Agenda 12/14/2021 Item #16A33 (Amend and Restate Developer Agreement w/WPPI Naples TF, LLC and TBC Tree Farm I, LLC)12/14/2021 EXECUTIVE SUMMARY Recommendation to approve the Amended and Restated Developer Agreement with WPPI Naples TF LLC and TBC Tree Farm I, LLC that will allow for the design, right-of-way and construction of intersection improvements on Collier Boulevard Extension at the future Government Center Complex/Tree Farm Planned Unit Development entrance and cost sharing and reimbursement plan. (Estimated Fiscal Impact: $443,582, Gas Tax Fund 313) OBJECTIVE: For the Developer to design, provide right-of-way and easements and construction activities to support intersection improvements on Collier Boulevard Extension. CONSIDERATIONS: In December 2018, TBC Tree Farm 1, LLC submitted a subdivision plat for a parcel within the Tree Farm PUD, referenced as PL20180003592. The access is anticipated to be on Collier Boulevard Extension. In May 2020, Collier County submitted a site development plan amendment, referenced as PL2020000953 for the Heritage Bay Government Center, which anticipated access to be on Collier Boulevard Extension. On December 8, 2020, the Board approved agenda item 16A47 which identified the cost sharing for coordinated access to provide for a roundabout that will facilitate an existing significant U-turn movement from properties within the Heritage Bay PUD. The Developer agreed to construct the improvements and be reimbursed for a portion of the improvements. Following the approval of the agreement, the Developer began the permitting process for the new roundabout. During the staff review of the permit, additional items were requested that were not addressed in the initial developer agreement. Those items include lighting, removal, and replacement of an existing pump station driveway as well as modification on the east side of the roadway to coincide with construction of the Heritage Bay Government Center. These additional scope items have increased the cost, therefore, modification to the not to exceed amount identified in the initial developer agreement are necessary. The developer agreement is being modified to increase the not to exceed amount to $403,582, which represents 61.6% of the revised engineers estimate inclusive of the additional scope items as well as to defer final payment of such improvements to December 1, 2022 or within six months of the completion of the Improvements, whichever is later. FISCAL IMPACT: The County will be responsible for 61.6% of the construction low bid amount, capped at $403,582 and 61.6% of any unanticipated costs, agreed upon by both parties and approved through a Change Order, capped at $40,000. The Developer will be reimbursed from gas taxes which will be budgeted within the agreed -upon time frame our of the Congestion Mgt Fare, Project 60066. LEGAL CONSIDERATIONS: This item has been reviewed by the County Attorney, is approved as to form and legality and requires majority vote for approval. -JAK GROWTH MANAGEMENT IMPACT: This item meets current Growth Management Plan standards to ensure the adequacy and availability of viable public facilities. RECOMMENDATION: To approve the amended and restated Developer Agreement with WPPI Naples TF LLC and TBC Tree Farm 1, LLC that will allow for the design, right-of-way and construction of intersection improvements on Collier Boulevard Extension and a cost sharing and reimbursement plan Prepared By: Trinity Scott, Deputy Department Head, Growth Management Department ATTACHMENT(S) 1. Exhibit 1 (PDF) Packet Pg. 1332 12/14/2021 2. Exhibit 2 Revised (PDF) 3. Amended Developer Agreement Tree Farm - Clean Rev 3 (PDF) Packet Pg. 1333 16.A.33 12/14/2021 COLLIER COUNTY Board of County Commissioners Item Number: 16.A.33 Doe ID: 20758 Item Summary: Recommendation to approve the Amended and Restated Developer Agreement with WPPI Naples TF LLC and TBC Tree Farm 1, LLC that will allow for the design, right-of-way and construction of intersection improvements on Collier Boulevard Extension at the future Government Center Complex/Tree Farm Planned Unit Development entrance and cost sharing and reimbursement plan. (Estimated Fiscal Impact: $443,582 Gas Tax Fund 313) Meeting Date: 12/14/2021 Prepared by: Title: Project Manager — Growth Management Development Review Name: Laurie Beard 12/06/2021 12:07 PM Submitted by: Title: Director — Capital Project Planning, Impact Fees, and Program Management Name: Matthew McLean 12/06/2021 12:07 PM Approved By: Review: Growth Management Department Lissett DeLaRosa Growth Management Department Growth Management Department Lisa Taylor Additional Reviewer Capital Project Planning, Impact Fees, and Program Management Trinity Scott Growth Management Department Trinity Scott Transportation Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Growth Management Operations Support Christopher Johnson County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review County Manager's Office Amy Patterson Level 4 County Manager Review Board of County Commissioners Geoffrey Willig Meeting Pending Completed 12/06/2021 12:31 PM Completed 12/07/2021 8:41 AM Additional Reviewer Skipped Completed 12/07/2021 8:44 AM Completed 12/07/2021 9:01 AM Additional Reviewer Completed Completed 12/08/2021 8:47 AM Completed 12/08/2021 11:02 AM 12/14/2021 9:00 AM Packet Pg. 1334 2,181 SF R.O.W. EASEMENT FOR CROSSWALK 0130' J PENINSULA ENGINEERINGA _ CIVIL ENGINEERING - LANDSCAPE ARCHITECTURE - ENVIRONMENTALCONILILTING LANDPLANNING - SITE PLANNING CO\STRUCTION MANAGEMENT OWNER REPRESENTATIVE 2600 Golden Cate Parkway Naples, Florida 34105 Phone: 239.403.6]00 Fax: 239.261.1797 Email: info�pen-eng.com Website: www.pen-eng.com Florida Cerii(iraie of Authorization 428275 PROJECT: COLLIER BOULEVARD ROUNDABOUT ---�L1501 TITLE. \\085' -J �1111011 0 rY w 0 0 m rY w J 0 U EXHIBIT "1" OWN ER/CLIENT/CONSULTANT: TREE FARM PUD a E U- SEC: 22 TWPA8S RGE: Designed by: ALEJANDRO A Drawn by: ALEJANDRO A\ Date: OCTOBER Drawing Scale: 1" = Project Number: P-BROK-003 , File Number: P-BROK-003-001-X14 Sheet N Packet Pg. 1335 16.A.33.b Exhibit 2 Project: COLLIER BOULEVARD ROUNDABOUT Task: ENGINEER'S COST ESTIMATE PAVING ID DESCRIPTION QTY UNIT TYPE UNIT PRICE TOTAL PRICE PAV-1 Brick Pavers 1,288 SF $ 10.50 $ 13,524.00 PAV-2 Type SP structural course, traffic "D", 3.5" thick 1,098 SY $ 30.36 $ 33,335.28 PAV-3 Type FC 12.5 friction course, traffic "D", 1.5" thick 1,098 SY $ 20.16 $ 22,135.68 PAV-4 12" type "B" stabilized subgrade, LBR 40 1,431 SY $ 2.40 $ 3,434.40 PAV-5 Optional base group 9, 10" thick 1,365 SY $ 57.96 $ 79,115.40 PAV-6 Type "D" Curb 169 LF $ 19.50 $ 3,295.50 PAV-7 Type "F" Curb (Curb & gutter) 3,090 LF $ 19.50 $ 60,255.00 PAV-8 8' Wide (6" Concrete Sidewalk) 4198 SF $ 5.82 $ 24,432.36 PAV-9 Signage and Striping 1 LS $ 20,000.00 $ 20,000.00 PAV-10 ADA Curb Ramps 4 EA $ 366.00 $ 1,464.00 PAV-11 ADA Truncated Done Mats 153 SF $ 27.00 $ 4,131.00 PAV-12 Concrete Traffic Separator 4' 126 LF $ 15.30 $ 1,927.80 PAV-13 Maintenance of Traffic 1 LS $ 7,500.00 $ 7,500.00 PAV-14 Embankment - (IMPORT FILL) 910 CY $ 14.25 $ 12,967.50 PAV-15 Irrigation Counduit 1 LS $ 4,000.00 $ 4,000.00 PAV-16 Bahia Sod 3,662 SY $ 3.00 $ 10,986.00 PAV-17 Silt Fence 1,600 LF $ 1.50 $ 2,400.00 PAV-18 Mobilization 1 LS $70134.00 $ 70,134.00 PAV-19 is PAVING SUBTOTAL = $ 39490 10:2 DRAINAGE 375, 037.92 ID DESCRIPTION CITY UNIT TYPE UNIT PRICE TOTAL PRICE DRA-1 15" RCP 2953 LF 44 159 $ 4- 8 8 427 DRA-2 Throat Inlets 3 EA $2,500 4 920 $ 7-500 14,760 DRA-3 Modified Existing Structure Top 2 EA $2,000 6 900 $ 4000 13,800 DRA-4 FDOT Type C. Dog House Structure 1 EA $ 13,050.00 $ 13,050.00 DRA-5 FDOT Type 5, Curb Inlet 1 EA $ 11,850.00 $ 11,850.00 DRA-6 Reinforced Concrete Pipe, 18" 67 LF $161.00 $ 10,787.00 DRA-7 Modify Existing FDOT Type J, Junction Box 1 EA $ 15,000.00 $ 15,000.00 DRAINAGE SUBTOTAL = $ $ IZ689- DEMOLITION 87,674 ID DESCRIPTION QTY UNIT TYPE UNIT PRICE TOTAL PRICE DEMO-1 Remove Existing Type "F" Curb 1,751 LF $ 1.50 $ 2,626.50 DEMO-2 Remove Existing Asphalt 1,819 SY $ 6.00 $ 10,914.00 DEMO-3 Mill & Resurface, 1.5" average depth, resurface with FC-12.5, traffic "D 2,816 SY $ 18.83 $ 53,025.28 DEMO-4 Remove Existing Sidewalk 1,050 SF $ 6.00 $ 6,300.00 DEMO-5 Remove Existing Limerock and Subgrade 1,819 SY 1 $ 3.00 $ 5,457.00 DEMOLITION SUBTOTAL = $ 78,322.78 UTILITYDRIVEWAYSUBTOTAL= $ 5,000 LIGHTING ID DESCRIPTION QTY UNIT TYPE UNIT PRICE TOTAL PRICE LIG-1 101-1 Mobilization 1 LS LM.00 J120.00 LIG-2 102-1 Maintenance of Traffic 1 LS 4965.00 4 965.00 LIG-3 630-2-11 Conduit (Furnish & Install) (Open Trench) 500 LF L1180 1190000 LIG-4 630-2-12 Conduit (Furnish & Install) (Directional Bore) 150 LF 12160 3 240.00 LIG-5 635-2-11 Pull and Splice Box (Furnish & Install) 12 EA $720.00 8 640.00 LIG-6 639-1-121 Electrical Power Service (F&I) Underground Furnish by 1 AS LK00.00 13 600.00 LIG-7 639-2-1 Electrical Service Wire (Furnish & Supply) 100 LF 7.20 t120.00 LIG-8 715-1-12 Lighting Conduction (Furnish & Supply) 2 200 LF 2.55 15 610.00 LIG-9 715-4-11 Light Pole Complete (Furnish & Supply) 8 EA 7380.00 $ 59,040.00 LIG-10 715-7-11 Load Center (Furnish & Install) Secondary Voltage 1 EA $ 13146.00 $ 13,146.00 LIG-11 999-999 Signed & Sealed As -built Record Drawings 11 EA 3550.00 3 550.00 LIGHTING SUBTOTAL = $ 109,131 TOTAL = $ 655,165.70 Packet Pg. 1336 16.A.33.c AMENDED AND RESTATED DEVELOPER AGREEMENT Tree Farm MPUD THIS AMENDED DEVELOPER AGREEMENT (hereinafter referred to as the "Agreement") is made and entered into this of , 2021 by and among WPPI Naples TF LLC (hereinafter referred to as the "Developer"), TBC Tree Farm 1, LLC ("TBC 1") and Collier County, a political subdivision of the State of Florida. RECITALS! WHEREAS, on June 26, 2007, the Board of County Commissioners approved Ordinance No. 07-54, which created the Tree Farm Mixed Use Planned Unit Development ("MPUD"), which ordinance was amended on January 14, 2020 by Ordinance No. 20-03; and WHEREAS the parties entered into a Developer Agreement on December 8, 2020 for the construction of Improvements; and WHEREAS, TBC 1 has an approved Subdivision Plat (PL20180003592) which provides access to Collier Boulevard; and WHEREAS, Collier County has applied for a Site Development Plan Amendment (PL20200000953) for the Heritage Bay Government Center, which provides for access to Collier Boulevard directly across from the Tree Farm MPUD; and WHEREAS, the new access points coincide with an existing U-turn opportunity on Collier Boulevard, which allows travelers leaving the Heritage Bay PUD to gain access to the traffic signal at Collier Boulevard and Immokalee Road; and WHEREAS the parties wish to coordinate and cooperate to construct an intersection that will operate efficiently for ingress/egress for the various uses under the terms and conditions set forth below; and WHERAS, the parties wish to amend the Developer Agreement based on additional scope items as a result of the County permit review. WITNESSETH NOW, THEREFORE, in consideration of Ten Dollars (10.00) and other good and valuable consideration exchanged amongst the parties, and in consideration of the covenants contained herein, the parties agree as follows: 1. All of the above RECITALS are true and correct and are hereby expressly incorporated herein by reference as if set forth fully below. This Agreement amends, replaces and supersedes the parties' December 8, 2020 Developer Agreement, which upon full execution of this Agreement shall be deemed of no further force or effect. Packet Pg. 1337 16.A.33.c 2. County will allow TBC 1 and Developer to proceed with the project on the following terms and conditions: A. Developer will design and construct the road and sidewalk improvements inclusive of a roundabout ("Improvements") as set forth in Exhibit 1. Developer will utilize the services of Peninsula Engineering and Trebilcock Consulting Solutions for professional engineering and surveying services pertaining to the design, permitting and construction of the Improvements. Developer will be solely responsible for the cost of design, permitting, and construction administration and certifications. Developer's design and permitting responsibilities will include submittal of a South Florida Water Management District (SFWMD) Environmental Resource Permit (ERP) for the modification of Collier Boulevard as depicted in Exhibit 1. B. The Improvements set forth in Exhibit 1 will require additional right-of-way in the form of an easement from TBC 1 for a crosswalk and other pedestrian facilities on the west side of the proposed roundabout as depicted in Exhibit 1. TBC 1, at its sole cost and expense, has provided this additional right-of-way for the area depicted on Exhibit 1 and shall convey to the County during the Subdivision Plat for Tree Farm, which is currently under review as PL20180003592. C. The County will contribute to the construction costs for the Improvements needed by the County. The County's contribution will be the lesser of 61.6% of the shared lump sum project construction costs, or $403,582, which is 61.6% of the engineer's estimated construction costs, as set forth in Exhibit 2. County will pay Developer on December 1, 2022 or within six months of the completion of the Improvements, whichever is later. For the purpose of this section, the completion of the Improvements will be defined as the issuance of a Certificate of Completion from the Collier County Growth Management Division for the Collier County Right -of -Way Permit for the Improvements shown in Exhibit 1. Prior to commencing construction of the Improvements, the County and the Developer shall cooperate to have Developer advertise and bid the Developer's Improvement project in accordance with the County's normal solicitation procedures for public road projects and using the County's electronic bid system. The County shall provide written notice to Developer documenting the result of such solicitation and ranking all qualified bids from lowest to highest, with the dollar amount of the lowest qualified bid being hereinafter referred to as responsible bidders. Developer may negotiate with any of the bidders or any other qualified contractor on its project to construct the Improvements, and in that regard Developer shall not be obligated to award the construction of the Improvements to the low bidder or to any of the responsive bidders; however, in no event shall the final reimbursement amount by the County exceed $403,582 or 61.6% of the low bid amount, whichever is less. In addition, the County acknowledges there may be unanticipated costs including, but not limited to, unforeseen site conditions encountered during construction. Should that occur, the County will pay 61.6% of the total for such additional costs, but not to exceed $40,000, on the conditions that (1) the additional work is agreed upon by both parties, and (2) the additional work is approved by the Board of County Commissioners through a Change Order, supported by proper documentation of any time and materials supporting the request. D. Developer will obtain a right-of-way permit for the Improvements at no cost. Neither Developer nor TBC 1 shall pay any lane or sidewalk rental fees for construction of the Packet Pg. 1338 16.A.33.c Improvements for the period of March 1, 2022 through July 31, 2022. Commencing on August 1, 2022, Developer and/or TBC 1, as applicable, will pay the customary lane and sidewalk rental fee charged by the County. However, any lane and sidewalk rental fees will be reduced by 61.6%. E. No further contribution of compensating right-of-way will be required from the property owners in the Tree Farm PUD for the construction of access points along Collier Boulevard that are consistent with the existing accesses approved as a part of Ordinance 20-03. F. The property owners' contributions of the construction Improvements shown in Exhibit 1 are considered to satisfy the property owners' "fair share" requirements of the Section 6.3.13 of Ordinance 20-03 for the intersection proposed for improvement in Exhibit 1. G. During construction of the site improvements within the Tree Farm PUD, the Developer and TBC 1 will be permitted to use the existing access to the Tree Farm PUD at the location of the Improvements as the construction access. Neither the Developer nor TBC 1 will be prohibited from access during construction due to the removal of the existing left turn lane into the Tree Farm PUD at the location of the Improvements. H. The Developer reserves the future right to petition Collier County to enter into a Landscape Maintenance Agreement to install and maintain enhanced landscaping within the area of the Improvements. Legal Matters 3. This Agreement shall not be construed or characterized as a development agreement under the Florida Local Government Development Agreement Act. 4. The burdens of this Agreement shall be binding upon, and the benefits of this Agreement shall inure to, all assigns successors in interest to the parties to this Agreement. The term "Developer" shall include all of Developer's assigns and successors in interest, including homeowner associations and commercial tenants. The term "TBC 1" shall include all of TBC1's assigns and successors in interest, including homeowner associations and commercial tenants. 5. In the event state or federal laws are enacted after the execution of this Agreement, which are applicable to and preclude in whole or in part the parties' compliance with the terms of this Agreement, then in such event this Agreement shall be modified or revoked as is necessary to comply with such laws, in a manner which best reflects the intent of this Agreement. 6. This Agreement shall be recorded by the County in the Official Records of Collier County, Florida, within fourteen (14) days after the Effective Date. The Developer shall pay all costs of recording this Agreement. The County shall provide a copy of the recorded document to the Developer upon request. 7. In the event of any dispute under this Agreement, the parties shall attempt to resolve such dispute first by means of the County's then -current Alternative Dispute Resolution Procedure, if any. Following the conclusion of such procedure, if any, either party may file an action for Packet Pg. 1339 16.A.33.c injunctive relief in the Circuit Court of Collier County to enforce the terms of this Agreement, and remedy being cumulative with any and all other remedies available to the parties for the enforcement of the Agreement. 8. Except as otherwise provided herein, this Agreement shall only be amended by mutual written consent of the parties hereto or by their successors in interest. All notices and other communications required or permitted hereunder (including County's option) shall be in writing and shall be sent by Certified Mail, return receipt requested, or by a nationally recognized overnight delivery service, and addressed as follows: To County: Collier County Manager's Office 3299 Tamiami Trail East, Suite 202 Naples, FL 34112-5746 To Developer: WPPI Naples TF, LLC 9800 Connecticut Dr., Suite A1- 100 Crown Point, IN 46307-7840 9. This Agreement (which include the references set forth in the Recitals) constitutes the entire agreement between the parties with respect to the activities noted herein and supersedes and takes the place of any and all previous agreements entered into between the parties hereto relating to the transactions contemplated herein. All prior representations, undertakings, and agreements by or between the parties hereto with respect to the subject matter of this Agreement are merged into, and expressed in, this Agreement, and any and all prior representations, undertakings, and agreements by and between such parties with respect thereto hereby are canceled. 10. Nothing contained herein shall be deemed or construed to create between or among any of the parties any joint venture or partnership nor otherwise grant to one another the right, authority or power to bind any other party hereto to any agreement whatsoever. REMAINDER OF PAGE INTENTIONALLY LEFT BLANK SIGNATURE PAGE TO FOLLOW Packet Pg. 1340 16.A.33.c IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed by their appropriate officials, as of the date first above written. AS TO COUNTY: ATTEST: BOARD OF COUNTY COMMISSIONERS CRYSTAL K. KINZEL, Clerk COLLIER COUNTY, FLORIDA, on behalf of Collier County, Florida By: By: Deputy Clerk Chairman Approved as to form and legality: Jeffrey A. Klatzkow, County Attorney SIGNATURES CONTINUED ON FOLLOWING PAGE Packet Pg. 1341 16.A.33.c AS TO DEVELOPER: WITNESS: (Signature) h LC2; IA; i,S e (Print full name), Signature) N teitx� j '�q-W. - -I(-r (Print full name) STATE OF INDbA.ISIA F'L ORL I RQ COUNTY D ?„AKA LcG WPPI NAPLES TF, LLC, a Delaware limited liability company By: WPPI/WL Tree Farm, LLC a Delaware limited liability company its: sole member By: WPPI/HS Naples TF Investment, LLC a Delaware limited liability company its: Operating Member By: WMB Corp., an Indiana corporation, its: Mana er i By: J. Matth w Chambers, Treasurer The foregoing instrument was acknowledged before me by means of Vphysical presence or 0 online notarization this �p+�' day of _� C - , 2021, by J. Matthew Chambers, the Treasurer of WMB Corp., an Indiana corporation, the Manager of WPPI/HS Naples TF Investment, LLC, a Delaware limited liability company, the Operating Member of WPPI/WL Tree Farm, LLC, a Delaware limited liability company, the Sole Member of WPPI Naples TF, LLC a Delaware limited liability company, who executed the foregoing document on behalf of said corporation in its capacity as the Manager of the Operating Member of the Sole Member of WPPI Naples TF, LLC, and Wd vho is personally known to me or Owho has produced as identification. (,C' a @ ..p;�a����;•,, Notary Public NAOMI J. WISE Commission # GG 335672 Expires May 16, 2023 Print Name:�7�; S P Bonded Thru Troy Fain Insurance800.365.7019 My Commission Expires:-5 Z t)" Packet Pg. 1342 2,181 SF R.O.W. EASEMENT FOR CROSSWALK 0130' J 4PENINSULA ENGINEERINGA _ CIVIL ENGINEERING - LANDSCAPE ARCHITECTURE - ENVIRONMENTALCONILILTING LANDPLANNING - SITE PLANNING CO\STRUCTION MANAGEMENT OWNER REPRESENTATIVE 2600 Golden Cate Parkway Naples, Florida 34105 Phone: 239.403.6700 Fax: 239.261.1797 Email: Web,iw: www.pen-enC.com PROJECT: COLLIER BOULEVARD ROUNDABOUT TITLE. 0 W 0 00 0 C) U EXHIBIT "1" 1 i - OWN ER/CLIENT/CONSULTANT: TREE FARM PUD 16.A.33.c 0 0 I I w a U U d E _ L n E E L u- L 00 Lo I- 0 N SEC: 22 TWPA8S RGE: Designed by: ALEJANDRO A Drawn by: ALEJANDRO A\ Date: OCTOBER Drawing Scale: 1" = Project Number: P-BROK-003 File Number: P-BROK-003-001-X14 Sheet N Packet Pg. 1343 16.A.33.c Exhibit 2 Project: COLLIER BOULEVARD ROUNDABOUT Task: ENGINEER'S COST ESTIMATE PAVING ID DESCRIPTION QTY UNIT TYPE UNIT PRICE TOTAL PRICE PAV-1 Brick Pavers 1,288 SF $ 10.50 $ 13,524.00 PAV-2 Type SP structural course, traffic "D", 3.5" thick 1,098 SY $ 30.36 $ 33,335.28 PAV-3 Type FC 12.5 friction course, traffic "D", 1.5" thick 1,098 SY $ 20.16 $ 22,135.68 PAV-4 12" type "B" stabilized subgrade, LBR 40 1,431 SY $ 2.40 $ 3,434.40 PAV-5 Optional base group 9, 10" thick 1,365 SY $ 57.96 $ 79,115.40 PAV-6 Type "D" Curb 169 LF $ 19.50 $ 3,295.50 PAV-7 Type "F" Curb (Curb & gutter) 3,090 LF $ 19.50 $ 60,255.00 PAV-8 8' Wide (6" Concrete Sidewalk) 4198 SF $ 5.82 $ 24,432.36 PAV-9 Signage and Striping 1 LS $ 20,000.00 $ 20,000.00 PAV-10 ADA Curb Ramps 4 EA $ 366.00 $ 1,464.00 PAV-11 ADA Truncated Done Mats 153 SF $ 27.00 $ 4,131.00 PAV-12 Concrete Traffic Separator 4' 126 LF $ 15.30 $ 1,927.80 PAV-13 Maintenance of Traffic 1 LS $ 7,500.00 $ 7,500.00 PAV-14 Embankment - (IMPORT FILL) 910 CY $ 14.25 $ 12,967.50 PAV-15 Irrigation Counduit 1 LS $ 4,000.00 $ 4,000.00 PAV-16 Bahia Sod 3,662 SY $ 3.00 $ 10,986.00 PAV-17 Silt Fence 1,600 LF $ 1.50 $ 2,400.00 PAV-18 Mobilization 1 LS $70134.00 $ 70,134.00 PAV-19 is PAVING SUBTOTAL = $ 39490 10:2 DRAINAGE 375, 037.92 ID DESCRIPTION CITY UNIT TYPE UNIT PRICE TOTAL PRICE DRA-1 15" RCP 2953 LF 44 159 $ 4- 8 8 427 DRA-2 Throat Inlets 3 EA $2,500 4 920 $ 7-500 14,760 DRA-3 Modified Existing Structure Top 2 EA $2,000 6 900 $ 4000 13,800 DRA-4 FDOT Type C. Dog House Structure 1 EA $ 13,050.00 $ 13,050.00 DRA-5 FDOT Type 5, Curb Inlet 1 EA $ 11,850.00 $ 11,850.00 DRA-6 Reinforced Concrete Pipe, 18" 67 LF $161.00 $ 10,787.00 DRA-7 Modify Existing FDOT Type J, Junction Box 1 EA $ 15,000.00 $ 15,000.00 DRAINAGE SUBTOTAL = $ $ IZ689- DEMOLITION 87,674 ID DESCRIPTION QTY UNIT TYPE UNIT PRICE TOTAL PRICE DEMO-1 Remove Existing Type "F" Curb 1,751 LF $ 1.50 $ 2,626.50 DEMO-2 Remove Existing Asphalt 1,819 SY $ 6.00 $ 10,914.00 DEMO-3 Mill & Resurface, 1.5" average depth, resurface with FC-12.5, traffic "D 2,816 SY $ 18.83 $ 53,025.28 DEMO-4 Remove Existing Sidewalk 1,050 SF $ 6.00 $ 6,300.00 DEMO-5 Remove Existing Limerock and Subgrade 1,819 SY 1 $ 3.00 $ 5,457.00 DEMOLITION SUBTOTAL = $ 78,322.78 UTILITYDRIVEWAYSUBTOTAL= $ 5,000 LIGHTING ID DESCRIPTION QTY UNIT TYPE UNIT PRICE TOTAL PRICE LIG-1 101-1 Mobilization 1 LS LM.00 J120.00 LIG-2 102-1 Maintenance of Traffic 1 LS 4965.00 4 965.00 LIG-3 630-2-11 Conduit (Furnish & Install) (Open Trench) 500 LF L1180 1190000 LIG-4 630-2-12 Conduit (Furnish & Install) (Directional Bore) 150 LF 12160 3 240.00 LIG-5 635-2-11 Pull and Splice Box (Furnish & Install) 12 EA $720.00 8 640.00 LIG-6 639-1-121 Electrical Power Service (F&I) Underground Furnish by 1 AS LK00.00 13 600.00 LIG-7 639-2-1 Electrical Service Wire (Furnish & Supply) 100 LF 7.20 t120.00 LIG-8 715-1-12 Lighting Conduction (Furnish & Supply) 2 200 LF 2.55 15 610.00 LIG-9 715-4-11 Light Pole Complete (Furnish & Supply) 8 EA 7380.00 $ 59,040.00 LIG-10 715-7-11 Load Center (Furnish & Install) Secondary Voltage 1 EA $ 13146.00 $ 13,146.00 LIG-11 999-999 Signed & Sealed As -built Record Drawings 11 EA 3550.00 3 550.00 LIGHTING SUBTOTAL = $ 109,131 TOTAL = $ 655,165.70 Packet Pg. 1344