Agenda 02/22/2022 Item #16A 5 (Record the Final Plat of Quarry Phase 1B)02/22/2022
EXECUTIVE SUMMARY
This item requires that ex parte disclosure be provided by Commission members. Should a hearing
be held on this item, all participants are required to be sworn in. Recommendation to approve for
recording the minor final plat of Quarry Phase 1B, Application Number PL20210001493.
OBJECTIVE: To approve for recording the final plat of Quarry Phase 1B, a subdivision of lands
located in Section 23 and 24, Township 48 South, Range 26 East, Collier County, Florida.
CONSIDERATIONS: The Development Review Division of the Growth Management Department has
completed the review of the minor final plat of Quarry Phase 1B, and these documents are in compliance
with the County Land Development Code (LDC) and Chapter 177, Florida Statutes. Under LDC Se ction
10.02.04 D, a minor final plat approval may be requested as an alternative to the standard construction
plans and plat approval where the plat does not require improvements, a construction and maintenance
agreement, a security performance bond, or phasing. This project is within the Heritage Bay PUD,
Ordinance 03-40, as amended. All fees have been paid. The Development Review Division
recommends that the minor final plat of Quarry Phase 1B be approved for recording.
FISCAL IMPACT: The County will realize revenues as follows:
Fund: Growth Management Fund 131
Agency: County Manager
Cost Center: 138327 - Land Development Services
Revenue generated by this project: Total: $1,075 plat review fee
GROWTH MANAGEMENT IMPACT: The developer must receive a Certificate of Adequate Public
Facilities (COA) prior to the issuance of the construction plan final approval letter and plat recordation,
except when the applicant elects to delay obtaining a COA for non-residential developments that are
required to obtain approval of a site development plan prior to the issuance of a building permit.
LEGAL CONSIDERATIONS: The applicant is requesting approval of the minor final subdivision plat.
The Board shall consider the County Manager or designee’s recommendation and shall take evidence and
testimony in regard to the minor final subdivision plat requirements identified in LDC sections 10.02.04
D, 10.02.04 B, 10.02.04 C, and other provisions of the LDC, as well as Chapter 177, Florida Statutes. If
the Board denies or places conditions on the minor final subdivision plat, it shall state reasons for such
denial or conditions.
In accordance with the LDC, the applicant is required to submit the minor final subdivision plat to the
County Manager or designee for recording within 18 months of the date of approval of the minor final
subdivision plat by the Board. However, following approval by the Board, but prior to recordation, the
County Manager or designee may approve minor insubstantial changes to the minor final subdivision plat,
and the Board may approve any changes that are not minor and insubstantial.
This item has been approved as to form and legality, and requires a majority vote for Board approval. --
DDP
RECOMMENDATION: To approve the minor final plat of Quarry Phase 1B, Application Number
PL20210001493 for recording.
Prepared by: Lucia S. Martin, Associate Project Manager, Development Review Division
ATTACHMENT(S)
1. Location Map (PDF)
2. Plat Map (PDF)
16.A.5
Packet Pg. 295
02/22/2022
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.A.5
Doc ID: 21052
Item Summary: This item requires that ex parte disclosure be provided by Commission members.
Should a hearing be held on this item, all participants are required to be sworn in. Recommendation to
approve for recording the minor final plat of Quarry Phase 1B, Application Number PL20210001493.
Meeting Date: 02/22/2022
Prepared by:
Title: Technician – Growth Management Development Review
Name: Lucia Martin
01/12/2022 3:47 PM
Submitted by:
Title: Environmental Specialist – Growth Management Department
Name: Jaime Cook
01/12/2022 3:47 PM
Approved By:
Review:
Growth Management Operations & Regulatory Management Kenneth Kovensky Additional Reviewer Completed 01/12/2022 3:49 PM
Growth Management Department Lissett DeLaRosa Growth Management Department Completed 01/13/2022 8:20 AM
Engineering & Natural Resources Jack McKenna Additional Reviewer Completed 01/15/2022 2:37 PM
Growth Management Development Review Brett Rosenblum Additional Reviewer Completed 01/24/2022 1:10 PM
Growth Management Department Jaime Cook Additional Reviewer Completed 01/28/2022 11:46 AM
Growth Management Department Trinity Scott Transportation Skipped 01/27/2022 10:08 AM
Growth Management Department James C French Growth Management Completed 01/28/2022 3:49 PM
County Attorney's Office Derek D. Perry Level 2 Attorney Review Completed 02/07/2022 9:57 AM
County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 02/07/2022 10:08 AM
Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 02/07/2022 10:13 AM
Office of Management and Budget Laura Zautcke Additional Reviewer Completed 02/10/2022 4:46 PM
County Manager's Office Geoffrey Willig Level 4 County Manager Review Completed 02/11/2022 10:04 AM
Board of County Commissioners Geoffrey Willig Meeting Pending 02/22/2022 9:00 AM
16.A.5
Packet Pg. 296
QUARRY PHASE 1B
LOCATION MAP
16.A.5.a
Packet Pg. 297 Attachment: Location Map (21052 : Final Plat - Quarry Phase 1B)
QUARRY PHASE 1BCOUNTY APPROVALSA REPLAT OF TRACTS "GC-6", "GC-7" AND TRACT "U", QUARRY PHASE 1, PLAT BOOK 42, PAGES 57 -67,BEING A PORTION OF SECTIONS 23 AND 24, TOWNSHIP 48 SOUTH, RANGE 26 EAST, COLLIER COUNTY, FLORIDA FILING RECORDCOUNTY ATTORNEYSURVEYOR'S CERTIFICATECOUNTY SURVEYORCOUNTY ENGINEERCOUNTY COMMISSION APPROVALACKNOWLEDGEMENT:LEGAL DESCRIPTION:GENERAL NOTES:THE QUARRY COMMUNITY ASSOCIATION, INC. ACCEPTANCEACKNOWLEDGEMENTDEDICATIONS:ϭϭͬϮϵͬϮϬϮϭDigitally signed by Michael Ward DN: cn=Michael Ward, o=RWA, Inc., email=maw@consult-rwa.com, c=US Date: 2021.11.29 11:18:31 -05'00'16.A.5.bPacket Pg. 298Attachment: Plat Map (21052 : Final Plat - Quarry Phase 1B)
QUARRY PHASE 1BA REPLAT OF TRACTS "GC-6", "GC-7" AND TRACT "U", QUARRY PHASE 1, PLAT BOOK 42, PAGES 57 -67,BEING A PORTION OF SECTIONS 23 AND 24, TOWNSHIP 48 SOUTH, RANGE 26 EAST, COLLIER COUNTY, FLORIDA 16.A.5.bPacket Pg. 299Attachment: Plat Map (21052 : Final Plat - Quarry Phase 1B)
QUARRY PHASE 1BA REPLAT OF TRACTS "GC-6", "GC-7" AND TRACT "U", QUARRY PHASE 1, PLAT BOOK 42, PAGES 57 -67,BEING A PORTION OF SECTIONS 23 AND 24, TOWNSHIP 48 SOUTH, RANGE 26 EAST, COLLIER COUNTY, FLORIDA 16.A.5.bPacket Pg. 300Attachment: Plat Map (21052 : Final Plat - Quarry Phase 1B)
QUARRY PHASE 1BA REPLAT OF TRACTS "GC-6", "GC-7" AND TRACT "U", QUARRY PHASE 1, PLAT BOOK 42, PAGES 57 -67,BEING A PORTION OF SECTIONS 23 AND 24, TOWNSHIP 48 SOUTH, RANGE 26 EAST, COLLIER COUNTY, FLORIDA 16.A.5.bPacket Pg. 301Attachment: Plat Map (21052 : Final Plat - Quarry Phase 1B)