Agenda 01/12/2021 Item #16A15 (PL20190001933)01/12/2021
EXECUTIVE SUMMARY
Recommendation to approve final acceptance and accept the conveyance of the potable water and
sewer utility facilities for Isles of Collier Preserve Phase 12C, PL20190001933 and authorize the
County Manager, or his designee, to release the Final Obligation Bond in the total amount of $4,000
to the Project Engineer or the Developer’s designated agent.
OBJECTIVE: To have the Board of County Commissioners, as Ex-Officio Governing Board of the
Collier County Water-Sewer District, approve final acceptance and accept the conveyance of these
potable water and sewer facilities and to release the Final Obligation Bond in the total amount of $4,000,
in accordance with the Collier County Utility Standards and Procedures, Ordinance No. 2004-31.
CONSIDERATIONS:
1) The Developer of Isles of Collier Preserve Phase 12C, has constructed the potable water and sewer
facilities within dedicated easements to serve this development. (See attached location map). The
potable water and sewer facilities were offered for conveyance to the County, as described in OR
Book 5687, Page 3685, and are located within County utility easements dedicated by the plat of Isles
of Collier Preserve Phase 12, recorded in Plat Book 64, Pages 64 through 72, of the Public Records
of Collier County, Florida.
2) Preliminary acceptance of these utility facilities was approved by the Development Review staff on
October 22, 2019. At that time, the value of these potable water and sewer utility facilities (assets)
was $70,288.08 and $59,058.40, respectively.
3) Staff recorded all preliminary acceptance documents associated with the facilities being conveyed to
the County in the public records of Collier County, which were reviewed and approved by the
County Attorney’s office as to form and legality. The County acquired its interest in the potable
water and sewer facilities by Utilities Facilities Warranty Deed and Bill of Sale recorded in Official
Records Book 5687, at page 3685 (“the Utilities Facilities Deed”) of the Public Record s of Collier
County, Florida.
4) The potable water and sewer utility facilities have been operated and maintained during the required
one (1) year warranty period, following preliminary acceptance.
5) A final inspection to discover defects in materials and workmanship has been conducted by the
Development Review staff on November 19, 2020, in coordination with Public Utilities and these
facilities have been found to be satisfactory and acceptable.
6) Staff recommends final acceptance of the subject utility facilities and to release the Final Obligation
Bond in the total amount of $4,000. Staff also recommends acceptance of the Utilities Facilities
Deed and the facilities described therein.
7) This final acceptance is in accordance with Collier County Ordinance No. 2004-31, as amended.
8) Staff is unaware of any issues that would serve to negate the recommendation to release the
applicable security.
FISCAL IMPACT: Approval of this Executive Summary will result in the Collier County Water -Sewer
District receiving title to the utility facilities, which at the time of preliminary acceptance, had a total
16.A.15
Packet Pg. 622
01/12/2021
gross value of $129,346.48 (no depreciation applied) and an asset will be recorded in the financial records
of the county.
GROWTH MANAGEMENT IMPACT: There is no growth management impact associated with this
action.
LEGAL CONSIDERATIONS: This item has been approved as to form and legality, and requires a
majority vote for Board approval. -DDP
RECOMMENDATION: To approve final acceptance and accept the conveyance of the potable water
and sewer utility facilities for Isles of Collier Preserve Phase 12C, PL20190001933, accept the
conveyance of the Utilities Facilities Deed and the facilities described therein, and to authorize the
County Manager, or his designee, to release the Final Obligation Bond in the total amount of $4,000 to
the Project Engineer or the Developer’s designated agent.
Prepared by: Valerie Kullick, Technician, Development Review Division
ATTACHMENT(S)
1. Location Map (PDF)
2. Exhibit A (PDF)
3. Contributory Assets (PDF)
4. Warranty Deed and Bill of Sale (PDF)
5. Plat Book 64 PP 64-72 (PDF)
16.A.15
Packet Pg. 623
01/12/2021
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.A.15
Doc ID: 14314
Item Summary: Recommendation to approve final acceptance and accept the conveyance of the
potable water and sewer utility facilities for Isles of Collier Preserve Phase 12C, PL20190001933 and
authorize the County Manager, or his designee, to release the Final Obligation Bond in the total amount
of $4,000 to the Project Engineer or the Developer’s designated agent.
Meeting Date: 01/12/2021
Prepared by:
Title: Technician – Growth Management Development Review
Name: Valerie Kullick
11/25/2020 9:20 AM
Submitted by:
Title: Director – Growth Management Department
Name: Matthew McLean
11/25/2020 9:20 AM
Approved By:
Review:
Water Pamela Libby Additional Reviewer Completed 11/25/2020 9:22 AM
Wastewater Steve Nagy Additional Reviewer Completed 11/25/2020 9:23 AM
Growth Management Department Judy Puig Level 1 Reviewer Completed 11/25/2020 9:52 AM
Growth Management Operations & Regulatory Management Rose Burke Additional Reviewer Completed 11/25/2020 3:14 PM
Water Steve Messner Additional Reviewer Completed 11/30/2020 12:17 PM
Wastewater Steve Messner Additional Reviewer Completed 11/30/2020 12:18 PM
Growth Management Development Review Marcus Berman Additional Reviewer Completed 12/01/2020 8:54 AM
Public Utilities Planning and Project Management Tom Chmelik Additional Reviewer Completed 12/01/2020 9:03 AM
Engineering & Natural Resources Jack McKenna Additional Reviewer Completed 12/07/2020 10:19 AM
Growth Management Department Matthew McLean Additional Reviewer Completed 12/14/2020 5:23 PM
Public Services Department James C French Deputy Department Head Review Completed 12/14/2020 10:54 PM
County Attorney's Office Derek D. Perry Level 2 Attorney Review Completed 12/16/2020 8:41 AM
Growth Management Department Thaddeus Cohen Department Head Review Completed 12/16/2020 1:13 PM
Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 12/16/2020 1:31 PM
Budget and Management Office Mark Isackson Additional Reviewer Completed 12/17/2020 1:52 PM
County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 12/22/2020 2:00 PM
16.A.15
Packet Pg. 624
01/12/2021
County Manager's Office Dan Rodriguez Level 4 County Manager Review Completed 12/22/2020 4:54 PM
Board of County Commissioners MaryJo Brock Meeting Pending 01/12/2021 9:00 AM
16.A.15
Packet Pg. 625
ISLES OF COLLIER PRESERVE PHASE 12C
LOCATION MAP
16.A.15.a
Packet Pg. 626 Attachment: Location Map (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
Exhibit A
Utilities Performance Security (UPS) and Final Obligation Bond
Amount Receipt Number
10% UPS Bond With Plat
Final Obligation Bond $4,000 2019652182
Total Amount $4,000
The 10% UPS Bond, if applicable, is based on the total amount of the water and/or sewer
utilities being installed for the whole project which includes material and labor. The
contributory assets reflect the cost of materials, not labor and are based on the assets of
which the county will be owning and maintaining.
Final Obligation Bond, if applicable, in accordance with Utility Ordinance 2004-31
Attachments:
1. Verification of Final Cost
2. Receipt of Payment
16.A.15.b
Packet Pg. 627 Attachment: Exhibit A (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.b
Packet Pg. 628 Attachment: Exhibit A (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.b
Packet Pg. 629 Attachment: Exhibit A (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
Collier County
Growth Management Division
2800 Horseshoe Drive N.
Naples, FL 34104
239-252-2400
RECEIPT OF PAYMENT
Receipt Number:2019652182
Transaction Number:2019-075456
Date Paid:08/19/2019
Amount Due:$4,000.00
Payment Details:Payment Method Amount Paid Check Number
Check $4,000.00 54026
Amount Paid:$4,000.00
Change / Overage:$0.00
Contact:MINTO COMMUNITIES, LLC
4400 W SAMPLE RD STE 200
COCONUT CREEK, FL 33703
FEE DETAILS:
Fee Description Reference Number Original
Fee
Amount
Paid
GL Account
Utility Performance
Refundable Bond
PL20190001933 $4,000.00 $4,000.00 670-000000-220113
Cashier Name:AlinaHarris
Batch Number:8513
Entered By: LuciaMartin
16.A.15.b
Packet Pg. 630 Attachment: Exhibit A (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.c
Packet Pg. 631 Attachment: Contributory Assets (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.c
Packet Pg. 632 Attachment: Contributory Assets (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.d
Packet Pg. 633 Attachment: Warranty Deed and Bill of Sale (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.d
Packet Pg. 634 Attachment: Warranty Deed and Bill of Sale (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.d
Packet Pg. 635 Attachment: Warranty Deed and Bill of Sale (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.d
Packet Pg. 636 Attachment: Warranty Deed and Bill of Sale (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.dPacket Pg. 637Attachment: Warranty Deed and Bill of Sale (14314 : Final Acceptance of Utilities - Isles of Collier Preserve
16.A.15.d
Packet Pg. 638 Attachment: Warranty Deed and Bill of Sale (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.d
Packet Pg. 639 Attachment: Warranty Deed and Bill of Sale (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.e
Packet Pg. 640 Attachment: Plat Book 64 PP 64-72 (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.e
Packet Pg. 641 Attachment: Plat Book 64 PP 64-72 (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.e
Packet Pg. 642 Attachment: Plat Book 64 PP 64-72 (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.e
Packet Pg. 643 Attachment: Plat Book 64 PP 64-72 (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.e
Packet Pg. 644 Attachment: Plat Book 64 PP 64-72 (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.e
Packet Pg. 645 Attachment: Plat Book 64 PP 64-72 (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.e
Packet Pg. 646 Attachment: Plat Book 64 PP 64-72 (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.e
Packet Pg. 647 Attachment: Plat Book 64 PP 64-72 (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))
16.A.15.e
Packet Pg. 648 Attachment: Plat Book 64 PP 64-72 (14314 : Final Acceptance of Utilities - Isles of Collier Preserve Phase 12C (UTCF))