Agenda 01/25/2022 Item #16A19 (Final Acceptance Bentley Village - Bentley Care Center Phase 1 Sewer Utility Facilities)01/25/2022
EXECUTIVE SUMMARY
Recommendation to approve final acceptance of the sewer utility facilities for Bentley Village -
Bentley Care Center Phase 1, PL20210002854.
OBJECTIVE: To have the Board of County Commissioners, as Ex-Officio Governing Board of the
Collier County Water-Sewer District, approve final acceptance of the sewer facilities, in accordance with
the Collier County Utility Standards and Procedures, Ordinance No. 2004-31.
CONSIDERATIONS:
1) The Developer of Bentley Village - Bentley Care Center Phase 1 has constructed the sewer facilities
within dedicated easements to serve this private development (see attached location map).
2) A final inspection to discover defects in materials and workmanship has been conducted by staff on
November 17, 2021, in coordination with Public Utilities, and these facilities have been found to be
satisfactory and acceptable.
3) Staff recommends final acceptance of the subject sewer utility facilities. The subject sewer facilities
are owned and maintained by the developer.
4) This final acceptance is in accordance with Collier County, Ordinance No. 2004-31, as amended.
5) Staff is unaware of any issues that would serve to negate the recommendation to release the project.
FISCAL IMPACT: Approval of this Executive Summary will have no specific financial impact.
GROWTH MANAGEMENT IMPACT: There is no growth management impact associated with this
action.
LEGAL CONSIDERATIONS: This item has been approved as to form and legality, and requires a
majority vote for Board approval. -DDP
RECOMMENDATION: To approve final acceptance of the potable water and sewer utility facilities for
Bentley Village - Bentley Care Center Phase 1, PL20210002854.
Prepared by: Valerie Kullick, Technician, Development Review Division
ATTACHMENT(S)
1. Location Map (PDF)
2. Verification of Final Cost (PDF)
16.A.19
Packet Pg. 1089
01/25/2022
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.A.19
Doc ID: 20890
Item Summary: Recommendation to approve final acceptance of the sewer utility facilities for
Bentley Village – Bentley Care Center Phase 1, PL20210002854.
Meeting Date: 01/25/2022
Prepared by:
Title: Technician – Growth Management Development Review
Name: Valerie Kullick
12/20/2021 4:05 PM
Submitted by:
Title: Environmental Specialist – Growth Management Department
Name: Jaime Cook
12/20/2021 4:05 PM
Approved By:
Review:
Public Utilities Planning and Project Management Tom Chmelik Additional Reviewer Completed 12/20/2021 4:27 PM
Growth Management Department Lissett DeLaRosa Growth Management Department Completed 12/20/2021 4:41 PM
Growth Management Development Review Marcus Berman Additional Reviewer Completed 12/21/2021 6:21 AM
Wastewater Steve Nagy Additional Reviewer Completed 12/21/2021 9:13 AM
Wastewater Beth Johnssen Additional Reviewer Completed 12/21/2021 11:39 AM
Engineering & Natural Resources Jack McKenna Additional Reviewer Completed 12/29/2021 2:33 PM
Growth Management Department Jaime Cook Additional Reviewer Completed 12/30/2021 8:42 AM
Growth Management Department James C French Growth Management Completed 12/31/2021 11:19 AM
Growth Management Department Trinity Scott Transportation Skipped 01/05/2022 12:11 PM
County Attorney's Office Derek D. Perry Level 2 Attorney Review Completed 01/10/2022 3:28 PM
Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 01/10/2022 4:09 PM
County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 01/12/2022 9:19 AM
Office of Management and Budget Laura Zautcke Additional Reviewer Completed 01/13/2022 3:49 PM
County Manager's Office Amy Patterson Level 4 County Manager Review Completed 01/16/2022 3:54 PM
Board of County Commissioners Geoffrey Willig Meeting Pending 01/25/2022 9:00 AM
16.A.19
Packet Pg. 1090
BENTLEY VILLAGE –
BENTLEY CARE CENTER PHASE 1
LOCATION MAP
16.A.19.a
Packet Pg. 1091 Attachment: Location Map (20890 : Final Acceptance of Utilities - Bentley Village - Bentley Care Center Phase 1 Sewer Only)
16.A.19.bPacket Pg. 1092Attachment: Verification of Final Cost (20890 : Final Acceptance of Utilities - Bentley Village - Bentley Care Center Phase 1 Sewer Only)