Loading...
Agenda 06/14/2022 Item #16G1 (Change Order #1 to Agreement #21-7987 w/Quality Enterprises USA, Inc.)06/14/2022 EXECUTIVE SUMMARY Recommendation to approve Change Order #1 to Agreement No. 21-7897, “Everglades Airpark Rehab Runway 15/33,” with Quality Enterprises USA, Inc., to increase the contract amount by $209,861.73, and approve all necessary budget amendments. OBJECTIVE: To approve a Change Order increasing Agreement No. 21-7897 by $209,861.73 to rehabilitate Runway 15/33 at the Everglades Airpark (X01), to account for an increased amount of limerock material due to settlement. CONSIDERATIONS: On September 28, 2021 (Agenda Item 14A.1) the Board awarded Agreement No 21-7897 to Quality Enterprises USA, Inc. for the construction of the Everglades Airpark’s Runway 15/33 Rehabilitation in the amount of $1,748,853.75. The Everglades Runway Rehabilitation project used a greater quantity of limerock than stipulated in the construction plans. The original plans specified a 6” section of limerock base; however, the contractor required additional limerock placed to construct the project due to settlement. Staff anticipated the settlement based on the findings of the geotechnical investigation, which indicated that soils were high in organic content and clay content. Therefore, appropriate actions were taken to mitigate the amount of settlement. A layer of geotextile reinforcement was placed between the stabilized subgrade and the limerock base of the pavement section throughout the entire surface area of the runway. Geotextile reinforcement reduces the risk of differential settlement and improves the serviceability of the pavement. However, during the placement of the limerock base, contractors encountered higher than anticipated settlement- approximately 10 to 14 inches in the areas of the runway widening, likely due to the high ground water table in the project area which is tidally influenced. Unfortunately, additional geotextile fabric could not be placed underneath the subgrade to further reduce settlement due to the high-water table. Placing geotextile fabric below the subgrade would have required extensive de-watering operations, significantly increasing project costs, and posing an environmental risk to nearby wetlands. Densities, as specified in the FAA P-211 technical specification, were therefore difficult to achieve and necessitated the placement of additional limerock. If densities are not achieved, the FAA P-211 technical specification, requires that the area must be reworked and recompacted until the specified density is reached. That procedure was repeated until the specification was satisfied. Staff recommends approval of the attached Change Order No. 1 because the application of the additional limerock was necessary to meet the technical specifications of the project and to keep the integrity of the identified pavement section. FISCAL IMPACT: This change order will increase the overall bid total by $209,861.73. Budget amendments are necessary to reallocate funds within the Airport Capital Fund (496) from Reserves to Project 33709. The Collier County Airport Authority (CCAA) will request additional fu nding from the Federal Aviation Administration for this project. GROWTH MANAGEMENT IMPACT: There is no impact to the Growth Management Plan related to this item. LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for Board approval.-SRT RECOMMENDATION: To approve Change Order No. 1 to Agreement 21-7897, “Everglades Airpark 15/33 Rehabilitation- Grant Funded,” with Quality Enterprises USA, Inc., to increase the contract amount 16.G.1 Packet Pg. 2007 06/14/2022 by $209,861.73, approve all necessary budget amendments, and authorize the Chairman to sign the attached Change Order. PREPARED BY: Andrew Bennett, Executive Airport Manager ATTACHMENT(S) 1. Change Order - Contract 21-7897 (PDF) 16.G.1 Packet Pg. 2008 06/14/2022 COLLIER COUNTY Board of County Commissioners Item Number: 16.G.1 Doc ID: 22268 Item Summary: Recommendation to approve Change Order #1 to Agreement No. 21-7897, “Everglades Airpark Rehab Runway 15/33,” with Quality Enterprises USA, Inc., to increase the contract amount by $209,861.73, and approve all necessary budget amendments. Meeting Date: 06/14/2022 Prepared by: Title: – Growth Management Operations Support Name: Heather Meyer 05/16/2022 9:41 AM Submitted by: Title: Division Director - Operations Support – Growth Management Department Name: Gene Shue 05/16/2022 9:41 AM Approved By: Review: Airport Authority Andrew Bennett Additional Reviewer Completed 05/16/2022 9:42 AM Procurement Services Ana Reynoso Level 1 Purchasing Gatekeeper Completed 05/16/2022 9:57 AM Procurement Services Sara Schneeberger Additional Reviewer Completed 05/16/2022 1:52 PM Growth Management Department Jeanne Marcella Growth Management Department Completed 05/16/2022 2:13 PM Procurement Services Jeanne Marcella Additional Reviewer Skipped 05/16/2022 3:37 PM Procurement Services Sandra Herrera Additional Reviewer Completed 05/16/2022 3:51 PM Growth Management Operations Support Tara Castillo Additional Reviewer Completed 05/16/2022 4:49 PM Growth Management Department Gene Shue Additional Reviewer Completed 05/17/2022 5:52 PM Growth Management Department Trinity Scott Transportation Completed 05/20/2022 3:00 PM County Attorney's Office Scott Teach Level 2 Attorney Review Completed 05/24/2022 10:49 AM Grants Erica Robinson Level 2 Grants Review Completed 05/27/2022 7:42 AM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 05/27/2022 10:04 AM Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 05/31/2022 8:28 AM Office of Management and Budget Susan Usher Additional Reviewer Completed 05/31/2022 1:21 PM Grants Therese Stanley Additional Reviewer Completed 06/01/2022 1:38 PM County Manager's Office Dan Rodriguez Level 4 County Manager Review Completed 06/02/2022 4:29 PM 16.G.1 Packet Pg. 2009 06/14/2022 Board of County Commissioners Geoffrey Willig Meeting Pending 06/14/2022 9:00 AM 16.G.1 Packet Pg. 2010 16.G.1.b Packet Pg. 2011 Attachment: Change Order - Contract 21-7897 (22268 : Change Order #1 Quality Enterprises-Everglades Airpark Runway) 16.G.1.b Packet Pg. 2012 Attachment: Change Order - Contract 21-7897 (22268 : Change Order #1 Quality Enterprises-Everglades Airpark Runway) 16.G.1.b Packet Pg. 2013 Attachment: Change Order - Contract 21-7897 (22268 : Change Order #1 Quality Enterprises-Everglades Airpark Runway) 16.G.1.bPacket Pg. 2014Attachment: Change Order - Contract 21-7897 (22268 : Change Order #1 Quality Enterprises-Everglades