Agenda 01/11/2022 Item #11B (Status Report for Collier County Local Government Infrastructure Sales Surtax Projects)01/11/2022 EXECUTIVE SUMMARY Recommendation to accept the status report for Collier County Local Government Infrastructure Sales Surtax Projects, acknowledge the planned move of the Domestic Animal Services (DAS) facility to County Site 305, and authorize completion of design for Sheriff’s Forensics/Evidence Building to include expanding the size of the Sheriff’s facility to accommodate a move of CCSO Criminal Investigations Division from 2373 East Horseshoe Drive to the GOBP campus. OBJECTIVE: To update the Board on completed, current, and future Collier County Local Government Infrastructure Surtax (Surtax) projects. CONSIDERATIONS: Voters approved an additional penny sales tax for infrastructure funding in November 2018. Collection of the Local Government Infrastructure Surtax began on January 1, 2019. Ordinance 2018-21, approved on April 24, 2018, along with Section 212.055(2), Florida Statutes govern the use of Surtax funds. Exhibit A of Ordinance 2018-21 specifies three primary categories of projects: Transportation, Facilities & Capital Replacements and Community Priorities. Ordinance 2018-21 also established the Infrastructure Surtax Citizen Oversight Committee (Committee). The Committee provides for citizen review of the expenditure of sales tax proceeds by the County. More specifically, the Committee has the responsibility to review the expenditure of Surtax proceeds against the ballot referendum approved by voters and Ordinance 2018-21. Staff provides project information and documentation to the Committee to allow it to conduct its review responsibilities. When the Committee makes a finding that project expenditures are a valid use of Surtax funding the project is considered to be validated. The following is a list of the County Sales Surtax projects authorized by Ordinance 2018-21. o Transportation: ▪ Roads $ 114,000,000 ▪ Bridge Replacements $ 33,000,000 ▪ New Bridges $ 34,000,000 ▪ Sidewalks $ 10,000,000 o Facilities & Capital Replacements: ▪ CCSO Forensics/Evidence Bld. $ 33,000,000 ▪ Big Corkscrew Regional Park $ 40,000,000 ▪ DAS Facility $ 6,000,000 ▪ HVAC/Roof and Capital R&R $ 39,000,000 ▪ Hurricane Resiliency $ 15,000,000 ▪ EMS Stations $ 6,000,000 o Community Priorities: ▪ Career & Tech Training Center $ 15,000,000 ▪ VA Nursing Home $ 30,000,000 ▪ Workforce Housing Trust Fund $ 20,000,000 ▪ Mental Health Facility $ 25,000,000 Total County Sales Surtax Projects $ 420,000,000 Domestic Animal Services Facility: The replacement of the DAS facility is an authorized and validated 11.B Packet Pg. 41 01/11/2022 Surtax project. On March 6, 2019, the Infrastructure Surtax Citizen Oversight Committee validated the project. In June of 2019 staff prepared a memo that discussed how best to achieve a best quality, best - value DAS facility to serve the residents of Collier County. The memo considered the advantages and disadvantages of renovating the existing DAS site versus relocating to County Site 305 adjacent to the Sports Complex and Government Operations Business Park. In September 2020 Davidson Engineering conducted a site review and concluded that the existing Davis Boulevard location is too small to accommodate the current and future needs of DAS. Both the staff memo and Davidson Engineering noted numerous disadvantages of the Davis Boulevard location including site size constraints, cost of maintaining normal operations during construction, cost of bringing the site up to code, permitting challenges, relative difficulty of meeting current standards of animal care in animal shelters, and the relative cost inefficiency of rebuilding at the current location compared to a new construction site. The recommendation was to construct a new DAS shelter on the County 305 Site. On September 22, 2021, the Surtax Committee validated the use of Sales Surtax funding for the acquisition of Site 305 property making the relocation of the DAS shelter a validated Surtax funded project. Staff recommends that the DAS shelter be relocated to Site 305. Construction contract award is estimated to be Fall of 2022. Government Operations Business Park Campus (GOBP or Core Campus No. 2): On June 25, 2019 the Board awarded a design contract to Stantec Consulting Services, Inc. for the Forensics/Evidence Building as well as the overall Government Operations Business Park (GOBP) Campus. The GOBP Project is consistent with the mission, vision, and guiding principles presented to the Board of County Commissioners at the Master Space Planning Workshop on June 4, 2019. Specifically, the GOBP location provides improved resiliency, improved accessibility to growth areas and represents a centralized location for deployment of operational divisions, equipment and resources. The GOBP design concept included the Collier County Sheriff’s Forensics/Evidence Building, a Public Utilities Logistics & Operations Center, a centralized County Security & Operations Center and a centralized inventory building. Sheriff’s Forensics/Evidence Building The construction of a Forensics/Evidence Facility for the Collier County Sheriff is an authorized and validated Surtax project. As design for the Sheriff’s Forensics/Evidence building proceeded it became evident that the County should consider upsizing the building by approximately 40,000 sqft to allow the Sheriff to completely relocate his Criminal Investigation Division, Youth Relations and Patrol Administration from its current location at 2373 East Horseshoe Drive. This move would achieve operational consolidation and efficiencies while eliminating a facility constructed in 1989 with sub-optimal design characteristics and long-term capital maintenance concerns including roofing, HVAC, building envelope and general moisture control, and energy efficiency. Staff is recommending finalizing design for an upsized Forensics/Evidence building be pursued. The cost of the addition construction scope will be provided by a combination of Pay-Go funding, interim and long-term financing, and potentially, proceeds from selling the 2373 East Horseshoe Drive property. The cost estimate and funding approach is discussed in the Fiscal Impact. The overall GOBP project is being pursued in two prioritized phases. Under the upsized Forensics/Evidence building concept the site will be fully developed to accommodate all phases. Phase 1 will include the Forensics/Evidence Facility followed closely by the Public Utilities Logistics & Operations Center. Phase 2 involves the General Government related functions, a centralized County Security & Operations center (Transportation/Traffic Ops & Facilities Management) and a centralized (Traffic Operations & Facilities Management) inventory building. Construction of Phase 2 is not expected to commence before Fall 2026. 11.B Packet Pg. 42 01/11/2022 Relative to the construction cost inflation being experienced currently, it is worth noting that the dates for GOBP construction contract awards are far enough in the future to potentially allow construction pricing to stabilize and perhaps move lower. The estimated award dates for the DAS Facility and the various GOBP phases are as follows: • DAS - Construction contract award, Spring 23 • Phase 1a GOBP Site Development - Construction contract award, Fall 2022 • Phase 1a GOBP CCSO Forensics/Evidence Building - Construction contract award, Fall 2022 • Phase 1b GOBP PUD, Logistics & Operations, Project Management & Inventory - Construction contract award, Fall 2023 • Phase 2 GOBP Traffic Operations, Facilities Mgt. Security & Operations and centralized inventory - Construction Contract award, Fall 2026 FISCAL IMPACT: The Sales Surtax funding will sunset in December 2025 or terminate in the calendar year when the total aggregate distributions to the Cities and County equal to or exceed $490 million. As of November 30, 2021, $267,998,521.45 has been received, the County’s portion is $242,110,664.44. The Infrastructure Surtax Citizen Oversight Committee has validated $346,718,300 in projects, including the DAS facility and the Sheriff’s Evidence and Forensics facility. There are only 4 projects remaining to be validated by the by the Infrastructure Surtax Citizen Oversight Committee. GOBP Campus: Surtax funding for the Sheriff’s Forensic/Evidence building is $33,000,000. Project costs including the recommended upsizing are estimated at $60.6M. Required additional funding of approximately $27.6M will be provided through Pay-Go funding and/or financing. The estimated cost of the PUD (CCWSD/SW) Logistics & Operations Center is $49.4M. Available funding including Pay-Go and existing bond financing total $27.1M leaving additional required funding of $22.2M to be provided through Pay-Go and/or financing. The estimated cost for the General Government Operations component of the GOBP Campus is $60.7M. Pay-Go funding of $12.4M has been provided. The required additional funding will be provided through a combination of Pay-Go funding and/or financing of approximately $48.3M. If in the future direction is obtained to dispose of 2373 East Horseshoe Drive, (Sheriff’s CID building), 4420 Mercantile Ave., (PUD/CCWSD operations buildings), and 2885 S. Horseshoe, (GMD Transportation), estimated proceeds of $14.4 million could be realized. These proceeds could be used to offset a portion of project costs. 11.B Packet Pg. 43 01/11/2022 GROWTH MANAGEMENT IMPACT: There is no direct growth management impact as a result of this Executive Summary. LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for approval. RECOMMENDATION: To accept the status report for Collier County Infrastructure Sales Surtax projects, acknowledge the construction of a new DAS facility at County Site 305, and authorize completion of design for the Sheriff’s Forensics/Evidence Building to include expanding the size of the building to accommodate the move of CCSO Criminal Investigations Division from 2373 East Horseshoe Drive to the GOBP campus. Prepared by: Ed Finn, Interim Director, Facilities Management Division ATTACHMENT(S) 1. Exhibit A (PDF) 2. Surtax Project Status List 12.3.2021 (PDF) 3. [Linked] Surtax Project Presentation by Category Rev. 1.5.2022 (PDF) 11.B Packet Pg. 44 01/11/2022 COLLIER COUNTY Board of County Commissioners Item Number: 11.B Doc ID: 20490 Item Summary: Recommendation to accept the status report for Collier County Local Government Infrastructure Sales Surtax Projects, acknowledge the planned move of the Domestic Animal Services (DAS) facility to County Site 305, and authorize completion of design for Sheriff’s Forensics/Evidence Building to include expanding the size of the Sheriff’s facility to accommodate a move of CCSO Criminal Investigations Division from 2373 East Horseshoe Drive to the GOBP campus. (Ed Finn, Interim Facilities Management Director) Meeting Date: 01/11/2022 Prepared by: Title: – Facilities Management Name: Paula Brethauer 10/29/2021 4:41 PM Submitted by: Title: Director - Facilities Maangement – Facilities Management Name: Ed Finn 10/29/2021 4:41 PM Approved By: Review: Facilities Management Ed Finn Director - Facilities Completed 10/30/2021 7:02 PM Public Utilities Operations Support Jennifer Morse Additional Reviewer Completed 11/01/2021 12:36 PM Public Utilities Department Drew Cody Level 1 Division Reviewer Completed 11/01/2021 2:57 PM Public Utilities Department Joseph Bellone Level 2 Division Administrator Review Completed 11/02/2021 1:53 PM County Attorney's Office Colleen Greene Level 2 Attorney Review Completed 11/02/2021 3:58 PM Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 11/02/2021 4:08 PM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 11/03/2021 8:49 AM Office of Management and Budget Susan Usher Additional Reviewer Completed 11/03/2021 9:44 AM County Manager's Office Amy Patterson Level 4 County Manager Review Completed 01/05/2022 2:49 PM Board of County Commissioners Geoffrey Willig Meeting Pending 01/11/2022 9:00 AM 11.B Packet Pg. 45 11.B.a Packet Pg. 46 Attachment: Exhibit A (20490 : Infrastructure Sales Surtax Status Report) PROJECT VALIDATED AMOUNT PROJECT STATUS Transportation: 60168 Vanderbilt Bch Rd Ext. - 951 to 8th/16th 74,000,000$ Design 100% 60201 Pine Ridge Rd, Livingston 23,000,000$ Design 60% Phase 1 66066 Bridge Replacement (11) **33,000,000$ Construction 90 Days In 60147 Randall Intersection (was Proj 60065)7,000,000$ Design Procurement 60190 Airport Rd. - Vanderbilt to Immok 4,000,000$ Design Procurement 60215 Triangle Blvd 6,000,000$ Construction 43% 60212 New Bridges (6 of 11) Golden Gate Estates **34,000,000$ GG Bridges Surtax Validated 9.22.21 / 16th Street 100% Design 60228 Sidewalks 10,000,000$ 100% Plans Location 1 & 2 Subtotal - Transportation 191,000,000$ Facilities & Capital Replacements 70167 Forensic/Evidence Bldg.33,000,000$ Design 60% CMAR Selected / Procurement 85% 80039 Big Corkscrew Island Regional Park 40,000,000$ Phase 1 Construction 75% 50145 DAS Facility Relocation 6,000,000$ Designer Selected / Procurement 50% HVAC, Roofing, & Cap Equip Replace at Sheriff's & County Facilities To Be Validated 1,700$ To Be Validated 50163 Naples (Central) Library HVAC Replacement 1,756,220$ Construction 75% 50164 Health Bldg. HVAC 1,644,417$ Approach under study 50165 Health Bldg. Roof 657,000$ Design 100% 50166 Jail & Chiller Plant HVAC-completed 1,324,490$ Complete 50176 Immokalee Health Bldg. HVAC/Roof 1,383,500$ Complete 50181 Jail Isolation Rooms HVAC-completed 175,835$ Complete 50182 Jail Steam to Hot Water Boiler Conversion 431,447$ Complete 50183 Jail Security System Replacement 1,632,790$ Project Closeout Process 50184 Jail Generator - Phase 1 & Phase 2 3,150,000$ Phase 1: Construction 85% Phase 2: 30% Procurement 50185 Jail Laundry Replacement & Safety Upgrades 1,450,000$ Design 100% Procurement 5% 50187 Museum - Everglades City Roof Replacement-completed 68,979$ Complete 50188 Switchgear Upgrade A, B, & K 1,481,887$ Complete 50189 Underground Chilled Water Pipe 4,000,000$ Design 85% Procurement 25% 50190 Vineyards Com Pk Air System Replacement-completed 223,453$ Complete 50191 Em Serv Ctr Chiller Replacement 949,282$ Complete 50214 New Chiller Plant - Building K 11,500,000$ Procurement 25% 50221 Reliable Building Automation Upgrade 4,000,000$ Procurement 70% Construction 60% Commissioning & Programming 50% 50237 Jail Fire Alarm Replacement 1,300,000$ Design 30% 53007 Jail Kitchen Renovation 1,869,000$ Construction 99% Hurricane Resilience To Be Validated 8,280,000$ To Be Validated 50390 ESC Enclose Bay 1,500,000$ Design 100% 50391 PUD Generators 4,650,000$ Design-Build Procurement 100% Design 15% 50393 Generators - NCRP & Immoklee Sports Complex 570,000$ Design 5% EMS Substations (3) 55211 Heritage Bay EMS station 2,222,200$ Design 5% / Permitting 5% 55212 Golden Gate Estates 2,500,000$ Design 75% Procurement 50% 55213 Old US 41 EMS Station 1,277,800$ Procurement 50% Subtotal - Fac & Cap Replacements 139,000,000$ Community Priorities Career and Tech Training Ctr (To Be Validated)15,000,000$ To Be Validated 50112 VA Nursing Home (To Be Validated)30,000,000$ To Be Validated Workforce Housing Land Trust Fund (To Be Validated)20,000,000$ To Be Validated 50239 Mental Health Facility 25,000,000$ Procurement 60% Subtotal - Community Priorities 90,000,000$ TOTAL VALIDATED AMOUNT 420,000,000$ 11.B.b Packet Pg. 47 Attachment: Surtax Project Status List 12.3.2021 (20490 : Infrastructure Sales Surtax Status Report) 1Exceeding Expectations, Every Day! Project Updates 2Exceeding Expectations, Every Day! •Transportation -$191,000,000 –(8 Projects) •Facilities & Capital Replacements -$79,000,000 (3 Projects) •HVAC, Roofing & Capital Equipment Replacements at Sheriff’s & County Facilities -$39,000,000 –(20 Projects) •Hurricane Resilience -$15,000,000 (4 Projects) •EMS Stations -$6,000,000 (3 Projects) •Community Priorities -$90,000,000 (4 Projects) TOTAL COST: $420,000,000 Surtax Projects Overall Summary 3Exceeding Expectations, Every Day! Surtax Projects GMD Transportation Planning 8 Projects In Progress Validated at: $191,000,000 4Exceeding Expectations, Every Day! Order Description Validated Amount Status Transportation 1 60168 Vanderbilt Bch Rd Ext.-951 to 8th/16th $74,000,000 100%Design 2 60201 Pine Ridge Rd,Livingston $23,000,000 Design 60% Phase 1 3 66066 Bridge Replacement (11)**$33,000,000 Construction 90 Days In 4 60147 Randall Intersection (was Proj 60065)$7,000,000 Design Procurement 5 60190 Airport Rd.-Vanderbilt to Immokalee $4,000,000 Design Procurement 6 60215 Triangle Blvd $6,000,000 Construction 43% 7 60212 New Bridges (6 of 11)Golden Gate Estates **$34,000,000 GG Bridges Surtax Validated 9.22.21 16th Street 100% Design 8 60228 Sidewalks $10,000,000 100% Plans Location 1 & 2 Total $191,000,000 5Exceeding Expectations, Every Day! Project Manager: Mario Puente, P.E., Sr. Project Manager Project Number: 60168 Project Description: Design, permit and construct a 7- mile extension of Vanderbilt Beach Road. 6-lane divided urban from east of Collier Blvd to Wilson Blvd., followed by two lanes up to 16th St. NE. New intersections and traffic signals on Wilson Blvd., 8th St. NE and 16th St. NE. Canal relocation to south of the roadway from 29th Street N.W. to 15th Street N.W. Improvements to existing intersecting streets including Weber Boulevard, Massey Street and Douglas Street. Current Phase: 100% Plans (County Review) Design Budget: $5,287,005 Design Consultant: Jacobs Engineering Construction Budget: $101.9M (estimate; $74M Surtax) Right-Of-Way: $32.5M -ongoing Milestones /Challenges To Date:Updated:1/5/2022 •Permit Status:SFWMD Permit received. FDEP Permit pending. (County inquiring with FDEP due to delayed permit approval) •ROW Status: o Order of Taking/Eminent Domain completed on Sep 2021 •Contract Status:preparing bid package for construction procurement •AIMS: currently no issues •Construction Procurement to start upon receipt of FDEP Permit. PUD portion will be included through an Addendum to avoid delays. 1/5/2022 Vanderbilt Beach Rd Extension Project Phase Anticipated Schedule 100% Design 01/2022 Court Condemnation/OT 10/2021 Construction Procurement 01/2022 –06/2022 Construction Start 06/2022 (pending FDEP Permit) Construction Duration 2.5 years 6Exceeding Expectations, Every Day! Project Manager: Mario Puente, P.E., Sr. Project Mgr. Project Number: 60201 Project Description: Design, permit, and construct improvements at the intersection of Livingston Road and Pine Ridge Road (Continuous Flow Intersection), at the intersection of Whippoorwill Lane and Pine Ridge Road and at the I-75 interchange on Pine Ridge Road (Diverging Diamond Intersection). Design-Build method. Current Phase: Negotiating with top-ranked Consulting Firm for Phase 1 (60% Design). Design Budget: $3.10M Design Consultant: TBD Construction Budget: $31M Incl. Grant Funding: $5.4M Milestones /Challenges To Date:Updated:1/5/2022 Current Status 1/5/22: •Permit Status: SWFMD Permit: TBD FDEP Permit: TBD •Contract Status: •Two design consultants’ proposals were received. BCC short list approval received on September 14th BCC Meeting. Currently negotiating with top ranked firm. •Monthly Coordination with FDOT –ongoing •AIMS: N/A 1/5/2022 Pine Ridge Rd Improvements Project Phase Anticipated Schedule FDOT PD&E Phase II 09/2019 –02/2022 Contract Award Design Consultant Phase 1 03/2022 60% Design Phase 1 10/2023 Design-Build Phase 1 & 2 07/2024 7Exceeding Expectations, Every Day! Project Manager: Robert White P.E., Sr. Field Inspector Project Number: 66066 Project Description: Replace 11 functionally obsolete and structurally deficient bridges. Two phase construction; one side of each new bridge is constructed while traffic passes on the other. Current Phase: Construction (90 days in) Construction: $29.4M Company: Package A –Thomas Marine Package B –ZEP Construction Package C –ZEP Construction Package D –Quality Enterprises (LAP) CEI Cost: $3.2M CEI Company: HighSpans Milestones / Challenges To Date: 1/5/2022 •PKG A -1 of 2 bridges under construction 18% complete •PKG B -1 of 4 bridges under construction, 11.5% complete •PKG C -2 of 4 bridges under construction, 4.5% complete •PKG D -1 bridge, waiting on FDOT CEI Contract 1/5/2022 11 Bridge Replacements East of SR29 Project Phase Anticipated Schedule Notice To Proceed for Construction 07/19/2021 Final Completion PKG A January 2023 Final Completion PKG B January 2024 Final Completion PKG C January 2024 8Exceeding Expectations, Every Day! Project Manager: Dennis McCoy, P.E., Sr. Project Mgr. Project Number: 60147 Project Description: Widening Randall Boulevard to four lanes (expandable to six lanes for future needs), constructing a continuous flow lane eastbound from Immokalee Road at Randall Boulevard intersection, adding a new traffic signal on Randall Boulevard at 8th Street NE intersection, adding on-street bike lanes and sidewalks and improving drainage within the project area. Future phase 2 consists of a flyover. Current Phase: Design Procurement Design Budget: $0.95M Design Consultant: TBD( in Negotiation with HNTB ) Construction Budget: $6.7M (estimate) –Surtax Right-Of-Way: $3.2M (both phases) Milestones / Challenges To Date: 1/5/2022 •Permit Status:not started •ROW Status: not started •Contract Status:TE is currently negotiating with HNTB Corporation for Design Services. •To improve safety until this project is completed, a temporary signal at Randall Blvd & 8th Str. NE is currently under design, to be installed early 2022. 1/5/2022 Randall Blvd & Immokalee Rd Intersection Project Phase Anticipated Schedule Design Procurement 05/2021 –01/2022 Design, Permitting & ROW/Mitigation 02/2022 –08/2023 Construction Procurement 08/2023 –02/2024 Construction 03/2024 –03/2025 9Exceeding Expectations, Every Day! Project Manager: Bee Thao, P.E., Sr. Project Manager Project Number: 60190 Project Description:Capacity improvement of Airport Road from north of Vanderbilt Beach Road to Immokalee Road.There will be a third southbound through lane,extend the third northbound through lane,improve the drainage within the project area,add on-street bike lanes and sidewalks,and improve the signals on this roadway. Current Phase: Design Procurement Design Budget: $1.5M ($1.5M CIGP Grant) Design Consultant: TBD Construction Budget: $14.5M($4.93M CIGP Grant) Right-Of-Way: $81,700 CEI Budget: $1.5M Surtax Validated amount: $4M Milestones /Challenges To Date:1/5/2022 •Permit Status:SFWMD Permit –to be done at 60%design stage •FDEP Permit –to be done at 60%design stage •ROW Status:TBD –Pending Design •ROW acquisition starts at the 60%design plan stage,preliminary plans require only a sidewalk easement from Stonebridge •Contract Status:01/11/22 –BCC Approval of final ranking of Design Engineering Consultant. •AIMS:Currently no issues 1/5/2022 Airport Rd Widening-Airport Road -Vanderbilt Project Phase Anticipated Schedule Design Procurement started 01/2021 Design & Permitting start 02/2022 Construction Start 07/2024 Construction Completion 01/2026 10Exceeding Expectations, Every Day! Project Manager: Shannon Bassett, Sr. Field Inspector Project Number: 60215 Project Description:Operational improvements include sidewalk improvements on both sides along Triangle Boulevard and Price Street and median modifications that will increase turn lane capacity and traffic flow at US 41 and Triangle Boulevard,Price Street and US 41 and all along the Triangle Boulevard corridor.To increase traffic flow and relieve congestion,one roundabout will be constructed at Triangle Boulevard and Celeste Drive. Current Phase: Construction Work completed: 43% Construction: $3,395,000 (Surtax funded) Company: Cougar Contracting CEI: In-house Surtax Validated amount: $6,000,000 Milestones / Challenges To Date: 1/5/2022 All medians project wide are under construction in multiple stages. The traffic circle has been installed. Construction on Price Street and US41 is underway, the signal improvements are ongoing. The project is running on schedule and within budget. Completion is planned for April 2022. 1/5/2022 60215 Triangle Blvd Improvements Project Phase Anticipated Schedule Notice To Proceed for Construction 04/2021 Substantial Completion 03/2022 Final Completion 04/2022 11Exceeding Expectations, Every Day! Project Manager: Marlene Messam, P.E, Principal PM Project Number: 60212 Project Description: Design and construct new bridges and related roadway & intersection improvements at the following locations: •47th Ave NE (btw Immokalee Rd. & Everglades Blvd.) •North end of 13th St. NW (north of Golden Gate Blvd.) •Wilson Blvd. S (south of Golden Gate Blvd.) •10th Ave SE (between Everglades Blvd. & Desoto Blvd.) •62nd Ave. NE (between Everglades Blvd. and 40th St. NE) Current Phase: Surtax Committee Validation Design Budget: $2,267,540 Design Consultant: TBD Construction Budget: $ 22,975,391 Right-Of-Way: $ 112,361 CEI-Services:$ 2,574,268 Combined GG Bridges Surtax Validated amount: $34M Milestones /Challenges To Date:1/5/2022 •Surtax Committee validated the project September 22, 2021. Procurement for Design Consultant for first two bridges starts in January 2022. Anticipate construction for 2025.1/5/2022 Golden Gate Estates Bridges Project Phase Anticipated Schedule Surtax Validation 09/22/2021 Design Procurement (2 bridges)01/2022 Design Procurement (3 bridges)01/2023 Construction anticipated 2025 through 2027 12Exceeding Expectations, Every Day! Project Manager: Dennis McCoy, P.E., Sr. Project Mgr. Project Number: 60212 Project Description: The project limits are from Golden Gate Boulevard to Randall Boulevard. The project will include: a new two-lane bridge over the Golden Gate Main Canal, a new sidewalk on the west side of the roadway’ improved drainage throughout the project area, shoulder widening and roadway resurfacing. Current Phase: Procurement of Design Services Design, Permitting & Construction: $9,030,000 Incl. Grants: $4.9M includes Surtax: $4.1M CEI Budget: $700,000 Combined GG Bridges Surtax Validated amount: $34M Milestones /Challenges To Date:1/5/2022 •Permit Status: SWFMD Permit to be submitted at 60% design stage FDEP Permit to be submitted at 60% design stage •ROW Status: to be determined •Contract Status: Procurement for Design Engineering Consultant is in process. Anticipate start of design in May 2022. Once the grant from FDOT is scheduled, the original PD&E Study needs to be re-evaluated as it has expired. •AIMS: None 1/5/2022 16th Street NE Bridge Project Phase Anticipated Schedule Design Consultant Procurement 12/2021 –08/2022 100% Design 01/2024 FDOT LAP/Grant expected FY24/25 PD&E Re-Evaluation FDOT 02/2024 –05/2024 Construction start 12/2024 –12/2025 13Exceeding Expectations, Every Day! Project Manager: Chad Sweet, P.E., PMP, Senior Project Manager Project Number: 60228 Project Description: Add new sidewalks in 8 different locations throughout the County. Current Phase:Design of first 4 locations in Naples Manor are underway.Design is complete in locations 1&2;locations 3&4 design will start shortly.Design locations 5 and 6 are being negotiated currently.Design locations 7&8 will start FY 22. Design & Permitting: $0.9M Construction Budget: $8.0M (Surtax funded) CEI Budget: $0.9M Right-Of-Way: $0.2M Surtax Validated amount: $10.0M Milestones /Challenges To Date:1/5/2022 •Permit Status: Locations 1&2 are permitted. Locations 3&4 will be permitted with PUD (Public Utility Department) and Stormwater. All four locations will be constructed in conjunction with PUD and Stormwater. •ROW Status: Corner clip acquisition is in progress in Location 2. Future acquisitions are undetermined at this time for project locations 3-8, will be identified in the design stage. •Contract Status: Construction of locations 1&2 will commence upon completion of PUD and Stormwater projects. Design of remaining locations continues per schedule and in coordination with other Departments. 1/5/2022 Sidewalks in Various Locations Project Phase Anticipated Schedule Design NTP –Location 1 & 2 9/21/2020 100% Plans-Location 1 & 2 7/2021 Construction Start 7/2022 (pending PUD & Stormwater project) Construction Duration est. 9 months 14Exceeding Expectations, Every Day! Surtax Projects Facilities Management 8 Completed Projects Validated at: $6,038,873 ($955,590 Returned to Reserves) 22 Projects In Process Validated at: $149,679,427 5 Future Projects To Be Validated: $73,281,700 Total Cost: $229,000,000 15Exceeding Expectations, Every Day! Facilities & Capital Replacements 16Exceeding Expectations, Every Day! Order Description Validated Amount Status Facilities &Capital Replacements 1 70167 Forensic/Evidence Building $33,000,000 Design 60% CMAR Selected / Procurement 85% 2 80039 Big Corkscrew Island Regional Park –Phase 1 $40,000,000 Construction 70% 3 50145 DAS Facility Relocation $6,000,000 Designer Selected Procurement 50% Total $79,000,000 17Exceeding Expectations, Every Day! District #: 1 Project #: 70167 Project Sponsor: Kevin Rambosk, Collier County Sheriff Project Manager: Ayoub Al-Bahou, P.E. Project Scope: This facility will house crime scene, evidence and technical services bureau and include storage for evidence, vehicles as well as large equipment. Construction Budget: $33,000,000 Architect/Engineer: Stantec Construction Manager: Manhattan GMP Expected: (60%) Fall 2021 Notice to Proceed Date:Fall 2022 Estimated Substantial Completion Date:Fall 2024 Milestones/Challenges To Date: 11/29/2021 •60% construction documents were delivered on 10/27/21 for the single-story (Forensic only) and the two-story (entire Criminal Investigation Division) buildings. •Manhattan Construction Company has provided cost estimate for both options. •Presentation to update BCC on the GOBP in December's Board meeting. CCSO Forensics / Evidence Building DESCRIPTION OF WORK % COMPLETE Procurement 85% Design 60% Construction 0% 18Exceeding Expectations, Every Day! District #: 5 Project #: 80039 Project Sponsor: Barry Williams, Director Parks & Rec. Project Manager: Dave Closas, PMP Project Scope: The BCIRP Phase 1 includes 4 soccer fields, 2 softball fields, north concession stand, outdoor basketball courts, tennis courts, pickleball courts, an aquatic center, playground, community center, a Maintenance Building, and Event Lawn. Construction Budget: $45,065,454 Architect/Engineer: Q Grady Minor & Victor Latavish Owner’s Representative (CEI): Wood E&IS General Contractor: ASTRA Construction Services Notice to Proceed Date: Nov. 12, 2019 Estimated Move In Date: January 2022 Surtax Validated amount: $40,000,000 Milestones/Challenges To Date: 12/06/2021 •North Phase is complete and working on punch list close out items with contractor. Six sports fields and north concession stand have been turned over to Parks and Recreation on 8/2/2021 and opened for organized leagues. •South Phase is 70% complete. Work continues enclosing facilities and interior finishes, mechanical/electrical/plumbing, site improvements, outdoor sports courts and events lawn earthwork. Big Corkscrew Island Regional Park -Phase 1 DESCRIPTION OF WORK % COMPLETE Procurement 100% Design 100% Construction 70% 19Exceeding Expectations, Every Day! District #: 3 Project #: 50145 Project Sponsor: Domestic Animal Services Project Manager: Camden Smith, PMP Project Scope: Construct a new DAS facility adjacent to the Government Operations Business Park (GOBP) & Paradise Coast Sports Complex. The new site will allow for program expansion to meet the current and future mission of Domestic Animal Services. Project Budget: $6,500,000 Surtax Validated Amount: $6,000,000 Surtax Oversight Committee: September 22, 2021 Designer: ADG Design Notice to Proceed Date: November 22, 2021 Notice to Proceed: Spring 2023 Estimated Completion Date: Fall 2024 Milestones/Challenges To Date: 12/28/2021 •CMAR solicitation bid opened 12/16/2021. Committee Organization meeting scheduled for 1/6/2022 •Design Programming Meeting held on 12/17/2021; initial design is under way •ADG Design Contract was approved by BCC 10/12/2021 •On September 22, 2021, the Surtax Oversight committee approved adding an additional expenditure category for land acquisition. DESCRIPTION OF WORK % COMPLETE Procurement 50% Design 0% Construction 0% DAS Facility Relocation 20Exceeding Expectations, Every Day! HVAC Roofing & Capital Equipment Replacements at Sheriff’s & County Facilities 21Exceeding Expectations, Every Day! Order Description Validated Amount Status HVAC,Roofing,&Cap Equip Replacements Sheriff's &County Facilities 1 To Be Validated $1,700 2 50163 Naples (Central ) Library HVAC Replacement $1,756,220 Construction 75% 3 50164 Health Bldg.HVAC $1,644,417 Approach Under Study 4 50165 Health Bldg.Roof $657,000 Design 100% 5 50166 Jail &Chiller Plant HVAC $1,324,490 Complete 6 50176 Immokalee Health Bldg.HVAC/Roof $1,383,500 Complete 7 50181 Jail Isolation Rooms HVAC $175,835 Complete 8 50182 Jail Steam to Hot Water Boiler Conversion $431,447 Complete 9 50183 Jail Security System Replacement $1,632,790 In Project Closeout Process 10 50184 Jail Generator -Phase 1 &2 $3,150,000 Phase 1 Construction 85% Phase 2 Procurement 30% 11 50185 Jail Laundry Replacement &Safety Upgrades $1,450,000 Design 100% Procurement 5% 12 50187 Museum -Everglades City Roof Replacement $68,979 Complete 13 50188 Switchgear Upgrade A,B, &K $1,481,887 Complete 14 50189 Underground Chilled Water Pipe $4,000,000 Design 85% Procurement 25% 15 50190 Vineyards Community Park Air System Replacement $223,453 Complete 16 50191 Emergency Service Center Chiller Replacement $949,282 Complete 17 50214 New Chiller Plant –Building K $11,500,000 Procurement 25% 18 50221 Reliable Building Automation Upgrade $4,000,000 Procurement 70% Construction 60% Commissioning & Programming 50% 19 50237 Jail Fire Alarm Replacement $1,300,000 Design 30% 20 53007 Jail Kitchen Renovation $1,869,000 Construction 99% Total $39,000,000 22Exceeding Expectations, Every Day! District #: 4 Project #: 50163 Project Sponsor: Tanya Williams, Director Library Division Project Manager: John McCormick, PE Project Scope: Remove and replace existing HVAC equipment, ductwork, acoustical grid ceiling, and inoperable 130-ton chiller. Install new BAC Net compatible controls with integrated IAQ sensors. Replace and/or re-lamp existing lighting fixtures with LED fixtures and bulbs. Increase size of chiller yard wall openings and install new larger louvers to allow for proper airflow to new chiller Construction Budget: $1,560,000.00 Architect/Engineer: Victor Latavish General Contractor: Cosugas LLC. Notice to Proceed Date: March 8, 2021 Estimated Substantial Completion Date: January 2022 Milestones/Challenges To Date: 12/22/2021 •Construction 95% complete. •Construction start delayed to off season at request of Library DESCRIPTION OF WORK % COMPLETE Procurement 100% Design 100% Construction 95% Naples Regional (Central) Library -HVAC Replacement 23Exceeding Expectations, Every Day! District #: 1 Project #: 50164 Project Sponsor: Facilities Management Project Manager: John McCormick, PE Project Scope: Construction Budget: $1,640,000 Architect/Engineer: TBD General Contractor: TBD Notice to Proceed Date: Estimated 3/1/2022 Estimated Substantial Completion Date: 6/1/2023 Milestone/Challenges To Date: 12/23/2021 •Current proposed HVAC Design is under review for potential redesign pending additional funding that will have an expanded scope to include all 3 Floors and additional Rooftop Equipment. Building H -HVAC DESCRIPTION OF WORK % COMPLETE Procurement 0% Design 0% Construction 0% 1 2 3 24Exceeding Expectations, Every Day! District #: 1 Project #: 50165 Project Sponsor: Facilities Management Project Manager: John McCormick, PE Project Scope: Roof Replacement Construction Budget: $600,000 Architect/Engineer: BSSW Architects General Contractor: TBD Notice to Proceed Date: Estimated 3/1/2023 Estimated Substantial Completion Date: 12/1/2023 Milestones/Challenges To Date: 12/23/2021 •Project on hold until Building H HVAC Replacement project is completed. Building H -Roof Replacement DESCRIPTION OF WORK % COMPLETE Procurement 0% Design 100% Construction 0% 25Exceeding Expectations, Every Day! District #: 1 Project #: 50166 Project Sponsor: CCSO Project Manager: John McCormick, PE Project Scope: Replace existing chiller with two new chillers. The new chillers will allow for a lead/lag operation thereby extending the usable life of each chiller as well as allow for redundancy in the system should one chiller fail. Construction Budget: $1,520,000 General Contractor: Air Mechanical and Service Corp. Surtax Validated Amount: $1,324,490 Project Completed: 7/30/2020 •Completed $201,000 under approved budget J1/J2 Chillers Plant HVAC DESCRIPTION OF WORK % COMPLETE Procurement 100% Design 100% Construction 100% 26Exceeding Expectations, Every Day! District #: 5 Project #: 50176 Project Sponsor: Mark Lemke, Immokalee Division Director FDOH Project Manager: John McCormick, PE Project Scope: Replace existing three-zoned AC and outside air units and add additional fourth zone to increase capacity and better serve the building. Replace existing roof, grid ceiling, and update lighting to energy efficient LED. Construction Budget: $1,403,500 Architect/Engineer: Victor Latavish General Contractor: DEC Contracting Group, Inc. Notice to Proceed Date: Aug. 5, 2020 Substantial Completion Date: July 31, 2021 Surtax Validated Amount: $1,383,500 Project Completed: 7/22/2021 •Completed $40,000 under approved budget. Immokalee Health Department HVAC and Roof Replacement DESCRIPTION OF WORK % COMPLETE Procurement 100% Design 100% Construction 100% 27Exceeding Expectations, Every Day! District #:1 Project #: 50181 Project Sponsor: Facilities Management Project Manager: John McCormick, PE Project Scope: Installation of new code compliant exhaust system to meet ASHRAE standards for Isolation rooms. System to include HEPA filtration with exhaust duct routed through the roof of the existing J3 building. Construction Budget: $273,000 Owner’s Representative (CEI) General Contractor: PlugSmart Substantial Completion Date: December 2019 Surtax Validated Amount: $175,835 Project Completed: 12/30/2019 •Completed $97,000 under approved budget. J3 Jail Isolation Room DESCRIPTION OF WORK % COMPLETE Procurement 100% Design 100% Construction 100% 28Exceeding Expectations, Every Day! District #: 1 Project #: 50182 Project Sponsor: Chief Middlebrook, Sheriff, Collier County Project Manager: John McCormick, PE Project Scope: This project encompasses the replacement of the three existing steam boilers, associated piping specialties, and water storage tanks with twelve new energy efficient rack mounted natural gas water heaters. Construction Budget: $550,000 General Contractor: Capital Contractors, LLC Notice to Proceed Date: Nov. 20, 2020 Completion Date: April 12, 2021 Surtax Validated Amount: $431,447 Project Completed: 4/12/2021 •Completed $118,553 under budget •Unused funding allocated to J1/J2/J3/PG1 Fire Alarm Replacement J1/J2 Jail Steam to Hot Water Boiler Conversion DESCRIPTION OF WORK % COMPLETE Procurement 100% Design 100% Construction 100% 29Exceeding Expectations, Every Day! Districts #: 1 & 5 Project #: 50183 Project Sponsor: Director Bouza, CSSO Project Manager: Dave Closas, PMP Project Scope: Project will provide an upgraded State –of-Art security and CCTV systems to meet the security and operational requirements for the Naples and Immokalee jail facilities. Construction Budget: $1,632,790 Design-Build Contractor: Stanley Convergent Security Solutions Notice to Proceed Date: Apr. 1, 2020 Estimated Final Completion Date: November 2021 Milestones/Challenges To Date: Updated 12/06/2021 •Currently preparing project closeout documents. •Immokalee Jail: Security System and Camera installs are complete and operational •Naples Jail: Security System and Camera installs are complete and operational DESCRIPTION OF WORK % COMPLETE Procurement 100% Design 100% Construction 100% CCSO Security & CCTV Upgrades –Jails 30Exceeding Expectations, Every Day! District #: 1 Project #: 50184 Project Sponsor: Collier County Sheriff’s Office Project Manager: Thomas James Orr Project Scope: Phase 1 of the Generator Project involves installing Temporary Electrical Power and Feeds so that the J1 Electrical Room can be de-energized. The Electrical Switchgear will then be dismantled, and a new section of the Switchgear will be installed that will allow the J1 J2 Jail to be fully powered by a Generator. The Contractor will also be installing a Tri Star Docking Station that will allow a Portable Generator to be connected to power up the J1 J2 Buildings. Surtax Awarded amount: $650,000 Bid awarded -Construction: $695386.22 Construction Budget: Architect/Engineer: Atkins North America General Contractor: EBL Partners LLC.& Simmonds Electrical Notice to Proceed Date: December 21, 2020 Estimated Substantial Completion Date: October 31,2021 Estimated Final Completion Date: November 31, 2021 Milestones/Challenges To Date: 12/06/2021 •Temporary Electric Service Complete 5-31-21. •Electrical Switchgear modifications complete needs to be tested •FPL Transformer is Energized Electric Meter is set •Tristar Docking Station on Site and being rigged into place Jail J1-J2 Generator -Phase 1 DESCRIPTION OF WORK % COMPLETE Procurement 100% Design 100% Construction 85% 31Exceeding Expectations, Every Day! District #: 1 Project #: 50184.0 Project Sponsor:CCSO Project Manager: John McCormick, PE Project Scope: J1/J2-Furnish and install the Support Platform and the surrounding wind screen for the generator. Furnish and install the generator, Diesel Fuel Tanks, pumps, and the related equipment. Connect the generator to the existing Tri- Star Docking Station located in the adjacent electrical room. Building H-Furnish and install a 1000 kW generator and sound attenuating panel enclosure. Reutilize the existing Diesel Fuel Storage Tank. Construction Budget: $2,500,000 Architect/Engineer: TBD General Contractor: TBD Notice to Proceed Date: TBD Estimated Substantial Completion Date: TBD Milestones/Challenges To Date: 12/23/2021 •FDEM Grant received for Generator purchase •Construction must be solicited independently to comply with FDEM grant. •Surtax Committee acceptance 9/22/21 to increase scope to include Building H generator DESCRIPTION OF WORK % COMPLETE Procurement 30% Design 0% Construction 0% Jail J1-J2 Generator Platform & Building H Generator –Phase 2 32Exceeding Expectations, Every Day! District #: 1 Project #: 50185 Project Sponsor: Collier County Sheriff’s Office Project Manager: Olivier Sureau, PMP Project Scope: The Jail Laundry Renovation Project includes a new laundry layout to provide for better supervision,new electrical, plumbing, and mechanical systems, and new equipment. Failing support infrastructure, coupled with aging equipment and improper space configuration, has created operational, security and safety issues with the laundry facility. Surtax Awarded Amount: $1,450,000 Design: $150,000 Construction: $900,000 (Est.) Bid Awarded -Construction: T.B.D Architect/Engineer: Stantec General Contractor: T.B.D Notice to Proceed Date: T.B.D Estimated Substantial Completion Date: End Q3 2023 Estimated Final Completion Date: End Q4 2023 Milestones/Challenges To Date: 12/22/2021 •Procurement assigned solicitation # 22-7959 and Kristofer Lopez on 12/09/21. Awaiting confirmation by CCSO of site visit date for the Pre-Bid meeting to advertise the project •Stantec filed permit application on 11/08/21. Fees were paid 12/10/21. Plans are under review •Permit plans and specs set received on 11/05/21 from Stantec •Procurement process takes between 4 to 6 months •Construction will take 420 days to substantial completion plus 120 days to final completion for a total of 540 days which is 18 months •Future challenge: how to secure the project area –which is centrally located in the Jail building. Will require access to the site directly from the outside of the building Jail Laundry Replacement & Safety Upgrades DESCRIPTION OF WORK % COMPLETE Procurement 10% Design 100% Construction 0% “Out of Order” Equipment Existing Equipment Condition Jail at Collier County Campus 33Exceeding Expectations, Every Day! District #:1 Project #: 50187 Project Sponsor: Park & Recreation Project Manager: John McCormick, PE Project Cost:$83,950 Surtax Validated Amount:$68,979 Project Completed: 6/25/2020 Museum Of The Everglades -Roof DESCRIPTION OF WORK % COMPLETE Procurement 100% Design 100% Construction 100% 34Exceeding Expectations, Every Day! District #: 1 Project #: 50188 Project Sponsor: Facilities Management Project Manager: John McCormick, PE Project Scope: New main disconnects will be designed and built with modified cradles to meet the current racking limitations at the existing cells within each switchgear bank in all three substations. New Sensors to be installed for data collection, continuous monitoring, and dashboard access for proactive maintenance. Construction Budget: $1,200,000 Architect/Engineer: Schneider/Square D General Contractor: Graybar/ Schneider Electric Owner’s Representative (CEI): Jerry Shukes/John McCormick, PE Notice to Proceed Date: April 17, 2020 Substantial Completion Date: March 15, 2021 Surtax Awarded Amount: $1,481,887 Project Completed: 4/30/2021 •Completed $318,113 under approved budget. •Unused funds allocated to J1/J2/J3/PG1 Fire Alarm Replacement Switchgear A, B, & K Upgrades DESCRIPTION OF WORK % COMPLETE Procurement 100% Design 100% Construction 100% 35Exceeding Expectations, Every Day! District #: 1 Project #: 50189 Project Sponsor: Facilities Management Project Manager: John McCormick, PE Project Scope: Replacement of approximately 2 miles of PVC Underground Chiller Water Main Piping now serving 11 Main Campus Buildings with HDPE or Polypropylene Butt Fusion Welded (seamless) pipe. Installation of approximately 14 pre-cast isolation valve boxes. Construction Budget: $4,000,000.00 Architect/Engineer: Stantec/Matern General Contractor: TBD Notice to Proceed Date: 9/16/2020 Estimated Substantial Completion Date: 12/1/2022 Milestones/Challenges To Date: 12/23/2021 •Design in progress. Alternate route to mitigate disruption to Jail operations in process •On site survey of existing piping complete. •Construction bundled CMAR with New Chiller Plant Building K. •CMAR negotiations complete. Pending outside legal review from Collier County. DESCRIPTION OF WORK % COMPLETE Procurement 25% Design 90% Construction 0% Chilled Water Piping Mains 36Exceeding Expectations, Every Day! District #: 3 Project #: 50190 Project Sponsor: Dan Rodriguez, PSD Dept. Head, PSD Project Manager: John McCormick, PE Project Description: Replace existing non-functional Roof Top Outside Air Units with new. Replace existing thermostats with new Reliable air quality monitoring controls. New units will monitor air quality for Temperature, Particulate, VOC, Humidity, and CO2. These controls will be integrated to the new Collier County Energy Dashboard for remote monitoring and diagnostics. Construction Budget: $300,000 General Contractor: United Mechanical Inc. Notice to Proceed Date:March 11, 2020 Substantial Completion Date: October 15, 2020 Project Completed: 11/10/2021 •Completed $24,706 under approved budget Vineyards Community Center Outside Air Systems Project DESCRIPTION OF WORK % COMPLETE Procurement 100% Design 100% Construction 100% 37Exceeding Expectations, Every Day! District #: 1 Project #: 50191 Project Sponsor: Dan Summers, Director-Emergency Services Division Project Manager: John McCormick, PE Project Scope: Replace two existing 300-ton air cooled chillers with new Collier County acquired 300- ton Trane ACR model air cooled chillers. Replace existing JCI controls with Reliable BACnet open protocol controls. Cut eight 4’x4’ openings in existing chiller yard walls and install Engineered Hurricane rated louvers to allow for proper airflow to new chillers. Construction Budget: $1,202,500 General Contractor: Capital Contracting/ Plug Smart Notice to Proceed Date: May 15, 2020 Substantial Completion Date: August 15, 2020 Final Completion Date: September 28, 2020 Project Completed: 9/28/2020 •Completed $253,218 under approved budget. •Unused funds allocated to J1/J2/J3/PG1 Fire Alarm Replacement Emergency Service Center Chiller Replacement DESCRIPTION OF WORK % COMPLETE Procurement 100% Design 100% Construction 100% 38Exceeding Expectations, Every Day! District #: 1 Project #: 50214 Project Sponsor: Facilities Management Project Manager: John McCormick, PE Project Scope: The proposed New Chiller Plant will include four (4) air-cooled chillers totaling 2,000 tons of cooling capacity, a supplemental Thermal Energy Storage (TES) chilled water tank, and two(2) dedicated 1250 kW emergency generators. Construction Budget: $11,500,000.00 Architect/Engineer: TBD General Contractor: TBD Notice to Proceed Date: TBD Estimated Substantial Completion Date: June 2023 Milestones/Challenges To Date: 12/23/2021 •Construction to be bundled CMAR with Underground Chilled Water Piping Mains project. •CMAR negotiations complete. Contract pending outside legal review from Collier County. •Design contract expected for BCC approval at 1/25/22 meeting Chiller Plant -Building K DESCRIPTION OF WORK % COMPLETE Procurement 25% Design 0% Construction 0% 39Exceeding Expectations, Every Day! District #: All Districts Project #: 50221 Project Sponsor: Facilities Management Division Project Manager: John McCormick, PE Project Scope: Replacement of the proprietary JCI/Metasys N2 HVAC controls with open protocol BACnet Reliable controls in 54 Collier County building. 23 of these buildings requiring total system replacement. Construction Budget: $4,000,000.00 Architect/Engineer: N/A General Contractor: Plug Smart Notice to Proceed Date: February 18, 2021 Estimated Substantial Completion Date: June 2022 Milestones/Challenges To Date: 12/23/2021 •Identified critical systems for priority replacement •14 Buildings completed, 6 in progress of 24 total •Supply chain disruptions continue. Reliable Building Automation Upgrades DESCRIPTION OF WORK % COMPLETE Procurement 80% Design 0% Construction 80% Commissioning and Programming 75% 40Exceeding Expectations, Every Day! District #: 1 Project #: 50237 Project Sponsor: CCSO Project Manager: John McCormick, PE Project Scope: Full replacement of the Fire Alarm Systems. The proposed replacement systems will incorporate state of the art non-proprietary devices, sensors and annunciator panels. This will resolve the nuisance alarms and inconsistent system performance, while bringing the structures into current Fire Code compliance Construction Budget: $1,300,000 Architect/Engineer: Victor Latavish General Contractor: TBD Notice to Proceed Date: TBD Estimated Substantial Completion Date: TBD Milestones/Challenges To Date: 12/23/2021 •Current structural As-Built drawings 98% complete. •Fire Alarm design in progress. •Surtax funding approved 9/22/2021. BCC amended 10/12/21 Jail J1-J2-J3-PG1 Fire Alarm Replacement DESCRIPTION OF WORK % COMPLETE Procurement 0% Design 30% Construction 0% 41Exceeding Expectations, Every Day! Jail -J1 Kitchen Renovation District #: 1 Project #: 53007 Project Sponsor: Collier County Sheriff’s Office Project Manager: Claudia Roncoroni Project Scope: The Jail Kitchen Renovation Project includes a new kitchen layout to provide for better supervision,a new floor, new restrooms, a new staff Lounge, new electrical, plumbing, and mechanical systems, and new kitchen equipment –including walk-in freezers and refrigerators. Surtax Awarded amount: $1,869,000 Bid Awarded -Construction: $1,763,302 Architect/Engineer: BSSW Architects General Contractor: SDP Consultants Corp. –SDP, Inc. Notice to Proceed Date: May 04, 2020 Substantial Completion Date: March 30, 2021 Estimated Final Completion Date: T.B.D. Substantial Completion is achieved when the CO is issued and all punch list items have been addressed. CO was issued on 06/03/2021. SDP is still however addressing punch list items and equipment related issues. Beltram is working with CCSO on the dishwasher replacement.Milestones/Challenges To Date: 12/06/2021 •Substantial Completion: issued on 03/30/21 •CO: issued on 06/03/21 •Final Completion still pending. SDP is working on a few punch list items. •Challenge: delays on the schedule triggered by COVID-19 related issues. •Challenge:resolution of a structural existing issue discovered in January 2021. •Challenge:having all existing open permits on the jail building properly closed. •Challenge:punch list items replacement has been impacted by materials availability and by supply chain disruptions. DESCRIPTION OF WORK % COMPLETE Procurement 100% Design 100% Construction 99% Before Renovation After Renovation Jail at Collier County Campus 42Exceeding Expectations, Every Day! Hurricane Resilience 43Exceeding Expectations, Every Day! Order Description Validated Amount Status Hurricane Resilience 1 To Be Determined (To Be Validated)$8,280,000 To Be Validated 2 50390 Emergency Service Center East Bay Enclosure $1,500,000 Design 100% 3 50391 PUD Generators (14 Emergency Power System)$4,650,000 Design-Build Procurement 100% Design 15% 4 50393 Generators -NRCP&Immokalee Sports Complex (Grant Match)$570,000 Design 5% Total $15,000,000 44Exceeding Expectations, Every Day! District #: 1 Project #: 50390 Project Sponsor: Dan Summers, Director of Emergency Services Project Manager: Dave Closas, PMP Project Scope: The project will enclose the east bay storage bay and provide a climate-controlled environment for the storage and distribution of disaster/Emergency supplies and support Emergency Service Center Operations. Design Cost: $97,800 Design/Construction Budget: $1,500.000 Architect/Engineer: Harvard Jolly General Contractor: 100% Construction/Bidding Documents: November 2021 Design Notice to Proceed Date: Dec. 14, 2020 Surtax Validated Amount:$1,500,000 Estimated Substantial Completion Date: TBD Milestones/Challenges To Date: 12/6/21 •100% construction drawings have been submitted and under view. Permitting is ongoing with GMD. •Will work with Procurement on developing acquisition strategy. Expected to release construction solicitation in February/March 2022 •Will go to the Surtax Board in March 2022 to request additional funding once bids are received. DESCRIPTION OF WORK % COMPLETE Procurement 50% Design 100% Construction 0% Emergency Service Center -East Bay Enclosure 45Exceeding Expectations, Every Day! District #: All Districts Project #: 50391 Project Manager: Dan Roman/Harry Raftopoulos Project Description: Install 14 permanent back-up power systems at critical wastewater pump stations (generators or diesel pumps depending on location) Purpose: To maintain compliance with local, state and federal regulations and to improve hurricane resiliency and operational reliability in the wastewater collections system. Design-Build Cost:$3,655,000 Design-Build Team: Quality Enterprises/Grady Minor Board Date: June 8, 2021 Commencement Date: 07/31/2021 Estimated Completion: 09/14/2022 Milestones / Challenges To Date: 11/29/2021 •Design In Progress 14 Emergency Power System DESCRIPTION OF WORK % COMPLETE Design-Build Procurement 100% Design 15% Construction 0% 46Exceeding Expectations, Every Day! District #: 5 Project #: 50393 Project Sponsor: Barry Williams Division Director Project Manager: John McCormick Project Scope: Install Two Emergency Generators Construction Budget:$ 1,038,000 Architect/Engineer:McKim & Creed General Contractor: T.B.D. Notice to Proceed Date: 10/11/2021 Estimated Substantial Completion Date: 7/1/2024 Milestones/Challenges To Date: 12/06/2021 •This is a transfer budget, approved by BCC on 2-25-2020 16D4 item 11257, this is a generator project that includes transfers of $145k for Immokalee and $425K for NCRP for a grant match in Fund 710.Projects numbers in 710 are 33668-01 and 33663-01 Immokalee Sports Park Generator DESCRIPTION OF WORK % COMPLETE Procurement 0% Design 0% Construction 0% 47Exceeding Expectations, Every Day! EMS Substations 48Exceeding Expectations, Every Day! Order Description Validated Amount Status EMS Substations 1 55211 Heritage Bay EMS station $2,222,200 Design 5% Permitting 5% 2 55212 Golden Gate Estates EMS 74 $2,500,000 Design 75% Procurement 50% 3 55213 Old US 41 EMS Station $1,277,800 Procurement 50% Total $6,000,000 49Exceeding Expectations, Every Day! District #: 2 Project #: 55211 Project Sponsor: Tabatha Butcher, Director, EMS Project Manager: Tony Barone, PMP Project Scope: Design and construct a new facility to support EMS and Fire District operations in the North Naples area to lower response times. Construction Budget: $2,220,000 Architect/Engineer: Stantec / Matern / Studio+ Construction Manager: Kaufman Lynn Construction Notice To Proceed Date: TBD Estimated Substantial Completion Date: TBD Milestones/Challenges To Date: 12/6/2021 •EMS Station originally included as a potential Phase 2 of the overall Heritage Bay Government Center. •New EMS modeling falls short of needing a new building at the moment but instead a new ambulance added to provide coverage. •Site is master planned to receive EMS Station or other building in Phase 2 area (maximum flexibility is built in for future development). EMS Station -Heritage Bay DESCRIPTION OF WORK % COMPLETE Design 5% Permitting 5% Construction 0% 50Exceeding Expectations, Every Day! District #: 5 Project #: 55212 Project Sponsor: Tabatha Butcher, Director, EMS Project Manager: Tony Barone, PMP Project Scope: Design and construct a new facility to support EMS and Fire District operations in the Golden Gate Estates area to lower response times. Construction Budget: $2,500,000.00 Architect/Engineer: Schenkel Shultz Architecture Construction Manager: TBD Notice to Proceed Date: TBD Estimated Substantial Completion Date: Jun 2023 Milestones/Challenges To Date: 12/06/2021 •Design documents submitted to planning and building for permit review. •30% budget estimate received, came to cost sharing agreement with Fire Districts for 40%/40%/20% split in development costs. (EMS/GNFD/NCFD) •County Attorney’s Office provided formal agreement document for funding and use interlocal agreement with the fire districts. EMS 74 -Golden Gate Estates DESCRIPTION OF WORK % COMPLETE Procurement 50% Design 95% Construction 0% 51Exceeding Expectations, Every Day! District #: 2 Project #: 55213 Project Sponsor: Tabatha Butcher, Director, EMS Project Manager: Tony Barone, PMP Project Scope: Design and construct a new facility to support EMS and Fire District operations in the North Naples area to lower response times. Project Budget: $2,900,000.00 (1,277,800 validated) Architect/Engineer: Schenkel Shultz Architecture Construction Manager: TBD Notice to Proceed Date: TBD Estimated Substantial Completion Date: Dec 2023 Milestones/Challenges To Date: 1/4/2022 •Design contract already in place. •Planning PO and NTP for design in February to align with the end of the procurement phase for EMS 74. •Discussions with North Collier Fire on a partnership ongoing. EMS Station 412 -Old 41 (Surtax) DESCRIPTION OF WORK % COMPLETE Procurement 50% Design 0% Construction 0% 52Exceeding Expectations, Every Day! Community Priorities 53Exceeding Expectations, Every Day! Order Description Validated Amount Status Community Priorities 1 Career and Tech Training Ctr (To Be Validated)$15,000,000 To Be Validated 2 50112 VA Nursing Home (To Be Validated)$30,000,000 To Be Validated 3 W orkforce Housing Land Trust Fund (To Be Validated)$20,000,000 To Be Validated 4 50239 Mental Health Facility $25,000,000 Procurement 60% Total $90,000,000 54Exceeding Expectations, Every Day! District #: TBD Project #: TBD Project Sponsor: County Manager’s Office Project Manager: Ayoub Al-Bahou Project Scope: Construct a career and technical training center to provide a space for classroom and hands-on training in a variety of fields, including advanced manufacturing and skilled trades. Construction Budget:$15,000,000.00 Architect/Engineer: General Contractor: Notice to Proceed Date: Estimated Substantial Completion Date: Milestone/Challenges To Date: Updated 12/06/2021 •Status: Develop and evaluate location alternatives •Build or buy •Site selection plan under development •Validation by Surtax Committee will be scheduled when appropriate Career & Tech Training Center DESCRIPTION OF WORK % COMPLETE Procurement 0% Design 0% Construction 0% PROJECT FEATURES (Pursuant to original Concept): •Facility would be located (TBD) •Lab space for hands-on training in advanced manufacturing, skilled trades •State-of-the art equipment/technology to teach adult learners on new/emerging trends in their trade •LEED certified “Green Building” COSTS AND FUNDING (Pursuant to original Concept): •Current surtax funding allocation $15 million •Build or buy •Site alternatives (TBD) •Existing structure alternatives (TBD) •Instructional program funding by private source (CMO responsibility) •School District management (CMO responsibility) •Ongoing facility O&M funding (TBD) 55Exceeding Expectations, Every Day! District #: 3 Project #: 50112 Project Sponsor: County Manager’s Office Project POC: John Mullins Project Scope: New Construction Construction Budget: $30,000,000 Architect/Engineer: TBD General Contractor: TBD Notice to Proceed Date: TBD Estimated Substantial Completion Date: TBD Milestone/Challenges to date: 11/29/2021 Golden Gate Golf Course is under consideration by FDVA as a potential location Staff conducted a site visit with representatives of FDVA on October 5, 2021 Surtax funds would be the match for the required federal grant needed to fund the construction of the State Veterans’ Nursing Home. Validation by Surtax Committee will be scheduled when appropriate State Veterans’ Nursing Home DESCRIPTION OF WORK % COMPLETE Procurement 0% Design 0% Construction 0% PROJECT FEATURES (Pursuant to original Concept): •Construction of a State Veterans' Nursing Home in Collier County would accommodate our growing population of veterans . •Collier County has 21,801 veterans over the age of 65 and was ranked #1 in a needs-based study in 2014 COSTS AND FUNDING (Pursuant to original Concept): •Surtax funding allocation $30 million 56Exceeding Expectations, Every Day! District #: TBD Project #: TBD Project Sponsor: County Manager’s Office Project POC: TBD Project Scope:New Construction Construction Budget: $20,000,000 Architect/Engineer: TBD General Contractor: TBD Notice to Proceed Date: TBD Estimated Substantial Completion Date: TBD Milestone/Challenges To Date: 11/29/2021 On October 22, 2019, the BCC approved establishing a non-profit Community Land Trust Staff is working with Rural Neighborhoods to develop essential services housing at the Golden Gate Golf Course site. Design is underway with construction intended to begin 3rd quarter of 2022 Validation by Surtax Committee will be scheduled when appropriate Workforce Housing Land Trust DESCRIPTION OF WORK % COMPLETE Procurement 0% Design 0% Construction 0% PROJECT FEATURES (Pursuant to original Concept): •Purchase land that can be reserved for housing that is affordable through extended County ownership •Provide a funding resource for the County’s Local Housing Trust Fund •Acquire land for housing that is affordable •Long term affordability of Collier’s housing stock •Promote economic development by increasing affordable housing options for the area's workforce COSTS AND FUNDING (Pursuant to original Concept): •Surtax funding allocation $20 million 57Exceeding Expectations, Every Day! Collier County Mental Health Facility (Surtax) District #: 3 Project #: 50239 Project Sponsor: Public Services Department Project Manager: Claudia Roncoroni Project Scope: The Collier County Mental Health Facility will be located on a parcel along Golden gate Parkway, not far from the David Lawrence Center Complex. The new facility will be approximately 54,000 square feet with a potential of 5,000 square feet future expansion. This new structure will increase crisis support, inpatient and addiction treatment capacity, and will function as the Central Receiving Center (CRC) for those receiving services under both the Baker and the Marchman Acts. Design & Construction Budget: $25,000,000 Architect/Engineer: T.B.D. General Contractor: T.B.D Owner’s Representative (CEI) : N/A Notice to Proceed Date: T.B.D Estimated Substantial Completion Date: T.B.D Estimated Final Completion Date: T.B.D DESCRIPTION OF WORK % COMPLETE Procurement 65% Design 0% Construction 0% Existing David Lawrence Center Complex Proposed Site Milestones / Challenges to date: 12/06/2021 •Design Solicitation was closed on 08/12/2021. •CMAR Solicitation was closed on 09/09/2021. •Design Solicitation ranking, with RG Architects ranked as number one, was approved by the Board on 10/26/2021. •CMAR Solicitation ranking, with DeAngelis Diamond ranked as number one, was approved by the Board on 11/09/21. •Currently under negotiation with RG Architects. •Currently under negotiation with DeAngelis Diamond.