Loading...
Agenda 07/13/2021 Item #16C 8 (Purchase Order for RFQ #19-7622-302.25)07/13/2021 EXECUTIVE SUMMARY Recommendation to approve a purchase order to US Water Services Corporation, in the amount of $435,105.01, Request for Quotation 19-7622-302.25, “Pump Station No. 302.25 Rehabilitation,” and authorize the necessary budget amendment (Project Number 70145). OBJECTIVE: To bring outdated utility infrastructure into compliance with current standards while meeting the demand for service, protecting public health and safety, and providing proactive environmental protections. CONSIDERATIONS: The proposed scope of work under Project Number 70145, “WW Pump Station TSP,” can be completed consistent with funding in the FY2021 Capital Improvement Project Budget approved by the Board on September 17, 2020. Pump Station (PS) 302.25 is located within the Woodmere Country Club, adjacent to the Whitaker Road right-of-way (ROW). The pump station is currently accessed from within the Woodmere Country Club. It is difficult to access, in need of rehabilitation, and does not meet Collier County standards. PS 302.25 receives flows from Woodmere lakes Club, Erin Woods Club, Woodmere Racquet Club, Naples Parkwood, and Edgewood and discharges into a 30-inch force main that runs along Whitaker Road. The service area of PS 302.25 contains 192 service accounts, and commercial parcels which include clubhouses with community pools and tennis courts. This portion of the rehabilitation project consists of civil site work, underground utility work, electrical components, and mechanical process piping work. The work includes the installation of a standby diesel generator for power resiliency and environmental protection, all piping, valves, wet well coating and other material or component necessary to place the pump station into service. The confined space valve vault will be eliminated by moving piping and appurtenances above grade. The condition of PS 302.25 has regressed to “Red: Level 3 - Risked Compliance”. The Request for Quotation 19-7622-302.25, “Pump Station No. 302.25 Rehabilitation,” was electronically distributed on June 1, 2021, to the four vendors under the Annual Agreement for Wastewater Pump Station Repair and Renovation Contract No. 19-7622. Four of those contractors submitted quotations by the June 14, 2021, deadline. The quotations are summarized below. VENDOR QUOTE US Water Services Corporation $ 435,105.01 Precision Lift Stations, Inc. $ 481,030.00 Quality Enterprises, Inc, $ 590,500.00 Douglas N Higgins, Inc. $ 668,300.00 Staff reviewed the quotations and determined US Water Services Corporation, to be the lowest qualified and responsive bidder, that bidding was competitive and representative of market conditions, and recommends awarding this project to US Water Services Corporation. The quotes received were approximately 26 percent above the engineer’s cost estimate due to large price swings of materials within the construction industry. The request for quotation and quote tabulation is Attachment 1 and Attachment 2, respectively. The project design professional, Q. Grady Minor & Associates, P.A., also recommends award of this purchase order to US Water Services Corporation, per the attached letter dated June 14, 2021 (Attachment 3). US Water Services Corporation was established and incorporated in the State of Florida in 2003 and 16.C.8 Packet Pg. 1267 07/13/2021 holds a General Contractor, Underground Utility Contractor, Plumbing and Electrical Licenses. The bid specifications informed the bidders there may be unforeseen conditions associated with the project. The project cost includes an allowance of $20,000 for owner-directed work due to unforeseen corrosive or geological conditions that include, but are not limited to, repairs due to structural deterioration, and/or replacement of defective mechanical equipment and deficient electrical components. Subject to the Procurement Ordinance, staff will negotiate a price for any additional work due to unforeseen conditions prior to the start of any work. FISCAL IMPACT: A budget amendment in the amount of $199,000 is required to reallocate funds within Wastewater User Fee Fund (414) to Project 70145. The source of funding is wastewater user fees. The project is expected to be completed in 2021. This is an improvement project and operating costs are not expected to change. Bonds will be obtained prior to issuing a purchase order. LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for Board approval. -SAA GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan standards to ensure the adequacy and availability of viable public facilities. RECOMMENDATION: That the Board of County Commissioners, Ex-officio Governing Board of the Collier County Water-Sewer District, approves a $435,105.01 purchase order under Request For Quotation 19-7622-302.25, “Pump Station No. 302.25 Rehabilitation,” (Project No. 70145) to US Water Services Corporation; approves the necessary budget amendments and, authorizes the Chair to approve the Purchase Order. Prepared By: Corinne Trtan, PMP, Project Manager, Public Utilities Engineering and Project Management ATTACHMENT(S) 1. Attachment 1 - Request for Quotation (PDF) 2. Attachment 2 - Quote Tabulation (PDF) 3. Attachment 3 - Letter of Recommendation (PDF) 16.C.8 Packet Pg. 1268 07/13/2021 COLLIER COUNTY Board of County Commissioners Item Number: 16.C.8 Doc ID: 16268 Item Summary: Recommendation to approve a purchase order to US Water Services Corporation, in the amount of $435,105.01, Request for Quotation 19-7622-302.25, “Pump Station No. 302.25 Rehabilitation,” and authorize the necessary budget amendment (Project Number 70145). Meeting Date: 07/13/2021 Prepared by: Title: Project Manager – Public Utilities Planning and Project Management Name: Corinne Trtan 06/17/2021 4:21 PM Submitted by: Title: Division Director - Public Utilities Eng – Public Utilities Planning and Project Management Name: Tom Chmelik 06/17/2021 4:21 PM Approved By: Review: Wastewater Steve Nagy Additional Reviewer Completed 06/18/2021 5:45 AM Wastewater Steve Messner Additional Reviewer Completed 06/18/2021 9:38 AM Public Utilities Planning and Project Management Tom Chmelik Additional Reviewer Completed 06/18/2021 4:55 PM Public Utilities Operations Support Tara Castillo Additional Reviewer Completed 06/21/2021 7:13 AM Public Utilities Operations Support Joseph Bellone Additional Reviewer Completed 06/21/2021 8:25 AM Public Utilities Operations Support Jennifer Morse Additional Reviewer Completed 06/21/2021 11:00 AM Public Utilities Planning and Project Management Craig Pajer Additional Reviewer Completed 06/21/2021 1:50 PM Public Utilities Department Drew Cody Level 1 Division Reviewer Completed 06/21/2021 2:42 PM County Attorney's Office Sally Ashkar Level 2 Attorney Review Completed 06/22/2021 11:58 AM Public Utilities Department George Yilmaz Level 2 Division Administrator Review Completed 06/23/2021 10:45 AM Procurement Services Ana Reynoso Level 1 Purchasing Gatekeeper Completed 06/24/2021 1:14 PM Procurement Services Evelyn Colon Additional Reviewer Completed 06/28/2021 12:00 PM Procurement Services Sue Zimmerman Additional Reviewer Completed 06/28/2021 1:21 PM Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 06/23/2021 11:56 AM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 06/28/2021 3:40 PM Budget and Management Office Ed Finn Additional Reviewer Completed 06/28/2021 6:13 PM 16.C.8 Packet Pg. 1269 07/13/2021 Office of Management and Budget Susan Usher Additional Reviewer Completed 07/04/2021 12:00 PM County Manager's Office Amy Patterson Level 4 County Manager Review Completed 07/06/2021 11:33 AM Board of County Commissioners Geoffrey Willig Meeting Pending 07/13/2021 9:00 AM 16.C.8 Packet Pg. 1270 16.C.8.aPacket Pg. 1271Attachment: Attachment 1 - Request for Quotation (16268 : PS 302.25 Rehabilitation) Item No.Item Description QTY Unit Unit Price Bid Total 1 Mobilization/Demobilization (Max 10% of Base)1 LS $22,520.40 $22,520.40 2 Pump Station Rehabilitation 1 LS $380,084.61 $380,084.61 3 Landscape 1 T&M $12,500.00 $12,500.00 4 Allowance 1 TBD $20,000.00 $20,000.00 $435,105.01 SCHEDULE OF VALUES RFQ 19-7622-302.25 - PS 302.25 Rehabilitation Collier County EPMD PROJECT No.: 70145.31 SECTION 1: GENERAL CONTRACTOR TOTAL BID 16.C.8.a Packet Pg. 1272 Attachment: Attachment 1 - Request for Quotation (16268 : PS 302.25 Rehabilitation) DATE SENT: June 1, 2021 Notifications Sent: 4 QUOTE DUE DATE: June 14, 2021 Viewed: 4 AWARD CRITERIA: Lowest Lump Sum Quote Submittals/Bids: 4 Summary Description US Water Services, Corp Precision Lift Stations, Inc Quality Enterprises, Inc.Douglas N Higgins, Inc Lump Sum Quote 435,105.01$ 481,030.00$ 590,500.00$ 668,300.00$ 19-7622-302.25 Pump Station 302.25 Rehabilitation Due: June 14, 2021 at 3:00PM 16.C.8.b Packet Pg. 1273 Attachment: Attachment 2 - Quote Tabulation (16268 : PS 302.25 Rehabilitation) Civil Engineers  Land Surveyors  Planners  Landscape Architects Q. Grady Minor & Associates, P.A. Ph. 239-947-1144  Fax. 239-947-0375 3800 Via Del Rey EB 0005151  LB 0005151  LC 26000266 Bonita Springs, FL 34134 www.gradyminor.com June 14, 2021 Ms. Corinne Trtan Project Manager Collier County Engineering and Project Management Division 3339 Tamiami Trail East, Suite 301 Naples, FL 34112 RE: Award Recommendation RFQ 19-7622-302.25 Rehabilitation Dear Ms. Trtan: Q. Grady Minor & Associates, P.A. (GradyMinor) has completed our review of the bid documents for the above referenced project and we are pleased to provide the following award recommendation. The scope of the PS 302.25 Rehabilitation includes the removal of existing pump station appurtenances and replacement with new above grade piping, concrete driveway, chain-link privacy fencing, and a backup diesel generator. Based on the bid tabulation (attached), U.S. Water Services, Corp. is the low bidder with a bid amount of $435,105.01, which is approximately 26% more than the project’s Opinion of Probable Construction Cost (OPCC) amount of $344,675.00. It is our experience that during the global pandemic, there has been large price swings with the costs of materials, which may have attributed to the difference between the project OPCC and the Contractor’s Bid. U.S. Water Services, Corp is an approved Contractor as part of Collier County Contract #19-7622 “Annual Agreement for Wastewater Pump Station Repair and Renovation”. U.S. Water has provided all the documentation required by this contract. Based on the above information, GradyMinor recommends U.S. Water Services, Corp. be awarded the PS 302.25 Rehabilitation Renewal Project in the amount of $435,105.01. Please feel free to call me with any questions. Very truly yours, Alexander Dunko, P.E. Project Manager 16.C.8.c Packet Pg. 1274 Attachment: Attachment 3 - Letter of Recommendation (16268 : PS 302.25 Rehabilitation) DATE SENT: June 1, 2021 Notifications Sent: 4 QUOTE DUE DATE: June 14, 2021 Viewed: 4 AWARD CRITERIA: Lowest Lump Sum Quote Submittals/Bids: 4 Summary Description US Water Services, Corp Precision Lift Stations, Inc Quality Enterprises, Inc.Douglas N Higgins, Inc Lump Sum Quote 435,105.01$ 481,030.00$ 590,500.00$ 668,300.00$ 19-7622-302.25 Pump Station 302.25 Rehabilitation Due: June 14, 2021 at 3:00PM 16.C.8.c Packet Pg. 1275 Attachment: Attachment 3 - Letter of Recommendation (16268 : PS 302.25 Rehabilitation)