Backup Documents 02/23/2021 Item #11D Commission Update NESA and GGC Feb 26 2021 CCWSD utility phased implementation strategy golden gate city northeast regional utilities Funding Needs Public Utilities Department Update February 23, 2021 Good morning Commissioners, for the record…Joe Bellone, Director Utilities Finance Thank you for the opportunity to discuss the utility’s continued expansion plans Just a few reminders before we get going, the Special Act of FL Legislature Section 1 determined that: extensive growth poses public health and water supply concerns There is a need to eliminate proliferation of package treatment plants The BCC has the responsibility to provide water and sewer services First, we’ll look at plans for the former FGUA Golden Gate Utility Service area Following that, I’ll provide an update on what’s in progress in the northeast service area, including construction on the northeast regional utility site, and what’s next Page 234 1 GOlden Gate city Public Utilities Department Update January 2021 Let’s begin with plans for expanded service in the Golden Gate utility service area Page 235 2 Guiding principles At acquisition of the Golden Gate Utility System: Public Health – move residents from drinking wells adjacent to septic systems to public water supply Public Safety – provide fire protection throughout the city through installation of fire hydrants Environmental - move residents along waterways with septic systems to public sewer system Transmission Mains are the initial steps to build the backbone to provide sufficient water to achieve the first two objectives Expansion of the wastewater treatment plant by 4 MGD will provide sufficient capacity to meet future demand from area growth (golf course development, Activity Center 9 and within Golden Gate City service expansion) 3 As you can see, the CCWSD is proceeding in accordance with the guiding principles established for the acquisition of this utility: The two potable water transmission mains will provide sufficient capacity to deliver drinking water which enables the utility to expand the distribution system to currently unserved areas in GGC…initially fire hydrants can be placed strategically along this main (packet page 248) The existing wastewater treatment plant is at 86% capacity. Current and planned construction in the adjacent area, including any housing and/or Veteran’s services on the Golf Course as well as in activity center 9 including the Sports Complex, the Sheriff’s evidence facility at the GOBP (and any other agency operations), Uline, Great Wolf Park, etc. Page 236 3 Next Steps FY2021 - FY2022 Potable Water Complete design of potable transmission mains by summer 2021 Proposals for transmission main construction (fall 2021) Contract award late 2021, with construction starting 2022 Total estimated cost $18 million Wastewater Treatment GG Central WRF expansion to add 4 mgd of capacity (design 60% complete) Will serve golf course development/Activity Center 9 and eventual service expansion within Golden Gate City FDEP requires High Level Disinfection treatment at this site (BCC approved TetraTech EOR 4-28-20 item 16C13) Total estimated cost $70 million ($65 million EOR estimate + CEI) Total Golden Gate estimated cost $88 million 4 As of today, our engineers are working to complete design work for the potable water transmission mains and capacity expansion to add 4 MGD of wastewater treatment capable of producing irrigation quality water for irrigation To move forward to actual construction, funding of approximately $88 million will be necessary, there is a more information about that later in the presentation Page 237 4 Northeast expansion Public Utilities Department Update January 2021 Now, we’ll discuss expansion of our next regional utility facilities to augment capacity of our existing interconnected water and wastewater treatment facilities Page 238 5 Approved customer base includes Hyde Park Village and Rivergrass Village Finalizing Interlocal Agreements/DCA with IRRV, Longwater and Belmar Villages for BCC review/approval in 2021 Awaiting Letter from Hogan Island Village for request for utility services 6 Note that the CCWSD purchased the northeast utility site (216.19 acres) in June of 2003, anticipating the need for regional expansion The Board approved expansion of the Water-Sewer District’s service boundary at an advertised public hearing on September 18, 2018, with the understanding that growth was coming and additional capacity was necessary Expansion of the service area was predicated on the provision of the Special Act which grants power to the Board to provide water and sewer services to prevent the proliferation of package treatment plants throughout the county Thus far, Hyde Park and Rivergrass have been approved, and the CCWSD has been requested to provide water and wastewater services to Longwater, Bellmar and the Immokalee Road Rural Village, all located in the northeast regional service area We anticipate providing service to Hogan Island Village as well, though a formal request has not yet been received Since utility infrastructure must be built in advance of the actual demand, all developers and land owners have been or will be providing impact fee payments in advance to mitigate some of the utility’s risk Page 239 6 Status of Work To Date Segment 1: 36” water main on 39th Ave NE is 100% complete Segment 2: Pipelines under BCIRP are 100% complete Segment 3: Transmission pipelines are 100% complete Segment 4: Pipelines along 41st Avenue are 80% complete, roadway paving completed and inspected December 2020 Segment 5a: Pipelines to IRRV not started Segment 5b: Pipelines to Hogan Island Village not started (1) Utility Plant Site: interim wastewater treatment plant, two storage tanks and water pump stations substantial completion in September 2021 Total cost $76 million funded by the Series 2019 Bond (1) Potential to serve HIV through IRVV under review 7 As you can see on this page, work is progressing. This initial utility infrastructure identified here was bonded in 2019, at which time both Fitch and Moody’s rating agencies rewarded the CCWSD with a AAA rating, citing a strong financial profile, a healthy debt profile, and continuation of residential and commercial development at its current vigorous pace. If you haven’t been to the northeast utility site lately, situated adjacent to the Big Corkscrew Island Regional Park, I urge you to do so, it’s pretty impressive. Page 240 7 Next Steps FY2021 - FY2022 Construct wells/raw water mains in developer easements (Orange Blossom Ranch/IRRV) Construct two Class 1 Deep Injection Wells and Monitoring Well on NE utility site (10/21 – 7/22) Design updates to 4 mgd Northeast Water Reclamation Facility Construct Water and WW transmission mains to Oil Well Road (through BCIRP Phase 2 before Fall 2021) Design and construct water and wastewater transmission mains and water storage tank to interconnect Bellmar with Rivergrass/Longwater (function of market demand) Total Northeast estimated cost $48.1 million Note that installing a landscape buffer around the utility site early on will enhance residents experience when large scale construction takes place 8 In preparation for future operation of regional utility plants on the northeast site, several elements of the infrastructure must be constructed in advance to operate such production and treatment plants: Raw water wells provide the “raw materials” to the potable water treatment process Deep injection wells provide for disposal of concentrate from the RO treatment process as well as one disposal method for effluent that does not meet irrigation quality water standards Transmission mains that will be buried under Phase 2 of the BCIRP must be constructed prior to the start of park construction Total estimated funding need of $48 million (detail on packet page 243) Page 241 8 funding needs Public Utilities Department Update January 2021 Now, we’ll talk dollars and cents, but mostly dollars Page 242 9 Estimated Funding Needs 10 The largest and more significant funding need today if for potable water transmission mains and wastewater treatment capacity expansion in Golden Gate City: $88M Construction of the underlying necessary utility infrastructure associated with the northeast utility: $48 million Future Funding Needs identified in this chart and its timing will be determined by market demands Page 243 10 Plan of Finance Preliminary discussion with OMB/PFM/Bond Counsel 12/15/20 Update BCC on utility plans 2/23/21 Funding needs FY21 – FY22 total $136 million (impact fee eligible) Schedule 2/23/21: Board endorses FY21-FY22 plan Feb 2021: Finance Committee Meeting to discuss financing options March – May 2021: Conduct Bond Feasibility Report (Raftelis/AECOM) June 2021: Accept Bids (Pricing/Award Bid) July 2021: Closing 11 So, how best to structure the debt to fund these requirements: Mr. Isackson will convene a Finance Committee Meeting (members include OMB staff, the Clerk of Courts and her Finance Director, Mr. Klatzkow, GMD Finance Director and myself) Also attending will be Bond Council from Nabors Giblin as well as the County’s Financial Advisors (PFM) PFM will develop a preliminary plan of finance I will request a Bond Feasibility Report (both financial and engineering components) with Raftelis Go to the market, accept bids with an anticipated closing sometime this summer (goal is approval at the July Board meeting) Page 244 11 OTHER FINANCIAL CONSIDERATIONS Interlocal Agreements/Developer Contribution Agreements require advance water and sewer impact fee payments to share the risk of expansion construction in the northeast with rate payers: Hyde Park paid $1,674,000 in August 2020 Rivergrass advance impact fee payment of $1,674,000 due upon resolution of legal challenge Longwater - $2,343,600 due 30 days after SRA approval Belmar - $4,352,400 due 30 days after SRA approval Advanced impact fee credits can only be used at 50% for each building permit, thus ensuring a continued revenue stream Ordinance 2019-48 (Impact Fee) increased cmbined water and wastewater fees by 27.2% effective March30, 2020 to fund expansion (next impact fee update due 2022) 12 For informational purposes, I’ve included on this slide highlights of advance impact fee payments either already paid, approved, or in process to mitigate the utility's risk of building infrastructure in advance of demand To ensure a continued revenue stream, developers will only be allowed to use 50% of the impact fee paid in advance against impact fees due at time of CO Recall that you approved water and sewer impact fee rate increases of just over 27% effective in March 2020 in anticipation of these expansion needs during the 10-year impact fee rate study 2019 to 2029 which included all treatment and production facilities. Impact Fee Rate Studies are done at least once every three years, or sooner of business conditions change significantly before that Page 245 12 recommendations Approve the Utility Plans for Golden Gate City wastewater plant expansion and construction of potable water transmission mains Endorse the Utility Plans for NE expansion Direct the County Manager, or his designees, to explore financing plans and begin a Bond Feasibility Report Explore financing plans with Finance Committee, PFM and Bond Counsel Develop a Bond Feasibility Report with Raftelis and AECOM 13 Commissioners, we’re asking you today to endorse these plans, and direct staff to explore a plan of finance and bring a bond approval to you later this fiscal year. One last critical piece of good news: Fitch recently completed its surveillance of the CCWSD in early February, included in that report is the anticipated approval of this $136 million loan. The Result: On February 11, 2021 Fitch released its report, reaffirmed its AAA rating, Stable Outlook, for the CCWSD, citing: Robust liquidity position, Disciplined rate setting, AND Growth expected to support a sustained low leverage liquidity position And with that, I can answer any questions you might have. Page 246 13 appendix 14 14 Golden Gate Potable Water Transmission Mains 15 The large potable water transmission mains to be completed in phases 15 Golden Gate WAsteWater Treatment plant Golden Gate City WWTP 16 Note there is plenty of room for expansion on the current treatment site 16 Deep injection wells 17 Timeline calls for construction to begin by the end of this calendar year 17 Landscape buffer Type A looking South toward site Type B looking north toward utility site 18 The rendering of the landscape buffer is NOT a part of this funding request, but just to point out for you that the earlier the plantings are completed, the longer they have to grow before the final regional production and treatment facilities are constructed and put into operation. 18