GG MSTU Minutes 04/19/2022
April 19, 2022 Golden Gate MSTU 1/6
l
GOLDEN GATE M.S.T.U. ADVISORY
COMMITTEE
8300 Radio Road
Naples, FL 34104
APRIL 19, 2022
MINUTES
I. Call to Order
The meeting was called to order at 4:30 P.M. by Chair Spencer. Attendance was called and a
quorum of four was present.
II. Attendance
Advisory Committee Patricia Spencer – Chair
Paula Rogan – Vice Chair
Florence “Dusty” Holmes
Ron Jefferson
Vacancy
Staff Michelle Arnold – PTNE Director
Dan Schumacher – Project Manager
Rosio Garcia – Administrative Assistant (Excused)
Landscape Mike McGee – Landscape Architect, McGee & Assoc.
Marcus May – Grounds Maintenance, Mainscape
Other Wendy Warren – Transcription, Premier
III. Pledge of Allegiance
The Pledge of Allegiance was recited.
IV. Approval of Agenda
Chair Spencer moved to approve the Agenda of the Golden Gate Beautification M.S.T.U.
Second by Mr. Jefferson. Carried unanimously 4 - 0.
V. Approval of Minutes March 15, 2022
Mr. Jefferson moved to approve the minutes of the March 15, 2022, meeting as presented.
Second by Chair Spencer. Carried unanimously 4 - 0.
18.A.3
Packet Pg. 453 Attachment: Signed Minutes - 04-19-22 Golden Gate (22396 : Golden Gate Beautification MSTU 05-17-22)
MINUTES
April 19, 2022 GOLDEN GATE MSTU 2/6
VI. Landscape Maintenance Report – Mainscape Landscaping Company
Mr. May reported:
• Plants under warranty and new replacement plants, as specified in the McGee & Associates
report, were installed.
• Paurotis Palms trees were pruned.
• Maintenance on Sunshine Boulevard was resumed, and replacement plants installed.
• The Irrigation division will perform a wet check the week ending April 30, 2022, to evaluate
irrigation coverage for replacement plants.
• Mainscape will notify Mr. Schumacher of the wet check schedule so he may be present.
A determination will be made if “hand watering” is necessary until the plants are established.
Mr. Schumacher will increase irrigation to run daily, minimum fifteen (15) to twenty (20) minutes per
cycle, for initial growing period for new plants.
VII. Landscape Architect’s Report – McGee & Associates
Mr. McGee presented a Summary Report dated April 5, 2022, noting it will be updated for the May meeting
to reflect installation of new plants.
General
In the event tree installation is recommended on medians, McGee & Associates will provide specifications
to ensure conformance with the Florida Department of Transportation (FDOT) horizontal and vertical sight
line requirements.
Pavers were pressure washed and treated with Wet & Forget” mold treatment spray in all areas.
Tropicana Boulevard
• Median #1: Install two-hundred fifty (250) Dwarf Jasmin due to missing plants and slow growth rate
due to shade from large Oaks.
Sunshine Boulevard
• Median #2: North end – Dead and brown foliage on Juniper Parsonii damaged by an auto accident
was pruned out.
• 18th Avenue SW Median: Plant Perennial Peanut “Golden Glory” during the rainy season.
Coronado Parkway
• Median #3: Remove southernmost existing Foxtail Palm and install new Foxtail Palm that has ten
(10) foot clear trunk height.
• Median #10: Address 5254 – Remove volunteer Schefflera plant growing on Sabal Palm.
Address 5237 - Fill in missing Perennial Peanut plants; quantity required fifty (50).
• Medians #14: Replace westernmost Alexander Palm with severe trunk damage. Fertilize Foxtail
Palm on northern end.
• Remove volunteer Schefflera plant growing on Sabal Palm.
Water Usage
March combined 2022 water use per WeatherTrak controller estimates:
• Tropicana Boulevard – 241,524 gallons.
• Sunshine Boulevard – 405,070 gallons; second highest amount recorded. Irrigation system will be
checked to confirm system is functioning properly.
• Coronado Pkwy & Hunter Boulevard – 338,188 gallons.
18.A.3
Packet Pg. 454 Attachment: Signed Minutes - 04-19-22 Golden Gate (22396 : Golden Gate Beautification MSTU 05-17-22)
MINUTES
April 19, 2022 GOLDEN GATE MSTU 3/6
Mr. Schumacher will:
• Schedule pressure washing and application of “Wet and Forget” with Mainscape Landscaping.
• Direct Mainscape’s Agronomy division to treat broadleaf weeds in turf areas.
• Request a Quote (RFQ) from Mainscape Landscaping to remove Crown of Thorns and plant
Perennial Peanut on Hunter Boulevard Median #2.
VIII. Project Manager’s Report
A. Election of Officers
Nomination for Chair
Ms. Holmes nominated Patricia Spencer for the position of Chair of the Golden Gate
Beautification M.S.T.U. Advisory Committee for one year.
Second by Mr. Jefferson. Carried unanimously 4 – 0.
Nominations were closed and no others were tendered. Ms. Spencer retained the Chair.
Nominations for Vice-Chair
Chair Spencer nominated Paula Rogan for the position of Vice-Chair of the Golden Gate
Beautification M.S.T.U. Advisory Committee for one year.
Second by Ms. Holmes. Carried unanimously 4 – 0.
Nominations were closed and no others were tendered. Ms. Rogan retained her position as
Vice-Chair.
B. Budget Report
Golden Gate MSTU Fund Budget 153 dated April 19, 2022 and Capital Asset Plan
• The FY-22 Millage rate remains constant at 0.5000 mills.
• Current Ad Valorem Tax, Line 1, is $533,600.00; an increase of 8.10% over FY-21.
• Transfers and Contributions, Line 13, are $1,136,560.68; a carry-over of unexpended
FY-21 funds.
• Total Revenue, Line 14, is $1,675,060.68, including investment interest, transfers, and
contributions.
• Purchase Orders: (Contractors)
Hart’s Electrical – Lighting Maintenance & Repair
Howard Fertilizer – Landscape Fertilizer
Mainscape – Landscape Incidentals, Ground Maintenance, and Irrigation.
McGee & Associates – Landscape Architecture
Premier Staffing – Transcription Services
Site One Landscape Supply – Irrigation Parts & Pumps
Varian Construction – Bus Shelter Repainting
• Red indicates the Purchase Order is closed and the money expended.
• Operating Expense, Line 31, is budgeted at $422,060.68; with current Commitments of
$143,517.75, Expenditures of $172,298.79, and a Budget Remainder (unspent operating
funds) of $106,244.14.
• Capital Outlay, Line 33, budgeted at $1,181,200.00, is available to fund planned long term
projects, consistent with the MSTU ordinance and upon a motion from the Advisory
Committee.
18.A.3
Packet Pg. 455 Attachment: Signed Minutes - 04-19-22 Golden Gate (22396 : Golden Gate Beautification MSTU 05-17-22)
MINUTES
April 19, 2022 GOLDEN GATE MSTU 4/6
• Transfer to Fund 111, Line 34, in the amount of $56,000.00, is for MSTU Staff salaries and
accrued County overhead related to M.S.T.U. operations.
• Transfer to the Property Appraiser, Line 35, in the amount of $4,500.00, is for computation
of MSTU Ad Valorem data for the tax rolls.
• Transfer to the Tax Collector, Line 36, in the amount of $11,300.00, is for collection of
MSTU millage as part of the tax bill, currently 0.5 mills.
• Total Budget, Line 38, lists FY-22 MSTU budgeted funds at $1,675,060.68; with tabulated
Commitments of $143,517.75, Expenditures of $185,382.80, and a Budget Remainder
(total unspent funds) of $1,346,160.13. The $1,675,060.68 amount does not change during
the fiscal year.
Mr. Schumacher noted Wm. Varian Construction’s invoice in the amount of $5,330.00, was for
refurbishment of two (2) bus stops in accordance with County specifications.
Asset Inventory Review & Cost Estimates
The Capital Asset Plan dated March 15, 2022, identifies MSTU assets and estimates financial
requirements to maintain these known assets. The following was noted:
• The list sequences MSTU assets by an anticipated year of replacement and replacement
cost, plus an ongoing annual maintenance cost where applicable.
• Assets include, but are not limited to, landscaping and irrigation, lighting, pump stations,
signs, and structures.
• Items #4, 8 and 11 projected expense reflects potential replacement of irrigation pumps on
Tropicana Blvd. (2027), Sunshine Blvd (2028) and Coronado Pkwy. (2029) as quoted by
Naples Electric Motor Works.
• Projected asset replacement costs through 2032 total $1,784,990. (w/ 7% annual inflation)
C. FY-23 Budget – Proforma
Fiscal Year 2023
A preliminary FY-23 Budget Proforma, effective October 1, 2022, with a millage rate consistent with
FY-22 was presented for informational purposes.
• Total Estimated Revenue is $1,774.400.00, including Ad Valorem Tax revenue, Investment
Interest, and estimated Transfers and Contributions in the amount of $1,243,700.00, a carry-
over of unexpended FY-22 funds, (minus a 5% reserve).
• Capital Outlay, reserved for special projects, is $1,412,700.00, an increase of 19.6% over
the FY-22 Adopted Budget.
• The line item for landscaping is negative 37% which accounts for a carry-over of FY-21
invoices processed in FY-22.
• Transfer to Fund 111 in the amount of $60,100.00, an increase of 7.32% over FY-22, is for
MSTU Staff salaries and accrued County overhead related to MSTU operations.
• Operating Expense, projected at $278,800.00, represents a 15.52% decrease over the FY-22
Adopted Budget.
Millage Rate
The millage rate is evaluated annually with consideration given to both Operating Expense and
Capital Outlay anticipated expenditures for FY-23 and future fiscal years. The MSTU is provided
two options for the millage rate, currently assessed at 0.5000 mils, as follows:
• Lower the current millage rate to establish a Revenue Neutral Policy, maintaining the FY-22
income level.
18.A.3
Packet Pg. 456 Attachment: Signed Minutes - 04-19-22 Golden Gate (22396 : Golden Gate Beautification MSTU 05-17-22)
MINUTES
April 19, 2022 GOLDEN GATE MSTU 5/6
• Maintain the current millage rate providing opportunity to fund future projects.
D. Replacement Bridge – Santa Barbara Canal
A public information meeting on the Golden Gate Parkway over Santa Barbara Bridge Replacement
Project was held March 29th at the Golden Gate Community Center for attendees to review the project
displays.
The Design for replacing this bridge has reached the sixty (60) percent design stage and the meeting
was for community members to review the plans and provide input. The plans include replacing the
three existing bridges with a single bridge including both shoulders and sidewalks on each side.
Improvements are anticipated to enhance mobility and maintain traffic and passage for vehicles,
bicycles, and pedestrians.
Railing Design
The bridge design group presented an alternate design modifying the infill panels. The Sunshine motif
panel will still be utilized.
Dennis McCoy, Sr. Engineering Project Manager, Growth Management Division, and the primary
contractor are finalizing pricing for the Sunshine Motif Infill Panel.
Mr. Schumacher will notify Advisory Committee members of the Sunshine Infill Panel cost.
E. Golden Gate Parkway – Add a “Welcome” sign in the ROW, near CR 951
A “Welcome to Golden Gate Sign in Median” on the Median tip at the intersection of Collier Blvd. (north)
and Golden Gate Parkway, in the Right of Way (ROW), is under consideration by the MSTU.
A rendering depicting bridge replacement location “Alternative 3” for the Collier Blvd. 951, six (6) lane
road widening project was distributed for reference.
• The area the MSTU has identified for sign placement may or may not be impacted depending on
the location selected for the replacement bridge across the parallel canal.
• The CR951 project will be reviewed by the Board of County Commissioners in May of 2022 with
a prospective bridge location expected to be determined.
The Committee discussed installing the sign with the understanding it would be removed, stored, and
reinstalled on completion of the CR951 interchange project. The concept will be tabled pending further
investigation and a location decision by the Board of County Commissioners (BCC).
Mr. Schumacher will update the Committee on the BCC’s decision regarding the interchange and
canal bridge location for the road widening project.
F. Parkway Turf at Santa Barbara Boulevard
The Committee previously discussed installation of irrigation and sod at the intersection of Santa
Barbara Blvd. and Golden Gate Parkway, west of the sign. The Road Maintenance Division is
responsible for maintaining the area and must approve the project.
Mr. Schumacher provided a version of an irrigation plan created by Mr. McGee to Pam Lulich,
Landscape Operations Manager, and requested refurbishment of the area. Conversations among
Mr. McGee, Mr. Schumacher, and Ms. Lulich indicate the County is receptive to restoring the area
to its original condition.