Agenda 06/08/2021 Item #16C 6 (Change Order #1 to Agreement #20-7709 w/Douglas N. Higgins, Inc.)06/08/2021 EXECUTIVE SUMMARY Recommendation to approve attached Change Order No. 1 to Agreement No. 20-7709, “South County Water Reclamation Facility Pump Station No. 5 & Piping Improvements," with Douglas N. Higgins, Inc., and authorize the Chair to sign the attached Change Order. (Project Number 70251) OBJECTIVE: To provide reliable, sustainable, and regulatorily compliant services by increasing the capacity and reliability of the plant drain pumping system at the South County Water Reclamation Facility (“SCWRF”). CONSIDERATIONS: On April 28, 2020 (Agenda Item 16.C.7), the Board approved Agreement No. 20-7709 to Douglas N. Higgins, Inc., for the SCWRF Pump Station 5 & Piping Improvements project, which included construction of a new plant drain pump station and adjustments to the plant drain piping system to increase capacity. During construction of this project the work crew encountered a 24-inch diameter pipe in direct conflict with the proposed precast concrete wet well structure for the new plant drain pum p station. The record drawings for the plant showed that pipe capped upstream and removed from the proposed wet well construction area. The County directed the contractor to attempt to locate the as -built location of the capped pipe to determine if it was still connected to the plant’s influent force main piping. The contractor’s exploration could not make this determination because the area had been backfilled with concrete. Continuing this effort, the County directed the contractor to install a saddle and tapping valve to allow a hole to be cut in the pipe in a safe and controllable manner. The pipe consisted of prestressed concrete cylinder pipe (“PCCP”). This material is not commonly available and any modifications, including the proposed tapping of the pipe, require special construction techniques. The successful pipe tap confirmed that the pipe was not active, and the piping in conflict with the new construction was removed. The record drawings for the project will be updated to reflect the pipe removal and other conditions revealed with the exploratory digging performed under this project. The attached Change Order authorizes a time extension of 101 days (31%) to allow for the exploratory work, scheduling and tapping of the 24-inch PCCP pipe, and resumption of work at the site. The time extension will allow for the remainder of the contractor work to be completed. The bid specifications informed the bidders that there may be unforeseen conditions associated with the project. The contract incorporated an allowance of $300,000 for owner-directed additional work. This Change Order authorizes use of $48,615.98 of the allowance to pay for the exploratory work and the tapping of the pipe. Staff issued attached Work Directives 3 & 5 to direct the contr actor to perform this work. The Change Order also includes Work Directive No. 4, which is a credit for specified work that staff found had already been completed during a review of field conditions. FISCAL IMPACT: There is no impact on funding from this action. LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for Board approval. -SRT GROWTH MANAGEMENT IMPACT: There is no impact to the Growth Management Plan from this action. 16.C.6 Packet Pg. 978 06/08/2021 RECOMMENDATION: To approve the attached Change Order No. 1 to Agreement No. 20-7709, “South County Water Reclamation Facility Pump Station No. 5 & Piping Improvements," with Douglas N. Higgins, Inc., and authorize the Chair to sign the attached Change Order. Prepared By: Wayne Karlovich, Senior Project Manager, Public Utilities Engineering and Project Management Division ATTACHMENT(S) 1. Change Order 1 - 20-7709 - SCWRF PS 5 (PDF) 16.C.6 Packet Pg. 979 06/08/2021 COLLIER COUNTY Board of County Commissioners Item Number: 16.C.6 Doc ID: 15905 Item Summary: Recommendation to approve attached Change Order No. 1 to Agreement No. 20- 7709, “South County Water Reclamation Facility Pump Station No. 5 & Piping Improvements," with Douglas N. Higgins, Inc., and authorize the Chair to sign the attached Change Order. (Project Number 70251) Meeting Date: 06/08/2021 Prepared by: Title: Project Manager, Senior – Public Utilities Planning and Project Management Name: Wayne Karlovich 05/13/2021 4:40 PM Submitted by: Title: Division Director - Public Utilities Eng – Public Utilities Planning and Project Management Name: Tom Chmelik 05/13/2021 4:40 PM Approved By: Review: Public Utilities Planning and Project Management Tom Chmelik Additional Reviewer Completed 05/13/2021 5:00 PM Public Utilities Planning and Project Management Craig Pajer Additional Reviewer Completed 05/13/2021 5:05 PM Water Steve Messner Additional Reviewer Completed 05/14/2021 9:00 AM Procurement Services Sandra Herrera Additional Reviewer Completed 05/17/2021 9:10 AM Procurement Services Catherine Bigelow Additional Reviewer Completed 05/17/2021 3:56 PM Public Utilities Operations Support Jennifer Morse Additional Reviewer Completed 05/17/2021 4:54 PM Public Utilities Operations Support Joseph Bellone Additional Reviewer Completed 05/20/2021 10:42 AM Public Utilities Department JenniferA Rainey Level 1 Division Reviewer Completed 05/20/2021 10:56 AM Public Utilities Department George Yilmaz Level 2 Division Administrator Review Completed 05/20/2021 2:43 PM County Attorney's Office Scott Teach Level 2 Attorney Review Completed 05/21/2021 11:45 AM Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 05/21/2021 11:55 AM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 05/24/2021 10:10 AM Budget and Management Office Ed Finn Additional Reviewer Completed 05/31/2021 3:46 PM Office of Management and Budget Susan Usher Additional Reviewer Completed 06/01/2021 4:29 PM County Manager's Office Amy Patterson Level 4 County Manager Review Completed 06/02/2021 10:14 AM Board of County Commissioners Geoffrey Willig Meeting Pending 06/08/2021 9:00 AM 16.C.6 Packet Pg. 980 16.C.6.a Packet Pg. 981 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 982 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 983 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 984 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 985 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 986 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 987 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 988 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 989 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 990 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 991 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 992 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 993 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 994 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 995 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 996 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 997 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 998 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 999 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1000 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1001 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1002 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1003 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1004 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1005 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1006 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1007 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1008 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1009 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1010 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1011 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1012 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1013 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1014 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1015 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1016 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1017 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1018 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1019 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project) 16.C.6.a Packet Pg. 1020 Attachment: Change Order 1 - 20-7709 - SCWRF PS 5 (15905 : Change Order No. 1 SCWRF Pump Station 5 Project)