Loading...
#16-6700 CO #2 (Cardno, Inc) � Procurement Services Colder County Change Order Form ®Contract Modification 0 Work Order Modification 0 Amendment Contract#: 16-6700 Change#: 2 Purchase Order#: 4500187495 Project#: 66066.15 Contractor/Firm Name: Cardno, Inc. Contract/Project: Stan Gober Memorial Bridge Repair/Rehab Mario A.Puente,PE-CGC1 GMD—Transportation Engineering Project Manager Name: Division Name: Original Contract/Work Order Amount $ 271,565.59 5/8/2018 16A Original BCC Approval Date; Agenda item# Current BCC ApproNied Amount $ 289,614.75'r 1/14/2020 Last BCC Approval Date; Agenda Item# Current Contract/Work Order Amount $ 289,614,75 5/27/2020 SAP Contract Expiration Date(Master) Dollar Amount of this Change $ 67,973.32 31.68% ;Total Change torn Original Amount Reused Contract/Work Order Total $ 357,588.07 23.47% Change from Current BCC Approved Amount • Cumulative Changes $ 86,022.48 _ 23.47% _Change from Current Amount Completion Date,Description of the Task(s)Change,and Rationale for the Change . Notice to Proceed 06/25/2018 Original 06/20/2019 Last Approved 05/27/2020 Revised Date TBD' Date Completion Date Date Ancludes this change) #of Days Added 365 i Select Tasks 0 Add new task(s) ❑Delete task(s) ❑Change task(s) 0 Other(see below) Provide a response to the following:1.)detailed and specific explanation/rationale of the requested change(s)to the task(s)and I or the additional days added(if requested);2.)why this change was not included in the original contract;and,3.) describe the impact if this change is not processed. Attach additional information from the Design Professional and/or Contractor if needed.• *This project is currently on a stop work notice with 5 days remaining. 1. Per the original scope of work,Cardno Inc.performed a thorough Bridge inspection Report(SIR)for Structure No.030184. Findings in the Consultant's BIR indicated that the depth measured from the left bridge rail at Pier 13 during the 2017 Bridge Inspection may have exceeded the scour critical depth by 1.3 feet.The concern was that the original revetment system,which was installed to protect the pier against scour,may have been moved by Hurricane Irma. • On Change Order No.1,the Consultant was asked to prepare an assessment detailing the findings of the inspection and the condition of this scour countermeasure system for a not-to-exceed fee of$18,049.16 and 72 calendar days.Per the rationale of Change Order No.1,Change Order No.2 would be processed once the results of the proposed assesment were known. Per the attached Exhibit A-Scope of Services for Change Order No.2,the Consultant will design scour countermeasures,as well as provide permitting services required for said scour measures,for a not-to-exceed amount of$67,973,32 and an additional 365 days. 2. The scope described above was not included In the original contract as the potential conditions descxbed above were not known prior to the SIR performed by the Consultant. 3. Scour is one of the main causes of bridge failure,and not processing this change order could leave the aforementioned potential issues untreated Prepared by: ('lutia ,A.. ------ Date: 1 /42/204 Mario A. ente,PE-CGC—GMD Transportation Engineering. Acceptance of this C nge Order shall constitute a modification to contract/work order identified above and will be subject to all the same terms and conditions s contained in the contract I work order indicated above,as fully as if the same were stated In this acceptance. The adjustment,If any,to the Contract shall constitute a full and final settlement of any and all claims of the Contractor/Vendor I Consultant I Design Professional arising out oj.er I- :d to , •nge set forth herein,including claims for impact and delay costs. Accepted by: ate, _ Date: 4/26/2021 Dougla.. Stok:/•E`Vi ; Presiden -Cardno Inc. del A/' Date: `,' '2 /�.Ui..f Approved by: �..... _ ,del App :. by: IILthWJJ 1 Date: Thaddeu ' A I e —Department He.. Digitally signed by SchneebergerSara Approved by:S L I I I I b e t' C'I a I U Date:2021.05.171 '- ' Date: Procurement Professions Revised: 10/28/2014 (Divisions who may require additional signatures may include on separate sheet.) PROCUREMENT USE ONLY AdIMn BCC BCC Es :..vRpt �.,�'. . ATTEST: BOARD II !UNTY COMMISSIONERS Crystal K. Kirin',Clerk of Courts COLLI t R 'O 4 TY, FLORI &Co II etreller By: °A1A19 Penny Taylor,Chairperson Dated: '- °- (JAL) ' ,a... • fv .'A ,tO` hairman's sicgn,, tuee oniy. App e to f rm legality: By, -c-it..G Scott R.Teach Deputy County Attorney C:3rdnoi April 13tn, 2021 Shaping the Future Mr. Mario Puente, PE-CGC Senior Project Manager Transportation Engineering Cardno Collier County Growth Management Division 380 Park Place Blvd 2800 Horseshoe Dr. N. Suite 300 Naples, Florida 34104 Clearwater,FL 33759 USA Re: Stan Gober Memorial Bridge Repair/Rehab. Project—Change Order No. 2 Phone: +1 727 531 3505 Fax: +1 727 532 9891 Dear Mr. Puente: www.cardno.com Cardno is pleased to submit this proposal that includes the design of scour countermeasures and additional permitting services for the Stan Gober Memorial Bridge. The scope of work for Change Order No. 2 includes: 1. Drainage(Scour) Analysis (Lump Sum) 2. Drainage (Scour) Plans (Lump Sum) 3. Environmental Permits, Compliance and Clearances (Lump Sum) The total proposed fee for the services provided in Change Order No. 2 is $67,973.32, resulting in a total contract amount of$357,588.07 We are ready to proceed with this effort and will complete the project within 365 calendar days of receiving NTP from the County. Cardno looks forward to continue working with Collier County on this project. If I can provide you with any additional information, please do not hesitate to contact me. Sincerely, Doug 5_91Fe"r, PE Transportation Practice Group Manager Direct Line (727)431-1550 Australia • Belgium • Canada • Colombia • Ecuador • Germany • Indonesia • Kenya • New Zealand • Nigeria • Papua New Guinea • Peru • Philippines • Singapore • United Arab Emirates • United Kingdom • United States • Operations in over 100 countries FEBRUARY 2021 EXHIBIT A SCOPE OF SERVICES FOR DESIGN AND RELATED SERVICES FOR STAN GOBER MEMORIAL BRIDGE REPAIR/REHABILITATION PROJECT PROJECT NUMBER 66066.2 INCLUDING BRIDGE NUMBER: 030184 CONTRACT NO. 16-6700 CHANGE ORDER NO. 2 l PURPOSE 3 2 PROJECT DESCRIPTION 3 6A DRAINAGE ANALYSIS 4 6I1 DRAINAGE PLANS 4 8 ENVIRONMENTAL PERMIT'S,COMPLIANCE AND CLEARANCES 5 Only sections relevant to the Change Order are included. They are numbered according to the original agreement. A-2 SCOPE OF SERVICES FOR CONSULTING ENGINEERING SERVICES BRIDGE/STRUCTURAL AND HIGWAY DESIGN Collier County Project Number: 66066.2 Description: Design and Related Services for Repair/Rehabilitation of the Stan Gober Memorial Bridge in Collier County, Florida. [CR-92 /San Marco Road over Marco Channel] Change Order No. 2 Bridge Number: 030184 1 PURPOSE The principle intent of this Change Order is to provide design a permitting for Stan Gober Memorial Bridge (No. 030184) Scour Countermeasures. 2 PROJECT DESCRIPTION After data from the FDOT Bridge Inspection Report (BIR) was reviewed in concert with the Phase IV Scour Analysis and 2008 Scour Countermeasure Plans, it was determined that the depth measured from the left bridge rail at Pier 13 during the 2017 Bridge Inspection exceeded the scour critical depth by 1.3 feet. Due to concerns with the scour countermeasure system including potential shifting due to Hurricane Irma, the CONSULTANT provided further investigation and evaluation of the Scour Countermeasures at Piers 6, 7, 8, 9, 12, 13, 14, 15, 16. Based on recommendations from the investigation and evaluation, this scope includes the design of scour countermeasures as well as the additional permitting services required for the scour countermeasures into the CONSULTANT's "Stan Gober Memorial Bridge Repair Assessment Report". A-3 6a DRAINAGE ANALYSIS 6a.17 Technical Special Provisions The CONSULTANT will develop technical special provisions for the scour countermeasure repairs. 6a.18 Other Drainage Analysis Data Collection The CONSULTANT will collect information and data necessary to perform the study including bathymetric data, topographic maps, bridge inspection reports, scour evaluation reports, and bridge plans. Also during this task, The CONSULTANT will compile the design hydraulic conditions at the site from the existing modeling. This task will not include a site visit. Recommendations Regarding Existing Protection The CONSULTANT will develop recommendations regarding rehabilitation, augmentation, or removal of the existing protection. Scour Countermeasure Design The CONSULTANT will develop the conceptual design for the scour protection. This includes defining the horizontal and vertical extents, specifying the type of material (e.g. sizing rubble riprap), and incorporating any design constraints. The CONSULTANT will document all methods, procedures, and results in a letter report. 6a.20 Technical Meetings 6a.22 Quality Assurance/Quality Control 6a.24 Supervision 6a.25 Coordination 6b DRAINAGE PLANS 6b.6 Miscellaneous Drainage Detail Sheets The CONSULTANT will develop a design for the scour protection. This includes defining the horizontal and vertical extents, specifying the type of material (e.g. sizing rubble riprap), and incorporating any design constraints. A-4 The CONSULTANT will develop construction plans that reflect the design. 6b.13 Quality AssurancelQuality Control 6b.14 Supervision 8 ENVIRONMENTAL PERMITS, COMPLIANCE AND CLEARANCES The CONSULTANT shall notify the COUNTY Project Manager, and other appropriate personnel in advance of all scheduled meetings with the regulatory agencies to allow a COUNTY representative to attend. The CONSULTANT shall copy in the Project Manager on all permit related correspondence and meetings. 8.2 Field Work The CONSULTANT shall perform the following Environmental Field Work. 8.2.2 Establish Wetland Jurisdictional Lines and Assessments Wetland jurisdictional lines will not be established because all maintenance work to be performed is over water. Submerged Aquatic Vegetation (SAV) survey and Essential Fish Habitat(EFH) assessment will be performed in the vicinity of the scour protection system only, for scour protection system repair. SAV/EFH assessment/substrate assessment for contractor barge access clearance is not included. 8.2.3 Species Survey The CONSULTANT shall perform preliminary species surveys. 8.3 Agency Verification of Wetland Data The CONSULTANT shall perform field visit with both agencies, at the same time, and shall submit required follow-up information. 8.4 Complete and Submit All Required Permit Applications The CONSULTANT shall perform the following work as part of the Environmental Permit Application process. 8.4.1 Complete and Submit All Required Wetland Permit Applications The CONSULTANT shall complete and submit all required wetland permit applications. This scope of work assumes a SFMWD Exemption Verification or • General Permit for bridge maintenance, and a USAGE Nationwide Permit. The scope includes completing and submitting permit applications, including the Uniform Mitigation Assessment Method (UMAM), assessing impacts, compiling A-5 Environmental Resource Permit (ERP) Environmental Support document, and assisting with responses to Requests for Additional Information. This scope assumes no permanent wetland impacts and no mitigation will be required. This scope assumes no bridge permitting is required, but that coordination with Aids to Navigation will be required and a memorandum will document the coordination and recommendations to the engineer. 8.5 Prepare Dredge and Fill Sketches (as needed) Assume no bridge permitting required, but that coordination with Aids to Navigation will be required and a teleconference 8.6 Prepare USCG Permit Sketches Assume no bridge permitting required, but that coordination with Aids to Navigation will be required and a teleconference memorandum will document the coordination and recommendations to the engineer. 8.17 Technical Meetings The CONSULTANT shall attend virtual meetings with the WMD/FDEP, USCG, USFWS, and Collier County. 8.18 Quality Assurance/Quality Control 8.19 Supervision 8.20 Coordination A-6 i • ae 0' 4 0p f_ i+ , v e S e e P P e e e e e e e e ce e e e !? P $: e V P 's_ 9 o e M N x r' v °i C 2Q 2 - 2 2 2[� 2 2 2(] 4p .a 2 2 2 2 2 2 2 R R li 6 a a' 1- N e Q N C Y H Y * le i M Q ln1 R tI g e R 2 !VI A A ,9 Q Q Q R r V i2 k � v N N N N N M •1 N N it 23 li ....... p ry mi. '� N N N N ,n N g Q !✓ .,. N 2 a8i 8 n ti :4 H o 2 N 2 2 2 2 2 ,•'i. .ni. `2 v2 2 v8 rnn 2 2e Jni i� g ei N (' u 0 ✓r ✓��` r Y 2 g m o 0 0 $ _ 0 ,� o 0 0 0 0 0 0 o n n o o u o o n o 0 o n 0 u u o 0 0 . !-. °'0 ait � erv- .3 L 8 , " 1 0 O n 0 0 0 n O n n n n n n n 0 0 0 0 0 o O n O n 0 0 o n o o n n e r qq E. AVI Y __ _.-_.._.. . M1 C .4 C q g S i 8 0 0 0 o n 0 0 o u u n o 0 o u u u 0 0 0 0 o n o 0 0 0 0 0 0 o 0 0 0 0 6 1C N 6 w DA K E o o n 0 o n n n u o 2 .6 0 _ f1 2 x r V 0 u; e o 0 0 0 o n o 0 0 o n o 0 n o n o 0 0 0 0 0 o a 0 2 8 7 = LL -«cft3332 � o V " 0 _ z .{ 2 .] 9 4 z CC.}} W k g R•( W a 9 1 W n n n u 0 1IUU e' yyS 0 0 0 0 0 0 o a o 0 0 0 0 0 0 0 0 0 o n o 0 0 0 0 o n o o o >,I t i O .„pp. C 'QRS ttg77qKK u 0. CO X Q e- Z V N 0 0 0 u w g N N O 1- F- 2 u o 0 u o o n n n n o 0 0 0 8 za0 0 o a o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o n a 0 O O .... _ ...___ M R1 00 0 . 000 0 0 0 00 0 . 0 00 u 0 0 0 00 00 0 0 0 0 0 0 0 n 0 0 8 Y Z non 0 u 0 0 " S _rz Q o 0 0 0 o 0 o n o 0 0 0 0 0 o a o 0 o n 0 0 o n o�� tt LL• c Y `• 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0n;r Et n O 2 e' 3 r. n o ^ 0000 00 0 n S a m ill v V, gi n o o ;1i / 0 0 o n o 0 0 0 0 0 0 0 0 0 0 0 o n o o n o 0 0 0 o n n ,,; A R • 1- m E Qg $9 es._ b—_ o o yg .. .G 0 0 0 0 0 0 0 o u 0 0 o . 0 0 0 0 o a o 0 0 0 0 0 0 0 0 0 e iR o u V [ N a 9 ii 2 i c8 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o a o 0 0 0 0 0 n o 0 0 0 0 0 0 0 0 a U E ry al li .N ____.._._ Yoe .t - t o O o n N ,A n O 0 .J n n O O n O O O n O O O _) o n O O 0 O O o O a„ ;u a24 Et a O t 0 3 r $ . n n n n n o 0 1 5,L -AoN Ltu00 ,q, n onno noououanonouu0o Z GGLt ell Lc = N 7 e ,1 7 u " b R € m 8. E a a , f rc m 1 •• C aU r a u N F S" 2 3 o L h v x ae pl g1 > 5 " 1 1 .i '.S b a 1:lag. _ L' it a- N�7. X ?' p 8 o, es s S ,r f n ^ a 4 3 E a o t e C C e gg 1 g @ • F ti a 2 § S 9 4 y N e Li a a 2 ; 1, t g k, ni �� .ry � G gS ,y-Z, 2n K fi it C .2 .; e y k S 4 .b�`6 g. P ? k 2 E Tt1. n 's C�i N `g R w n .a O O , ;t N 6 6 Vn N N N Yl & !%1 1%1 6 6 6 Y i -bb1 N r p�p.1 - a : ` a Y .n z b • .- n n .. N n 1- n n R r, N N v ry N n ,Y la n pi r� ,11 H /Uu. n 1. m a• - -- - INTERA PROPOSAL Local Scour Countermeasure Design for the Stan Cober(Goodland) Bridge(CR-92 over Marco Channel)(Bridge No.030184) Collier County INTERA Incorporated January 2019 Problem Understanding Collier County has requested the design of local scour countermeasures for the existing Stan Clober (Goodland) Bridge over Marco Channel (Bridge No. 030184). Cardno, Inc. requested preparation of this Scope of Services from 1N1'ERA Incorporated. The purpose of this Scope of Services is to provide recommendations regarding the existing scour protection and to develop to design scour countermeasures for several of the interior bents. Assumptions We based our scope of services on the following assumptions: I. Cardno will provide INTERA with survey data (bathymetric and topographic) from the bridge location. 2. Cardno will provide INTERA with plans of the existing bridge. 3. Design will rely upon existing hydraulic modeling of the area contained in the Phase 2 Scour Evaluation Report for the bridge. Scope of Services Task I Data Collection INTERA will collect information and data necessary to perform the study including bathymetric data, topographic maps, bridge inspection reports, scour evaluation reports, and bridge plans. Also during this task, INTERA will compile the design hydraulic conditions at the site from the existing modeling. This task will not include a site visit. Task 2 Recommendations Regarding Existing Protection As part of the rehabilitation project,Cardno indicated that an underwater inspection will occur to evaluate the condition of the existing scour protection. Based on the results of this inspection, INTERA will develop recommendations regarding rehabilitation,augmentation,or removal of the existing protection. Task 3 Scour Countermeasure Design INTERA will develop the conceptual design for the scour protection. This includes defining the horizontal and vertical extents, specifying the type of material (e.g. sizing rubble riprap), and incorporating any design constraints. INTERA will document all methods, procedures, and results in a letter report. Additionally, as part of this task, INTERA will review the construction plans and specifications developed by Cardno to ensure that the final drawings reflect the conceptual design as well as to address any variances as they arise. Task 4 Quality Control Review INTERA will conduct a complete internal review before submission to the Cardno for its review and comment. Task 5 Project Coordination/Meetings 1N'I'IRA will participate in teleconferences, as necessary, with the Cardno during the length of INTERA's involvement with the project. Budget The cost to perform these services is$14,257.32.This cost reflects 91 hours of fully burdened labor. IIIIIIIMIIIIIIIIIMIIMIlla --1 ya � � FQ gesv � Keq; L 'egeir � Pt i sS8$$ " r, _ jg t: stuse -. tss . uuuasssu :� asassssxu : Rsss ' 4 U 4 • f a7r voo I� . . ,1„,, ,,0 near. nnaaooaennna noo aoaennn 6 Z o F. N 1- -ao o n o e o a o o o n o a o 0 0 o n o 0 0 0 0 o e n e o o u o 0 O n•� I� � t� i4 ,a rN 3 3 -- t 1 V ^ n" 8 o ,I a none ono .., , 00 ooae 0o0no0 R 000 . enean , ., a aeeea ., .. aeeae ,., er. a, neaa ., annlg a z 2 P 9 e n FW- P 9 P N n Wj n.g 9 C e o o u u u o c o 0 0 0 0 0 0 o e B '' — fg L O 6 O O U•p a o e n o n O O n O n a u o o V o o 0 2 dg YI 1 U P m z,I'..1 = n O Z - - �So� S� KN�u Q 'M A -_ __-_—_-_.__—_-- .._.___ 5.5 0 O V e n C. CI n e e C o V u n u V o V p o n Con a. 0 o n a CIn o 0 0 a J Z -- ? 0 0 0 o a u o o o e o n 0 0 0 e 0 e e o a 0 e n o 0 o n o n o a o H o a zn 's • £' F. in ar rgl 1. O q o o n 0 .., e n n a n o e 0 0o 0e o 0 o Coea .. 0 0 0 0 n Cs n 0 0 010 A 1.. w ' 0 0000 , 0 C0000oa0 0 000000n sN8 :Y o 0 c n > r, 0e a .. o@ 0 .o u O w u I r h — — a e n a n vJ o Z W w w nen00 n0oonn ., .. r 0 o n n ., n n 0 u o o " E d n '� Oo00 000ee oeeo0oe .,�y,R 3 w E ee a 0 a a e g e e o n o a n n 0 n S s o C w z.__._.._..__Y... ----- 3 1 y 0 0 0 0 ' . n o 0 0 0 0 r, n a e o 0 o n e n ., e 0 0 o a o e a r j{ x o a n 3 a ^a. B € S 1 1 I 1; e n o0n ^ nne. a00 n o n o o o 0 0 000o,� 8 113 El 0 0 o n e e o o n n o n o o n 0 0 o a, a e o e 0 a o 0 0 e 11 .I0h h u. na/ a� of .2 E E 8 I ` ; 1 Y ga e 'tomp� m Y }'nib h ` S' E ii . e6 -5 :a it Q : w i.1 1 t �ltt r yg . 1h Ia V. 1, $ .7 k € ., . . v. 1 ,,? 5 aK• i a & F -2 t -S T _LL E R I t i M � $ tt i! tPi111. . S 5 akiSi €L -y� mt.ls , i 1 X, �.9S T. R CS :i :{ 7t d x I,