwzw�wwwowwwowwwwwawwww_ Z J J J J= J J J J J J J J 'w J J J 2 g O J Q J Y J J J J J W J Z J J J Z J J J Q J J J a J J 2 a as JaJaJa Ja Ja Q¢aaaazaaaaaaaa�aaaaUaaaaa aaaaaa2aaaaa Ja g a Uaa aaaoa aaaaaaamaaaaagaaaa zzzzzzzz �zzzzmzzzzzzzzOzzzz�zzzzzazzzzzz¢zzzzzz�z�zzinzzzaz zzzwzzzazzzzz�zzzzm 0 N N O M 7 > U ZO v W w o m w p J J J J m Z Z> p > Q a U> W w S. > O W>> W J Z W O w K 2 2 2- w K Q K N Q W W W W N O K= W a' W W 02 Y N N N N 2 r W (Y N y J In J J J Z F F w Q�C J m m F N Q J Q q O Q m a fn J F a f J m a J H Z H m m m m H Z OLU ~ J J a F J a J m x W Q m N J Z W m F O W H !n J f Q m J m f a J m F OJ x O O O y F H H H o K o H J H H H 0 H J f f p o m m O H 2 H M M M M H a r H o o H H w H W W f; M o o w w- c w e 0 OU O _ro _M OO ' O N OU W U H U U U o o U m o K M U M Q M rn o rn 2 0 2 In o- U rn rn U' 0 0 o rn rn rn rn o- o U U r_ o Q 0 0 0 m a m X U a K LLLL> r r N N O M r Z O N M N n M lA O r W N O O M m W O O N m 0 0 0 0 0. m O r N N 0 0 0 (m0 O O N N O m 0> 0 0 0 OJ O O O m N r m 0 0> lA M 0 0 W O N O N V M W r N N N N (D M O N (D N W O N r O O r 0 OD OD V (O 0p M Yl M V fyyp fp fp O W V N O W W V W M r W O m M N O O N N r Op M N In V a M V O� N l0 N Q N N O M mw O t2 O � � M 1. �� M�--- N N t N� � M-- — V M N a � M M N� N N � M a y � � T� ,H H H H H H H H H H H H H H H H H H H H H H H H H H f f f f f f f H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H f f f f f f f H H H zzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzz W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W N p p 0 0 0 0 p p p p p p p p p p p p p p p p p p p p p p p p p p p p p p p p p p p p p p p p O 0 0 p p p p p p p p p p p p p p p p p p p p p p p p p p p p p p Wlnlnln/nlnlnlnlnlnlnlnfnfnfnfnwwww NNNNNNww w w w w w w w w w fNfAf/1f w w w w N N wwwwwwNMMMMNNNNNNNNNNNNNw w w w w w NNN � W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W 2 H H H H H H H H H H H H H H H H H H H H H H H H H H f f f f f f f H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H f f f H H H IZ Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z z z z z z z z z z z z z z z z z z z z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z z z Z Z W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W Of 2 w w w w w w w w w w w w w w w w w w w K K K K K K K K K K K K K K K K K K K K K K K K of w w w w K w w w w w w w w w K K K K K K K K K K K K K K K K K K K KKKKKKKKKKKKKKKKKKKKKKKKKKK "of"of"ofK K K K K� K a' a' a' a' a' a' a' a' a' KKKKKKKKKKKKKKKKKKKKKKwK K K K 'orK K K a' a' U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U KKKKKKKKKKKKKKKKK KKKKKKK�� a' a' a' a' a' a' a' a' a' a' m m m KKKKKKKKK KKKKKKKKKKK x x x x m m x w w w 00000000000000000 0000000000000000000000000 00000000000 00000000000 0000000000 ww FF as In /n ww as WW 22 00 ww z z p Q 2 2 K W W a W W K Q < O U a W W W U > F w Q 0LU H F J m p U U 0 0 J ^�� ZQ zzaa w12 p QQww 0 �mrn OLL OLL Z N a a to OO w W NNW W z gyp�(( gy LU p�(( w t¢ a(Yx LL'LL' J 7 co 7 Q Np� p Np�� 2� OJ O O D U¢ W Q Q Z U Z Z O O Z Q U U a a Q J J /A xx p F g p p z z 2¢ w w 2 W Z ~~ m J J O Y Y�� W W O Q Y Y O U w w z LOU J J 2 F F __ Z Y Y¢ QQ Z Z W W >_ m m ~ zpp JUU pp j jU i5 i�Ua a. a. �. �. i� ¢ LL � � Q J J W_ a'a' W W 22> JJOOZ Z_U xQNQ QNQ f H w 0991, Z W z z w w Q J O O w W p U U 2 '. a s a w N Z Z p U U �� i w w� 2 2 J W J Z W W O 9 Y Y ¢ Q J J U U U Z fn fn W W J J J O O- 2 2 a U 2 z W W w z z> S J a U U W W fn K m W F F m a¢ J J ❑ p p p p J J J a' a' W W Z W N W Q Q N N Z J J Z Z W O W >> fn M a W w w m' ���(� wa' W W W 3 W ��� Q Q a a g- a 0 Z Z z z qa Y Y a ¢ w a a¢ v�v� w w U U W W p p a w z z O J J mmmmmNfnfn`naaJJJ w.a V<o 2(/lO¢¢QQ ly 66f J J J--Q z p a ao Z @2Sw.ss-"a W JJOOQ W a FFZ a' N w w w F F J J >> 0 0 J z uoggttN p m J J w O a a a a a 0 0 W W W W W UUUd00 Ca'1Ur Ur www;zo li W Z»�� O W W a OoOOpK W O W W O J J"QQ ��YYUQUUfU/lO� W j W W W a'J NNZ Z S S Np J-->> U- Z Z O N N O Opp a' J O O O O O a a a w w N m rn 4 W Q Q Q a J J W>> U Q J J O O O Q U w w z¢ Q a a x x a a Z Z� a a a U U p z� 0 0¢ 0 U p a Z z 0 0 0000 U U U U U F F F W 2 2 O O W W °� w Z Z N Q Q Q O O a Y Y z x cc ou > z > z W W U W tq Oa' W Q Q 4lt/l K K w w w w_ ' a a i' S S qa qa a a o z z ui a a a w 3 3 W W W W d d Nr N N H H H J » K K K Z U U F O » m m a'rn N Q O O K m m W W J J J J H N N J> Z Z LL LL J p N 0 0} U U O O o m m � J K K �N...000.. a<Mmzzwwwwwawww WWAN 000aaaaaax 333000000x aammwwwW---oXXWJ0000aaaa Q Q Q Q Q Q Q Q Q Q Q Q a m m m m m m m m m m m m m U U U U U U U U U U U U U U U U U U U p p p p p p p p p Q Q p p p w w LL LL LL LL LL o U' U' U' U' p ............. O O ...... O ......... O .... O O O O. lOp O N N O O N N ...N..—... O O ..... O O O O O ...... 22O O J r 0 ............................0 0 0 0 0 0 0 O O O O O O O O O O O O O ...........................0 0 0 W O O O N W W W N N W W W O O .. fD N O O W (D (D O O OD OD O OD W V N N N (D (D (O 0p 0p 0p O O O m N N O O O O O O y O fp fD W N O O O O N V O W W V W W V V (O (O V V O O O V U b W N N n n r W W M M n n M M rn n rn ro ro p o y 0 o ro ro y r O O M y� lD y� N ......... N r O O N N O O t0 N M M M M N M N M M p O O O N ....... ..000O M r r r r M M r r r O e. r r m O W W M M I O O N M, O r M M M M M N r r O M M N r r W r M M W W M M lA r dJ ........11 ......... N N N N .. N N r N r N N W W N N N r W N N N N w w n W h fo0 fo0 N n n...... I.. W w ... h W h h N N W N N In N N N In In r r OD N N M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M N N M 10 f0 M M r r M M M M M M M M M M M M M M M M M M M M M M M M M tp tp M M a N O O O O O O m O n o r M r n r N r ❑ ❑ . N ❑ a E E E 5 0 0 � a E E E 2 v v m a` v` a a a m m m � � N O � — O — � n LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL Z LL LL LL LL 0 LL LL LL LL LL Z l l l l l l l l l l l l l I LL LL LL LL LL LL LL LL LL LL LL LL LL LL a LL LL U LL U LL LL LL LL LL LL LL LL LL LL LL LL❑ lJL lJL m 0 z W Z � J H w LL W W W W W W W W W W W W W W W W W W W Q W W W W Z W W W W W Y W W W W W W W W W W W W W W W W m W W W W W W W W W W W J w w Q w J w w w w w w W W a W a W M W W LL J J J J O J J a J> J J J J J J J O J= Q LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL N LL LL LL LL LL U LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL qLL a a a a a a a a a a a a a z LL z LL LL LL LL LL LL LL a w LL z a 3 a a Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z m Z Z Z Z� Z Z Z Z Z x Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z w Z Z Z Z Z Z Z Z Z Z Z OU Z Z w Z M Z Z Z Z Z Z Z Z � Z Om Z Z Z Z r m M N N H Z Z In ❑ ❑ 2 � K O W a O M 0 w ❑ N Q F C7 K W Q U z❑ O y w W Z Q J ❑ 0 ❑ w ❑ 2i J w O W J Z ❑ ❑ j ❑ ❑ ❑_ = ❑ H ❑ ❑ } 3 333J3o3 3 3 3>} 3 wo w3J3?�mm 333 3 3�3�3w33333333'n3 a �: 3: 3: rnLLN�mOY��w0U)u�3m3�mfnm Jmfnmrnmmmm}mmFm>i�3wmmmmmmmm 3c�mz3J w��ww>�w=w�>����w�wamWw�❑Fww�wzw2g��zwww�>�gw>wpwjw>wwwwawwWw�Q�Qwwwwwwww �Z!�ir S x S S S S LL x w S S S S w x x x x 3 a¢ x w x x o x J 0 x x t° x x x x❑ x¢ J❑ J❑ J S S❑ J x x x x x x (/J J S F 2❑ S S J S S S 2 2 2 LL J Z S Z o �moom�oQom�marnrnorn OU gz❑UU.¢rnmo�og OU OxarnH000aNaQ OU MOU Z OU moNOU o o o Qoox OU rnw rnwoo OU 00000�rnw OU�rn❑ M N Q m M N M U� M M O M N w N Z �i M M O O O V M M M H N N O a O N M rn O V V V H N M>> M O O N O O O O V yy M f MOM 2 Or O O rn N O O m 0 0 0 0 n 0 ❑ n N N O O rn rn N NMN., O O N N 0 0 0 0 N N ifl N m N M m N N m N N N N 0> O N N O N O O N M O O N F O m M V rn M M N M V rn M rn rn M N O N N m rn rn n m u> M 0 N m N M rn r V m m m M O m rn rn m O N M V m r m m o v m n v o m M N V m N N N N O N O m H H H H H H H H H H H H H H H H H H H H H H H H f f f f f f f H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H f f f f f f f H H z Z Z Z Z z Z Z Z z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z z z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z z z Z Z z z z z z z z z z Z Z Z Z Z z z z z z z z z z z z z z W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W O O O ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ O O O O O O O O O O O O O O O O O O O O O O O O O ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ O ❑ ❑ ❑ O ❑ ❑ ❑ ❑ lnlnlnlnlnlnln fn fn fnm mfn fO fO fOmmmmmmmmmmmmmmmmmmmvi vi vi vi fq fn fn f9 U U rnNrnNNNNNNf�f�f�f�NNNNNrnrnrnrnrnrnrnNNNNNNNNNN K KKKKKKKKKKKKKKKKKKKKKKK LL' LL' LL' LL' LL' LL' LL' LL' LL' LL' LL' LL' LL' LL' LL' LL' LL' LL' LL' LL' LL' LL'KKKKKKKKKKKKK K K K w w w w w K K K K K K K K K K K K K Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z K KKKKKKKK K w w w w w w w w w w w w w w LL' LL' LL' LL' LL' 0: LL' LL' LL' LL' LL' 0: 0: 0: 0: 0: 0: 0: w LLLL w w w w K K w w K K K K K K K K K w w w w w K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K 0_ K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K x x K U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0'02 0 02 0 02 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0202 0 0 0 LL LL o 00000000000000000000000000000000000000000000000000000000000000000000000000000000 M� rnrn Of of ww mm ?z 00 0 22 zz o ¢¢ QQ w N 0 0 Q Q U U W0 0 0 w > K K wF N �� w LU ❑ 00 00 2 ❑ ❑ t4N W W> 0 ZQ JJ N U Q Q 0 0 J J w Z K 22 Z Z z N W W w a H H W 0 0 w w w J J J J CO 2 w J J LL W U 00 W W (900 Z Z Z >> y W W 2 zwx ww �0� a Mr� o0 00o ww 00 x Omm a J aNw ww JJ0 (D xQ a LLLL as 333 mof o: w 00 w W Z O K K W J W 8 2 U U -- LL Z ZZZ z K w U U w x Y Y Y Q Q Q W W m H H a S W K w~ W W W W W— Q Q 0 Z Z }} K K K U w U N } > LL O Q Y Y N N> J W W W W❑ a00 2 2 O U U Q Q Q Q N J J w K UJ W W U 0= 77 W mm Z_Z_ a'S W oiS �UU a s m UUOD_ D:U Z Z LL. LL. Q � W H H W_ W LL. LL. gJJ w ❑❑ O a J Q¢ Q¢ Z Q J� z Z ❑ J a s O O H H 2 a 0 0 0 O ❑ 7 7 W Q Q Z Z Z J w LL LL Q Q J W U O a W a a Q } H O O N Z W U U LL LL J J Z x❑❑❑ O W K K K ~~ Z Z Q Q Q a Q Q 2 2 m m U J !n W Z— In W W Q O Q m Ha HQ Q J J U U J J J J J J O V J J J J O O W H H LL_ w w❑❑ Z Z 3 3 3 K W W U_ U Z Q Q Q H Hir } J Q U O W W W W F K W Z F K K w Q (/1 F W W J J} a a J J U U a a> N w Q W W Z O O❑❑ Z Z OR.- ❑❑ 0: O z z U a a 0 a W ��~FFFFwUK OOLL gFFNNO-x x J J J J LL' LL' LL LL w K K K K Z OZ U U Z D: LL'-- W W ZZHHz00f wH f (0)(.)w29 2 wW<wzaaaaz �z�� NyLLaa��= mNJJoozZ��3333�xozz'JLLLLFFJJ xxx �aaaaYd_wwww---- � O' M M- O O O O j w w O J O O w LLO O O M M O w w W W lJi lJi 3i 3:¢ = H K>> J J Q Q w w N N N W X X Y Y 7 m m 0 0 0 O D U J J W Q OU Q aaQWWWWN Zf:1000Z qLL mmQQNui xxo �wUwwwwz�ZZZ0a OOZZ 22 w w w w w Cw, 77WWJ of of OOXXUOZZZ N 000>❑000wggomWWLLZ�wNNWW00000-cWMHD.� zzzz��=zzUwzzaamm000000mmc3JJSS.LLFU:) ,U �``naoRoz <<< M O O,<<< w w S a a Z Z Q Q Q QQQQQ U LL M M Q Q Q Q Q Q Q Q 000 W ���o c°���000MMMMLLLL°x__°�°�>?>?»>$�YY33333335www o00033�333�3��� ������������ M m r M m O M M V rn O N N m m rn rn m N N N O V V m m V V r r N T T y ry V M M V M M r M N N m m r r V N M N r M rn rn h m m m m N N M M O V M M O O N m M O O ........................ . ....................... m m O ..................................................... O O m m O O ........................... O .... O 0 0 0 0 0 0 .......... O O 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O O O O O O O O O O O O N ICON �� AMMO ry�yy�yO NNrONtO00000000Mt0'l yO yOr r OO yO N.... AN N .... MM�� � �.......... W MMr000. OMM`R`° -N r m W N W V a a a a a n N N Oh N M M .. � n n anD anD anD anD OM1 OM1 N 001 t00 t00 W M N � 001 t00 m m n n n� M n W O W M.11 O n n m m o 0 0 0 0 o n o n m m m m ... n n O O O rn N n O N rn m m 0 r r n n rn rn n n 0 0 0 n n m m m O O m �n rn rn n n n O M OOm OOm OOP OmmmmmmNmNrnrnNNmmmin l(1 N In!)In!)IAmmmr m tD the mmr N N m In O M ........... mmmNNNrnrnrn- r NNNmN M M M M M M M M r M M M M M M M M M M N N M M M M M M M M M M M N N M M n n M n M M M M M M N M M M M M M M M M M M M M M M M M M M M N N m m M n M M M M M M M m omm nTm�N�o �oo�Tr�cr���c e�c �c� o�c cc �cN cc cc cc �cr r �cr �_ m� `r° o� o��o��mo�g�r<oTr�o�cr ��cN cc cc �cN cc �cr or � � �o �omn y_y �_ �_ per_p per_p p_p p_p p_p M yam_y yam_y y_y y_y y_y yam_y y_y y_y y_y yam_y yam_y yam_y yam_y yam_y yam_y yam_y yy y_ y y y y yy y_y y_y y_y �_ �_ �_ per_p p_p p_p p_p per_p yy y_y y_y y_y yam_y y_y y_y y_y yam_y yam_y y_y yam_y y_y y_y y_y yam_y yam_y �_ J J J J J J J J J J J S J J J J J J J J X J J J J J J J J J J J J J J J J J Q J J J J J J J Q J J J J J J J J J J J J J J J J J J J J J J J J J J J J J J J J J LL LL LL LL LL LL LL LL LL LL LL p LL LL LL LL LL LL LL LL r LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL> LL LL LL LL LL LL LL p LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL LL x W 0 J 0 m Z LL = = W Z U U Of U N Q Q y W W W W W W W LL W W W Z W W W W W W O W N W W W W W W W W W W W W W W W W W W W W W W W W m W m W W W W W W W W W W W W W W W W W W W W W W W W W W p W W W W K JJJOJJJJJJUJgJJJJJJJJJJJJJJJJJOJJ}JJJJ U'JOJJJJJJJJJJJ JJ O J J J JJ JJJJ J J J U J J JJ JaJaaJaJaJaJawaaaKaaaaaaKaJaaaaaaaaaaaaaaaaaaa aaaaZaKaaaaaaaaaaaaazaaaaaaaaaaaaKaaaa aaaQQQawQQaYaaaaaa¢aaaaaaaaaaaaaaaaaaaoaaQQQQOQwQQaaaaaaaaaaa-aaaaaaaaaaaa¢aaaa zzzzzzzOzzzQzzzzzz2zozzzzzzzzzzzzzzzzzazzWzzzzJz>zzzzzzzzzzzzZ§Zzzzzzzzzzzz2zzzz a o p N N w voi w z 0 Y W o ~>~ °> w> m a W Z j K z 3 J v~i w w K ai 3¢ K > W > J z m K W o�m3a3m Zmmw°'o�tiO3�mzm��?N3>a���m3m.33S3�oa my}m aw3a33N3m��m3a3000 m 3Jw3°00a3 >3w�>Ww Www�aa,wm�<wgw>~w°mzwwow�aw��Z�>wwww�azO����wza>zw�o�ow>wzW��°°g�w>wz� 0 K J S S a J Q J J Z OF O W x S F S a J w J O S a 2 3 W 0 2 S ozwa J 2 W 2 x 2 om O x° W S q�q J S H W O f/J m p m m F a W Q O J m p a N F a J F J N Oj W 4%lL ¢ F Q V% M U °U O r H O X F O O W�002 O x O °U O °U N O O K O o o w a O W W laL O~i N g O l °U O a a X O K 0 a a (n °U J O O O °U 2 O X T >� r m uNi CO T m M W N r T O M O 0 a- M m O O N 0 O T N O N O O M O O N W M M O m O a 0 0 0 O M O O M M 0 0 0 N n N N M m O a N O Z a M 0 0 fpTT V O NOJ�MNfD IDTMON�MNMMOMN TOE N� N(D� mNr n N TfONON N NOM V NfD V N(DT�O(D V coNn On N r MN N n NO T O IpNT NlONOp�N�NOJ OJN OJOMONM�OfDTT NOT (DTON N � TTn 000 ep � ��N��0000T O NT N� W �NcpNT W (O� � � N Opp �p ape MOTS T H H H H H H H H H H H H H H H H H H H H H H H H f f f f f f f H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H H f f f f f f f H H H H H H H H Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W O O O O m 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 m 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0❑ ln/n/nlglglqlqfqfqfqfqwwww NNNNNNNNNNNNNNNNNNNNNNN N N m m mlglglqwwwwmtllwwww NNNNNNNNNNNNNNNNNNNNNNN N W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U U K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K K 0 0 0 0 0 0 0 0 0000000000000000000000000000000000000000000000000000000000000000000000 00000000 z z O N W a W U U m ?? ¢ z 0 zz OODU o ' O m spa» p x x z O CY �� O OONN NZ U¢ W U a 0 J Z Z Q N Q Q m N N Q N O ww ��� UUaa Z Z J J W J J F F a a O ° fn N m m O Z Q U W W} J J K K O Z~ p O O J J O a S S Z O F U U N N ~~> W a Z K JK� » J QQ O O a a N 0 W W W W O O Z J J Z S S O O¢¢ K K a Lu } J to tnUO W W J J J 0,0,¢ S U JJ W Q Q Q W W a} 00 a' } W W z'QQN 0 J J �� J Jaa� fn fn pp W K K W❑ Q KKJ W >>(n (/la W W UUZ Z W ¢¢aa C�C�mZ >ZZQf�fn NNOO a ¢ Z F F J J O O J W W 0 0 J H H a 7 a H K N 2}} a W W W W Ka Ka W Z J J K K »> p Q Z y O D O O fn fn W Q U U 1. W W J O O >>_= K J J J Z Z Q a J J U Z Z J J 0 0 fn N Y W W O m W K K K K Jyou W W U U J J K K Z Z K JO KK WMM O w Q OOOO Z0J W OOWH W ozz ZZwaaLLwUaaNNppKaawKKa DUa:Z KK KKOO Z N0?KKO W a>a>K 0 aU oOZQQNaa¢¢aKK oo a aQQ>OOJ az z wwWz K W LC LC �� oow==zzoouu°O» KKKKKKK O N N 0 0 0 0 .... 11 00 0 0 0 ... O O O O O O ... 00 0 0 0 0 0 N N ..OO O O 0W �Q¢¢¢��¢o��33 m FZM>>>>>>>K O O N O O N N O O O O O O O O O O O O O O O O N N O O O O N N O 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 tp 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O O N W V V O fD fD N O O (D (D (D (D lD lD V O 0 0 OD O O V V V V V O O N O (D yNy O (O OD N OOO �MM i0[JMMMNONJ^^NMM W W �ONtppOO��r n ON N-m.... m N N r 0 W OJ fD W OJ T 0 0 ....... 0 W O O r r OMi W N N N N W W r r W W W O W W W W W O N M M M M M M M M N N M M M M M M M M N .... Mrr M M M M M M M M r M M M M Cp'f M V O 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O O O O O O 0 0 880 O O O O O O O O O O O O O f0 fp O fp fp O O V V W W V V lD W 0 0 0 lD V N N (D O O O O V V 0 0 0 0V V O NM N NONNOOOOOOMM NOOO M....... ............ y W W W W W W W ...... ...... O O am.--r r r r O O r r W W 0 0 0.. W (�D W M M n M M n n ..... ............. TW W Orr ......... V M M M M M M n r M M M M M M M M M M M M M M M M M M M M M M M M w 0 z w a O LU ¢�m���ommmm� wwwwwwwwzwwwwm a aazaaaaagaaaaN zzz ZZZZZOZZZZY F U wo o w N Q N w > y w >w j j j p o y w w w w Of Oa000 z Q x 0 C3 m w W W W W g� 0�.� Fw000UU m�amui m3al oxv�mwwwvi0wwwwv�g U W H W W W Hz>w t/l tq fqU J U F J F J y N K K K U F FJOOOOz a0Mm'-�v�Moauiuiuia6 a r M fp N fp V V y N r OJ W W t2 zzzzzzzzzzzzzzz W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W z z z z z z z z z z z z z z z W W W W W W W W W W W W W W W K K K K K K K K K K K K K K K U U U U U U U U U U U U U U U 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 000000000000000 Collier Boulevard Widening Projject rand Bridge Location Study Collier County is conducting a public information meeting for the Collier El condado de Collier esta Ilevando a cabo una reunion de information Boulevard Widening Project 60 Percent Design Plans and the Collier piiblica para el Proyecto deAmpliacion de Collier Boulevard 60 por ciento Boulevard Bndge Location Study The protect is located along Collier de planes de diseno y el Estudio de Ubicacion del Puente de Collier Boulevard between Coy Gate Boulevard North and Green Boulevard Boulevard El proyecto esta ubicado a to largo de Collier Boulevard entre The proposed improvements will help relieve congestion improve City Gate Boujevard North y Green Boulevard Las mejoras propuestas safely and accommodate future traffic demands within the area ayudaran a ativiar la congestion mejorar la segundad y adaptarse a las The Collier Boulevard Widening Project involves widening Collier futuras demandas de lrafico dentro del area Boulevardfromfour-to six -lanes wrthinthe projecttimils(approximately El Proyecto de Ampliacion de Collier Boulevard consiste en ampliar 2 1 miles) This is the final project in a series of five projects to improve Collier Boulevard de cualro- a leis-carrsles dentro de los limites del 15 miles of Collier Boulevard from US 41 to Immokalee Road to a proyecto (aproximadamente 2,1 millas) Este es el proyecto final en una six -lane roadway This project includes widening within the median serve de cinco proyectos para melorar 15 mitlas de Collier Boulevard and along the west side of Collier Boulevard and realigns porllons entre US 41 y Immokalee Road a una carrelera de sells carriles Este of the adjacent CR 951 Canal Multimodal improvements include the proyecto incluye la ampliacion dentro de la mediana ya to largo del addition of bike lanes along Collier Bou;evard. as well as two 10-foot- lado oeste de Collier Boulevard, y reatinea panes del canal CR 951 wide shared -use pathways along the west side of Collier Boulevard adyacente Las meloras multimodates incluyen la adicion de carnles and along the west side of 39th Street SW para bicitietas a to largo de Copier Boulevard asi como dos vial de The Cotner Boulevard Bridge Location Study is evaluating various use comparlido de 10 pies de a icho a to largo del lado oeste de Calder locations for a bridge connection (over the CR 951 Canal) between Bou!evard y a to largo del lado oeste de 39th Street SW Collier Boulevard and 39th Street SW The Collier Boulevard El Estudio de UNcacion del Puente de Collier Boulevard esta evaluando Widening Project will remove the existing bridge at 251h Avenue SW to vartas ubicactones para una conexion de puenle (sobre el canal CR 951) accommodate the proposed improvements Locations being evaluated entre Coiner Boulevard y 39th Street SW El Proyecto de Ampliaaon for the new replacement bridge include Golden Gate Parkway 25th de Copier Boulevard ellmmara ei puente exestente en 25th Avenue SW Avenue SW. 27th Avenue SW. and 29th Avenue SW. para acomodar las mejoras propuestas Las ubicaciones que se estan evaluando para el nuevo puente de reempiazo lncluyen Golden Gate Parkway 25th Avenue SW 27th Avenue SW y 29th Avenue SW YOU"RE INVITED ESTAS INVITIADO Coker County nvites you to par;:cipate in the upcoming E Condado de Co l er to nvita a participar en la proxima vista publica public information meeting for the Collier Boulevard 6 para presentar el 60 poraento de los pianos de diseno para et Proyecto Wideninq Protect 60 Percent Des it Plans and Collier de Amptiacien de Collier Boufevard y el Estudio de Ub€cacion del Boulevard Bridge Location Study Trie Puente de Collier Boulevard La { vista publica se ltevara a cabo el public meeting will be held e,r IIMCZZCM GREEN StVD --s - -"":. miercoles 6 de abril de 2022, Wednesday. April 6, 2022, from Wednesday April 6, 2022 desde las 5 p.m, hasta las 7 p.m. 5 p.m. to 7 p.m. at the Golden 5 p m to 7 p m �n , E b„ en el Centro Comumtano Golden Gate Ccrrmunity Center 4701 Golden Gate Community Center Gate 4701 Golden Gate Parkway, Golden Gate Parkway. Naples. 4701 Golden Gate Parkway Naples, FL aa11s "%"�3" Naples FL 34116 La vista publica FL 34116 The meeting will be conducted in air informal open PROJFr aRrA se ltevara a cabo en un ambsenle informal de puertas abienas y house setting with no formal ,_„,� sin una presentation formal Los GOLDEN GATE PICyVY presentation Attendees may �+�•�� asistentes podran rewsar las review the project d splays. and ° exhibiciones del proyecto y de tene„ talk one-on-one with the project m m . -„I iw alguna pregunta podran habla• team regarding any questions `a personatmente con el equipo d,. As an allemative to attending the 3 trabaio del proyecto meeting in person the meeting 9 displays and handouts will be a s q Corno altemativa de no poder aslstir a la reunion en persona, posted on the countys website a on April 6 2022 Your input is lasexhibicloriesyy los areun on se publitareosd anf onel s Q very important and we encourage web del Condado el 6 de oirt de 2022 Su opinion es nte you to share your comments Comment forms will be available y to alentamos a due compana sus co pare sus at the public information meeting as well as on the county websile comentanos Los formulanos para comentanos estaran disponibles en la vista publica, asi corrur en el sitio web del Condado El penode para The public comment penod will end Apnl 20 2022 comentanos del publico finalizara el 20 de abnt de 2022 PROJECT SCHEDULES The Collier Boulevard Widening Project CALENDARIO DEL PROYECTO Se preve que et diseno par:: is anticipated to complete design by mid-2023 Funding for widening el proyecto de Ampliacion de Collier Boulevard este terminado a Collier Boulevard is anticipated in the projected Collier County 2022 mediafos de 2023 Segun el Programa de Trabajo de Cinco arms del Five-year Work Program for design right-ol-way and construction Years 2022 2026 The Collier Boulevard Bridge Condado Collier 2022 se anticipa que la financlacion para ell dus ik between Fiscal and derecho de paso y la construction del proyecto sea entre los afros Location Study Is anticipated to be completed and presented to the fiscales 2022 y 2026 Se preve que el Estud>o de Ubicacion del Puente Board of County Commissioners by mid-2022 for approval The de Ccfher Boulevard este completado y sea presenlWo a Li Junta de proposed bndge would be constructed as part of the Collier Boujevard Com:sionados del Condado a mediados de 2022 para su awobacion El Widening Protect puente propuesto se construira corno parte del Proyecto de Arrjrhi dP Collier 60,jlevarn , Col Pier Count y Principal Planner, Lorraine M Lantz AICP Collier County Transportation Management Services 2685 S. Horseshoe Drive, Suite #103 Naples. FL 34104 DODIA, SONAL OR CURRENT RESIDENT 1912 PRINCESS CT NAPLES, FL 34110 i0tti :- ORLANDO FL 328 22 1'4 AR 2022 . ll G L. f�tjtfFi�lt'�411�1�lltil�l'lllrl,l,l�llll�tll�,t111�'linlii�lll r t._,`. PUBLIC INVOLVEMENT One of the most important PARI'ICIPACION PUBLICA Una de los aspectos aspects of design and studies is public involvement. It is mas importantes del diseno y los estudfos es la participacion very important for you to be able to provide your comments publics Es muy importante que ustedes puedan aportar sus related to the proposed improvements We use a vanety of comentanos sobre las meloras propuestaS..Se usaran una methods for you to stay involved In the process such as public vadedad de methods para que ustedes <Igan partjCipando en meetings, small group meetings, and the project webslte In el proyecto tal come vistas publican reunioaqq eft grupos addition. Collier County mails notifications to all property pequenos y en un sitio web del proyecto tt. W[on. el owners within the study area as well as to agencies and local Condado de Collier envuw por correo notificacows a todos officials prior to the public meeting los duerios de propiedades dentro del area de estudio y a las agendas y funclor.- -.s locales antes de las reuniones PROJECT CONTACT CONTACTO DEL PROYECTO if you have any 4uestions conuner�ts of concerns regarding S, keno jlajna arc>jur7iomentano o inquietud con the projectplease contact us respect° al proyecto contactenos Pou ed an kreyol, tanpn kontakte Diana Francois sou Diaria.Francois@Jacobs. k.II dr:Jt7' !.in-J F'CIF„-; See Thao P E . Senioi Project Manager SCAN N4E Colliei County Transportoi,on Ergineei,rg aw, 2R8` S. Horseshoe Drive FL 34104;239j 252 5844Bee ThaouCofherCovr'yFL gov r FOR MORE PROJECT INFORMATION GO TO: www collie►counlyfl govltransportation projects rwo cr mae mEnitiers of the Board of County Commsskoers 18C'Ci nvy be present and pamc,pate Wks rneetm, � ^A sutyev Warm of this materon "Wif N all cirri tar d=u&vw and Kfun et a future 8CC meehng Anyane who "Utres an aurdrary and a serwe far edPcfrve mrrnwrrce o ou r PasariaMe areu�rrnairi4+oror h� par! r pah± vi this proc eeding srrcwtd contact the Cdter County faut,'1,es Aanarpwf Dms on bcNed et 3)JS Tamwr, Tract E Narkw FbrHaa 34 t r1 x 1.i9 2516 i8� ns , �,t as r.,ss ue such reasons acrorr+modatrors w51) be pro~ ar M cost to the rdvrduai Dins o rnm mfernbm de Is Junta de Ctmsra,adus del Condada (SCC jw sus myss en ,n]4s) p"twi estav presen res y partrcipar a pu9de ser un terra de d=usibn y wccr, el arip futula rouron def BCC ClfMqu.e persona qua fequOera Byllda SPh'. dl di:M l dr rai:9 r•'O r Ytn.tster k r t 'rt e! t .a'tR adWtara^rras razonadte�para partopar on esfe omce&wnta. d&W comumarse con !a Orv,ston ae armnz rac'" in instaiurxs hs de, corwew LIP Gcuip::,cv nd.f wo rJ_5 Tamrarnr Trarl f A'a*s Fr ida 34 11 f? o 23SL252.6380 corn tan prrsrrro Conic sea pavve Totes ad4placew-' 'a,rcnabh s se pripow onarAn sr costo 9i4v% pars at nYkbW" Social Media Posts County to post on social media on Wednesday, 3/30/22 Collier Boulevard Widening Project 60 Percent Design Plans and Bridge Location Study Public Information Meeting - Wednesday, April 6, 2022, at 5 p.m. Location: Golden Gate Community Center, Auditorium, 4701 Golden Gate Parkway, Naples, FL 34116 3: 15THAVE SW� GREEN BLVD MEETING LOCATION 17TH AVE S W Wednesday, April 6, 2022 5 p.m. to 7 p.m. Golden Gate Community Center 19TH AVE S W — 4701 Golden Gate Parkway Naples, FL 34116 21STAVE SW PROJECT AREA 23THAVESW- GOEiIEW GATE PMY 25TH AVE SW J > m 27TH AVE SW J mJ z 29TH AVE SW � O V m U a) 31 STAVE SW H V Z _ CITY GATE BLVD N Cam. If you live off or commute on Collier Boulevard (between City Gate Boulevard North and Green Boulevard) you won't want to miss this public meeting! Attendees may review the design plans associated with widening Collier Boulevard from four- to six -lanes, and alternative locations for a new bridge to connect Collier Boulevard to 391" Street SW. Potential bridge connection locations include Golden Gate Parkway, 251" Avenue SW (replacement), 27th Avenue SW, and 29th Avenue SW. More information about the project will be available on the day of the meeting, April 6, 2022 at: www.colliercountyfL.gov/transportationproj.ects (under "Projects in Design"). If you aren't able to attend the meeting, please review the project information online and provide us with your feedback. 9:061 mill ^ O, Collier County, Florida C� Posts About Photos • Mentions � Collier County, Florida "' �5d Q If you live off or commute on Collier Boulevard (between City Gate Boulevard North and Green Boulevard) you won't want to miss this public meeting! Attendees may review the design plans associated with widening Collier Boulevard from four - to six-lanesr and alternative locations for a new bridge to connect Collier Boulevard to 39... See More 15THAVE SW GREEN BLVD MEETING • • •—Z� 17THAVE SW Wednesday, April 6, 2022 5 p.m. to 7 p.m. "' Golden Gate Community Center 19TH AVE SW 4701 Golden Gate Parkway Maples, FL 34116 21STAVE SW I�JI PROJECT AREA — GOLDEN GATE PKWY ' + 25THAVE SW J > m m 27TH AVE SW W z co 29TH AVE SW J 0 U r m O1 U 31STAVE SW Q LV CITY GATE BLVD N t7 75 61 Comments 91 Shares 05 Like Q Comment Share �• CS Home Watch Profile News Notifications Menu 3:48 .1 4:Fw .M. ( General This is a post from a t. Local Agency. Collier County Government 6 Social Media Coordinator Collier County Florida • 5d �: 15THAVE SW ON GREEN BLVI] - = 1TTHAVE. SYV Wednesday, April 6, 2022 5 p.m. to l p.m. 197H AVE SW Golden Gate Community Center 4701 Golden Gate Parkway Maples, FL 34116 , 21STAVF. SW PROJECT `` AREA 23THAVE $W I� — :. OLDEW GATE: PKWY 25TH AVE SW m 27TH AVE SW y LLI ¢ - r. •" i J Z _ 29TH AVE SW 31STAVE SVV - GIT" GATE 6t.V0 N Collier Boulevard Widening Project 60 Percent design Plans and Bridge Location Study Public Information Meeting — Wednesday, April 0, 2022, at 5 p.m. If you live off or commute on Collier Boulevard (between City Gate Boulevard North and Green Boulevard) you won't want to miss this public meeting! Attendees may review the design plans associated with widening Collier Boulevard from four- to six -lanes, and alternative locations for a new bridge to connect Collier Boulevard to 39th Street SW. Potential bridge connection locations include Golden Gate Parkway, 25th Avenue SW (replacement), 27th Avenue Sal, and 29th Avenue SW. More information about the project will be available on the day of the meeting, April 6, 2022 at: www.colliercountvfl.aovltransoortationoroiects (under tit ... Home Groups For Sale Notifications More 9:031 Ir <— Tweet Collier County Government @CollierGov If you live off or commute on Collier Boulevard, you won't want to miss this public meeting! Attendees may review the design plans associated with widening Collier Boulevard, and alternative locations for a new bridge to connect Collier Boulevard to 39th Street SW #CollierCoianty Tweet your reply County to post on social media on Wednesday, 4/6/22 Collier Boulevard Widening Project 60 Percent Design Plans and Bridge Location Study Public Information Meeting - Wednesday, April 6, 2022, at 5 p.m. Location: Golden Gate Community Center, Auditorium, 4701 Golden Gate Parkway, Naples, FL 34116 15TH AVE S W GREEN BLVD 17TH AVE SW Wednesday, April 6, 2022 5 p.m. to 7 p.m. "' Golden Gate Community Center 19TH AVE SW 4701 Golden Gate Parkway Naples, FL 34116 21STAVE SW - PROJECT AREA 23THAVESW Y 25TH AVE SW 0 � J > m m 27TH AVE SW Q ll l J Z m J 29TH AVE SW � � O m V 31 STAVE SW U Z CITY GATE BLVD N Don't forget tonight's meeting for the Collier Boulevard Widening Project 60 Percent Design Plans and Bridge Location Study! Attendees will be able to review the design plans for widening Collier Boulevard from four- to six -lanes, as well as bridge location alternatives to connect Collier Boulevard to 39th Street SW. To learn more about the project visit www.colliercountyfl.gov/transportationprojects (under "Projects in Design"). If you aren't able to attend the meeting, please review the project information online and provide us with your feedback. Your input is important to us! 10:30 Collier County, Florida About Photos • Mentions 91 Don't forget tonight's meeting for the Collier Boulevard Widening Project 60 Percent Design Plans and Bridge Location Study! Attendees will be able to review the design plans for widening Collier Boulevard from four- to six -lanes, as well as bridge location alternatives to connect Collier Boulevard to 39th Street SW. To learn more about the project visit www.colliercountyfI.gov/transportationprojects (under "Projects in Design"). If you aren't able to attend the meeting, please review the project information online and provide us with your feedback. Your input is important to us! #CollierCounty GREEN Wednesday, April 6, 2022 5 p.m. to 7 p.m. Golden Gate Community Center 4701 Golden Gate Parkway Naples, FL 34116 GOLDEN GATE PKWY Q � Q � W Ca QM L) zJZ * a � Home Watch Profile 3 15TH AVE SW 17TH AVF SW 19TH AVE SW 21STAVr SVv PROJECT AREA 23THAVE �;.'. 25TH AVE SW 27TH AVE SW Z 29TH AVE SW U ° 31STAVE SW U qu C9 News Notifications CITY GATE BLVD N A Menu Attachment 1.2 Public Information Meeting Materials Project Newsletter Collier)Boulevard Widening Project and Bridge Location Study Collier County is conducting a public information meeting for the Collier Boulevard Widening Project 60 Percent Design Plans and the Collier Boulevard Bridge Location Study. The project is located along Collier Boulevard between City Gate Boulevard North and Green Boulevard. The proposed improvements will help relieve congestion, improve safety, and accommodate future traffic demands within the area. The Collier Boulevard Widening Project involves widening Collier Boulevard from four- to six -lanes within the project limits (approximately 2.1 miles). This is the final project, in a series of five projects, to improve 15 miles of Collier Boulevard, from US 41 to Immokalee Road, to a six -lane roadway. This project includes widening within the median and along the west side of Collier Boulevard, and realigns portions of the adjacent CR 951 Canal. Multimodal improvements include the addition of bike lanes along Collier Boulevard, as well as two 10-foot- wide shared -use pathways along the west side of Collier Boulevard and along the west side of 39th Street SW. The Collier Boulevard Bridge Location Study is evaluating various locations for a bridge connection (over the CR 951 Canal) between Collier Boulevard and 39th Street SW. The Collier Boulevard Widening Project will remove the existing bridge at 25th Avenue SW to accommodate the proposed improvements. Locations being evaluated for the new replacement bridge include Golden Gate Parkway, 25th Avenue SW, 27th Avenue SW, and 29th Avenue SW. D YOU'RE INVITED Collier County invites you to participate in the upcoming public information meeting for the Collier Boulevard Widening Project 60 Percent Design Plans and Collier Boulevard Bridge Location Study. The public meeting will be held on LOCATION Wednesday, April 6, 2022, from Wednesday, April 6, 2022 5 p.m. to 7 p.m. at the Golden 5 p.m. to 7 p.m. Gate Community Center, 4701 Golden Gate Community Center Golden Gate Parkway, Naples, 4701 Golden Gate Parkway FL 34116. The meeting will be Naples, FL 34116 conducted in an informal, open house setting with no formal presentation. Attendees may review the project displays, and talk one-on-one with the project m team regarding any questions. As an alternative to attending the meeting in person, the meeting - — displays and handouts will be posted on the county's website z on April 6, 2022. Your input is H very important and we encourage �► you to share your comments. Comment forms will be available at the public information meeting as well as on the county website. The public comment period will end April 20, 2022. PROJECT SCHEDULES The Collier Boulevard Widening Project is anticipated to complete design by mid-2023. Funding for widening Collier Boulevard is anticipated in the projected Collier County 2022 Five-year Work Program for design, right-of-way, and construction between Fiscal Years 2022 and 2026. The Collier Boulevard Bridge Location Study is anticipated to be completed and presented to the Board of County Commissioners by mid-2022 for approval. The proposed bridge would be constructed as part of the Collier Boulevard Widening Project. NEWSLETTER #1 March 2022 El Condado de Collier esta Ilevando a cabo una reunion de informacion publica para el Proyecto de Ampliacion de Collier Boulevard 60 por ciento de planes de diseno y el Estudio de Ubicacion del Puente de Collier Boulevard. El proyecto esta ubicado a Io largo de Collier Boulevard entre City Gate Boulevard North y Green Boulevard. Las mejoras propuestas ayudaran a aliviar la congestion, mejorar la seguridad y adaptarse a las futuras demandas de trafico dentro del area. El Proyecto de Ampliacion de Collier Boulevard consiste en ampliar Collier Boulevard de cuatro- a seis-carriles dentro de los limites del proyecto (aproximadamente 2,1 millas). Este es el proyecto final, en una serie de cinco proyectos, para mejorar 15 millas de Collier Boulevard, entre US 41 y Immokalee Road, a una carretera de seis carriles. Este proyecto incluye la ampliaci6n dentro de la mediana ya Io largo del Iado oeste de Collier Boulevard, y realinea partes del canal CR 951 adyacente. Las mejoras multimodales incluyen la adicion de carriles para bicicletas a to largo de Collier Boulevard, asi como dos vias de use compartido de 10 pies de ancho a to largo del Iado oeste de Collier Boulevard y a Io largo del Iado oeste de 39th Street SW. El Estudio de Ubicacion del Puente de Collier Boulevard esta evaluando varias ubicaciones para una conexion de puente (sobre el canal CR 951) entre Collier Boulevard y 39th Street SW. El Proyecto de Ampliacion de Collier Boulevard eliminara el puente existente en 25th Avenue SW para acomodar las mejoras propuestas. Las ubicaciones que se estan evaluando para el nuevo puente de reemplazo incluyen Golden Gate Parkway, 25th Avenue SW, 27th Avenue SW y 29th Avenue SW. ESTAS INVITADO ONE El Condado de Collier to invita a participar en la proxima vista publica para presentar el 60 porciento de los planos de diseno para el Proyecto de Ampliacion de Collier Boulevard y el Estudio de Ubicacion del 15TH AVE SW Puente de Collier Boulevard. La GREEN BLVD N vista publica se Ilevara a Cabo el 17THAVE SW miercoles 6 de abril de 2022, desde las 5 p.m. hasta las 7 p.m. 19THAVE SW en el Centro Comunitario Golden Gate, 4701 Golden Gate Parkway, 21$TAVE8w Naples, FL 34116. La vista publica PROJECT se Ilevara a Cabo en un ambiente AREA 23THAVESW informal de puertas abiertas y sin una presentacion formal. Los -DEN eare_Picw► . ism AVE sw asistentes podran revisar las o exhibiciones del proyecto y de tener m 277HAVE SW alguna pregunta podran hablar personalmente con el equipo de z 29THAVE SW trabajo del proyecto. 0 m Como alternativa de no poder 318T AVE SW asistir a la reunion en persona, las exhibiciones y los folletos de CITY GATE BLVD N la reunion se publicaran en el sitio web del Condado el 6 de abril de 2022. Su opinion es muy importante y Io alentamos a que comparta sus comentarios. Los formularios para comentarios estaran disponibles en la vista publica, asi como en el sitio web del Condado. El periodo para comentarios del publico finalizara el 20 de abril de 2022. CALENDARIO DEL PROYECTO Se preve que el diseno para el proyecto de Ampliacion de Collier Boulevard este terminado a mediados de 2023. SegOn el Programa de Trabajo de Cinco anos del Condado Collier 2022 se anticipa que la financiacion para el diseno, derecho de paso y la construcci6n del proyecto sea entre los anos fiscales 2022 y 2026. Se preve que el Estudio de Ubicacion del Puente de Collier Boulevard este completado y sea presentado a la Junta de Comisionados del Condado a mediados de 2022 para su aprobacion. El puente propuesto se construira como parte del Proyecto de Ampliacion de Collier Boulevard. Co yer County Principal Planner, Lorraine M. Lantz, AICP Collier County Transportation Management Services 2685 S. Horseshoe Drive, Suite #103 Naples, FL 34104 PUBLIC INVOLVEMENT One of the most important aspects of design and studies is public involvement. It is very important for you to be able to provide your comments related to the proposed improvements. We use a variety of methods for you to stay involved in the process such as public meetings, small group meetings, and the project website. In addition, Collier County mails notifications to all property owners within the study area as well as to agencies and local officials prior to the public meeting. PROJECT CONTAC If you have any questions, comments, or concerns regarding the project, please contact us: PARTICIPACION PUBLICA Uno de los aspectos mas importantes del diseno y los estudios es la participaci6n publica. Es muy importante que ustedes puedan aportar sus comentarios sobre las mejoras propuestas. Se usaran una variedad de met000s para que ustedes sigan participando en el proyecto, tal como vistas publicas, reuniones en grupos pequenos y en un sitio web del proyecto. En adici6n, el Condado de Collier enviara por correo notificaciones a todos los duenos de propiedades dentro del area de estudio y a las agencias y funcionarios locales antes de las reuniones. CONTACTO DEL PROYE Si tiene alguna pregunta, comentario o inquietud con respecto al proyecto, contactenos: Pou ed an krey6l, tanpri kontakte Diana Francois sou Diana.Francois@jacobs. Collier Boulevard Widening Project Collier Boulevard Bridge Study Project Bee Thao, P.E., Senior Project Manager SCAN ME: Lorraine Lantz, AICP, Principal Planner Collier County Transportation Engineering Nlr '& Collier County Transportation Management Services 2885 S. Horseshoe Drive 2685 S. Horseshoe Drive, Suite # 103 Naples, FL 34104 Naples, FL 34104 Phone (239) 252-5844 { Phone (239) 252-5779 Bee.Thao@CollierCountyFL.gov ,_; Lorraine.Lantz@CollierCountyFL.gov FOR MORE PROJECT INFORMATION GO TO: www.colliercountyfl.gov/transportationprojects Two or more members of the Board of County Commissioners (BCC) may be present and participate at this meeting. The subject matter of this meeting may be an item for discussion and action at a future BCC meeting. Anyone who requires an auxiliary aid or service for effective communication, or other reasonable accommodations to participate in this proceeding, should contact the Collier County Facilities Management Division located at 3335 Tamiami Trail E., Naples, Florida 34112, or 239-252-8380 as soon as possible. Such reasonable accommodations will be provided at no cost to the individual. Dos o mas miembros de la Junta de Comisionados del Condado (BCC, por sus siglas en ingles) pueden estar presentes y participar en esta reuni6n. El tema de esta reuni6n puede ser un tema de discusi6n y acci6n en una futura reunion del BCC. Cualquier persona que requiera ayuda o servicio auxiliar para tener comunicaci6n eficaz, u otras adaptaciones razonables para participar en este procedimiento, debe comunicarse con la Division de Administraci6n de Instalaciones del Condado de Collier ubicada en 3335 Tamiami Trail E., Naples, Florida 34112, 6 239-252-8380 como tan pronto como sea posible. Tales adaptaciones razonables se proporcionaran sin costo alguno para el individuo. Room Layout m c x W *' E W _ �i C as s E 6 v m N m Ln zm Table Tent Signs Im O V CF) Im 0 v 0 v 3 m Public Information Meeting Displays WELCOME to the CSWTbulevard Widening Bridge Location Study Project Public Information Meeting I co [,eY coHnty -1 Jacobs I TITLE VI COMPLIANCE The proposed project is being developed in accordance with the Civil Rights Act of 1964. Under Title VI of the Civil Rights Act, public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. To express concerns relative to the County's compliance with Title VI, please contact: Collier Boulevard Widening Project Collier Boulevard Bridge Study Project Bee Thao, P.E. Lorraine Lantz, AICP Project Manager Collier County Transportation Engineering 2885 S. Horseshoe Drive Naples, FL 34104 Phone (239) 252-5844 Bee.Thao@CollierCountyFL.gov Project Manager Collier County Transportation Management Services 2685 S. Horseshoe Drive, Suite 103 Naples, FL 34104 Phone (239) 252-5779 Lorraine.Lantz@CollierCountyfl.gov Collier Count y CollierBo;1evar�\t land Bridge Location Study cm OW U LU LU � k_ k k § 2k q� E j AIC / \ / 1041 g m E .¥ d C) 3 e , m � to \ V � } L) .. 2 / E 3 k C E b= CD \ y ƒ ® = 2 m_ _ g/ � _ n ± 2 / E y ± e m v ± w p d E C � >w. . m @ 06 / y 2 ± ® � /� / \ 2 -- -- 2 \ $ 2 — £ F £ ƒ co ƒ / ƒ 7 w / 3 m m \cn e $ / 0 CO k ® ® = 7 a o m 0 k\ U/ m k w ƒ 4 § o y ? \ k / of C) THANK YOU for attending the Co oulevard Widening Project 0 d Bridge Location Study Public Information Meeting -1 Cooler county Jacobs V Z � t W ti y 3� 0 � v J W J 0 m �a a J �! J N u°° N �I 1 y g a r 'a y a r CN; yea I �r >c m 1 1 Ifl Z.0 to O �J? yea � So BULL m c d r 9N NNJ O Wm> # Co ifa 40 W N? 9 ci C Ct 4 0) N v u 3 p d n - = a� 0 cccc i d m' 9 3' D D tl W L TO A N!!� J T� '. ) At Vein y 'v yO y O ,..� N m=0 N > y q C « y C y f0 t O Z j o 2 C O . "�. Jf,O L 'c a W w �. h a `000m 3 `oo0.0i O UmIt a 0a0w e r� ��' _ ���, If',v 11Y9r�� COLLIER BOULEVARD WIDENING PROJECT: TYPICAL SECTIONS All Sections Looking North - 60% Design 4 Existing 4-Lane Roadway Main Golden Gate Canal to Green Blvd Proposed 6-Lane Roadway Golden Gate Pkwy to Green Blvd (West Side Widening, Median Widening, East Side Widening) . 20'-28' NORTHBOUND . -• MEDIAN (3) 11' LANES CR-951 CANAL 10' (EX1 51 VARIES • 4' 81KELANE ' „ PATHWAY (EXISTI \ Proposed 6-Lane Roadway 27th Ave SW to Golden Gate Pkwy (West Side Widening, Median Widening, East Side Widening) riupu�oeu u-Lane Ruauway .. Main Golden Gate Canal to 27th Ave SW (West Side Widening, Median Widening) Jacobs F I N A L COLLIER BOULEVARD BRIDGE OVER MAIN GOLDEN GATE CANAL 60% Design: Construction Phasing - Typical Section(s) All Sections Looking North - 35-X B9•-9"z - 17-a' @ Survey Collier Blvd. - 35-6" Traffic Separator ]Y-0" ]Y-a 1'-6" 1'1 I1-0" 12'-0" la -a• k;rShldr. Lane Lane Shoulder Shoulder Lane Lane Shldr. - --:.T. I-- @ survey Collier Bmd. 42'-17 �"S Limits of Removal 13'-IW± I 35-6" 2-a' I'-0" Delineator la-0" ", 10'-a 2-0" Type K Temporary Shltlr. earner Index 102-110 Lane Lane Lane Shltlr Peeeso-ra Railing Index 515 061 g 3 Temp P th ! E t g be,,, with damage per Record Plans @ Const. Collier Blvd. --I @ Survey Collier Blvd. 6B'-Y'+ New Construction 14'-BY 35-6" 27' Concrete Parapet Pedestrian/Bicycle I I 1'-a' Delineator with Bullet Railing Index 521-820 Type K Temporary 2-0" la-0" Ia-6. la-0" 1, Traffic Railing (36" single -Slope) ldex 52]-42] FSB with 6" C-1-P topping (TYp.) Barrier Index Pedestrian/Bicycle Shdr. Lane Lane Lane ShOr ).02 Ft/F[ Railing Index 515-06Z �To T i T 1-6 P6L LT —1 TL CpI15f. Collier BIVtl. -1 [— PGL RT Shlor. I— L.ne Le -12 L... fledii� en Lfe Lane Lfe Shlor- t T It Ft FSB with 6W C-I-P topping (Typ.) 1�-y-,. Railing Jacobs F- 0 o 0 _ ou wxs m a«a w mel7 c v 3�.a m c m 'o « a,Fmi 00 m c c o N m. p« o O O a F c m y E o m C }O, o a Q O N` 2 N W c o m c E> o 0 3 O p o 3 3 M '°` 'E > .E 10 a F r o ry l7 c s «�aciz L a a r ° E w m o Y c c£ s, a 3 c p w omo a v:°_ v vat y:n'o c Vc'a w M o m m « c a > ov E a o v• m y v N o i £ �_ d N o a a a o £ 3 a o v ° _ c v a Y a .o m 3 m •F ri a m N ,K l7 a m a 'F c .F o u« 3 > t 3 o c v o v a o m uO p m C Y M a-o a3a v C y 0 a Y W mo-'F 3a m L n N O E r Tm 3 C c E o o'N s ,� i W. m g a n 3 p W. 3 '° c m a 10 m C x a ,� u « v m l7 y p a_ x ' .F p o 3 u M 3 c m a c m mu cC v o L pa tp Cm m 3 v_ a� w ,^ E a f0 d a eo o M a a 3 c 3 '-�� d- m y m o a s 0 c o _ o a u " 3 c c s m c o M o M i0 v m •c -a H Y c a o a m o c« m y a . M •- .°, m m N Y o. x `m ',n m d a a 'v m m ri > o a a y c '° a e C7 !� a E c s- •p a s o f y c c° v v c v v= m- y= .F •3 Y u v w o 0 o y i� 'u •F C L W y c 3s av 7 am+ N w ''E ° a Y r•aa m p-0 am u a m L N O,FaI F `oc « Oa je N N C m ¢w av°+mz° c o'°^�a ¢zwZ° a Z $�� °c-c�v'v E c c o - - Z • v i z z c m Z MQ. W a Q o. a o. a MU > a o m E E E E 9 f W m W c v 0 oo o W p C « « y v a ai a Y« a d «« w a« d 3« o v y E m a c E c m d c yo m a c o s a c C a m y o m .F 3 E c a m m u m W o m •o c a m m u m c o m y c am m u m m C 0 m y c a m m (j « WI N •� N t o N« F y t o A-M .� N L o A «''r. = C E o E o -0 - 5£ o E 'o .m 5 E o E o y 'm S o E o' .Y m .0 Ep L L « - m o £p t 4 - m ,n . E y L L £ +' -p t o 7° v c; d o m ',Fi, c 3 a a m c; a o m c 3 u a m I ._ c a+ 3 C c- 0 0 '- ,n p- a c .vFi s+ c- ,n c a c •� a+ 3 c- ,n v a c N .. c N o• a c a` m£ w y: m E u w W v m u �+%+ w °-' m u w W a m u V R « O -MO C o m y 'F M m 'm 00 .i c c M E ,• £ a « c « lJ c E £ 10 x c o y 0 C mo .t N« E° r Sc j. = c w N c a H W N a m y m M - W p a a m a- u T T -p C ,n C L j 0°0 O = a0+Po w N V 00 m m C 6 O C m o -p N m a m mw,c y a m N m o •x •x •x E m 3 a a a a v a 3 x E 'm o v p •` m o m r a a 0£ c m O N c d, F F l7 -Z N v� a m a` l7 N °« c 'F c y G >. i 0 a 10 c m c O u 'F o ° y £ o E a•F a o 3 'p a° C ° - w 'o«'viwa"i mv'^a om .� EaaN a �3 °Jw ,•°m c v« £ c 3 .E c c o 3 c o ocy v m a •- 3 'F m £ wQ E E Z a W > w a C a> O =of avw 2O £ N 0 c C N > E mY. Z N Ma « a Z m L W L L O u c 9 Y m m Q N Q N Q N ? o �p Q 0 6 Final 2-Mile Segment of Collier Boulevard Conversion to 6-1-ane Facility (15 Miles Total) ` \ Immokalee Rd h:7 • > rr-h I r Vanderbilt Beach Rd ^ ' z rn �- J a J 0' IT ,� Q — l.L — ' t .ter dine Ridge Rd white Blvd ��- 'Green Blvd a>Le Pkwy ocat on Main Golden Gate Canal lCity Gate 31vd N Lr - Radio Rd - Id la C 1SJ 84 t' m v Aft/.� C Rattlesnake Hammock Rd —1� 41G r� 4 e ' Six Lanes Constructed 0 0.5 1 Miles I I Project Location (Existing Four Lanes) GULF OF M E X I C O collier County .pacobs 3 a Project Handout April 2022 CollierIBle and Widening Project and Bridge Location Study PUBLIC INFORMATION FACT SHEET Collier County plans to widen Collier Boulevard from four- to six -lanes between City Gate Boulevard North and Green Boulevard (approximately 2.1 miles). This project is in the design phase and includes widening within the existing roadway median and along the east and west side of Collier Boulevard in some locations. Due to its proximity to the Golden Gate Parkway intersection the existing bridge over the CR 951 Canal (betwee Collier Boulevard and 39th Street SW) at 25th Avenue SW will be removed. Concurrently, Collie County is evaluating a bridge replacement location Locations under evaluation include Golden Gat Parkway, 27th Avenue SW and 29th Avenue SW. Project Purpose and Need The widening of Collier Boulevard is needed to help relieve congestion, improve safety and accommodate future traffic demands within the area. The project includes such enhancements as dedicated bike lanes and shared -use pathways. Proposed Typical Secti —i �li�ll Ire — LEGEND Mill ID N 75 ss� �rw1R\ L The proposed typical section includes three 11-foot-wide travel lanes in each direction. Dedicated bike lanes (4 feet wide) are proposed adjacent to the northbound and southbound travel lanes. Sidewalk (6 feet wide) is proposed along the west side of Collier Boulevard, from Golden Gate Parkway to Green Boulevard. Shared -use pathways (10 feet wide) are proposed along the west side of Collier Boulevard from City Gate Boulevard North to Golden Gate Parkway and along the west side of 39th Street SW (east of the CR 951 Canal). Other Considerations As part of the project improvements, Collier County is considering adding a new pedestrian bridge to provide bicycle and pedestrian access between Collier Boulevard and 39th Street SW (for access to dining, shopping, and entertainment). To provide safer access to those who use public transportation within the project area, Collier County is also considering relocating Bus Stop #276 and adding a designated bus turn- out, a bus shelter and a mid -block signal for pedestrian crossing. Collier County greatly appreciates your feedback on these considerations. Please complete the Project Survey and Comment Card available at tonight's meeting or online. SCAN ME: 0 ad � More information about this project can be found online at: http://www.colliercountyfl.gov/transportationpromects (under "Projects in Design") Frequently Asked Questons How long has this project been planned? This is the final project in a series of five projects to widen Collier Boulevard to six lanes from US 41 to Immokalee Road. The first widening project began in 2005 and since then, Collier County has invested over $200 million for the improvements along Collier Boulevard. live/work along the project area. Is additional land or right-of-way necessary for this project? No additional right-of-way is anticipated for the improvements. Should any right-of-way be required, the Collier County Right -of -Way Acquisition Section would contact impacted property owners. When will construction begin? The design phase is anticipated to be completed in the fourth quarter of 2023. The earliest construction is anticipated to begin is early 2024. Another public meeting is anticipated to be planned when the design plans are 90 percent complete. When will the final replacement bridge location be determined? The bridge location study will incorporate comments received as part of this public involvement meeting and is anticipated to be complete by mid-2022. The study will then be presented to the Board of County Commissioners for approval. The final bridge location will be incorporated into the design phase of the Collier Boulevard Widening Project. Will there be access changes along Collier Boulevard as a result of the improvements? There will be multiple changes to access along Collier Boulevard to improve traffic operations and enhance safety due to the new six -lane configuration. Proposed median opening locations (to allow left -turn movements) are as follows but are subject to change: • Northbound Collier Boulevard drivers: o Workforce housing location entrance (final location to be determined) o 27th Avenue SW (proposed golf/entertainment facility entrance) 0 23rd Avenue SW 0 20th Place SW 0 18th Avenue SW • Southbound Collier Boulevard drivers: o 27th Avenue SW (pending outcome of bridge location study) o 20th Place SW (for U-turn access) Proposed access with intersecting streets and the southbound movement of Collier Boulevard includes right -turn in and right -turn out only with the following: • 23rd Avenue SW • 20th Place SW • 18th Avenue SW 1 :2:Z9aJ x4 VIA] 011 V_« &15 Collier Boulevard Widening Project Bee Thao, P.E., Senior Project Manager Transportation Engineering Division Phone (239) 252-8192 Bee.Thao4CollierCountyFL.gov Collier COuftty Collier Boulevard Bridge Study Project Lorraine Lantz, AICP, Principal Planner Transportation Planning Section Phone (239) 252-5779 Lorraine. La ntzMCollierCountyFL.gov Comment Form We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? ❑ Yes ❑ No 2. How often do you use this section of Collier Boulevard? ❑ Daily ❑ Weekly ❑ Other 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ❑ (A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW GREEN BLVo I ITH AVE 5W J y m } — 19TH AVE 5W J 0 U � 21STAVE SW_ - 2 Q _ U 6i 23RDAVE SW � ' 1. ip T. G01 Of> GATE PKWY _ 25TH AVE SW m a t� z7rH AVE SW r j B 29TH AVE 5W -- - C 31STAVESW Bridge Location 0 o25 a.s Mpes Altemative — J-64�BEW 6At�A1W CR37At ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW _14 El (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW ..�i—e.OULIER BL■VD- - srit B"C sT ❑ I do not use the CAT system � OptionA F �- option B W El Other - Option C Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name *Address *City, State, Zip *Phone Number *Email Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@colliercountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? ❑ Yes ❑ No 2. How did you hear about this project? (Mark all that apply.) ❑ Email ❑ Social Media ❑ Roadway Message Sign ❑ U.S. Mail ❑ Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Cd�e'- Crnmty Completed Sign -In Sheets i \V7 V V ` s V N v 1 M � Zs � v v\ v W to 1,6 \ � M Q -�C y V71 01 ❑' p _ Oi O Oi O ❑ \O _ 1 01 2 O [ 2 O ❑ 2 O c � 2 0 J 0 El 0 L O ❑'� W O O - Oi O ❑ m w -M v - m w -ao � 'a i v m w a in 3 ❑ $ L❑ m 3 ai in 3 ,m in w° 3 in v 3 3 U ui in 3 w 3 I ao z • � L rl ra K exMlzr- f O 0 j O V r ? r^ VI on ..7+ 00 0 4 Q U v h \ ] V • c O ❑3❑❑®❑❑❑❑❑❑101❑❑❑❑❑ c O m O a a 0 c 0 m rn g 0 2 O c g 0 c 2 O ❑❑C�]❑❑❑e c 2 O m m 0 rn O rn 2 O J c° .-_ c O ❑ v 'n m v m a a a m 'v a v :2 T a m m in 3 in 3 m m 3 y 3 3 3 of 3 fn 3 in 3 in $ 3 m 3 r'n 3 Wo 3 in 3 c. n 13 M � CM N Y F QN J v � OJ Ln VIP .r 4z ■ O M O g 0 9 O 9 O 9 'U 9 O 1 O g. O �85 m ll O L O t m O C L m O C L m O m A m m AR m M a m m m m m 3 ❑❑ in 3 ❑❑ $ 3 ❑❑ a y 3 El Ell s N ❑❑ n in ❑❑ n 3 ❑❑ U m° 3 El El m ron ❑❑ N 3 ❑OF .o a m 11 m n N 3 ❑❑ n in 3 ❑U m n in 3 ❑❑ a ❑❑ a • FIN IRN NN 1 Wo !V M 0 ONm � Iz- G o • =o C N olu va V � c/1 q V N M C� 7Z� 72. s O O c t Om c O ❑C rn m O C O C rn O O ❑ O CC❑--❑❑: O O rn O 2 O ❑ _ _ _ _ - w _ _ _ _ - H - _ _ _ _ _ _ _ _ _ w _ _ _ _ _ E o � o 3a J V i a 4 0 Zi v aj M a -41 _ J � ki O ❑❑❑❑❑❑L�7❑�❑❑❑❑❑❑❑❑❑❑❑❑❑❑❑❑❑❑ O 2 O 2 O O g 0 O O g 0 O O O O O O _ • °' �• � v AM aOi � o � v m a_ v AR v � v tC v � � v w � v n � v AM w � 12 d � d v � v � v N A � A v � v !a A n N N .0 9 A l0 L m U L in 3 L m 3 N d y 3 0 N 3 q N y 3 'a—' 3 m0 in 3 go Ell 00 S Ca Z-All m� O rn c v g 0 rn� 2 O w c � 2 0 � � 0 rn� 0 � � O m• O m c L F. O rn� 2 O rn• 2 rn c L 2 O rn c L 2 O c � to z 2 O �• O m Ti m 'n m + m + m w m m m a m T, m w w mui m w w y m m m I._� ❑ _ ! ❑ a 1 • 13, d },fin 1 M I ry QH S N - L L. wl � M w a- VY C s Lo 13 m a cls Y O W g 0 g 0 W S W L g 0 � L 0 W 0 W 2 O � W C L : 0 � L m O W C ` 9 O � L 3 O � � O W C L 2 O • 'o 'a m a 'a '95a • �� �� A2 'v -• .m v 'a m° 3 m y 3 m in 3 in 3 m as in U is m° rDn 3 a in 3 m Q m a;u 3 a in 3 m� y is a — r0 3 El a a E E Cl) J LL Q ca Z • W Y I `m 4. N l9 0 c N C -0 O O - 0 16 N O R O • 'y O U d f0 ~ C � � a a w o w W J • o. N � d a a` ti a o a Q W LO • N N C N C O (0 F � 2 O K IL c w W U_ Q O W 7 J a a • N N • • • • • C J N m a m C �\ N a � m z rc IL W , • ` . , co W. . .. 1 • • • • • • .. Ja ao , . • • , , `m E .O Z U • , ,� • Z m U a C U N 0 U m U Q >+ C U N 0 U T C U N 0 U m o a T C U N 0 U T C U N o U T C U N 0 U T C U N 0 U T C U N 0 U T C U N 0 U >. C U N o U U) m O Q C O N U U > Y N = p f6 Y c0 LL Y J J C > LL1 O) C J (6 o CA C J Q L 0)C J m a)U) J (6 � E m (A 70 m O Q C O UM)U)7 O � N O U N � AO O U U1 c LL O C (n � O U _ C' z N V M J LL N N a m Z • m 3 Y f0 a m G � o o - (, R N O R m O Y C ~ •/ _ � C� CC C O U d io r 0 z w a -6 w O N U w w • a E v Ca v O Q W N 04 GI N O .Q Q m G N G O fQ F � Z O d' IL w W U Q W 3 J ` d a d -o a c G Epp •R • • • • • • • � C G G7 .o a` cm z ` N W U N • i . ,' W ' � IL d � .LD R O Z U • Attachment 1.3 Public Comments We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? 15: 4 05 :: No 2. How often do you use this section of Collier Boulevard? g Daily Li Weekly 5: Other �� _ — /I 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. �C(A) Golden Gate Parkway (B) 27th Avenue SW ❑ (C) 29th Avenue SW GREEN BLVD [il 17THAVESW d a . 1 sTH AVE SW J � u z 21STAVE SW O { M 23RD AVE SW J Q GOLDEN GATE PKW A 25TH AVE Sw a m � r- I � m 27TH AVE SW Q B z /k 29TH AVE. SW C ❑ Brdge Locaton o �sss a 31STAVE SW ARemative AI --_ ^ VFM F,gTF MANCAitA1 ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? Yes, I'd be encouraged to use the pedestrian bridge No, I wouldn't use a pedestrian bridge I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? Daily X Weekly ❑ Other ` i do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. Ei (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW I do not use the CAT system Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. 'Name ti n 'Address 'City, State. Zip ry 'Phone Number t `Email _T__ 1kjl,��i,CO�i Please return comments to: Growth Management Department Attn Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth management@colliercountyfl gov Please provide your comments on the following space provided If more space is needed, please use an additional sheet of Paper. Place your comments in the "Comment Box provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? ❑ Yes ❑ No 2. How did you hear about this project? (Mark all that apply.) Email Social Media Roadway Message Sign U.S. Mail Other 'Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Collier coHhty We are looking for your input to assist with bicyclists and pedestrians. _liMll 1- Please provide o planning and designing the best roadwa Y ur input by answering a few questions below to serve motorists, 1 Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? ,IXYes ❑ No 2. How often do you use this section of Collier Boulevard? Daily ❑ Weekly ❑ Other 3. if you live on the east side of 39th StreetSW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. A(A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? 1K Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? Daily ❑ Weekly ❑ Other 1� �6S Sti G teczss ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW All do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. Name /1.1 4:5 th Iq1-�' III ;Address ���1� l'A t/ s `City, State, Zip `3 tl// *Phone Number �-G � ` !T 7 / 'Email �1 ZZ G ),*-S P A-n L , C dr11 Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. ! �lCGGe_Unris C� �1�/ Ijl < �� Gti' 4 !� de' Cti� L�✓� 6�__ 4� K-f I r 1�_ J--k G o o OL Y 1 r. n, s' ! r I i eq l (,AY, eS 91� L,� 4,� f=L GO>+'r.e4 � ! 6,,r fk\,—1 ejfS�-r64r,J W Ci►/ 1 r� a. / Ci1/ s W �lJ e.� r (obi Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? �4 Yes FNo 2. How did you hear about this project? (Mark all that apply.) Email 0 Social Media M Roadway Message Sign F U.S. Mail F1 Other 'Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet, You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. We are looking for your input to assist with planning and designing the hest roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? I NO - _ Ay t77HAVE 5W Yes El� - 1 - 2. How often do you use this section of Collier - ri W 19TH&V sW Boulevard? -- _ 2iSTAVE SW ❑ weekly tj Daily , ❑ Zil ZJRO AVE sw- Other- 3. if you live on the east side of 39th Street SW, iP A ZM A►E-W_ after reviewing the bridge location alternatives, which bridge location do you �f ti _ snH_AVE- SW prefer? Refer to the diagram on the right for � � l rY 1 �1i B bridge locations. y _29THAAE-§W 9 .1 -L C (A) Golden Gate Parkway j - 31S AVE 5W _. 0 (B) 27th Avenue SW After aUve o L ° s6 "' AEtemavva _ ^, �orM skre ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th street 5W (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? NQ Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? p Daily 'sj Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 6. if you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW N I do not use the CAT system ❑ Other public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. "Name 0, �O y +- W "Address 35l l 2 1 f Vvyl -City, State, Zip 3 t 7 'Phone Number rf "Email pSa1 re Y" Please return comments to: Growth Management Department Atfn- Connie Deane, Community Liaison} 2885 Horseshoe Drive South Naples. FL 34104 You may also send your comments via e-mail to: growth.management@colliercountyfl.gov Please provide your comments on the following space provided. if more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Sax" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? if not, what additional information could have been provided? Yes No — 2. How did you hear about this project? (Marl~ all that apply.) Email D Social Media 1:1 Roadway Message Sign U.S. Mail Other -Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a govemment agency If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county wehsite for additional information. Coder COUXy -,tA We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes ❑ No _1_ _ GREEN BLVD 17THAVE SW 2. How often do you use this section of Collier Boulevard? 0 Daily ❑ Weekly '�� ❑ Other if �\,r��K, II - 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. V(A) Golden Gate Parkway N((B) 27th Avenue SW ❑ (C) 29th Avenue SW ❑ 1 do not live on the east side of 39th Street SW Bridge Location Alternative M k— 19TH AVE SW J � $3 21 STAVE 6W 2 y 23RDAVE SW A 25TH AV_E sW, _B 27TH AVE SW 2BTHAVE SW C 31STAVE SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? 16 Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily IrWeekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW X I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. �J *Name *Address 3L35 6T"" I '�- *City, State, Zip l�l � 2 �-� 5 �- 3 u 11 % *Phone Number a3q aq) 9`1c�G *Email LW i7 C K a 1 _J IJ�1 e J ✓yl G o Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. 6 i� ' y, �.�s1 �� �11`� '�Y l �(, i C_ (�P n G -e fv�. ' S o t V \ roLam£I� tqL cc wP v S . U Evaluation L,a ,2.—" to eu-,Li ik a-,Dv,-6--d11e J 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? ® Yes No 2. How'did you hear about this project? (Mark all that apply.) 1-1 Email P Social Media ❑ Roadway Message Sign 0 U.S. Mail F Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. 1 COMMENT FORM Collier Boulevard VWdurling Project and Bridge Low6on Study • Pebllc Inlatmntron MFellnp • Apnl 0, 2022 • 5 P,m to 7 P.M. 0 Golden Crate Community Center • 4701 Golden Gate Pkwy • Naples, FL 3A1 t8 We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? /Yes ❑ No 2. How often do you use this section of Collier Boulevard? ( Daily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. (A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW GREEN BLVD 17TH AVE SW J - � m 19THAVE SW 21STAVE_SW _ c3 x 23RDAVE SW V LDE GATE PKIIIIY di L.25THA\V9 W % 27TH AVE SW B 29TH AVE SW Bridge Location �� 25 31STAVE SW Alternative GOLDEN GATE MA CRNA 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly lJo-Other��r� - ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW IJO do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name _ Please return comments to: *Address t`t 4 /' Q S ui Growth Management Department ofir, \1 (bttn: Connie Deane, Community Liaison �11 2885 Horseshoe Drive South *City, State, Zip Naples, FL 34104 *Phone Number You may also send your comments via e-mail to: growth.management@collierccountyfl.gov *Email F � Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? could have been provided? WYes ❑ No If not, what additional information 2. How did you hear about this project? (Mark all that apply.) Email q�SocialMedia Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. co er County ,9A We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? rf fd lies 0 pia I I _ _ GREEN g�w - 2. How often do you use this section of Collier Boulevard? Gaily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. J. gRIA) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenu6 SW ❑ I do not live on the east side of 39th Street SW --i — J�f -J Bridge Location Alternative G -i 17THAVE SW m o: ff . J 19TH AVE SW Ci �0 A 21STAVESW d 23RDAVE SW I � _e 25THAV. E_5_W.— Q.Y6 �xnq: GATE MAN r-'ANA 27TH AVE SA a 29T H AV E SW V 31STAVE SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge 1401 I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ WeeklyI ❑Other --- El I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW &- do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. 9 *Name 15 J %L Z G *Address *City, State, Zip l!�ll� Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 *Phone Number23?Z `�� -� - � ;77 You may also send your comments via e-mail to: *Email growth.management@collierccountyfl.gov �%S-f�C 7cj?L CZ(�%�%��%t�-��•'�,�_ !'C�/'a' Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. 6( Cr(S C3� Ell C,)V 31 /&S tvc y CL /fir 5y //GI p Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could fbave been provided? M' Yes -�— M. No -- 2. How did you hear about this project? (Mark all thAapply.) 1-1 Email FISocial Media Roadway Message Sign FlU.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Collier County ti COMMENT FORM C0111F:r Boulevard Wde incd Proleef and Bridge I ocabori Study • Public Information Meeting • April P, 20Z2 • 5 n.m ro i 1) T1 • r_Solden Gata: Community Gonh:r • 4701 Goldnn Gale r'kwy • Naples. Ft. 341 le We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard No h and Green Boulevard)? ❑ No GREEN SLVD 17TH AVE SW 2. How often do you use this section of Collier i Boulevard? 1 Daily ❑ Weekly ❑ Other 0 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for ridge locations. ,IV(A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW j� Bridge Locatlon {� Alternative ❑ 1 do not live on the east side of 39th Street SW o _ U � (r f ( 11 01 c� GOLDEN GATE IPIKWY l-!I GOLD FN GAl"G 1 l� 19TH AVE SW 21STAVE SW 23RDAVE SW w 25THAVE SW 1 27TH AVE SW B 29TH AVE SW �c 31STAVE S* 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? 2 Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly (Other e ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW Yd ) The existing location, at 17th Avenue SW o not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. r y ' fk *Name Please return comments to. `' �� Growth Management Department *Address Attn: Connie Deane, Community Liaison *City, State, Zip '�' F L I 2885 Horseshoe Drive South Naples, FL 34104 *Phone Number - { l L You may also send your comments via e-mail to: growth.management@collierccountyfl.gov *Email � � �"' � Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box' provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? cou have been provided? Yes FINo If not, what additional information 2. How did you hear about this project? (Mark a I that apply.) Email ❑ Social Media Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. c�,�r co�rrcy 5A We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? F• Vyes ❑ No 2. How often do you use this section of Collier Boulevard? Daily ❑ Weekly ❑ Other 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. It] (A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW GREEN BLVD j 17TH AVE SW W 19THAVE SW \ V - 4 21STAVE SW -, - 23RD AVE SW ATE PiKV-, ' A 25TH AVE SW 4 27TH AVE SW 29THAVE SW Bridge Location 31STAVE SW o oxa a� I^ Alternative GOt 4Ei4 GAiE hM1A'N PCAN'. 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? eyes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily 'Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. -I (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW ❑ I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name L 4a 4 *Address 37/,0 ;22 2 7`t V e� 50 *City, State, Zip Mat,18,6 z *Phone Number p?�_.�� l3 7e/ *Email &17-eeM 1tl dorYl. Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? _ :� , )") - e, Ve FJ Yes No 2. How did you hear about this project? (Mark all jhat apply.) Email Social Media F�Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Col�iier County We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard Norto and Green Boulevard)? 'Yes 0 No _ GUEN gwo. _ 17TH AVE SW 2. How often do you use this section of Collier B plevard? �w� ! �� _ I9THAVE SW -'j Daily ❑ Weekly - — - — �r $ 3 -• a � 21STAVtt$W Cn ❑ Other o i4 I J W "' 23RDAVE 3. if you live on the east side of 39th Street SW, _P after reviewing the bridge location _ A 25THAVE alternatives, which bridge location do you a prefer? Refer to the diagram on the right for a 27THAVE badge locations.-� _ 41 29THAVE (A) Golden Gate Parkway ` C 1 �I�B) 27th Avenue SW I�1 BridgeLocatIon a •� _ 31STAVE; u Altemative ❑ (C) 29th Avenue SW _ sosaer+��ATt MAW AN ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ,t� Yes, I'd be encouraged to use the pedestrian bridge No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW �I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? I GREEN BLVD Yes ❑ NO g� ��- Q 17THAVE SW 2. How often do you use this section of CollierAx _ m �_ T J Boulevard? 19TH AVE SW Daily ❑ Weekly 21STAVE SW ❑ Other �' L- F p _ A, 23RD AVE SW 3. If you live on the east side of 39th Street SW, _ - -1 �j - �� _ � ��� after reviewing the bridge location 61A 25THAVE SW _ j alternatives, which bridge location do you r �J prefer? Refer to the diagram on the right for 27THA�Esw B bridge locations. a 29TH AVE SW ( (A) Golden Gate Parkway ll r ii C ❑ (B) 27th Avenue SW o 0.xs' o.k — 31STAVESW Bridge Location I Bridge GQLpENGajt= MAIN CANAL ❑ (C) 29th Avenue SW - ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge l� No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW 16 1 do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name �=-• J�t3r'Ij<�� *Address *City, State, Zip ' " N K Y/J 7 *Phone Number ZEJ c — *Email l_ ��U +( I,�"�� j�l — AUk COO) Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box' provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the p7rofec� osed improvements? If ot, what additional information could have been provided? �C� we Vi Yes ❑No 2. How did you hear about this project? (Mark all that apply.) Email 5�.Social Media $�'Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Cc�I[ier Cc�trnty A We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard N h and Green Boulevard)? Trtes ElNo GREEN BLVD 2. How often do you use this section of Collier Boulevard? Daily ❑ Weekly ❑ Other 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. X(A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW 1.1 �� 17THAVESW 19TH AVE SW I_ �J (` _1 !-- 1 f' {I 1 21 ST AVE i J i GOLDE GATE P{tWY Wi� 23RD AVE SW < < l� 27THAVE SW 29TH AVE SW 1 ro �a�jj C31 STAVE SW ❑Brldge Location a g Alternative GOLDEN GALE MAIN rANAI. ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge XNo, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑Weekly _LOther ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW I do not use the CAT system Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. "Name rr , (5-ut °� "Address q7 `U 2� L e_ �w *City, State, Zip "Phone Number 13 7-27 _ qZ e q *Email Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. ,1V hri da- u,4.j 6c mapcd 2,7 at- '4 fA h k/A, k `tyl0, d r I lit ��rn �� CI�Dv �d !� S�yu �►y�yn G �r �� .Sl At _—d I f ikCts i AA 62 e y e a4 d C tip,, ts- A& _�K Q w e Ae V ll�U ✓ � t1Y.eS ►'�v�- y�lGn o�•u:'Y�� ��� �C!✓�r•��2:`S f�c G�c.r�•� � u,n Pr.-r�:. �.�..._ !Le at � � C 12 al � 6-Pc � Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? ❑ Yes ❑ No 2. How did you hear about this project? (Mark all that apply.) [—]Email ❑ SOCial Media ❑ Roadway Message Sign ❑ U.S. Mail ❑ Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. COIL C094hty We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? )(Yes ❑ No 2. How often do you use this section of Collier Boulevard? Daily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. (A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW GREEN B�LVD 17TH AVE SW :M — 19TH AVE SW lX, 21STAVE SW of Ems., 23RD AVE SW EFKWY 25TH AVE_SWLU _ ✓, 27TH AVE SW �- e 29TH AVE,Y f Bridge Location 31STAVE SW � n ^��' - °�� Alternative C,OLOEN C+AiE [iAJ11N BANAL _ ❑ 1 do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? Xyes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily X Weekly ❑ Other ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW -�9,1 do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name am LAI 0,artv 11 *Address —3R,76 o25-1-A 1 ' vs -S m _ *City, State, Zip Moles 7 *Phone Number *Email end N P C 'Yoh and eam l l . 'u-m Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. P PoSed brAje, 1afA�;a-yi5 5ouU & _ 6- 6 iOLA w,'c? ka Did this meeting provide you with sufficient information on the proposed improvements? could have been provided? XN Yes F1 No If not, what additional information 2. How did you hear about this project? (Mark all that apply.) ❑ Email N Social Media XRoadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. cn l couHcy We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes ❑ No 2. How often do you use this section of Collier Boulevard? .� Daily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ❑ (A) Golden Gate Parkway R (B) 27th Avenue SW ❑ (C) 29th Avenue SW GREEN BLVD 17TH AVE SW 19THAVE SW ;r f J r J _ f r- q G LDE GATE P}tWY � A25THAVE.$�1 ' / 1 ,, <` • C ` �,.. J G 27TH AVE SW 13 Z a =�w 29TH AVE SW c r II 31STAVE SW Bridge Location o o.M Alternative i c>oEDeM cA; [ rnn N rnrin� ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? X Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily Weekly Other 1v?,oN;l, L,It ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW El (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW -1�'I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name ;Sash 1�O�Q�Au� *Address 33ti �;' 15t�` ,1JF Sly/ *City, State, Zip /)AALE5 11 FL -1 q 11 *Phone Number ✓` 02 - 9T71- 'la 3 g *Email Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Pt Eas E PR16 u Z.D I~ ADA �Qcc�s� ARLE I � S70P C6.1_mg, I�LVD ,SP/Jc.E Fol� To BE /4BL1_ Tr°i S�F GY it/Azr aSi� ME CAT 8rc> SYSTFtlA Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? NYes No -- 2. How did you hear about this project? (Mark all that apply.) Email Social Media Roadway Message Sign ❑ U.S. Mail _rQ Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard Noyth and Green Boulevard)? Yes ❑ No 2. How often do you use this section of Collier Bo yard? aily ❑ Weekly ❑ Other 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. [>& ) Golden Gate Parkway 0 (B) 27th Avenue SW ❑ (C) 29th Avenue SW GREEN BLVD 17THAVE SW 19TH AV_ E SW Y^ LLL r l in 21STAVE SW ! 23RO AVE SW G' D iE PKWY 27TH AVE SW h 2971`11 AVE SW �. C _ _ 31STAVE SW Bridge Location .. a �•---�� Alternative f GOLDEN GATE MAIN C ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW o not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. �0 L*Name �� ) g v / Please return comments to: Growth Management Department *Address Attn: Connie Deane, Community Liaison *Cit , State, Zip 2885 Horseshoe Drive South Y P Naples, FL 34104 *Phone Number f <� r� / �j� ✓�/You may also send your comments via e-mail to: r j tt growth.management@collierccountyfl.gov `Email f 00 Please provide our comments on the following space rovid��,more space�isnbfedtlease use an additional sheet of P Y 9 P P P paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? - I Yes No 2. How did you hear about this project? (Mark all that apply.) Email cial Media Roadway Message Sign U.S. Mail Other *Please be advi ed - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. C.Aler OoMHty Elio We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes ❑ No GREEN BLVD � 17TH AVE SW 2. How often do you use this section of CollierI� I I b C Boulevard? ,�` 19THAVE SW Daily ❑ Weekly 4 -- ,%�� i � ', = 18 ;0) 21STAVE SW ❑ Other I 23- RDAVE SW � 3 3. if you live on the east side of 39th Street SW, 1 _] - _ - after reviewing the bridge location A725THAVE SW alternatives, which bridge location do you 27TH AVE SW prefer? Refer to the diagram on the right for bridge locations. B 29TH AVE. Slv '16 (A) Golden Gate Parkway - c 31STAVESW Bridge ❑ (B) 27th Avenue SW ElAlterrnatloeation 7i: GULDEN LATE MAIN CANM ❑ (C) 29th Avenue SW ---- - ❑ 1 do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? 50 Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ,®; Daily ❑ Weekly ❑ Other ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW 0 1 do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. 111111111111110 *Name �n Ycii1 *Address 1 2cftf`-AA,L SSW *City, State, Zip F iu) j *Phone Number 2't- 5 37 lQA I *Email 'at, j 3t,,5-Nit,12 -% ! �o � Lbm Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. W� - -ik' K --Vint, V\C 1�1-a A N , Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? ® Ye,s No 2. How did you hear about this project? (Mark all that apply.) Email ©Social Media ® Roadway Message Sign ❑ U.S. Mail ❑ Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. CAL-r County We are looking for your input to assist with planning- and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes ❑ No 1 GREEN BLVD o> 17TH AVE SW 2. How often do you use this section of Collier Boulevard? h baily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. d X(A) Golden Gate Parkway N ❑ (B) 27th Avenue SW Bridge Location Alternative ❑ (C) 29th Avenue SW - ❑ I do not live on the east side of 39th Street SW m ��! w J 19TH AVE SW ' 0 3 F- 2_1STAVE -SW. Lf�r—l 23ROAVESW A 25THAVESW 27TH AVE SW r'� t B 29TH AVE SW C ] 31STAVE SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? >CYes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ,Other ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW ,XI do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. "Name 38Pf-t) "Address r *City, State, Zip m f 1-7 *Phone Number 2?R 2_0 Y�� Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes ❑ No 2. How did you hear about this project? (Mark all that apply.) 1-1 Email Social Media Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Caller Coravity We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? XYes ❑ No 2. How often do you use this section of Collier Boulevard? KDaily ❑ Weekly ❑ Other 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. (A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW GREEN BLVD 17TH AVE SW I 1a � 19TH_AVE $W 21STAVE SW %3 23RD AVE SW m — G -nAT IS A 25THAVE-S-W_ 27TH AVE SW _ B N _ 29THAVE S 4 C a oaa o,t I 31STAVE SW Bridge Location— Altemative 1 GOL6E GATE MA N CANA ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge )(No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly j�OtherL ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW 7�jI do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name ta1 Z Please return comments to: 1 h-1ve1 5 � Growth Management Departmen7,,q.- *Address ��! 11 �/ Attn: Connie Deane, Communitys *City, State, Zip IV_t�� S ,� 1ZZZ 2885 Horseshoe Drive South Q� Naples, FL 34104 *Phone Number -� ���yQ�U You may also send your comments via e-mail to: ,• /l )) /l e A growth.management@collierccountyfl.gov *Email �1 liYl f7l{G,hf�O�Z�r�1,� i,tY?Ct! �o Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? qYes F1No 2. How did you hear about this project? (Mark all that apply.) Email Social Media �1 Roadway Message Sign ❑ U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Collier County We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard and Green Boulevard)? �North I1G] Yes ❑ No ._ GREEN BLVD 17TH AVE SW 2. How often do you use this section of Collier Boulevard? I LI_ ��... I "I"J" LLU 19TH AVE SW f-- Y. L :� aily ❑ Weekly — _� F 21STAVE SW ._ ❑ Other _ ` s= iE r_ 23RD AVE S+N 3. if you live on the east side of 39th Street SW, l._,� �� _ ' after reviewing the bridge location _ - - r1A. 25TH AVE SW - alternatives, which bridge location do you refer? Refer to the diagram on the right for 27THAVESW _ p g g B bridge locations. n 2.9Ti AVE SW X(A) Golden Gate Parkway Pfi4S-7 cNvtL J 11 I C El(B) 27th Avenue SW Bridge Location srsTAVE SW Alternative i GATE MA raNA� ww_ (C) 29th Avenue SW S-ec,vD ct/o,'G� GOLDEN' ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge � No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW �I' (C) The existing location, at 17th Avenue SW ❑ 1 do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. M *Name To>v *Address *City, State, Zip Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 *Phone Number -'n S_ -r / You may also send your comments via e-mail to: f 1 o growth.management@collierccountyfl.gov *Email � t rY1 I � c� � r�C1 ou5',� �, �C�) �tc/-'y 1 J � . r'tI o� Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. 6-4-7 PLAC6�- foe -11,1 DR-1b&6 - WOge-D 447 &/4T� l�i��� y �'�CQ rvO ,tar 5 7 �C��-i��/ l.UouC,,O 6e �i'�,r b s' d. 7y`fv n /r7 7 j'jrr�I riW Lc%&tG/, .8,f 4 -a''UGAIL- 2)iS7AA)Ct_ V1Od✓n �J�[ PKwY n b r J vT uJj ti7' yi e 69, be L=- Fl 7 a `7 �f/ I'' IJt� cu) <—/ J k-i06 (9 Itl PA-40 ����,`f �'%2 ��T� , � O A),07 1,0,)Y )'A) InY MA F1'& A7 GXY7-- Pkwy; Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes FINo - - 2. How did you hear about this project? (Mark all that apply.) 5i Email Social Media n Roadway Message Sign 0 U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes ❑ No x GREEN BLVD ®J — = > 17TH AVE SW 2. How often do you use this section of Collier Boulevard? Jy. i 19THAVESW .s Dail ❑ Weekly y Y f- s MTAVE .S.W ❑ Other _ V 23RDAVE SW 3. if you live on the east side of 39th Street SW _ , -- LID GATE P after reviewing the bridge location __ _ A?STHAVE SW alternatives, which bridge location do you prefer? Refer to the diagram on the right for �,� B 27THAVE SW bridge locations. 29TH AVE SW (A) Golden Gate Parkway C 31STAVE SW El(B) 27th Avenue SW Bridge Location o �ozs Me _Alternative r- ❑ (C) 29th Avenue SW - i ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge .)� No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly Other ❑ I do not live on the east side of Collier Boulevard fir, 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW XI do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. `Name TMIA_�lVC *Address --r'� 1 � �� c��TYc ► � � �� *City, State, Zip t `1 *Phone Number 3301— 2-a— six 2� *Email I t4eL _--mmon Mqqq Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? ❑ Yes P No 2. How did you hear about this project? (Mark all that apply.) Email Social Media Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. cA L►- COUXty We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes ❑ No 2. How often do you use this section of Collier Boulevard? Daily ❑ Weekly ❑ Other 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. (A) Golden Gate Parkway ❑ (B) 27th Avenue SW Bridge Location f Altemative ❑ (C) 29th Avenue SW -- _ - ❑ 1 do not live on the east side of 39th Street SW GREEN BLVD 0�- �r 1 GOLDEN GATE GA1 E 17TH AVE SW J m a W 19TH AVE SW I --: N 21STAVE SW N r S; 23RD AVE SW ;WY 25TH AVE SW �- 1 27THAVE SW t 29TH AVE SW i= +e� I 31STAVE SW rtius MAIN CANAL 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other WoU2,J N�—j L), cE 1 1 - ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name E L D X1v ? ' Please return comments to 37 � 2 q Ay L S Growth Management Department *Address Attn: Connie Deane, Community Liaison *City, State, Zip N Q i_f`5 ' �- .� �} l j� 2885 Horseshoe Drive South ( Naples, FL 34104 *Phone Number 2 3 q r S 3 �S You may also send your comments via e-mail to: growth.management@collierccountyfl.gov *Email Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes No 2. How did you hear about this project? (Mark all that apply.) Email � Social Media U Roadway Message Sign U.S. Mall Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. CAXW Cot4"ty r We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? ❑ Yes ❑ No `p ! . -A 4 2. How often do you use this section of Collier Boulevard? Daily ❑ Weekly , ❑ Other 3. ►f you live on the east side of 39th Street SW, after reviewing the brid a location � I GREEN BLVD i p J m L LI_ W O _ r _ GOLDEN GATE PKWY f g alternatives, which bridge location do you prefer? Refer to the diagram on the right for a ! r { bridge locations. H `� A Golden Gate Parkwa 1 ' () y�i/�.s ❑ (B) 27th Avenue SW Bridge Location �M11" Alternative GOL74M GALL MAIN CANA 1' (C) 29th Avenue SW .S,'`eD,1,P- ❑ I do not live on the east side of 39th Street SW 17TH AVE SW 19TH AVE SW N 21STAVE SW 23RD AVE SW ]A 25TH AVE SW 27TH AVE SW B 29TH AVE SW ]c 31STAVE SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard S. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW TA- ;�.- i C7 (B) Relocate across from 18th Avenue SWsii (C) The existing location, at 17th Avenue SW '--^ 39TH ❑ I do not use the CAT system OptionA FE, ❑ Other Option C ,� y Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. Name 1 11 / �t _ Please return comments to: "Address: 3�Growth Management Department Attn: Connie Deane, Community Liaison � 2885 Horseshoe Drive South Stale, to e, ip , f 44 ,jPL ;lT_ Naples, FL 34104 *Phone Number'2 �� ���You may also send your comments via e-mail to: I_�[I % growth.management@collierccountyfl.gov Email `�I.10�� IC�It'%1'iD4,,rLrQ,ey A,/y Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes No 2. How did you hear about this project? (Mark all that apply.) 2 Email ❑ Social Media ❑ Roadway Message Sign ICJ U.S. Mail ❑ Other `Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. CcAer COWILy We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes ❑ No 2. How often do you use this section of Collier Boulevard? Daily ❑ Weekly ❑ Other 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. (A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW GREEN BLVD 17TH AVE SW J I. ;� l 19TH AVE SW f fi 1 3' 21STAVE. SW . _i 23RD AVE SW l l GbLD GATE P IN . _ A 25TH AVE SW i 27TH AVE SW B j l 29TH AVE SW � 31 Bridge LocSTAVE SW ation-� °,� Alternative � reue ❑ 1 do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? VYes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW 41 do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name i�157e�a�� *Address *City, State, ZipG/��Ps,/ G 3 �/ *Phone Number Z 3q *Email t�0rlo�i �r�'�� t'�iv�. GOB► Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. 0A n 17,11 Ve ' .4 Evaluation �l 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? r � Yes LP No 4e,f— / �' 2. How did you hear about this project?` I{�1ark malt apply.) v ' Email Social Media Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. c if r county ao R We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? ),Yes ❑ No 2. How often do you use this section of Collier Boulevard? * Daily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. (A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW GREEN BLVD -J i j I 17TH AVE SW Q: 19TH AVE SW a 21STAVE SW LDE GATEPK4-y A 25TH AVE SW_ .- 27TH AVE SW 29TH AVE SW 1 ' �- C L� I i 31STAVE SW Bridge Locetlon Altemative GOLDEN GATE MAIN LANAI. 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly Other ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW ❑ 1 do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name *Address 3 a 3 o _-2 5-�cA Ave Ov *City, State, Zip G L 3(" 11-7 U. *Phone Number ;A3 I " 7 3093 *Email iJeM gV,(2#1+0 0 ao/, co✓v) Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. /3Lce,we- five ���cr �Yn �* k" A -},ye- ceg"�ey- Zahn �7�5 6 VaIe,?v,6E1% PL n V CO, C- h ,U V d i S C-s ✓1 / y7 �'Di.G WiP La D c'� 0 4/ e CavS° h e r►-,, e Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? IQYes No - 2. How did you hear about this project? (Mark all that apply.) 4 Email Social Media Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Coder C094ffty We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Pes ElNo 2. How often do you use this section of Collier Boulevard? XDaily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. (A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th A -Anue SW ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? _ Daily ❑ Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW (C) The existing location, at 17th Avenue SW ❑ I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. a� � *Name "��Q (S *Address 5(9 1:(3 At,-7— *City, State, Zip PA-PL-�L_S R_ 341 Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 *Phone Number �' 27�$`Z�� You may also send your comments via e-mail to: 'r growth.management@collierccountyfl.gov *Email �' �Qc f�) U� �Pr�IC�'�� `i {�!-+�� . LDv►-� Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. N{. U I�'��-�►�.) � rJ� ���,J i S � c� S_S �� � r r� 4^r.� ct�C,c C� _ ,` AdY.�t` 'v cJ t5,.] - Cti t . E Ls 1 �b r c. c r s-c: �' �-� �S ti !, , .� f ..� n _L�Cc �� ► C 1 i 4 J a r a �� �� � Ti•t�� ���n � � � ►.� rya- �'c.}� �-�-�`� �d �Sr.� '`i-- i Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? ed have been provided? Yes No 2. How did you hear about this project? (Mark it that apply,) 1-1 Email ❑ Social Media Roadway Message Sign ❑ U.S. Mail .90ther If not, what additional information *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want, your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. C.OAier County "Name *Add re: *City, S Please return comments to: 4Rq Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 *Phone Number LIYou may also send your comments via e-mail to: growth.mwagement@collierccountyfl.gov *Email 314q) Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Eva -uation 1. D' this meeting provide you with sufficient information on the proposed improvements? If not, what additional information uld have been provided? Yes No 2. How did you hear about this project? (Mar all that apply.) ❑ Email Social Media Roadway Massage Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes ❑ NO � 1 GREEN LVD Q 17TH AVE SW 2. How often do you use this section of Collier 1 „ Boulevard? - �- _ . �/ } `f I`� 19TH AVF SW �l 'D Pf Daily ❑Weekly 21STAVE SW ❑ Other L- {- — 3{ 23RD AVE SW 3. if you live on the east side of 39th Street SW, QQm _ G LGENGATePtiwv after reviewing the bridge location a; a 25THAVE SW alternatives, which bridge location do you i 27TH AVE SW prefer? Refer to the diagram on the right for - \r �, r-- bridge locations.t 6 H r 29TH AVE SW X(A) Golden Gate Parkway - i - r C ❑ (B) 27th Avenue SW Bridge Location — 6za • a 31STAVESW Alternative xna ❑ (C) 29th Avenue SW - F GOL6EWGAiEMA;MCA?4AL ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge WNo, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ A Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW X, do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name 44V *Address 3 �ep 2" IF how- f 1/ *City, State, Zip h&alef + �� `� (�� *Phone Number 2 3�� ���� 72- *Email L�i1 6prarlol/D�r�,%iGi "Car1 Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? 2. How did you hear about this project? (Mark all that apply.) Email Social Media I Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. �I We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Pa Yes ❑ No GREEN BLVD <' ! A r� ! a 17THAVE SW 2. How often do you use this section of Collier -- _ ' l -_I Boulevard? 19TH AVE SW fu ti - j U 3 ,Daily Weekly -,1 � _ .f = 2 STAVESW ❑ Other �. (�' 23RDAVE SW I �.. 3. ff you live on the east side of 39th Street SW, m _ 1 4 GOLDEN GATE PKM � after reviewing the bridge location 11 A25THAVE SW alternatives, which bridge location do you r r 27TH AVE SW prefer? Refer to the diagram on the right for bridge locations. B y 29THAVE SW _ f 54 (A) Golden Gate Parkway i �-� - - ' ' C � 31STAVE SW ❑ (B) 27th Avenue SW �jBrldg®Location fo �! fJ Altamative GOLDEN GAPE MAIN CANAI ❑ (C) 29th Avenue SW -- ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge JJ( No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly[� Other rev 0 ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW7 44-T ❑ (B) Relocate across from 18th Avenue SW o�� �r-�w';;;- ,' f� ❑ (C) The existing location, at 17th Avenue SW - -- - — .�..r.. �..�.. A . 39TH ST B - C do not use the CAT system " : OptionA • ` �,, a ❑ Other O lion C Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name t[{� *Address 21 74 42t Ste' *City, State, Zip ( *Phone Number 237- -/?? *Email CA5 I �cJ�od cb� Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? EJ "Yes [—] No 2. How did you hear about this project? (Mark all that apply.) Email Social Media Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. CO aer Cc��vitLy We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard 7yes h and Green Boulevard)? ❑ No 11�- GREEN BLVD . / L--�{. k-� n I 17TH AVE SW 2. How often do you use this section of Collier Boulevard? (Daily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location _ alternatives, which bridge location do you r�. prefer? Refer to the diagram on the right for bri ge locations. 7{A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ Bridge Location Altemative ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW i to j a I 19TH AVE SIN 4 g l� N 21STAVE SVV., _ m 'x ° 23RD AVE SW LJJLA5THAVE SW 7TH AVE SW GATE 29TH AVE � F III __31STAVE 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW M,I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. 9 *Name *Address Ol44, Ai it J Li *City, State, Zip N cral z S r� L ; L{ f *Phone Number `}`3I � ��� � ' � (9 C. � *Email 0 ct v t� C �117 3to (t MC4 i �- Co M Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Q/Yes ❑ No 2. How did you hear about this project? (Mark all that apply.) ❑ Email Social Media [gllkoadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Collier c wnty EM A We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard No h and Green Boulevard)? YES ❑ No GREEN BLVD 17TH AVE SW 2. How ften do you use this section of Collier Bo evard? Daily ❑ Weekly ❑ ther 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. AA) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW Go m —.i l r Bridge Location zB Alternative ,UL�EN c�A1E M ❑ I do not live on the east side of 39th Street SW J CO a w 19TH AVE:SW Ll!� 21STAVE SW �) x W 23RD AVE SW _A WH AVE- 1 27TH AVE SW 29THAVE SW 31STAVE SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gatp Parkway or Collier Boulevard? R Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed p estrian bridge? ❑ Daily ❑ Weekly ther ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW 1 do not use the CAT system ❑ ther Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name *Address (2 *City, State, Zip *Phone Number *Email.�LG� P Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box' provided at tonight's meeting, or send to Connie Deane at the address nt tha tnn rinht-hnnri rnrnar by Warinacrinu Anril on 9n99 Gmoilcr! nnmmcnfe - nlen nn mf�klc Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information ey have been provided? es ❑ No - 2. How did you hear out this project? (Mark all that apply.) 1-1 Email Social Media Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. CA%v Cot4m ;y We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? dYes ❑ No GREEN BLVD s '• � '--��--L- ° 17TH AVE SW 2. How often do you use this section of Collier levard? Daily ❑ Weekly ❑ Other 19TH AVE SW 21STAVE SW 3. if you live on the east side of 39th Street SW, �� - after reviewing the bridge location alternatives, which bridge location do you , prefer? Refer to the diagram on the right for N bridge locations. (A) Golden Gate Parkway ' , f ❑ (B) 27th Avenue SW Bridge Location Alternative ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW 23RD AVE SW ----4 LIJ 'ILIA 25TH AVE SW 27THAVESW _ 29TH AVE SW �_ 1 1 C 31STAVE SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge ®' No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? p Daily ❑ Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW s __- z El (B) Relocate across from 18th Avenue SWr:;,�t� .� _ , a �, f. Mo6L•LIER•BLV13"-- - ❑ C) The existing location, at 17th Avenue SW ;i39TH SMks 1N B C I do not use the CAT systemPt.( n A1 ,�► Qplan B '!q ❑ Other o lion C Q: Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name V-{-I r� *Address 3a- C99 1-0 r{ u Q SA V *City, State, Zip Nogr_ *Phone Number l_ Z Z��'OCSL10 *Email 14 L� Qw 01 �p Nt tyry-%- Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. 1� 0 Evaluation 1. Di this meeting provide you with sufficient information on the proposed improvements? If not, what additional information c Id have been provided? YesEl No 2. How did you hear about this project? (Mark a I that apply.) Email 1 Jocial Media Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes ❑ No G�RE"EN-BLVD 17TH AVE SW 2. How often do you use this section of CollierLl IL Boulevard? - y/�}� 1sTHAVE sw "aily ❑ Weekly _ _ �U, N 21STAVE SW ❑ Other _ _ _ _ r.-�.- _ � � 23f2DAVE 5W 3. if you live on the east side of 39th Street SW, 14 _ +, LbE cATE'- PKM_ after reviewing the bridge location - Y ��LJJ�_A,25TH_AVESW alternatives, which bridge location do you F 27THAVE SW prefer? Refer to the diagram on the right for ► _ B bridge locations. g H ! _ 29TH AVE Svv ❑ (A) Golden Gate Parkway [ C 31STAVE SW El (B) (B) 27WAvenue SW Bridge Location 1 Alternative t GOLflEN GATE �29th Avenue SW - -- ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes ' be encouraged to use the pedestrian bridge o, l wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW xT w 1 ❑ (B) Relocate across from 18th Avenue SW a' +�wEOL•LIER+BLVD ❑ (C) The existing location, at 17th Avenue SW A �a9aH r� to-rfot use the CAT system Option A ! rt- Option B w ❑ Other �� Option C Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name i-0 ! `f "Address 33 �v[- S *City, State, Zip � PL ` � /�� *Phone Number -.I 3 q - (, b - - 2-1 *Email Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? ❑ Yes R No 2. How did you hear about this project? (Mark all t apply.) Email Social Media Roadway Message Sign U.S. Mail Other "Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Co rer County H We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? dyes ❑ No GREEN BLVD-J 4�-J—'_�_• �il ` i i i 17TH AVE SW 2. How often do you use this section of Collier Boulevard? Daily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. (A) Golden Gate Parkway ❑ (B) 27th Avenue SW 19TH AVE SW S 21STAVE 5W_--- - - 23RDAVE SW y 1_ A 25TH AVE SW 27TH AVE SW _ / r D 29TH AVE SW EMM�f � o ^oaa ai I 31STAVE SW Bridge Location a4�. Alternative 1. ❑ (C) 29th Avenue SW i � - ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge r�No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW h(C) The existing location, at 17th Avenue SW ❑ 1 do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. M *Name &vt't *Address 3Z55 *City, State, Zip Q4&s , r' L 31�,U *Phone Number *Email Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. L.' I Mal of mil' • / I .�i+' �a f • W*14FArRo-ALA smog --viol Kelp. 1111, Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information uld have been provided? c Yes No 2. How did you hear about this project? (Mark all that apply.) Email 0 Social Media FA Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North nd Green Boulevard)? es ❑ No 2. How often do you use this section of Collier Boul yard? Daily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for 7a locations. ) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW GREEN BLVD 17THAVE SW �Jirv-� J m 19TH AVE SW - !F 215TAVEW 23RD AVE SW �r€P i1A _ED C�A 25TH AVE SW_ 27TH AVf SW - 29THAVE SW Bridge Location D a.2rS o� i 31STAVE SW AItemative __ 1C,oN CANAL 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gat arkway or Collier Boulevard? Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposZOth destrian bridge? ❑ Daily ❑ Weekly er isV\ ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C he existing location, at 17th Avenue SW I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name SCAB *Address3:1Soo Z1R�U� 4k -o *City, State, Zip f J N Pr� f:!-- ' 4 l 1 l *Phone Number 23`N Zc-� (--T *Email Oscf_�G-�}�J 2'q�� �i �0 Please return comments to: q9 Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. (3ev� �6"' *"k— �t_A+ t+- i� -�i.►� S��e�k o� a� �v�1� Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? kJ `X Yes ❑ No - 2. How did you hear about this project? (Mark all apply.) ❑ Email ❑ Social Media Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. C�COHHty_ 1 We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes [INo G�RE_E�N_BLVD > 1 17TH AVE SW I J 2. How often do you use this section of Collier -'`l _ - i 1in Boulevard? { _ 3 19THAVE SW Daily El Weekly 03 - '0 21STAyesw_ . ❑ Other 2 23RD AVE SW 3. If you live on the east side of 39th Street SW, after reviewing the bridge location _ _ � A-25THAVE SW_ alternatives, which bridge location do you prefer? Refer to the diagram on the right for � f " r A`. B 2rr�tAVE sw bridge locations. _ zsTHAVE SW /<(A) Golden Gate Parkway I, �~ C 31STAVE SW ❑ (B) 27th Avenue SW ❑Bridge Location Altemativa 1 GOLDEN GATE MA1N 0 ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge XNo, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly A Other N t Ve /Z ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. A(A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW ❑ 1 do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name 111t1ty QbV'r4 L �i� Please return comments to: 3 � � Z 4TH A VC ,, 14j Growth Management Department *Address e 1 (� Attn: Connie Deane, Community Liaison *City, State, Zip �� PLzf FL c� l �'� 2885 Horseshoe Drive South p Naples, FL 34104 *Phone Number 2 u You may also send your comments via e-mail to: growth.management@collierccountyfl.gov *Email ZVI-i'E'V. 601) { o Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. t 0 (p)L, "T S, c 1-1 ati/ © Pi-toVJ IJ Q� L o j/2 3 of �C 11-1 PAfSd1L7 Y-Afe `i f'.i vt wE cuV)&A,1t4.`7 Wive w,7K 2.sr�l !1V c+ 6yi c 'bto E W C Alet Or If14- rV E'V� 0 h N 6C O 1 (;o c a &ti a 4 re plkL4iy W('t l Tn4FF<< Ce`4�-I'Tf Fo4 _ lFt coney v77 Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes ❑ No 2. How did you hear about this project? (Mark all that apply.) Email Social Media Roadway Message Sign U.S. Mail ,,Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? fi Yes ❑ No 2. How often do you use this section of Collier { ji Boulevard? Daily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, m f after reviewing the bridge location a alternatives, which bridge location do you 4 prefer? Refer to the diagram on the right for bridge locations. N r (A) Golden Gate Parkway ❑ (B) 27th Avenue SW Bridge Location Alternative ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW GREEN BLVD 17TH AVE SW _ J m 1 M ��++ I•f �L w 19THAVESW �+ %} 21STAV.E $W , U � I � 0' 23RD AVE SW i A 25TH AVE $W 27H AVE SW,. ✓� !C 29THAVE 5W � I r 11 31STAVE SW GOLDEN GA7 E 61A N CANAL 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? % Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? '0 Daily ❑ Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard S. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW to (C) The existing location, at 17th Avenue SW ❑ 1 do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. IM *Name �e� e— �rG� Please return comments to: Growth Management Department 'Address Attn: Connie Deane, Community Liaison J {� 2885 Horseshoe Drive South *City, State, Zip v ►Q Jf s I Naples, FL 34104 *Phone Numbers/ � You may also send your comments via e-mail to: growth.management@collierccountyfl.gov *Email - �''^ Please provide your comments on the follo ing space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. <rld(-e f)�7 2 s� U s a"c .sV . Evaluation r e- se° : 41 v t- ti 4roo -ek 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? �0 � Yes No ow did you hear about this project? (Mark all that apply.) Email Social Media ❑ Roadway Message Sign U.S. Mall Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Cn�ire�r G�uK#�y We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. 2. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes ❑ No - GREEN BLVD 20 L 17TH AVE SW How often do you use this section of Collier Boulevard? JJ �.- f I I I f,-��� 1 W 19THAVE SW @8 Daily ❑ Weekly ❑ Other 3. If you live on the east side of 39th Street SW, after reviewing the bridge location a alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. y f (A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW Bridge Location J Alternative I { - w 'GOLDEN GATE MAW GANA 21STAVE SW 23RD AVE SW A 25TH AVE SW 27TH AVE SW t3 29TH AVE SW G 31 STAVE SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? #Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? [§ Daily ❑ Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW (C) The existing location, at 17th Avenue SW ❑ I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name A n C, ` ' ` " *Address 3 7 Vr J 14 ) S *City, State, Zip r`-' 4�° s �'" 3 Yin *Phone Number _ o�J "'J — V L *Email a G) P 11,E V, 1 �Gl " �7 WL-i Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. 4 h Y('/ , A/c mod J P-e-- I t'e j k) Iz� e4 d c'S V e y e>v,- tke S Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? ® Yes No 2. How did you hear about this project? (Mark all that apply.) Email F Social Media EJ Roadway Message Sign ® U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Cr11trer Gom"q We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? {i es El No 2. How often do you use this section of Collier Boulevard? o-daily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW GREEN BLVD 1 17TH AVE SW 1 m 19TH AVE sw - 8 21STAVE SW 23RDAVE SW a - OLDEN GATE PKWY A25THAVE SW I 27TH AVE SIN MH AVE SW C Bridge Location 315TAVE SW Alternative GOIpE j GATE M1IN CANAL ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gatee Parkway or Collier Boulevard? M- es, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily Fi4 eekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. b4(A) Relocate across from 20th Place SWLU - ❑ (B) Relocate across from 18th Avenue SW � �1;,, ."„ ;; r�'iq ❑ (C) The existing location, at 17th Avenue SW '--=co��JeR Bevo r A ,39TH 5 SW B C ❑ 1 do not use the CAT system ;-0 optionA �+-- Option B S El Other `.�j ' o tionc ,� a Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name "Addres *City, Si Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 "Phone Number (_J _�C ca-9 Uf Ja(o U You may also send your comments via e-mail to: "Email 1y �:s_l(� growth.management@collierccountyfl.gov .l � .'�LIL' •�..�-Q�I Q�) �'� '� ��j Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes No - 2. How did you hear about this project? (Mark all that apply.) ❑ Email ❑ Social Media Roadway Message Sign U.S. Mail Other "Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. 35 g We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? g Yes ❑ No 2. How often do you use this section of Collier Boulevard? ES Daily ❑ Weekly ❑ Other 3. If you live on the east side of 39th Street SW, m after reviewing the bridge location alternatives, which bridge location do you a prefer? Refer to the diagram on the right for bridge locations. N (A) Golden Gate Parkway GREEN BLVD J 17TH AVE SW - _ l m -� iJf I I a ICJ J 19TH AVE SW o 3: Z TAVEsW M `Q~' 33RD AVE SIN l GOLDEN GATE PKVVY ❑ (B) 27th Avenue Sllj(QBridge Location Altemative ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW 27TH AVE V�l ! B 29TH AVE 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? 4 Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily W Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. (1*0 Relocate across from 20th Place SVV ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW X I do not use the CAT system ❑ Either Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. �m :Name *Address Za6 Q W7 l�� 0 9-- S *City, State, Zip *Phone Number *Email Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth. management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes No 2. How did you hear about this project? (Mark all that apply.) Email ❑ Social Media � Roadway Message Sian U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. C" ier Co&iiT y We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? XYes ❑ No 2. How often do you use this section of Collier Boulevard? '( Daily ❑ Weekly ❑ Other 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ❑ (A) Golden Gate Parkway � i(B) 27th Avenue SW ❑ (C) 29th Avenue SW _ GREEN �BLVD 17TH AVE SW J 19THAVE SW 21STAVE SW Ito S 23RDAVE SW 4 �1 GOLDEN GATE I wy a q —_ _---. A 25TH AVE SW_ 27TH AVE SW B 29TH AVE SW G �, Altemative31STAVESW Bridge Lo ation GOLaEf� GATE M CAMAL- ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge �yNo, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW X1 do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name n *Address 2)w ;z�' �l *City, State, Zip �/t ���� *Phone Number 25- aCN 61 *Email Please return comments 9 to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? , , , y _/,:7 A, f_ / _ ] /I Yes Not i 2. How did you hear about this project? (Mark all that apply.) Q�(J/!.//��j i✓} 4041U,cJ O Email 0 Social Media Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, f " e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such,information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Cc) Wr Cotsvtty We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? El Yes Jai NO GREEN BLVD 17TH AVE SW 2. How often do you use this section of Collier Boulevard? ❑ Daily vWeekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ❑ (A) Golden Gate Parkway ❑ (B) 27th Avenue SW o lJll � j j m . I a J m � j — -j Bridge Location I _ I Alternative ❑ (C) 29th Avenue SW I — 1 `I do not live on the east side of 39th Street SW IPA m J ! 19TH AVE SW n 21STAVE SW N _ z 191923RD AVE SW 5f lIJ -• � - f =� rMul GOLDEN GATE MAIN LANAI 'A 25TH AVE SW 27TH AVE SW B 29TH AVE SW 31STAVE SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW `1I do not use the CAT system i❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name �" ` —�7i t� *Address *City, State, Zip !yX?LEs !F— J 91 1(p Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 *Phone Number 5�t� 790 IN? You may also send your comments via e-mail to: growth. management@collierccountyfl.gov *Email �TGU�� YU 191 ' J ►J �- "dill L, C�^l Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. UZ P 2�-"WS t t L w I'tom UA� E�t i n 0 'Pc? r3i I ^,�. j c U13E. T 61F �)L_u,,z) r v4-- tau LDIb-Ae, &<,, n 41-L-T- ALLc tra�S �� f� Lt.F Y m; ct_F IS I tJ �- � � 1•' +r.�' i �►.� 1Jcc w .�� US .'' l R� b� L-,) W w , �� I w� �+�L�C aTE i-y r 1AVALL T �� � ,- I r✓5 , ► �s t S s c �- � i,661)1 I55 vT_:S C)O —(—f G k)GsL S , i) ,E_� Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes ❑ No How did you hear about this oroiect? (Mark all that anolv.l Email FJ Social Media Roadway Message Sign U.S. Mail F1 Other *Please be advised - this information is used to contact you regarding this project and futurerubricmeetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Collier Cc)t*triy We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? >QYes ❑ No 2. How often do you use this section of Collier Boulevard? KDally [I Weekly r r❑Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ❑ (A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW F a v, . � -] �IBridge Location Alternative ❑ 1 do not live on the east side of 39th Street SW l GOLDS CA GREEN BLVD rr GATE PKW 17TH AVE SW m� J t9THAVE SW ,_21STAVESW S; 23RD AVE SW 9 A 25TH AVE $W 27TH AVE SW B 29TH AVE SW C 31STAVE SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ,,< I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other -<I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW C7 A Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name *Address l -1 1���� *City, State, Zip *Phone Number 6 t 5S Ll ,3L) t -- q s 3 -- 1 fA 3 .x�. 303 Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov *Email TV-4 Please provide your comments on the following pace provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box' provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. 04ft 41 ,rv< Ce edt�,, IV 94-W bg LO 0 A "- YoV i�l.� K� ' 1' �a L-; r A 1,1 Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes No 2. How did you hear about this project? (Mark all that apply.) Email Social Media Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are pubfrc records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Carer Co"nty We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes ❑ No 2. How often do you use this section of Collier Boulevard? dl�Dally ❑ Weekly ❑ Other 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ;�(A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW GREEN BLVD Q 17TH AVE SW 7 19TH AVE SW o s f U 23RDAVE SW GU DE GATE PKWY A25THAVE SW 27TH AVE SW y Y 29TH AVE SW C 7EBridge Location 31STAVE SW rniws Alternative GOLE)Eh GATE MAN CANAL ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily A Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name *Address �3 2 f Ac ) rV *City, State, Zip /tV a d L 911 k *Phone Number �- q, t 7 r K 24 20 *Email a Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. 6 (—/J sad � ��" �i a�1ci C-Abw CL Gyr,-.A 4 �} m, og U t �'n PxAr o. rs �'-� t► c5 cs t)�L�. rJd V'dVe I,.,mJl� fie o, qwm i A�� b cc+s-�Se If Irn45 �A 5'a�0- kC-a„szfi �0 39ti, Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes ❑ No 2. How did you hear about this project? (Mark all that apply.) Email Social Media � Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. CnT wl cott"l.y V We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? (Yes ❑ No 2. How often do you use this section of Collier Boulevard? I� Daily [I Weekly ❑ Other 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. Lam] (A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW GREEN BLV_D 17TH AVE SW J I m J f9THAVE SW — a 21STAVE SW N r- fi z3RD AVE SW _ A 25TH AVE SW 27TH AVE SW " �a , \ — B y 29THWESW` C �1I Bridge Location �-Uy31 STAVE SW � _ L_J Alternative GOLOEN GATE MAW CANAi- ❑ 1 do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? d Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily (Weekly ❑ Other ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW C) The existing location, at 17th Avenue SW I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name *Address 3 ��kG INVe- SW *City, State, Zip n,4g1 rr . F 1L 3� 11t-7 *Phone Number Llcl — fr_?J O — $ S96 *Email Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. S' rt J +u(cH of A,, Sw it is 44- V,Ci�. t�V "� T'1c l �SV[t CJri , h rev Ia cv�.rt CCL s'CC��v . ��l4�cr Yi�cl' ri C. 4".. K 1. f-,J 11,a— 1V4k V vst ��-�• n.-•� ( cc Et c t... T� I v c� , .�I .1 .� t-yF�-�• u �. V rc �{] {4 c� !-�1 ✓1�w i 10�, crl C r� F t ��ic.. �rs•�[ 1•"�"� t J -XL, o • I x r 1 , �-e s ke �'l}4v .-. ' • .. 1y1 - nrf� S �c� erl F�.c -1 1{s� • \ �. �• J N `{ 1 L/V llk lowt IF � L JV1 4" CtSJ y. l 1' C l "l a Li C •r s s •. � o� �,. � '�*-{ Flo. gLC/T4t J r 10' Cs " At,,.. So,�a-�.- o K C.� 44 l r . �i ��[i • �"� y .�i c..-•�'�+f- �.r . c� � t• I w c •� c.. •-�i � s � s4ti �) Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? [YYes No 2. How did you hear about this project? (Mark all that apply.) Email Q Social Media 0 Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Coder County 0 - I I COMMENT FORM Collier Boulevard Widening Project and Bridge Location Study • Public Information Meeting • April 6, 2022 • 5 p.m. to 7 p.m. • Golden Gate Community Center • 4701 Golden Gate Pkwy • Naples FL 34116 e are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? t(Yes ❑ No v How often do you use this section of Collier Boulevard? *aily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. )<(A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW _ GREEN BLVD 17THAVE SW � I m 19TH AVF GW LL❑"- 'j� d S 21STAVE SW & 23RD AVE S_ W m i GOLDEN GATE P wy Li ;_ 25TH AVE SW 27TH AVE SW �9 29TH AVE 5W, Bridge Location Q.� 31STAVE SW Alternative 1 1t, GOLDEN GAPE MAIN f.:ANAI. ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? es, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily eekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW go ) The existing location, at 17th Avenue SW not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name *Addre *City, *Phone *Email 4t Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov (Om Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. ROM ••WM Fam, l Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? could have been provided? YesNo If not, what additional information 2. How did you hear about this project? (Mark all that apply.) Email Social Media Roadway Message Sign U.S. Mail Other *Please be advised ` this information is used to contact you regarding this project and future public meetings. Under lorida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. �k CA.,- copy -J COMMENT FORM Collier Boulevard widening Project and Bridge Localion Study • Public Infonnallon Meeting • April 6. 2022 0 5 p.rn to 7 p in, • Golden Gate Community ('enter • 4701 Golden (,ate Pkwy • Naples. FL 341 16 e are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? AYes ❑ No 2. How often do you use this section of Collier Boulevard? 1� Daily ❑ Weekly ❑ Other 3. If you live on the east side of 39th Street SW, m after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. y (A) Golden Gate Parkway ❑ A 27th Avenue SW ❑ (C) 29th Avenue SW GREEN BLVD 0 J c�S � LDE GATE_P10 Y_f RXCIC �� Bridge Location *Ai) .11 Altemative i;U6{]EN GATE MAIN CANA ❑ 1 do not live on the east side of 39th Street SW 17TH AVE SW 19TH AVE SW N r 21STAVE _S_W 23RD AVE SW A 25TH AVE SW 27TH AVE SW B -j 29TH AVE SW C 31STAVE SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? AYes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly Other _ ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW tl do not use the CAT system Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name *Address :_mill `�)7" Ave `SW *City, State, Ziprf'�eS 3�(� *Phone Number *Email jh//D 3 �� Lkl-A01) Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. eve- 0A2!tire^ � -in�VIPY �g c�I� fiJ 7b Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information c uld have been provided? Yes No z. riow afa you near about tnis project-t (mark all that apply.) Email ❑ Social Media Roadway Message Sign ❑ u.s. Maul Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Ftori law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your a -mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Coiner Couvay to6-kASS &a, S Napv Ro 6 0t-SOVIJL0A6-- We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? -Yes ❑ No 2. How often do you use this section of Collier Boulevard? 1 Daily ❑ Weekly Other 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ❑ (A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW I GREEN BLVD n J 1 m 111 4 h a �3 Ov GOLDEN GATE PKWY 'I, 11_i 17TH AVE SW 19TH AVE SW N 21STAVE SW. m x 23RD AVE SW A 25TH AVE_3W 27THAVE SW ,J'j 29TH AVE SW — Brldge Location o r` � I II { 131STAVE a.zs' _o.t "- SW El Alternative Mlles GOLOEN 6XI C MAIN LANAI ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW G7 I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name S#aq A b ir,560, DA/(T *Address *City, State, Zip go"oe_s IrL/ *Phone Number A 3 e16 Y— 531 *Email sa23q W AOL, Cc Please return comments to: Growth Management Department - Attn: Connie Deane, Community Liaison' 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. 71" / P-E y0aC'0r6M1q _To Y2ovi &0- ) W 611r t «.St Co VaA,,., 7 0 rt) 121-. AJ r e`V)a, e N 1,gP1 - To 0 om 04, If-. (ap- r' ) q peopt T + �)O k DN [ AVC �r lw(( q riLfe 602 - laos� L_c.t► N 04_ Su a l)'+(3c)m i t r .f T*e_rReAll 1�;_ n4 r •V5 ro QN-f 7rfi`� T rev CU R I o u C.E « W.i t �` c o OK -E, W e Alr, - Hese- °To �zc=�- � _ �� �rz ► � = l �2�r� �.} C n4���=�-�,� �s t� �' fFS — CTti r ils y.fJN ese- �e(LoS E cu _ Oto ttp E ASS"itxaNce-l-hW Evaluation 2�AJ d s► N 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided?�.^ J ks r-�_A ' E-ee-i � CAS ( • //of Yes No B u f 7ay AAMA .P L 2. How did you hear about this project? (Mark all that apply.) TV Email Social Media .1 Roadway Message Sign U.S. Mail ® Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Coiiiar Cocxrity We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes ❑ No 2. How often do you use this section of Collier Boulevard? 15� Daily ❑ Weekly ❑ Other 3. /f you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. (A) Golden Gate Parkway OILS`� ❑ (B) 27th Avenue SW \F7 (C) 29th Avenue SW Q-9-6(`cLi 1 GREEN BLVD m — 17THAVE SW f 1 19TH AVE SW f 21STAVE SW iT, � 23RD AVE SW f _ �25TH AVE $1�(—_. � 27TH AVE sw y 3. 4FT A1,_ s, 1� ation 0 T� I 31 ST AVE SW AlternativeBridge GOi:OEfV CAFE MA1kCANA [] I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge Z No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW (C) The existing location, at 17th Avenue SW ❑ 1 do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name TA iLI 1 r 7 i f c Please return comments to: "qN *Address - 3Y91 " 7 E-i4y�y sco Growth Management Department Attn: Connie Deane, Community Liaison *City, State, Zip1�-�� �- "7 2885 Horseshoe Drive South Naples, FL 34104 *Phone Number 3��` 1�� r��� You may also send your comments via e-mail to: 1 growth.management@collierccountyfl.gov *Email if `� G/� ill �ib�S�C�C�h�-ur�I��41�j,� Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. 'CbkC,6t 76 19-60 A) 7H&'- 071Ff&Y C0MfIh;v7 s,#6�- 7 %F ct.,b6o l ;s P w 7 1-)-7 '77fi Ac/& SSLL) oe, Ac,,�F- sc0 ti c z� �l rim u� 6 1�J�� �� r� �� .4 ter✓ c�� �� > �� v �H� s r� _ Gc3C r";,?l Lotr q /3 UL 63-7 Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes No 2. How did you hear about this project? (Mark all that apply.) © Email Social Media Roadway Message Sign LJ U.S. Mail ❑ Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your a -mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. ca Wr c�HnLy Ulm COMMENT FORM Collier Gaulnvard Widening Protect and Fin0go Localion Study • Public Information Meeting • April 6. 2022 • S p.rn.. to 'i p.m. • Golden Oate Community Canker • 4701 Golden Gale Pkwy • Naples. Fl. 341 le We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes ❑ No GREEN BLVD 17TH AVE SW m� 2. How often do you use this section of Collier III r � If Boulevard? I, 1.--.) J _ I �' ! ,� 19TH AVE SW y 1 V .Daily ❑ Weekly, ''.�� I 0 ❑ Other ; �... r W 23RDAVE S R 3. ff you live on the east side of 39th Street SW, a GOLDEN GATE PK1NY after reviewing the bridge location p zrH AVE sw alternatives, which bridge location do you prefer? Refer to the diagram on the right for Q.. �' 27rHAVE sw bridge locations. a X 1{ w ,j �•r = 28TH AVE SW ❑ (A) Golden Gate Parkway 1 1 i� l C 31STAVE SW a Bridge Location o.zit • ii 7,,(B) 27th Avenue SW MIt« Alternative i (;OLDEN GATE MAIN CAN ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? `Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW C] (B) Relocate across from 18th Avenue SW - El (C) The existing location, at 17th Avenue SW -24 do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. a5P *Name a fir_ *Address 3 33 S) S lei *City, State, Zip-y"L�s" *Phone Number - 2-33 . _S 3 f 90111 *Email Please return comments to: 19 Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. u J cu a �Q (* ej i fit' �- ^v lP n -t F _ doo J 2 Evaluation Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? ,1 _ n .-t . . . I n r 1 _J n_1- _ , _L_ ---.I NYes No 2. How did you hear about tl LJ Email U Social Media U Roadway Message Sign W U.S. Mail ❑ Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Cn�irar Cotsnry COMMENT FORM Colliei Boulevard Widening Project and Bridge Localion Study • Public Information Meeting • April R, 2022 • S p,m. to 7 p, iTi, • Golden Gale Community Center • 4701 Golden Gale Pkwy • Naples, Ft, 34118 We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard NortP and Green Boulevard)? es ❑ No 2. How often do you use this section of Collier Boulevard? VDaily ❑ Weekly ❑ Other 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. IB) A) Golden Gate Parkway 27th Avenue SW ❑ (C) 29th Avenue SW 17THAVE SW I_/ 19THAVE SW 21 ST AV.,E SYV 23RD AVE SW 1 A 25TH AVE SW _ 27TH AVE SW B 29TH AVE SW r C ❑Bridge Locatio31STAVE SW n � �Z--� —;MI Altemative GULDEN GATE MAIN CANAL- - ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate! Parkway or Collier Boulevard? ;Yes, I'd be encouraged to use the pedestrian bridge p g ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ ) The existing location, at 17th Avenue SW I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. * F Name *Add ress *City, State, Zip *Phone Number *Email Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. a Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes F]No 2. How did you hear about this project? ( ark all that apply.) Email Social Media Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. CAwr Comvtty COMMENT FORM COW Boulevard Widening Project and Bridge Localion 5hidy • Puhhc Information Mee ing • APT4 6 2022 • 5 p m to 7 p m • ';olden Gate C,nrnimirnlV Centel • 4101 Golden Gate Phv✓y • Naples, rt. 141 In e are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard 7Ye and Green Boulevard)? s n No GREEN BLVD 2. How often do you use this section of Collier Boulevard? E] Daily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ❑ (A) Golden Gate Parkway ❑ (B) 27th Avenue SW E/(C) 29th Avenue SW 0 J m m L1 J {tit ► {r iBridge Locatlnn a 0.26 �ai! i Alternative C70EN GAIC MAIN CANA1 ❑ I do not live on the east side of 39th Street SW 17TH AVE SW a J 19TH AVE SW J U r 21STAVE SW r , ° 23RD AVE SW A 257H AVE SW 27TH AVE SW B 29TH AVE SW 31STAVE SW _ 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge h;a'No, I wouldn't use a pedestrian bridge .4-0 n ova vL err i-cS ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly 9 Other RO {-£ 1 ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ ( ) The existing location, at 17th Avenue SW p do not use the CAT system ❑ Other Option A Option B Option C Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name (' ill a'i -�' *Address — S� � f _sT S" *City, State, Zip Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 *Phone Number 23 q 0 -1 7 `C 2 \ You may also send your comments via e-mail to: *Email � E C f growth.management@collierccountyfl.gov � � � �- � �'�-a r'' �6Y(/f Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. N Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information cou have been provided? Yes n No 2. How did you hear about this project? (Mark all hat apply.) 1-1Email❑ Social Media Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Ca Ter Cot4nty We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? 9 Yes ❑ No 2. How often do you use this section of Collier Boulevard? X Daily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, �m after reviewing the bridge location alternatives, which bridge location do you i prefer? Refer to the diagram on the right for a bridge locations. ❑ (A) Golden Gate Parkway I 1, ❑ (B) 27th Avenue SW I Bridge Location °"oz l Altemative GOLnEN GA �((C) 29th Avenue SW- ❑ I do not live on the east side of 39th Street SW GREEN BLVD r j J 17TH AVE SW m � 19THAVE sw 21STAVE SW 23RDAVE SW A 25TH AVE SW 27TH AVE SW s 29TH AVE SW f C 31STAVE SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge XNo, I wouldn't use a pedestrian bridge ��(GU:� ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly *Other rarel ❑ 1 do not live on the east side of Collier Boulevard 6y 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ C) The existing location, at 17th Avenue SW I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name L t w Irwin *Address 3 75 J J 1 h l U e, (& *City, State, Zip Z21 r • ' V n .lin FL *Phone Number a — or��V —q qC)"5 *Email MAY-1QG �U y Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box' provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? 1�rYes ❑ No - 2. How did you hear about this project? (Mark all that apply.) Email Social Media Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. C(�iirer C014"ty We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes ❑ No GREEN BLVO �l __ , -J j 17THAVE SW 2. How often do you use this section of Collier Boulevard? �aily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, a after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ❑ (A) Golden Gate Parkway ❑ (B) 27th Avenue SW '0\'(C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW ti Bridge Location Alternative GOLDEN GATE 19TH AVE SW U � F . 215TAVE SW, 23RD AVE SW a 'A 25TH AVE SW 27TH AVE SW i 29TH AVE SW 31STAVE SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge *o, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bri ge?1 �p r ❑ Daily ❑ Weekly Other eV C� ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW jl do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Name �L� V " " .31 *Address s *City, State, Zip Iv ► { i r ' *Phone Number ` - I *Email � 4,Z1 Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes No 2. How did you hear about this project? (Mark all that apply.) Email ❑ Social Media [A Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. cr�� c��►�y ilr COMMENT FORM Curlier Boulovonl+AAdenuq Pralert anti BrlrtyR Lo"Non Sludy • Public Information Mealing • Apaq 8, 2022 • 5 p.m to 7 p,m • Gulden Ga to Community Cenlor • 4701 GOO en Gatti PHviy • Maples, FL adt 1a We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? ❑ Yes > N o 2. How often do you use this section of Collier Boulevard? ❑ Daily Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ❑ (A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW GREEN BLVD 17THAVE SW o19TH AVE SW i _ �21STAVESWrx- 23R❑AVE SW LDM GAT€-0 WY A 25TH AVE SW qq �, DB 27TH AVE SW 29TN_AVE 5W Bridge Locu Qom: I9� 31STAVE SW ation 1 _� � Alternative GDLE]EN GATE MAIN CAntfit- a I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily Kweekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW l -U fl, 121, (B) Relocate across from 18th Avenue SW (n �a 1r QM" ❑ (C) The existing location, at 17th Avenue SW --- - 9;H B- - �-� C ❑ I do not use the CAT system e' Op Ion A ul ❑ Other l,r,/ Option B _Sy''� �r t Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. 50 "Name �Ll ��Y C�L�h` *Address �IXDS Y al {.fA V "City, State, Zip *Phone Number cl70 , l 50 - 01 *Email 0'\0S/1') u"Y Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. i�il►�►�L�71!_�1'�S�/��%��G''�I�JlI'�ll.�lJ�I �/1i�1� Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? ,F[ Yes ❑ No 2. How did you hear about this project? (Mark all that apply.) ,Email Social Media Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? ❑ Yes ❑ No 2. How often do you use this section of Collier Boulevard? ❑ Daily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ❑ (A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW GREEN BLVD -J ; a0 17TH AVE SW 11II _ L f` W 19THAVE SW 21STAVE SW ( v ° 23RD AVE SW GOLDEN GATE F Y 1 / �� A 25THAVE SW :, r1 27TH AVE SW 29THAVE SW IN Bridge Location If�I"I� Ess �10k II t 31STAVE SW L_1 Alternative r,4LDF�1 GATE MAIN CAN ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW--* - a -t!• 1 '..- waver : >,uo�j ❑ (B) Relocate across from 18th Avenue SW --i—COGLlER-BL-VD -- ❑ (C) The existing location, at 17th Avenue SW A ❑ I 9TH5TSC., ., W �B .�. , I do not use the CAT system gplion A on l3 a �' ui ❑ Other' OOptiption C Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. ylD *Named�`M,Ct S 6F rlf *Address t__2 2'5 *City, State, Zip"-` 47 *Phone Number 3� *Email V c-- v^ ,:ALCA_ LJ i s �� ,,/\ Please return comments to: "q Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes ❑ No 2. How did you hear about this project? (Mark all that apply.) Email Social Media ❑ Roadway Message Sign ❑ U.S. Mail i2rother *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Cc�ilier Catsr�ty 52 A We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? 'es i\IC' GREEN BLVD a 17TH AVE SW 2.tow often do you use this section of Collier - - Boulevard? W 19ryAvSw _ J O ❑ Daily ❑ Weekly 3: � 21STAVE S]�l _ ❑ Other 0- l me _ - z I I - F a I �1 t._ �l o� I�', 23RD AVE SW 3. If you lire on the east side of 39th Street SW, —j GOLDEN GATE PKWY after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for a� '� ` , - �, �_ a7THAvesw z B bridge locations. a "' - ; -rf �'9TH AVC SW r t• ...❑tA , I l �_Golden Gate Pakway L�� . ��1,1 � �B) 27th Avenue SVV _0 Bridge Location a. ��gl I I 31STAVE3W 1 Alternative ❑ (C) 29th Avenue SVd o iJEN'GATE MAtMCAN� ❑ i do not live on the east side of 39th Street SW 4. 4a. if there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? �es, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ i do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly tither ❑ I do not live on the east side of CollitrBoulevard 5. if you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20tn Piace SVV ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW ❑ I do not use the CAT system ❑ Other -� �J 0 ,� CEA tCv7 Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. hl P `Blame &L/lm0 1.V_ ,«-Nk0J: l 7 �{ S�-E ( Cep �r *Address *City, State, Zip 6f9-C?. r!!5= Q&k *Phone Number 3 2 -3 f�2 *Email Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes No How did you hear about this project? (Mark all that apply.) ❑ Email F Social Media Roadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under FI rida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. 1 Co iar Couilty as F We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard No h and Green Boulevard)? es ❑ No 2. How often do you use this section of Collier Boulevard? Daily ❑ Weekiy ❑ Other 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ❑ (A) Golden Gate Parkway 1J (B) 27th Avenue SW ❑ (C) 29th Avenue SW I_-= ❑ I do not live on the east side of 39th Street SW GREEN BLVD 17TH AVE SW J 19TH AVE SW 0 21STAVE SW II A 25FHAVE SW 27TH AVE SW v f t r"� 29TH AVE SW J 31STAVE SW Bridge Location 001 o �1.-, Alternative ,cru-n[N71 ttAiNeawAr 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑-'Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? 0 Daily ❑ Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 29th r iace SW ❑ (B) Relocate across from 18th Avenue SW ,0 (C) The existing location, at 17th Avenue SW ❑ 1 do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. 'Name �n�.�nJo � � 19� ��a✓ � ilk Please return comments to: Growth Management Department Address Attn: Connie Deane, Community Liaison Ftt'' 7 2885 Horseshoe Drive South *City, State, Zip +���0— Naples, FL 34104 *Phone Numberc i 40 i 7 You may also send your comments via e-mail to: growth.management@collierccountyfl.gov "Email Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. T—OC4I+d cl, rrl s'�]un4 )wr� Q+ ���� I_�,' � Q>L;r % �C�r t'rc✓3-, � y �th AV,. bfi, to GiL!- A��,CA T�£ riFd�Tr�cnn h`KJQ4 if�C7�A J cry uIr II + 1u4 Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? hl"J Yes No i 2. How did you hear about this project? (Mark all that apply.) ❑ Email FISocial Media Roadway Message Sign U.S. Mail ' -Other 'Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Co ler Cou'aty We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. ❑o you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? FJ Yes ❑ No 2. How often do you use this section of Collier Boulevard? F� Daily ❑ Weekly ❑ Other 3. If you live on the east side of 39th Street SIN, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. r`^(A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW [ GREEN atvn ITTH AVE SW { m y 2iSTAVE -S ► a m of"-TPl I A 24TH AVE 5W 2TTH AVE SW B Bridge �3TH AVE SW 4.2¢ Q� 31STAVE SW Akemat vo�aahen S � �- ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, Shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? *Yes, I'd be encouraged to use the pedestrian bridge ❑ No, 1 wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and world not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW ,0'1 do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability orfamily status. "Name ! f % v "Address { `City, Stater, Zip 49 Please return comments to. Growth Management Department Attn: Connie Deane, Cornmungy Liaison 2885 Horseshoe Drive South Naples, FL 34104 *Phone Number You may afro send your comments via e-mail to: growth. management@colliercountyfl,gov "Email Please provide your comments on the Following space provided. If more space is needed, please use an additional sheet of paper. Place your Comments in the 'Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand comer by Wednesday, April 20, 2022. Emailed comments are also acceptable- , - r e-1 e r f�J7 f � 5 h ♦ �� �+ .,F � e- 11111=2204 MOM �� �+ i Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes ❑ No 2. How did you hear about this project? (Mark all that apply-)�� Email ❑ Social Media ❑ Roadway Message Sign U.S. Mail ether *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff vn your own to obtain updates on the project as well as checking the County website for additional information. Crier CA 3unxty r {IF�Y'!" y,,.r �] _il•r.r.y.1� �- :S 7, _ C-1 ti )1 r�.ja.� �� rr. .�sr raar,rSri--,7stclC'ii�10 m �.n-�` r�� l,l ... We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? ® Yes ❑ NO 2. How often do you use this section of Collier Boulevard? ® Daily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ® (A) Golden Gate Parkway 1 st option ❑ (B) 27th Avenue SW ® (C) 29th Avenue SW 2nd option a bridge Locaban o �ois� i o,5 -,�.��:� AI#amafive ❑ 1 do not live on the east side of 39th Street SW 17TH AVE S W 19TH AVE SW--_l `a 21STAVE SW _ S s 23RAVE 5W JM 2b—i F-1 AVE SV�' 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ® Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ® Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently,,or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SYJ ❑ A Relocate across from 18th Avenue SW ❑ (C) The. existing location, at 17th Avenue SW 50 1 do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. 'Name Heather Myers `Address 3541 27th Ave SW *City, State, zip Naples, Florida 34117 Phone Number 407-913-0429 *Email cintron_h@yahoo.com Please return comments to: Growth Management Department ?' Attn: Connie Deane, Community Liaison +r 2886 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth. management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box' provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. _My request would be to put the bridge location at eithher Golden Gate Parkway or 29th Ave SW. Golden Gate Parkway already has some of the infrastructure needed to accomodate the bridge and already holds a traffic light. The second suggestion would be 29th Ave SW due to no houses being at the end of the street since it is currently the location of the church. On 27th Ave SW we have many children that ride their bikes to the end of the road for school and utilize the bike rack and the amount of traffic the bridge at 27th Ave SW would cause would be very unsafe for our families. There are currently several accidents on Collier around 29th Ave SW so this may eliminate some if there is a bridge and a light to accomodate this traffic trying to turn onto 39th Ave and back on to Collier Blvd. Another concern that the families on 27th Ave SW have is the potential for a thru road and this would cause siginificant harm and worry on the parents that allow their children to ride their bikes or families that currently walk on this street. Golden Gate Parkway also makes sense due to the traffic that Cracklin Jacks attracts and would allow these visitors to safely proceed to Golden Gate Parkway and exit back on to Collier that way. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? 7 Yes No 2. How did you hear about this project? (Mark all that apply.) Email Social Media1:1 Roadway Message Sign 7U.S. Mail F Other `Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released If the county receives a public records request, you can refrain form including such information on this sheet You have the option of checking with the county staff on your own to obtaln updates on the project as well as checking the county website for additional information. r {IF�Y'!" y,,.r �] _il•r.r.y.1� �- :S 7, _ C-1 ti )1 r�.ja.� �� rr. .�sr raar,rSri--,7stclC'ii�10 m �.n-�` r�� l,l ... We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? ® Yes ❑ NO 2. How often do you use this section of Collier Boulevard? ® Daily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ® (A) Golden Gate Parkway 1 st option ❑ (B) 27th Avenue SW ® (C) 29th Avenue SW 2nd option a Bridge Locaban � Altemabve ❑ I do not live on the east side of 39th Street SW 17TH AVE S W 19TH AVE SW--_l `a 21STAVE SW _ S s 23RAVE 5W JM 2b—i F-1 AVE SV�' 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ® Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ® Meekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently,,or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SYJ ❑ A Relocate across from 18th Avenue SW ❑ (C) The. existing location, at 17th Avenue SW ® I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. 'Name Jeffrey Myers `Address 3541 27th Ave SW *City, State, zip Naples, Florida 34117 Phone Number 407-697-2816 *Email jmyers327@hotmail.com Please return comments to: Growth Management Department ?' Attn: Connie Deane, Community Liaison +r 2886 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth. management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box' provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. My request would be to put the bridge location at eithher Golden Gate Parkway or 29th Ave SW. Golden Gate Parkway already has some of the infrastructure needed to accomodate the bridge and already holds a traffic light. The second suggestion would be 29th Ave SW due to no houses being at the end of the street since it is currently the location of the church. On 27th Ave SW we have many children that ride their bikes to the end of the road for school and utilize the bike rack and the amount of traffic the bridge at 27th Ave SW would cause would be very unsafe for our families. There are currently several accidents on Collier around 29th Ave SW so this may eliminate some if there is a bridge and a light to accomodate this traffic trying to turn onto 39th Ave and back on to Collier Blvd. Another concern that the families on 27th Ave SW have is the potential for a thru road and this would cause siginificant harm and worry on the parents that allow their children to ride their bikes or families that currently walk on this street. Golden Gate Parkway also makes sense due to the traffic that Cracklin Jacks attracts and would allow these visitors to safely proceed to Golden Gate Parkway and exit back on to Collier that way. Putting the bridge on Golden Gate Parkway would allow larger vehicles with trailers to exit the side streets safely and enter on to Collier Blvd. safely at the light to either make a left or right turn on Collier which would be much safer. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? xX Yes No 2. How did you hear about this project? (Mark all that apply.) Email Social Media 0 Roadway Message Sign 7U.S. Mail F Other `Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released If the county receives a public records request, you can refrain form including such information on this sheet You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. r {IF�Y'!" y,,.r �] _il•r.r.y.1� �- :S 7, _ C-1 ti )1 r�.ja.� �� rr. .�sr raar,rSri--,7stclC'ii�10 m �.n-�` r�� l,l ... We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? ® Yes ❑ NO 2. How often do you use this section of Collier Boulevard? ® Daily ❑ Weekly ❑ Other 3. if you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ® (A) Golden Gate Parkway 1 st option ❑ (B) 27th Avenue SW ® (C) 29th Avenue SW 2nd option a Bridge Locaban � Altemabve ❑ I do not live on the east side of 39th Street SW 17TH AVE S W 19TH AVE SW--_l `a 21STAVE SW _ S s 23RAVE 5W JM 2b—i F-1 AVE SV�' 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ® Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ® Meekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently,,or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SYJ ❑ A Relocate across from 18th Avenue SW ❑ (C) The. existing location, at 17th Avenue SW ® I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. 'Name Mason Myers `Address 3541 27th Ave SW *City, State, zip Naples, Florida 34117 Phone Number 407-697-2816 *Email jmyers327@hotmail.com Please return comments to: Growth Management Department ?' Attn: Connie Deane, Community Liaison +r 2886 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth. management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box' provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. My suggestion would be to put the bridge and traffic light at Golden Gate Parkway or 29th Ave SW. Golden Gate Parkway makes sense because there is already a light and an intersection. 29th Ave SW makes sense because there are no houses at the end of the street like there are on 27th Ave. If the bridge is put on 27th Ave SW my parents will not feel safe with me riding my bike to the bus stop or down the street at all which would cause hardship on them to find someone to get me from the bus stop eventually. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? xX Yes No 2. How did you hear about this project? (Mark all that apply.) Email Social Media 0 Roadway Message Sign 7U.S. Mail F Other `Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. N We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? 9yes ❑ No GREEN sLVD 1rn-IAVE sw 2. How often do you use this section of Collier m Boulevard? M 19TH AVE SW J Daily ❑ Weekly 21STAVE.$w_ ' N ❑ Other hr 23RD AVE SW 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you a prefer? Refer to the diagram on the right for bridge locations. N F4 (Al Golden Gate Parkway GOLDEN GATE PKWY 25TH AVE SW 7` O 0.5 0 6 El(B) 27th Avenue SW { BridgeL! tion s _J AUma5ve EiFFxA�cMAlltri El(C) 29th Avenue SW - ❑ I do not live on the east side of 39th Street SW j 27TH AVE SW B 29TH AVE SW 31 STAVE SW 4. 4a. if there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? XYes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ® Weekly ❑ Other _ ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW 4sz;n� � LU �. El (B) Relocate across from 18th Avenue SWa.a�. �` a[: �Pm _ _ ❑ (C) The existing location, at 17th Avenue SW j� I do not use the CAT system Qptian A �� t _ Option B .� ❑ Other dptlon C ¢ Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. *Nam cl f��►. 112JIe-I 1/0� G *Address *City, State, Zip A6 �71 'Phone Number 'Emaila-1-=-- "q" Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountytl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. az 717 e J ZZ GrJCJ L /�,� G[ CCr Ct Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? Could have been provided? Yes No If not, what additional information 2. How did you hear about this project? (Mark all that apply.) Email ❑ Social Media VRoadway Message Sign U.S. Mai! Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form Including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Dodia, Sonal From: Ken Becker <klbkbecker@gmail.com> Sent: Friday, April 15, 2022 9:37 AM To: Growth Management Subject: Comment form on CR 951 widening EXTERNAL EMAIL: This email is from an external source. Confirm this is a trusted sender and use extreme caution when opening attachments or clicking links. Questions 1. 1 live within 1 mile of the project area between City Gate Boulevard and Green Boulevard. 2. 1 use this area to travel multiple times a day. 3. 1 live on the east side of 39th St. and I have reviewed the bridge proposals. Golden Gate Parkway makes the most sense to me. 4. 1 would not use a pedestrian Bridge however I think one would be useful for those people that bike or walk across the bridge at 25th Ave. 5. 1 do not use the Collier area transit system and don't have a preference on a location for bus stop 276. 1 will say that one is definitely necessary at one of those three locations due to the number of migrant workers that stack up along the guard rail on a daily basis. Comments Ken Becker 3676 29th Ave. SW. Naples, FL 34117 Phone number 239-595-3960 Email address klbkbecker@gmail.com I strongly believe that the bridge should be placed at Golden Gate Parkway and is the best location for this project. Wherever the bridge is placed a light is needed immediately at that location. Expecting traffic that want to go southbound to head north before making a U-turn is ridiculous and it's very dangerous to all motorist on Collier Boulevard. I know at one time there was discussions of having 25th Ave. be a East/West Thorough Way into the Estates. Even though that project may be years away I think by placing the bridge at Golden Gate Parkway now it would make for an easier transition in the future . Evaluation 1. 1 feel that the meeting provided significant information on the proposed improvements. 2. 1 heard about this project on social media. Sent from my iPhone 1 We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard No, tti and Green Boulevard)? Yes ❑ No 2. How often do you use this section of Collier Boulevard? �ily ❑ Weekly ❑ Other 3. !f you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? efer to the diagram on the right for �rGolden locations. Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW ❑ 1 do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or hike to dining, shopping, and entertainment along Golden Gate arkway or Collier Boulevard? es, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly her_5__- 0 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C he existing location, at 17th Avenue SW do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or ramify status. *Name 'AddressSP1°'� *City, State, Zip l J *Phone Number >� 17 *email Please return comments to: Growth Management Department Attm Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via a -mail to: growth. man agement@coilierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the `Comment Bo)' provided at tonight's meeting, or send to Connie Deane at the address 9t the tnn rinht-hand comer by Wednesday. April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? Yes No 2. How did you hear about this project? (Mark all t apply.) Email Social Media Roadway Message Sign U.S. Mail Other *Please be advised - this infomiation is used to contact you regarding this project and future public meetings. Under Fiodda law, e-mail and certain home addresses are public records once received by a govemment agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Co per Co4crsty We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard Nand Green Boulevard)? ._ Yes U NC 2. How often do you use this section of Collier Bou ard? Daily ij Weekly ❑ Other 3. H you live on the east side of 39th Street SIN, after reviewing the bridge location alternatives, which bridge location do you prefer?,ftfer to the diagram on the right for brid locations. (�) Golden Crate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW E1 I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden =encouraged or Collier Boulevard? to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pe strian bridge? ❑ Dail ❑ Weekly they y y 41 ❑ I do not live on the east side of Collier Boulevard S. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ A Relocate across from 18th Avenue SW ) The existing location, at 17th Avenue SW I do not use the CAT system ❑ Other Public participation it solicited without regard to race, color, national origin, age, sea, religion, disability or family status. Now -4ft . "Name S� "Address °City, State, Zip *Phone Number "Email Please return comments to: Growth Management [department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccourityfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Bwe provided at tonight's meeting, or send to Connie [wane at the address at the top right-hand comer by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information or, the proposed improvements? If not, what additional information could have been provided? yak+-- 2. How did you hear about this project? (Mark all that apply.) 1-1 Email Social Media ❑ Roadway Message Sign L .S. Mail ®tither 'Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you ran retrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information izr �a�artty We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. I . Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? es iJ Nc-, 2. How often do you use this section of Collier Boulev rd? aily ❑ Weekly ❑ Other 3. ff you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge cations. A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW CAEEN BLVD I MI AVE M z I A 19TH AVE SW V. 1 23RaAVE SW - �4 -- [- - J H AVER 17TH AVF SW X✓' - MH AVE SW C 31STAVE SW i J Anmobtic ❑ 1 do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Ga�Pay or Collier Boulevard? be encouraged to use the pedestrian bridge 9 P 9 ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed ped strian bridge? El Daily ❑ Weekly then _ ❑ 1 do not live on the east side of Collier Boulev rd 6. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 2767 The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ '5 he existing location, at IIth Avenue SVV do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national orlpin, age, sex, religion, disability or family status. M, - �N AN �� fr °Phone Number *Email " qw► Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2865 Horseshoe Drive South Naples, FL 34104 You may also send your comments via email to: growth. management@collierccountyfl. gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the 'Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand comer by Wednesday, April 20, 2022. Emaded comments are also acceptable. Evaluation t. Did this meeting provide you with sufficient information on the proposed improvements? If riot, what additional information could have been provided? F1fit[- ❑rr J - ..._. — -- _.�_ �— - --� �_ _., __._ - - _- 2. How did you hear about this project? (Mark all that apply.) Email F Social Media ❑ Roadway Message Sign ® U.S. Mail ❑ Other 'Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida lawn, e-mail and certain home addresses are public records ter:ce rived by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can retrain form including such information can this sheet. You have the option of checking with the county staff on your own to obtain updates on the projert as well as checking the county website for additional information Go �r sUa�y We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? p/Ires ❑ No 2. How often do you use this section of Collier Boulevard? gaily ® Weekly ® Other 3. N you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridg locations. A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW M I do not five on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate rkway or Collier Boulevard? es, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly Other 5 ALter e ❑ 1 do not live on the east side of Collier Boulevard s. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 28th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C The existing location, at 17th Avenue SVt not use the CAT system ❑ Other Public participation it solicited without regard to race, color, national origin, ape, sex, religion, disability or family status. `Name _, ] J f i% U WL _ 'Address ILL ?Ls,I." °City, State, Zip NAAo,` *Phone Number `Email Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth. management@collierccountyfi.gov Please provide your oomments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box' provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand comer by Wednesday, April 20, 2022. Emailed comments are aisc acceptable. Evaluation 1, Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? ® Yet 140 -,. How did you hear about this project? (Mark all that apply_) D Email ❑ social Media ❑ Roadway Message Sign ❑ U.S. Mail ❑ Other 'Please be advised a this information is used to contact you regarding this proved and future public meetings. tinder Florida lase, e-mail and certain home addresses are public records once received by a government agency_ If you do not want you( e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional infrxmation C_.oKni,;y We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? P,Yes ❑ NO _ — — GREEN BLVQ 7 17TH AVE SW 2. How often do you use this section of Collier i - °° 19TH AVE &W Boulevard?,� '0 E�.... lQ (Daily ❑ Weekly :- -� -r /f _ T -jQ !n 21ST..aVa-,5w_ [I Other _1J'I '` �I III�-�t� " i� 23RQ AVE SW 3. If you live on the east side of 39th Street SW, d ' F-1 iI L 1� I I 25TH AVE after reviewing the bridge location �I -- --LLLL alternatives, which bridge location do you �a �`-" 277HAVE prefer? Refer to the diagram on the right for = h k _; B bridge locations. m � ` 1— , -J 29THAVE "9, I (A) Golden Gate Parkway 31SIT AVE ❑ (B) 27th Avenue SW Brldge Locationjp Altemative =GOL-DEN-GATEMAINtRNAL - _.� ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shoppling, and entertainment along Golden Gate Parkway or Collier Boulevard? X Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily *,Weekly ❑ Other ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or farniiy status. "Name *Address 56CLOO" [ L)IE2- *city, State, Zip —3 Ll 7 - *Phone Number '2 + 2n *Email LZA61 17 - ! 1y i L(O 4:::-" Ak L LL , C_ a-1 Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, EL 34104 You may also send your comments via a -mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box' provided at tonight's meeting, or send to Connie Deane at tfle address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. 12 Ekrl L_ I G 6 i &i-1*r C- -V-7 2 Qc �/1fo r �� w2GLn.eG ►� D c7l-Z_ mil. C r` "ZI1�E� UI� 14L n L Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? ❑ Yes �No -c�IA Win.: � 1 2. How did you hear about this project? (Mark all that apply.) ❑ Email Social Media ❑ Roadway Message Sign; U.S. Mail AOther *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information, co�,er cry We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1 Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? 2. How often do you use this section of Collier Boulevard? X Daily ❑ Weekly ❑ Other 3. it you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. X (A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? X Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily X Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW y� E';m ❑ (B) Relocate across from 18fih Avenue SW ��. ��xi• _., - � ❑ (C) The existing location, at 17th Avenue SW " B - C j,K l do not use the CAT system - Option option B ❑ Other Option C P blic participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. s 0 r 'Name �DJf+ a1U WS "Address _37DS 29 �ti vk SL1r "City, State, Zip Z L = G `3 'Phone Number /, S/ - 33 & 3 9 - "Email Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth. management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper_ Place your comments in the "Comment Bob' provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. NJ , � r _rH Evaluation �vT act E ✓ �Jn� Fi G D�J , 0 5 % v TAI VI r V D ru o '1�/FFf/G 4 C f - — aAj ro J , Z77H 151 M U TAeAVC _ �. _ C ■r_ f'�., r,C.1 /�/J lv � fiJ �i�/Z� I�;�" 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? N Yes No 2. How did you hear about this project? (Mark all that apply.) Email F Social Media ® Roadway Message Sign 11 U.S. Mail El Other Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. if you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Go��er C�ouniy I We are looking for your input to assist yourwith planning by answeand ring a few questions below.igning the best to serve motorists, bicyclists and pedestrians. Please provide 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? _ GREEN BLVD 17TH AVE SW _ 2. How often do you use this section of Collier i, '- 1 j -� 4 ..- n �sTHaysw I Boulevard? r�� j--- .._ _ L- 21STAVE SW ❑ Daily C]Weekly 4 , zsROA AVE SW Other 0� ,t,.a�t UL inyv� �-� ; , 1 � `� ,LI_ W1 3. if you live on the east side of 39th Street SW, zGOLDEN GATE PKsTHAVESW _ A ... __ - after reviewing the bridge location a' alternatives, which bridge location do you z7THAVE sw.__ prefer? Refer to the diagram on the right for B ` a, 29TH AVE SW .., bridge locations. ` C (A) Golden Gate Parkway R 1 31STAVE SW Br'kdge Loaabon ❑ (B) 27th Avenue SW L—!Altemab'40 COWFN t,',A t: •'`[ F'f4L ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden o din n Parkwayath Street SW nd entertainment along Golden (crossing the canal), would it encourage you to walk or bikeg shopping, Gate Parkway or Collier Boulevard? ❑ Yes, 1'd be encouraged to use the pedestrian bridge ® No, l wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly % Othei - ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW m 18th Avenue SW;Ja`" " ❑ (B) Relocate across from �ea1iUiE�BUV --�- -, ❑ (C) The existing location, at 17th Avenue SW �gTK - BBC . F' l do not use the CAT system opt1on s .. option c ❑ Other - - ..�- rd to race, color, national origin, age, sex, religion, disability or family status. Public participation is solicited without rega *Name *Address *City, State, Zips*PhoneNumber 1S ©1$ *Email *1 ' 'D V 1 ES i c) "MAIL C13 M Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.managernent@collierccountyfi.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. i s.l W A a-ev H A -r~ t F 'Vrk E 6(_k ❑CiL-0 C ATZL-D o r•] ale r Sp . ] t't ��a rr aM �-r o F Epe A tito� PAD - " 0 A A I�. �r r t rt l t_ tT w 6L - ` R t-E oKM0 Cot R 1I W tJ SE (zC 2S J ' 4 f hJ -afWeIc Li CH7� � r N-11 t ~C12 C+t.J eo �(� IS -So AT 1 T k461 f �(_-Ct DAIS • A K• T HA T -59-tPr4e vs L� rt L' fi11S �S �IZAFF 1c� a l.�ll� iCi-{ ' s:37.i� {� D�I7►=+ � id MIT. 1 F TS A tii D �N ¢ E� L-N NHS i d + MPr9-c D L.►[ K r✓ }� t 61n1 i �C ' 5 m ft y-r sS - -A T JQ 14 �rj C1�os5 .CKE is Q-t 1C,$ f i T nio-W --CR6:; oNr SQF6 6P-rw4 is �Co T D �D+✓t� C'+ -Cry ram' R s CU CA 4 SrP_ft Wr v'n� pC4ATE �t ' H Ts DO P-A= Ir E �iLt ,•(o E 1 pJ. A f4 a T ig+ ()LSo �Jalrt-iJ L K c, i T b�vT H e - rs ' g'�AoAiQ0 Ha�� AM tr'� w - � � -� i3�,vT •cat ►J w E a J �A 1�i0 � -i .�- Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? K �r!'FE Lfi �u LT HE x Ala A is - ❑ Yes x❑ No 2. How did you hear about this project? (Mark all that apply.) ❑ Email IN Social Media ❑ Roadway Message Sign ❑ U.S. Mail ❑ Other `Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request. you car+ refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? XYes ❑ No 2. How often do you use this section of Collier Boulevard? Daily ❑ Weekly ❑ Other 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ,;!�4A) Golden Gate Parkway ❑ (B) 27th Avenue SW C 29th A S W GREEN BLVD W17THAVESW µ j { I 19THAVE SW 21STAVE SW 23RDAVE SW Q GOCflETLAraAP WY �STH AVE_$W 27T- H AVE 5V� B 29TH AVE SW 1 I T 31STAVESW Bridge Location u zs o ! 1 Aliamative � �,p6p��A�MA�NCAtvat ❑ ( ) venue ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian Fridge 'I�No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW X C) The existing location, at 17th Avenue SW do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. `Name *Add ress *City, State, Zip ✓V Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 1 � "`Phone Number el)9( b .7 UYou may also send your comments via e-mail to: * �} ' 0 /ygrowth.management@collierccountyfl.gov Email 1 !/ �„ \1 Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 9. Did this meeting provide you with sufficient information on the proposed improvements? could have been provided? ex Yes ❑ No If not, what additional information 2. How did you hear about this project? (Mark all that apply.) Email Social Media JjkA oadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. April 7, 2D22 Attn: Connie Deane, Community Liaison From: Yana St. John RE: Comment on proposed project on Collier Blvd between City Gate Boulevard North and Green Boulevard. As a resident of 271h Ave SW, I navigate this area multiple times throughout the day. It is always difficult and time consuming to leave and return home due to the current access route. After attending the meeting on April 61h, and reviewing the study results, I believe the Golden Gate Parkway Bridge is the optimum decision. I would much rather wait at a light knowing that I will eventually have a light to turn to go as opposed to waiting ad infinitum on the kindness and mercy of other drivers and the assertiveness of the drivers in front of me. Sincerely, Yana St. John 3161 27th Ave SV Naples, FL 3411 We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes ❑ No 2. How often do you use this section of Collier Boulevard? j Daily ❑ Weekly �-3T,�e nS El Other . 3. If you live on the east side f 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. (A) Golden Gate Parkway p (B) 27th Avenue SW ❑ (C) 29th Avenue SW j I GREEN BLVD 1TTHAVE SW — w I 19TH AVE SW l - 0 —'-4 21STAVE SW I+ EfLM 23RDAVE SW -6 IbENI GATE P .2srHAVE sw--- -i� 2TTH AVE SW i - ' 29TH AVE SW ;C 31STAVE SW Sr4e Location 9 gas 9. Alternative �£-SkTEi�iAMlCANAt ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? O NI r� C f� es, I'd be encouraged to use the pedestrian bridge f f A7,e-�CF/G No, I wouldn't use a pedestrian bridge AS wel/ ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the p. oposed pedestrian bridge? ❑ Daily KWeekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW -fpI do not use the CAT system ❑ Other Public participation is solicited without regard to race: color, national origin, age, sex, religion, disability or family status. i `Name Please return comments to: Z1 OJ Growth Management Department `Address Attn: Connie Deane, Community Liaison "City, State, Zip f 2885 Horseshoe Drive South Naples, FL 34104 *Phone Number -3 You may also send your comments via e-mail to: J, growth.management@collierccountyfl.gov "Email M t 1� ` t 1 Please provide your commen s on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information_ on the proposed improvements? c uld have been provided? Yes ❑ No If not, what additional information 2. How did you hear about this project? (Mark all that apply.) ❑ Email ❑ Social Media 1�f Roadway Message Sign U.S. Mail Other 'Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. CIELI ]Y CONSTRUCTION iNCORPORATED GENERAL CONTRACTOR 3161 27th Ave. SW NAPLES, FL 34117 239-263-7010 CGCO53501 April 7, 2022 Attn: Connie Deane, Community Liaison From: John Mincieli RE: Comment on proposed project on Collier Blvd between City Gate Boulevard North and Green Boulevard. As a lifelong resident, and as a general contractor in Naples for over 30 years I would like to further address the bridge/intersection options. After attending the meeting on April 6', and reviewing the study results, I believe the Golden Gate Parkway Bridge is the optimum decision. There are X amount of residents needing to get from Golden Gate Parkway to 39thSt., and X amount of residents needing to get from 39th St., to Golden Gate Parkway (this daily number is only growing). Our current situation is a well-known nightmare. During busy times the current means of crossing over onto the bridge requires not only courteous, but conscious drivers in both oncoming lanes to yield way. This is a very dangerous situation which has led (as you are aware) to multiple accidents weekly. Neither of the other bridge options alleviate this problem, they only spread it out, and let the road (turning lanes) hold more vehicles in waiting. The same applies when trying to make a right turn and quickly get into the left lane to get onto Golden Gate Parkway. Regarding the time added to the signal cycle, which is the only drawback, we understand there will be added time for the light to fully complete its cycle. However, when you take into account the time lost waiting for other drivers to be courteous and yield, the time delay is a wash. But when you take into account the safety factors involved, it is very clear, to not only me, but unanimously with all the other neighbors I have talked with about the situation, that the Golden Gate Pkwy. Bridge is the best option for all concerned. Sincerely, Jahn �Minci�ellli.. �— We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? �es ❑ No 2. How often do you use this section of Collier Boulevard? -�rDaily ❑ Weekly ❑ Other 7 _� �c5 3. If you live on t e east side of 39th Stree , after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. �X) Golden Gate Parkway ❑ (B) 27th Avenue SW (C) 29th Avenue SW GaEE N_ sLvn 17TH AVE 5W L _ J isTHAVE SW a 23RDAVE SW L i W KV1fY I25THAVE W 27THAVE SW B uai j� 29TH AVE SW r` C 31STAVE SW Bridge Location o 025 Mrs Altamative ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge XNo, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily "eekly ❑ Other C��Q \% tU r.� ��- ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ ( ) The existing location, at 17th Avenue SW do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. "Name `Address -_ 7qQ 27 X4/4 Cl,) 'City, State, Zip "Phone Number 1z XC/ - 0 "Email Please return comments to: Growth Management Department Attn: Connie Deane; Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl gov Please provide your comments on the following space provided. If more space is needed. please use an additional sheet of paper, Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information cou d have been provided? `I'es No --- 2. How did you hear about this project? (Mark all that apply.) El Email Social Media oadway Message Sign U.S. Mail Other "Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or horse address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking witty the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Coder Cour�y April 7, 2022 Attn: Connie Deane, Community Liaison From: Violette Jequier RE: Comment on proposed project on Collier Blvd between City Gate Boulevard North and Green Boulevard. As a resident of 27th Ave SW, I navigate this area multiple times throughout the day. I agree with my neighbors that it is always difficult and time consuming to leave and return home due to the current access route. After attending the meeting on April 6t", and reviewing the study results I believe the Golden Gate Parkway Bridge is the optimum decision. A traffic light at Golden Gate Parkway will greatly improve the access to and from home for me. Sincerely, Violette Jequier We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? P,Yes ❑ NO _ — — GREEN BLVQ 7 17TH AVE SW 2. How often do you use this section of Collier i - °° 19TH AVE &W Boulevard?,� '0 E�.... lQ (Daily ❑ Weekly :- -� -r /f _ T -jQ !n 21ST..aVa-,5w_ [I Other _1J'I '` �I III�-�t� " i� 23RQ AVE SW 3. If you live on the east side of 39th Street SW, d ' F-1 iI L 1� I I 25TH AVE after reviewing the bridge location �I -- --LLLL alternatives, which bridge location do you �a �`-" 277HAVE prefer? Refer to the diagram on the right for = h k _; B bridge locations. m � ` 1— , -J 29THAVE "9, I (A) Golden Gate Parkway 31SIT AVE ❑ (B) 27th Avenue SW Brldge Locationjp Altemative =GOL-DEN-GATEMAINtRNAL - _.� ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shoppling, and entertainment along Golden Gate Parkway or Collier Boulevard? X Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily *,Weekly ❑ Other ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW I do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or farniiy status. "Name *Address 56CLOO" [ L)IE2- *city, State, Zip —3 Ll 7 - *Phone Number '2 + 2n *Email LZA61 17 - ! 1y i L(O 4:::-" Ak L LL , C_ a-1 Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, EL 34104 You may also send your comments via a -mail to: growth.management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box' provided at tonight's meeting, or send to Connie Deane at tfle address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. 12 Ekrl L_ I G 6 i &i-1*r C- -V-7 2 Qc �/1fo r �� w2GLn.eG ►� D c7l-Z_ mil. C r` "ZI1�E� UI� 14L n L Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? ❑ Yes �No -c�IA Win.: � 1 2. How did you hear about this project? (Mark all that apply.) ❑ Email Social Media ❑ Roadway Message Sign; U.S. Mail AOther *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information, co�,er cry We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1 Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? 2. How often do you use this section of Collier Boulevard? X Daily ❑ Weekly ❑ Other 3. it you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. X (A) Golden Gate Parkway ❑ (B) 27th Avenue SW ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? X Yes, I'd be encouraged to use the pedestrian bridge ❑ No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily X Weekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW y� E';m ❑ (B) Relocate across from 18fih Avenue SW ��. ��xi• _., - � ❑ (C) The existing location, at 17th Avenue SW " B - C j,K l do not use the CAT system - Option option B ❑ Other Option C P blic participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. s 0 r 'Name �DJf+ a1U WS "Address _37DS 29 �ti vk SL1r "City, State, Zip Z L = G `3 'Phone Number /, S/ - 33 & 3 9 - "Email Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth. management@collierccountyfl.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper_ Place your comments in the "Comment Bob' provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. NJ , � r _rH Evaluation �vT act E ✓ �Jn� Fi G D�J , 0 5 % v TAI VI r V D ru o '1�/FFf/G 4 C f - — aAj ro J , Z77H 151 M U TAeAVC _ �. _ C ■r_ f'�., r,C.1 /�/J lv � fiJ �i�/Z� I�;�" 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? N Yes No 2. How did you hear about this project? (Mark all that apply.) Email F Social Media ® Roadway Message Sign 11 U.S. Mail El Other Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. if you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Go��er C�ouniy I We are looking for your input to assist yourwith planning by answeand ring a few questions below.igning the best to serve motorists, bicyclists and pedestrians. Please provide 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? _ GREEN BLVD 17TH AVE SW _ 2. How often do you use this section of Collier i, '- 1 j -� 4 ..- n �sTHaysw I Boulevard? r�� j--- .._ _ L- 21STAVE SW ❑ Daily C]Weekly 4 , zsROA AVE SW Other 0� ,t,.a�t UL inyv� �-� ; , 1 � `� ,LI_ W1 3. if you live on the east side of 39th Street SW, zGOLDEN GATE PKsTHAVESW _ A ... __ - after reviewing the bridge location a' alternatives, which bridge location do you z7THAVE sw.__ prefer? Refer to the diagram on the right for B ` a, 29TH AVE SW .., bridge locations. ` C (A) Golden Gate Parkway R 1 31STAVE SW Br'kdge Loaabon ❑ (B) 27th Avenue SW L—!Altemab'40 COWFN t,',A t: •'`[ F'f4L ❑ (C) 29th Avenue SW ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden o din n Parkwayath Street SW nd entertainment along Golden (crossing the canal), would it encourage you to walk or bikeg shopping, Gate Parkway or Collier Boulevard? ❑ Yes, 1'd be encouraged to use the pedestrian bridge ® No, l wouldn't use a pedestrian bridge ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly % Othei - ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW m 18th Avenue SW;Ja`" " ❑ (B) Relocate across from �ea1iUiE�BUV --�- -, ❑ (C) The existing location, at 17th Avenue SW �gTK - BBC . F' l do not use the CAT system opt1on s .. option c ❑ Other - - ..�- rd to race, color, national origin, age, sex, religion, disability or family status. Public participation is solicited without rega *Name *Address *City, State, Zips*PhoneNumber 1S ©1$ *Email *1 ' 'D V 1 ES i c) "MAIL C13 M Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.managernent@collierccountyfi.gov Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. i s.l W A a-ev H A -r~ t F 'Vrk E 6(_k ❑CiL-0 C ATZL-D o r•] ale r Sp . ] t't ��a rr aM �-r o F Epe A tito� PAD - " 0 A A I�. �r r t rt l t_ tT w 6L - ` R t-E oKM0 Cot R 1I W tJ SE (zC 2S J ' 4 f hJ -afWeIc Li CH7� � r N-11 t ~C12 C+t.J eo �(� IS -So AT 1 T k461 f �(_-Ct DAIS • A K• T HA T -59-tPr4e vs L� rt L' fi11S �S �IZAFF 1c� a l.�ll� iCi-{ ' s:37.i� {� D�I7►=+ � id MIT. 1 F TS A tii D �N ¢ E� L-N NHS i d + MPr9-c D L.►[ K r✓ }� t 61n1 i �C ' 5 m ft y-r sS - -A T JQ 14 �rj C1�os5 .CKE is Q-t 1C,$ f i T nio-W --CR6:; oNr SQF6 6P-rw4 is �Co T D �D+✓t� C'+ -Cry ram' R s CU CA 4 SrP_ft Wr v'n� pC4ATE �t ' H Ts DO P-A= Ir E �iLt ,•(o E 1 pJ. A f4 a T ig+ ()LSo �Jalrt-iJ L K c, i T b�vT H e - rs ' g'�AoAiQ0 Ha�� AM tr'� w - � � -� i3�,vT •cat ►J w E a J �A 1�i0 � -i .�- Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information could have been provided? K �r!'FE Lfi �u LT HE x Ala A is - ❑ Yes x❑ No 2. How did you hear about this project? (Mark all that apply.) ❑ Email IN Social Media ❑ Roadway Message Sign ❑ U.S. Mail ❑ Other `Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request. you car+ refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? XYes ❑ No 2. How often do you use this section of Collier Boulevard? Daily ❑ Weekly ❑ Other 3. If you live on the east side of 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. ,;!�4A) Golden Gate Parkway ❑ (B) 27th Avenue SW C 29th A S W GREEN BLVD W17THAVESW µ j { I 19THAVE SW 21STAVE SW 23RDAVE SW Q GOCflETLAraAP WY �STH AVE_$W 27T- H AVE 5V� B 29TH AVE SW 1 I T 31STAVESW Bridge Location u zs o ! 1 Aliamative � �,p6p��A�MA�NCAtvat ❑ ( ) venue ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian Fridge 'I�No, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily ❑ Weekly ❑ Other ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW X C) The existing location, at 17th Avenue SW do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. `Name *Add ress *City, State, Zip ✓V Please return comments to: Growth Management Department Attn: Connie Deane, Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 1 � "`Phone Number el)9( b .7 UYou may also send your comments via e-mail to: * �} ' 0 /ygrowth.management@collierccountyfl.gov Email 1 !/ �„ \1 Please provide your comments on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 9. Did this meeting provide you with sufficient information on the proposed improvements? could have been provided? ex Yes ❑ No If not, what additional information 2. How did you hear about this project? (Mark all that apply.) Email Social Media JjkA oadway Message Sign U.S. Mail Other *Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. April 7, 2D22 Attn: Connie Deane, Community Liaison From: Yana St. John RE: Comment on proposed project on Collier Blvd between City Gate Boulevard North and Green Boulevard. As a resident of 271h Ave SW, I navigate this area multiple times throughout the day. It is always difficult and time consuming to leave and return home due to the current access route. After attending the meeting on April 61h, and reviewing the study results, I believe the Golden Gate Parkway Bridge is the optimum decision. I would much rather wait at a light knowing that I will eventually have a light to turn to go as opposed to waiting ad infinitum on the kindness and mercy of other drivers and the assertiveness of the drivers in front of me. Sincerely, Yana St. John 3161 27th Ave SV Naples, FL 3411 We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? Yes ❑ No 2. How often do you use this section of Collier Boulevard? j Daily ❑ Weekly �-3T,�e nS El Other . 3. If you live on the east side f 39th Street SW, after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. (A) Golden Gate Parkway p (B) 27th Avenue SW ❑ (C) 29th Avenue SW j I GREEN BLVD 1TTHAVE SW — w I 19TH AVE SW l - 0 —'-4 21STAVE SW I+ EfLM 23RDAVE SW -6 IbENI GATE P .2srHAVE sw--- -i� 2TTH AVE SW i - ' 29TH AVE SW ;C 31STAVE SW Sr4e Location 9 gas 9. Alternative �£-SkTEi�iAMlCANAt ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? O NI r� C f� es, I'd be encouraged to use the pedestrian bridge f f A7,e-�CF/G No, I wouldn't use a pedestrian bridge AS wel/ ❑ I do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the p. oposed pedestrian bridge? ❑ Daily KWeekly ❑ Other ❑ I do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ (C) The existing location, at 17th Avenue SW -fpI do not use the CAT system ❑ Other Public participation is solicited without regard to race: color, national origin, age, sex, religion, disability or family status. i `Name Please return comments to: Z1 OJ Growth Management Department `Address Attn: Connie Deane, Community Liaison "City, State, Zip f 2885 Horseshoe Drive South Naples, FL 34104 *Phone Number -3 You may also send your comments via e-mail to: J, growth.management@collierccountyfl.gov "Email M t 1� ` t 1 Please provide your commen s on the following space provided. If more space is needed, please use an additional sheet of paper. Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information_ on the proposed improvements? c uld have been provided? Yes ❑ No If not, what additional information 2. How did you hear about this project? (Mark all that apply.) ❑ Email ❑ Social Media 1�f Roadway Message Sign U.S. Mail Other 'Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or home address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking with the county staff on your own to obtain updates on the project as well as checking the county website for additional information. CIELI ]Y CONSTRUCTION iNCORPORATED GENERAL CONTRACTOR 3161 27th Ave. SW NAPLES, FL 34117 239-263-7010 CGCO53501 April 7, 2022 Attn: Connie Deane, Community Liaison From: John Mincieli RE: Comment on proposed project on Collier Blvd between City Gate Boulevard North and Green Boulevard. As a lifelong resident, and as a general contractor in Naples for over 30 years I would like to further address the bridge/intersection options. After attending the meeting on April 6', and reviewing the study results, I believe the Golden Gate Parkway Bridge is the optimum decision. There are X amount of residents needing to get from Golden Gate Parkway to 39thSt., and X amount of residents needing to get from 39th St., to Golden Gate Parkway (this daily number is only growing). Our current situation is a well-known nightmare. During busy times the current means of crossing over onto the bridge requires not only courteous, but conscious drivers in both oncoming lanes to yield way. This is a very dangerous situation which has led (as you are aware) to multiple accidents weekly. Neither of the other bridge options alleviate this problem, they only spread it out, and let the road (turning lanes) hold more vehicles in waiting. The same applies when trying to make a right turn and quickly get into the left lane to get onto Golden Gate Parkway. Regarding the time added to the signal cycle, which is the only drawback, we understand there will be added time for the light to fully complete its cycle. However, when you take into account the time lost waiting for other drivers to be courteous and yield, the time delay is a wash. But when you take into account the safety factors involved, it is very clear, to not only me, but unanimously with all the other neighbors I have talked with about the situation, that the Golden Gate Pkwy. Bridge is the best option for all concerned. Sincerely, Jahn �Minci�ellli.. �— We are looking for your input to assist with planning and designing the best roadway to serve motorists, bicyclists and pedestrians. Please provide your input by answering a few questions below. 1. Do you live or work within 1 mile of the project area (Collier Boulevard between City Gate Boulevard North and Green Boulevard)? �es ❑ No 2. How often do you use this section of Collier Boulevard? -�rDaily ❑ Weekly ❑ Other 7 _� �c5 3. If you live on t e east side of 39th Stree , after reviewing the bridge location alternatives, which bridge location do you prefer? Refer to the diagram on the right for bridge locations. �X) Golden Gate Parkway ❑ (B) 27th Avenue SW (C) 29th Avenue SW GaEE N_ sLvn 17TH AVE 5W L _ J isTHAVE SW a 23RDAVE SW L i W KV1fY I25THAVE W 27THAVE SW B uai j� 29TH AVE SW r` C 31STAVE SW Bridge Location o 025 Mrs Altamative ❑ I do not live on the east side of 39th Street SW 4. 4a. If there was a pedestrian bridge at Golden Gate Parkway from 39th Street SW (crossing the canal), would it encourage you to walk or bike to dining, shopping, and entertainment along Golden Gate Parkway or Collier Boulevard? ❑ Yes, I'd be encouraged to use the pedestrian bridge XNo, I wouldn't use a pedestrian bridge ❑ 1 do not live along the east side of Collier Boulevard and would not use the bridge 4b. How often would you use the proposed pedestrian bridge? ❑ Daily "eekly ❑ Other C��Q \% tU r.� ��- ❑ 1 do not live on the east side of Collier Boulevard 5. If you currently, or plan to, use the Collier Area Transit (CAT) system, which location would you prefer for Bus Stop 276? The existing Bus Stop 276 is located at "C" in the following figure. ❑ (A) Relocate across from 20th Place SW ❑ (B) Relocate across from 18th Avenue SW ❑ ( ) The existing location, at 17th Avenue SW do not use the CAT system ❑ Other Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. "Name `Address -_ 7qQ 27 X4/4 Cl,) 'City, State, Zip "Phone Number 1z XC/ - 0 "Email Please return comments to: Growth Management Department Attn: Connie Deane; Community Liaison 2885 Horseshoe Drive South Naples, FL 34104 You may also send your comments via e-mail to: growth.management@collierccountyfl gov Please provide your comments on the following space provided. If more space is needed. please use an additional sheet of paper, Place your comments in the "Comment Box" provided at tonight's meeting, or send to Connie Deane at the address at the top right-hand corner by Wednesday, April 20, 2022. Emailed comments are also acceptable. Evaluation 1. Did this meeting provide you with sufficient information on the proposed improvements? If not, what additional information cou d have been provided? `I'es No --- 2. How did you hear about this project? (Mark all that apply.) El Email Social Media oadway Message Sign U.S. Mail Other "Please be advised - this information is used to contact you regarding this project and future public meetings. Under Florida law, e-mail and certain home addresses are public records once received by a government agency. If you do not want your e-mail or horse address released if the county receives a public records request, you can refrain form including such information on this sheet. You have the option of checking witty the county staff on your own to obtain updates on the project as well as checking the county website for additional information. Coder Cour�y April 7, 2022 Attn: Connie Deane, Community Liaison From: Violette Jequier RE: Comment on proposed project on Collier Blvd between City Gate Boulevard North and Green Boulevard. As a resident of 27th Ave SW, I navigate this area multiple times throughout the day. I agree with my neighbors that it is always difficult and time consuming to leave and return home due to the current access route. After attending the meeting on April 6t", and reviewing the study results I believe the Golden Gate Parkway Bridge is the optimum decision. A traffic light at Golden Gate Parkway will greatly improve the access to and from home for me. Sincerely, Violette Jequier 8-9 Z- 15 A: E� % 2 b o I 7Z ig ig g E t 44 E Z d E E �E 0 all EZE< ER El From: annl �.ra To: Kirbv. Felida; Ross. Colleen/ORL Ca: TT�h gPge; C•rnmPr. Bill/SWF Subject: (EXTERNAL] FW: Collier Blvd. Widening and Bridge Location study Date: Tuesday, Mardi 8, 2022 2:19:30 PM Attachments: rn-002.ona maoe003.ona FYI — see below. Please add Mr. and Mrs. Mitchell to the distribution list for the project and the public involvement log. Parcel No 3605,1320007 FT Name /Atltlress MRCHFL4 GARy 1=8,IOANA 3899 27TH AVE SW Site Address-D' Iaimer 38NZTrH AVE SW Sae City NAPLES Site Zene'Note 34117 City NAPLFS 5db FL ZIP 34117 7131 1 4826 9tD 1461 Seddon T - Ramie_ Asres 'Estimated 4626 i3490014614B26 26 49 26 2.61 Legal GOLDEN GATE EST UNIT 28 W 1127R OF 146 MiISubJConde 334900-60L0ENWTEES1UNrT28 Schaal M511ag¢Ra Ot„r"Calculatinm ToW Use Cotle01 51NGLE FAMILY RESIDENTIAL 4.a99 6.7155 11.6045 Latest Sales History 2021 Certified Tax Rail (no<,a:,ice are r.<.d a..,o ra..�a..<�arhyl nwi.�. m tM1..ae1 Dale Baak-Page Amount III Value 11/12/96 2249-923 50 (,) Improved Value 11/O6/96 2247-2030 $60,000 (_) Marketvu- (-) Say.nur Ham. (-) A a—d Value I Homestead (_) Schaal TaxabFe Value (-) Additional H.mestead (_) —bl¢ Value Lorraine M. Lantz, AICP Principal Planner coer county Collier County Capita/ Projects, Planning, Impact Fees A Program Management NOTE: Email Address Has Changed 2685 S. Horseshoe Drive, Suite 8103 Naples, FL 34104 Phone: (239) 252-5779 From: Lantzl-orrame Sent: Tuesday, March 8, 2022 2:15 PM TO:'gjmitchellhouse@centuryl ink. net' <gjmitchell house@centurylink. net> Subject: Collier Blvd. Widening and Bridge Location Study Mr. and Mrs. Mitchell, S 156,fi00 f 3Tl,158 $533.758 6 2 .,z. 5295,656 f 25,000 S 270,S5S Is 25,000 f 215,555 I have been informed that you inquired about the Collier Blvd. Widening Project and the related Bridge Location Study public information meeting. We are in the early stages of planning the meeting. I can confirm that we will be having a open house style public meeting on Wednesday, April 6, 2022 from 5:00 pm to 7:00 pm. The meeting will be held at Golden Gate Community Center, Auditorium, 4701 Golden Gate Parkway, Naples, FL 34116. Additional information will be available as it is developed. I will add your contact information to our project distribution list. Please contact me if you have any questions as the project begins to move forward. Respectfully, Lorraine Lorraine M. Lantz, AICP Principal Planner coiiie-r Comity Collier Caunty Capital Projects, Planning, Impact Fees 8 Program Management NOTE: Email Address Has Changed 2685 S. Horseshoe Drive, Suite #103 Naples, FL 34104 Phone: (23" 252-5779 Lorraine. Lanfx.C011lerCounfvFL.co V Under Florida Law, a -mail addresses are public records. If you do not want your e-mail address released in response to a public records request, do not and eI,d,ni, mail to this entity. Instead, contact this offce by telephone or in writing. From: Kirby, Felicia To: Dodia, Sonal Subject: FW: Collier Boulevard Bridge Location Study Date: Tuesday, April 5, 2022 12:56:30 PM Attachments: Collier Blvd Widening - Public Information Meeting Newsletter.pdf Hey Sonal, Can you please add this to the comments log (excel) and save the email as a PDF and save to "Log Backup" folder? Thanks! Felicia From: Lantz Lorraine <Lorraine.Lantz@colliercountyfl.gov> Sent: Friday, April 1, 2022 10:25 AM To: Kirby, Felicia <Felicia.Kirby2@jacobs.com> Subject: [EXTERNAL] FW: Collier Boulevard Bridge Location Study Please add to the Public Involvement report. Thanks! Respectfully, Lorraine Lorraine M. Lantz, AICP Principal Planner o i t C�a141.ty Collier County Capital Projects, Planning, Impact Fees & Program Management NOTE: Email Address Has Changed 2685 S. Horseshoe Drive, Suite #103 Naples, FL 34104 Phone: (239) 252-5779 Lorraine.Lantz@CollierCountyFL.gov From: LantzLorraine Sent: Friday, April 1, 2022 9:51 AM To: 'Jared R. Brown' <irbl@iohnsoneng.com> Subject: RE: Collier Boulevard Bridge Location Study Hi Jared, Attached is the Public Information Newsletter regarding the meeting on April 6th. The information available at the public meeting will be placed on the Transportation Engineering website on April 6th. http://www.colliercountyfl.gov/transportationproiects Please let me know if you need any additional information. Respectfully, Lorraine Lorraine M. Lantz, AICP Principal Planner i o ler County Collier County Capital Projects, Planning, Impact Fees & Program Management NOTE: Email Address Has Changed 2685 S. Horseshoe Drive, Suite #103 Naples, FL 34104 Phone: (239) 252-5779 Lorraine.Lantz@CollierCountyFL.gov From: Jared R. Brown <jrb(@iohnsoneng.com> Sent: Friday, April 1, 2022 8:52 AM To: LantzLorraine <Lorraine.Lantz(@colliercount)lfl.gov> Subject: Collier Boulevard Bridge Location Study EXTERNAL EMAIL: This email is from an external source. Confirm this is a trusted sender and use extreme caution when opening attachments or clicking links. Hi, Lorraine. With the message boards up I have friends and neighbors asking about the 951 widening, and specifically the canal crossing near the Parkway. What portions of the Collier Boulevard Bridge Location Study are publicly available or when might they become available? Thanks -jared Jared R. Brown, P.E., LEED AP JOHNSON ENGINEERING, INC. 2350 Stanford Court Naples, Florida 34112 Phone: 239.280.4321 0brown6Diohnsoneng com www.'ohnsonengineering.com Under Florida Law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by telephone or in writing. From: iTh ,Bag Z Diana cralmr Subject: RE: ALT #4 Design Flaw for 39 th St.. bridge Hi Ms. Diane Stalzer, Currently, the land from 3 tat Ave. SW to the south is privately own, therefore, the County cannot extend 39th St SW beyond 3 tat Ave. SW. The project was not budgeted to purchase this private property(ies), therefore, the improvement will stop at 3lst Ave. SW. Respectfully, Bee Thao, P.E. Senior Project Manager Transportation Management Services Department Transportation Engineering Division 2885 South Horseshoe Drive, Naples, Florida 34104 Phone: 239.252.5844 Cell: 239.206.0194 Bee.Thao@colliercountyfl.gov -----Original Message ----- From: Diane Stalzer <dstalzer@embargmail.com> Sent: Friday, April 8, 2022 11:32 AM To: ThaoBee <Bee.Thao@colliercountyfl.gov> Subject: Re: ALT #4 Design Flaw for 39 th St.. bridge EXTERNAL EMAIL: This email is from an external source. Confirm this is a trusted sender and use extreme caution when opening attachments or clicking links. OK Good deal..Question; would it be possible to extend 39 st SW, from 31 at Ave. S.W.south to City Gate Blvd.? possible traffic relief route. ----- Original Message ----- From: "ThmBee" <Bee.Thao@colliercountyfl.gov> To: "Diane Stalzer" <dstalzer@embargmail.com>, "LantzLormine" <Lorraine.Lantz@colliercountyfl.gov> Sent: Thursday, April 7, 2022 3:48:13 PM Subject: RE: ALT #4 Design Flaw for 39 th St.. bridge Good Afternoon Diane, Thank you for taking some time out from your busy schedule to join the County for the Public Informational Meeting for the Collier Blvd. Widening Project from Green Blvd. to City Gate Blvd. Thank you for noticing and pointing out the error in the ALT #4 design of the potential bridge crossing locations. The error is an oversight on the County and the consultant during the printing process. If ALT #4 is selected, there will be a southbound left turn lane from Collier Blvd. to 39th Street SW at Golden Gate Parkway. The error will be corrected and posted in the County website, httns://urldefense.com/v3/_hito://www.colliercountyfl.goy/transi2ortationproiects_:!!BScixuoO7ltTeg!UK7Fhz5KTInIU l laV WOgbXH_e4635OQBJSnbcalldvdJgXiPPnmTCt l Af3HaDiwen4H_Wg$ , by early next week. Again, thank you for bringing this error to the County's attention. Please do not hesitate to contact me if your have any other questions or comments regarding the project. Respectfully, Bee Thao, P.E. Senior Project Manager Transportation Management Services Department Transportation Engineering Division 2885 South Horseshoe Drive, Naples, Florida 34104 Phone: 239.252.5844 Cell: 239.206.0194 Bee.Thao@colliercountyfl.gov -----Original Message ----- From: Diane Stalzer <dstalzer@embargmail.com> Sent: Thursday, April 7, 2022 10:37 AM To: ThmBee <Bee.Thao@colliercountyfl.gov>; LantzLorraine <Lorraine.Lantz@colliercountyfl.gov> Subject: ALT #4 Design Flaw for 39 th St.. bridge EXTERNAL EMAIL: This email is from an external source. Confirm this is a trusted sender and use extreme caution when opening attachments or clicking links. Yesterday I attended the meeting at Golden Gate Community Center for proposed new 39th ST. bridge and noticed a slight flaw in design #4. When southbound on Collier Blvd. at the new proposed bridge and traffic light at Golden Gate Parkway (ALT #4) there is NOT a left hand turn lane to access 39th St.(there is an existing one now )like at Green Blvd.After eating at Mel's Diner , I would have to go to Green Blvd. to access 39th ST. S.W,or go to City Gate Blvd. make a U-Turn and come back to new bridge to access 39th St, S.W.. I live on 29th Ave.S.W.This is a tremendous inconvenience for all residents from 19th Ave.S.W. to 3lst Ave. S.W.to have access to 39th ST.S.W. from Green Blvd. only. Thank You. Dennis Stalzer Under Florida Law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by telephone or in writing. From: ThaoBee To: Kirby, Felicia Cc: DeaneConnie Subject: [EXTERNAL] FW: 951 Widening Comments Date: Friday, May 13, 2022 2:13:20 PM Hi Felicia, Please see below for my responses back to Mr. Rozansky. Respectfully, M,e JLtl, Senior Project Manager Transportation Management Services Department Cott' County Transportation Engineering Division 2885 South Horseshoe Drive, Naples, Florida 34104 Phone: 239.252.5844 Cell: 239.206.0194 Bee.Thao(@colliercountyfl.gov From: ThaoBee Sent: Wednesday, May 11, 2022 3:19 PM To: 'Christopher Rozansky' <crozansky@sbcgloba1.net>; Growth Management <Growth.Management@colliercountyfl.gov> Cc: Beth Rozansky <beth.a.rozansky@gmail.com>; MessamMarlene <Marlene.Messam@colliercountyfl.gov>; DeaneConnie <Connie.Deane@colliercountyfl.gov> Subject: RE: 951 Widening Comments Good Afternoon Chris, Firstly, please accept my sincere apology for not providing a follow up sooner. I thought these were additional comments for the project as part of the Public Information Meeting (PIM) and was not expecting to provide a correspondence until are comments from the PIM are addressed. Please see below (turquoise) texts for responses to your comments. If you have any other questions concerning the projects, please don't hesitate to contact me. Respectfully, Senior Project Manager Transportation Management Services Department U PIeT COUnty Transportation Engineering Division 2885 South Horseshoe Drive, Naples, Florida 34104 Phone: 239.252.5844 Cell: 239.206.0194 Bee.Thao(@colliercountyfl.gov From: Christopher Rozansky <crozansky(@sbcglobal.net> Sent: Monday, April 18, 2022 11:32 AM To: ThaoBee<Bee.Thao(@colliercountyfl.gov>; Growth Management <Growth.ManagementPcolliercount)zfl.gov> Cc: Beth Rozansky <beth.a.rozansky(@gmail.com> Subject: 951 Widening Comments EXTERNAL EMAIL: This email is from an external source. Confirm this is a trusted sender and use extreme caution when opening attachments or clicking links. Hello, 1. The bridge over the canal to 39th should be in line with Golden Gate Parkway. The current intersection alignment is dangerous, especially at rush hour; New Bridge will either be at GGP, 27th or 29th. Existing Condition of Bridge at 25th is being eliminated. 2. Consideration should also be given to a 2nd bridge at 29th, but only if the residents nearby support it. One reason for this is the extreme rate of speed some people drive on 39th. I live a bit further north on 1 lth Ave SW east of 951 and would separately appreciate anything that could be done to slow people down on 39th. I refuse to allow my kids to use the paved path along the canal because of how fast people drive on 39th, frequently using it as a short cut from Green to White Blvd east at +50 mph; Based on existing traffic volumes, at this time there is only a need for 1 bridge to serve this area. Therefore, only one bridge is being considered. 3. Is there any way to slow folks down on 951? I regularly notice people traveling at 60-70 mph approaching GGP; Posted Speed limit along CR951 is 45 MPH. There are limited physical "Design" modifications that can be done to slow traffic along the 6-Lane corridor. Traffic along 951 is monitored/patrolled by CC Sheriff to help reduce speeding. 4. Please eliminate the curb cuts that don't have turn lanes in the median. Drivers slow down and nearly stop in the flow of traffic while trying to slow down. Very dangerous! There will be no median openings without associated turn lanes 5. Please add sidewalks on both sides south of GGP. People, sometimes with children walk in the grass or right next to the road; There will be a Pathway along the west side of Collier Boulevard and along the west side of 39th Street for pedestriansibicyclists 6. Is there room for bike lane? Cyclists sometimes ride along the edge of 951 practically in the edge of the driving lane since there's no path. Many people use bikes in GGC; Four foot Bike lanes are being included in the new facility 7. Please maintain a landscaped median. The current landscaping is nice and improves the aesthetic of GGC; Landscaped median will be re-established once roadway project is complete. 8. Eliminate the ability of vehicles to turn north on 951 from 23rd Ave SW by Ace Hardware. They can use the intersection at GGP. That turn movement will be eliminated with the new design I hope there's opportunity to review the next set of draft plans. There will be another Public Meeting at 90% Plans Milestone Thanks again, Chris Rozansky 3893 1Ith Ave SW Under Florida Law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by telephone or in writing. Dodia, Sonal From: ThaoBee <Bee.Thao@colliercountyfl.gov> Sent: Wednesday, May 11, 2022 3:00 PM To: Chris Subject: RE:4464121 Qustion Hi Chris, My apology, we currently do not have a set schedule. What we have is a high level schedule with anticipated dates: - June/July 2022: Bridge Study Report - Board of County Commissioners' review/approval - 4Q 2023/1Q 2024: Final Design Acceptance - 4Q 2024: Start of Construction - 1Q 2027: Construction Final Completion As mentioned above, these are very high level schedule. Hoping to have a more detail schedule in 1Q of 2023. Respectfully, M�e�/w, q-Y� Senior Project Manager Transportation Management Services Department Cotner of Transportation Engineering Division 2885 South Horseshoe Drive, Naples, Florida 34104 Phone: 239.252.5844 Cell: 239.206.0194 Bee.Thao@colliercountyfl.gov From: Chris <christinemtl2@gmail.com> Sent: Monday, May 2, 2022 1:08 PM To: ThaoBee <Bee.Thao@colliercountyfl.gov> Subject: Re: 4464121 Qustion EXTERNAL EMAIL: This email is from an external source. Confirm this is a trusted sender and use extreme caution when opening attachments or clicking links. Good afternoon, Bee! I wanted to follow up on this. Thank you, Christine Otakan On Mon, Apr 18, 2022 at 1:21 PM Chris <christinemtl2@gmail.com> wrote: Good afternoon, Bee! Thanks so much for your email. I saw the meeting materials. Can you please tell me the current schedule since that was not posted under the project? 1 Thank you, Christine Otakan On Fri, Apr 1, 2022 at 10:56 AM ThaoBee <Bee.Thao@colliercountyfl.gov> wrote: Hi Chris, The consultant is diligently working on the displays for the upcoming Public Informational Meeting (PIM) on 4/06/22. The PIM information/displays will be uploaded into the website http://www.colIiercountyfl.gov/transportationprojects on the meeting day, 4/06/22. As an alternative to physically attending the PIM, the public are welcome to visit the site and provide feedback to the County via the comment form in the site. Respectfully, 66e6 M10, 16,P-W. Senior Project Manager Transportation Management Services Department oifiRepir COUnty Transportation Engineering Division 2885 South Horseshoe Drive, Naples, Florida 34104 Phone: 239.252.5844 Cell: 239.206.0194 Bee.Thao@colliercountyfl.gov From: Chris <christinemtl2@gmail.com> Sent: Friday, April 1, 2022 10:34 AM To: ThaoBee <Bee.Thao@colliercountyfl.gov> Subject: Re: 4464121 Qustion EXTERNAL EMAIL: This email is from an external source. Confirm this is a trusted sender and use extreme caution when opening attachments or clicking links. Hello! I am following up again. I saw you were still out of the office. Happy Friday! Thank you, Christine Otakan On Sat, Mar 19, 2022 at 5:10 PM Chris <christinemtl2@gmail.com> wrote: Good afternoon! I saw you were out of the office and wanted to follow up on this. Thank you, Christine Otakan On Fri, Mar 4, 2022 at 11:53 AM Chris <christinemtl2@gmail.com> wrote: Good morning, Bee. I wanted to ask about 4464121- Collier Blvd from Golden Gate Canal to Green Blvd. I heard there will be a public meeting happening soon. Has the meeting been scheduled yet? Where can I view the information online? Thank you, Christine Otakan Under Florida Law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by telephone or in writing.