Bayshore CRA Joint Workshop Presentation March 31 Draft
Bayshore Gateway Triangle
Community Redevelopment Area
April 6, 2021
Joint workshop
1
Bayshore Beautification MSTU
Haldeman Creek MSTU
Maurice Gutierrez Chairman
Al Schantzen Vice-Chair, Resident
Karen Beatty Bayshore Resident
Larry Ingram Business Owner
Michael Sherman Bayshore Resident
Dwight Oakley Bayshore Resident
Steven Rigsbee Gateway Resident
Camille Kielty Bayshore Resident
Steve Main Business Owner
Roy Wilson, Chair
Jim King, Vice-Chair
Bill Robbins
Jacob Dutry van Haeften
Vacant
Maurice Gutierrez, Chairman,
Sandra Arafet, Vice-Chair
Jim Bixler
Susan Crum
George Douglas
Robert Messmer
John Smith
2
Highlights of 2020/2021
Closing on Mini-Triangle
Construction start of CRA Parking Lot
Completion of Fire Suppression Phase 2
Start of Fire Suppression Phase 3
3 of the 15 scattered lots under construction – SF homes
Del’s Acquisition – 1.84 acre Site
Submittal of Land Development Code and Comp Plan Revisions
17 Acres – RFP Process initiated
Start of Thomasson Drive Enhancement Project – MSTU
3
Mini Triangle - Sold
Gateway Mini Triangle Project
Property sold to Metropolitan Naples and Naples Triangle Development – November 13, 2020 for $6,372,959
Mixed Use Development – hotel/apartments/retail
Next Steps:
Demolition
Utility Easement
Subdivision Plat – 3 parcels
First Parcel –Naples Triangle Development 240 Luxury Apartments – Construction anticipated in January 2022
4
Three properties – 4 Lots:
Lot 3 - .44 +/- Acres Zoned C-5
Lots 1& 2 - .77 +/- Acres Zoned
C-5 (.38 AC) and C-3 (.38 AC)
Lot 4 - .63 +/- Acres Zoned RMF-6
Benefits:
Reducing intensity of uses
Enhance Thomasson Drive
Potential Partnership
Next Steps:
Survey
Demolition of Store and Warehouse
Securing boatyard building
Highest and Best Use Analysis
Community input
Del’s - 1.84 +/- Acres
5
17 acres
Status:
2021 – Consultant Selection
RFP advertised to design, permit and develop construction documents to build boardwalk connection to Sugden Park.
Evaluate Stormwater Capacity
Master Plan - Identify future phases and development potential
2022 – Construction of Boardwalk
6
Thomasson Drive Beautification Project
From Hamilton Ave to Orchard Lane: sidewalks, decorative streetlighting, and landscaping. Improved drainage and roundabout.
Total Amount: $6,684,350.95
Funding source: Bayshore MSTU
Construction Start Date: 05/01/2020
Substantial Completion Date: 05/26/2021
Final Completion Date: 06/25/2021
7
Hamilton Ave Project Current Conditions – From Thomasson to Bay Street
Memorial Day Weekend – 2017
98 Cars/trailers
Existing Condition
Sidewalk Ends – South side of Thomasson and Hamilton
Danford Street Flooding
8
Hamilton Ave Project
From Thomasson to Bay Street – connects into Thomasson Drive project.
Proposed Project: Creates permitted parking spaces, sidewalk connection to Bayview Park, connects Thomasson Drive to Hamilton.
9
Hamilton Ave Project
Connecting Thomasson to Hamilton. Adding Cross-walk, transition of bike lane, multi-use path, decorative streetlighting, and landscaping.
10
Commercial and Residential Grant Programs
Commercial Renovation - $30,000 Exterior + $20,000 Interior
Proposed Change in 2021:
Administrative changes
Refine list of eligible uses
Expand program to mirror goals of 2019 Redevelopment Plan
Reduce match for residential
Residential Grant Program – 2019 resumed funding
Site Improvement - $8,000
Sweet Equity - $1,000
Shoreline Stabilization - $5,000
Landscape Improvement - $2500
Before
After – Things I Like by Catherine
Before
After – Site Improvement Grant
11
Stormwater and Road Maintenance Partnership
Sabal Shores Neighborhood – Fire Suppression Phase 3 Completion
Stormwater Maintenance Improvements
Road Resurfacing
Stormwater Project 2021 –
Becca, Weeks, Pine – Design Contract pending
Gateway Triangle Neighborhood – Area 4 – Design Contract pending
Holly Ave
Neighborhood Clean Up – 2019
Neighborhood Watch – March 2021
Infrastructure Plan – stormwater, streetlighting, Limited resurfacing
12
Future Items
Hamilton Ave - MSTU
North Bayshore Drive – Joint MSTU and CRA Project
Access Management
Landscape/Hardscape Renovation Project
Land Development Code Changes
17 Acres – Sugden Park Connection/Master Plan/Construction
Shuttle Service – Bayshore Drive
Grant Program Updates
Del’s – Highest and Best Use Study –Board Direction
MSTU Boundary Expansions – Haldeman Creek and Bayshore Beautification
Haldeman Creek – Ordinance requiring maintenance of vegetation along creek
13
QUESTIONS
OPEN DISCUSSION
14