Agenda 07/13/2021 Item #16C 3 (Certification of Financial Responsibilty)07/13/2021
EXECUTIVE SUMMARY
Recommendation to approve a Certification of Financial Responsibility required by the Florida
Department of Environmental Protection in connection with the renewal of an existing permit to
Operate a Non-Hazardous Class 1 Injection Well System at Collier County's South County
Regional Water Treatment Plant (“SCRWTP”) Facility on City Gate Drive.
OBJECTIVE: To certify, unconditionally, to the Florida Department of Environmental Protection
(“FDEP”) the county’s obligation to close, plug, and abandon its SCRWTP Deep Injection Well (DIW)
and related dual zone monitoring well as required by Chapter 62-528, Florida Administrative Code.
CONSIDERATIONS: The permit renewal application requires the county to complete and execute a
Certification of Financial Responsibility form. This form certifies that the county will be unconditionally
obligated to have the financial resources necessary to close, plug, and abandon the Class I injection well
and related monitoring well.
The initial Certification of Financial Responsibility for the SCRWTP DIW and its dual zone monitoring
well was included in the county's Application to Construct DEP Form No.62-528.900(1) submitted on
August 26, 2005. At the time of the initial application, the estimate to plug and abandon the wells was
$333,000.00 At the time of the most recent renewal of operating permits (FDEP Permit No. 173528 -009-
UO/I I & 173528-0 I 0-UO/I I) the estimated cost was $731,578.00. The current estimated cost to plug
and abandon is $621,240.00.
FISCAL IMPACT: The actual expenditure of funds is not anticipated and would only be required if the
county abandoned the injection wells. Funds to cover these costs, if needed, are maintained in the
Reserves for Contingency line item in Fund (408), which is funded through user fees.
GROWTH MANAGEMENT IMPACT: There is no growth management impact associated with
executing this document.
LEGAL CONSIDERATIONS: This item is approved for form and legality and requires a majority vote
for Board action. - SRT
RECOMMENDATION: To approve and authorize the Chair to sign the attached Certification of
Financial Responsibility form.
Prepared by: Steve Messner, Director, Water Division
ATTACHMENT(S)
1. Cert of Finan Respon 061521 (PDF)
2. Plugging and Abandonment SCRWTP Cost Estimate (PDF)
3. Resolution no 2001-294 (PDF)
16.C.3
Packet Pg. 1208
07/13/2021
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.C.3
Doc ID: 16254
Item Summary: Recommendation to approve a Certification of Financial Responsibility required
by the Florida Department of Environmental Protection in connection with the renewal of an existing
permit to Operate a Non-Hazardous Class 1 Injection Well System at Collier County's South County
Regional Water Treatment Plant (SCRWTP) Facility on City Gate Drive.
Meeting Date: 07/13/2021
Prepared by:
Title: – Public Utilities Department
Name: Drew Cody
06/11/2021 11:58 AM
Submitted by:
Title: Division Director - Water – Water
Name: Steve Messner
06/11/2021 11:58 AM
Approved By:
Review:
Water Drew Cody Additional Reviewer Skipped 06/11/2021 11:59 AM
Water Steve Messner Additional Reviewer Completed 06/11/2021 12:04 PM
Wastewater Steve Messner Additional Reviewer Completed 06/11/2021 12:05 PM
Public Utilities Operations Support Joseph Bellone Additional Reviewer Completed 06/11/2021 3:41 PM
Water Randy Lewis Additional Reviewer Completed 06/14/2021 3:06 PM
Public Utilities Department Drew Cody Level 1 Division Reviewer Completed 06/14/2021 3:10 PM
Public Utilities Department George Yilmaz Level 2 Division Administrator Review Completed 06/15/2021 2:56 PM
County Attorney's Office Scott Teach Level 2 Attorney Review Completed 06/15/2021 4:40 PM
Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 06/15/2021 4:43 PM
County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 06/16/2021 11:19 AM
Budget and Management Office Ed Finn Additional Reviewer Completed 06/22/2021 2:51 PM
County Manager's Office Amy Patterson Level 4 County Manager Review Completed 06/28/2021 4:37 PM
Board of County Commissioners Geoffrey Willig Meeting Pending 07/13/2021 9:00 AM
16.C.3
Packet Pg. 1209
16.C.3.aPacket Pg. 1210Attachment: Cert of Finan Respon 061521 (16254 : Cert of Financial Responsibility SCRWTP DIW)
16.C.3.aPacket Pg. 1211Attachment: Cert of Finan Respon 061521 (16254 : Cert of Financial Responsibility SCRWTP DIW)
'''I >
May 3, 2021
Steve Messner
Director, Water Division
Collier County Public Utilities Department
3339 Tamiami Trail East, Suite 30 I
Naples, FL 3441 12
Subject: Collier County Public Utilities Department
SCRWTP fW-1 and IW-2
Plugging and Abandonment Cost Estimate
FDEP Permit No. 173528-009-UO/I I & 173528-0 I 0-UO/I I
Dear Mr. Messner:
As requested, WSP has prepared this cost estimate for the plugging and abandonment of the
injection wells at the South County Regional Water Treatment Plant (SCRWTP). Collier County
owns and operates two Class I deep injection wells at the SCRWTP. The injection well system
consists of two deep injection wells (IW-1 and IW-2) and one dual-zone monitor well (DZMW-
1 ). Each of the three wells would need to be filled with cement to land surface to complete the
abandonment process. The open hole sections of the injection wells would be filled with gravel
prior to grouting the injection well casings.
The estimate provided is based on a previous cost estimate for plugging and abandonment of the
injection well system prepared during 2016 and review of recent bids for injection well work in
South Florida. Please feel free to call me if you have any questions or if you require additional
information.
Yours sincerely,
Scott Manahan, P.E.
Senior Engineering Manager
WSP USA Inc.
1567 Hayley Lane
Suite 202
Fort Myers, FL 33907
(239)481-6494
WSP.com
16.C.3.b
Packet Pg. 1212 Attachment: Plugging and Abandonment SCRWTP Cost Estimate (16254 : Cert of Financial Responsibility SCRWTP DIW)
\\\lt
Procedures and costs for the plugging and abandonment of
injection wells IW-l and fW-2 and dual-zone monitoring well DZMW-I
Collier South County Regional Water Treatment Plant
Plans for the plugging and abandonment of injection wells lW- l and lW-2 and dual-zone monitor
well DZMW-l are provided in Figure C-1. For the purpose of preparing a cost estimate, it is
assumed that dual-zone monitoring well DZMW- l would be abandoned. However, the
possibility exists that well DZMW-l might be retained outside of the Florida Department of
Environmental Protection (FDEP) Underground Injection Control (UIC) program as a regional
monitor well.
Injection wells IW-l and IW-2 would be abandoned by first "killing" the flow of the well and
then removing the wellhead. The open hole in each well would then be filled with gravel to l0
feet below the base ofthe 14.48-inch inner diameter fiberglass reinforced plastic (FRP) injection
tubing. The remaining open hole and FRP tubings would be cemented to land surface.
The dual-zone monitoring well would be abandoned by filling both the 6 5/8-inch and 12.75-inch
outer diameter casings with Portland cement to land surface. Neat Portland cement would be
used unless permission is granted by the Florida Department ofEnvironmental Protection (FDEP)
to use extenders.
The abandonment plans for the well includes 6 major bid items:
Bid ltem #l includes all work associated with mobilization and demobilization ofthe drilling rig
and supporting equipment required for the task. This bid item also includes the work required to
retrofit the drilling pad with new pad walls to ensure that injected or formation fluids are not
accidentally spilled on the ground.
Total (lump sum): $ 185,000
Bid Item #2 consists ofmechanical integrity tests
Contractor costs (2 wells @ $50,000): $100,000
Bid Item #3 includes the materials and work required to "kill" the flow ofthe injection wells
Lump sum (2 wells): $25,000
Bid Item ll4 includes all work required to fill the injection wells with gravel to approximately l0
feet below the bottom ofthe 14.48-inch fiberglass tubing (estimated 3,615 ft3 at 4.50/ft3):
Estimated cost (2 wells): $25,000
Bid ltem #5 includes all materials and work required to fill the remaining open holes and
nominal 14.48-inch I.D. injection tubings of injection wells andthe DZMW-l casings and open
hole with neat cement to land surface (estimated 5,400 ft3 at $16.00/ft3) plus rig time (3 wells):
$ 132,700
Bid Item li6 includes cleanup ofthe site and disposal of materials: $50,000
TOTALCONTRACTORCOSTS: $517.700
CONTINGENCY (20%): $103,540
TOTAL CONTRACTOR COSTS & CONTINCENCY: $621 .240
16.C.3.b
Packet Pg. 1213 Attachment: Plugging and Abandonment SCRWTP Cost Estimate (16254 : Cert of Financial Responsibility SCRWTP DIW)
1■抑
…
2∞α
:NJECT!(
(AS‐BU:L
IN」ECT10N WELL″1∥Wl
(AS‐BU:LT WELL PROFILE)
ヨlD
「
υ7嗣 :響 忍疑習E
「
t雪 器 計
□G瑞 』醐ぎ
□
N¨RIANO CEME嗜
)N WELL滋 ∥W21
T WELL PROF:LE)(AS‐BUILT WELL PROF:LE)
```じ
l〕
$tdi.ksfu19ll*rh,SUFdIFaffiSh:{2!}{r4ffidl@rillaa-t46
Colid Courty Pubac Uihi.s Ocpalfut
C‐f16.C.3.b
Packet Pg. 1214 Attachment: Plugging and Abandonment SCRWTP Cost Estimate (16254 : Cert of Financial Responsibility SCRWTP DIW)
RESOLUT:ONN0 2∞1‐294 16B8'1
A RESOLUT10N APPOINTINC AND AUrHORIZING THE
COMMUNITY DEVELOPMENT & ENVIRONMENTAL
SERVICES, EMERCENCY SERViCES, PUBLIC SERVICES,PUBLIC UT:LIT:ES, SuPPoRT SERV:CES ANつ
TRANSPORTAT:ON ADMINISTRATORS AND ANY
DEPARTMENT DIREC■ORS THEV ttY APPO:NT AND
ALIHORIZL TO EXECUTE CRANT APPLICATIONS,PERMIT
APPLICAT10NS Aヽ D OTHER DOCUMENTS PERTAINIヽ C TOTHE CONSTRCCT10N OF CA PITAL IMPROVEMENT
PROJE∝SWHEREAS thc Board of County COmmissloncrs oF Conicr cOunty Fl。■da has a need
for eapital proleci des18n and construclon act,vitics thiou3hout thC COunty which may rcquirc
appl,cation for Fants and pcrmits through 10cュ l state and Fedc:`l agcneicsi and
W HEREAS, it is thc intention or said Bodrd !。 makc app!icallons to local, statc and
Fcdcral agcnctes;.lnd
WHEREAS.in ordc「to cxPcd tC proccssing it is neccsary to offlciBlly aPPOint and havc
Or record county ofrcials Outho■zed tO cxccute grmi 3ppl c●tiOns,pcmit`pp cutiOns IInd othe「
documents pe・ taining`o the conslnlction of capital impr●vemcnt prolects On bch31F O,thc Board
to va●ous●gcncics including but nOtllmited to thc following:
Federal Avi310n AdministratiOn
Fttral Environmental Protcction Agencン
Flo●da Depanment of EnvirOnmcnta Pmtcc10n
Flo●da Depanment of TranspOnation
Flolda nsh and wild∥rc Conservalon Commission
South Flo●d●Watcr Man.lgcncnt Disl●ci
O S Amy Corps or En3incers
O S CoastCu●rd
NOW, THEREFORE. BE IT RESOLVED BY THE BOARD OF COUNTY
COMMISSIONERS OF CO[iIER COUNTY.FLOR:DA.that:L漁 榊醐鮒爾鶯I鷺 W猫
2 RcsOlu:lo■No 2000‐18ワ is hereby supersedcd by thi6 RcbolutiOn
THIS RESOLUT【ON ADOPTED AFrER MOT:ON SECOND AND MAJORITY
VOTE FAVORING ADOPTЮN
Appr●v“
`,1。口 m andI・
“
]ヽ uf“にncメ
BOARD OF COUNTY COMMISS10NERS
16.C.3.c
Packet Pg. 1215 Attachment: Resolution no 2001-294 (16254 : Cert of Financial Responsibility SCRWTP DIW)