Agenda 04/26/2022 Item #16A14 (Change Order #1 for Contract #20-7791 for Vanderbilt Underground Utility Conversion Phase 4 w/MasTec North America, Inc.)04/26/2022 EXECUTIVE SUMMARY Recommendation to approve Change Order #1 for Construction Agreement No. 20-7791 (the “Agreement”), Vanderbilt Underground Utility Conversion Phase 4, with MasTec North America, Inc., to increase the contract amount by $124,919.50 and adding 107 days to the project completion date, due to the delays in coordination efforts with FPL and CenturyLink, and other issues discovered during construction. (Vanderbilt Beach MSTU Fund 143) OBJECTIVE: To ensure continuous construction services with MasTec for the final phase of the Vanderbilt Beach Aerial to underground Utility Conversion project. CONSIDERATIONS: On February 23, 2021 (agenda 11J), the Board awarded Agreement No. 20-7791 to MasTec North America to install and activate the FPL, CenturyLink, and Comcast utility conversion network from aerial to underground for the Phase IV Vanderbilt Beach MSTU Utility Conversion Project at a value of $1,765,869.40. The County issued the Notice to Proceed on May 17, 2021. However, due to the COVID pandemic, transportation and supply shortages, and increased product costs, the actual start of the work was delayed until October 2021. During construction the project discovered underground conflicts, the contractor experienced difficulty obtaining drilling crews, and the utility entities, FPL and Comcast, made modifications that required different methods of installation than anticipated, all contributing to the project delays. The additional time required to complete the project is projected to be 107 days. The project modifications require additional material and the limited right -of-way in portions of the project created challenges for the project. As an alternative construction method to the original contract, the contactor proposes to perform a single bore to contain multiple conduits to minimize the conflict with the other utilities in the area. These modifications is resulting in a cost increase of $124,919.50. The additional funding will change the total value of the contract to $1,890,788.90. The Vanderbilt Beach MSTU Advisory Board voted to recommend approval of this Change Order by a vote of 5-0 on April 7, 2022. Staff reviewed the quoted additional work and services, compared it to earlier bid items and similar work under the agreement, and has determined that the quoted work is reasonable for the proposed additional services. FISCAL IMPACT: Funding in the amount of $124,919.50 is available in Vanderbilt Beach MSTU Fund (143) to cover the additional cost for this work. GROWTH MANAGEMENT IMPACT: This item has no Growth Management Impact. LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for Board approval. -SRT RECOMMENDATION: The Board approve Change Order #1 for Construction Agreement No. 20- 7791, Vanderbilt Underground Utility Conversion Phase 4, with MasTec, North America Inc., to increase the contract amount by $124,919.50 and adding 107 days to the project completion date (through and including September 1, 2022), and authorize the Chairman to sign the attached Change Order. Prepared By: Harry Sells, MSTU Project Manager - PTNE Division ATTACHMENT(S) 1. CO #1 Mastec 040422 (PDF) 2. 20-7791 MasTecNorthAmerica_Contract. 16.A.14 Packet Pg. 615 04/26/2022 COLLIER COUNTY Board of County Commissioners Item Number: 16.A.14 Doc ID: 21810 Item Summary: Recommendation to approve Change Order #1 for Construction Agreement No. 20-7791 (the “Agreement”), Vanderbilt Underground Utility Conversion Phase 4, with MasTec North America, Inc., to increase the contract amount by $124,919.50 and adding 107 days to the project completion date, due to the delays in coordination efforts with FPL and CenturyLink, and other issues discovered during construction. (Vanderbilt Beach MSTU Fund 143) Meeting Date: 04/26/2022 Prepared by: Title: Project Manager – Public Transit & Neighborhood Enhancement Name: Harry Sells 03/31/2022 4:08 PM Submitted by: Title: Division Director - Pub Tran & Nbrhd Enh – Public Transit & Neighborhood Enhancement Name: Michelle Arnold 03/31/2022 4:08 PM Approved By: Review: Public Transit & Neighborhood Enhancement Caroline Soto Additional Reviewer Completed 03/31/2022 4:18 PM Growth Management Department Jeanne Marcella Growth Management Department Completed 04/01/2022 2:52 PM Public Transit & Neighborhood Enhancement Michelle Arnold Director Review Completed 04/01/2022 3:00 PM Procurement Services Ana Reynoso Level 1 Purchasing Gatekeeper Completed 04/01/2022 4:03 PM Procurement Services Sandra Herrera Additional Reviewer Completed 04/05/2022 7:38 AM Growth Management Department Trinity Scott Transportation Completed 04/05/2022 10:07 AM County Attorney's Office Scott Teach Additional Reviewer Completed 04/12/2022 10:52 AM Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 04/12/2022 11:01 AM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 04/13/2022 1:44 PM Growth Management Operations Support Christopher Johnson Additional Reviewer Completed 04/14/2022 9:58 AM County Manager's Office Dan Rodriguez Level 4 County Manager Review Completed 04/20/2022 11:04 AM Board of County Commissioners Geoffrey Willig Meeting Pending 04/26/2022 9:00 AM 16.A.14 Packet Pg. 616 16.A.14.aPacket Pg. 617Attachment: CO #1 Mastec 040422 (21810 : Mastec Change Order #1 Contract 20-7791) 16.A.14.aPacket Pg. 618Attachment: CO #1 Mastec 040422 (21810 : Mastec Change Order #1 Contract 20-7791) 16.A.14.aPacket Pg. 619Attachment: CO #1 Mastec 040422 (21810 : Mastec Change Order #1 Contract 20-7791) 16.A.14.aPacket Pg. 620Attachment: CO #1 Mastec 040422 (21810 : Mastec Change Order #1 Contract 20-7791) 16.A.14.aPacket Pg. 621Attachment: CO #1 Mastec 040422 (21810 : Mastec Change Order #1 Contract 20-7791)