Agenda 10/26/2021 Item #16A 9 (Contract #20-7710 Change Order No. 1 w/Atkins North America)10/26/2021 16.A.9 EXECUTIVE SUMMARY Recommendation to approve Change Order No. 1 to Contract Number 20-7710, "Plantation Island Waterways Pre -Design Study" with Atkins North America Inc. (Project Number 60238), to extend the length of the contract by 95 days. OBJECTIVE: To extend the length of the contract to allow additional time due to additional surveying required necessary via the grant to complete the goals of the "Plantation Island Waterways Pre -Design Study" Project and, to promote the most efficient use of time and resources and proceed in a fiscally responsible manner. CONSIDERATIONS: On January 12, 2021, the Board approved Contract Number 20-7710 (Agenda Item 16A30) for $423,404.00, with Atkins North America Inc. Change Order No. 1 is requesting additional 95 days to the complete the contract scope. A stop work order was issued on September 7, 2021. This change order is necessary to allow for additional surveying of the waterways. The existing vegetation required a Florida Department of Environmental Protection permit for trimming in order to complete the contracted scope. This time extension will allow for the survey to be completed and incorporated into the pre -design plans of this project. FISCAL IMPACT: This change order will not increase the cost of the project GROWTH MANAGEMENT IMPACT: This project is consistent with the goals and objectives of the Stormwater Element of the Growth Management Plan. LEGAL CONSIDERATIONS: This item has been reviewed by the County Attorney, is approved as to form and legality and requires majority vote for Board approval. -JAK RECOMMENDATION: To approve Change Order No. 1 to Contract Number 20-7710, "Plantation Island Waterways Pre -Design Study" with Atkins North America Inc. (Project Number 60238), to extend the length of the design contract by 95 days. Prepared By: Brittany Lazo, Stormwater, Capital Project Planning, Impact Fees, and Program Management Division ATTACHMENT(S) 1. Atkins 20-7710 Change Order #1 - CAO 4500209451 (PDF) Packet Pg. 741 16.A.9 10/26/2021 COLLIER COUNTY Board of County Commissioners Item Number: 16.A.9 Doe ID: 20155 Item Summary: Recommendation to approve Change Order No. 1 to Contract Number 20-7710, "Plantation Island Waterways Pre -Design Study" with Atkins North America Inc. (Project Number 60238), to extend the length of the contract by 95 days. Meeting Date: 10/26/2021 Prepared by: Title: — Capital Project Planning, Impact Fees, and Program Management Name: Heather Yilmaz 09/21/2021 2:15 PM Submitted by: Title: Director — Capital Project Planning, Impact Fees, and Program Management Name: Matthew McLean 09/21/2021 2:15 PM Approved By: Review: Growth Management Operations Support Jeanne Marcella Growth Management Department Lissett DeLaRosa Additional Reviewer Procurement Services Ana Reynoso Additional Reviewer Procurement Services Sandra Herrera Additional Reviewer Procurement Services Sara Schneeberger Additional Reviewer Capital Project Planning, Impact Fees, and Program Management Matthew McLean Growth Management Department Lisa Taylor Additional Reviewer Capital Project Planning, Impact Fees, and Program Management Ian Barnwell Procurement Services Catherine Bigelow Additional Reviewer Capital Project Planning, Impact Fees, and Program Management Matthew McLean Growth Management Department Trinity Scott Transportation Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Office of Management and Budget Susan Usher Additional Reviewer Grants Therese Stanley Additional Reviewer County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review County Manager's Office Amy Patterson Level 4 County Manager Review Additional Reviewer Skipped Completed 09/22/2021 3:45 PM Completed 09/23/2021 11:18 AM Completed 09/23/2021 11:57 AM Completed 09/27/2021 8:47 AM Additional Reviewer Skipped Completed 09/28/2021 10:05 AM Additional Reviewer Completed Completed 09/29/2021 8:35 AM Additional Reviewer Completed Completed 10/11/2021 8:49 AM Completed 10/11/2021 11:55 AM Completed 10/13/2021 11:33 AM Completed 10/13/2021 2:12 PM Completed 10/13/2021 2:21 PM Completed 10/18/2021 9:38 AM Packet Pg. 742 16.A.9 10/26/2021 Board of County Commissioners Geoffrey Willig Meeting Pending 10/26/2021 9:00 AM Packet Pg. 743 colvier County ❑ Contract Modification ® Work Order Modification 16.A.9.a Procurement Services Change Order Form Contract #: 20-7710 Change #: 1 Purchase Order #: 4500209451 Project #: 60238 Contractor/Firm Name: FAtkins North America Inc. Contract/Project: Plantation Island Waterways Pre -Design Study Project Manager Name: Brittany Lazo Division Name: Capital Project Planning, Impact Fees & Program Original Contract/Work Order Amount $ 423,404.00 01/12/21 16A30 Original BCC Approval Date; Agenda Item ; Current BCC Approved Amount $ 423,404.0 01/12/21 16A30 Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 423,404.00 9/10/2021 SAP Contract Expiration Date (Master) Dollar Amount of this Change $ 0.00 0.00% Total Change from Original Amount Revised Contract/Work Order Total $ 423,404.00 0.00% Change from Current BCC Approved Amoui Cumulative Changes $ 0.00 0.00% Change from Current Amount I Completion Date, Description of the Task(s) Change, and Rationale for the Change Notice to Proceed 2/12/2021 Original 9/10/2021 Last Approved 9/10/2021 Revised Date TBD Date Completion Date Date (Includes this change) # of Days Added 95 Select Tasks ❑ Add new task(s) ❑ Delete task(s) ❑ Change task(s) ® Other Provide a response to the following: 1.) detailed and specific explanation/rationale of the requested change(s) to the task(s) and / or the additional days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the impact if this change is not processed. Attach additional information from the Design Professional and/or Contractor if needed. This project is currently on a Stop work order with three (3) days remaining. 1. This change order will add 95 days to the contract to allow for the additional surveying of the waterways. 2. This was not included in the original contract because the site conditions did not indicate additional surveying was needed. 3. If the changes are not approved, quality of the pre -design plans will likely be inadequate to meet the goals and requirements of this grant funded project. OgiWy ayn0 try laznBniny Prepared by: -LazoB-----.. Date: (Brittany Lazo, Project Manager, Capital Project Planning, Impact Fees & Program Mgt.) Acceptance of this Change Order shall constitute a modification to contract / work order identified above and will be subject to all the same terms and conditions as contained in the contract / work order indicated above, as fully as if the same were stated in this acceptance. The adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor / Vendor / Consultant / Design Professional arising out o j -r related to the ch �j e set forth herein, including claims for impact and delay costs. Accepted by: (Mark E Atkins North America Inc.) Gerald N. Kurtz Digitally signed by Gerald N. Kurtz Approved b Date: 2021.08.18 12:43:57-04'00' Date: (Gerald N. Kurtz, PE, Prinicple Project Mgr., Capital Project Planning, Impact Fees& Program Mgt ) Revised: 01/14/2021 (Divisions who may require additional signatures may include on separate sheet.) PROCUREMENT USE ONLY Admin BCC r Q Rpt a Packet Pg. 744 16.A.9.a Approved by: Matthew McLean DNB 202.08.1'8Y','6°;440 O; a0111erCoi�.,'v'I.9oV.CN-Ma,1hew M�L�a� (Division Director) Digitally signed by ScottTrinity >� cottTrinity Date:2021.09.08 14:19:52-04'00' Approved by: (Trinity Scott, Deputy Department Head) Sc h n ee be rg e rSa ra Digitally signed by SchneebergerSara Date: 2021.09.20 14:57:15-04'00' Approved by: (Procurement Professional) Revised: 01/14/2021 (Divisions who may require additional signatures may include on separate sheet.) Date: Date: Date: rn c Q c m E PROCUREMENT USE &t ,Y Q Admin Rpt BCC ES Packet Pg. 745 16.A.9.a Change Order/Amendment Summary CO# AMD# Description COST TIME Justification Additive (+) Deductive (-) Days Added New Amount 1 Add 95 days 0 0 95 305 Additional time is requested to survey the waterways. Revised: 01/14/2021 (Divisions who may require additional signatures may include on separate sheet.) N c Y r Q C E t V r Y PROCUREMENT USE OKY YQ Admin RP1 BCC ES Packet Pg. 746 ATKINS August 17, 2021 16.A.9.a Atkins North America, Inc. 4030 West Boy Scout Boulevard, Suite 700 Tampa, Florida 33607 Telephone: +1.813.282.7275 www.atkinsgiobal.com/northamerica Brittany Lazo Associate Project Manager Capital Project Planning, Impact Fees & Program Management Division 2685 South Horseshoe Dr. Naples, FL 34104 RE: Plantation Island Waterways Pre -Design Study Contract No. 20-7710 Purchase Order/Work Order No. 4500209451 Collier County Project No. 60238 Brittany, This letter is to request Collier County for a time extension of 95 days for the above -mentioned project. The reason for this request is to be sure we meet the County's grant expiration date after allowing for additional mangrove trimming (not known during project scoping) within the project area which is being conducted as part of a separate County project. This project is as important to us as it is to the County and this extension will allow Atkins to assist the County in successfully meeting the grant requirements while creating a pre -design study for the citizens of Plantation Island that has the best opportunity to move forward. Please call me if you have any questions. Thank you for working with Atkins on this project. Sincerely, ATKINS Mark Erwin, P.E., CFM Packet Pg. 747